Survey Report
Survey Report
BY
2024BC157801
APRIL 2024
ENGINEERING SURVEY
Introduction to Surveying
Surveying is the art, science and technology of examining and recording the area and features of a piece
of land determining the terrestrial or three-dimensional position of points, distance and angles between
them. It is done in order to achieve the following objectives:
• To determine measure and represent land three-dimensional objects in a map, plan or a deed plan
• To assemble and interpret land and geographical information
LEVELLING SURVEY
Introduction
Levelling is a method used to measure the elevation difference between two or more points. In this
practical report, we focus on one of the levelling techniques known as the fly level observation or the rise
and fall method.
Objective
Conduct a close fly-levelling survey (vertical control) from a benchmark (TBM) to the site location.
Guidelines
1. The following guidelines will help a surveyor reduce errors resulting from any line of sight in his
or her work:
2. Backsight and foresight should be equal distance of 4M.
3. The length of sight should be kept less than 100M
Instruments used
Digital level: An optical device used to establish or verify points in the same horizontal plane. It measures
height differences and transfers, measures, and sets heights.
Staff: A graded hardwood or aluminum rod used with a leveling device to determine height differences or
the heights of points above a vertical datum.
Procedure
Hold the staff vertically on the datum and take a reading. This reading will be the backsight because it is
the first staff reading after setting the instrument.
Move the staff to point A and take a reading. This will be the intermediate sight.
Move the staff to the next point and take a reading. This will also be the intermediate sight.
Move the staff to point D and take a reading. This will be a foresight because after this point the level will
be moved.
The distance between the stations should be measured and recorded into the field book as well.
Set up the level at position 2 and level the staff at point D, then take a reading this will be the back sight.
Move the staff to point E and take a reading this will be the fore sight.
Survey Location
The levelling survey was conducted at a Kenya School of TVET field opposite the ICT department
building.
Site Characteristics
Topography:
The survey site is gently sloping, with a gradual elevation change from the starting point to the endpoint.
Vegetation consists of grass and trees along the field perimeter hence allowing clear visibility for
levelling observation.
Ground Conditions:
No significant structures or buildings are present within the immediate survey area.
Staff Readings:
Staff readings were challenging due to the mud from the previous days' rain.
Surveyors used caution to avoid damaging and sinking the staff during placement.
Results and Discussion
The following results are obtained at site during the practical exercise from the field opposite the ICT
building at KSTVET. The reduced levels were done by both the rise and fall method and the height of
collimation:
Height of Collimation
Station Back Sight Inter Sight Fore Sight H.O.C Reduced Remarks
Level
3.850 353.850 350.000
3.650 350.200
3.398 350.452
3.140 3.250 353.740 350.600
2.942 350.798
2.770 2.768 353.742 350.972
2.650 351.092
2.500 351.242
2.360 351.382
2.245 351.497
2.130 351.612
2.000 351.742
1.970 351.952
1.760 351.982
1.605 351.137
1.440 352.302
1335 352.407
1.235 352.507
1.085 352.657
0.965 352.777
0.900 352.842
0.815 352.927
0.775 352.967
0.765 352.977
0.735 353.007
0.725 353.017
0.715 353.027
0.725 353.017
0.720 353.022
0.705 353.037
0.715 353.027
0.640 353.102
0.590 353.152
0.600 353.142
0.620 353.122
0.700 353.042
0.820 0.690 353.052
Conclusion
In conclusion the exercise achieved its objectives and as a student I was able to know how to conduct a
levelling exercise from start to finish.