V-D211-21BAT10-YA-001 - 3 - Installation, Operation and Maintenance Instruction Manual
V-D211-21BAT10-YA-001 - 3 - Installation, Operation and Maintenance Instruction Manual
D211-EKA-TTCL-004
FINAL
SECTION TITLE
1 Transportation 6
1.1 Cautions for Transportation
1.2 Inspection and instruction on
Arrival at site
2 Before Installation 12
2.1 Storage
2.2 Inspection of packages and unpacking
CONTENT
SECTION TITLE
3 Installation 18
3.1 Caution for transformer installation
3.2 Supervisor for work and safety measures
3.3 Preparation of tools, instruments and material
3.4 Flow chart for installation
3.5 Setting of the transformer on a bed
3.6 De-aerated oil filling up to the level above coil
3.7 Fitting of radiators
3.8 Fitting of mounts for bushing
3.9 Fitting of conservator
3.10 Fitting of cooling fan
3.11 Oil piping
3.12 Piping and wiring of electrical system
3.13 Fitting of bushing
3.14 Fitting of condenser type bushing
3.15 Fitting of solid type bushing
3.16 Oil filling and draining process
3.17 Caution for thermometer lead line
To enter in local control cabinet
CONTENT
SECTION TITLE
4 Transportation 67
4.1 Inspection and test after installation
4.2 Field test after installation
4.3 Painting
4.4 Re-drying of the transformer at job site
4.5 Caution when energizing transformer
SECTION 1
TRANSPORTATION
Ref.No. : IE-12101
1.1 CAUTIONS FOR Rev. : C
DAIHEN ELECTRIC TRANSPORTATION Date : 24-Nov-09
CO., LTD. Page : 1 / 3
Use a steel wire having sufficient strength to lift the transformer, etc.
Hoist it by the lifting lugs specified by the transportation drawing.
Transformer
Boat
Transformer
Fig. 2
Pressure gauge
Transformer
Transformer
Fig. 3 Fig. 4
When the transformer is shipped by rail, there is no problem while the train is
running, however attention should be paid to prevent shock during loading and
unloading work. It is undesirable to incline the transformer too sharply. The angle
of slope should be within 10° as illustrated in Fig. 5.
Ref.No. : IE-12101
1.1 CAUTIONS FOR Rev. : C
DAIHEN ELECTRIC TRANSPORTATION Date : 24-Nov-09
CO., LTD. Page : 3 / 3
Transformer
Cargo train
10º
Fig. 5
It is better to install a tachometer on the trailer or the train or attach a shock meter to
the transformer itself. To measure the angle of slops of the transformer, use a plum
bob.
1.2 INSPECTION AND Ref.No. : IE-11101
INSTRUCTIONS
Rev. : D
DAIHEN ELECTRIC Date : 23-Jan-07
CO., LTD. ON ARRIVAL AT SITE Page : 1 / 2
Immediately on arriving at site, the following examination should be made for any
damage sustained in transport, and a check for lost parts.
Remove the protective cover for the compound gauge mounted on the tank, and
open the connecting valve, and check the gas pressure. (After checking the
pressure, close the valve tightly.) Positive indication shows that air and / or water has
not entered into the tank.
If the point read zero, air ingress might happen. At this occasion, measure the
insulation resistance of windings to know the degree of moisture impregnation refer
to the "INSTRUCTIONS FOR INSPECTION AND MAINTENANCE" for the criterion
of moisture impregnation.
Measurement in low humidity atmosphere is preferable to prevent the live parts
from moisture impregnation. If the measured value is lower than the criterion, a
drying treatment will be required.
When a shock recorder is provided, check the records carefully after arrival at
site. If the recorded figures at all axis exceed 3 G, please contact DAIHEN
ELECTRIC CO.,LTD.
(2.2) Rust
When the painting is damaged or the metal parts are rusted, remove the rust
with a sandpaper, and coat with touch-up paint.
Check if the bolts and nuts are loosed. When the bolts fastening the covers or
valves are loosed, make measurement for insulation resistance mentioned above
(1).
Check the impact recorder chart before transferring the transformer and after the
arrival to the destination. If the recorded figure exceeds the following value,
please ask manufacture for further information.
- Vertically : 3 G
- Length-wise : 3 G
- Short-wise : 3 G
(3) Transport at site and unpacking
Refer to IE-12101 and IE-14101 in this instruction manual.
CAUTION :
Before removing a manhole cover, shipping plate, or other device, vent the
transformer to atmospheric pressure. Do not enter the transformer until the gas
space has been flushed with dry air, or a suitable oxygen (not less than 18% of
oxygen in the tank) supply is available for safety working.
SECTION 2
BEFORE INSTALLATION
Ref.No. : IE-21102
Rev. : A
2.1 STORAGE 18-Dec-09
DAIHEN ELECTRIC Date :
CO., LTD. Page : 1 / 1
It is recommended that the transformer will be put into service immediately in its
permanent location. If this is not possible, the following precautions must be taken
to insure the proper storage of the transformer.
(1) The transformer tank has been filled with dry nitrogen gas totally . When
stored for more than 4 months from the date of shipment, the transformer tank
should be filled with insulating oil up to the level lower than the tank cover by
about 25 cm. The gas space between the cover and the oil should be filled with
dry nitrogen gas.
As to the oil filling method , refer to clause IE - 41201 in this instruction . The
gas pressure must be checked periodically .
After fill with insulation oil up to the level lower than the tank cover by about
25 cm,the nitrogen gas will dessolve into insulation oil .
When nitrogen gas pressure deteriorated less than 0.1 kg/cm², the nitrogen
gas shall be supplemented.
The gas filling pressure ,refer as following.
(2) It is recommended that the transformer tank and accessories will be stored
indoor. The accessories would be stored in the boxes to avoid the loss of them.
When the accessories are taken out from the boxes, vinyl sheets covering the
accessories should not be removed.
When stored outdoor, cover totally the tank and accessories with strong water
proof sheets to prevent the water ingress. And lay wooden beams under the
tank and boxes. The tank and accessories should be stored in a dry and clean
location, free form corrosive gases or fumes.
It is necessary to inspect the number of packages and unpack these in the presence
of a representative of your company and our technical staff in the
following manner.
Especially to the packages opened at the time of custom clearance, this should
be carried out most carefully, As to the packages damaged or packages whose
contents are missing, take the necessary action regarding an insurance claim and
take pictures to cover a future claim for insurance money.
(3) Unpacking
When the checking of the number of packages and inspection of the appearance
is over, open the packages. Unpack the wooden boxes carefully by using pincers
so that the contents are not damaged. As far as possible avoid the use of a crow
bar. After unpacking a wooden box, or cardboard box etc. inspect the number
and appearances of the parts according to (1) and (2).
Crow bar
Pincer
Fig. 1
Unpack the package holding bushing carefully according to the following
method, and using care not to damage the contents.
Ceiling
When the package is longer in
Cover the upright position as shown by
the figure at left, do not lay it down
Inner partition in a horizontal position but open it
board in upright position according to the
following.
Cover
Support
- Do not cut
Fig. 3
When the packing is an inclined package as shown above, do not cut off the
supports but draw out the nails by pincer and remove the cover and inner
partition board while keeping it in the inclined position. Do not use a crow bar.
As for the handling of bushing after unpacking, refer to the instructions for
bushing.
Ref.No. : IE-14101
2.2 INSPECTION OF Rev. : -
DAIHEN ELECTRIC PACKAGES AND UNPACKING Date : 20-Jan-04
CO., LTD. Page : 3 / 4
Cover
Fig.4
When the package is a horizontal type as shown above, draw out nails by pincers
and remove the cover and inner partition board. Do not use a crow bar.
No good No good
Good
Ref.No. : IE-14101
2.2 INSPECTION OF Rev. : -
DAIHEN ELECTRIC PACKAGES AND UNPACKING Date : 20-Jan-04
CO., LTD. Page : 4 / 4
In storing the radiators vertically, do not arrange them in more than 3 levels.
Prevent damage by inserting wood blocks in between the radiators. (Fig.6)
Wood
Aligned vertically
Fig.6
SECTION 3
INSTALLATION
Ref.No. : IE-13404
3.1 CAUTIONS FOR Rev. : C
DAIHEN ELECTRIC TRANSFORMER INSTALLATION Date : 20-Jan-04
CO., LTD. Page : 1 / 4
The main tank must be lifted by the same manner as IE-12101. When the transformer
is skidded, moved on rollers or jacked up, take care not to injure the base and not to tip
over the transformer. The transformer is also equipped with jacking bosses . Jacks
should be placed under the jacking bosses . The transformer should never be lifted or
moved with jacking up the radiators or other accessories . When rollers are used , skids
must be placed between the base and the rollers to distribute the stress .
3) Lifting of accessories
Position and direction of the accessories and other parts should be according to the
transformer drawing exactly. Before fitting them, read the instructions completely.
Mishandling will result in damage to the accessories.
b) Apply the liquid gasket (Super Three Bond 1215) to both sides of CN-PG,
smoothly and uniformly.
c) Then, attach the separated parts to their positions with gasket.
d) Start of oil filling should be more than 24 hours after applying the liquid gasket .
e) If temporary fixing of gaskets are needed for vertical or inclined joints , apply the
adhesive ( Cemedine 501 ) around the gasket (refer to Fig.1) Cemedine 501 is
included in our packing .
xxxx
xxxxxxxxx
Flange (mm.) 5 5
5 5
(mm.)
Cemedine 501
( o maker ) Fig. 1
NBR - PG
Flange Fig. 2
Cemedine 501
( o maker )
Ref.No. : IE-13404
3.1 CAUTIONS FOR Rev. : C
DAIHEN ELECTRIC TRANSFORMER INSTALLATION Date : 20-Jan-04
CO., LTD. Page : 3 / 4
5) Fastening of stud-bolts
Each stud-bolt should be screwed rigidly. But in order to avoid the stud-bolt broken,
fasten the stud-bolt under suitable torque as follows by measuring torque wrench or
torque meter.
Lower side
Thermometer
Silicone
Terminal box
Silicone
Ref.No. : IE-15101
3.2 SUPERVISION FOR WORK Rev. : -
DAIHEN ELECTRIC AND SAFETY MEASURES Date : 23-Dec-03
CO., LTD. Page : 1 / 6
Customer like
Our company
your company
Supervisor Engineer, Person-in-charge
Workmen
The leader in turn assigns a specific part of the work to each workman, and
then the working party executes.
First of all, measure the concentration of oxygen inside the tank by means of
the oxygen densitometer, confirm that the oxygen concentration is more than
18% and record the concentration value.
Working lamp
Next, it is necessary to use working lamp having a sufficient intensity of
illumination for safety and to facilitate work inside the tank.
A working lamp with guard is recommended in order to prevent a workman
from receiving an electric shock as well as to protect the bulb from damage
due to unintentional knocks. Oil proof lead wire is recommended.
The lower the voltage of working lamp the better it is, for safety.
Pay attention to the above-mentioned points, and carry out work inside the
transformer tank.
Moreover, prohibit one man work inside the tank, and station a watch at a
place from where he can see workmen.
Finally, consider the fastening of a rope to each workman who enters the
transformer tank.
This can be used in an emergency. The rope would be the means of
rescuing a workman and would be pulled form the outside.
In the case of lifting an article under the horizontal condition or in the case of
fine adjustment in lowering, it is recommended to use a chain block together
with crane car.
Chain
block
In the case of work to be done inside the transformer and work on the
indoor panel, it such work is difficult to do wearing the above-
mentioned clothes, it is in order to put on the cloth working cap and
canvas shoes instead of the helmet and leather laced boots with
permission of customer's person in charge and field work responsible
person of our company.
e.2) A workman should not come within a less distance than show in the
following table from any high-tension part:
Ref.No. : IE-15101
3.2 SUPERVISION FOR WORK
Rev. : -
AND SAFETY MEASURES
DAIHEN ELECTRIC Date : 23-Dec-03
CO., LTD. Page : 6 / 6
The items, specifications and requirements for all tools and materials
required for assembling, inspection and testing of transformer are listed below.
Acceptance criteria
More than 30kV for average value
Standard reference
IEC 60156 (1995)
Acceptance criteria
Limit (Max) 0.20 mg KOH/g
Acceptance criteria
Limit (Min) 25.0 mN/m
Procedure 1 Sampling oil from main tank into water content tester
2 Set timer 10 – 15 Sec for testing
3 Test result will be record by tester ( PPM)
Acceptance criteria
< 35 PMM
Standard reference
ASTM D 1533
Acceptance criteria
< 0.5% @ 25 ºC
1.6 Colour test ( Sampling by Ekarat and submit to EGAT Lavatories) Standard
reference ASTM D 1500
Acceptance criteria
Limit (Max) 2.50
Appendix 1 Page 2/2
Objective Dissolved gas in oil shall be analyzed by automatic dissolved gas in oil analyzer. Oil
shall be collected from filter valve at time of before any tests and after dielectric
tests and temperature rise tests.
Standard reference
ASTM D3612-02 (2009)
Acceptance criteria
No C2H2
Ref.No. : IE-81101
3.3 PREPARATION OF TOOLS, Rev. : A
DAIHEN ELECTRIC INSTRUMENTS AND MATERIALS Date : 21-Dec-03
CO., LTD. Page : 4 / 6
(c) Ammeter
One set each of the following precision
double range ammeter are required for
measurement of exciting current when low
voltage is impressed on the transformer and
for measurement of current of auxiliary
apparatus of the transformer such as cooling
fan, oil pump, etc. If they are equipped on
the transformer.
AC 20/100 mA ...................... 1 set
AC 10/50 A ...................... 1 set
(e) Megger
Megger is used for measurement of
insulation resistance.
Manually operated megger having rating of
about 2000V and 2000MW as appropriate.
(k) Others
Instruments necessary of executing a
temperature rise test, measurement of
dielectric loss tangent (d), noise test
and High voltage test should be
obtained.
(3) Tools
(a) Drum opener
(b) Screw driver for cross recessed head screws
(c) Screw driver for slotted head screws
(d) Scissors
2
(e) Compression pliers (for 2.0, 3.5, 5.5, 8.0mm )
(f) Pliers
2
(g) Wire stripper (for 2.0, 3.5, 5.5, 8.0mm )
(h) Jack with capacity of 10 t
(i) Monkey wrench 6", 8", 10", 12"
(j) Spanner
(k) Pincer.
Ref.No. : IN-10013
3.4 FLOW CHART Rev. : C
DAIHEN ELECTRIC
FOR INSTALLATION Date : 19-Jan-09
CO., LTD. Page : 1 / 1
Yes
Note
No
FIT COMMON PIPES OF RADIATOR Note :
In case of oil filling
VACUUM TREATMENT under vacuum up to level
above coil from factory.
(#1) OIL FILLING UP TO LEVEL ABOVE COIL
(1) On bed
Take care not to incline the transformer too sharply, and prevent it from shocking
during installation work. The foundation should be able to bare the load and the
vibration of an earthquake. Since the center of the transformer is marked ( ↓ ) at the
bottom side, line it up to the center of the specified installation site. To adjust the
perpendicular alignment of transformer, use the markings at the top and bottom of the
transformer and check with a plumb bob, etc. If it is not perpendicular, insert thin iron
plates at an approprite point to adjust it perpendicularly.
Install the transformer with attached anchor bolts at the correct position in the way
previously stated and then fix the anchor bolts with cement. After a few days, when
the cement is sufficiently dry, again clamp the anchor bolts and secure them.
It is necessary to carry out dielectric strength test of insulating oil stored in the
drums before oil filling.
Take samples from each drum and check whether they have specified
dielectric strength. If the oil does not have specified dielectric strength, filter the
entire oil content. Oil filling should be carried out only after its dielectric strength
reaches the specified value.
There are two methods to carry out oil filling. The first method is to fill with oil
through the drain valve while discharging gradually the nitrogen gas filled in the
tank. (see Fig. 2) The nitrogen gas pressure in the transformer tank should be
kept the value of from 0.05 to 0.2 kg/cm2 during oil filling.
The second one is to do oil filling after vacuuming the transformer. (See Fig. 3)
This method is superior to the first one.
approx. 25 cm
Insulating oil
Tank
Coil
Fig. 1
Discharging N2 gas
Compound gauge
Fig. 2
Compound gauge
Transformer
1. Fitting of radiators :
Radiators are shipped separately. Blank covers are attached to the openings
of radiators and radiator valves to prevent moisture. Radiator valve is located on
each radiator connection so that any individual radiator may be removed in time
of necessity without lowering the oil level of the transformer tank.
As each radiator has an oil drain plug and an air relief plug, it is easy to drain
the oil individually.
The radiator withstands the same vacuum (full vacuum) and pressure condition
as the main tank.
Radiators should be handles carefully to prevent bending or puncturing the
panels.
Position number is stamped on the upper header of each radiator and this
should be matched with the position number stamped on the flange on the main
tank side. Fit the radiator according to the following procedures.
(1) Hoist the radiator from the stored position, and pay attention not to
damage other radiators with the hoisting tools.
(2) Remove the blank cover and gasket on the radiator.
(11) Match the radiator valve and the flange surface of the radiator and
clamp them by nuts. (See Fig.2)
(12) Clamp the pair of nuts located diagonally one after another in order to
clamp evenly. (See Fig. 4)
(13) Clamp them tightly until the radiator valve and radiator flange closely
match with each other.
When radiator fitting is over, attach the supports and the fasteners of the
radiator symmetrically as shown in fig. 5 and 6
(1) Fit the supports (E) at the transformer tank wall. (since the radiator in
outer and obstacle for fitting the supports (E) , it is preferable of fitting the
radiator) before.
(2) Put the fasteners (A) and (B) on the upper side of the radiators and put
(C) under the lower side (see Fig.7)
(3) Set jacks under the support (C) and jack up until the radiator may be
vertical (see Fig.6)
(4) Keeping the radiators vertical, joint the supports (E) to the support (C)
and fix with nut.
Clean surface
Fig. 1
Ref.No. : IE-61202
Rev. : A
3.7 FITTING OF RADIATORS
DAIHEN ELECTRIC Date : 24-Dec-03
CO., LTD. Page : 3 / 4
Radiator valve
Fig. 2 Clamp it until there is
no clearance
Stemp of number
Radiator
Fig. 3
Incline and
drain residual
oil.
Fig. 4
Ref.No. : IE-61202
Rev. : A
3.7 FITTING OF RADIATORS
DAIHEN ELECTRIC Date : 24-Dec-03
CO., LTD. Page : 4 / 4
(B)
(A)
Radiator
(C)
(E)
Jack
(C)
Fig. 6
Fig. 5 (A),(C)
(B)
Fig. 7
O S O S
The mechanism of the transformer which may be equipped with the mount is
showing Fig. 1.
Do not give severe shock to the mount since the current transformer is often
located in it.
(1) Check the stamp indicate which phase the mount is fitted to . (See Fig. 2)
(2) Open the CT terminal box attached to the mount and measure the insulation
resistance of CT. It should be 200 MΩ and above.
(3) Remove the top and bottom blank cover of the mount, pass the insulated
wire into CT and check the polarity of CT for all taps . (See Fig. 3) The
polarity is shown in the nameplate .
(4) Carefully remove the blank cover on the mount fitting flange, and also
remove gasket. (On the transformer side).
At this time, pay attention not to let bolts, nuts, tools and dirt fall into the
transformer.
(5) Clean the flange part by sand paper, and apply a small amount of adhesive
to the surface, and fix the new gasket.
(6) Hoist the mount by crane car and pass the lead wire through the central
hole of it. (See Fig. 6)
The lead wire is fixed in the transformer by tape during transport. When
drawing up it, remove the tape and pay attention not to damage the lead
wire and not to apply external force to the transformer coil.
(7) Clamp the bolts and nuts uniformly until the stopper on the flange matches
to the mount flange. (See Fig. 4).
(8) when fitting is over, tie the lead wire at the nut which welded below the
blank cover. (See Fig. 5)
Bushing Stamping
Insulated wire
Mount CT terminal
box terminals
Trans-
former CT
CT G
Fitting flange
Fig. 1 Fig. 2 Fig. 3
Nut
Fig. 4 Fig. 5
Mount
Lead wire
Tank cover
Core
Transformer coil
Fig. 6
Ref.No. : IE-63401
3.9 FITTING OF CONSERVATOR Rev. : C
DAIHEN ELECTRIC Date : 20-Jan-04
CO., LTD. Page : 1 / 3
(1) The rubber cell type conservator is shipped separately and filled with
nitrogen gas to prevent from moisture.
When mounting the conservator on the transformer, it is necessary to take
care of the followings.
Don't heat the conservator by welding or grinding, as the rubber
diaphragm is installed in.
Please refer to the instruction of rubber cell type conservator in detail.
Handhold
Oil level gauge Conservator
Rubber cell
Protective relay
Fig. 1
Float
Conservator Float
Indicator
Lifting lug
Conservator
Mounting bracket
(1) Fitting
The cooling fans attached to the radiator panel The radiators, which provided
with fan fitting supports, are located at the end of each cooling bank.
The fans will be installed to the supports by nuts fastened surely. The fan
motors should be placed so that their cable outlets will be at the bottom of a fan
motor.
(2) Cabling
The terminal boxes, to which fan motor cables are to be connected , are
attached to the fitting supports on the radiator panel . After terminating the
cables as shown in Fig.1, connect them with the terminal blocks with confirming
to match the wire color to the block mark, i.e. The black covered wire is
connected to the blue mark U, the grey to V, the red to W and the black to E .
(3) Checking
After wirings are completed, supply the proper power to the fan motors, and
make sure that the fans rotate in the normal direction and without abnormal
sound.
U V W E Terminal block
Blue Black
Red
Reinforced with vinyle tape
Grey
Rotation
Fan fitting Fan motor
supports Junction box
Radiator panel
Cable
Terminal box
The oil piping should be in accordance with the diagram of PIPING ROUTE and
PIPING SYSTEM shown in the instruction manual, and based on the number tag
attached to the each pipe.
(1) Remove the blank covers from the separated oil pipes
Oil piping is provided for connecting the oil circuit of various accessories, and
some oil piping is transported separately.
Prior to fitting the oil pipes, remove the blank cover from them. Then remove
old gaskets which used for the blank covers, and clean sufficiently the gasket
groove and the gasket face by means of sandpaper.
After cleaning, be sure to wipe off foreign matter with a dry waste. If the
painted face is found to be spoiled, repaint with rust-proof paint.
(3) Remove the blank cover from the oil pipes on the transformer side.
Remove the blank covers and clean the piping faces. Check that no foreign
matter is allowed to enter inside the transformer tank.
(4) Assembling
Apply a small amount of adhesive to the gasket groove and fit the new gasket.
Tighten the clamp bolts in diagonal order and evenly until the flange faces
match.
(5) The connecting valves are also joined to oil pipes by means of above
procedure.
Flange without a
gasket groove
Fig. 1
Match surface
Fig. 2
Ref.No. : IE-66301
3.12 PIPING AND WIRING Rev. : -
DAIHEN ELECTRIC OF ELECTRIC SYSTEM Date : 25-Dec-03
CO., LTD. Page : 1 / 3
Protective relay
Thermometer
wiring
WRONG GOOD
Fig. 4
Conduit pipe
Insulated wires
Fig. 5
Cotton tube
Ref.No. : IE-62101
3.13 FITTING OF Rev. : -
DAIHEN ELECTRIC BUSHING (GENERAL) Date : 25-Dec-03
CO., LTD. Page : 1 / 1
Make connections to both ends of the bushings in such a manner that strain is
avoided. When heavy busbars are connected to bushings, flexible connections
should be used to prevent damage that might possibly result from expansion and
contraction due to temperature changes. Be sure that all connections are tight to
prevent local heat of the terminal.
When the bushings are installed on the transformer , change a gasket to new one
for the fitting seat. The flange should be fixed uniformly by nuts in such manner
as shown in Fig. 1.
Throughout the work, worker should not use the gloves and tools-monkey
wrench, spanner, etc., unless they are tied to the worker with hempen strings to
prevent them being dropped into the transformer tank.
3' 2
Each pair of stud bolt 1-1', 2-2' and 3-3'
should be tighten with nuts at same time
2' 3 in order to fix the flange uniformly .
1'
Bushing fitting flange
Fig.1
Before fitting the bushing, read the attached instruction manual in which
described bushing handling manner such as unpacking, lifting.
4. Attach a ring screw (M12) to the top of the inner terminal stud, and then
tie the lower end of string to the ring screw as shown in Fig.2 .
5. Pass the lead wire through the bushing while pulling up the string and
bringing down the bushing gradually.
Do not pull the string too strong not to damage the transformer winding
and the lead wire.
6. Match the flange surface of bushing to the fixing part by tightened with
nuts. (See Fig.3)
7. Draw the inner terminal stud from the bushing head, and insert refraining
pin into bushing tube through inner terminal stud as shown in Fig.4 .
8. Fix the inner terminal stud to the outer terminal stud. It is unnecessary to
change the flat gasket to new one (See Fig.4)
9. Fix the top terminal to the outer terminal stud head with bolts as shown in
Fig.5 .
(3) Put the bushing on the seat, and tighten nuts until the flange surface matches to
the seat.
Do not over-tighten.
(4) Connect the copper plate brought out from the transformer winding to the
bushing terminal tightly by using bolts, nuts and washers.
Gasket
Washer
Nut (A) Spring washer
Nut (B) Bolte
Lead terminal
Terminal Plate
Bolte
X X'
Lead
Nut
X - X'
Table B
IEEE C57.106 IEC60422
Voltage class Minimum voltage (kV) Voltage class Minimum voltage (kV)
(kV) at 1 mm gap at 2 mm gap (kV) at 2.5 mm gap
≤ 69 ≥ 25 ≥ 45 < 72.5 > 55
> 69 - < 230 ≥ 30 ≥ 52 72.5 - 170 > 60
> 230 - < 345 ≥ 32 ≥ 55 > 170 - 400 > 60
> 345 ≥ 35 ≥ 60 Note : Test metho d accor ding t o IEC60156
Note : Test metho d accor ding t o ASTM D1816
2) The oil filling apparatus should be clean and free from moisture, care should be taken to
prevent moisture from being introduced into oil though oil line.
3) Do not energize the transformer when vacuuming and filling oil.
4) In the case of transformer with resistor type on-load tap-changer the partition wall of diverter
switch compartment can not withstand full vacuum. Before exhausting air from the transformer,
open the equalizing valve located between the switch compartment and the transformer tank in
order to maintain same pressure as the transformer interior.
5) In the case of transformer with diaphragm type conservator. Before exhausting air from the
transformer, open the equalizing valve located with the conservator in order not to damage the
diaphragm.
6) In the case of transformer with nitrogen seal equipment. Before exhausting air from the
transformer, do not vacuum the nitrogen gas expansion tank, because the tank can not
withstand full vacuum.
3) Start oil filling until the indication of oil level gauge of main conservator indicates the scale 3-4.
Then temporary stop oil filling.
4) Close (15), (20) and stop vacuum pump.
5) Take off the vacuum line from (16) and replace with nitrogen gas line, open (15) and fill
nitrogen gas into the rubber cell until it comes into atmospheric pressure. Take off the nitrogen
gas line from (16).
6) Take off service tool from (13) and (21), Then close (21) by blank cover, Open (20)
7) Open (18) and start oil filling again when oil come out (18), Close (18), Then adjust oil level
until oil level of main conservator indicated follow at oil level-temperature curve, Then close (1)
After residual gas is released, carry out oil level adjustment according to "Oil level-Oil
temperature curve" attached to the transformer.
(7) (3)
Buchholz
(3 (2) Serv ic e too l
Relay
(19)
Q S R E2 Sudden pressure
Radiator
(9) OLTC
(12) (1)
(10)
To Oil Line
No. Description Vacuuming Oil Filling In Service Oil Drianing
close- open- close- open-
1 Drain valve for main tank close close
close close
2 Filler valve for main tank close close close close
3 Connecting valve for main conservator open open open open
open -close -
4 Connecting valve for OLTC conservator open open open
open
5 Drain valve for main conservator close close close close
6 Drain valve (plug) for OLTC conser. close close close close
7 Equalizing valve for OLTC. open open -close close close
8 Connecting valve for oil filter unit close close close close
close- open-
9 Connecting valve for oil filter unit close close close
close
10 Connecting valve for radiator open open open open
11 Gas release valve close close close close
12 Oil sampling valve ( If any) close close close close
To
13 Connecting flange for Air breather open open
Air breathe r
open
Alarm 80 ° C 100 ° C
Trip 90 ° C 110 ° C
stop -°C
2 nd Stage
of Cooli ng
start-up 90 ° C
(NOTE) In the case of over load operation,there is a possibility
of alarm and / or trip contacts operating
1) Construction
Make sure that all parts are located on their proper position, and clamping of
all bolts and nuts is complete.
2) Connection
Make sure that electrical connections are complete and wiring are without
mistake.
3) Cooling equipment
Make sure that all radiator valves are opened, and cooling control device,
cooling fans operates is normal condition.
4) Tap changer
Make sure that the tap-changer operates smoothly, and the tap position is
corresponding to the specified voltage. Control device for OLTC is in normal
condition.
5) Protective relays
Check the contact operation.
6) Indicators
Check the oil level gauges or thermometers indicate the proper position of the
scale.
7) Dehydrating breathers
Check the breathers operation.
8) Check air-release is complete.
9) Check the valves are in the proper position.
10) Grounding system
Make sure that the ground system of the transformer is perfect. Since the
surface of ground pads are painted to prevent it from rusting during transport;
remove the paint for good connection of ground cable.
When above inspections are complete, carry out the field test such as insulation
resistance measuring, ratio test angular displacement measuring. Execution of
applied potential test and temperature rise test is preferable.
In the field test to be conducted during and after field assembly, there are the
following.
a) Insulation resistance measurement
b) Polarity, phase rotation & transformation ratio tests
c) Test of alarm devices and control units
d) High voltage test
Criterion Polarity
H V1 > V2 Subtractive
X1
V1 < V2 Additive
V1
X2
H
V2
H
X2
H X3 H
X1 H3-X3=H2-X2 < H3-X2=H2-X3
H2
X2
H1 H3
X1 X3
H2
X2
H1 H3
X1 X3 H3-X3=H3-X2=H2-X2 < H2-X3
H2
X2
H1 H3
X1 X3
V V
Primary Secondary
V
V
Primary Secondary
Primary Secondary
d) Others
Continuously pressurize the transformer with pressure of 0.3 kg/cm2
(preferably delivered by nitrogen gas) for more than 24 hours, and visually
inspect to see if there are any oil leaks. With reference to drawings, carry
out appearance, dimensional and other checks on the transformer,
Measure insulation oil for its measurable properties such as withstand
voltage, acid value, volume, specific resistance, water content, etc.
It is also recommended to measure the winding resistance.
Ref.No. : IE-72101
Rev. : -
4.3 PAINTING Date : 25-Dec-03
DAIHEN ELECTRIC
CO., LTD. Page : 1 / 4
(I) Clean the whole transformer with use of thinner and rag.
(II) Polish with emerypaper any parts that have been scratched or marked, and
further clean each area lightly with emerypaper so that paint will adhere to
surface.
(III) By a brush, apply under coat (red primer) to the parts where flaws were found.
(IV) Cover up the following parts with paper or vinyl sheet so as to prevent them
from being fooled by paint. (See 2-3)
(V) By means of the spray gun, apply paint to the whole transformer.
(VI) After painting is over, remove the paper of vinyl sheet which is set out in the
above procedure (IV).
Further details of painting, including those parts that should not be painted, and
items that demand special attention when under coating and/or finish coating are
to be done after assembly of transformer is completed at site.
Examples
Part to be
subjected to
foundation coating
Part not to be
subjected to
coating
Brushing Spraying
Paint
(%) (%)
Foundation
Daigo (#200) 5 20-30
coating
Finish Graston 10 15-25
coating Phtharon 10-20 30
d) When dirt, dust, etc. are found on the surface to be painted, apply coating
only after removing.
Ref.No. : X-80-02
4.4 RE-DRYING OF Rev. : -
DAIHEN ELECTRIC THE TRANSFORMER AT JOB SITE Date : 21-Jan-04
CO., LTD. Page : 1 / 7
Re-drying
Drying the transformer at job site is necessary in the following cases :
- When air-tightness is broken during transport or during storage (if nitrogen
gas leakage is found after checking it's pressure, see IE-11101)
1) Principle
Hot oil and vacuum treatment method
- Heating Preliminary vacuum treatment to judge the degree of humidity.
Oil filling under vacuum.
Oil circulation during heating.
- Judgment Judgment of the drying degree from dew point, vapor pressure
and temperature.
2) Heating
2-1 Preparation
- Mount the bushings on the transformer to measure the winding temperature
by resistance method.
- Drain off the residual oil completely by pumping out from the drain valve.
- Open the upper filter valve so as to make the air in tank for draining the
residual oil.
- Fit the transparent tube, as the oil level indicator, between the drain valve
and the flange located on the cover (or the flange on the conservator
connecting pipe). This tube must endure a vacuum and withstand hot oil.
Clamp the flange sufficiently.
- Connect the vacuum pump equipped with a vacuum gauge and a condenser
to the upper part of the transformer (to a flange on the cover, for example).
- After lead wire connections of all bushing are finished, take preliminary
measurements of winding resistance and temperature so as to get a basis of
comparison for the subsequent operations.
- Put the vacuum pump into operation until a vacuum of at least 3 torrs is
obtained in the tank.
- Every hour, measure the volume of water taken from the condenser of the
vacuum pump until not more than 500g of water per hour is drained off.
- Once this value is reached, connect the oil purifier through two pipes
(suction on the lower filter value and delivery on the upper filter valve). Close
the under filter valve, and open the upper filter valve, and start the oil filling
(treated, dried and deserted oil) through the upper filter valve to the
transformer under vacuum.
The oil is then raised to the temperature of 50~60°C approximately. When
the oil level is 15 cm. Below the tank cover stop the oil filling and close upper
and lower filter valves. Continue the operation of the vacuum pump.
Note ;
For measuring temperatures, two alternatives are possible.
- by measuring the resistance variation of one of the windings (by using a
measuring bridge and a D.C. battery)
- by interpolation; the temperature of the core-coil assembly lies between
the oil temperature at suction and delivery.
These temperature measurements should be made as near as possible to
the transformer so as to prevent any error due to heat, losses in the piping.
The oil temperature difference between suction and delivery must not
exceed 5 to 10°C.
Ref.No. : X-80-02
4.4 RE-DRYING OF Rev. : -
DAIHEN ELECTRIC THE TRANSFORMER AT JOB SITE Date : 21-Jan-04
CO., LTD. Page : 3 / 7
The oil temperature should not exceed at 100°C . During the whole
heating process, record the temperature indicated by the thermometer at
every hour.
3) Drying
3-1 Preparation
- Stop the vacuum pump and break the vacuum in the tank
- Close the upper and lower filter valves and remove the oil circulating apparatu
- Completely drain the total quantity of insulating oil through the lower filter
valves, filling the tank with nitrogen gas (Blow the nitrogen gas through the
orifice of the cover) .
4) Judgment
- When the water volume curve reaches below 50g per hour ,stop the vacuum
pump operation.
- Measure the pressure in the tank at every minute and plot the pressure
curve as a function of time. Fig. 1 shows the typical pressure curve.
- Decide the end point of vapor generation from this curve.
Ref.No. : X-80-02
4.4 RE-DRYING OF Rev. : -
DAIHEN ELECTRIC THE TRANSFORMER AT JOB SITE Date : 21-Jan-04
CO., LTD. Page : 4 / 7
5) Oil filling
- Start the vacuum pump operation again, and continue the vacuum pump
operation until the vacuum degree is obtained at least 3 torrs in the tank
(Maintain this vacuum value at least for 1 hour.) .
- Start the oil filling to the transformer through the lower filter valve.
- Bring the oil level as up as possible to the cover. Close the lower filter valve.
- Maintain the vacuum operation for 4 hours.
Installation, Operation and maintenance
SECTION TITLE
1 Transportation 6
1.1 Cautions for Transportation
1.2 Inspection and instruction on
Arrival at site
2 Before Installation 12
2.1 Storage
2.2 Inspection of packages and unpacking
CONTENT
SECTION TITLE
3 Installation 18
3.1 Caution for transformer installation
3.2 Supervisor for work and safety measures
3.3 Preparation of tools, instruments and material
3.4 Flow chart for installation
3.5 Setting of the transformer on a bed
3.6 De-aerated oil filling up to the level above coil
3.7 Fitting of radiators
3.8 Fitting of mounts for bushing
3.9 Fitting of conservator
3.10 Fitting of cooling fan
3.11 Oil piping
3.12 Piping and wiring of electrical system
3.13 Fitting of bushing
3.14 Fitting of condenser type bushing
3.15 Fitting of solid type bushing
3.16 Oil filling and draining process
3.17 Caution for thermometer lead line
To enter in local control cabinet
CONTENT
SECTION TITLE
4 Transportation 67
4.1 Inspection and test after installation
4.2 Field test after installation
4.3 Painting
4.4 Re-drying of the transformer at job site
4.5 Caution when energizing transformer
SECTION 1
TRANSPORTATION
Ref.No. : IE-12101
1.1 CAUTIONS FOR Rev. : C
DAIHEN ELECTRIC TRANSPORTATION Date : 24-Nov-09
CO., LTD. Page : 1 / 3
Use a steel wire having sufficient strength to lift the transformer, etc.
Hoist it by the lifting lugs specified by the transportation drawing.
Transformer
Boat
Transformer
Fig. 2
Pressure gauge
Transformer
Transformer
Fig. 3 Fig. 4
When the transformer is shipped by rail, there is no problem while the train is
running, however attention should be paid to prevent shock during loading and
unloading work. It is undesirable to incline the transformer too sharply. The angle
of slope should be within 10° as illustrated in Fig. 5.
Ref.No. : IE-12101
1.1 CAUTIONS FOR Rev. : C
DAIHEN ELECTRIC TRANSPORTATION Date : 24-Nov-09
CO., LTD. Page : 3 / 3
Transformer
Cargo train
10º
Fig. 5
It is better to install a tachometer on the trailer or the train or attach a shock meter to
the transformer itself. To measure the angle of slops of the transformer, use a plum
bob.
1.2 INSPECTION AND Ref.No. : IE-11101
INSTRUCTIONS
Rev. : D
DAIHEN ELECTRIC Date : 23-Jan-07
CO., LTD. ON ARRIVAL AT SITE Page : 1 / 2
Immediately on arriving at site, the following examination should be made for any
damage sustained in transport, and a check for lost parts.
Remove the protective cover for the compound gauge mounted on the tank, and
open the connecting valve, and check the gas pressure. (After checking the
pressure, close the valve tightly.) Positive indication shows that air and / or water has
not entered into the tank.
If the point read zero, air ingress might happen. At this occasion, measure the
insulation resistance of windings to know the degree of moisture impregnation refer
to the "INSTRUCTIONS FOR INSPECTION AND MAINTENANCE" for the criterion
of moisture impregnation.
Measurement in low humidity atmosphere is preferable to prevent the live parts
from moisture impregnation. If the measured value is lower than the criterion, a
drying treatment will be required.
When a shock recorder is provided, check the records carefully after arrival at
site. If the recorded figures at all axis exceed 3 G, please contact DAIHEN
ELECTRIC CO.,LTD.
(2.2) Rust
When the painting is damaged or the metal parts are rusted, remove the rust
with a sandpaper, and coat with touch-up paint.
Check if the bolts and nuts are loosed. When the bolts fastening the covers or
valves are loosed, make measurement for insulation resistance mentioned above
(1).
Check the impact recorder chart before transferring the transformer and after the
arrival to the destination. If the recorded figure exceeds the following value,
please ask manufacture for further information.
- Vertically : 3 G
- Length-wise : 3 G
- Short-wise : 3 G
(3) Transport at site and unpacking
Refer to IE-12101 and IE-14101 in this instruction manual.
CAUTION :
Before removing a manhole cover, shipping plate, or other device, vent the
transformer to atmospheric pressure. Do not enter the transformer until the gas
space has been flushed with dry air, or a suitable oxygen (not less than 18% of
oxygen in the tank) supply is available for safety working.
SECTION 2
BEFORE INSTALLATION
Ref.No. : IE-21102
Rev. : A
2.1 STORAGE 18-Dec-09
DAIHEN ELECTRIC Date :
CO., LTD. Page : 1 / 1
It is recommended that the transformer will be put into service immediately in its
permanent location. If this is not possible, the following precautions must be taken
to insure the proper storage of the transformer.
(1) The transformer tank has been filled with dry nitrogen gas totally . When
stored for more than 4 months from the date of shipment, the transformer tank
should be filled with insulating oil up to the level lower than the tank cover by
about 25 cm. The gas space between the cover and the oil should be filled with
dry nitrogen gas.
As to the oil filling method , refer to clause IE - 41201 in this instruction . The
gas pressure must be checked periodically .
After fill with insulation oil up to the level lower than the tank cover by about
25 cm,the nitrogen gas will dessolve into insulation oil .
When nitrogen gas pressure deteriorated less than 0.1 kg/cm², the nitrogen
gas shall be supplemented.
The gas filling pressure ,refer as following.
(2) It is recommended that the transformer tank and accessories will be stored
indoor. The accessories would be stored in the boxes to avoid the loss of them.
When the accessories are taken out from the boxes, vinyl sheets covering the
accessories should not be removed.
When stored outdoor, cover totally the tank and accessories with strong water
proof sheets to prevent the water ingress. And lay wooden beams under the
tank and boxes. The tank and accessories should be stored in a dry and clean
location, free form corrosive gases or fumes.
It is necessary to inspect the number of packages and unpack these in the presence
of a representative of your company and our technical staff in the
following manner.
Especially to the packages opened at the time of custom clearance, this should
be carried out most carefully, As to the packages damaged or packages whose
contents are missing, take the necessary action regarding an insurance claim and
take pictures to cover a future claim for insurance money.
(3) Unpacking
When the checking of the number of packages and inspection of the appearance
is over, open the packages. Unpack the wooden boxes carefully by using pincers
so that the contents are not damaged. As far as possible avoid the use of a crow
bar. After unpacking a wooden box, or cardboard box etc. inspect the number
and appearances of the parts according to (1) and (2).
Crow bar
Pincer
Fig. 1
Unpack the package holding bushing carefully according to the following
method, and using care not to damage the contents.
Ceiling
When the package is longer in
Cover the upright position as shown by
the figure at left, do not lay it down
Inner partition in a horizontal position but open it
board in upright position according to the
following.
Cover
Support
- Do not cut
Fig. 3
When the packing is an inclined package as shown above, do not cut off the
supports but draw out the nails by pincer and remove the cover and inner
partition board while keeping it in the inclined position. Do not use a crow bar.
As for the handling of bushing after unpacking, refer to the instructions for
bushing.
Ref.No. : IE-14101
2.2 INSPECTION OF Rev. : -
DAIHEN ELECTRIC PACKAGES AND UNPACKING Date : 20-Jan-04
CO., LTD. Page : 3 / 4
Cover
Fig.4
When the package is a horizontal type as shown above, draw out nails by pincers
and remove the cover and inner partition board. Do not use a crow bar.
No good No good
Good
Ref.No. : IE-14101
2.2 INSPECTION OF Rev. : -
DAIHEN ELECTRIC PACKAGES AND UNPACKING Date : 20-Jan-04
CO., LTD. Page : 4 / 4
In storing the radiators vertically, do not arrange them in more than 3 levels.
Prevent damage by inserting wood blocks in between the radiators. (Fig.6)
Wood
Aligned vertically
Fig.6
SECTION 3
INSTALLATION
Ref.No. : IE-13404
3.1 CAUTIONS FOR Rev. : C
DAIHEN ELECTRIC TRANSFORMER INSTALLATION Date : 20-Jan-04
CO., LTD. Page : 1 / 4
The main tank must be lifted by the same manner as IE-12101. When the transformer
is skidded, moved on rollers or jacked up, take care not to injure the base and not to tip
over the transformer. The transformer is also equipped with jacking bosses . Jacks
should be placed under the jacking bosses . The transformer should never be lifted or
moved with jacking up the radiators or other accessories . When rollers are used , skids
must be placed between the base and the rollers to distribute the stress .
3) Lifting of accessories
Position and direction of the accessories and other parts should be according to the
transformer drawing exactly. Before fitting them, read the instructions completely.
Mishandling will result in damage to the accessories.
b) Apply the liquid gasket (Super Three Bond 1215) to both sides of CN-PG,
smoothly and uniformly.
c) Then, attach the separated parts to their positions with gasket.
d) Start of oil filling should be more than 24 hours after applying the liquid gasket .
e) If temporary fixing of gaskets are needed for vertical or inclined joints , apply the
adhesive ( Cemedine 501 ) around the gasket (refer to Fig.1) Cemedine 501 is
included in our packing .
xxxx
xxxxxxxxx
Flange (mm.) 5 5
5 5
(mm.)
Cemedine 501
( o maker ) Fig. 1
NBR - PG
Flange Fig. 2
Cemedine 501
( o maker )
Ref.No. : IE-13404
3.1 CAUTIONS FOR Rev. : C
DAIHEN ELECTRIC TRANSFORMER INSTALLATION Date : 20-Jan-04
CO., LTD. Page : 3 / 4
5) Fastening of stud-bolts
Each stud-bolt should be screwed rigidly. But in order to avoid the stud-bolt broken,
fasten the stud-bolt under suitable torque as follows by measuring torque wrench or
torque meter.
Lower side
Thermometer
Silicone
Terminal box
Silicone
Ref.No. : IE-15101
3.2 SUPERVISION FOR WORK Rev. : -
DAIHEN ELECTRIC AND SAFETY MEASURES Date : 23-Dec-03
CO., LTD. Page : 1 / 6
Customer like
Our company
your company
Supervisor Engineer, Person-in-charge
Workmen
The leader in turn assigns a specific part of the work to each workman, and
then the working party executes.
First of all, measure the concentration of oxygen inside the tank by means of
the oxygen densitometer, confirm that the oxygen concentration is more than
18% and record the concentration value.
Working lamp
Next, it is necessary to use working lamp having a sufficient intensity of
illumination for safety and to facilitate work inside the tank.
A working lamp with guard is recommended in order to prevent a workman
from receiving an electric shock as well as to protect the bulb from damage
due to unintentional knocks. Oil proof lead wire is recommended.
The lower the voltage of working lamp the better it is, for safety.
Pay attention to the above-mentioned points, and carry out work inside the
transformer tank.
Moreover, prohibit one man work inside the tank, and station a watch at a
place from where he can see workmen.
Finally, consider the fastening of a rope to each workman who enters the
transformer tank.
This can be used in an emergency. The rope would be the means of
rescuing a workman and would be pulled form the outside.
In the case of lifting an article under the horizontal condition or in the case of
fine adjustment in lowering, it is recommended to use a chain block together
with crane car.
Chain
block
In the case of work to be done inside the transformer and work on the
indoor panel, it such work is difficult to do wearing the above-
mentioned clothes, it is in order to put on the cloth working cap and
canvas shoes instead of the helmet and leather laced boots with
permission of customer's person in charge and field work responsible
person of our company.
e.2) A workman should not come within a less distance than show in the
following table from any high-tension part:
Ref.No. : IE-15101
3.2 SUPERVISION FOR WORK
Rev. : -
AND SAFETY MEASURES
DAIHEN ELECTRIC Date : 23-Dec-03
CO., LTD. Page : 6 / 6
The items, specifications and requirements for all tools and materials
required for assembling, inspection and testing of transformer are listed below.
Acceptance criteria
More than 30kV for average value
Standard reference
IEC 60156 (1995)
Acceptance criteria
Limit (Max) 0.20 mg KOH/g
Acceptance criteria
Limit (Min) 25.0 mN/m
Procedure 1 Sampling oil from main tank into water content tester
2 Set timer 10 – 15 Sec for testing
3 Test result will be record by tester ( PPM)
Acceptance criteria
< 35 PMM
Standard reference
ASTM D 1533
Acceptance criteria
< 0.5% @ 25 ºC
1.6 Colour test ( Sampling by Ekarat and submit to EGAT Lavatories) Standard
reference ASTM D 1500
Acceptance criteria
Limit (Max) 2.50
Appendix 1 Page 2/2
Objective Dissolved gas in oil shall be analyzed by automatic dissolved gas in oil analyzer. Oil
shall be collected from filter valve at time of before any tests and after dielectric
tests and temperature rise tests.
Standard reference
ASTM D3612-02 (2009)
Acceptance criteria
No C2H2
Ref.No. : IE-81101
3.3 PREPARATION OF TOOLS, Rev. : A
DAIHEN ELECTRIC INSTRUMENTS AND MATERIALS Date : 21-Dec-03
CO., LTD. Page : 4 / 6
(c) Ammeter
One set each of the following precision
double range ammeter are required for
measurement of exciting current when low
voltage is impressed on the transformer and
for measurement of current of auxiliary
apparatus of the transformer such as cooling
fan, oil pump, etc. If they are equipped on
the transformer.
AC 20/100 mA ...................... 1 set
AC 10/50 A ...................... 1 set
(e) Megger
Megger is used for measurement of
insulation resistance.
Manually operated megger having rating of
about 2000V and 2000MW as appropriate.
(k) Others
Instruments necessary of executing a
temperature rise test, measurement of
dielectric loss tangent (d), noise test
and High voltage test should be
obtained.
(3) Tools
(a) Drum opener
(b) Screw driver for cross recessed head screws
(c) Screw driver for slotted head screws
(d) Scissors
2
(e) Compression pliers (for 2.0, 3.5, 5.5, 8.0mm )
(f) Pliers
2
(g) Wire stripper (for 2.0, 3.5, 5.5, 8.0mm )
(h) Jack with capacity of 10 t
(i) Monkey wrench 6", 8", 10", 12"
(j) Spanner
(k) Pincer.
Ref.No. : IN-10013
3.4 FLOW CHART Rev. : C
DAIHEN ELECTRIC
FOR INSTALLATION Date : 19-Jan-09
CO., LTD. Page : 1 / 1
Yes
Note
No
FIT COMMON PIPES OF RADIATOR Note :
In case of oil filling
VACUUM TREATMENT under vacuum up to level
above coil from factory.
(#1) OIL FILLING UP TO LEVEL ABOVE COIL
(1) On bed
Take care not to incline the transformer too sharply, and prevent it from shocking
during installation work. The foundation should be able to bare the load and the
vibration of an earthquake. Since the center of the transformer is marked ( ↓ ) at the
bottom side, line it up to the center of the specified installation site. To adjust the
perpendicular alignment of transformer, use the markings at the top and bottom of the
transformer and check with a plumb bob, etc. If it is not perpendicular, insert thin iron
plates at an approprite point to adjust it perpendicularly.
Install the transformer with attached anchor bolts at the correct position in the way
previously stated and then fix the anchor bolts with cement. After a few days, when
the cement is sufficiently dry, again clamp the anchor bolts and secure them.
It is necessary to carry out dielectric strength test of insulating oil stored in the
drums before oil filling.
Take samples from each drum and check whether they have specified
dielectric strength. If the oil does not have specified dielectric strength, filter the
entire oil content. Oil filling should be carried out only after its dielectric strength
reaches the specified value.
There are two methods to carry out oil filling. The first method is to fill with oil
through the drain valve while discharging gradually the nitrogen gas filled in the
tank. (see Fig. 2) The nitrogen gas pressure in the transformer tank should be
kept the value of from 0.05 to 0.2 kg/cm2 during oil filling.
The second one is to do oil filling after vacuuming the transformer. (See Fig. 3)
This method is superior to the first one.
approx. 25 cm
Insulating oil
Tank
Coil
Fig. 1
Discharging N2 gas
Compound gauge
Fig. 2
Compound gauge
Transformer
1. Fitting of radiators :
Radiators are shipped separately. Blank covers are attached to the openings
of radiators and radiator valves to prevent moisture. Radiator valve is located on
each radiator connection so that any individual radiator may be removed in time
of necessity without lowering the oil level of the transformer tank.
As each radiator has an oil drain plug and an air relief plug, it is easy to drain
the oil individually.
The radiator withstands the same vacuum (full vacuum) and pressure condition
as the main tank.
Radiators should be handles carefully to prevent bending or puncturing the
panels.
Position number is stamped on the upper header of each radiator and this
should be matched with the position number stamped on the flange on the main
tank side. Fit the radiator according to the following procedures.
(1) Hoist the radiator from the stored position, and pay attention not to
damage other radiators with the hoisting tools.
(2) Remove the blank cover and gasket on the radiator.
(11) Match the radiator valve and the flange surface of the radiator and
clamp them by nuts. (See Fig.2)
(12) Clamp the pair of nuts located diagonally one after another in order to
clamp evenly. (See Fig. 4)
(13) Clamp them tightly until the radiator valve and radiator flange closely
match with each other.
When radiator fitting is over, attach the supports and the fasteners of the
radiator symmetrically as shown in fig. 5 and 6
(1) Fit the supports (E) at the transformer tank wall. (since the radiator in
outer and obstacle for fitting the supports (E) , it is preferable of fitting the
radiator) before.
(2) Put the fasteners (A) and (B) on the upper side of the radiators and put
(C) under the lower side (see Fig.7)
(3) Set jacks under the support (C) and jack up until the radiator may be
vertical (see Fig.6)
(4) Keeping the radiators vertical, joint the supports (E) to the support (C)
and fix with nut.
Clean surface
Fig. 1
Ref.No. : IE-61202
Rev. : A
3.7 FITTING OF RADIATORS
DAIHEN ELECTRIC Date : 24-Dec-03
CO., LTD. Page : 3 / 4
Radiator valve
Fig. 2 Clamp it until there is
no clearance
Stemp of number
Radiator
Fig. 3
Incline and
drain residual
oil.
Fig. 4
Ref.No. : IE-61202
Rev. : A
3.7 FITTING OF RADIATORS
DAIHEN ELECTRIC Date : 24-Dec-03
CO., LTD. Page : 4 / 4
(B)
(A)
Radiator
(C)
(E)
Jack
(C)
Fig. 6
Fig. 5 (A),(C)
(B)
Fig. 7
O S O S
The mechanism of the transformer which may be equipped with the mount is
showing Fig. 1.
Do not give severe shock to the mount since the current transformer is often
located in it.
(1) Check the stamp indicate which phase the mount is fitted to . (See Fig. 2)
(2) Open the CT terminal box attached to the mount and measure the insulation
resistance of CT. It should be 200 MΩ and above.
(3) Remove the top and bottom blank cover of the mount, pass the insulated
wire into CT and check the polarity of CT for all taps . (See Fig. 3) The
polarity is shown in the nameplate .
(4) Carefully remove the blank cover on the mount fitting flange, and also
remove gasket. (On the transformer side).
At this time, pay attention not to let bolts, nuts, tools and dirt fall into the
transformer.
(5) Clean the flange part by sand paper, and apply a small amount of adhesive
to the surface, and fix the new gasket.
(6) Hoist the mount by crane car and pass the lead wire through the central
hole of it. (See Fig. 6)
The lead wire is fixed in the transformer by tape during transport. When
drawing up it, remove the tape and pay attention not to damage the lead
wire and not to apply external force to the transformer coil.
(7) Clamp the bolts and nuts uniformly until the stopper on the flange matches
to the mount flange. (See Fig. 4).
(8) when fitting is over, tie the lead wire at the nut which welded below the
blank cover. (See Fig. 5)
Bushing Stamping
Insulated wire
Mount CT terminal
box terminals
Trans-
former CT
CT G
Fitting flange
Fig. 1 Fig. 2 Fig. 3
Nut
Fig. 4 Fig. 5
Mount
Lead wire
Tank cover
Core
Transformer coil
Fig. 6
Ref.No. : IE-63401
3.9 FITTING OF CONSERVATOR Rev. : C
DAIHEN ELECTRIC Date : 20-Jan-04
CO., LTD. Page : 1 / 3
(1) The rubber cell type conservator is shipped separately and filled with
nitrogen gas to prevent from moisture.
When mounting the conservator on the transformer, it is necessary to take
care of the followings.
Don't heat the conservator by welding or grinding, as the rubber
diaphragm is installed in.
Please refer to the instruction of rubber cell type conservator in detail.
Handhold
Oil level gauge Conservator
Rubber cell
Protective relay
Fig. 1
Float
Conservator Float
Indicator
Lifting lug
Conservator
Mounting bracket
(1) Fitting
The cooling fans attached to the radiator panel The radiators, which provided
with fan fitting supports, are located at the end of each cooling bank.
The fans will be installed to the supports by nuts fastened surely. The fan
motors should be placed so that their cable outlets will be at the bottom of a fan
motor.
(2) Cabling
The terminal boxes, to which fan motor cables are to be connected , are
attached to the fitting supports on the radiator panel . After terminating the
cables as shown in Fig.1, connect them with the terminal blocks with confirming
to match the wire color to the block mark, i.e. The black covered wire is
connected to the blue mark U, the grey to V, the red to W and the black to E .
(3) Checking
After wirings are completed, supply the proper power to the fan motors, and
make sure that the fans rotate in the normal direction and without abnormal
sound.
U V W E Terminal block
Blue Black
Red
Reinforced with vinyle tape
Grey
Rotation
Fan fitting Fan motor
supports Junction box
Radiator panel
Cable
Terminal box
The oil piping should be in accordance with the diagram of PIPING ROUTE and
PIPING SYSTEM shown in the instruction manual, and based on the number tag
attached to the each pipe.
(1) Remove the blank covers from the separated oil pipes
Oil piping is provided for connecting the oil circuit of various accessories, and
some oil piping is transported separately.
Prior to fitting the oil pipes, remove the blank cover from them. Then remove
old gaskets which used for the blank covers, and clean sufficiently the gasket
groove and the gasket face by means of sandpaper.
After cleaning, be sure to wipe off foreign matter with a dry waste. If the
painted face is found to be spoiled, repaint with rust-proof paint.
(3) Remove the blank cover from the oil pipes on the transformer side.
Remove the blank covers and clean the piping faces. Check that no foreign
matter is allowed to enter inside the transformer tank.
(4) Assembling
Apply a small amount of adhesive to the gasket groove and fit the new gasket.
Tighten the clamp bolts in diagonal order and evenly until the flange faces
match.
(5) The connecting valves are also joined to oil pipes by means of above
procedure.
Flange without a
gasket groove
Fig. 1
Match surface
Fig. 2
Ref.No. : IE-66301
3.12 PIPING AND WIRING Rev. : -
DAIHEN ELECTRIC OF ELECTRIC SYSTEM Date : 25-Dec-03
CO., LTD. Page : 1 / 3
Protective relay
Thermometer
wiring
WRONG GOOD
Fig. 4
Conduit pipe
Insulated wires
Fig. 5
Cotton tube
Ref.No. : IE-62101
3.13 FITTING OF Rev. : -
DAIHEN ELECTRIC BUSHING (GENERAL) Date : 25-Dec-03
CO., LTD. Page : 1 / 1
Make connections to both ends of the bushings in such a manner that strain is
avoided. When heavy busbars are connected to bushings, flexible connections
should be used to prevent damage that might possibly result from expansion and
contraction due to temperature changes. Be sure that all connections are tight to
prevent local heat of the terminal.
When the bushings are installed on the transformer , change a gasket to new one
for the fitting seat. The flange should be fixed uniformly by nuts in such manner
as shown in Fig. 1.
Throughout the work, worker should not use the gloves and tools-monkey
wrench, spanner, etc., unless they are tied to the worker with hempen strings to
prevent them being dropped into the transformer tank.
3' 2
Each pair of stud bolt 1-1', 2-2' and 3-3'
should be tighten with nuts at same time
2' 3 in order to fix the flange uniformly .
1'
Bushing fitting flange
Fig.1
Before fitting the bushing, read the attached instruction manual in which
described bushing handling manner such as unpacking, lifting.
4. Attach a ring screw (M12) to the top of the inner terminal stud, and then
tie the lower end of string to the ring screw as shown in Fig.2 .
5. Pass the lead wire through the bushing while pulling up the string and
bringing down the bushing gradually.
Do not pull the string too strong not to damage the transformer winding
and the lead wire.
6. Match the flange surface of bushing to the fixing part by tightened with
nuts. (See Fig.3)
7. Draw the inner terminal stud from the bushing head, and insert refraining
pin into bushing tube through inner terminal stud as shown in Fig.4 .
8. Fix the inner terminal stud to the outer terminal stud. It is unnecessary to
change the flat gasket to new one (See Fig.4)
9. Fix the top terminal to the outer terminal stud head with bolts as shown in
Fig.5 .
(3) Put the bushing on the seat, and tighten nuts until the flange surface matches to
the seat.
Do not over-tighten.
(4) Connect the copper plate brought out from the transformer winding to the
bushing terminal tightly by using bolts, nuts and washers.
Gasket
Washer
Nut (A) Spring washer
Nut (B) Bolte
Lead terminal
Terminal Plate
Bolte
X X'
Lead
Nut
X - X'
Table B
IEEE C57.106 IEC60422
Voltage class Minimum voltage (kV) Voltage class Minimum voltage (kV)
(kV) at 1 mm gap at 2 mm gap (kV) at 2.5 mm gap
≤ 69 ≥ 25 ≥ 45 < 72.5 > 55
> 69 - < 230 ≥ 30 ≥ 52 72.5 - 170 > 60
> 230 - < 345 ≥ 32 ≥ 55 > 170 - 400 > 60
> 345 ≥ 35 ≥ 60 Note : Test metho d accor ding t o IEC60156
Note : Test metho d accor ding t o ASTM D1816
2) The oil filling apparatus should be clean and free from moisture, care should be taken to
prevent moisture from being introduced into oil though oil line.
3) Do not energize the transformer when vacuuming and filling oil.
4) In the case of transformer with resistor type on-load tap-changer the partition wall of diverter
switch compartment can not withstand full vacuum. Before exhausting air from the transformer,
open the equalizing valve located between the switch compartment and the transformer tank in
order to maintain same pressure as the transformer interior.
5) In the case of transformer with diaphragm type conservator. Before exhausting air from the
transformer, open the equalizing valve located with the conservator in order not to damage the
diaphragm.
6) In the case of transformer with nitrogen seal equipment. Before exhausting air from the
transformer, do not vacuum the nitrogen gas expansion tank, because the tank can not
withstand full vacuum.
3) Start oil filling until the indication of oil level gauge of main conservator indicates the scale 3-4.
Then temporary stop oil filling.
4) Close (15), (20) and stop vacuum pump.
5) Take off the vacuum line from (16) and replace with nitrogen gas line, open (15) and fill
nitrogen gas into the rubber cell until it comes into atmospheric pressure. Take off the nitrogen
gas line from (16).
6) Take off service tool from (13) and (21), Then close (21) by blank cover, Open (20)
7) Open (18) and start oil filling again when oil come out (18), Close (18), Then adjust oil level
until oil level of main conservator indicated follow at oil level-temperature curve, Then close (1)
After residual gas is released, carry out oil level adjustment according to "Oil level-Oil
temperature curve" attached to the transformer.
(7) (3)
Buchholz
(3 (2) Serv ic e too l
Relay
(19)
Q S R E2 Sudden pressure
Radiator
(9) OLTC
(12) (1)
(10)
To Oil Line
No. Description Vacuuming Oil Filling In Service Oil Drianing
close- open- close- open-
1 Drain valve for main tank close close
close close
2 Filler valve for main tank close close close close
3 Connecting valve for main conservator open open open open
open -close -
4 Connecting valve for OLTC conservator open open open
open
5 Drain valve for main conservator close close close close
6 Drain valve (plug) for OLTC conser. close close close close
7 Equalizing valve for OLTC. open open -close close close
8 Connecting valve for oil filter unit close close close close
close- open-
9 Connecting valve for oil filter unit close close close
close
10 Connecting valve for radiator open open open open
11 Gas release valve close close close close
12 Oil sampling valve ( If any) close close close close
To
13 Connecting flange for Air breather open open
Air breathe r
open
Alarm 80 ° C 100 ° C
Trip 90 ° C 110 ° C
stop -°C
2 nd Stage
of Cooli ng
start-up 90 ° C
(NOTE) In the case of over load operation,there is a possibility
of alarm and / or trip contacts operating
1) Construction
Make sure that all parts are located on their proper position, and clamping of
all bolts and nuts is complete.
2) Connection
Make sure that electrical connections are complete and wiring are without
mistake.
3) Cooling equipment
Make sure that all radiator valves are opened, and cooling control device,
cooling fans operates is normal condition.
4) Tap changer
Make sure that the tap-changer operates smoothly, and the tap position is
corresponding to the specified voltage. Control device for OLTC is in normal
condition.
5) Protective relays
Check the contact operation.
6) Indicators
Check the oil level gauges or thermometers indicate the proper position of the
scale.
7) Dehydrating breathers
Check the breathers operation.
8) Check air-release is complete.
9) Check the valves are in the proper position.
10) Grounding system
Make sure that the ground system of the transformer is perfect. Since the
surface of ground pads are painted to prevent it from rusting during transport;
remove the paint for good connection of ground cable.
When above inspections are complete, carry out the field test such as insulation
resistance measuring, ratio test angular displacement measuring. Execution of
applied potential test and temperature rise test is preferable.
In the field test to be conducted during and after field assembly, there are the
following.
a) Insulation resistance measurement
b) Polarity, phase rotation & transformation ratio tests
c) Test of alarm devices and control units
d) High voltage test
Criterion Polarity
H V1 > V2 Subtractive
X1
V1 < V2 Additive
V1
X2
H
V2
H
X2
H X3 H
X1 H3-X3=H2-X2 < H3-X2=H2-X3
H2
X2
H1 H3
X1 X3
H2
X2
H1 H3
X1 X3 H3-X3=H3-X2=H2-X2 < H2-X3
H2
X2
H1 H3
X1 X3
V V
Primary Secondary
V
V
Primary Secondary
Primary Secondary
d) Others
Continuously pressurize the transformer with pressure of 0.3 kg/cm2
(preferably delivered by nitrogen gas) for more than 24 hours, and visually
inspect to see if there are any oil leaks. With reference to drawings, carry
out appearance, dimensional and other checks on the transformer,
Measure insulation oil for its measurable properties such as withstand
voltage, acid value, volume, specific resistance, water content, etc.
It is also recommended to measure the winding resistance.
Ref.No. : IE-72101
Rev. : -
4.3 PAINTING Date : 25-Dec-03
DAIHEN ELECTRIC
CO., LTD. Page : 1 / 4
(I) Clean the whole transformer with use of thinner and rag.
(II) Polish with emerypaper any parts that have been scratched or marked, and
further clean each area lightly with emerypaper so that paint will adhere to
surface.
(III) By a brush, apply under coat (red primer) to the parts where flaws were found.
(IV) Cover up the following parts with paper or vinyl sheet so as to prevent them
from being fooled by paint. (See 2-3)
(V) By means of the spray gun, apply paint to the whole transformer.
(VI) After painting is over, remove the paper of vinyl sheet which is set out in the
above procedure (IV).
Further details of painting, including those parts that should not be painted, and
items that demand special attention when under coating and/or finish coating are
to be done after assembly of transformer is completed at site.
Examples
Part to be
subjected to
foundation coating
Part not to be
subjected to
coating
Brushing Spraying
Paint
(%) (%)
Foundation
Daigo (#200) 5 20-30
coating
Finish Graston 10 15-25
coating Phtharon 10-20 30
d) When dirt, dust, etc. are found on the surface to be painted, apply coating
only after removing.
Ref.No. : X-80-02
4.4 RE-DRYING OF Rev. : -
DAIHEN ELECTRIC THE TRANSFORMER AT JOB SITE Date : 21-Jan-04
CO., LTD. Page : 1 / 7
Re-drying
Drying the transformer at job site is necessary in the following cases :
- When air-tightness is broken during transport or during storage (if nitrogen
gas leakage is found after checking it's pressure, see IE-11101)
1) Principle
Hot oil and vacuum treatment method
- Heating Preliminary vacuum treatment to judge the degree of humidity.
Oil filling under vacuum.
Oil circulation during heating.
- Judgment Judgment of the drying degree from dew point, vapor pressure
and temperature.
2) Heating
2-1 Preparation
- Mount the bushings on the transformer to measure the winding temperature
by resistance method.
- Drain off the residual oil completely by pumping out from the drain valve.
- Open the upper filter valve so as to make the air in tank for draining the
residual oil.
- Fit the transparent tube, as the oil level indicator, between the drain valve
and the flange located on the cover (or the flange on the conservator
connecting pipe). This tube must endure a vacuum and withstand hot oil.
Clamp the flange sufficiently.
- Connect the vacuum pump equipped with a vacuum gauge and a condenser
to the upper part of the transformer (to a flange on the cover, for example).
- After lead wire connections of all bushing are finished, take preliminary
measurements of winding resistance and temperature so as to get a basis of
comparison for the subsequent operations.
- Put the vacuum pump into operation until a vacuum of at least 3 torrs is
obtained in the tank.
- Every hour, measure the volume of water taken from the condenser of the
vacuum pump until not more than 500g of water per hour is drained off.
- Once this value is reached, connect the oil purifier through two pipes
(suction on the lower filter value and delivery on the upper filter valve). Close
the under filter valve, and open the upper filter valve, and start the oil filling
(treated, dried and deserted oil) through the upper filter valve to the
transformer under vacuum.
The oil is then raised to the temperature of 50~60°C approximately. When
the oil level is 15 cm. Below the tank cover stop the oil filling and close upper
and lower filter valves. Continue the operation of the vacuum pump.
Note ;
For measuring temperatures, two alternatives are possible.
- by measuring the resistance variation of one of the windings (by using a
measuring bridge and a D.C. battery)
- by interpolation; the temperature of the core-coil assembly lies between
the oil temperature at suction and delivery.
These temperature measurements should be made as near as possible to
the transformer so as to prevent any error due to heat, losses in the piping.
The oil temperature difference between suction and delivery must not
exceed 5 to 10°C.
Ref.No. : X-80-02
4.4 RE-DRYING OF Rev. : -
DAIHEN ELECTRIC THE TRANSFORMER AT JOB SITE Date : 21-Jan-04
CO., LTD. Page : 3 / 7
The oil temperature should not exceed at 100°C . During the whole
heating process, record the temperature indicated by the thermometer at
every hour.
3) Drying
3-1 Preparation
- Stop the vacuum pump and break the vacuum in the tank
- Close the upper and lower filter valves and remove the oil circulating apparatu
- Completely drain the total quantity of insulating oil through the lower filter
valves, filling the tank with nitrogen gas (Blow the nitrogen gas through the
orifice of the cover) .
4) Judgment
- When the water volume curve reaches below 50g per hour ,stop the vacuum
pump operation.
- Measure the pressure in the tank at every minute and plot the pressure
curve as a function of time. Fig. 1 shows the typical pressure curve.
- Decide the end point of vapor generation from this curve.
Ref.No. : X-80-02
4.4 RE-DRYING OF Rev. : -
DAIHEN ELECTRIC THE TRANSFORMER AT JOB SITE Date : 21-Jan-04
CO., LTD. Page : 4 / 7
5) Oil filling
- Start the vacuum pump operation again, and continue the vacuum pump
operation until the vacuum degree is obtained at least 3 torrs in the tank
(Maintain this vacuum value at least for 1 hour.) .
- Start the oil filling to the transformer through the lower filter valve.
- Bring the oil level as up as possible to the cover. Close the lower filter valve.
- Maintain the vacuum operation for 4 hours.
Installation, Operation and maintenance
11/6.9 kV, ONAN 8 MVA, Oil Immersed, Conservator tank with rubber bag
CONTENT
PAGE
1 Introduction 1/1
2 Handling and Installation 1/2-2/2
3 Commissioning and Testing 1/1
4 Inspection after Energizing 1/1
5 Operating Instruction 1/1
6 Inspection and Maintenance 1/1
7 Safety and Environment 1/1
8 Information on Nameplate 1/1
9 Inspection and Maintenance of Warranty 1/2-2/2
10 Services Centers 1/1
EKARAT ENGINEERING PUBLIC COMPANY LIMITED SET PAGE
Operating and Maintenance Instruction Manual for Oil-immersed A 1/1
Transformer
DOCUMENT NO. EFFECTIVE DATE CHAPTER REV.
EN-S-004 01 / 10 / 03 1 0
1. INTRODUCTION
1.1 General
This instruction manual covers oil – immersed transformers (hereinafter called the transformer) suitable
for outdoor and/or indoor installation. The transformers are gas cushions sealed tank type } hermetically
completely filled with oil type or conservator type. The transformers shall be operated and serviced only
by competent personnel , having experienced good safety practices. This instruction manual is
prepared for such personnel and is not intended as a substitute for adequate training and experience in
the use of transformers. The transformer outline drawing shows details and location of nameplate ,
equipment and accessories.
1.2 Caution
Please read this instruction manual carefully before attempting to handle , install , use or make services
to the transformers. In case that assistance required or having any questions , please contacts your local
Ekarat Sales and Services Officers , which are located throughout Thailand.
EKARAT ENGINEERING PUBLIC COMPANY LIMITED SET PAGE
Operating and Maintenance Instruction Manual for Oil-immersed A 1/2
Transformer
DOCUMENT NO. EFFECTIVE DATE CHAPTER REV.
EN-S-004 01 / 10 / 03 2 0
2.2 Lifting
Lifting lugs or eyes are on the transformer tank cover and attached to the tank wall for the small and
big transformer respectively.
In case of large transformers , the lifting eyes on tank cover are used for lifting the internal parts
during untanking or tanking only , untanking weight for selection of proper hoist or chain hoist can be
obtained from lifting weight as stated in nameplate. The lifting lugs and lifting eyes are shown on
transformer outline drawing for proper lifting position.
2.3 Jacking
Refer to the transformer outline drawing for jacking area on the transformer tank. Only this area can
be used for this purpose only.
2.4 Storage
Transformers , parts and accessories should be kept indoor in clean and dry area.
2.5 Installation
The correct and appropriate installation is one of the safety factor of the operators , asset and lifetime
of transformers.
2.5.1 Transformers should be located at the appropriate location , comfortably moving in and out ,
inspecting and maintaining both outdoor yard/pole mounted and indoor room.
EKARAT ENGINEERING PUBLIC COMPANY LIMITED SET PAGE
Operating and Maintenance Instruction Manual for Oil-immersed A 2/2
Transformer
DOCUMENT NO. EFFECTIVE DATE CHAPTER REV.
EN-S-004 01 / 10 / 03 2 0
2.5.2 Provision of good ventilation of transformers should be made to ensure that the transformers is
sufficient ventilated during operating.
2.5.3 In case of indoor installation , these should be at least 100 cm and 60 cm space between
transformer and wall , and transformer and ceiling respectively. Also at least 30 cm from
inflammable material , clearance shall be provided.
2.5.4 Outdoor installation of transformers should be fenced at least 100 cm space between wall or
fence and live part of high voltage , at least 180 cm .
2.5.6 Level of floor or platform must be even and strong enough for each transformers.
EKARAT ENGINEERING PUBLIC COMPANY LIMITED SET PAGE
Operating and Maintenance Instruction Manual for Oil-immersed A 1/1
Transformer
DOCUMENT NO. EFFECTIVE DATE CHAPTER REV.
EN-S-004 01 / 10 / 03 3 0
After the transformers are energized , do the following inspection to ensure proper function of the
transformers.
4.1 Any vibration during operating
4.2 Measuring the output voltage whether it is correct according to selected tap position
EKARAT ENGINEERING PUBLIC COMPANY LIMITED SET PAGE
Operating and Maintenance Instruction Manual for Oil-immersed A 1/1
Transformer
DOCUMENT NO. EFFECTIVE DATE CHAPTER REV.
EN-S-004 01 / 10 / 03 5 0
5. OPERATING INSTRUCTION
The general operating conditions are applicable according to IEC 354/1991 or equivalent standards
unless deviating customer specifications have been agreed upon. The following are general operating
guideline.
5.1 Ambient temperature should not exceed 40° c
5.2 When electrical connections are made , all mounting or connecting must be done according to the
correct procedure.
5.3 Electrical protection equipment must be properly selected to match the transformers.
5.4 Operating voltage should not exceed ±5 % at on load and should not exceed ±10% at no load.
5.5 Normally Ekarat transformers are designed for oprating at maximum 3300 feet above sea level ,
any installation above 3300 feet will affect to the capabilityof transformer and oil temperature.
5.6 Frequency range of source voltage should be as that of stated on the nameplate.
Please contact Ekarat’s representative if more explanation is needed.
EKARAT ENGINEERING PUBLIC COMPANY LIMITED SET PAGE
Operating and Maintenance Instruction Manual for Oil-immersed A 1/1
Transformer
DOCUMENT NO. EFFECTIVE DATE CHAPTER REV.
EN-S-004 01 / 10 / 03 6 0
8. INFORMATION ON NAMEPLATE
Nameplate which gives the basic information for reference is supplied and attached on one side of every
transformer.
Information shown on Nameplate :
8.1 kVA : Power output in kilovolt – ampere of transformers under the specified
condition of operating.
8.2 Phase : The number of phase
8.3 Frequency : Frequency of the system on which transformer is connected
8.4 Type : Type of cooling system.
8.5 Class : Class of insulation, which used for production.
8.6 Pri. Volt and Amp./ : Rated line voltage and rated line current of primary and secondary of
transformers.
Sec. Volt and Amp.
8.7 Percent Imp : Impedance voltage in percentage.
8.8 Oil Temp. Rise : AN Top oil temperature rise above ambient temperature at rated kVA
8.9 Oil Qty (L) : The estimated oil volume in liter.
8.10 Drain Oil Qty (L) : This information is for “hermetically sealed” (completely oil filled)
transformer, and used by manufacturer only.
8.11 Total Wt. (Kg) : Total weight of whole transformer.
8.12 Lifting Wt. (Kg) : The weight of total internal parts for untanking.
8.13 Voltage and Tap : The relevant primary voltage at any Tap position with the condition of
position constant secondary voltage.
8.14 Connection : Position of terminal of primary and secondary side.
Diagrams
8.15 Vector Diagram : The phase rotation and phase angle shift between the high voltage and low
voltage
8.16 Item Code : Manufacturer’s particular design reference.
8.17 Serial Number : Identification number of each specific transformer. Please refer to this
serial number.
EKARAT ENGINEERING PUBLIC COMPANY LIMITED SET PAGE
Operating and Maintenance Instruction Manual for Oil-immersed A 1/2
Transformer
DOCUMENT NO. EFFECTIVE DATE CHAPTER REV.
EN-S-004 01 / 03 / 04 9 0
TYPE OF TRANSFORMER
INSPECTION ITEM Nitrogen Hermetically
Conservator
gas scaled sealed
1.Test of Moisture Content, Acid Number, Power Factor 9 9 9
2.DGA Test 9 9 9
3.Insulation test by Polarize index 9 9 9
REMARK : - If the oil test results are not according to standard, filtering or changing the oil is a MUST
- Our sales person and service can provide the cost of inspection & maintenance for
transformer put in service 3 years and more.
EKARAT ENGINEERING PUBLIC COMPANY LIMITED SET PAGE
Operating and Maintenance Instruction Manual for Oil-immersed A 1/1
Transformer
DOCUMENT NO. EFFECTIVE DATE CHAPTER REV.
EN-S-004 01 / 03 / 04 10 0
สารบัญ
หน้ า
1. บทนํา 1/1
2. การบรรจุหบี ห่ อและการจัดเก็บ 1/1
3. การเคลื่อนย้ ายและการขนส่ ง 1/1
4. การติดตัง้ 1/1
5. การจ่ ายไฟ 1/1
6. ข้ อแนะนําในการใช้ งานและการบํารุ งรั กษา 1/1
7. การเกิดความเสียหาย การรื อ้ และการซ่ อมแซม 1/1
8. วงจรควบคุมอุณหภูมแิ ละอุปกรณ์ ตรวจจับอุณหภูมิ 1/1
9. ระยะปลอดภัยสําหรั บ ROUND BUSBARS ด้ านแรงสูง 1/1
10. ตารางข้ อมูลต่ างๆ 1/1
11. ข้ อควรระวังในการต่ อสายแรงสูง 1/1
12. การตรวจสอบหม้ อแปลงไฟฟ้ าในระยะประกัน 1/3-3/3
บริษัท เอกรัฐวิศวกรรม จํากัด (มหาชน) ชุด หน้ าที่
คูม่ ือสนับสนุน C 1/1
เรื่ อง การใช้ งานและบํารุงรักษาหม้ อแปลง รหัสเอกสาร เริ่ มใช้ งาน บทที่ แก้ ไขครัง้ ที่
ไฟฟ้าชนิดแห้ งแบบ Cast Resin EN-S-003 01/08/57 1 0
1.บทนํา
หม้ อแปลง CAST RESIN ของบริษัท เอกรัฐวิศวกรรม จํากัด (มหาชน) เป็ นหม้ อแปลงไฟฟ้าชนิดแห้ ง(DRY TYPE) ผลิต
โดยสอดคล้ องกับมาตรฐาน IEC 60076-11 เมื่อเปรี ยบเทียบกับหม้ อแปลงไฟฟ้าชนิดแห้ งโดยทัว่ ไป หม้ อแปลง CAST
RESIN จะมีความแตกต่างที่ขดลวดอลูมิเนียมด้ านแรงสูง จะถูกห่อหุ้มด้ วย RESIN โดยผ่านกระบวนการหล่อในสภาพ
สูญญากาศที่ไม่มีฟองอากาศหลงเหลืออยู่ ทําให้ มนั่ ใจได้ วา่ มีโอกาสเกิด PARTIAL DISCHARGE ได้ น้อยมาก(สามารถ
ทนแรงดันฟ้าผ่าและแรงดันจากการปลด / สับสวิทซ์ได้ ดี) ในขณะเดียวกันทางด้ านขดลวดแรงตํ่าจะใช้ แผ่นอลูมิเนียม
(ALUMINIUM FOIL) พันทับไปกับฉนวน และเคลือบผิวโดยการจุ่ม RESIN (EPOXY RESIN-IMPREGNATED
INSULATION) ลักษณะการออกแบบเช่นนี ้ ทําให้ ทนต่อการลัดวงจรได้ ดีและมีความแข็งแรงทางฉนวนสูงสุด นอกจากนี ้
หม้ อแปลง CAST RESIN ไม่มีตวั ถังเหมือนหม้ อแปลงชนิดนํ ้ามัน จึงสามารถตรวจสอบรายละเอียดต่างๆ ของตัวหม้ อ
แปลงได้ อย่างสะดวกในแง่ของการบํารุงรักษา นอกจากนี ้ข้ อมูลทางเทคนิคอื่นๆ ได้ ถกู จัดเตรี ยมไว้ ให้ แล้ ว ได้ แก่
- วงจรการต่อสายแรงสูง และเนมเพลท (ติดที่ตวั หม้ อแปลง)
- แบบขนาดมิตขิ องตัวหม้ อแปลง
- แบบวงจรคอนโทรล
- ผลการทดสอบ (ถ้ าต้ องการ)
เพื่อให้ เกิดความปลอดภัยทังทรั้ พย์สนิ และตัวบุคคล ดังนัน้ ผู้ปฏิบตั งิ านควรอ่านคูม่ ือเล่มนี ้อย่างละเอียดก่อนที่จะ
ปฏิบตั จิ ริ ง หากมีข้อสงสัยหรื อต้ องการรายละเอียดเพิ่มเติม สามารถติดต่อได้ ที่ศนู ย์บริการของ บริษัท เอกรัฐวิศวกรรม
จํากัด (มหาชน) ที่มีอยูท่ วั่ ประเทศ
บริษัท เอกรัฐวิศวกรรม จํากัด (มหาชน) ชุด หน้ าที่
คูม่ ือสนับสนุน C 1/1
เรื่ อง การใช้ งานและบํารุงรักษาหม้ อแปลง รหัสเอกสาร เริ่ มใช้ งาน บทที่ แก้ ไขครัง้ ที่
ไฟฟ้าชนิดแห้ งแบบ Cast Resin EN-S-003 01/08/57 2 0
2. การบรรจุหบี ห่ อและการจัดเก็บ
ดังที่ได้ กล่าวมาแล้ วว่าหม้ อแปลง CAST RESIN เป็ นหม้ อแปลงที่มีความทนทานต่อสภาพแวดล้ อมต่าง ๆ ได้ ดี ใน
การขนส่งหรื อจัดเก็บในระยะเวลาสัน้ ๆ ไม่มีความจําเป็ นต้ องป้องกันเป็ นพิเศษแต่อย่างใด เพียงแต่ใช้ ผ้าใบหรื อแผ่น
พลาสติกคลุมอย่างมิดชิดก็เป็ นการเพียงพอแล้ ว
กรณีมีการจัดเก็บหม้ อแปลงเป็ นเวลานาน ให้ ระมัดระวังเรื่ องฝุ่ น,สิ่งสกปรกและความเปี ยกชื ้น ควรจัดเก็บไว้ ใน
ที่มีอากาศถ่ายเทสะดวก
บริษัท เอกรัฐวิศวกรรม จํากัด (มหาชน) ชุด หน้ าที่
คูม่ ือสนับสนุน C 1/1
เรื่ อง การใช้ งานและบํารุงรักษาหม้ อแปลง รหัสเอกสาร เริ่ มใช้ งาน บทที่ แก้ ไขครัง้ ที่
ไฟฟ้าชนิดแห้ งแบบ Cast Resin EN-S-003 01/08/57 3 0
3. การเคลื่อนย้ ายและการขนส่ ง
3.1 การเคลื่อนย้ าย
3.1.1 การยกโดยใช้ เครน ต้ องยกที่หหู ิ ้วเท่านัน้ สําหรับวิธีการและอุปกรณ์ที่ควรใช้ ได้ ให้ คําแนะนําติดไว้ ที่หม้ อ
แปลง ผู้ใช้ ควรปฎิบตั ติ ามคําแนะนําเพื่อเป็ นการป้องกันความเสียหายต่อโครงสร้ างภายในหม้ อแปลง
3.1.2 การลาก ในกรณีจําเป็ นต้ องลากหม้ อแปลงเข้ าสถานที่ตดิ ตัง้ ให้ ใช้ รูเจาะที่จดั ทําไว้ ที่ฐานหม้ อแปลง และห้ าม
ไม่ให้ โยกหม้ อแปลงมิเช่นนันอาจจะเกิ
้ ดความเสียหายได้
3.2 การขนส่ง เพื่อหลีกเลีย่ งความเสียหายระหว่างการขนส่ง ควรมีการป้องกันหม้ อแปลงลื่นไถลหรื อล้ ม ถ้ าเป็ นไป
ได้ ควรถอดล้ อออกเสียก่อน
บริษัท เอกรัฐวิศวกรรม จํากัด (มหาชน) ชุด หน้ าที่
คูม่ ือสนับสนุน C 1/1
เรื่ อง การใช้ งานและบํารุงรักษาหม้ อแปลง รหัสเอกสาร เริ่มใช้ งาน บทที่ แก้ ไขครัง้ ที่
ไฟฟ้าชนิดแห้ งแบบ Cast Resin EN-S-003 01/08/57 4 0
4. การติดตัง้
4.1 หลังนําวัสดุที่ห่อหุ้มออกแล้ ว ให้ ทําความสะอาดอย่างระมัดระวังโดยตรวจดูร่องระบายอากาศต่างๆ ภายในขดลวด
หรื อระหว่างขดลวด เพื่อมิให้ มีวสั ดุแปลกปลอมเข้ าไปขวางทางระบายความร้ อนได้
4.2 ตรวจสอบสถานที่ตดิ ตัง้ ต้ องมีความมัน่ คงแข็งแรง รับนํ ้าหนักหม้ อแปลงได้ มีการระบายอากาศที่ดี โดยปกติ
ขณะที่หม้ อแปลงทํางาน อุณหภูมิของหม้ อแปลงจะสูงกว่าอากาศโดยรอบประมาณ 50-80 องศาเซลเซียส ขึ ้นอยูก่ บั
การจ่ายโหลดมากหรื อน้ อย ดังนันการระบายอากาศร้
้ อนที่ตวั หม้ อแปลงให้ เร็วด้ วยการแทนที่ด้วยอากาศที่เย็นกว่า
จึงเป็ นสิง่ จําเป็ น สําหรับการติดตังหม้
้ อแปลงภายในห้ องหม้ อแปลงหากการระบายอากาศไม่ดี เพียงพอจะทําให้
อุณหภูมิของหม้ อแปลงสูงเกินไป และจะทําให้ อายุการใช้ งานของหม้ อแปลงสันลงกว่ ้ าเวลาอันควรจึงมีข้อแนะนํา
ดังนี ้
4.2.1 ในห้ องติดตังหม้ ้ อแปลง ควรจัดให้ มีช่องทางเข้ าของอากาศเย็นและช่องทางออกของอากาศร้ อนในทิศทาง
ตรงกันข้ าม โดยช่องอากาศเย็นควรจัดให้ เข้ าทางด้ านล่างของตัวหม้ อแปลง ส่วนช่องอากาศร้ อน ควรจัดให้
อยูด่ ้ านบนเหนือตัวหม้ อแปลงหรื อห้ องหม้ อแปลง
4.2.2 โดยทัว่ ไปพื ้นที่ของช่องระบายอากาศต้ องไม่น้อยกว่า 10 ตร.ซม./kVAและต้ องไม่เล็กกว่า 500 ตร.ซม.
ตําแหน่งติดตังหม้ ้ อแปลงควรให้ หา่ งจากฝาผนังหรื อหม้ อแปลงเครื่ องอื่นๆไม่ น้ อยกว่า 50 ซม.
4.2.3 กรณีที่การระบายความร้ อนไม่ดีพอ จําเป็ นต้ องติดตังพั ้ ดลมดูดอากาศเข้ า-ออกเพิ่มเติมที่ผนังห้ อง โดยมี
เงื่อนไขว่า ลมดูดอากาศเข้ าห้ องหม้ อแปลง (INLET AIR) ต้ องมีอณ ุ หภูมิไม่เกิน 40 องศาเซลเซียส โดยติดตัง้
เทอร์ โมมิเตอร์ ตรวจวัด
4.3 อุปกรณ์หรื อชิ ้นส่วนต่างๆ ของหม้ อแปลงให้ ประกอบอย่างระมัดระวัง นัต โบท์ลต่างๆ เมื่อขันแน่นแล้ ว ให้ ใช้ ปากกา
เมจิกชนิด PERMANENTทําเครื่ องหมายไว้ ให้ ชดั เจน เพื่อป้องกันการลืมขัน (ในการขัน นัต โบล์ทอย่าขันแน่น
จนเกินไป เพราะอาจจะทําให้ เนื ้อ RESIN บริเวณขัวขดลวดแรงสู
้ งแตกหักเสียหายได้ และควรขันด้ วยประแจ
ทอร์ คตามค่าที่กําหนดไว้ ในตารางด้ านหลัง
4.4 กรณีที่มีการสัง่ ซื ้อตู้ HOUSING ให้ ประกอบตู้และติดตังพั
้ ดลมระบายความร้ อนให้ ถกู ต้ องตามแบบสัง่ งานที่
กําหนด
บริษัท เอกรัฐวิศวกรรม จํากัด (มหาชน) ชุด หน้ าที่
คูม่ ือสนับสนุน C 1/2
เรื่ อง การใช้ งานและบํารุงรักษาหม้ อแปลง รหัสเอกสาร เริ่ มใช้ งาน บทที่ แก้ ไขครัง้ ที่
ไฟฟ้าชนิดแห้ งแบบ Cast Resin EN-S-003 01/08/57 5 0
5. การจ่ ายไฟ
ก่อนมีการจ่ายไฟควรมีการตรวจสอบครัง้ สุดท้ าย โดยดําเนินการตามขันตอนต่ ้ อไปนี ้
5.1 ตรวจสอบการติดตังตามรายละเอี
้ ยดในข้ อ 4
5.2 ตรวจสอบ สายต่อลงดิน ของหม้ อแปลง
5.3 ตรวจสอบวัสดุแปลกปลอม ที่อาจตกหล่นในหม้ อแปลงและทําความสะอาดถ้ าจําเป็ น
5.4 ตรวจสอบสายตรวจจับสัญญาณอุณหภูมิ อยูใ่ นตําแหน่งถูกต้ องหรื อไม่ (ฝังในขดลวดแรงตํ่าทัง้ 3 เฟส กับบาร์
อลูมิเนียม) และยึดแน่นพอดีไม่หลวมคลอน การเดินสายสัญญาณจากขดลวดแรงตํ่ามายัง TERMINAL BLOCK
ต้ องเรี ยบร้ อยและขันแน่น
5.5 ตรวจสอบการทํางานของวงจรคอนโทรลและทิศทางของพัดลม ถูกต้ องหรื อไม่
5.6 การต่อสายเคเบิลแรงสูง จุดต่อ ลําดับเฟสและการต่อแท็ปถูกต้ องหรื อไม่ ดูรายละเอียดจากเนมเพลท
5.7 นัต โบล์ท ที่ขวแท็
ั ้ ปหรื อที่ขวด้
ั ้ านขดลวดแรงสูงและแรงตํ่าทังหมดจะต้
้ องขันซํ ้า ด้ วยประแจทอร์ ค ตามค่าใน
ตาราง TORQUE VALUES ด้ านหลัง
5.8 อุปกรณ์ตา่ งๆ เช่น บาร์ แรงตํ่า กับดักฟ้าผ่า สายเคเบิล โครงเหล็กยึดอุปกรณ์ สายไฟ และชิ ้นส่วนที่เป็ นสือ่ ทาง
ไฟฟ้า ที่ไม่ใช่ชิ ้นส่วนของตัวหม้ อแปลงที่เตรี ยมมาให้ จะต้ องติดตังให้
้ มีระยะห่างดังตาราง A และ B
บริษัท เอกรัฐวิศวกรรม จํากัด (มหาชน) ชุด หน้ าที่
คูม่ ือสนับสนุน C 2/2
เรื่ อง การใช้ งานและบํารุงรักษาหม้ อแปลง รหัสเอกสาร เริ่ มใช้ งาน บทที่ แก้ ไขครัง้ ที่
ไฟฟ้าชนิดแห้ งแบบ Cast Resin EN-S-003 01/08/57 5 0
หมายเหตุ ถึงแม้ วา่ หม้ อแปลง CAST RESIN จะถูกหุ้มด้ วย RESIN อย่างมิดชิด แต่ไม่ได้ หมายความว่า
สามารถสัมผัสหรื อจับต้ องได้ นัน่ คือการปฏิบตั งิ านใดๆเกี่ยวกับ หม้ อแปลงจะต้ องดับไฟ
และลัดวงจรลงดินก่ อนเสมอ
บริษัท เอกรัฐวิศวกรรม จํากัด (มหาชน) ชุด หน้ าที่
คูม่ ือสนับสนุน C 1/1
เรื่ อง การใช้ งานและบํารุงรักษาหม้ อแปลง รหัสเอกสาร เริ่ มใช้ งาน บทที่ แก้ ไขครัง้ ที่
ไฟฟ้าชนิดแห้ งแบบ Cast Resin EN-S-003 01/08/57 6 0
PRINCIPLE SKETCH
Replace Transformer
Turn Ratio Test
Polarize Index
อายุ การใชงาน
Ground Test
Tightening
้
Cleaning
Control
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
ทํา ตามวาระ ควรทํา เพิ่มเติม ควรทํา เพิ่มเติมหากผลการทดสอบมีปัญหาหรือตามผู้ให้ บริการแนะนํา
หมายเหตุ
การเปลี่ยนยางรอง Coil ของหม ้อแปลง Cast Resin มีขีดจํากัดหลายอย่างในทางปฏิบ ัตห
ิ ลายอย่าง
1. อุป กรณประกอบของหม ้อแปลง เช ่น พัดลมระบายความร ้อน ต ้องถอดก่อนการเปลี่ยนยางรอง Coil
2. การจับ ยึด Coil ขณะที่เปลี่ยนยางรอง Coil ที่อาจทําให ้ Coil deform ไปจากเดิม และระยะทางฉนวนไฟฟ้าไม่เพียงพอ
3. เครื่องทดสอบฉนวนทางด ้านแรงสูง ทางบริษัท ไม่มี (Apply Voltage Test) ในการทดสอบที่หน ้างาน
Installation, Operation and maintenance
CHAPTER 2
TRANSPORT AND LANDING : Neutral Grounding Resistors packed for domestic shipments by carton
box, for overseas shipments by wooden materials. NTD transported by forklift or winch. On the NTD
specially manufactured inox lifting ring for safe transportation. We use these inox rings for landing and
carrying operation by winch. With the help of fork lift , fork should be locate not to damage
CHAPTER 3
INSTALLATION AND MAINTENANCE
The most reliable mounting is to connect the neutral point of desired restriction O.G. coil of phase-earth
short circuit current with the O.G. cable (min. 70mm2 cross-section copper wire) to the access of NER
(neutral grounding resistor). Installation of NER is completed by contacting of the outer casing of NER
Merkez / Head Office: 1. O.S.B. 1 .Yol. No : 16 54580 ARİFİYE / SAKARYA / TURKEY Tel: 90.264.275 55 40 Fax: 90.264.275 12 76
Şube / Branch Office: Perpa-Elektrokent K: 5 No: 444 ISTANBUL / TURKEY Tel: 90.212.210 68 54 Fax: 90.212.221 10 25
www.hilkar.com [email protected]
CHAPTER 4
Spare Part: Normal operating conditions does not need any spare parts. But you can apply to our
company for any repair or spare part needs.
Safety rules in work time : All medium voltage safety rules applies as per IEC and IEEE.
Preparation for Commissioning: Neutral Grounding Resistor must be installed on a level concrete
floor by anchorage bolts and nuts before comissioning.
Merkez / Head Office: 1. O.S.B. 1 .Yol. No : 16 54580 ARİFİYE / SAKARYA / TURKEY Tel: 90.264.275 55 40 Fax: 90.264.275 12 76
Şube / Branch Office: Perpa-Elektrokent K: 5 No: 444 ISTANBUL / TURKEY Tel: 90.212.210 68 54 Fax: 90.212.221 10 25
www.hilkar.com [email protected]