Method Statement For Fixing of Slab Reinforcement
Method Statement For Fixing of Slab Reinforcement
12
METHOD STATEMENT
FOR FIXING OF SLAB Rev: 0 Working status :
REINFORCEMENT WORK Page 1 / 5 Date : 02.11.2023
Page | 1
TPHL/QMS Document No. 12
METHOD STATEMENT
FOR FIXING OF SLAB Rev: 0 Working status :
REINFORCEMENT WORK Page 2 / 5 Date : 02.11.2023
CONTENTS
3. Materials required
4. Engineering works
5. Responsibility
6.1 Hazards
7. Sequence of work
7.3 Miscellaneous
8. Documentation
Page | 2
TPHL/QMS Document No. 12
METHOD STATEMENT
FOR FIXING OF SLAB Rev: 0 Working status :
REINFORCEMENT WORK Page 3 / 5 Date : 02.11.2023
3. Materials required:
3.1 Binding wire as approved
3.2 PVC/concrete cover blocks
3.3 Marker pen
3.4 Timber Log
3.5 Scaffolding standard and Ledger
3.6 Scaffolding Joint Pin
3.7 Adjustable base jack
3.8 Scaffolding Coupler
3.9 Scaffolding Clamp
3.10 Scaffolding Prop jack
3.11 Steel decking
4. Engineering works:
As receipt of drawings the Engineer-in-charge shall review the received drawings and discuss with their
senior for any technical doubts and clarifications.
5. Responsibility:
5.1 The Engineer-in-charge will be responsible for implementing everything in this method
statement.
5.2 Safety officer will ensure that all safety procedures and measures are implemented in relation to
the type of work being done according to the project’s HSE plan.
5.3 QA/QC representative will be responsible for the implementation of QA/QC works as spelled out
in the Quality Management Plan.
Page | 3
TPHL/QMS Document No. 12
METHOD STATEMENT
FOR FIXING OF SLAB Rev: 0 Working status :
REINFORCEMENT WORK Page 4 / 5 Date : 02.11.2023
Page | 4
TPHL/QMS Document No. 12
METHOD STATEMENT
FOR FIXING OF SLAB Rev: 0 Working status :
REINFORCEMENT WORK Page 5 / 5 Date : 02.11.2023
6.3.7 Detailed investigation will be made into the incident, other than natural calamities, and the
learning points disseminated to the work force.
6.3.8 In less serious cases, first aid or clinical aid shall be extended to injured victims if any and the
matter intimated to all concerned. Adequate first aid boxes shall be in place and trained first
aiders provided at site.
7. Sequence of work:
8.1 Preparation for fixing of Slab reinforcement:
8.1.1 The Engineer-in-charge will ensure layout work shall be completed as per drawings and to be
checked by him.
8.1.2 All required dia of reinforcement bars cut and prepared shape & dimensions as per drawing.
8.1.3 Site Engineer shall ensure the reinforcement bars prepared by bar-bender before fixing at location
as per drawings.
8.1.4 Bar-bender shall shift all reinforcement bars to the location for fixing.
8.3 Miscellaneous:
The completed works shall be inspected and any left-out items, minor defects if any, will be
rectified immediately.
8. Documentation: RFI and checklist shall be maintained by the site Engineer for the work.
Page | 5