The document provides a quote for substructure materials for a construction project. It lists various materials needed like blocks, cement, sand, rebar, and their quantities and prices. It also provides payment terms of 50% down payment and 50% upon completion of work.

Uploaded by

Fred Kazimilo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views2 pages

MR Zulu

The document provides a quote for substructure materials for a construction project. It lists various materials needed like blocks, cement, sand, rebar, and their quantities and prices. It also provides payment terms of 50% down payment and 50% upon completion of work.

Uploaded by

Fred Kazimilo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

FREX BUILDERS LTD Client : Mr S.

Zulu
Situated :off Leonard hill road plot 48/48 Attention: by F.Kazimilo
bauleni lusaka
Contact :+260977654606/0956874838
Email :[email protected] DATE: 31/07/20

SUBSTRUCTURE MATERIALS (ONLY )

DESCRIPTION QTY UNIT PRICE AMOUNT


Blocks 8” ( 400*200*200mm) 2500 No. K 4,60 K 11,500,00
Cement 556 50 Kgs Bag K 125,00 K 69,000,00
Building sand 02 40 Tones K 2,000,00 K 4,000,00
Quarry dust 04 80 Tones K 2,500,00 K 10,000.00
Crush stones 20mm 03 60Tones K 2,500,00 K 7,500,00
Anti-Termite 02 5Liters K 605,00 K 1,210,00
Rebar Y12 (12mm) 115 Pieces 12m K 115,00 K 13,225,00
Rebar Y 16 (16 mm) 45 Pieces 12m K 180,00 K 8,100,00
Rebar Y20 ( 20mm) 06 12m K 450,00 K 2,700,00
Rebar Y 8 (8mm) 95 Pieces 6m K 60,00 K 6,175,00
Corn Force wire Heavy duty (257) 03 Roll Meters 50m K 1,600,00 K 4,800,00
Brick force wire (6”) 4 Batches Batches K 180,00 K 720,00
Wire Nails (4”) 10 1Kgs K 30,00 K 300,00
Concrete Nails (4”) 10 1Kgs K 50,00 K 500,00
Wire Nails (3”) 10 1Kgs K 30,00 K 300,00
Polythene Sheets heavy duty 03 Rolls Meters 100m K 275,00 K 825,00
Laterite/Glavel 06 20 Tones K 1,200,00 K 7,200,00
Timbers 50*50mm 30 Pieces 5 Meters K 65,00 K 1,950,00
Fascia Boards 200*25mm 30 Pieces 5 Meters K 180,00 K 5,400,00
Tying Wire 02 batches Kgs 25 K 410,00 K 820,00
Premix concrete slab {SINOMA} 40.00 /cubic meter K1,200,00 K 48.000,00

BANK NAME: FIRST NATIONAL BANK VAT 16% K


A/C NAME : FRED KAZIMILO LABOUR COST 35% K 71,478,00
A/C NUMBER: 62745941379 SUBTOTAL K 204,225,00
BRANCH CODE: 005
TOTAL K 276,210,00
Terms of payments 50 % down payment. 50% upon completion of the work. Excellence