0% found this document useful (0 votes)
29 views

Method Statement For Fixing of Slab Reinforcement

Uploaded by

Karambir Singh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views

Method Statement For Fixing of Slab Reinforcement

Uploaded by

Karambir Singh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

TPHL/QMS Document No.

12
METHOD STATEMENT
FOR FIXING OF SLAB Rev: 0 Working status :
REINFORCEMENT WORK Page 1 / 5 Date : 02.11.2023

TRIDENT HILLS PRIVATE LIMITED

PROJECT NAME:- WINDSONG RESIDENCES, PANCHKULA

Prepared by : Karambir Singh Reviewed by: Approved by :

Page | 1
TPHL/QMS Document No. 12
METHOD STATEMENT
FOR FIXING OF SLAB Rev: 0 Working status :
REINFORCEMENT WORK Page 2 / 5 Date : 02.11.2023

CONTENTS

1. Objective and scope

2. Tools and Equipments

3. Materials required

4. Engineering works

5. Responsibility

6. Health & Safety

6.1 Hazards

6.2 General Control Measures

6.3 Recovery Measures

7. Sequence of work

7.1 Preparation for fixing of Slab reinforcement

7.2 Procedure fixing of Slab Reinforcement

7.3 Miscellaneous

8. Documentation

Prepared by : Karambir Singh Reviewed by: Approved by :

Page | 2
TPHL/QMS Document No. 12
METHOD STATEMENT
FOR FIXING OF SLAB Rev: 0 Working status :
REINFORCEMENT WORK Page 3 / 5 Date : 02.11.2023

1. Objective and scope:


This method statement describes work procedure for fixing of Slab reinforcement in a building as
specified in the tender document/drawing. It shall be done by experienced workers as per the relevant
standards/drawings and to the full satisfaction of the Engineer-in-charge.

2. Tools and Equipments:


All tools and tackles required for the complete execution and completion of the work shall be arranged
well in advance. The list of tools to be required for the work as followings: -
2.1 Personnel Protective Equipments
2.2 Plumb bob
2.3 Measuring tape
2.4 Torque wrench
2.5 Framing square
2.6 Spirit Level
2.7 Adjustable wrench
2.8 Thread or Line Dori
2.9 Hammer

3. Materials required:
3.1 Binding wire as approved
3.2 PVC/concrete cover blocks
3.3 Marker pen
3.4 Timber Log
3.5 Scaffolding standard and Ledger
3.6 Scaffolding Joint Pin
3.7 Adjustable base jack
3.8 Scaffolding Coupler
3.9 Scaffolding Clamp
3.10 Scaffolding Prop jack
3.11 Steel decking

4. Engineering works:
As receipt of drawings the Engineer-in-charge shall review the received drawings and discuss with their
senior for any technical doubts and clarifications.

5. Responsibility:
5.1 The Engineer-in-charge will be responsible for implementing everything in this method
statement.
5.2 Safety officer will ensure that all safety procedures and measures are implemented in relation to
the type of work being done according to the project’s HSE plan.
5.3 QA/QC representative will be responsible for the implementation of QA/QC works as spelled out
in the Quality Management Plan.

6. Health & Safety


6.1 Hazards
6.1.1 Hot Sunrays
6.1.2 Hot Weather
6.1.3 Fall of heavy objects

Prepared by : Karambir Singh Reviewed by: Approved by :

Page | 3
TPHL/QMS Document No. 12
METHOD STATEMENT
FOR FIXING OF SLAB Rev: 0 Working status :
REINFORCEMENT WORK Page 4 / 5 Date : 02.11.2023

6.1.4 Fall of persons from height


6.1.5 Dust
6.1.6 Noise during the works
6.1.7 Defective tools - chisel, hammer, nail extractor etc.
6.1.8 Defective hand tools, improper use of tools
6.1.9 Heat stress
6.1.10 Germicide and Insecticide
6.1.11 Food contamination
6.1.12 Water contamination
6.1.13 Skin contact/clothing contact
6.1.14 Eye contact

6.2 General Control Measures:


6.2.1 Tool Box Meeting
6.2.2 Use of proper PPE
6.2.3 Follow Procedures
6.2.4 Keep adequate warning signs and barricading in appropriate location.
6.2.5 Use skilled personnel
6.2.6 Deploy right person for the right job with valid licenses wherever required.
6.2.7 Impart proper Job Specific Training
6.2.8 Use proper Tools & Tackles
6.2.9 First Aider
6.2.10 Drinking Water
6.2.11 Deploy well maintained Lifting and Shifting Equipment
6.2.12 Underneath area shall be barricaded
6.2.13 Use of full body harness & 100 % tie off shall be ensured
6.2.14 Proper scaffolding shall be made & green tag shall be provided
6.2.15 No over load shall be allowed on working platform
6.2.16 Proper House Keeping
6.2.17 Start the work only after ensuring that it is safe in all respects
6.2.18 Stop work when it is not safe
6.2.19 Identify Assembly Point
6.2.20 Emergency contact will be annexed in project safety plan

6.3 Recovery Measures:


6.3.1 In case any undesired event or incident does happen at the work site or residential camp, in spite
of the essential HSE protection systems and procedures are in place, the same shall be handled in
such a way as to reduce the severity of human injury or damages and to regain control within the
least possible time.
6.3.2 In incidents of major nature such as those resulting in fatalities, severe human injuries, fire and
explosion and natural calamities like rain, wind, sand storm etc.
6.3.3 Work will be stopped immediately and appropriate emergency response procedures adopted as
per procedures of company.
6.3.4 The matter will be communicated to key personnel by the easiest available means, seeking
assistance and advice.
6.3.5 Further work will be started only on getting clearance from senior management.
6.3.6 Tool box meeting will be conducted of all employees to explain the HSE part of the incident, the
immediate and the corrective/control measures that are essential to prevent further occurrences of
similar incidents.
Prepared by : Karambir Singh Reviewed by: Approved by :

Page | 4
TPHL/QMS Document No. 12
METHOD STATEMENT
FOR FIXING OF SLAB Rev: 0 Working status :
REINFORCEMENT WORK Page 5 / 5 Date : 02.11.2023

6.3.7 Detailed investigation will be made into the incident, other than natural calamities, and the
learning points disseminated to the work force.
6.3.8 In less serious cases, first aid or clinical aid shall be extended to injured victims if any and the
matter intimated to all concerned. Adequate first aid boxes shall be in place and trained first
aiders provided at site.
7. Sequence of work:
8.1 Preparation for fixing of Slab reinforcement:
8.1.1 The Engineer-in-charge will ensure layout work shall be completed as per drawings and to be
checked by him.
8.1.2 All required dia of reinforcement bars cut and prepared shape & dimensions as per drawing.
8.1.3 Site Engineer shall ensure the reinforcement bars prepared by bar-bender before fixing at location
as per drawings.
8.1.4 Bar-bender shall shift all reinforcement bars to the location for fixing.

8.2 Procedure for fixing of Slab reinforcement:


8.2.1 Surveyor shall mark the level/line for slab formwork according to drawing.
8.2.2 Bar-bender shall fix the reinforcement as per drawing.
8.2.3 Site engineer shall ensure the fixing of reinforcement bars is going on according to drawing and
lap length is fixed as per drawing.
8.2.4 Site engineer shall ensure all lap of reinforcement bars are placed in NO LAP ZONE.
8.2.5 Site engineer shall ensure all hooks of stirrups in beam/columns are bent at 135 degree angle.
8.2.6 Site engineer shall ensure tie of reinforcement is rigid and supported to ensure the displacement
during concreting.
8.2.7 Site engineer shall ensure extra reinforcement is fixed near openings as per drawing.
8.2.8 Site engineer shall ensure the clear cover to reinforcement is fixed as per drawing.
8.2.9 Site Engineer shall ensure all reinforcement works are completed as per drawing.

8.3 Miscellaneous:
The completed works shall be inspected and any left-out items, minor defects if any, will be
rectified immediately.

8. Documentation: RFI and checklist shall be maintained by the site Engineer for the work.

Prepared by : Karambir Singh Reviewed by: Approved by :

Page | 5