0% found this document useful (0 votes)
31 views106 pages

Workings

The document provides a bill of quantities estimation for the structural works of a proposed integrated office building project. It includes excavation quantities and details of reinforced concrete works including footings and columns across different grids of the building structure.

Uploaded by

Vasim Shaikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views106 pages

Workings

The document provides a bill of quantities estimation for the structural works of a proposed integrated office building project. It includes excavation quantities and details of reinforced concrete works including footings and columns across different grids of the building structure.

Uploaded by

Vasim Shaikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 106

Date :

Project : Proposed Integrated Office Build


Client : Dalmia Bharat Cement
Main Contractor : Emperor Construction
Architect : Architect Studio Plus, New Delhi
PROJECT PARTICULARS

Structural Consultant :
MEP Consultant :
PMC :
SubContractor1 :
SubContractor2 :
Subject : Structural Bill of quantity estimation (A
Floor Area in Sqm : 891
Total Builtup Area in Sqm :
Project Commencement Date :
Schedule Completion Date :
Duration in days : 180
BUILDING AREA
Dimensions in m
Sl. No. Particulars Unit
no
L

1.1.1.1 Soft / Loose Soil Excavation upto 3 m depth cum


1.1.1.2 Soft / Loose Soil Excavation - 3 m to 6 m depth cum
1.1.2.1 Hard/ Dense Soil Excavation upto 3 m depth cum
1.1.2.2 Hard/ Dense Soil Excavation - 3 m to 6 m depth cum
1.1.3.1 Ordinary Rock Excavation upto 3 m depth cum
1.1.3.2 Ordinary Rock Excavation from 3 m to 6 m depth cum
1.1.5.1 Hard Rock Excavation upto 3 m depth cum
1.1.5.2 Hard Rock Excavation from 3 m to 6 m depth cum
2 a) Filling with Available Earth Material cum
2 b) Filling with Imported Filling Material cum
3 a) PCC - 1:3:6 in Grade Slab cum

3 b) PCC - 1:4:8 in Footings cum


In Footings
Along Grid C
F3 3 1.65
F4 2 1.95
F8 1 2.55
Along Grid D
F3 4 1.65
Along Grid D1
F3 1 1.65
F4 1 1.95
Along Grid D2
F3 1 1.65
F5 1 1.95
Along Grid E
F3 3 1.65
F7 1 2.25
Along Grid E1
Along Grid F
CF3 1 3.75
F3 3 1.65
F6 1 2.25
F5 1 1.95
Along Grid G
CF3 1 3.75
F8 2 2.55
F4 1 1.95
F7 1 2.25
F3 1 1.65
Along Grid G1
F4 1 1.95
F5 1 1.95
Along Grid H
CF3 1 3.75
F7 1 2.25
F4 1 1.95
F6 1 2.25
F5 1 1.95
Along Grid H1
F6 1 2.25
Along Grid I
F6 2 2.25
F5 2 1.95
Along Grid I1
F2 1 1.65
Along Grid I2
CF2 1 2.65
Along Grid J
F2 1 1.65
F10 1 3.45
F8 1 2.55
Along Grid J1
F9 1 2.55
Along Grid J2
F8 1 2.55
Along Grid K
F5 2 1.95
F8 1 2.55
F7 1 2.25
F3 1 1.65
Along Grid K1
F3 1 1.65
Along Grid L
F5 1 1.95
F3 1 1.65
Along Grid L1
F1 1 1.35
Along Grid L2
Along Grid L3
F3 1 1.65
Along Grid L4
Along Grid M
CF1 1 3.55
F5 1 1.95
F4 1 1.95
Along Grid N
CF1 1 3.55
F5 1 1.95
F3 1 1.65
Along Grid O
CF1 1 3.55
F4 1 1.95
F3 1 1.65
Along Grid P

4 a) i) RCC - M25 - Below 0 Level (CC: 330 kg/cum) cum


In Footings
Along Grid C
F3 3 1.5
F4 2 1.8
F8 1 2.4
Along Grid D
F3 4 1.5
Along Grid D1
F3 1 1.5
F4 1 1.8
Along Grid D2
F3 1 1.5
F5 1 1.8
Along Grid E
F3 3 1.5
F7 1 2.1
Along Grid E1
Along Grid F
CF3 1 3.6
F3 3 1.5
F6 1 2.1
F5 1 1.8
Along Grid G
CF3 1 3.6
F8 2 2.4
F4 1 1.8
F7 1 2.1
F3 1 1.5
Along Grid G1
F4 1 1.8
F5 1 1.8
Along Grid H
CF3 1 3.6
F7 1 2.1
F4 1 1.8
F6 1 2.1
F5 1 1.8
Along Grid H1
F6 1 2.1
Along Grid I
F6 2 2.1
F5 2 1.8
Along Grid I1
F2 1 1.5
Along Grid I2
CF2 1 2.5
Along Grid J
F2 1 1.5
F10 1 3.3
F8 1 2.4
Along Grid J1
F9 1 2.4
Along Grid J2
F8 1 2.4
Along Grid K
F5 2 1.8
F8 1 2.4
F7 1 2.1
F3 1 1.5
Along Grid K1
F3 1 1.5
Along Grid L
F5 1 1.8
F3 1 1.5
Along Grid L1
F1 1 1.2
Along Grid L2
Along Grid L3
F3 1 1.5
Along Grid L4
Along Grid M
CF1 1 3.4
F5 1 1.8
F4 1 1.8
Along Grid N
CF1 1 3.4
F5 1 1.8
F3 1 1.5
Along Grid O
CF1 1 3.4
F4 1 1.8
F3 1 1.5
Along Grid P

68
In Columns
Along Grid C
C1A 5 0.3
C3 1 0.6
Along Grid D
C1A 2 0.3
C1 2 0.3
Along Grid D1
C1 2 0.3
Along Grid D2
C1A 1 0.3
C1C 1 0.3
Along Grid E
C1 2 0.3
C1A 2 0.3
Along Grid E1
Along Grid F
C1 4 0.3
C1B 1 0.3
C2A 1 0.3
C1A 1 0.3
Along Grid G
C1 3 0.3
C1D 2 0.3
C2A 1 0.3
C1A 1 0.3
Along Grid G1
C1D 2 0.3
Along Grid H
C1 4 0.3
C2A 1 0.3
C1C 1 0.3
Along Grid H1
C3 1 0.6
Along Grid I
C1 3 0.3
C1C 1 0.3
Along Grid I1
C1A 1 0.3
Along Grid I2
C1 1 0.3
Along Grid J
C1 1 0.3
C1A 1 0.3
C4 1 0.45
C3A 1 0.6
Along Grid J1
C3A 1 0.6
Along Grid J2
C1 1 0.3
Along Grid K
C1B 1 0.3
C2 2 0.3
C1 1 0.3
C1A 1 0.3
Along Grid K1
C1 1 0.3
Along Grid L
C1 1 0.3
C1A 1 0.3
Along Grid L1
C1A 1 0.3
Along Grid L2
Along Grid L3
C1 1 0.3
Along Grid L4
Along Grid M
C1A 2 0.3
C1 2 0.3
Along Grid N
C1A 2 0.3
C1 2 0.3
Along Grid O
C1A 4 0.3
Along Grid P
75

In Plinth Beams

4 a) ii) RCC - M25 - Above 0 Level (CC: 330 kg/cum) cum


In Grade Slab
In Columns

RCC - M30 - Below 0 Level (CC: 340 kg/cum) in Fire


4 b) i) cum
driveway ramps
RCC - M30 - Above 0 Level (CC: 340 kg/cum) in Fire
4 b) ii) cum
driveway ramps
RCC in 1:1:2 Towards chajjas, projection, coping, steps,
4 c) i) cum
kerbs, lintel beams…etc.
5 a) i) Formwork - From 0.00 mtr. to (-)9.00 mtr. Lvl. sqm
5 a) ii) Formwork - From 0.00 mtr. to (+)9.00 mtr. Lvl. sqm
6 Scaffolding sqm
7 R/F Steel MT
8 Anti Termite Treatment sqm
9 Insert Plate MT
10 a) Brick Masonry : Full Brick - Substructure - 1:4 cum
10 b) Brick Masonry : Full Brick - Superstructure - 1:4 cum
11 Brick Masonry : Half Brick - 1:3 sqm
Autoclaved Aerated Concrete [AAC] Block Masonary -
12 a) cum
600mm (l) x 300mm (w) x 200mm (d)] - 3:1
13 a) Plaster 1:4 - 15 to 18 mm to uneven surface sqm
13 b) Plaster 1:4 - 12 mm to even surface sqm
14 Waterprofing to Wet Areas sqm
15 a) 110mm dia pipe sleeves m
15 b) 150mm dia pipe sleeves m
16 a) Roof Waterproofing - Brickbat Coba - 1:4 sqm
16 b) Roof Finish Layer - Glazed China Mosaic - 1:4 sqm
17 a) Toe Wall with RRM - 1:6 in Substructure cum
Between Grid B to F
14.34
0.9
1.05

17 b) Toe Wall with RRM - 1:6 in Superstructure cum

18 Rubble Soling : Sub Base - 230 mm thick cum


19 SS 304 - horizontal fins / grills kg
20 a) RW Pipe - 110mm dia nominal size m
Making plinth protection / apron 50mm thick of cement
21 cum
concrete 1:3:6
22 Weep Holes 75mm Dia PVC m
23 PVC Khurra (45 cm X 45 cm) - 1:2:4 no
24 Concrete Pavements (150 mm thk) - 1:3:4 cum
sed Integrated Office Building Complex for Murli Cement Works at Chandrapur
a Bharat Cement
r Construction
ct Studio Plus, New Delhi

al Bill of quantity estimation (Actual)

BUILDING AREA EXTERNAL AREA


Dimensions in m Dimensions in m

Qty. Net Qty no Particulars


B D L B D

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1.65 0.075 0.61
1.65 0.075 0.48
2.25 0.075 0.43
-
1.65 0.075 0.82
-
1.65 0.075 0.20
1.65 0.075 0.24
-
1.65 0.075 0.20
1.95 0.075 0.29
-
1.65 0.075 0.61
2.25 0.075 0.38
-
-
1.75 0.075 0.49
1.65 0.075 0.61
1.95 0.075 0.33
1.95 0.075 0.29
-
1.75 0.075 0.49
2.25 0.075 0.86
1.65 0.075 0.24
2.25 0.075 0.38
1.65 0.075 0.20
-
1.65 0.075 0.24
1.95 0.075 0.29
-
1.75 0.075 0.49
2.25 0.075 0.38
1.65 0.075 0.24
1.95 0.075 0.33
1.95 0.075 0.29
-
1.95 0.075 0.33
-
1.95 0.075 0.66
1.95 0.075 0.57
-
1.45 0.075 0.18
-
1.45 0.075 0.29
-
1.45 0.075 0.18
3.15 0.075 0.82
2.25 0.075 0.43
-
2.55 0.075 0.49
-
2.25 0.075 0.43
-
1.95 0.075 0.57
2.25 0.075 0.43
2.25 0.075 0.38
1.65 0.075 0.20
-
1.65 0.075 0.20
-
1.95 0.075 0.29
1.65 0.075 0.20
-
1.35 0.075 0.14
-
-
1.65 0.075 0.20
-
-
1.75 0.075 0.47
1.95 0.075 0.29
1.65 0.075 0.24
-
1.75 0.075 0.47
1.95 0.075 0.29
1.65 0.075 0.20
-
1.75 0.075 0.47
1.65 0.075 0.24
1.65 0.075 0.20
-
-
- 20.27

1.5 0.4 2.70


1.5 0.4 2.16
2.1 0.6 3.02
-
1.5 0.4 3.60
-
1.5 0.4 0.90
1.5 0.4 1.08
-
1.5 0.4 0.90
1.8 0.5 1.62
-
1.5 0.4 2.70
2.1 0.6 2.65
-
-
1.6 0.4 2.30
1.5 0.4 2.70
1.8 0.45 1.70
1.8 0.5 1.62
-
1.6 0.4 2.30
2.1 0.6 6.05
1.5 0.4 1.08
2.1 0.6 2.65
1.5 0.4 0.90
-
1.5 0.4 1.08
1.8 0.5 1.62
-
1.6 0.4 2.30
2.1 0.6 2.65
1.5 0.4 1.08
1.8 0.45 1.70
1.8 0.5 1.62
-
1.8 0.45 1.70
-
1.8 0.45 3.40
1.8 0.5 3.24
-
1.3 0.4 0.78
-
1.3 0.3 0.98
-
1.3 0.4 0.78
3 0.9 8.91
2.1 0.6 3.02
-
2.4 0.65 3.74
-
2.1 0.6 3.02
-
1.8 0.5 3.24
2.1 0.6 3.02
2.1 0.6 2.65
1.5 0.4 0.90
-
1.5 0.4 0.90
-
1.8 0.5 1.62
1.5 0.4 0.90
-
1.2 0.4 0.58
-
-
1.5 0.4 0.90
-
-
1.6 0.5 2.72
1.8 0.5 1.62
1.5 0.4 1.08
-
1.6 0.5 2.72
1.8 0.5 1.62
1.5 0.4 0.90
-
1.6 0.5 2.72
1.5 0.4 1.08
1.5 0.4 0.90
-
-
- 114.33
-

0.6 0.525 0.47


0.6 0.525 0.19
-
0.6 0.525 0.19
0.6 0.525 0.19
-
0.6 0.525 0.19
-
0.6 0.525 0.09
0.6 0.525 0.09
-
0.6 0.525 0.19
0.6 0.525 0.19
-
-
0.6 0.525 0.38
0.6 0.525 0.09
0.75 0.525 0.12
0.6 0.525 0.09
-
0.6 0.525 0.28
0.6 0.525 0.19
0.75 0.525 0.12
0.6 0.525 0.09
-
0.6 0.525 0.19
-
0.6 0.525 0.38
0.75 0.525 0.12
0.6 0.525 0.09
-
0.6 0.525 0.19
-
0.6 0.525 0.28
0.6 0.525 0.09
-
0.6 0.525 0.09
-
0.6 0.525 0.09
-
0.6 0.525 0.09
0.6 0.525 0.09
0.9 0.525 0.21
0.6 0.525 0.19
-
0.6 0.525 0.19
-
0.6 0.525 0.09
-
0.6 0.525 0.09
0.75 0.525 0.24
0.6 0.525 0.09
0.6 0.525 0.09
-
0.6 0.525 0.09
-
0.6 0.525 0.09
0.6 0.525 0.09
-
0.6 0.525 0.09
-
-
0.6 0.525 0.09
-
-
0.6 0.525 0.19
0.6 0.525 0.19
-
0.6 0.525 0.19
0.6 0.525 0.19
-
0.6 0.525 0.38
-
-
- 7.70
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-

0.45 0.45
0.45 0.45
0.45 0.45
REA

Total
BOQ Qty Rate Amount
Qty. Net Qty Actual Qty

650

700

500

600
100
740
205
106

98
300
610

22

35
4
1200
4560
1650
112
1335
0.06
70
286
35
312
1312
2750
120
6
6
810
810
110

60

450
6000
60
4.8
150
12
40
Plinth Area Building Floor Area
L W L W
56.95 17.96 55.15 16.16

Remarks
PROJECT REPORT

Status As on Date Date of Reporting

Project Name: Proposed Integrated Office Building Complex for Murli Cement Works at Chandrapur

Status Update
Status -
Criticality -
Date Open / In
Particulars Responsibility & IMPACT Low / Mitigation for the issue & Status Target Date Date Closed
Identified Progress /
Medium / High
Closed
DESIGN & DRAWINGS STATUS

COMMERCIAL RELATED STATUS - BILLING & VARIATIONS

HSE STATUS

QUALITY STATUS

PROCUREMENT STATUS

PROGRESS STATUS
%
Event Schedule and Quantity Tracker Sheet - CIVIL WORKS Executed
MAX DIFF
Actual
Rate Per
Duration
As on 5/12/2024 11:14 Number
in Days
Actual
SN Activity Actual Start
Completion
1 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
2 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
3 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
4 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
5 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
6 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
7 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
8 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
9 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
10 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
11 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
12 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
13 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
14 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
15 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
16 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
17 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
18 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
19 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
20 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
21 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
22 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
23 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
24 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
25 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
26 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
27 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
28 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
29 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
30 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
31 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
32 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
33 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
34 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
35 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
36 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
37 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
38 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
39 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
40 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
41 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
42 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
43 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
44 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
45 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
46 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
47 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
48 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
49 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
50 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
51 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
52 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
53 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
54 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
55 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
56 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
57 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
58 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
59 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
60 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
61 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
62 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
63 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
64 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
65 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
66 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
67 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
68 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
69 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
70 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
71 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
72 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
73 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
74 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
75 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
76 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
77 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
78 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
79 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
Total Work Done Amount in Rs.
Bal. to
Drg. Qty. Executed
Execute Qty.
in no Qty. in no
in no

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Labor
Component
Bal. to
Drg. Qty. Drg. Amount - Total BOQ Anticipated Bal. to Total Executed
Execute UOM Rate
(Actual) Actual Prvision Variance Execute Qty.
Amount

- - - - - sqm
- - - - - cum
- - - - - cum
- - - - - MT
- - - - - cum
- - - - - no
- - - - - Item
- - - - - cum
- - - - - no
- - - - - no
- - - - - no
- - - - - cum
- - - - - cum
- - - - - no
- - - - - cum
- - - - - - cum
- - - - - MT
- - - - - MT
- - - - - - MT
- - - - - no
- - - - - no
- - - - - - cum
- - - - - - cum
- - - - - cum
- - - - - - MT
- - - - - - cum
- - - - - - MT
- - - - - - MT
- - - - - - MT
- - - - - - cum
- - - - - - MT
- - - - - - cum
- - - - - - cum
- - - - - cum
- - - - - - cum
- - - - - no
- - - - - - MT
- - - - - - MT
- - - - - - cum
- - - - - no
- - - - - cum
- - - - - - cum
- - - - - - cum
- - - - - - cum
- - - - - - MT
- - - - - - cum
- - - - - no
- - - - - - MT
- - - - - no
- - - - - MT
- - - - - MT
- - - - - sqm
- - - - - - cum
- - - - - - m
- - - - - - sqm
- - - - - - MT
- - - - - - cum
- - - - - - LS
- - - - - - LS
- - - - - - cum
- - - - - - MT
- - - - - - cum
- - - - - - MT
- - - - - - cum
- - - - - - cum
- - - - - - sqm
- - - - - - sqm
- - - - - - cum
- - - - - - sqm
- - - - - - MT
- - - - - - cum
- - - - - - MT
- - - - - - cum
- - - - - - cum
- - - - - - sqm
- - - - - - LS
- - - - - cum
- - - - - sqm
- - - - - cum
- - - - -
Qty. Breakup
Executed Amount %
(Work Done) Completed
1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 6-Apr 7-Apr 8-Apr 9-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr

- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
#DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
- #DIV/0!
#DIV/0!
- #DIV/0!
-
16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 1-May 2-May 3-May 4-May 5-May 6-May
7-May 8-May 9-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May
26-May 27-May 28-May 29-May 30-May 31-May 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun 13-Jun
14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 1-Jul 2-Jul 3-Jul 4-Jul
5-Jul 6-Jul 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul
25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 1-Aug 2-Aug 3-Aug 4-Aug 5-Aug 6-Aug 7-Aug 8-Aug 9-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug
15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 1-Sep 2-Sep 3-Sep 4-Sep
5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep
26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct
17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 1-Nov 2-Nov 3-Nov 4-Nov 5-Nov 6-Nov
7-Nov 8-Nov 9-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov
26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 1-Dec 2-Dec 3-Dec 4-Dec 5-Dec 6-Dec 7-Dec 8-Dec 9-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec
15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 1-Jan 2-Jan
3-Jan 4-Jan 5-Jan 6-Jan 7-Jan 8-Jan 9-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan
24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 1-Feb 2-Feb 3-Feb 4-Feb 5-Feb 6-Feb 7-Feb 8-Feb 9-Feb 10-Feb 11-Feb 12-Feb 13-Feb
14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb
Date 13 May 2024

Project Proposed Integrated Office Building Complex for Murli Cemen

Client Dalmia Bharat Cement


PROJECT PARTICULARS

Main Contractor Emperor Construction

Architect Architect Studio Plus, New Delhi


Structural Consultant
MEP Consultant
PMC
SubContractor1
SubContractor2
Subject LEVEL CONTROL RECORD

Dimension

SL NO Elements Demarcation Type


no L B D

BUILDING AREA
1 In Footings
2 Along Grid C
3 F3 3 1.500 1.500 0.400

4 F4 2 1.800 1.500 0.400

5 F8 1 2.400 2.100 0.600

6 Along Grid D
7 F3 4 1.500 1.500 0.400

8 Along Grid D1
9 F3 1 1.500 1.500 0.400

10 F4 1 1.800 1.500 0.400

11 Along Grid D2
12 F3 1 1.500 1.500 0.400

13 F5 1 1.800 1.800 0.500

14 Along Grid E
15 F7 1 2.100 2.100 0.600

16 F3 3 1.500 1.500 0.400

17 Along Grid E1
18 Along Grid F
19 CF3 1 3.600 1.600 0.400

20 F3 3 1.500 1.500 0.400

21 F6 1 2.100 1.800 0.450

22 F5 1 1.800 1.800 0.500

23 Along Grid G
24 CF3 1 3.600 1.600 0.400

25 F8 2 2.400 2.100 0.600

26 F4 1 1.800 1.500 0.400

27 F7 1 2.100 2.100 0.600

28 F3 1 1.500 1.500 0.400

29 Along Grid G1
30 F4 1 1.800 1.500 0.400

31 F5 1 1.800 1.800 0.500

32 Along Grid H
33 CF3 1 3.600 1.600 0.400

34 F7 1 2.100 2.100 0.600

35 F4 1 1.800 1.500 0.400

36 F6 1 2.100 1.800 0.450

37 F5 1 1.800 1.800 0.500

38 Along Grid H1
39 F6 1 2.100 1.800 0.450

40 Along Grid I
41 F6 2 2.100 1.800 0.450

42 F5 2 1.800 1.800 0.500

43 Along Grid I1
44 F2 1 1.500 1.300 0.400

45 Along Grid I2
46 CF2 1 2.500 1.300 0.300

47 Along Grid J
48 F2 1 1.500 1.300 0.400

49 F10 1 3.300 3.000 0.900

50 F8 1 2.400 2.100 0.600

51 Along Grid J1
52 F9 1 2.400 2.400 0.650

53 Along Grid J2
54 F8 1 2.400 2.100 0.600

55 Along Grid K
56 F5 2 1.800 1.800 0.500

57 F8 1 2.400 2.100 0.600

58 F7 1 2.100 2.100 0.600

59 F3 1 1.500 1.500 0.400

60 Along Grid K1
61 F3 1 1.500 1.500 0.400

62 Along Grid L
63 F5 1 1.800 1.800 0.500

64 F3 1 1.500 1.500 0.400

65 Along Grid L1
66 F1 1 1.200 1.200 0.400

67 Along Grid L2
68 Along Grid L3
69 F3 1 1.500 1.500 0.400

70 Along Grid L4
71 Along Grid M
72 CF1 1 3.400 1.600 0.500

73 F5 1 1.800 1.800 0.500

74 F4 1 1.800 1.500 0.400

75 Along Grid N
76 CF1 1 3.400 1.600 0.500

77 F5 1 1.800 1.800 0.500

78 F3 1 1.500 1.500 0.400

79 Along Grid O
80 CF1 1 3.400 1.600 0.500

81 F4 1 1.800 1.500 0.400

82 F3 1 1.500 1.500 0.400

83 Along Grid P
84
85 Sub Total
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
EXTERNAL AREA
GRAND TOTAL
Complex for Murli Cement Works at Chandrapur

NEEDS TO TAKE ACTUAL UPO


Filling Qty Cum Till
Excav. Qty Cum Redu
Footing Top
Concrete PCC
Qty Cum THK
Soil Rock Available Imported OGL RTL RBL

3.313 4.084 8.167 8.939 0.075 - 0.500 - 1.500


2.643 3.218 6.435 7.010 0.075 - 0.500 - 1.500
3.454 2.869 5.738 5.152 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
4.417 5.445 10.890 11.918 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
1.104 1.361 2.722 2.980 0.075 - 0.500 - 1.500
1.321 1.609 3.218 3.505 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
1.104 1.361 2.722 2.980 0.075 - 0.500 - 1.500
1.905 1.901 3.802 3.799 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
3.026 2.531 5.063 4.568 0.075 - 0.500 - 1.500
3.313 4.084 8.167 8.939 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
2.796 3.281 6.563 7.048 0.075 - 0.500 - 1.500
3.313 4.084 8.167 8.939 0.075 - 0.500 - 1.500
2.030 2.194 4.388 4.551 0.075 - 0.500 - 1.500
1.905 1.901 3.802 3.799 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
2.796 3.281 6.563 7.048 0.075 - 0.500 - 1.500
6.909 5.738 11.475 10.304 0.075 - 0.500 - 1.500
1.321 1.609 3.218 3.505 0.075 - 0.500 - 1.500
3.026 2.531 5.063 4.568 0.075 - 0.500 - 1.500
1.104 1.361 2.722 2.980 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
1.321 1.609 3.218 3.505 0.075 - 0.500 - 1.500
1.905 1.901 3.802 3.799 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
2.796 3.281 6.563 7.048 0.075 - 0.500 - 1.500
3.026 2.531 5.063 4.568 0.075 - 0.500 - 1.500
1.321 1.609 3.218 3.505 0.075 - 0.500 - 1.500
2.030 2.194 4.388 4.551 0.075 - 0.500 - 1.500
1.905 1.901 3.802 3.799 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
2.030 2.194 4.388 4.551 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
4.060 4.388 8.775 9.102 0.075 - 0.500 - 1.500
3.810 3.802 7.605 7.597 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
0.959 1.196 2.392 2.629 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
1.263 1.921 3.843 4.501 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
0.959 1.196 2.392 2.629 0.075 - 0.500 - 1.500
9.725 5.434 10.868 6.576 0.075 - 0.500 - 1.500
3.454 2.869 5.738 5.152 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
4.232 3.251 6.502 5.522 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
3.454 2.869 5.738 5.152 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
3.810 3.802 7.605 7.597 0.075 - 0.500 - 1.500
3.454 2.869 5.738 5.152 0.075 - 0.500 - 1.500
3.026 2.531 5.063 4.568 0.075 - 0.500 - 1.500
1.104 1.361 2.722 2.980 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
1.104 1.361 2.722 2.980 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
1.905 1.901 3.802 3.799 0.075 - 0.500 - 1.500
1.104 1.361 2.722 2.980 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
0.713 0.911 1.822 2.021 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
1.104 1.361 2.722 2.980 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
3.186 3.106 6.212 6.133 0.075 - 0.500 - 1.500
1.905 1.901 3.802 3.799 0.075 - 0.500 - 1.500
1.321 1.609 3.218 3.505 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
3.186 3.106 6.212 6.133 0.075 - 0.500 - 1.500
1.905 1.901 3.802 3.799 0.075 - 0.500 - 1.500
1.104 1.361 2.722 2.980 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
3.186 3.106 6.212 6.133 0.075 - 0.500 - 1.500
1.321 1.609 3.218 3.505 0.075 - 0.500 - 1.500
1.104 1.361 2.722 2.980 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
134.596 135.110 270.220 - 270.733

- - - - 0.075 - 0.500 - 1.500


- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - 0.075 - 0.500 - 1.500
- - - - -
134.596 135.110 270.220 - 270.733
ABBREVATIONS:
Rock Top
FTL Footing Top Level RTL
Level
Rock
OGL / Original/Natural
RBL Bottom
NGL Ground Level
Level

Excavated
IL Invert Level EL
Level

FTL IL NGL RTL RBL EL


VAR VAR VAR VAR VAR VAR

S TO TAKE ACTUAL UPON COMPLETION

Reduced Level (RL) / Established level (EL)

REQD PCC PB PED. UGFL /


EL SGT FOOT. TOP PBB
EL TOP TOP TOP Plinth

- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050


- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.825 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.825 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.975 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.825 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.825 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.825 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.975 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.975 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.975 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.125 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.525 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.825 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.775 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.825 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.825 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.825 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 0.925 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.025 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050
- 1.500 - 0.525 - 1.425 - 1.425 1.050 1.050

- 1.500 - 0.525 - 1.425 - 1.425


- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
- 1.500 - 0.525 - 1.425 - 1.425
Plinth Beam UFGL / Plinth Upper Finished
PBB
Bottom Level Ground Level

Plinth Beam
PBT FFL First Floor Level
Top

Lower Ground
LGL SFL Second Floor Level
Level

Levels
PCC TOP FT. TOP PBT PBB LGL UFGL
VAR VAR VAR VAR 0.6 1.05

HEIGHT

SOIL ROCK
FILL PLINTH COLUMN
EXCAV EXCAV
REMARKS

0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000

0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
0.500 1.000
SGT SUB GRADE TOP

RFL Roof Level

FT. Top Footing Top

FFL SFL RFL SGT


5.05 9.05
BILL OF QUANTITIES [BOQ] WITH WORKING SPECIFICATION TOWARDS CIVIL & STRUCTURE [ONLY]
INCLUDING PERIPHERAL SITE DEVELOPMENT FOR THE PROJECT INTEGRATED OFFICE BUILDING
COMPLEX FOR MURLI CEMENT WORKS AT CHANDRAPUR [MAHARASHTRA]

A. CIVIL & STRUCTURAL WORK : PART-A


S. No. Description Unit Qty. Rate Amount Remarks
(Rs.) (Rs.)
1 EARTHWORKS -
1.1 Excavation:
1.1.1 Earth work in excavation including clearing away -
vegetation, if any, in foundations, trenches, drains etc., in
all type of soft/loose soil as classified in the
specifications, in both dry and wet conditions, including
back filling, dewatering, ramming and compacting of
excavated earth into the space between the building or
1.1.1.1 From average ground level to 3 m depth. CuM 650.00 240.00 156,000.00
1.1.1.2 3.0 m to 6.0 m depth CuM 340.00
1.1.2 Earth work in excavation including clearing away
vegetation, if any, in foundations, trenches, drains etc., in
all type of Hard / Dense soil as classified in the
specifications, in both dry and wet conditions, including
back filling, dewatering, ramming and compacting of
excavated earth into the space between the building or
1.1.2.1 From average ground level to 3 m depth. CuM 700.00 280.00 196,000.00
1.1.2.2 3.0 m to 6.0 m depth CuM 380.00
1.1.3 Earth work in excavation including clearing away
vegetation, if any, in foundations, trenches, drains etc. in
all type of ordinary rock as classified in the
specifications, including back filling, dewatering, ramming
and compacting of excavated earth into the space
1.1.3.1 between the building
From average ground or intotothe
level 3 mplinth,
depth.foundation as per CuM 500.00 460.00 230,000.00
1.1.3.2 3.0 m to 6.0 m depth CuM 560.00 -
1.1.5 Earth work in excavation including clearing away
vegetation, if any, in foundations, trenches, drains etc. in
all type of hard rock (blasting prohibited) chiselling as
classified in the specifications, including back filling,
dewatering, ramming and compacting of excavated earth
1.1.5.1 From average ground level to 3 m depth. CuM 600.00 1,750.00 1,050,000.00
1.1.5.2 3.0 m to 6.0 m depth CuM 100.00 1,850.00 185,000.00
-
2 Earth Filling: -
a) Filling available excavated earth [excluding rock] in CuM 740.00 220.00 162,800.00
specified area as per Engineer-In-Charge in layers not
exceeding 20cm in depth, breaking clods, watering,
rolling each layer with 1/2 tonne roller or wooden or
steel rammers and rolling every 3rd and top most layer
with power rollers of minimum 8 tones,...complete in all
respect at all levels / heights.

b) Foreign / Imported Earth: CuM 205.00 590.00 120,950.00


Excavating, supplying and filling of local earth [including
royalty] by mechanical transport upto a lead of 5 KM also
including ramming and watering of the earth in layers
not exceeding 20cm in depth, breaking clods, watering,
rolling each layer with 1/2 tone roller or wooden / or
steel rammers and rolling every 3rd and top most layer
with power roller of minimum 8 tones,....., complete in
all respect at all levels / heights.

- 99 - REVISION : R0
S. No. Description Unit Qty. Rate Amount Remarks
(Rs.) (Rs.)
3 Cement Concrete [Cast in Situ] towards PCC: -
Providing and laying PCC using graded stone aggregate of
specified size and down. The job includes machine /
manual mixing, placing, compacting by hand ramming,
curing for a period of 14 days etc., all complete. Vibrator
to be used whenever required without any extra cost at
all levels / heights. Removing of shuttering to be done
carefully without shock and vibration as to avoid damage
to the PCC work.

a) 1:3:6 [1 Cement : 3 coarse sand (zone-III) derived from CuM 106.00 4,400.00 466,400.00
natural sources : 6 graded stone aggregate 20 mm
nominal size derived from natural sources] base
preparation / leveller towards grade slab.

b) 1:4:8 [1 Cement : 4 coarse sand (zone-III) derived from CuM 98.00 4,400.00 431,200.00
natural sources : 8 graded stone aggregate 40 mm
nominal size derived from natural sources] base
preparation / leveler towards footings & foundations.

-
4(a) RCC : Weigh Batching [RMC] -
Providing and laying in position at all levels / heights
ready mixed cement of M-25 grade cement concrete for
reinforced cement concrete work, using cement content
as per approved design mix, including pumping of
concrete to site of laying at all levels / heights but
excluding the cost of centering, shuttering, finishing and
reinforcement, including admixtures in recommended
proportions as per IS: 9103 to accelerate, retard setting
of concrete, improve workability without impairing
strength and durability as per direction of Engineer-in-
charge, curing for a period of 28 days, removing of
shuttering......vibrator to be used whenever required
without any additional cost.
Note : Cement content considered in this item is @ 330
kg/CuM. Excess / less cement used as per design mix is
payable / recoverable separately.

i. Towards foundation, plinth beam, columns, grade slab, CuM 300.00 4,750.00 1,425,000.00
tie beams, floor / roof slabs….. from 0.00 mtr. to (-)9.00
mtr. Lvl.

ii. Towards foundation, plinth beam, columns, grade slab, CuM 610.00 4,950.00 3,019,500.00
tie beams, floor / roof slabs…..from 0.00 mtr. to (+)9.00
mtr. Lvl.

-
4(b) RCC : Weigh Batching [RMC] -
Providing and laying in position at all levels / heights
ready mixed cement of M-30 grade cement concrete for
reinforced cement concrete work, using cement content
as per approved design mix, including pumping of
concrete to site of laying at all levels / heights but
excluding the cost of centering, shuttering, finishing and
reinforcement, including admixtures in recommended
proportions as per IS: 9103 to accelerate, retard setting
of concrete, improve workability without impairing
strength and durability as per direction of Engineer-in-
charge, curing for a period of 28 days, removing of
shuttering......vibrator to be used whenever required
without any additional cost.
Note : Cement content considered in this item is @ 340
kg/CuM. Excess / less cement used as per design mix is
payable / recoverable separately.

i. Towards Fire Tender Driveway / Ramp -


From 0.00 mtr. to (-)9.00 mtr. Lvl. CuM 22.00 4,950.00 108,900.00
From 0.00 mtr. to (+)9.00 mtr. Lvl. CuM 35.00 5,150.00 180,250.00

- 100 - REVISION : R0
S. No. Description Unit Qty. Rate Amount Remarks
(Rs.) (Rs.)
4(c) RCC : Volumetric Batching - Qty. is
Providing and laying at all levels / heights site batched added in
design mix cement concrete 1:1:2 [1 cement : 2 coarse item
sand (zone-III) derived from natural sources : 3 graded no.4(a)ii
stone aggregate 20mm nominal size derived from natural
sources] excluding the cost of centering, shuttering,
finishing and reinforcement, including admixtures in
recommended proportions as per IS: 9103 to accelerate,
retard setting of concrete, improve workability without
impairing strength and durability as per direction of
Engineer-in-charge, curing for a period of 28 days,
removing of shuttering......vibrator to be used whenever
required without any additional cost.

i. Towards chajjas, projection, coping, steps, kerbs, lintel CuM 4.00 -


beams…etc.
-
5 Form Work: -
Centering and shuttering including strutting, propping
etc. at all levels / heights and removal of form for :

a) Foundations, footings, bases of columns, etc. -


Floors, roofs, landings, balconies and access platform.
Lintels, beams, plinth beams, tie beam, bressumers and
cantilevers
Columns, Pillars, Piers, Abutments, Posts, Pedestal and
Struts

i. From 0.00 mtr. to (-)9.00 mtr. Lvl. SqM 1,200.00 610.00 732,000.00
ii. From 0.00 mtr. to (+)9.00 mtr. Lvl. SqM 4,560.00 690.00 3,146,400.00
-
6 Scaffolding: SqM 1,650.00 - Item is not
Providing and fixing double scaffolding system (cup lock req.
type) on the exterior side of building/structure, upto 25 Formwork
metre height, above ground level, including additional rate will
rows of scaffolding in stepped manner as per included
requirement of site, made with 40mm dia M.S. tube, scaffolding
placed 1.5 metre centre to centre, horizontal & vertical cost
tubes joint with cup & lock system with M.S. Tubes, M.S.
tube challis, M.S. clamps and staircase system in the
scaffolding for working platform etc. and maintaining it in
a serviceable condition for execution of work of cleaning
and/ or pointing and/ or applying chemical and removing
it thereafter. The scaffolding system shall be stiffened
with bracings, runners, connecting with the building etc,
wherever required, if feasible, for inspection of work at
required locations with essential safety features for the
workmen etc., complete as per directions and approval
of Engineer-in-charge.
Notes :
1. The elevational area of the scaffolding shall be
measured for payment purpose.
2. The payment will be made once only for execution of
all items for such works.

- 101 - REVISION : R0
S. No. Description Unit Qty. Rate Amount Remarks
(Rs.) (Rs.)
7 Reinforcement Steel: MT 112.00 18,000.00 2,016,000.00 steel will be
Supply, fabrication, hoisting and placing in position suplay from
Thermo-Mechanically Treated [TMT] bars of grade Fe- client.
500D or more as per drawing including cutting, bending, (Dalmiya
cranking and tying with 18 SWG black annealed binding cement)
wire pre cast fibre concrete cover block & plastic spacers
complete. The rates shall be applicable for all heights and
depths. Payment shall be made as per reinforcement
drawings and with theoretical weights only including all
authorised laps, chairs and hooks.

-
8 Anti Termite Treatment: SqM 1,335.00 230.00 307,050.00
Diluting and injecting chemical emulsion for anti-termite
treatment to the soil under PCC bed using chemical
emulsion [Chlorpyriphos / Lindane E.C. 20% with 1%
concentration] @one litre per hole @300mm interval
including drilling 12mm diameter holes at 45 degree and
plugging them with cement mortar 1:2 [1 cement : 2
coarse sand] upto the full depth of the hole to match the
existing top surface.
Notes:
1. Rates inclusive of chemical emulsions.
2. Contractor will have to submit 10 years guarantee
bond on Rs. 100/- stamp paper [non-judicial] for the
treatment.

-
9 Insert Plate: MT 0.06 18,000.00 1,080.00
Providing and keeping inserts including M.S angles,
channels, bars, lugs, plates etc at specified levels during
casting with necessary fixing arrangements so that
they remain true in position complete inclusive of all
requisite materials, labour complete as per drawing /
direction at all levels / heights.

-
10 Brick Masonry : Full Brick 6,150.00 -
Constructing brick masonry @230mm thick in cement
mortar 1:4 [1 cement : 4 coarse sand (zone-III) derived
from natural sources-Red Bricks] using locally available
bricks of Class designation 7.5 including providing all
openings and projections, raking the joints to 1 cm deep,
soaking of bricks in water prior to use and curing 7/10
days etc. all complete as per specifications at all levels /
heights.
a) Substructure underneath plinth beam CuM 70.00 6,150.00 430,500.00
b) Superstructure within the building - internal walls at all CuM 286.00 6,300.00 1,801,800.00
floors.
-
11 Brick Masonry : Half Brick: SqM 35.00 1,390.00 48,650.00
Constructing brick masonry @115mm thick partition
wall in cement mortar 1:3 [1 cement : 3 coarse sand
(zone-III) derived from natural sources-Red Bricks] using
locally available bricks of Class designation 7.5 including
providing all openings and projections, raking the joints
to 1 cm deep, soaking of bricks in water prior to use and
curing 7/10 days etc. all complete as per specifications
including providing and placing in position 2 Nos 6mm
dia MS bars at every third course of half brick masonary
at all levels / heights.

- 102 - REVISION : R0
S. No. Description Unit Qty. Rate Amount Remarks
(Rs.) (Rs.)
12 Autoclaved Aerated Concrete [AAC] Block Masonary: -
Providing, laying in position of AAC Block [Size : 600mm
(l) x 300mm (w) x 200mm (d)] of dry weight density of
21.6 kg with self curing block jointing mortar in 3:1
[powder to water] at levels & height, completed in all
respect.

a) Superstructure of wall thickness 300mm / 200mm CuM 312.00 7,350.00 2,293,200.00


towards external peripheral wall of the building.

13 Plaster: -
Providing and laying average required thick cement
plaster in ratio 1 : 4 : 1 [1 cement : 4 fine sand derived
from natural sources : 1 coarse sand (zone-III) derived
from natural sources]. Rate to include use of
waterproofing compound as per manufacturer's
recommendation and providing necessary chicken wire
mesh at all joints of brick and concrete surfaces, with a
minimum overlap of 150 mm in all directions and curing
7/15 days complete. No extra payment shall be made for
additional thickness if required to achieve perfect line
and level. The job includes cleaning, wetting of surface
before plastering etc. all complete. Required grooves to
be formed as required / directed.

a) 15-18mm thick towards uneven surface SqM 1,312.00 395.00 518,240.00


b) 12mm thick towards even surface SqM 2,750.00 395.00 1,086,250.00
-
14 Waterproofing: SqM 120.00 490.00 58,800.00
Providing and laying waterproofing treatment in sunken
portion of wet area by applying cement slurry mixed with
waterproofing cement coumpound consisting of
applying:

a) First layer of slurry of cement @ 0.488 kg/sqm mixed -


with waterproofing cement compound @ 0.253 kg/ sqm
including rounding off junction of verticals and horizontal
surface. This layer will be allowed to air cure for 4 hours

b) Second layer of slurry of cement @ 0.242 kg/sqm mixed -


with waterproofing cement compound @ 0.126 kg/sqm
including rounding off junction of verticals and horizontal
surfaces. This layer will be allowed to air cure for 4 hours
followed with water curing [ponding] for 48 hours.

Note : The rate includes preparation of surface, -


treatment and sealing of all joints, corners, junctions of
pipes and masonry with polymer mixed slurry.
-
15 Sleeve: -
Providing and placing pipe sleeve [circular] at
appropriate position and length across the RCC beams /
slabs during casting of following cross - sectional
diameters.

a) For 110mm dia pipe Rmt 6.00 350.00 2,100.00


b) For 150mm dia pipe Rmt 6.00 350.00 2,100.00
-

- 103 - REVISION : R0
S. No. Description Unit Qty. Rate Amount Remarks
(Rs.) (Rs.)
16 Terracing : Waterproofing with Thermal Insulation -
a) Step A : Brick Bat Coba SqM 810.00 1,190.00 963,900.00
Providing and placing wholly burnt brick bat soaked
overnight in water of the size 70mm to 120mm in
staggered manner [to avoided continuous horizontal
joint of the mortar] in a slope of 1:150 laid over 110mm
thick base green mortar 1:4 [1 cement : 4 coarse sand
(zone-III) derived from natural source] admixed with
waterproof about 70mm near rainwater pipe / khurra's
and 150mm at ridge, keeping 15/20mm gap in between
is fitted with cement sand mortar 1:4, admixed with
waterproof. In hot and dry weather, the surface should
be covered with wet gunny bags, immediately after
finishing. Continuous curing for 7 days start next day
[Rates inclusive of surface preparation @ cleaning with
hard wire brush and washed with water and elimination
of surface cracks with polymer modified concrete]

b) Step B : Finishing Layer - Glazed China Mosaic SqM 810.00 1,190.00 963,900.00
Top surface finished with 20/25mm thick cement sand
mortar 1:4 [1 cement : 4 coarse sand (zone-III) derived
from natural source] uniformly and checked for level and
slope and left for a day to harden. Water is sprinkled on
this bed [machine] and dry cement is spread on the work
area for 15 minutes and then after pieces of glazed
broken chine mosaic tiles are placed over in pattern
closely packed with gap of 3mm / 4mm presses and fitted
in position upto 300mm vertical height on parapet and all
curves / golas. Then after the laid glazed broken china
mosaic tiles are hammered with wooden mallet to
achieve a uniform surface then after gap in between is
filled with white cement slurry with a small travel over to
remove. The surface is cleaned with saw dust, to remove
excess cement sticking to the glazed china mosaic
surface and then curing for 15 days of ponding with
forming bunds.

-
17 Toe Wall:
Providing and constructing random rubble masonry with
hard stone in Cement mortar 1:6 [1 cement : 6 coarse
sand (zone-III) derived from natural sources] for
substructure [foundation @600mm width, pedestal upto
plinth / ground level] & superstructure [pedestal
@350mm width & height ≤1050mm w.r.t. ground level]
as per IS 1597 Part I, Latest Edition maintaining place
even exposed elevational surface including levelling up
with cement concrete 1:6:12 [1 cement : 6 coarse sand
(zone-III) derived from natural sources : 12 graded stone
aggregate 20mm nominal size derived from natural
sources]. Rate to include soaking stones, cleaning the
erta mortar over stone by wire brush, raking the joints to
10mm deep and curing complete [exposed one side
elevation surface and top]. One through / bond stone
shall be provided for every square meter of facing, evenly
distributed in a staggered pattern. They shall have about
0.03 sqm in face area and shall have a tailing for the full
width of masonry upto 600mm / 350mm.

a) Substructure CuM 110.00 4,100.00 451,000.00


b) Superstructure CuM 60.00 4,100.00 246,000.00
-

- 104 - REVISION : R0
S. No. Description Unit Qty. Rate Amount Remarks
(Rs.) (Rs.)
18 Rubble Soling : Sub Base CuM 450.00 2,100.00 945,000.00 Qty. was in
Providing rubble soling of thickness 230mm including Sq.M. and
surface dressing & compaction, soaking the rubbles changed in
before laying, packing the gaps using small size rubble / CuM.
murrum and hand ramming / using mechanical roller /
compactor, complete in all respect [Applicable for the
area fire tender, driveway, footpath, plinth protection
and area of grade slab,....any area of having earth filling
≥600mm].

-
19 Providing and fixing stainless steel [Grade-304] horizontal Kg 6,000.00 625.00 3,750,000.00
fins / grills made of hallow circular tubes, channels,
plates etc. including welding, grinding, buffing, polishing
and fitting the same with necessary stainless steel nuts &
bolts complete with necessary accessories & stainless
steel dash fasteners,... of required size on top / bottom /
sides of waist sub-strate with suitable arrangement [For
payment purpose only weight of stainless steel members
shall be considered excluding fixing accessories such as
nuts / bolts / fasteners...etc.] at all levels / height.

-
20 Rainwater Pipe: -
Providing, placing in position [vertical stacking /
horizontal laying] and fixing UPVC SWR pipe Class-V
[@10kg/cm2] Compliance to IS : 4985 with fittings
[elbow, reducing elbow, tee, reducing tee, reducing
coupler, end cap, male / female threaded adaptor, jali
round, vent cowl, pipe clamp, service saddle, multi floor
trap, reducing bush, flange tale piece, PVC solvent
cement...] Compliance to IS : 7834 resting in plan [in
case of horizontal laying] on 75mm thick and 250mm
wide in cement concrete [1:2:4 mix (1 cement : 2 coarse
sand (zone-III) derived from natural sources : 4 stone
aggregate of 10mm and down size derived from natural
sources)] bed and all around of approved make with
gradient between 1/4" per foot to 1/8" per foot in plan
as the case of following diameter.

a) 110mm dia nominal size Rmt 60.00 400.00 24,000.00 48.00


-
21 Making plinth protection / apron 50mm thick of cement CuM 4.80 4,100.00 19,680.00 Qty. was in
concrete 1:3:6 [1 cement : 3 coarse sand (zone - III) Sq.M. and
derived from natural sources : 6 graded stone aggregate changed in
20 mm nominal size drived from natural sources] over CuM.
75mm thick bed of dry brick ballast 40 mm nominal size,
well rammed and consolidated and grouted with fine
sand, including necessary excavation, levelling & dressing
& finishing the top smooth

-
22 Weep Holes 75mm Dia PVC: Rmt 150.00 400.00 60,000.00
Providing, fabricating and installing in place, 75 mm dia
6Kg / sqcm PVC Pipes of various lengths & at places as
approved and directed at site on the random rubble
masonry wall for self water drainage. The pipes shall be
fixed with nylon jali using resin / glue on inside end of
wall.

- 105 - REVISION : R0
S. No. Description Unit Qty. Rate Amount Remarks
(Rs.) (Rs.)
23 Khurra: Nos 12.00 900.00 10,800.00
Making khurras 450 x 450mm with average minimum
thickness of 50mm cement concrete 1:2:4 [1 cement : 2
coarse sand : 4 graded stone aggregate of 20 mm
nominal size] over P.V.C. sheet 1 m x1 m x 400 micron,
finished with 12 mm cement plaster 1:3 [1 cement : 3
coarse sand] and a coat of neat cement, rounding the
edges and making and finishing the outlet complete.

-
24 Concrete Pavements: CuM 40.00 5,500.00 220,000.00
Providing and laying 150mm thick cement concrete
prepared with batch mixing machine in 1:3:4 [1 cement :
3 coarse sand (zone-III) derived from natural sources : 4
graded stone aggregate 40mm nominal size derived from
natural sources] in pavements. Laid to required slope and
camber in panels using MS channel shuttering, vibrating
with screed board vibrator, laid in block of required size,
cutting the joints by diamond blade saw and filling gaps
with hardening compound, pond curing for 14 days,
vacuum dewatering, finished with power trowelling in
brush finish, complete in all respect.

-
TOTAL 27,830,450.00

- 106 - REVISION : R0

You might also like