Vdocument - in DPWH Blue Book 559abbac69281
Vdocument - in DPWH Blue Book 559abbac69281
c om
FOREWORD
FLORANTE SORIQUEZ
Acting Secretary
Department Order )
)
No. 24 )
Series of 2005 )
SUBJECT : DPWH Standard Specifications for Public
Works and Highways, 2004 Edition: Volume II,
Highways, Bridges and Airports.
All previous issuances contrary with this Order are hereby revoked.
SGD
FLORANTE SORIQUEZ
Acting Secretary
VOLUME II
TABLE OF CONTENTS
PAGE
Item
Item 201-
202- Aggregate Base Course
Crushed Aggregate Base Course ---------------
--------------- 41
44
Item 203- Lime Stabilized Road Mix Base Course --------------- 46
Item 204- Portland Cement Stabilized Road Mix --------------- 51
Base Course
Item 205- Asphalt Stabilized Road Mix Base --------------- 53
Course
Item 206- Portland Cement Treated Plant Mix --------------- 54
Base Course
Item 207- Aggregate Stockpile --------------- 57
Item 300-
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 Aggregate Surface Course --------------- 59 4/437
G- PROTECTION STRUCTURES
Item 500- Pipe Culverts and Storm Drains --------------- 282
Item 501- Underdrains --------------- 288
Item 502- Manholes, Inlets and Catch Basins --------------- 291
Item 503- Drainage Steel Grating with Frame --------------- 294
Item 504- Cleaning and Reconditioning Existing --------------- 298
Drainage Structures
Item 505- Riprap and Grouted Riprap --------------- 300
Item 506- Stone Masonry --------------- 304
Item 507- Rubble Concrete --------------- 308
Item 508- Hand-Laid Rock Embankment --------------- 310
Item 509- Sheet Piles --------------- 312
Item 510- Concrete Slope Protection
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281
--------------- 313 5/437
Item
Item 712-
713- Structural
Treated andMetal
Untreated Timber ---------------
--------------- 408
415
Item 714- Water --------------- 416
Item 715- Geotextiles --------------- 417
PART A
FACILITIES FOR THE ENGINEER
A.1 REQUIREMENTS
All facilities provided by the Contractor shall be near the job site, where
necessary and shall conform to the best standard for the required types. On
completion of the Contract, the facilities provided by the Contractor including
utilities and communication facilities shall revert to the Government including
office equipment, apparatus, pieces of furniture, laboratory equipment, etc,
unless otherwise specified in the Contract documents.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 7/437
The Contractor shall be responsible for raising the ground (if necessary)
5/7/2018 DPW H Blue Book - slide pdf.c om
The whole area of the Engineer’s compound shall be fenced with barbed
wire (or equivalent) with necessary gates as directed by the Engineer.
The contractor shall maintain the vehicle in first class condition and shall
be supplied with appropriate fuel and lubricants al all times
He shall provide equivalent substitute vehicles during any period when the
specified vehicles are taken out of service for maintenance, repair or any other
reason. Unless otherwise specified, the vehicle shall at the end of the Contract
become the property of the Government.
The Contractor shall at all times during the duration of the Contract
provide for the use of the Engineer all equipment, instruments and apparatus, all
information and records and qualified chainmen and laborers required by the
Engineer for inspecting and measuring the Works. Such equipment, instruments
and apparatus shall include those listed in the Special Provisions.
A.1.4 Photographs
The Contractor shall provide record photographs taken as, when and
where directed by the Engineer at intervals of not more than one month. The
photographs shall be sufficient in number and location to record the exact
progress of the Works. The Contractor shall provide one proof print of each
photograph taken, and the negative and ten copies, not less than 254 mm x 203
mm and printed on glossy paper, of any of the photographs by the Engineer. The
photographs retained by the Engineer will become the property of the
Government and the Contractor shall supply approved albums to accommodate
them. Two copies are to be signed by the Contractor, one of which will be signed
by the Engineer and returned to the Contractor.
A.2.1 Measurement
4. The quantities for the provision of vehicles for the Engineer shall be the
number of each type of vehicle supplied. The unit of measure is “each”.
5. The quantities for the operation of vehicle for the Engineer shall be for
the time the Engineer is supplied with each vehicle prior to their finally becoming
the property of the Government. The unit of measure is “month”.
PART B
The contractor shall provide and maintain such offices, stores, workshops
latrines, housing and messing accommodations as are necessary. These should
be located in the Contractor’s compound, distinct and separate from the
Engineer’s compound. The location, dimensions and layout of such buildings and
places shall be subject to the approval of the Engineer. The Contractor shall not
be permitted to erect temporary buildings or structures on the site without the
specific permission in writing of the Engineer including approval of the
dimensions of such buildings or structures. Before the commencement of the
period of Warranty, the Contractor shall fence of the Contractor’s store area from
the rest of the Site. By the end of the Period of Warranty, the Contractor shall
remove this fence and all buildings shall be cleared and the area shall be graded
as required by the Engineer.
3. Thetolocation
made known of the medical
all employees room
by posting onand any other
prominent arrangements
locations suitableshall be
notices
in the Site.
4. The Contractor’s arrangement to comply with this Section shall be
subject to the approval of the Engineer and also to the approval of any qualified
Medical Officer designated by the Government to supervise medical
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 11/437
5/7/2018 DPW H Blue Book - slide pdf.c om
PART C – EARTHWORK
100.1 Description
This item shall consist of clearing, grubbing, removing and disposing all vegetation and
debris as designated in the Contract, except those objects that are designated to remain in
place or are to be removed in consonance with other provisions of this Specification. The work
shall also include the preservation from injury or defacement of all objects designated to remain.
The Engineer will establish the limits of work and designate all trees, shrubs, plants and
other things to remain. The Contractor shall preserve all objects designated to remain. Paint
required for cut or scarred surface of trees or shrubs selected for retention shall be an approved
asphaltum base paint prepared especially for tree surgery.
Clearing shall extend one (1) meter beyond the toe of the fill slopes or beyond rounding
of cut slopes as the case maybe for the entire length of the project unless otherwise shown on
the plans or as directed by the Engineer and provided it is within the right of way limits of the
project, with the exception of trees under the jurisdiction of the Forest Management Bureau
(FMB).
All surface objects and all trees, stumps, roots and other protruding obstructions, not
designated to remain, shall be cleared and/or grubbed, including mowing as required, except as
provided below:
(1) Removal of undisturbed stumps and roots and nonperishable solid objects with a
minimum depth of one (1) meter below subgrade or slope of embankment will not
be required.
(2) In areas outside of the grading limits of cut and embankment areas, stumps and
nonperishable solid objects shall be cut off not more than 150 mm (6 inches) above
the ground line or low water level.
(3) In areas to be rounded at the top of cut slopes, stumps shall be cut off flush with or
below the surface of the final slope line.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 12/437
5/7/2018 DPW H Blue Book - slide pdf.c om
designated by the Engineer, and disposed outside the clearing and grubbing limits
as indicated in the typical roadway section.
Except in areas to be excavated, stump holes and other holes from which obstructions
are removed shall be backfilled with suitable material and compacted to the required density.
If perishable material is burned, it shall be burned under the constant care of component
watchmen at such times and in such a manner that the surrounding vegetation, other adjacent
property, or anything designated to remain on the right of way will not be jeopardized. If
permitted, burning shall be done in accordance with applicable laws, ordinances, and
regulation.
The Contractor shall use high intensity burning procedures, (i.e., incinerators, high
stacking or pit and ditch burning with forced air supplements) that produce intense burning with
little or no visible smoke emission during the burning process. At the conclusion of each
burning session, the fire shall be completely extinguished so that no smoldering debris remains.
In the event that the Contractor is directed by the Engineer not to start burning
operations or to suspend such operations because of hazardous weather conditions, material to
be burned to
Contractor which interferes
temporary with subsequent
locations construction
clear of construction operations
operations and shall
later, be moved by
if directed the
by the
Engineer, shall be placed on a designated spot and burned.
Materials and debris which cannot be burned and perishable materials may be disposed
off by methods and at locations approved by the Engineer, on or off the project. If disposal is
by burying, the debris shall be placed in layers with the material so disturbed to avoid nesting.
Each layer shall be covered or mixed with earth material by the land-fill method to fill all voids.
The top layer of material buried shall be covered with at least 300 mm (12 inches) of earth or
other approved material and shall be graded, shaped and compacted to present a pleasing
appearance. If the disposal location is off the project, the Contractor shall make all necessary
arrangements with property owners in writing for obtaining suitable disposal locations which are
outside the limits of view from the project. The cost involved shall be included in the unit bid
price. A copy of such agreement shall be furnished to the Engineer. The disposal areas shall
be seeded, fertilized and mulched at the Contractor’s expense.
Woody material may be disposed off by chipping. The wood chips may be used for
mulch, slope erosion control or may be uniformly spread over selected areas as directed by the
Engineer. Wood chips used as mulch for slope erosion control shall have a maximum
thickness of 12 mm (1/2 inch) and faces not exceeding 3900 mm 2 (6 square inches) on any
individual surface area. Wood chips not designated for use under other sections shall be
spread over the designated areas in layers not to exceed 75 mm (3 inches) loose thickness.
Diseased trees shall be buried or disposed off as directed by the Engineer.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 13/437
5/7/2018 DPW H Blue Book - slide pdf.c om
trimmed to give a clear height of 6 m (20 feet) above the roadbed surface. All trimming shall be
done by skilled workmen and in accordance with good tree surgery practices.
Timber cut inside the area staked for clearing shall be felled within the area to be
cleared.
Individual trees or stumps designated by the Engineer for removal and located in areas
other than those established for clearing and grubbing and roadside cleanup shall be removed
and disposed off as specified under Subsection 100.2.2 except trees removed shall be cut as
nearly flush with the ground as practicable without removing stumps.
100.3 Method of Measurement
1. Area Basis. The work to be paid for shall be the number of hectares and
fractions thereof acceptably cleared and grubbed within the limits indicated on the
Plans or and
clearing as may be adjusted
grubbing limits in field staking
shown on the by the Engineer.
Plans Areas
or not staked for not withinand
clearing the
grubbing will not be measured for payment.
2. Lump-Sum Basis. When the Bill of Quantities contains a Clearing and Grubbing
lump-sum item, no measurement of area will be made for such item.
3. Individual Unit Basis (Selective Clearing). The diameter of trees will be measured
at a height of 1.4 m (54 inches) above the ground. Trees less than 150 mm (6
inches) in diameter will not be measured for payment.
When Bill of Quantities indicates measurement of trees by individual unit basis, the units
will be designated and measured in accordance with the following schedule of sizes:
The accepted quantities, measured as prescribed in Section 100.3, shall be paid for at
the Contract unit price for each of the Pay Items listed below that is included in the Bill of
Quantities, which price and payment shall be full compensation for furnishing all labor,
equipment, tools and incidentals necessary to complete the work prescribed in this Item.
This Item shall consist of the removal wholly or in part, and satisfactory disposal of all
buildings, fences, structures, old pavements, abandoned pipe lines, and any other obstructions
which are not designated or permitted to remain, except for the obstructions to be removed and
disposed off under other items in the Contract. It shall also include the salvaging of designated
101.2.1 General
The Contractor shall perform the work described above, within and adjacent to the
roadway, on Government land or easement, as shown on the Plans or as directed by the
Engineer. All designated salvable material shall be removed, without unnecessary damage, in
sections or pieces which may be readily transported and shall be stored by the Contractor at
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 15/437
5/7/2018 DPW H Blue Book - slide pdf.c om
All existing bridges, culverts and other drainage structures in use by traffic shall not be
removed until satisfactory arrangements have been made to accommodate traffic. The
removal of existing culverts within embankment areas will be required only as necessary for
the installation of new structures. Abandoned culverts shall be broken down, crushed and
sealed or plugged. All retrieved culvert for future use as determined by the Engineer shall be
carefully removed and all precautions shall be employed to avoid breakage or structural
damage to any of its part. All sections of structures removed which are not designated for
stockpiling or re-laying shall become the property of the Government and be removed from the
project or disposed off in a manner approved by the Engineer.
Steel bridges and wood bridges when specified to be salvaged shall be carefully
dismantled without by
marking is waived damaged. Steel members
the Engineer. shallmaterial
All salvaged be matchshallmarked unless
be stored as such match
specified in
Subsection 101.2.1.
Structures designated to become the property of the Contractor shall be removed from
the right-of-way.
Unless otherwise provided, all pipes shall be carefully removed and every precaution
taken to avoid breakage or damaged. Pipes to be relaid shall be removed and stored when
necessary so that there will be no loss of damage before re-laying. The Contractor shall
replace sections lost from storage or damage by negligence, at his own expense.
All concrete pavement, base course, sidewalks, curbs, gutters, etc., designated for
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 16/437
5/7/2018 DPW H Blue Book - slide pdf.c om
(3) Otherwise demolished and disposed off as directed by the Engineer. When
specified, ballast, gravel, bituminous materials or other surfacing or pavement
materials shall be removed and stockpiled as required in Subsection 101.2.1,
otherwise such materials shall be disposed off as directed.
There will be no separate payment for excavating for removal of structures and
obstructions or for backfilling and compacting the remaining cavity.
When the Contract stipulates that payment will be made for removal of obstructions on
lump-sum basis, the pay item will include all structures and obstructions encountered within the
roadway. Where the contract stipulates that payment will be made for the removal of specific
items on a unit basis, measurement will be made by the unit stipulated in the Contract.
Whenever the Bill of Quantities does not contain an item for any aforementioned
removals, the work will not be paid for directly, but will be considered as a subsidiary obligation
of the Contractor under other Contract Items.
Roadway excavation will include excavation and grading for roadways, parking areas,
intersections, approaches, slope rounding, benching, waterways and ditches; removal of
unsuitable material from the roadbed and beneath embankment areas; and excavating selected
material found in the roadway as ordered by the Engineer for specific use in the improvement.
Roadway excavation will be classified as “unclassified excavation”, “rock excavation”, “common
excavation”, or “muck excavation” as indicated in the Bill of Quantities and hereinafter
described.
(2) Rock Excavation. Rock excavation shall consist of igneous, sedimentary and
metamorphic rock which cannot be excavated without blasting or the use of rippers,
and all boulders or other detached stones each having a volume of 1 cubic meter or
more as determined by physical measurements or visually by the Engineer.
(3) Common Excavation. Common excavations shall consist of all excavation not
included in the Bill of Quantities under “rock excavation” or other pay items.
(4) Muck Excavation. Muck excavation shall consist of the removal and disposal of
deposits of saturated or unsaturated mixtures of soils and organic matter not
suitable for foundation material regardless of moisture content.
Borrow excavation shall consist of the excavation and utilization of approved material
required for the construction of embankments or for other portions of the work, and shall be
obtained from approved sources, in accordance with Clause 61 and the following:
The material shall meet the quality requirements determined by the Engineer unless
otherwise provided in the Contract.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 18/437
5/7/2018 DPW H Blue Book - slide pdf.c om
undertaken by the Contractor under the control of the Engineer to serve as basis for the
computation of the actual volume of the excavated materials.
Where provided for on the Plans or in the Special Provisions, suitable topsoil
encountered in excavation and on areas where embankment is to be placed shall be removed
to such extent and to such depth as the Engineer may direct. The removed topsoil shall be
transported and deposited in storage piles at locations approved by the Engineer. The topsoil
shall be completely removed to the required depth from any designated area prior to the
beginning of regular excavation or embankment work in the area and shall be kept separate
from other excavated materials for later use.
The Engineer will designate as unsuitable those soils that cannot be properly compacted
in embankments. All unsuitable material shall be disposed off as shown on the Plans or as
directed without delay to the Contractor.
Only approved materials shall be used in the construction of embankments and backfills.
All excess material, including rock and boulders that cannot be used in embankments
shall be disposed off as directed.
Material encountered in the excavation and determined by the Engineer as suitable for
topping, road finishing, slope protection, or other purposes shall be conserved and utilized as
directed by the Engineer.
Borrow material shall not be placed until after the readily accessible roadway excavation
has been placed in the fill, unless otherwise permitted or directed by the Engineer. If the
Contractor places moré borrow than is required and thereby causes a waste of excavation, the
amount of such waste will be deducted from the borrow volume.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 19/437
5/7/2018 DPW H Blue Book - slide pdf.c om
by truck watering units, to ensure that the embankment material contains the proper moisture at
the time of compaction.
The Contractor shall provide drilling equipment capable of suitably checking the moisture
penetration to the full depth of the excavation.
102.2.5 Presplitting
Unless otherwise provided in the Contract, rock excavation which requires drilling and
shooting shall be presplit.
Presplitting to obtain faces in the rock and shale formations shall be performed by: (1)
drilling holes at uniform intervals along the slope lines, (2) loading and stemming the holes with
appropriate explosives and stemming material, and (3) detonating the holes simultaneously.
Prior to starting drilling operations for presplitting, the Contractor shall furnish the
Engineer a plan outlining the position of all drill holes, depth of drilling, type of explosives to be
used, loading pattern and sequence of firing. The drilling and blasting plan is for record
purposes only and will not absolve the Contractor of his responsibility for using proper drilling
and blasting procedures. Controlled blasting shall begin with a short test section of a length
approved by the Engineer. The test section shall be presplit, production drilled and blasted and
sufficient material excavated whereby the Engineer can determine if the Contractor’s methods
are satisfactory. The Engineer may order discontinuance of the presplitting when he
determines that the materials encountered have become unsuitable for being presplit.
The holes shall be charged with explosives of the size, kind, strength, and at the spacing
suitable for the formations being presplit, and with stemming material which passes a 9.5 mm
(3/8 inch) standard sieve and which has the qualities for proper confinement of the explosives.
The finished presplit slope shall be reasonably uniform and free of loose rock. Variance
from the true plane of the excavated backslope shall not exceed 300 mm (12 inches); however,
localized irregularities or surface variations that do not constitute a safety hazard or an
impairment to drainage courses or facilities will be permitted.
A maximum offset of 600 mm (24 inches) will be permitted for a construction working
bench at the bottom of each lift for use in drilling the next lower presplitting pattern.
All materials excavated from side ditches and gutters, channel changes, irrigation
ditches, inlet and outlet ditches, toe ditchers, furrow ditches, and such other ditches as may be
designated on the Plans or staked by the Engineer, shall be utilized as provided in Subsection
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 20/437
5/7/2018 DPW H Blue Book - slide pdf.c om
Furrow ditches shall be formed by plowing a continuous furrow along the line staked by
the Engineer. Methods other than plowing may be used if acceptable to the Engineer. The
ditches shall be cleaned out by hand shovel work, by ditcher, or by some other suitable method,
throwing all loose materials on the downhill side so that the bottom of the finished ditch shall be
approximately 450 mm (18 inches) below the crest of the loose material piled on the downhill
side. Hand finish will not be required, but the flow lines shall be in satisfactory shape to provide
drainage without overflow.
Rock shall be excavated to a depth of 150 mm (6 inches) below subgrade within the
limits of the roadbed, and the excavation backfilled with material designated on the Plans or
approved by the Engineer and compacted to the required density.
When excavation methods employed by the Contractor leave undrained pockets in the
rock surface, the Contractor shall at his own expense, properly drain such depressions or when
permitted by the Engineer fill the depressions with approved impermeable material.
Material below subgrade, other than solid rock shall be thoroughly scarified to a depth of
150 mm (6 inches) and the moisture content increased or reduced, as necessary, to bring the
material throughout this 150 mm layer to the moisture content suitable for maximum
compaction. This layer shall then be compacted in accordance with Subsection 104.3.3.
The Contractor shall notify the Engineer sufficiently in advance of opening any borrow
areas so that cross-section elevations and measurements of the ground surface after stripping
may be taken, and the borrow material can be tested before being used. Sufficient time for
testing the borrow material shall be allowed.
All borrow areas shall be bladed and left in such shape as to permit accurate
measurements after excavation has been completed. The Contractor shall not excavate
beyond the dimensions and elevations established, and no material shall be removed prior to
the staking out and cross-sectioning of the site. The finished borrow areas shall be
approximately true to line and grade established and specified and shall be finished, as
prescribed in Clause 61, Standard Specifications for Public Works and Highways, Volume 1.
When necessary to remove fencing, the fencing shall be replaced in at least as good condition
as it was originally. The Contractor shall be responsible for the confinement of livestock when a
portion of the fence is removed.
operations in such a way that the Engineer can take the necessary cross-sectional
measurements before the backfill is placed.
The excavation of muck shall be handled in a manner that will not permit the entrapment
of muck within the backfill. The material used for backfilling up to the ground line or water
level, whichever is higher, shall be rock or other suitable granular material selected from the
roadway excavation, if available. If not available, suitable material shall be obtained from other
approved sources. Unsuitable material removed shall be disposed off in designated areas
shown on the Plans or approved by the Engineer.
The cost of excavation of material which is incorporated in the Works or in other areas of
fill shall be deemed to be included in the Items of Work where the material is used.
Measurement of Unsuitable or Surplus Material shall be the net volume in its original
position.
The Contractor shall be deemed to have included in the contract unit prices all costs of
obtaining land for the disposal of unsuitable or surplus material.
The accepted quantities, measured as prescribed in Section 102.3 shall be paid for at
the contract unit price for each of the Pay Items listed below that is included in the Bill of
Quantities which price and payment shall be full compensation for the removal and disposal of
excavated materials including all labor, equipment, tools, and incidentals necessary to complete
the work prescribed in this Item.
This Item shall consist of the necessary excavation for foundation of bridges, culverts,
underdrains, and other structures not otherwise provided for in the Specifications. Except as
otherwise provided for pipe culverts, the backfilling of completed structures and the disposal of
all excavated surplus materials, shall be in accordance with these Specifications and in
reasonably close conformity with the Plans or as established by the Engineer.
This Item shall include necessary diverting of live streams, bailing, pumping, draining,
sheeting, bracing, and the necessary construction of cribs and cofferdams, and furnishing the
materials therefore, and the subsequent removal of cribs and cofferdams and the placing of all
necessary backfill.
replaceItunsuitable
shall alsomaterial
include encountered
the furnishing andthe
below placing of approved
foundation foundation
elevation fill material to
of structures.
Prior to starting excavation operations in any area, all necessary clearing and grubbing in
that area shall have been performed in accordance with Item 100, Clearing and Grubbing.
103.2.2 Excavation
(1) General, all structures. The Contractor shall notify the Engineer sufficiently in
advance of the beginning of any excavation so that cross-sectional elevations and
measurements may be taken on the undisturbed ground. The natural ground
adjacent to the structure shall not be disturbed without permission of the Engineer.
After each excavation is completed, the Contractor shall notify the Engineer to
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 23/437
5/7/2018 DPW H Blue Book - slide pdf.c om
When the footing is to rest on material other than rock, excavation to final grade
shall not be made until just before the footing is to be placed. When the foundation
material is soft or mucky or otherwise unsuitable, as determined by the Engineer,
the Contractor shall remove the unsuitable material and backfill with approved
granular material. This foundation fill shall be placed and compacted in 150 mm (6
inches) layers up to the foundation elevation.
When foundation piles are used, the excavation of each pit shall be completed
before the piles are driven and any placing of foundation fill shall be done after the
piles are driven. After the driving is completed, all loose and displaced materials
shall be removed, leaving a smooth, solid bed to receive the footing.
(3) Pipe Culverts. The width of the pipe trench shall be sufficient to permit satisfactory
jointing of the pipe and thorough tamping of the bedding material under and around
the pipe.
Where a firm foundation is not encountered at the grade established, due to soft,
spongy, or other unstable soil, such unstable soil under the pipe and for a width of
at least one diameter on each side of the pipe shall be removed to the depth
directed by the Engineer and replaced with approved granular foundation fill
material properly compacted to provide adequate support for the pipe, unless other
special construction methods are called for on the Plans.
Cofferdams or cribs for foundation construction shall in general, be carried well below the
bottoms of the footings and shall be well braced and as nearly watertight as practicable. In
general, the interior dimensions of cofferdams shall be such as to give sufficient clearance for
the construction of forms and the inspection of their exteriors, and to permit pumping outside of
the forms. Cofferdams or cribs which are tilted or moved laterally during the process of sinking
shall be righted or enlarged so as to provide the necessary clearance.
When conditions are encountered which, as determined by the Engineer, render it
impracticable to dewater the foundation before placing the footing, the Engineer may require the
construction of a concrete foundation seal of such dimensions as he may consider necessary,
and of such thickness as to resist any possible uplift. The concrete for such seal shall be
placed as shown on the Plans or directed by the Engineer. The foundation shall then be
dewatered and the footing placed. When weighted cribs are employed and the mass is
utilized to overcome partially the hydrostatic pressure acting against the bottom of the
foundation seal, special anchorage such as dowels or keys shall be provided to transfer the
entire mass of the crib to the foundation seal. When a foundation seal is placed under water,
the cofferdams shall be vented or ported at low water level as directed.
Any pumping that may be permitted from the interior of any foundation enclosure shall be
done in such a manner as to preclude the possibility of any portion of the concrete material
being carried away. Any pumping required during the placing of concrete, or for a period of at
least 24 hours thereafter, shall be done from a suitable sump located outside the concrete
forms. Pumping to dewater a sealed cofferdam shall not commence until the seal has set
sufficiently to withstand the hydrostatic pressure.
Unless otherwise provided, cofferdams or cribs, with all sheeting and bracing involved
therewith, shall be removed by the Contractor after the completion of the substructure.
Removal shall be effected in such manner as not to disturb or mar finished masonry.
Excavated areas around structures shall be backfilled with free draining granular material
approved by the Engineer and placed in horizontal layers not over 150 mm (6 inches) in
thickness, to the level of the original ground surface. Each layer shall be moistened or dried as
required and thoroughly compacted with mechanical tampers.
Engineer establishes
pressure created by thethat the masonry
methods used andhas attained
materials sufficient
placed withoutstrength to strain
damage or withstand anya
beyond
safe factor.
Backfill or embankment shall not be placed behind the walls of concrete culverts or
abutments or rigid frame structures until the top slab is placed and cured. Backfill and
embankment behind abutments held at the top by the superstructure, and behind the sidewalls
of culverts, shall be carried up simultaneously behind opposite abutments or sidewalls.
Broken rock or coarse sand and gravel shall be provided for a drainage filter at
weepholes as shown on the Plans.
Bedding, Backfill and Embankment for pipe culverts shall be done in accordance with
Item 500, Pipe Culverts and Storm Drains.
The volume of excavation to be paid for will be the number of cubic metres measured in
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 26/437
5/7/2018 DPW H Blue Book - slide pdf.c om
(2) The volume of excavation for culvert and sections outside the vertical plane for
culverts stipulated in (1) above.
(3) The volume outside of neat lines of underdrains as shown on the Plans, and outside
the limits of foundation fill as ordered by the Engineer.
(4) The volume included within the staked limits of the roadway excavation, contiguous
channel changes, ditches, etc., for which payment is otherwise provided in the
Specification.
(5) Volume of water or other liquid resulting from construction operations and which
(7) the volume of any material rehandled, except that where the Plans indicate or the
Engineer directs the excavation after embankment has been placed and except that
when installation of pipe culverts by the imperfect trench method specified in Item
500 is required, the volume of material re-excavated as directed will be included.
(8) The volume of excavation for footings ordered at a depth more than 1.5 m (60
inches) below the lowest elevation for such footings shown on the original Contract
Plans, unless the Bill of Quantities contains a pay item for excavation ordered below
the elevations shown on the Plans for individual footings.
The volume of bridge excavation to be paid shall be the vertical 450 mm (18 inches)
outside of and parallel to the neat lines of the footing. The vertical planes shall constitute the
vertical faces of the volume for pay quantities regardless of excavation inside or outside of
these planes.
The volume of foundation fill to be paid for will be the number of cubic metres measures
in final position of the special granular material actually provided and placed below the
foundation elevation of structures as specified, complete in place and accepted.
excavation included in the work of this Section, to a depth of 1.5 m below the lowest elevation
shown on the Plans for each separable foundation structure.
(2) Concrete will be measured and paid for as provided under Item 405, Structural
Concrete.
(3) Any roadway or borrow excavation required in excess of the quantity excavated for
structures will be measured and paid for as provided under Item 102.
(4) Shoring, cribbing, and related work required for excavation ordered more than 1.5
m (60 inches ) below Plan elevation will be paid for in accordance with Part K.
Selected Borrow, for topping – soil of such gradation that all particles will pass a
sieve with 75 mm (3 inches) square openings and not more than 15 mass percent
will pass the 0.075 mm (No. 200) sieve, as determined by AASHTO T 11. The
material
T 90 andshall have
a liquid a plasticity
limit index
of not more of30
than notasmore than 6 as
determined by determined
AASHTO T by89.ASSHTO
(c) Soils with liquid limit exceeding 80 and/or plasticity index exceeding 55.
(e) Soils with very low natural density, 800 kg/m3 or lower.
104.3.1 General
Prior to construction of embankment, all necessary clearing and grubbing in that area
shall have been performed in conformity with Item 100, Clearing and Grubbing.
Where provided on the Plans and Bill of Quantities the top portions of the roadbed in
both cuts and embankments, as indicated, shall consist of selected borrow for topping from
excavations.
104.3.2 Methods of Construction
Where there is evidence of discrepancies on the actual elevations and that shown on the
Plans, a preconstruction survey referred to the datum plane used in the approved Plan shall be
undertaken by the Contractor under the control of the Engineer to serve as basis for the
computation of the actual volume of the embankment materials.
When is
embankment embankment is toagainst
to be compacted be placed and
existing compacted or
embankments, on when
hillsides, or whenis new
embankment built
one-half width at a time, the existing slopes that are steeper than 3:1 when measured at right
angles to the roadway shall be continuously benched over those areas as the work is brought
up in layers. Benching will be subject to the Engineer’s approval and shall be of sufficient width
to permit operation of placement and compaction equipment. Each horizontal cut shall begin at
the intersection of the original ground and the vertical sides of the previous cuts. Material thus
excavated shall be placed and compacted along with the embankment material in accordance
with the procedure described in this Section.
When shoulder excavation is specified, the roadway shoulders shall be excavated to the
depth and width shown on the Plans. The shoulder material shall be removed without
disturbing the adjacent existing base course material, and all excess excavated materials shall
be disposed
before being off as provided in Subsection 102.2.3. If necessary, the areas shall be compacted
backfilled.
Where embankment is to be constructed across low swampy ground that will not support
the mass of trucks or other hauling equipment, the lower part of the fill may be constructed by
dumping successive loads in a uniformly distributed layer of a thickness not greater than
necessary to support the hauling equipment while placing subsequent layers.
When excavated material contains more than 25 mass percent of rock larger than 150
mm in greatest diameter and cannot be placed in layers of the thickness prescribed without
crushing, pulverizing or further breaking down the pieces resulting from excavation methods,
such materials may be placed on the embankment in layers not exceeding in thickness the
approximate average size of the larger rocks, but not greater than 600 mm (24 inches).
Even though the thickness of layers is limited as provided above, the placing of individual
rocks and boulders greater than 600 mm in diameter will be permitted provided that when
placed, they do not exceed 1200 mm (48 inches) in height and provided they are carefully
distributed, with the interstices filled with finer material to form a dense and compact mass.
Each layer shall be leveled and smoothed with suitable leveling equipment and by
distribution of spalls and finer fragments of earth. Lifts of material containing more than 25
mass percent of rock larger than 150 mm in greatest dimensions shall not be constructed
above an elevation 300 mm ( 12 inches) below the finished subgrade. The balance of the
embankment shall be composed of suitable material smoothed and placed in layers not
exceeding 200 mm (8 inches) in loose thickness and compacted as specified for embankments.
Dumping and rolling areas shall be kept separate, and no lift shall be covered by another
until compaction complies with the requirements of Subsection 104.3.3.
Hauling and leveling equipment shall be so routed and distributed over each layer of the
fill in such a manner as to make use of compaction effort afforded thereby and to minimize
rutting and uneven compaction.
104.3.3 Compaction
Compaction Trials
Before commencing the formation of embankments, the Contractor shall submit in writing
to the in
used Engineer for approval
the works. The his proposals
proposals for include
shall the compaction of each type
the relationship of fill material
between to be
the types of
compaction equipment, and the number of passes required and the method of adjusting
moisture content. The Contractor shall carry out full scale compaction trials on areas not less
than 10 m wide and 50 m long as required by the Engineer and using his proposed procedures
or such amendments thereto as may be found necessary to satisfy the Engineer that all the
Earth
The Contractor shall compact the material placed in all embankment layers and the
material scarified to the designated depth below subgrade in cut sections, until a uniform
density of not less than 95 mass percent of the maximum dry density determined by AASHTO T
99 Method C, is attained, at a moisture content determined by Engineer to be suitable for such
density. Acceptance of compaction may be based on adherence to an approved roller pattern
developed as set forth in Item 106, Compaction Equipment and Density Control Strips.
The Engineer shall during progress of the Work, make density tests of compacted
material
including inthe
accordance with AASHTO
use of properly T 191,
calibrated T 205,
nuclear or other
testing approved
devices. field density
A correction tests,
for coarse
particles may be made in accordance with AASHTO T 224. If, by such tests, the Engineer
determines that the specified density and moisture conditions have not been attained, the
Contractor shall perform additional work as may be necessary to attain the specified conditions.
At least one group of three in-situ density tests shall be carried out for each 500 m of
each layer of compacted fill.
Rock
Embankment materials classified as rock shall be deposited, spread and leveled the full
width of the fill with sufficient earth or other fine material so deposited to fill the interstices to
produce a dense compact embankment. In addition, one of the rollers, vibrators, or
compactors meeting the requirements set forth in Subsection 106.2.1, Compaction Equipment,
shall compact the embankment full width with a minimum of three complete passes for each
layer of embankment.
During the construction of the roadway, the roadbed shall be maintained in such
condition that it will be well drained at all times. Side ditches or gutters emptying from cuts to
embankments
erosion. or otherwise shall be so constructed as to avoid damage to embankments by
If embankment can be deposited on one side only of abutments, wing walls, piers or
Rounding-Except in solid rock, the tops and bottoms of all slopes, including the slopes of
drainage ditches, shall be rounded as indicated on the Plans. A layer of earth overlaying rock
shall be rounded above the rock as done in earth slopes.
All earth slopes shall be left with roughened surfaces but shall be reasonably uniform,
without any noticeable break, and in reasonably close conformity with the Plans or other
surfaces indicated on the Plans or as staked by the Engineer, with no variations therefrom
readily discernible as viewed from the road.
Cut slopes in rippable material (soft rock) having slope ratios between 0.75:1 and 2:1
shall be constructed so that the final slope line shall consist of a series of small horizontal steps.
The step rise and tread dimensions shall be shown on the Plans. No scaling shall be
performed on the stepped slopes except for removal of large rocks which will obviously be a
safety hazard if they fall into the ditchline or roadway.
When called for in the Contract, permanent earth berms shall be constructed of well
graded materials
When local with
material no rocks
is not havingacceptable
acceptable, a diameter greatershall
material thanbe0.25 the height
imported, of the by
as directed berm.
the
Engineer.
Compacted Berm
Uncompacted Berm
Uncompacted berm construction shall consist of drying, if necessary and placing material
in locations shown on the Plans or as established by the Engineer. Material shall contain no
frozen material, roots, sod or other deleterious materials. Contractor shall take precautions to
prevent material from escaping over the embankment slope.
The quantity of embankment to be paid for shall be the volume of material compacted in
place, accepted by the Engineer and formed with material obtained from any source.
Material from excavation per Item 102 which is used in embankment and accepted by
the Engineer will be paid under Embankment and such payment will be deemed to include the
cost of excavating, hauling, stockpiling and all other costs incidental to the work.
Material for Selected Borrow topping will be measured and paid for under the same
conditions specified in the preceding paragraph.
The accepted quantities, measured as prescribed in Section 104.4, shall be paid for at
the Contract unit price for each of the Pay Items listed below that is included in the Bill of
Quantities. The payment shall continue full compensation for placing and compacting all
materials including all labor, equipment, tools and incidentals necessary to complete the work
prescribed in this Item.
Payment will be made under:
structural layers. It shall extend to full width of the roadway. Unless authorized by the
Engineer, subgrade preparation shall not be done unless the Contractor is able to start
immediately the construction of the pavement structure.
105.2 Material Requirements
Unless otherwise stated in the Contract and except when the subgrade is in rock cut, all
materials below subgrade level to a depth 150 mm or to such greater depth as may be specified
shall meet the requirements of Section 104.2, Selected Borrow for Topping.
Prior to commencing preparation of the subgrade, all culverts, cross drains, ducts and
the like (including their fully compacted backfill), ditches, drains and drainage outlets shall be
completed. Any work on the preparation of the
subgrade shall not be started unless prior work herein described shall have been approved by
the Engineer.
The finished compacted surface of the subgrade shall conform to the allowable
tolerances as specified hereunder:
Permitted variation from + 20 mm
design LEVEL OF SURFACE - 30 mm
Permitted SURFACE IRREGULARITY
MEASURED BY 3-m STRAIGHT EDGE 30 mm
Permitted variation from
design CROSSFALL OR CAMBER + 0.5 %
All materials immediately below subgrade level in earth cuts to a depth of 150 mm, or to
such greater depth as may be specified, shall be compacted in accordance with the
requirements of Subsection 104.3.3.
105.3.4 Subgrade in Rock Excavation
Surface irregularities under the subgrade level remaining after trimming of the rock
excavation shall be leveled by placing specified material and compacted to the requirements of
Subsection 104.3.3.
After the embankment has been completed, the full width shall be conditioned by
removing any soft or other unstable material that will not compacted properly. The resulting
areas and all other low sections, holes, or depressions shall be brought to grade with suitable
material. The entire roadbed shall be shaped and compacted to the requirements of
Subsections 104.3.3. Scarifying, blading, dragging, rolling, or other methods of work shall be
performed or used as necessary to provide a thoroughly compacted roadbed shaped to the
cross-sections shown on the Plans.
Subsection 104.3.3.
Subsection 105.3.2. The resulting subgrade level shall conform to the allowable tolerances of
The Contractor shall be required to protect and maintain at his own expense the entire
edges in sufficient number to check the accuracy of the work, as provided in this Specification.
1. The compaction of existing ground below subgrade level in cuts of common material
as specified in Subsection 105.3.3.
105.4.2 Payment for all work for the preparation of the subgrade, including shaping to the
required levels and tolerances, other than as specified above shall be deemed to be
included in the Pay Item for Embankment.
The accepted quantities, measured as prescribed in Section 105.4, shall be paid for at
the appropriate contract unit price for Pay Item listed below that is included in the Bill of
Quantities which price and payment shall be full compensation for the placing or removal and
disposal of all materials including all labor, equipment, tools and incidentals necessary to
complete the work prescribed in this Item.
2. Steel-wheel rollers other than vibratory shall be capable of exerting a force of not less
than 45 Newton per millimeter of width of the compression roll or rolls.
4. Pneumatic-tire rollers shall have smooth tread tires of equal size that will provide a
uniform compacting pressure for the full width of the roller and capable of exerting a
ground pressure of at least 550 kpa (80 pounds per square inch).
5. Heavier compacting unit may be required to achieve the specified density of the
embankment.
106.2.2 Construction of Control Strips and Determination of Target Density
To determine target density, a control strip shall be constructed at the beginning of work
each course of material to be compacted. Each control strip, constructed to acceptable density
and surface tolerances shall remain in place and become a section of the completed roadway.
Unacceptable control strip shall be corrected or removed and replaced at the Contractor’s
expense.
of the sameAdepth
control strip shall
specified have
for the an area ofofapproximately
construction 335 itsquare
the course which meters and shall be
represents.
The materials used in the construction of the control strip shall conform to the
specification requirements. They shall be furnished from the same source and shall be of the
same type to be used in the remainder of the course represented by the control strip. The
placed to the specified thickness, and shall be continuous and uniform over the entire surface.
Compaction of the control strip shall be continued until no discernible increase in density can be
If the mean density of the control strip is less than 98 percent of the density of laboratory
compacted specimens as determined by testing procedures appropriate for the material being
placed, the Engineer may order the construction of another control strip.
A new control strip may also be ordered by the Engineer or requested by the Contractor
when:
2. Ten days of production have been accepted without construction of a new control
strip.
3. There is reason to believe that a control strip density is not representative of the
material being placed.
Unless otherwise provided, the cost of constructing the control strip will be considered
incidental to the cost of the work item for which a control strip is required. Payment for the
work item shall be deemed to include compensation for performing the work herein specified
and the furnishing of all materials, labors, tools, equipment and incidentals necessary to
construct the density control strip. No payment will be made for any material used in the
distance.
The overhaul distance for material obtained and placed within the roadway limits will be
measured along the centerline of the roadway. No allowance will be made for transverse or
lateral movement to or from the centerline except materials moved to or from designated areas
outside the roadway limits; such as Case 1, Borrow Pits, disposal areas, etc. In such case,
measurement shall be along the shortest route determined by the Engineer to be feasible and
satisfactory unless otherwise provided.
If the Contractor chooses to haul material over some other route, and such other route is
longer, the computation for payment shall be based on the overhaul distance measured along
the route designated by the Engineer.
The number of cubic metre-kilometres of overhaul to be paid for shall be the number of
cubic meters of overhaul material multiplied by the overhaul distance in kilometers. The unit
“cubic meter-kilometer” is the amount of hauling required to move one cubic meter a distance of
one kilometer beyond the free-haul distance.
The accepted quantities, measured as prescribed in Section 107.2, shall be paid for the
contract unit price for Overhaul, for the particular Pay Item listed below that is shown on the Bill
of Quantities, which price and payment shall be full compensation for overhaul, including all
labor, equipment, tools and incidentals necessary to complete the work prescribed in this Item.
Payment will not be made for overhaul of Borrow, Case 2, Foundation Fill, bedding
materials and material removed in the rounding of cut slopes when rounding is a separate pay
item.
When the Bill of Quantities does not show estimated quantities for “Overhaul” from the
Pay Item listed below, overhaul will not be directly paid for, but will be considered as a
subsidiary obligation of the Contractor under other contract items.
200.1 Description
Sieve Designation
Standard, mm Alternate US Standard Mass Percent Passing
50 2” 100
25 1” 55 – 85
9.5 3/8” 40 – 75
0.075 No. 200 0 - 12
The fraction passing the 0.075 mm (No. 200) sieve shall not be greater
than 0.66 (two thirds) of the fraction passing the 0.425 mm (No. 40) sieve.
The fraction passing the 0.425 mm (No. 40) sieve shall have a liquid limit
not greater than 35 and plasticity index not greater than 12 as determined by
AASHTO T 89 and T 90, respectively.
The coarse portion, retained on a 2.00 mm (No. 10) sieve, shall have a
mass percent of wear not exceeding 50 by the Los Angeles Abrasion Tests as
determined by AASHTO T 96.
The material shall have a soaked CBR value of not less than 25% as
d i d b AASHTO T Th CBR l h ll b b i d h
200.3.2 Placing
The placing of material shall begin at the point designated by the Engineer.
Placing shall be from vehicles especially equipped to distribute the material in a
continuous uniform layer or windrow. The layer or windrow shall be of such size
that when spread and compacted the finished layer be in reasonably close
conformity to the nominal thickness shown on the Plans.
When uniformly mixed, the mixture shall be spread to the plan thickness,
for compaction.
180, Method D has been achieved. In-place density determination shall be made
in accordance with AASHTO T 191.
After final compaction of each trial section, the Contractor shall carry out
such field density tests and other tests required as directed by the Engineer.
200.3.5 Tolerances
be paidThe
for accepted quantities,
at the contract measured
unit price as prescribed
for Aggregate in Section
Subbase Course 200.4, shall
which price
and payment shall be full compensation for furnishings and placing all materials,
including all labor, equipment, tools and incidentals necessary to complete the
work prescribed in this Item.
201.1 Description
The fraction passing the 0.075 mm (No. 200) sieve shall not be greater
than 0.66 (two thirds) of the fraction passing the 0.425 mm (No. 40) sieve.
The fraction passing the 0.425 mm (No. 40) sieve shall have a liquid limit
not greater than 25 and plasticity index not greater than 6 as determined by
AASHTO T 89 and T 90, respectively.
The coarse portion, retained on a 2.00 mm (No. 10) sieve shall have a
mass percent of wear not exceeding 50 by the Los Angeles Abrasion test
determined by AASHTO T 96.
The material passing the 19 mm (3/4 inch) sieve shall have a soaked CBR
value of not less than 80% as determined by AASHTO T 193. The CBR value
shall be obtained at the maximum dry density (MDD) as determined by AASHTO
T 180, Method D.
If filler, in addition to that naturally present, is necessary for meeting the
grading requirements or for satisfactory bonding, it shall be uniformly blended with
the base course material on the road or in a pugmill unless otherwise specified or
approved. Filler shall be taken from sources approved by the Engineer, shall be
free from hard lumps and shall not contain more than 15 percent of material
retained on the 4.75 mm (No. 4) sieve.
The existing surface shall be graded and finished as provided under Item
201.3.5 Tolerances
The aggregate base course shall be laid to the designed level and
transverse slopes shown on the Plans. The allowable tolerances shall be in
accordance with following:
Aggregate Base Course will be measured by the cubic meter (m 3). The
quantity to be paid for shall be the design volume compacted in-place as shown
on the Plans, and accepted in the completed base course. No allowance shall
be given for materials placed outside the design limits shown on the cross-
sections. Trial sections shall not be measured separately but shall be included in
the quantity of aggregate base course.
202.1 Description
This Item shall consist of furnishing, placing and compacting crushed
gravel, crushed stone or crushed rock on a prepared subgrade/subbase in one or
more layers in accordance with this Specification and lines, grades, thickness and
typical cross-sections shown on the Plans or as established by the Engineer.
The portion of the material passing the 0.425 mm (No. 40) sieve shall have
a liquid limit of not more than 25 and a plasticity index of not more than 6 as
5/7/2018 determined by AASHTO T 89 and T 90, respectively. DPW H Blue Book - slide pdf.c om
The coarse aggregate retained on a 2.00 mm (No. 10) sieve shall have a
mass percent of wear not exceeding 45 by the Los Angeles Abrasion Test as
determined by AASHTO T 96, and not less than 50 mass percent shall have at
least one (1) fractured face.
The material passing the 19 mm (3/4 inch) sieve shall have a minimum
soaked CBR-value of 80% tested according to AASHTO T 193. The CBR-value
shall be obtained at the maximum dry density determined according to AASHTO
T 180, Method D.
If filler, in addition to that naturally present, is necessary for meeting the
grading requirements or for satisfactory bonding, it shall be uniformly blended with
the crushed base course material on the road or in a pugmill unless otherwise
specified or approved. Filler shall be obtained from sources approved by the
Engineer, free from hard lumps and not contain more than 15 percent of material
retained on the 4.75 mm (No. 4) sieve.
203.1 Description
This Item shall consist of a foundation for surface course composed of soil
aggregate, lime and water in proper proportions, road-mixed and constructed on a
prepared subgrade/subbase in accordance with this Specification and the lines,
grades and typical cross-sections shown on the Plans or established by the
Engineer.
It shall consist of any combination of gravel, sand, silt and clay or other
approved combination of materials free from vegetable or other objectionable
matter. It may be materials encountered in the construction site or materials
obtained from approved sources. The crushed or uncrushed granular material
shall consist of hard, durable stones and rocks, of accepted quality, free from an
excess of flat, elongated, soft or disintegrated pieces or other objectionable
matter. It is the intent of this Specification to utilize soils existing on the roadbed
if the quality is satisfactory. If the quality and/or quantity is deficient, the soil
aggregate shall be obtained wholly or partly from approved outside sources.
The materials passing the 4.75 mm (No. 4) sieve produced in the crushing
operation of either stone or gravel shall be incorporated in the base material to the
extent permitted by the gradation requirements. The plasticity index shall not be
less than 4 nor more than 10.
203.2.3 Water
CBR Test for Gravelly Soils. The mixture passing the 19 mm (3/4 inch)
sieve shall have a minimum soaked CBR-value of 100% tested according to
AASHTO T 193. The CBR-value shall be obtained at the maximum dry density
determined according to AASHTO T 180, Method D.
Lime shall not be applied during windy, rainy or impending bad weather.
In the event rain occurs during the operations work shall be promptly stopped
These equipment shall be on the project site in good condition and shall
have been approved by the Engineer, both as to type and condition, and provided
with experienced operators before the start of construction.
The slurry is distributed by one or more passes over a measured area until
the specified percentage (based on lime solids content) is obtained. To prevent
203.3.5 Mixing
After the last lime application and partial mixing, the entire mass of the
mixture shall be windrowed on the road surface and then mixed by blading the
mixture from side to side of the road, or by manipulation producing equivalent
results, until the whole mass has a uniform color and the mixture is free from fat
or lean spots or balls of unmixed particles. During the mixing operations, care
shall be taken to avoid cutting into the underlying course. When directed, the
mixing process shall be confined to part of the width or area of the road so as to
allow traffic to pass.
mixtureWhen theformed
shall be mixing
intooperations have
a windrow of beencross-section.
uniform satisfactorily completed, the
Each pass shall terminate at least 910 mm (3 ft) in advance or to the rear of the
end of the preceding pass. During compaction, the surface shall be dragged or
bladed as necessary to fill ruts and to remove incipient corrugation or other
5/7/2018 DPW H Blue Book - slide pdf.c om
irregularities. Rolling shall continue until the surface is of uniform texture and
satisfactory compaction is obtained. Initial rolling shall be performed with a
pneumatic tire roller and final rolling with a 3-wheel or tandem-type steel wheel
roller. Rolling shall be discontinued whenever it begins to produce excessive
pulverizing of the aggregate or displacement of the mixture.
When the compacted thickness of the road mix lime stabilized base course
is to be more than 150 mm, the mixture shall be spread from the windrow and
compacted in two (2) approximately equal layers, the first layer to be bladed and
After the lime-stabilized base course has been finished as specified herein,
the surface shall be protected against rapid drying for a period of at least five (5)
days by either of the following curing methods:
The Contractor
work within the limits ofshall be required
his Contract to maintain
in good at satisfactory
condition his own expense
to the the entire
Engineer
from the time he first started work until all work shall have been completed.
Maintenance shall include immediate repairs of any defects that may occur before
and after the lime-stabilized base course has been compacted and finished, which
work shall be done by the Contractor at his own expense and repeated as may be
Lime Stabilized Road Mix base Course will be measured by the cubic
meter (m3). The quantity to be paid for shall be the design volume compacted in
place as shown on the Plans, and accepted in the completed course. No
allowance shall be given for materials placed outside the design limits shown on
the cross-sections. Trial sections shall not be measured separately but shall be
included in the quantity of lime stabilized road mix base course.
5/7/2018
204.2 Material Requirements DPW H Blue Book - slide pdf.c om
Soil-Aggregate
205.1 Description
205.2.1 Soil-Aggregates
Asphalt Stabilized Road Mix Base Course will be measured by the cubic
meter (m3). The quantity to be paid for shall be the design volume compacted in
place as shown on the Plans, accepted in the completed course. No allowance
shall be given for materials placed outside the design limits shown on the cross-
sections. Trial sections shall not be measured separately but shall be included in
the quantity of Asphalt stabilized Road Mix Base Course.
(New or Salvaged)
Soil-Aggregate
and the lines, grades, thickness and typical cross-sections shown on the Plans or
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 58/437
Portland Cement shall not be applied during windy, rainy or impending bad
weather. In the event rain occurs, work shall be promptly stopped and the entire
section shall be reconstructed in accordance with this Specification.
A maximum time of 2 hours shall be permitted for wet mixing laydown and
in the quantities specified. Mixing shall continue until a uniform mixture has been
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 59/437
obtained.
5/7/2018
206.3.4 Spreading, Compacting and Finishing DPW H Blue Book - slide pdf.c om
The compaction and finishing shall be completed within 2 hours of the time
water is added to the mixture.
The rate of application shall be between 0.5 L/m 2 to 1.00 L/m2 of surface.
The exact rate will be determined by the Engineer. Curing seal will be applied in
sufficient quantity to provide a continuous film over the base. The film shall be
maintained at least 5 days unless the treated base is protected by a subsequent
course.
206.3.7 Tolerances
Same as Subsection 203.3.9.
206.3.8 Traffic
on the cross-sections. Trial sections shall not be measured separately but shall
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 60/437
be included in the quantity of Portland Cement Treated Plant Mix Base Course.
5/7/2018
206.5 Basis of Payment DPW H Blue Book - slide pdf.c om
(New or Salvaged)
Soil-Aggregate
207.1 Description
The aggregate shall conform to all requirements of the specified Item No.
of the Specifications.
300.1 Description
The coarse aggregate material retained on the 2.00 mm (No.10) sieve shall
have a mass percent of wear by the Los Angeles Test (AASHTO T 96) of not
more than 45.
When crushed aggregate is called for in the Bill of Quantities, not less than
fifty (50) mass percent of the particles retained on the 4.75 mm (No. 4) sieve shall
have at least one (1) fractured face.
Materials for gravel surface course and crushed aggregate surface course
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 63/437
shall have a soaked CBR Value of not less than 25% and 80% respectively as
determined by AASHTO T 193. The CBR Value shall be obtained at the maximum
5/7/2018
dry density and determined by AASHTO T 180, Method D.
DPW H Blue Book - slide pdf.c om
300.3.1 Placing
The aggregate surface course shall be laid to the designed level and
transverse slopes shown on the Plans. The allowable tolerances shall be as
specified hereunder:
will be given for material placed outside the design limits shown on the cross-
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 64/437
sections. Trial sections shall not be measured separately but shall be included in
the quantities as measured above.
5/7/2018 DPW H Blue Book - slide pdf.c om
301.1 Description
This Item shall consist of preparing and treating an aggregate base course
with material in accordance with the Plans and Specifications, preparatory to the
construction of a bituminous surface course.
301.3.2 Equipment
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 65/437
The liquid bituminous material shall be sprayed by means of a pressure
distributor of not less than 1000 liters capacity, mounted on pneumatic tires of
5/7/2018 DPW H Blue Book - slide pdf.c om
such width and number that the load produced on the road surface will not exceed
1 kN(100 kgf) per cm width of tire.
The tank shall have a heating device able to heat a complete charge of
bituminous liquid to 1800C. The heating device shall be such that overheating will
not occur. Consequently, the flames must not directly touch the casing of the
tank containing the bituminous liquid. The liquid shall be insulated in such a way
that the drop in temperature when the tank is filled with bituminous liquid at 1800C
0
and not heated will be less than 2 C per hour. A thermometer shall be fixed to
the tank in order to be able to measure continuously the temperature of the liquid.
The thermometer shall be placed in such a way that the highest temperature in
tank is measured. The tank shall be furnished with a calibrated dipstick to
indicate the contents. The pipes for filling the tank shall be furnished with an
easily changeable filter.
The distributor shall be able to vary the spray width of the bituminous liquid
in maximum
nozzles fromsteps
whichofthe
100liquid
mm tois asprayed
total width of 4 m. on
fan-shaped Thethe
spraying bar shall
road surface have
equally
distributed over the total spraying width.
For adding the liquid bituminous material, the distributor shall have a pump
either driven by a separate motor, or with a device to synchronize its speed with
the speed of the distributor. The pump shall be furnished with an indicator
showing the rate of flow. The suction side of the pump shall have an easily
changeable filter. A thermometer shall be fixed, such that it indicates the
temperature of the liquid immediately before it leaves the spraying bar.
that it will not be picked up by the wheels of passing vehicles. The Contractor
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 66/437
shall maintain the prime coat until the next course is applied. Care shall be taken
that the application of bituminous material is not in excess of the specified
amount, any excess shall be blotted with sand or removed as directed by the
5/7/2018 DPW H Blue Book - slide pdf.c om
Bituminous Prime Coat shall be measured by the tonne (t). The quantity to
be paid for shall be the number of tonnes of bituminous material applied and
accepted in the completed work.
including all labor, equipment, tools and incidentals necessary to complete this
Item.
302.1 Description
302.3.2 Equipment
Immediately before applying the tack coat, the full width of the surface to be
treated shall be cleaned of loose and foreign materials by means of a power
broom or power blower, supplemented as necessary by hand sweeping. Where
required by the Engineer, immediately prior to the application of the tack coat, the
surface shall be lightly sprayed with water but not saturated. Bituminous material
shall be applied by means of a pressure distributor at the temperature given in
Item 702, Bituminous Materials, of the particular material being used. The rate of
application of either the Rapid Curing Cut-back or the Emulsified Asphalt shall be
within the range of 0.2 to 0.7 litre/m2, the exact rate as determined by the
Engineer.
Traffic shall be kept off the tack coat at all times. The tack coat shall be
sprayed only so far in advance on the surface course as will permit it to dry to a
“tacky” condition. The Contractor shall maintain the tack coat until the next
course has been applied. Any area that has become fouled by traffic or
otherwise, shall be cleaned and resprayed at the Contractor’s expense before the
next course is applied.
The bituminous tack coat shall be measured by the tonne (t), completed
and accepted in-place.
The approximate amounts of materials per square metre for seal coats of
the several types shall be as provided in Table 303.1. The exact amounts to be
used shall be set by the Engineer.
Aggregate for Type 3 seal coat shall be crushed stone, crushed slag or
crushed gravel. Only one type of aggregate shall be used in a project unless
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 69/437
The aggregate shall have a mass percent of wear not exceeding 40 when
tested by AASHTO T 96.
When crushed slag is used, it shall be of uniform density and quality and
shall have a density of not less than 960 kg/m 3 (60 lb/cu. ft.) as determined by
AASHTO T 19.
Seal coating shall not be undertaken during foggy or rainy weather or when
the surface to be treated is wet. Wet cover coat material shall not be used on the
work. No seal coating work shall be continued at night unless provided with
sufficient lighting. The Engineer shall always be consulted before the
commencement of the work and all work shall be terminated at once in the event
of rain.
Seal coating operations shall not be started until the bituminous surface is
methods are authorized by the Engineer. Dried mud or other foreign material
which cannot be removed otherwise shall be removed by hand methods.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 70/437
303.3.3 Application of Bituminous Material
5/7/2018 DPW H Blue Book - slide pdf.c om
303.3.5 Maintenance
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 71/437
The Contractor shall be responsible for the maintenance of the surface until
the work is accepted by the Engineer. The maintenance work shall consist of
5/7/2018
keeping any excess aggregate evenly spread over the asphalt surface by
DPW H Blue Book - slide pdf.c om
304 1 D i ti
operations for single and double surface treatment shall be as provided in Table
304.1 and Table 304.2, whichever is called for in the Bill of Quantities.
The quantities given in the Tables are those of aggregates having a bulk
specific gravity of 2.65 as determined by AASHTO T 84 and T 85. Proportionate
corrections will be made when the aggregate furnished on the job has a bulk
specific gravity above 2.75 or below 2.55. In such case, the corrected amount
will be the
specific product
gravity of the quantity
of aggregate to 2.65.shown in the tables and the ratio of the bulk
The amounts given in the Tables are approximate and the exact amounts
will be set by the Engineer. Total amount of bituminous material per square
metre may be varied by the Engineer as necessary to fit conditions, but the total
amount of aggregate per square metre, after adjusting for specific gravity will not
be changed.
First Course:
Apply bituminous material, L/m 0.7 – 1.1 AC 1.6 – 2.0 AC
0.9 – 1.5 MC 1.8 – 2.3 MC
Spread Aggregate:
Grading A, kg/m2 22.0 – 27.0
Grading B, kg/m2 11.0 – 14.0
Second Course:
Apply bituminous material, L/m2 2.3 – 2.7 AC
2.8 – 3.5 MC
Spread Aggregate:2
Grading C, kg/m 11.0 – 14.0
First Course:
Apply bituminous material, L/m2 0.9 – 1.6 1.4 – 2.0
Spread Aggregate:
Grading A, kg/m2 14.0 – 19.0
Grading B, kg/m2 11.0 – 14.0
Second Course:
Apply bituminous material, L/m2 2.1 – 3.0
Spread Aggregate:
Grading C, kg/m2 5.0 – 8.0
304.2.3 Aggregates
The aggregate shall have a mass percent of wear not exceeding 40 when
tested by AASHTO T 96.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 74/437
When crushed gravel is used, not less than 50 mass percent of the
5/7/2018 particles retained on the 4.75 mm (No. 4) sieve shall have at least one fractured
DPW H Blue Book - slide pdf.c om
face.
When crushed slag is used, it must be of uniform density and quality and
shall have a density not less than 960 kg/m3 (60 lb/cu.ft.) as determined by
AASHTO T 19.
The Contractor shall provide weighing equipment on the Site to control the
application of aggregates. The weighing equipment shall have an approved
multiple beam type scale with indicator and other necessary dials for accurately
weighing the aggregate. The scale shall be protected by a weather-proof house
with a floor area not less than 10 m 2. The Contractor shall at his own expense
have the scale tested and approved by the Department of Public Works and
Highways.
304.3.2 Equipment
Spraying shall not be done unless the road temperature has been above
200C for at least one hour prior to the commencement of spraying operations, and
the temperature shall not be less than 200C during the spraying.
The application temperature for asphalt cement shall be within the range
that produces a viscosity of 10 to 60 second Saybolt Furol and for cut-back
asphalt shall be within the range given in Item 702, Bituminous Material. The
temperature shall be such that no fogging occurs.
The Contractor shall take all steps necessary to control traffic over newly-
laid bituminous surface treatment so that the surface is not damaged in any way.
Traffic shall be prohibited from traveling at speeds in excess of 40 km/h until the
asphaltic material has set. The Contractor shall ensure that no vehicles,
including those delivering aggregates, shall be permitted to turn around on newly-
laid material.
304
304 (1) Bituminous Surface Treatment
Aggregate Grading Tonne
Tonne
304 (2) Asphalt Cement Pen. Grade Tonne
304 (3) RC ___ Cut-back Asphalt Tonne
304 (4) MC ___ Cut-back Asphalt Tonne
304 (5) Emulsified Asphalt Tonne
305.1 Description
This Item shall consist of furnishing and placing one or more courses of
graded aggregate and one or more application of bituminous material, followed by
a seal coat with cover aggregate constructed on a prepared base in accordance
with this Specifications and in conformity with the lines, grades and typical cross-
sections shown on the Plans.
The weights given in the Table are those of aggregates having a bulk
specific gravity of 2.65 as determined by AASHTO T 84 and T 85. Proportionate
corrections will be made when the aggregates furnished on the job have a bulk
aggregate per square metre, after adjusting for specific gravity will not be
changed.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 77/437
Second Layer:
Spread Aggregate:
Key Aggregate, kg/m2 13 10
Apply bituminous material, L/m2 1.8 3.5
Third Layer:
Spread Aggregate:
Key Aggregate, kg/m2 11 8
Apply bituminous material, L/m2 1.4 2
Fourth Layer:
Spread Aggregate:
Cover Aggregate, kg/m2 8 8
Total Quantities:
Bituminous Material, L/m2 7.2 11
Aggregate, kg/m2 122 126
Quantities.
Materials. The It Penetration
shall conform to the
Grade requirements
Number of asphaltofcement
Item 702, Bituminous
and type and/or
grade of cut-back or emulsified asphalt will be specified in the Special Provisions.
305.2.3 Aggregate
63 2 – 1/2” 100 - - -
50 2” 90 – 100 - - -
37.5 1 – 1/2” 35 – 70 - - -
25 1” 0 – 15 - 100 -
19 ¾” - 100 90 – 100 -
12.5 ½” 0–5 90 – 100 20 – 55 100
9.5 3/8” - 40 – 70 0 – 15 85 – 100
4.75 No. 4 - 0 – 15 0–5 10 – 30
2.36 No. 8 - 0–5 - 0 – 10
1.18 No. 16 - - - 0–5
The aggregate shall have a mass percent of wear not exceeding 40 when
tested by AASHTO T 96.
When the crushed gravel is subjected to five cycles of the sodium sulfate
soundness test (AASHTO T 104), the weighted loss shall not exceed 12 mass
percent.
When crushed slag is used, it must be of uniform density and quality and
shall have a density not less than 1120 kg/m3 (70 lb/cu. ft.) as determined by
AASHTO T 19.
305.3.2 Equipment
Before spreading the aggregate, the base shall be cleaned of all loose
foreign materials. The existing base shall be swept until the embedded large
aggregate is exposed, or in the case of a previously constructed asphalt surface,
until the surface is free of mud or other covering.
If shown on the Plans and called for in the Bill of Quantities, a prime coat
shall be applied
Bituminous Primeto Coat,
the prepared untreated
or in case base in constructed
of previously accordance asphalt
with theor
Item 301,
cement
surface tack coat shall be applied in accordance with Item 302, Bituminous Tack
Coat.
Materials
segregated which
in such are crushed
a manner excessively
as to prevent under
free and the roller
uniform or becomes
penetration of the
bituminous material shall be removed and replaced with suitable aggregate. The
compacted aggregate shall have a firm and even surface.
Aggregate in any layer that becomes coated or mixed with dirt or clay prior
to the application of the bituminous material shall be removed and replace with
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 80/437
Each
covered layer
before of aggregate
wheels or tracksshall
passbe spread
over it. so that the bituminous material is
The distributors shall not be cleaned or discharged into ditches, borrow pits
or shoulders along the right-of-way.
306.1 Description
306.2.2 Aggregate
2. Salvaged Aggregate
already in place, the Contractor shall not be responsible for its grading
or quality except
aggregate to be for removal
used of oversize
for road pieces.course
mix surface In general, salvaged
will consist of
5/7/2018 DPW H Blue Book - slide pdf.c om
materials meeting the requirements given in Item 703, Aggregates, for
new aggregate or may consist of selected granular material for other
gradings. Any particles of salvaged aggregate appearing in the
surface at the time of lay-down and finishing that will not pass 37.5
mm (1-1/2 inch) sieve shall be removed by the Contractor as directed
by the Engineer.
During the mixing operation, one-half to one (0.5 to 1.0) mass percent of
hydrated lime, dry aggregate basis, shall be added to the mixture. The lower
percentage limit is applicable to aggregates which are predominantly calcareous.
When new aggregate is to be used for the road mix surface course,
the existing base shall be scarified lightly and bladed to uniform grade
and to the cross-section shown on the Plans and shall then be rolled or
watered and rolled, as directed. If so ordered by the Engineer,
depressions shall first be filled and weak portions of the base
strengthened with new aggregate.
In lieu of aerating and drying the aggregate, the Contractor may use an
approved additive, except where emulsified asphalt is used, which shall be
satisfactorily blended with the bituminous material. The additive shall permit
suitable coating of the wet aggregate and shall prevent the bituminous coating
from stripping in the presence of water.
306.3.6 Mixing
After the last application of bituminous material and partial mixing, the
entire mass of bituminous material and aggregate shall be windrowed on the road
surface and then mixed, by blading the mixture from side to side of the road, or by
manipulation producing equivalent results, until all aggregate particles are coated
with bituminous material and the whole mass has a uniform color and the mixture
is free from fat or lean spots, or balls of uncoated particles. During the mixing
operations, care shall be taken to avoid cutting into the underlying course or
contaminating the mixture with earth or other extraneous matter. When directed,
the mixing process shall be confined to part of the width or area of the road so as
to allow traffic to pass.
otherwise manipulated
The spreading of the mixuntil thenotmoisture
shall be doneand volatile
when content
the surface to are satisfactory.
be covered is in
an unsatisfactory condition. At the end of each day’s work, or when the work is
interrupted by weather conditions or otherwise, all loose materials shall be bladed
into a windrow, whether mixing is completed or not, and shall be retained in a
After the material is spread, the surface shall be rolled. Rolling shall be
parallel to the road center line and shall commence at the outer edges of the road,
overlapping the shoulders and progressing towards the center, overlapping on
successive passes by at least one-half the width of the roller, except that on
superelevated curves, rolling shall progress from the lower to the upper edge.
Each pass shall terminate at least 910 mm (3 ft) in advance or to the rear of
the end of the preceding pass. During compaction, the surface shall be dragged
or bladed as necessary to fill ruts and to remove incipient corrugations or other
irregularities. Rolling shall continue until the surfacing is of uniform texture and
satisfactory compaction is obtained. Initial rolling shall be performed with a
pneumatic-tire roller and final rolling with a 3-wheel or tandem type steel wheel
roller. Rolling shall be discontinued whenever it begins to produce excessive
pulverizing of the aggregate or displacement of the mixture.
When the compacted thickness of the road mix surface is to be more than
50 mm (2 inches), the mixture shall be spread from the windrow and compacted in
two layers, the first layer to be bladed and rolled before the second layer is
spread.
While the surface is being compacted and finished, the Contractor shall
trim the edges neatly to line.
CourseBituminous material
will be measured andtonne
by the aggregate forquantity
(t). The Bituminous RoadforMix
to be paid shallSurface
be the
number of tonnes of bituminous material and aggregate used and accepted in the
completed work. The weight of all moisture in the aggregate will be deducted
from the pay quantity.
307.1 Description
This item includes general requirements that are applicable to all types of
bituminous plant mix surface courses irrespective of gradation of aggregate or
kind and amount of bituminous material. Derivations from these general
requirements will be indicated in the specific requirements for each type.
Each job-mix formula submitted shall propose definite single values for:
After the job-mix is established, all mixture furnished for the project shall
conform thereto within the following ranges of tolerances:
The mixture shall have a minimum compressive strength of 1.4 MPa (200
psi).
The mixture shall have a mass percent air voids with the range of 3 to 5.
The mixture shall also have an index of retained strength of not less than
70 when tested by AASHTO T 165. For aggregates having maximum sizes
over 25 mm (1 inch), AASHTO T 165 will be modified to use 150 mm x 150 mm (
6 x 6 inches) cylindrical specimens. The 150 mm (6 inches cylinders will be
compacted by the procedures outlined in AASHTO T 167 modified to employ 10
repetitions of a molding load of 9.6 MPa (1400 psi), with no appreciable holding
time after each application of the full load.
Hydrated lime shall be added to the mixture during the mixing operation in
the amount of one-half to one (0.5 to 1.0) mass percent, dry aggregate basis.
The lower percentage limit is applicable to aggregates which are predominantly
calcareous.
Bituminous Plant mix shall not be placed on any wet surface, or when
weather conditions would prevent the proper handling or finishing of the
bituminous mixtures.
Sufficient storage space shall be provided for each size of aggregate. The
different aggregate sizes shall be kept separated until they have been delivered to
the cold elevator feeding the drier. The storage yard shall be maintained neat
and orderly and the separate stockpiles shall be readily accessible for sampling.
Plants used for the preparation of bituminous mixtures shall conform to the
requirements for all plants under (a) below except that scale requirements shall
apply only where weight proportioning is used. In addition, batch mixing plants
and continuous mixing plants shall conform to the respective requirements which
follow this Subsection.
the bituminous material bucket throughout the dry and wet mixing
periods. The dry mixing period is defined as the interval of time
between the opening of the weigh box gate and the start of
5/7/2018
introduction of bituminous material. The wet mixing period is the
DPW H Blue Book - slide pdf.c om
The control of the timing shall be flexible and capable of being set
at intervals of 5 seconds or less throughout a total cycle of up to 3
minutes. A mechanical batch counter shall be installed as a part of
the timing device and shall be so designed as to register only
completely mixed batches.
type, adequately
within the job-mixheated and capable
tolerances. It shallofbeproducing
equippeda with
uniform mixture
a discharge
within the job mix tolerances. It shall be equipped with a discharge
hopper with dump gates which will permit rapid and complete
5/7/2018
discharge of the mixture. The paddles shall be adjustable for angular
DPW H Blue Book - slide pdf.c om
position on the shafts and reversible to retard the flow of the mix.
The mixer shall have a manufacturer’s plate giving the net volumetric
contents of the mixer of the several heights inscribed on a permanent
gauge. Charts shall be provided showing the rate of feed or
aggregate per minute for the aggregate being used.
2. Hauling Equipment
Trucks used for hauling bituminous mixtures shall have tight, clean, smooth
metal beds which have been thinly coated with approved material to prevent the
mixture from adhering to the beds. Each truck shall have a cover of canvass or
other suitable material of such size as to protect the mixture from the weather.
When necessary, such that the mixture will be delivered on the road at the
specified temperature, truck beds shall be insulated and covers shall be securely
fastened.
3. Bituminous Pavers
The Contractor shall furnish the long ski, the short ski or shoe and furnish
and install all required stakes and wire for a taut stringline.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 94/437
Should the automatic control systems become inoperative during the day’s
work, the Contractor will be permitted to finish the day’s work using manual
5/7/2018 controls, however, work shall not be resumed thereafter until the automatic control
DPW H Blue Book - slide pdf.c om
The Contractor shall provide and have ready for use at all times enough
covers, as may be necessary, for use in any emergency such as rain, chilling
wind, on unavoidable delay, for the purpose of covering or protecting any material
that may have been dumped and not spread.
4. Rollers
The equipment shall be of the steel and/or pneumatic tire type and shall be
in good condition, capable of reversing without backlash, and shall be operated at
speeds slow enough to avoid displacement of the bituminous mixture. The
number and weight of rollers shall be sufficient to compact the mixture to the
required density while it is still in a workable condition. The use of equipment
which results in excessive crushing of the aggregate will not be permitted.
properly adjusted to avoid damage to the aggregate and to avoid soot on the
aggregate. Moisture content of the mixture from drum dryer plants shall not
exceed three (3) percent of the output, as determined by AASHTO T 110.
307.3.6 Mixing
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 95/437
The dried aggregates and the bituminous material shall be measured or
5/7/2018 gauged and introduced into the mixer in the amount specified by the job mix
DPW H Blue Book - slide pdf.c om
formula.
The mixture shall be spread and struck off to the grade and elevation
established. Bituminous pavers shall be used to distribute the mixture either over
the entire width or over such partial width as may be practicable.
The longitudinal joint in one layer shall offset that in the layer immediately
below approximately 15 cm (6 inches); however, the joint in the top layer shall be
at the center line of the pavement if the roadway comprises two (2) lanes, or at
lane lines if the roadway is more than two (2) lanes, unless otherwise directed.
The mixture shall be placed at a temperature not less than 1070C (2250F)
as measured in the truck just prior to dumping into the spreader.
When tar is used, the mixture shall be placed at between 660C and 1070C
(150 F and 2250F).
0
307.3.8 Compaction
Immediately after the mixture has been spread, struck off and surface
lane, the longitudinal joint should be rolled first followed by the regular rolling
procedure. On superelevated curves, the rolling shall begin at the low side and
progress to the high side overlapping of longitudinal trips parallel to the center
line.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 96/437
Rollers shall move at a slow but uniform speed with the drive roll or wheels
nearest the paver.. Rolling shall be continued until roller marks are eliminated
5/7/2018 and a minimum of 97 mass percent of the density of the laboratory compacted
DPW H Blue Book - slide pdf.c om
To prevent adhesion of the mixture to the rollers, the wheels shall be kept
properly moistened with water or water mixed with very small quantities of
detergent or other approved material. Excess liquid will not be permitted.
Along forms, curbs, headers, walls and other places not accessible to the
rollers, the mixture shall be thoroughly compacted with hot hand tampers,
smoothing irons or with mechanical tampers.
307.3.9 Joints
Engineer,
transverseajoints
brushbefore
coat ofadditional
bituminous material
mixture shall beagainst
is placed used onthe
contact surfaces
previously of
rolled
material.
The contractor shall cut full depth samples as directed, from the finished
pavement, for testing. Samples shall be neatly cut by saw or core drill. Each
sample shall be at least 150 mm x 150 mm or 100 mm diameter full depth. At
least one, but not more than three samples shall be taken for each full day’s
operation. If no core samples were taken during the day’s operation, core samples
shall be taken from the completed pavement for every 100 L. M. per lane. The
contractor shall supply and furnish new material to backfill boreholes left by the
The compacted pavement shall have a density equal to, or greater than 97
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 97/437
If the deficiency in the core thickness is more than 5 mm, additional layer
may be permitted in order to meet the designed thickness, however, the minimum
additional asphalt overlay thickness should be dependent on the minimum
thickness capacity of asphalt paver but it should not be less than 50 mm (2
inches) and that proper construction procedures are followed.
The variation of the surface from the testing edge of the straight-edge
between any two contacts with the surface shall not exceed 6 mm.
Tests will be made immediately after initial compaction and any variations
detected shall be corrected by removing or adding materials, as may be
necessary. Rolling shall then be continued as specified. After final rolling, the
smoothness of the course shall be checked again and any area defective in
texture or composition shall be corrected, including removal and replacement of
unsatisfactory material at the Contractor’s expense as directed by the Engineer.
The area to be paid for under this item shall be the number of square
meters (m2) of asphalt pavement placed, compacted and accepted based on the
308.1 Description
Cold Mix) prepared in central mixing plant, laid cold, on the prepared base in
accordance with this Specification and in conformity with the lines, grades and
5/7/2018
typical cross-section shown on the Plans. DPW H Blue Book - slide pdf.c om
The asphalt cold mix shall be composed of coarse mineral aggregates, fine
mineral aggregates, mineral fillers and chemically bonding bitumen.
Each job-mix formula submitted shall propose definite single value for:
1. The percentage of coarse mineral aggregates passing each specified sieve
size.
Stability Requirements:
Cold Asphalt Plant Mix shall be placed only when the specified density can
be obtained. The mixture shall not be placed on any wet surface or when weather
condition will prevent its proper handling or finishing. Asphalt surface mixture
shall not be placed when the surface temperature of the base course is below
100C (500F).
should be entirely absorbed by the base course and the prime should be
fully set and cured before placing the surface.
5. Immediately prior to application of the asphalt tack coat all loose and
foreign material shall be removed by sweeping or by blowing, or both.
through separate bins to cold elevator feeders. They shall not be blended in
the stockpile.
3. Cold aggregates shall be fed carefully to the plant so that surpluses and
shortages will not occur and cause breaks in the continuous operation.
4. Mixing time shall be the shortest time that will produce a satisfactory
mixture.
The base course mixture shall be placed in one or more lifts with an asphalt
paver or spreader to provide a nominal compacted thickness of the base course.
The mix shall be compacted immediately after placing. Initial rolling with a
steel-wheeled tandem or three wheeled roller, vibratory roller, or a pneumatic-tired
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 101/437
roller shall follow the paver as closely as possible. If needed, intermediate rolling
with a pneumatic tired roller shall be done immediately behind the initial rolling. An
application of choke aggregate may be necessary to prevent mix pick-up by the
5/7/2018
pneumatic-tired roller. Final rolling shall eliminate marks from previous rolling. In
DPW H Blue Book - slide pdf.c om
areas too small for the roller a vibrating plate compactor or a hand-tamper shall be
used to achieve thorough compaction.
308.3.6 Safety
Safety precautions shall be used at all times during the progress of the
work. As appropriate, workmen shall be furnished with hard hats, safety shoes,
respirators, and any other safety apparel that will reduce the possibility of injury
from accidents. All Occupational Safety and Health Act requirements shall be
observed.
Divide asphalt mixture production into lots, each lot equal to the mix
produced during one day. Determine the target density for each lot by measuring
the average density of six laboratory prepared specimens representing two
randomly chosen subsamples from trucks delivering mixture to the jobsite. The
target density should be reported as dry density.
Determine the compacted density in the field from five randomly located
positions in each lot of the compacted mixture. The density of freshly compacted
material can be determined using a properly calibrated nuclear density device or
other procedure. Density determinations made after a period of curing may be
determined on samples obtained from compacted material by a suitable core
drilling technique. All compacted densities should be converted to dry densities. It
is recommended that the average of five field density determinations made in
each lot be equal to or greater than 97 percent of the average density of the six
laboratory prepared specimens, and that no individual determination be lower than
95 percent.
308.4.1 Equipment
1. Asphalt mixing plants designed to produce a uniform mix within the job-mix
tolerances.
5/7/2018 DPW H Blue Book - slide pdf.c om
308.5 Sampling
308.6 Testing
Laid, which price and payment shall be full compensation for furnishing all
materials, handling, placing, rolling, compacting, labor, equipment, tools and
5/7/2018 incidentals necessary to complete this Item. DPW H Blue Book - slide pdf.c om
309.1 Description
mixed in a central
maintenance needs. plant. The mixture is stockpiled for immediate or future
The type and grade of bituminous material shall be in accordance with the
following guidelines:
309.2.3 Aggregate
Table 309.1.
5/7/2018 The combined aggregate after going through the drier, shall have a sand
DPW H Blue Book - slide pdf.c om
The coarse aggregate shall have a mass percent of wear not exceeding 40
when tested by AASHTO T 96.
Slag, if used, shall weigh not less than 1120 kg/m3 (70 lb/cu. ft.).
Sieve Designation
Standard, mm Alternate U.S. Standard Mass Percent Passing
19.0 ¾ in 100
12.5 ½ in 80 – 100
9.5 3/8 in 70 – 90
4.75 No. 4 50 – 70
2.36 No. 8 35 – 50
0.60 No. 30 18 – 30
0.30 No. 50 15 – 25
0.15 No. 100 8 – 15
0.075 No. 200 4 - 10
SurfaceIt Course
shall conform to the requirements of Item 307, Bituminous Plant Mix
– General.
The aggregate, mineral filler, and hydrated lime shall be fed into the plant in
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 105/437
specified by the Engineer. Mixing shall be thorough and shall continue until all
aggregate particles are well coated.
309.3.2 Stockpiling
The area to be paid for under this item shall be the number of square
meters (m2) of asphalt pavement placed, compacted and accepted based on the
thickness and density of the cores taken in accordance with subsection 307.3.10
(Acceptance, Sampling and Testing).
309.5 Basis of Payment
this Specification and in conformity with lines, grades, thickness and typical cross-
section shown on the Plans.
310.2.3 Aggregates
During the mixing operation, one-half to one (0.5 to 1.0) mass percent of
hydrated lime, dry aggregate basis, shall be added to the mixture. The lower
percentage limit is applicable to aggregates which are predominantly calcareous.
The area to be paid for under this item shall be the number of square
meters (m2) of asphalt pavement placed, compacted and accepted based on the
thickness and density of the cores taken in accordance with subsection 307.3.10
(Acceptance, Sampling and Testing).
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 107/437
310.5 Basis of Payment
5/7/2018 DPW H Blue Book - slide pdf.c om
The accepted quantity, measured as prescribed in Section 310.4, shall be
paid for at the contract unit price for Bituminous Concrete Surface Course, Hot-
Laid, which price and payment shall be full compensation for furnishing all
materials, handling, mixing, hauling, placing, rolling, compacting, labor,
equipment, tools and incidentals necessary to complete this Item.
Payment will be made under:
311.1 Description
Cement which for any reason, has become partially set or which contains
lumps of caked cement will be rejected. Cement salvaged from discarded or
used bags shall not be used.
It shall not contain more than three (3) mass percent of material passing
the 0.075 mm (No. 200 sieve) by washing nor more than one (1) mass percent
each of clay lumps or shale. The use of beach sand will not be allowed without
the approval of the Engineer.
If the fine aggregate is subjected to five (5) cycles of the sodium sulfate
soundness test, the weighted loss shall not exceed 10 mass percent.
The fine aggregate shall be well-graded from coarse to fine and shall
conform to Table 311.1
It shall contain not more than one (1) mass percent of material passing the
0.075 mm (No. 200) sieve, not more than 0.25 mass percent of clay lumps, nor
more than 3.5 mass percent of soft fragments.
If the coarse aggregate is subjected to five (5) cycles of the sodium sulfate
soundness test, the weighted loss shall not exceed 12 mass percent.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 109/437
It shall have a mass percent of wear not exceeding 40 when tested by
AASHTO T 96.
5/7/2018 DPW H Blue Book - slide pdf.c om
If the slag is used, its density shall not be less than 1120 kg/m3 (70 lb./cu.
ft.). The gradation of the coarse aggregate shall conform to Table 311.2.
Only one grading specification shall be used from any one source.
Table 311.2 – Grading Requirement for Coarse Aggregate
75.00 Standard
3 in. 100 - -
63.00 2-1/2 in. 90-100 100 100
50.00 2 in. - 90-100 95-100
37.5 1-1/2 in. 25-60 35-70 -
25.0 1 in. - 0-15 35-70
19.0 ¾ in. 0-10 - -
12.5 ½ in. 0-5 0-5 10-30
4.75 No. 4 - - 0-5
311.2.4 Water
The sleeves for dowel bars shall be metal of approved design to cover 50
mm ( 2 inches), plus or minus 5 mm (1/4 inch) of the dowel, with a closed end,
and with a suitable stop to hold the end of the sleeve at least 25 mm (1 inch) from
the end of the dowel. Sleeves shall be of such design that they do not collapse
during construction.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 110/437
311.2.6 Joint Fillers
Poured joint fillers shall be mixed asphalt and mineral or rubber filler
5/7/2018
conforming to the applicable requirements of Item 705, Joint Materials.
DPW H Blue Book - slide pdf.c om
311.2.7 Admixtures
Chemical
requirements admixtures,
of AASHTO if specified or permitted, shall conform to the
M 194.
to allow the earliest deliveries to be used first and to provide easy access for
identification and inspection of each shipment. Storage buildings shall have
5/7/2018 capacity for storage of a sufficient quantity of cement to allow sampling at least
DPW H Blue Book - slide pdf.c om
twelve (12) days before the cement is to be used. Bulk cement, if used, shall be
transferred to elevated air tight and weatherproof bins. Stored cement shall meet
the test requirements at any time after storage when retest is ordered by the
Engineer. At the time of use, all cement shall be free-flowing and free of lumps.
The handling and storing of concrete aggregates shall be such as to
prevent segregation or the inclusion of foreign materials. The Engineer may
require that aggregates be stored on separate platforms at satisfactory locations.
In order to secure greater uniformity of concrete mix, the Engineer may
require that the coarse aggregate be separated into two or more sizes. Different
sizes of aggregate shall be stored in separate bins or in separate stockpiles
sufficiently
piles removed intermixed.
from becoming from each other to prevent the material at the edges of the
The Contractor shall prepare the design mix based on the absolute volume
method as outlined in the American Concrete Institute (ACI) Standard 211.1,
“Recommended Practice for Selecting Proportions for Normal and Heavyweight
Concrete”.
The mix design shall be submitted to the Engineer for approval and shall be
accompanied with certified test data from an approved laboratory demonstrating
the adequacy of the mix design. A change in the source of materials during the
progress of work may necessitate a new design mix.
provided
requested,free access tocopies
informational recent plantdesign,
of mix production records,
materials and if
certifications
and sampling and testing reports.
3. Qualification of Workmen
5. Documentation
The Contractor shall maintain adequate records of all inspections
and tests. The records shall indicate the nature and number of
observations made, the number and type of deficiencies found, the
quantities approved and rejected, and nature of any corrective action
taken.
The location
random Engineerfor may take independent
acceptance assurance
purposes as he samples at
deems necessary.
311.3.2 Equipment
Equipment and tools necessary for handling materials and performing all
parts of the work shall be approved by the Engineer as to design, capacity and
mechanical condition. The equipment shall be at the jobsite sufficiently ahead of
the start of construction operations to be examined thoroughly and approved.
2. Mixers.
c. Truck Mixer and Truck Agitators. Truck mixers used for mixing
and hauling concrete, and truck agitators used for hauling
central-mixed concrete, shall conform to the requirements of
AASHTO M 157.
5. Forms
After the subgrade of base has been placed and compacted to the required
density, the areas which will support the paving machine and the grade on which
the pavement is to be constructed shall be trimmed to the proper elevation by
means of a properly designed machine extending the prepared work areas
compacted at least 60 cm beyond each edge of the proposed concrete pavement.
If loss of density results from the trimming operations, it shall be restored by
additional compaction before concrete is placed. If any traffic is allowed to use
1. Base Support.
The foundation under the forms shall be hard and true to grade so
that the form when set will be firmly in contact for its whole length and
at the specified grade. (Any roadbed, which at the form line is found
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 116/437
2. Form Setting
When any form has been disturbed or any grade has become
unstable, the form shall be reset and rechecked.
When side forms have been securely set to grade, the subgrade or base
course shall be brought to proper cross-section. High areas shall be trimmed to
proper elevation. Low areas shall be filled and compacted to a condition similar
to that of surrounding grade. The finished grade shall be maintained in a smooth
and compacted condition until the pavement is placed.
Unless waterproof subgrade or base course cover material is specified, the
subgrade or base course shall be uniformly moist when the concrete is placed. If
Stockpiles shall be built up in layers of not more than one (1) meter in thickness.
Each layer shall be completely in place before beginning the next which shall not
be allowed to “cone” down over the next lower layer. Aggregates from different
sources and of different grading shall not be stockpiled together.
When mixed at the site or in a central mixing plant, the mixing time shall not
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 118/437
be less than fifty (50) seconds nor more than ninety (90) seconds, unless mixer
performance tests prove adequate mixing of the concrete is a shorter time period.
5/7/2018
Four (4) seconds shall be added to the specified mixing time if timing starts
DPW H Blue Book - slide pdf.c om
at the instant the skip reaches its maximum raised positions. Mixing time ends
when the discharge chute opens. Transfer time in multiple drum mixers is
included in mixing
removed before time. The
a succeeding contents
batch of an
is emptied individual mixer drum shall be
therein.
The batches shall be so charged into the drum that a portion of the mixing
water shall be entered in advance of the cement and aggregates. The flow of
water shall be uniform and all water shall be in the drum by the end of the first
fifteen (15) seconds of the mixing period. The throat of the drum shall be kept
free of such accumulations as may restrict the free flow of materials into the drum.
Mixed concrete from the central mixing plant shall be transported in truck
mixers, truck agitators or non-agitating truck specified in Subsection 311.3.2,
Equipment. The time elapsed from the time water is added to the mix until the
concrete is deposited in place at the Site shall not exceed forty five (45) minutes
when the concrete is hauled in non-agitating trucks, nor ninety (90) minutes when
hauled in truck mixers or truck agitators, except that in hot weather or under other
conditions contributing to quick hardening of the concrete, the maximum allowable
time may be reduced by the Engineer.
No concrete
insufficient, unless shall be mixed,
an adequate placed
and or finished
approved artificialwhen natural
lighting light is
system is
operated.
During hot weather, the Engineer shall require that steps be taken to
prevent the temperature of mixed concrete from exceeding a maximum
temperature of 900F ( 320C)
Concrete not in place within ninety (90) minutes from the time the
ingredients were charged into the mixing drum or that has developed initial set
shall not be used. Retempering of concrete or mortar which has partially
hardened, that is remixing with or without additional cement, aggregate, or water,
shall not be permitted.
In order that the concrete may be properly protected against the effects of
rain before the concrete is sufficiently hardened, the Contractor will be required to
have available at all times materials for the protection of the edges and surface of
the unhardened concrete.
discharge bucket or hopper into a joint assembly unless the hopper is well
centered on the joint assembly. Should any concrete material fall on or be
5/7/2018 worked into the surface of a complete slab, it shall be removed immediately.
DPW H Blue Book - slide pdf.c om
As work progresses, at least one (1) set consisting of three (3) concrete
beam test specimens, 150 mm x 150 mm x 525 mm or 900 mm shall be taken
from each 330 m2 of pavement, 230 mm depth, or fraction thereof placed each
day. Test specimens shall be made under the supervision of the Engineer, and
the Contractor shall provide all concrete and other facilities necessary in making
the test specimens and shall protect them from damage by construction
operations. Cylinder samples shall not be used as substitute for determining the
adequacy of the strength of concrete.
The beams shall be made, cured, and tested in accordance with AASHTO
T 23 and T 97.
Following the placing of the concrete, it shall be struck off to conform to the
cross-section shown on the Plans and to an elevation such that when the concrete
is properly consolidated and finished, the surface of the pavement will be at the
elevation shown on the Plans. When reinforced concrete pavement is placed in
two (2) layers, the bottom layer shall be struck off and consolidated to such length
and depth that the sheet of fabric or bar mat may be laid full length on the
concrete in its final position without further manipulation. The reinforcement shall
then be placed directly upon the concrete, after which the top layer of the concrete
shall be placed, struck off and screeded. Any portion of the bottom layer of
concrete which has been placed more then 30 minutes without being covered with
the top layer shall be removed and replaced with freshly mixed concrete at the
Contractor’s expense. When reinforced concrete is placed in one layer, the
reinforcement may be firmly positioned in advance of concrete placement or it
may be placed at the depth shown on the Plans in plastic concrete, after
311.3.12 Joints
Joints shall be constructed of the type and dimensions, and at the locations
required by the Plans or Special Provisions. All joints shall be protected from the
intrusion of injurious foreign material until sealed.
1. Longitudinal Joint
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 121/437
enclosed in tubes
adjacent lanes of or sleeves. are
pavement When shown on
constructed the Plans steel
separately, and when
side
forms shall be used which will form a keyway along the construction
joint. Tie bars, except those made of rail steel, may be bent at right
angles against the form of the first lane constructed and straightened
into final position before the concrete of the adjacent lane is placed, or
in lieu of bent tie bars, approved two-piece connectors may be used.
shall not deviate more than 6 mm from a straight line. If joint fillers
are assembled in sections, there shall be no offsets between adjacent
5/7/2018
units. No plugs of concrete shall be permitted anywhere within the
DPW H Blue Book - slide pdf.c om
expansion space.
concrete from the last preceding joint shall be removed and disposed
off as directed.
5/7/2018 DPW H Blue Book - slide pdf.c om
andDowel,
centerwhen
line used,
of theshall
slabbebyheld in position
a metal parallel
device that to
is the
left surface
in the
pavement.
The portion of each dowel painted with one coat of lead or tar, in
conformance with the requirements of Item 404, Reinforcing Steel,
shall be thoroughly coated with approved bituminous materials, e.g.,
MC-70, or an approved lubricant, to prevent the concrete from binding
to that portion of the dowel. The sleeves for dowels shall be metal
designed to cover 50 mm plus or minus 5 mm (1/4 inch), of the dowel,
with a watertight closed end and with a suitable stop to hold the end of
the sleeves at least 25 mm (1 inch) from the end of the dowel.
1. Sequence
under and around all load transfer devices, joint assembly units, and
other features designed to extend into the pavement. Concrete
adjacent to joints shall be mechanically vibrated as required in
Subsection 311.3.9, Placing Concrete.
After the concrete has been placed and vibrated adjacent to the
joints as required in Subsection 311.3.9, the finishing machine shall
be brought forward, operating in a manner to avoid damage or
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 124/437
fromdirectly
set in frontonoftop
andofoff
thethejoint
joint.
and The front screed
the forward shall
motion of be
the lifted and
finishing
machine resumed. When the second screed is close enough to permit
the excess mortar in front of it to flow over the joint, it shall be lifted
and carried over the joint. Thereafter, the finishing machine may be
run over the joint without lifting the screeds, provided there is no
segregated concrete immediately between the joint and the screed or
on top of the joint.
3. Machine Finishing
4. Hand Finishing
the grade.
b. In narrow widths or areas of irregular dimensions where
5/7/2018 DPW H Blue Book - slide pdf.c om
operations of the mechanical equipment is impractical, hand
methods may be used.
5. Floating
After the concrete has been struck off and consolidated, it shall be
further smoothed,
float, either trued,
by hand and consolidated
or mechanical method. by means of a longitudinal
not more than one-half the length of the float. Any excess water
or soupy material shall be wasted over the side forms on each
pass.
After the floating has been completed and the excess water
successive stages of not more than one-half the length of the straight-
edge. Any depressions found shall be immediately filled with freshly
mixed concrete, struck off, consolidated and refinished. High areas
shall be cut down and refinished. Special attention shall be given to
assure that the surface across joints meets the requirements for
smoothness. Straight-edge testing and surface corrections shall
continue until the entire surface is found to be free from observable
departures from the straight-edge and the slab conforms to the
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 127/437
required grade and cross-section.
7. Final Finish
5/7/2018 DPW H Blue Book - slide pdf.c om
waterthe
from sheen hastopractically
center the edgedisappeared. The broom
of the pavement shall bestrokes
with adjacent drawn
slightly overlapping. The brooming operation should be so executed
that the corrugations produced in the surface shall be uniform in
appearance and not more than 1.5 mm in depth. Brooming shall be
completed before the concrete is in such condition that the surface will
be unduly roughened by the operation. The surface thus finished shall
be free from rough and porous areas, irregularities, and depressions
resulting from improper handling of the broom. Brooms shall be of the
quality size and construction and be operated so as to produce a
surface finish meeting the approval of the Engineer. Subject to
satisfactory results being obtained and approval of the Engineer, the
Contractor will be permitted to substitute mechanical brooming in lieu
of the manual brooming herein described.
the edges of the pavement along each side of each slab, and on each
side of transverse expansion joints, formed joints, transverse
construction joints, and emergency construction joints, shall be
worked with an approved tool and rounded to the radius required by
the Plans. A well – defined and continuous radius shall be produced
and a smooth, dense mortar finish obtained. The surface of the slab
shall not be unduly disturbed by tilting the tool during the use.
At all joints, any tool marks appearing on the slab adjacent to the
joints shall be eliminated by brooming the surface. In doing this, the
rounding of the corner of the slab shall not be disturbed. All concrete
on top of the joint filler shall be completely removed.
to provide sufficient cover material of whatever kind the Contractor may elect to
use, or the lack of water to adequately take care of both curing and other
requirements, shall be a cause for immediate suspension of concreting
operations. The concrete shall not be left exposed for more than ½ hour between
stages of curing or during the curing period.
The mats used shall be of such length (or width) that as laid they will
extend at least twice the thickness of the pavement beyond the edges
of the slab. The mat shall be placed so that the entire surface and the
edges of the slab are completely covered. Prior to being placed, the
mats shall be saturated thoroughly with water. The mat shall be so
placed and weighted down so as to cause them to remain in intimate
contact with the covered surface. The mat shall be maintained fully
wetted and in position for 72 hours after the concrete has been placed
unless otherwise specified.
2. Waterproof Paper
3. Straw Curing
down during the morning of the fourth day, and the cover shall remain
in place until the concrete has attained the required strength.
Thepigmented
white entire surface of the
curing pavement
compound shall be sprayed
immediately uniformly
after the with
finishing of
the surface and before the set of the concrete has taken place, or if
the pavement is cured initially with jute or cotton mats, it may be
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 130/437
applied upon removal of the mass. The curing compound shall not
be applied during rain.
5/7/2018 DPW H Blue Book - slide pdf.c om
shall be maintained in place for 72 hours after the concrete has been
placed.
expense of the Contractor. Any area or section so removed shall not be less than
the distance between weakened plane joint nor less than the full width of the lane
involved.
Joints shall be sealed with asphalt sealant soon after completion of the
curing period and before the pavement is opened to traffic, including the
Contractor’s equipment. Just prior to sealing, each joint shall be thoroughly
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 131/437
cleaned of all foreign materials including membrane curing compound and the
joint faces shall be clean and surface dry when the seal is applied.
5/7/2018 DPW H Blue Book - slide pdf.c om
The seals shall be in one piece for the full width of each transverse joint.
The Contractor shall protect the pavement and its appurtenances against
both public traffic and traffic caused by his own employees and agents. This shall
include watchmen to direct traffic and the erection of and maintenance of warning
signs, lights, pavement bridges or cross-overs, etc. The Plans or Special
Provisions will indicate the location and type of device or facility required to protect
the work and provide adequately for traffic.
constructed asphaltconcrete/asphalt
with the prescribed and concrete pavements shall be immediately
mix after completion filled/restored
of the drilling works.
1. Grade
After the grade or base has been placed and compacted to the
required density, the areas which will support the paving machine
shall be cut to the proper elevation by means of a properly designed
machine. Thebrought
shall then be grade on which
to the the pavement
proper profile byismeans
to be constructed
of properly
designed machine. If the density of the base is disturbed by the
grading operation, it shall be corrected by additional compaction
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 132/437
2. Placing Concrete
stopping
reason, it and starting of
is necessary to the
stoppaver held tomovement
the forward a minimum.
of the If, for any
paver the
vibratory and tamping elements shall also be stopped immediately.
No tractive force shall be applied to the machine, except that which is
4. Curing
the
leastquality
three of
(3)concrete represented
representative coresby failed
shall betest results
taken fromiseach
acceptable
member in or
place.
area At
of
concrete in place that is considered deficient. The location of cores shall be
determined by the Engineer so that there will be at least impairment of strength of
If the strength of control specimens does not meet the requirements of this
Subsection, and it is not feasible or not advisable to obtain cores from the
structure due to structural considerations, payment of the concrete will be made at
an adjusted price due to strength deficiency of concrete specimens as specified
hereunder:
15
20 to
to less
less than
than 20
25 60
50
25 or more 0
The Engineer will decide when the pavement may be opened to traffic.
The road will not be opened to traffic until test specimens molded and cured in
accordance with AASHTO T 23 have attained the minimum strength
requirements in Subsection 311.2.11. If such tests are not conducted prior to the
specified age the pavement shall not be operated to traffic until 14 days after the
concrete was placed. Before opening to traffic, the pavement shall be cleaned
and joint sealing completed.
1. General
2. Pavement Thickness
The area to be paid for under this Item shall be the number of square
meters (m2) of concrete pavement placed and accepted in the completed
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 136/437
pavement. The width for measurements will be the width from outside edge to
outside edge of completed pavement as placed in accordance with the Plans or
5/7/2018 as otherwise required by the Engineer in writing. The length will be measured
DPW H Blue Book - slide pdf.c om
horizontally along the center line of each roadway or ramp. Any curb and gutter
placed shall not be included in the area of concrete pavement measured.
400.1 Description
400.1.1 Scope
This Item shall consist of piling, furnished, driven or placed, cut and spliced
in accordance with this Specification and in reasonably close conformity with the
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 137/437
Plans.
5/7/2018 The Contractor shall furnish the piles in accordance with an itemized list,
DPW H Blue Book - slide pdf.c om
which will be provided by the Engineer, showing the number and lengths of all
piles. When cast-in-place concrete piles are specified on the Plans, the Engineer
will not furnish the Contractor an itemized list showing the number and length of
piles. When test piles and load tests are required in conformance with Sub-
section 400.1.2 and 400.1.3, respectively, the data obtained from driving test piles
and making test loads will be used in conjunction with other available sub-soil
information to determine the number and lengths of piles to be furnished. The
Engineer will not prepare the itemized list of piles for any portion of the foundation
area until all specified loading tests in the Contract representative of the portion
have been completed.
For his own information, the Contractor may drive at the location of the
regular piles indicated on the Plans such test piles as he may consider necessary
in addition to the test piles specified in the Contract and shall be considered as
regular piles. When called for in the Bill of Quantities, a pile if required to be
subjected to load test shall conform to the provision as provided in Subsection
400.1.3, Load Tests. The Contractor shall furnish and drive test piles of the
dimensions and at the locations designated by the Engineer. They shall be of the
material shown in the Bill of Quantities and shall be driven to refusal or to such tip
elevation or approximate bearing value as the Engineer may request. Test piles
prior test loads and foundation data. The ground at each test pile shall be
excavated to the elevation of the bottom of the footing before the pile is driven.
Load
Dynamic tests High-Strain
Method, for files shall be either
Dynamic Static
Method andorCross-Hole
Pile Testing by Logging.
Sonic Low-Strain
When load tests are specified, the number and location of piles to be tested
will be designated by the Engineer. Load tests shall be done by methods
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 138/437
approved by the Engineer. The Contractor shall submit to the Engineer for
approval detailed plans of the loading apparatus he intends to use. The
5/7/2018 apparatus shall be so constructed as to allow the various increments of the load to
DPW H Blue Book - slide pdf.c om
be placed gradually without causing vibration to the test piles. If the approved
method requires the use of tension (anchor) piles, such tension piles shall be of
the same type and diameter as the permanent piles and shall be driven in the
location of permanent piles when feasible. Piling not a part of the structure shall
be removed or cut off at least 300mm below the bottom of the footing or finished
elevation of the ground upon completion of the test load. Permanent piling used
as anchor piling which is raised during the test load shall be redriven to original
grade and bearing.
Each load increment shall be held for an interval of two and one-half
minutes. Each succeeding increment shall be as directed by the Engineer or as
shown on the Plans and shall be applied immediately after the two and one-half
minute interval readings have been made.
have been removed and at each interval of two and one-half minutes for a total
period of five (5) minutes.
All load tests shall be carried to failure or to the capacity of the equipment,
unless otherwise noted on the Plans.
After the completion of loading tests, the load used shall be removed and
the piles including tension piles, shall be utilized in the structure if found by the
Engineer to be satisfactory for such use. Test piles not loaded shall be utilized
similarly. If any pile, after serving its purpose as a test or tension pile, is found
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 139/437
Pile integrity
D-5882-96. testing by
It is a so-called Low-Strain
Low Dynamic
Strain Method, Method
since shall conform
it requires to of
the impact ASTM
only
a small hand-held hammer, and also referred to as a Non-Destructive Method.
inspects the drilled shaft structural integrity, and extent and location of defects, if
any. At the receiver probe, pulse arrival time and signal the concrete affects
strength. For equidistant tubes, uniform concrete yields consistent arrival times
with reasonable pulse wave speed and signal strengths. Non – uniformities such
as contamination, soft concrete, honeycombing, voids, or intrusions of foreign
other hammers to be calibrated are used, the minimum number of hammer blows
per unit of pile penetration needed to obtain the specified bearing value of piles
5/7/2018
shall be determined by load tests, as provided in Subsections 400.1.2 and
DPW H Blue Book - slide pdf.c om
400.1.3. In the absence of load tests, the safe bearing value of each timber pile
shall be determined by whichever of the following approximate formulas is
applicable:
1000 WH
For gravity hammer, P = ------------- x ---------------
6 S+25.4
1000 WH
P = ----------- x -----------------
6 S+2.54
1000 x -----------------
P = ------------ E
6 S+2.54
1000 E
P = ---------- x ------------------------
6 S+2.54 (Wp/W)
Where:
or other
3. The serious impairment.
penetration is reasonably quick and uniform.
4. There is no measurable bounce after the blow.
5. A follower is not used.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 141/437
2WH (W)
Ru = ----------------------------
(S+K) (W+Wp)
Ru
Ra = ---------------
FS
Where:
b. Hiley’s Formula shall be used when the ratio of the weight of ram
or hammer to weight of pile is less than one fourth (1/4).
Ep
n =
= modulus
coefficientofofelasticity of pile
restitution (refer to table)
FS = factor of safety (min. = 3)
Note:
Formula for other pile hammers with suggested factor of safety
should be as provided/recommended by their respective
Materials to which Easy Driving: Medium Driving: Hard Driving: Very Hard
blow is applied P1 = 3.45 MPa P1 = 6.90 MPa P1 = 10.34 MPa Driving:
(500 psi) (1000 psi) (1500 psi) P1 = 13.88 MPa
on Pile Butt If on Head or Cap. on Head or Cap. (2000 psi)
no cushion, mm (in.) mm (in.) on Head or Cap.
mm (in.) mm (in.)
Head of timber pile 1.27 (0.05) 2.54 (0.10) 3.81 (0.15) 5.08 (0.20)
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 143/437
Concrete Pile 0.635 (0.025) 1.27 (0.05) 1.905 (0.075) 2.54 (0.10)
Steel-covered cap.
containing wood
packing but steel
piling at pipe 1.016 (0.04) 2.032 (0.08) 3.048 (0.12) 4.064 (0.16)
b
The first figure represent the compression of the cap and wood dolly or
packing above
compression thewood
of the cap,packing
whereas the second
between figure
the cap and the represent
pile head. the
P1 = Ru/A
Values of Efficiency of Hammer, ef
Hammer Type ef
Drop Hammer
Drop Hammer actuated
released by
by rope
trigger
and friction winch 1.00
0.75
McKiernan-Terry Single-acting hammers 0.85
Warrington-Vulcan Single –acting hammers 0.75
Reinforced
Concrete Helmet with dolly
green heart composite
on topplastic
of pile or 0.40 0.50
The formulas specified in the preceding Subsection for timber piling may be
used in determining a rough approximation for the bearing power of precast and
cast-in-place concrete piles and of steel piles.
In all cases when the bearing power of concrete and steel piles is
determined by formula, the piles shall be driven until the safe bearing power of
each is computed to be not less than 27 tonnes.
When the safe bearing power of any pile is found by test or computation to
be less than the design load, longer piles or additional piles shall be driven as
ordered in writing by the Engineer.
The safe bearing power of jetted piles shall be determined by actual tests
or
Noby
jet the
shallappropriate methods
be used during andblows.
the test formulas given in the preceding Subsections.
noted on the Plans or Special Provisions, only the best grade shall be used. It
shall be free from loose knots, splits, wormholes, decay, warp, ring separation or
any defect which will impair its strength or render it unfit for its intended use. Any
specie specified on the Plans may be used for untreated timber and if the specie
is not available, a specie of equivalent strength and durability may be used if
authorized by the Engineer.
Round piles shall be cut above the ground swell and shall taper from butt to
tip. A line drawn from the center of the tip to the center of the butt shall not fall
outside of the cross-section of the pile at any point more than one percent of the
length of the pile.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 145/437
In short bends, the distance from the center of the pile to a line stretched
5/7/2018 from the center of the pile above the bend to the center of the pile below the bend
DPW H Blue Book - slide pdf.c om
shall not exceed four percent of the length of the bend or a maximum of 65mm.
Unless otherwise specified, all piles shall be peeled removing all rough
bark and at least 80 percent of the inner bark. Not less than 80 percent of the
surface on any circumference shall be clean wood. No strip of inner bark
remaining on the pile shall be more than 20mm wide and 200mm long. All knots
shall be trimmed close to the body of the pile.
The pile sizes shall conform to the dimensions shown in Table 400.1.
Table 400.1 – Dimension of Piles
Less
12 to than 12 metres
18 metres 300
320 450
450 200
180
More than 18 metres 350 500 150
treatment of structural timbers sawn from woods native to the Philippines. The
treatment shall be so regulated that the curing process will not induce excessive
checking. The minimum penetration of the preservative into the surface of the
timber shall be 20 mm. All piles shall retain the minimum amount of preservative
specified in Table 400.2.
Type of Processing
Use
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281
Empty Cell Process Full Cell Process 146/437
The Engineer shall inspect the timber prior to the treatment to determine
conformance with the Specifications and suitability of conditions for treatment. He
shall be permitted free access to the plant in order that temperatures, pressures
and quantities and type of treatment materials used may be observed. Samples of
the creosote or creosote petroleum mixtures shall be furnished as required for
test.
The timber shall be checked to determine penetration of treatment, quantity
of free preservative remaining on the timber and any visual evidence that the
treatment has been performed in a satisfactory manner. The penetration of
treatment shall be determined by boring a sufficient number of well-distributed
holes to determine the average penetration. All such holes shall be plugged with
plugs approximately 2 mm larger in diameter than the bit used in boring the holes.
Unless otherwise called for on the Plans or Special Provisions, shells for
cast-in-place concrete piles shall have a minimum 305mm diameter at cut off and
a minimum 203mm diameter at tip: made from not less than 4.55mm in thickness
plate stock conforming to AASHTO M 183. Shells may either be spirally welded
or longitudinally welded and may either be tapered or constant in section. Tips
shall be sealed as shown on the Plans.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 147/437
without injury and to resist harmful distortion and/or buckling due to soil pressure
after driven and the mandrel removed. Butt and tip dimension shall be as called
for on the Plans or Special Provisions.
Filled Steel Pipes (filled with concrete) shall conform to the requirements of
ASTM A 252, Grade 2, Welded and Seamless Pipe Piles. Closure Plates for
closed piles shall conform to the requirements of AASHTO M 183.
Unfilled Tubular Steel Piles shall conform to the requirements of ASTM A
252, Grade 2, with chemical requirements meeting ASTM Designation A 53,
Grade B. The wall thickness shall not be less than 4.76mm.
Steel sheet piles shall meet the requirements of AASHTO M 202 (ASTM A
328), or AASHTO M 223. All other sheet piles shall meet the requirements
prescribed above the particular material specified. The joints shall be practically
400.2.9 Splices
Material for pile splices, when splicing is allowed, shall be of the same
quality as the material used for the pile itself and shall follow the requirements
given on the Plans.
400.2.10 Paint
All excavations for the foundation on which the piles are to be driven shall
be completed before the pile driving, unless otherwise specified or approved by
the Engineer. After driving is completed, all loose and displaced materials shall
be removed from around the piles by hand excavation, leaving clean solid surface
to receive the concrete of the foundation. Any requirement for granular fill and
lean concrete shall be indicated on the Plans or as directed by the Engineer.
400.3.2 Determination of Pile Length
Pile length and bearing capacity shall be determined by the Engineer from
the results of the test piling and load tests.
The Contractor shall be responsible for obtaining the correct pile length and
bearing capacity according to the criteria given by the Engineer.
cap or underneath the superstructure in case of pile bents. All piles pushed up by
the driving of adjacent piles or any other cause shall be redriven.
shall be regulated so as to avoid injury to the pile and shall in no case exceed
4.50m for timber and steel piles and 2.50m for concrete piles unless otherwise
specified or approved by the Engineer.
The plant and equipment furnished for steam hammers shall have sufficient
capacity to maintain, under working condition, the pressure at the hammer
specified by the manufacturer. The boiler or pressure tank shall be equipped with
an accurate pressure gauge and another gauge shall be supplied at the hammer
intake to determine the drop in pressure between the gauges. When diesel
hammers or any other types requiring calibration are used, they shall be calibrated
with test piling and/or test loads in accordance with Subsection 400.1.2, Test
Piles.
Water jets shall be used only when permitted in writing by the Engineer.
When water jets are used, the number of jets and the nozzle volume and pressure
shall be sufficient to erode freely the material adjacent to the pile. The plant shall
have sufficient capacity to deliver at all time a pressure equivalent to at least 690
KPa at two 19 mm (3/4 inch) jet nozzles. The jets shall be shut off before the
required penetration is reached and the piles shall be driven solely by hammers to
final penetration as required by the Engineer.
Piles shall be supported in line and position with leads while being driven.
Pile driving leads shall be constructed in such a manner as to afford freedom of
movement of the hammer, and shall be held in position by guys or steel braces to
insure rigid lateral support to the pile during driving. The leads shall be of
sufficient length to make the use of a follower unnecessary and shall be so
designed as to permit proper placing of batter piles. The driving of the piles with
followers shall be avoided if practicable and shall be done only under written
Full length piles shall be used where practicable. Splicing of piles when
permitted, shall be in accordance with the provisions of Subsection 400.3.7 and
400.3.8. All piles shall be continuously driven unless otherwise allowed by the
Engineer.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 150/437
Piles shall not be driven within 7 m of concrete less than 7 days old.
400.3.4 Timber Piles
5/7/2018 DPW H Blue Book - slide pdf.c om
Piles shall be strapped with three metal straps: one about 450mm from the
butt, one about 600mm from the butt, and the third, about 300mm from the tip.
Additional straps shall be provided at about 4.5m on centers between tip and butt.
Strapping should encircle the pile once and be tensioned as tightly as possible.
Straps shall be 38mm wide, 0.8mm thick, cold rolled, fully heat treated, high
tensile strapping, painted and waxed.
Piles for any one bent shall be carefully selected as to size, to avoid undue
bending or distortion of the sway bracing. Care shall be exercised in the
distribution of piles of various sizes to obtain uniform strength and rigidity in the
bents of any given structure.
Cut offs shall be made accurately to insure full being between caps and
piles of bents.
Piles shall be cured and finished in accordance with Items 405, Structural
Concrete and 406, Prestressed Concrete Structures.
Cylinder specimens shall be made and tested in accordance with Item 405.
Piles shall not be moved until the tests indicate that the concrete has attained a
compressive strength of at least 80 percent (80%) of the design 28-day
compressive strength and they shall not be transported or driven until the design
28-day compressive strength has been attained.
When concrete piles are lifted or moved, they shall be supported at the
points shown on the Plans; if not shown, they shall be supported at the quarter
points.
1. Drilled Holes
All holes for concrete piles cast in drilled holes shall be drilled dry to tip
elevation shown on the Plans. All holes will be examined for straightness and any
hole which on visual inspection from the top shows less than one-half the
diameter of the hole at the bottom of the hole will be rejected. Suitable casings
shall be furnished and placed when required to prevent caving of the hole before
concrete is placed.
All loose material existing at the bottom of the hole after drilling operations
have been completed shall be removed before placing concrete.
The use of water for drilling operations or for any other purpose where it
may enter the hole will not be permitted. All necessary action shall be taken to
prevent surface water from entering the hole and all water which may have
infiltrated into the hole shall be removed before placing concrete.
The inside of shells and pipes shall be cleaned and all loose materials
removed before concrete is placed. The concrete shall be placed in one
continuous operation from tip to cut-off elevation and shall be carried on in such a
manner as to avoid segregation.
The top 3m of concrete filled shells, or to the depth of any reinforcing cage,
whichever is greater, shall be consolidated by acceptable vibratory equipment.
Pipes shall be of the diameter shown on the Plans. The pipe wall thickness
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 152/437
shall not be less than that shown on the Plans but in no case less than 5mm. The
pipe, including end closures, shall be of sufficient strength to be driven by the
pipe, including end closures, shall be of sufficient strength to be driven by the
specified methods without distortion.
5/7/2018 DPW H Blue Book - slide pdf.c om
Closure plates and connecting welds shall not project more than 12.5mm
beyond the perimeter of the pile tips.
No shell or pipe shall be filled with concrete until all adjacent shells, pipes,
or piles within a radius of 1.5m or 4 ½ times the average pile diameter, whichever
is greater, have been driven to the required resistance.
After
be driven a shell
within 6mor pipe has
thereof untilbeen filled
at least 7 with
daysconcrete, no shell, pipe or pile shall
have elapsed.
3. Drilled Shafts
Drilled shafts are deep foundations formed by boring a cylindrical hole into
soil and/or rock and filling the hole with concrete. Drilled shafts are also
commonly referred to as caissons, bored piles or drilled piers.
Drilled shafts, like driven piles, transfer structural loads to bearing stratum
well below the base of the structure by passing soils having insufficient strength to
carry the design loads.
a. The construction of the pile or shaft in a wet condition while the walls of
the excavation are stabilized by hydrostatic pressure of water or a mineral slurry
until the concrete is placed by tremie methods for the full length of the pile.
The mineral slurry shall be premixed thoroughly with clean fresh water and
adequate time allotted for hydration prior to introduction into the shaft excavation.
Adequate slurry tanks will be required when specified. No excavated slurry pits
will be allowed when slurry tanks are required on the project without written
permission of the Engineer. Adequate desanding equipment will be required
when specified. Steps shall be taken as necessary to prevent the slurry from
“setting up” in the shaft excavation, such as agitation, circulation, and adjusting
the properties of the slurry.
Control tests using suitable apparatus shall be carried out by the Contractor
on the mineral slurry to determine density, viscosity, and pH. An acceptable
range of values for those physical properties is shown in the following table.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 154/437
Range of Values (At 20o [68oF])
5/7/2018 DPW H Blue Book - slide pdf.c om
Viscosity 28 to 45 28 to 45 Marsh
(sec. per quart) Cone
pH 8 to 11 8 to 11 pH Paper
or Meter
Note:
a) Increase density values by 0.314 KN/m3 (2 pcf) in salt water.
Prior to placing shaft concrete, slurry samples shall be taken from the
bottom and at intervals not exceeding 3.05m (10 feet) for the full height of slurry.
Any heavily contaminated slurry that has accumulated at the bottom of the shaft
shall be eliminated. The mineral slurry shall be within specification requirements
The base of the shaft excavation may be cleaned using a cleaning bucket
followed by airlifting. Reverse circulation techniques may also be used to clean
the base of the shaft.
diameter of casing shall not be less than the specified size of the shaft. It shall
conform to AASHTO M 270 (ASTM A 709) Grade 36 unless otherwise specified.
c. The use of a permanent casing which is left in place within the portion of
the pile which is in unstable material.
The reinforcing steel cage consisting of the steel shown on the Plans plus
cage stiffener bars, spacers, centralizers and any other necessary appurtenances
shall be completely assembled and placed as a unit immediately after the shaft
excavation is inspected and accepted and prior to shaft concrete placement.
elevation of the shaft. Placement shall continue after the shaft is full until good
quality concrete is evident at the top of the shaft. Concrete shall be placed
5/7/2018 through a suitable tube. DPW H Blue Book - slide pdf.c om
For piles less than 2.5 meters in diameter, the elapsed time from the
beginning of concrete placement in the shaft to the completion of placement shall
not exceed 2 hours. For piles 2.50 meters and greater in diameter, the concrete
placing rate shall not be less than 9.0 meters of pile height per each 2-hour
period. The concrete mix shall be of such design that the concrete remains in a
workable plastic state throughout the 2-hour placement limit.
When the top of pile elevation is above ground, the portion of the pile
above ground shall be formed with a removable form or permanent casing when
specified.
For at least 48 hours after pile concrete has been placed, no construction
operations that would cause soil movement adjacent to the shaft, other than mild
vibration, shall be conducted.
Construction Tolerances:
c. After all the shaft concrete is placed, the top of the reinforcing steel
cage shall be no more than 15.24 cm (6”) above and no more than 7.62
cm (3”) below plan position.
d. When casing is used, its outside diameter shall not be less than the
shaft diameter shown on the plans. When casing is not used, the
minimum diameter of the drilled shaft shall be the diameter shown on
the plans for diameters 60.96 cm (24”) or less, and not more than 2.54
cm (1 inch) less than the diameter shown on the plans for diameters
greater than 60.96 cm (24”).
e. The bearing area of bells shall be excavated to the plan bearing area as
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 157/437
a minimum. All other plan dimensions shown for the bells may be
varied, when approved, to accommodate the equipment used.
5/7/2018 DPW H Blue Book - slide pdf.c om
f. The top elevation of the shaft shall be within 2.54 cm (1 inch) of the plan
top of shaft elevation.
g. The bottom of the shaft excavation shall be normal to the axis of the
shaft within 62.5 mm/m (3/4 inch per foot) of shaft diameter.
Steel H-Pile shall consist of structural steel shapes of the sections indicated
on the Plans.
When placed in the leads, the pile shall not exceed the camber and sweep
permitted by allowable mill tolerance. Piles bent or otherwise damaged will be
rejected.
400.3.10 Splicing
b. By cutting away the concrete at the end of the pile, leaving the
reinforcing steel exposed for a length of 40 bar diameters for corrugated
5/7/2018 or deformed bars and 60 bar diameters for plain bars. The final cut of
DPW H Blue Book - slide pdf.c om
the concrete shall be perpendicular to the axis of the pile.
Reinforcement of the same size as that used in the pile shall be spliced
to the projecting steel in accordance with Item 404, Reinforcing Steel,
and the necessary formwork shall be placed, care being taken to
prevent leakage along the pile. The concrete shall be of the same
quality as that used in the pile. Just prior to placing concrete, the top of
the pile shall be wetted thoroughly and covered with a thin coating of
2. Prestressed Piles
Concrete piles shall, when approved by the Engineer, be cut off at such a
level that at least 300mm of undamaged pile can be embedded in the structure
above. If a pile is damaged below this level, the Contractor shall repair the pile to
the satisfaction of the Engineer. The longitudinal reinforcement of the piles shall
be embedded in the structure above to a length equal to at least 40 times the
diameter of the main reinforcing corrugated bars (60 diameters for plain bars).
The distance from the side of any pile to the nearest edge of the cap shall not be
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 159/437
less than 200mm.
When the cut off elevation for a precast pile or for the steel shell or pile for
5/7/2018
a cast in place concrete pile is below the elevation of the bottom of the pile cap,
DPW H Blue Book - slide pdf.c om
the pile may be built-up from the butt of the pile to the elevation of the bottom of
the cap by means of reinforced concrete extension constructed in accordance with
Subsection 400.3.10 or as approved by the Engineer.
Cut-offs of structural steel piles shall be made at right angles to the axis of
the pile. The cuts shall be made in clear, straight lines and any irregularity due to
cutting or
bearing burning shall be leveled-off with deposits of weld metal prior to placing
caps.
cleaning and painting metal surfaces in accordance with Item 403, Metal
Structures. This protection shall extend from the elevation shown on the Plans to
the top of the exposed steel.
The Contractor
the record shall be givenshalltokeep
the records
Engineerofwithin
all piles driven
two or installed.
(2) days A copy
after each of
pile is
driven. The record form to be used shall be approved by the Engineer. The pile
records shall give full information on the following:
1. Piles Furnished
The quantity to be paid for will be the sum of the lengths in metres of
the piles of the several types and lengths ordered in writing by the
Engineer, furnished in compliance with these Specifications and stockpiles
in good condition at the project site by the Contractor and accepted by the
Engineer. The length to be paid for will include test and tension piles
ordered by the Engineer, but not those furnished by the Contractor at his
option. No allowance will be made for piles, including test piles, furnished
by the Contractor to replace piles previously accepted by the Engineer that
are subsequently lost or damaged while in stockpile, or during handling or
driving, and are ordered by the Engineer to be removed from the site of
work.
The quantity to be paid for will be the sum of actual lengths in meters of
the piles cast and left in-place in the completed and accepted work.
Measurements will be from the pile tip to the bottom of cap or footing. Portions of
piles cast deeper than the required length through over-drilling will not be
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 162/437
The quantity to be paid for, including test pile shoes, will be the number of
pile shoes driven shown on the Plans or ordered in writing by the Engineer,
furnished by the Contractor in accordance with these Specifications and accepted
by the Engineer. Pile shoes furnished by the Contractor at his option or to replace
those that are lost or damaged in stockpile or handling will not be measured for
payment.
400.4.4 Load Tests
The quantity of the load tests to be paid for will be the number of tests
completed and accepted except that load tests made to calibrate different types of
hammers, if not included in the Bill of Quantities, will not be measured for
payment.
Anchor and test piling which are not part of the completed structure, will be
included in the unit bid price for each “Load Test”. Anchor and test piling or
anchor and test shafts which are a part of the permanent structure will be paid for
under the appropriate Item.
400.4.5 Splices
The quantity to be paid for will be the number of splices which may be
required to drive the pile in excess of the estimated length shown on the Plans for
cast-in-place steel pipes or shells or in excess of the order length furnished by the
Engineer for all other types of piling. Splices made for the convenience of the
400
400 (15)
(16) Precast, Prestresssed
Test Piles, Concrete
furnished and driven Piles, driven Meter
Meter
400 (17) Concrete Piles cast in Drilled Holes Meter
400 (18) Concrete Piles cast in Steel Shells Meter
400 (19) Concrete Piles cast in Steel Pipes Meter
400 (20) Pile Shoes Each
400 (21) Splices Each
400 (22) Load Tests Each
400 (23) Bored Piles (dia. __m) Meter
400 (24) Permanent Casing (dia. ___m) Meter
401.1 Description
401.2.1 Concrete
It shall conform to the requirements of Item 710, Reinforcing Steel and Wire
Rope.
401.2.3 Steel
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 164/437
Structural
and castings shallsteel consisting
conform of steel and iron
to the requirements plates,
of Item 403, shapes, pipes, fittings
Metal Structures.
5/7/2018 DPW H Blue Book - slide pdf.c om
401.2.4 Aluminum
401.2.5 Timber
These shall conform to the requirements of Item 505, Stone Masonry and
Item 704, Masonry Units.
401.2.7 Paint
401.3.1 General
Railings shall be constructed to the lines and grades shown on the Plans
and shall not reflect any unevenness in the structure. All railing posts shall be set
Galvanized surfaces which have been abraded so that the base metal is
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 165/437
exposed, threaded portions of all fittings and fasteners and cut ends of bolts shall
be painted with two (2) coats of zinc-dust and zinc oxide paint.
5/7/2018 DPW H Blue Book - slide pdf.c om
401.3.2 Metal Railing
1. Railing Cast-In-Place
2. Precast Railings
The materials used in masonry brick railing and parapet and the work to be
done shall conform to the requirements of this Specification. The workmanship
shall be first class and the finished construction shall be neat in appearance and
true to line and grade.
The quantity to be paid for shall be the number of linear meters of specified
railing actually completed and accepted measured from center to center of end
posts.
402.1 Description
402.2.1 Timber
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 167/437
Timber.It shall conform to the requirements of Item 713, Treated and Untreated
5/7/2018 DPW H Blue Book - slide pdf.c om
402.2.2 Hardware
All hardware shall be of the kind and size specified on the Plans. All bolts,
including drift bolts, shall be either wrought iron or medium steel. Washers shall
be either ogee gray iron casting or malleable cast iron unless cut washers are
specified on the Plans.
Bolts shall have square heads and nuts, unless otherwise specified. Nails
shall be cut or round wire of standard form. Spikes shall be cut wire or spikes, or
boat spikes, as specified. All hardware shall be galvanized in conformity with
AASHTO M 232 or cadmium plated per ASTM M 165 Type OS, unless otherwise
specified on the Plans or Special Provisions.
402.2.3 Paint
It shall conform to the requirements of Item 709, Paints or Item 411, Paint.
402.2.5 Preservatives
The preservative shall be creosote oil or creosote petroleum oil blend as
All timber which is to be stored on the job for any length of time prior to its
use in the structure shall be neatly stacked in piles to prevent warping or
distortion. Untreated timber shall be open-stacked at least 300mm above the
ground and the stack shall be sloped so as to shed water. Creosote-treated
timber shall be close-stacked and piled to prevent warping. The ground under-
neath and in the vicinity of all material piles shall be cleared of all weeds and
rubbish.
Any cut made or hole bored in treated timber that shall expose untreated
wood shall be given three coats of hot creosote or carbolineum before the
exposed part is assembled.
The minimum penetration of the preservative with the surface of the timber
shall be 20mm. The minimum retention of preservative per cubic metre of timber
shall be as follows:
The Engineer shall be notified at least ten (10) days in advance of the date
that the treating process will be performed in order that the untreated timber, the
treatment process, and the finished treated timber may all be inspected. The
Engineer will inspect the timber prior to treatment to determine conformance with
Any excessive checking caused by the treating process shall be cause for
rejection of the pieces in which the excessive checking occurs.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 169/437
The
pressure treating
gages plant
so that the shall be can
process equipped with adequate
be accurately controlledthermometers and
and a continuous
5/7/2018 record made of stages of the treating process. If requested by the Engineer,
DPW H Blue Book - slide pdf.c om
Washers of the size and type specified shall be used under all bolt heads
and nuts that would otherwise be in contact with wood. Cast iron washers shall
have a thickness equal to one fourth the diameter of the bolt and the diameter of
the washer shall be four times its thickness. For malleable or plate washers, the
diameter or side size of the square shall be equal to four times the diameter of the
bolt. Cap washers shall be used when the timber is in contact with earth. All nuts
shall be checked effectively after being finally tightened.
The piles for any one bent shall be carefully selected as to size and quality
to avoid undue bending or distortion of the sway bracing. However, care shall be
exercised in the distribution of piles of various sizes to secure uniform strength
and rigidity in the bents of any given structure. Cut offs shall be accurately made
to insure perfect hearing between caps and piles.
Sills shall have true and even bearing on piles or pedestals. They shall be
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 170/437
drift-bolted
possible, allwith
earthbolts extending
shall into from
be removed the piles or pedestals
contact at that
with sills so leastthere
150mm. When
will be free
5/7/2018 circulation of air around the sills. DPW H Blue Book - slide pdf.c om
402.3.8 Caps
Timber caps shall be placed to obtain even and uniform bearing over the
tops of the supporting posts or piles with their ends in alignment. All caps shall be
secured by driftbolts, set approximately at the center extending at least 230mm
into the post or piles.
402.3.9 Bracing
402.3.10 Stringers
Planks for laminated or strip floors shall have a nominal thickness of 50mm
and shall be surfaced to a uniform width (SIE), and when so specified, to a
uniform thickness (SIS). Unless otherwise stipulated, no splicing of planks will be
allowed.
Planks shall be laid with the surfaced edge down and each plank shall be
toe-nailed to each alternative stringer. The nailing of successive planks shall be
staggered so that the spacing of nails along each stringer shall not be less than
100mm. In addition, each piece shall be nailed horizontally to adjacent pieces at
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 171/437
450mm
adjacent centers,
pieces. and staggered
All floors both
shall be cuthorizontally
to a straightand
linevertically
along thewith nails
sides in
of the
5/7/2018 roadway. DPW H Blue Book - slide pdf.c om
Railing and rail posts shall be built as shown on the Plans and shall be
constructed in a workmanlike and substantial manner. All railing and rail post
materials shall be surfaced on four sides (S4S). All rails shall be continuous and
squarely butt-joined at the post.
403.1 Description
This work shall consist of steel structures and the steel structure portions of
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 172/437
composite
grades andstructures,
dimensionsconstructed in Plans
shown on the reasonably close conformity
or established with the lines,
by the Engineer.
5/7/2018 DPW H Blue Book - slide pdf.c om
The work will include the furnishing, fabricating, hauling, erecting, welding
and painting of structural metals called for in the Special Provision or shown on
the Plans. Structural metals will include structural steel, rivet, welding, special
and alloy steels, steel forgings and castings and iron castings. This work will also
include any incidental metal construction not otherwise provided for, all in
accordance with these Specifications, Plans and Special Provisions.
Materials shall meet the requirements of Item 712, Structural Metal; Item
409, Welded Structural Steel, and Item 409, Welded Structural Steel; and Item
709, Paints.
403.3.1 Inspection
The Contractor shall give the Engineer at least fifteen (15) days notice prior
to the beginning of work at the mill or shop, so that the required inspection may be
made. The term “mill” means any rolling mill, shop or foundry where material for
the work is to be manufactured or fabricated. No material shall be rolled or
fabricated until said inspection has been provided.
The Contractor shall furnish the Engineer with copies of the certified mill
reports of the structural steel, preferably before but not later than the delivery of
the Engineer shall be notified of such intention at least fifteen (15) days in
advance of commencing fabrication to permit sampling and testing. When so
indicated or directed, the Contractor shall select such material as he wishes to use
from stock, and place it in such position that it will be accessible for inspection and
sampling. The Contractor shall select identified material from as few heat
numbers as possible, and furnish the certified mill test reports on each of such
heat numbers. Two samples shall be taken from each heat number as directed,
one for a tension test and one for a bend test.
In the case of unidentified stock, the Engineer may, at his discretion, select
any number of random test specimens.
Each bin from which rivets or bolts are taken shall subject to random test.
Five rivets or bolts may be selected by the Engineer from each bin for test
purposes.
Structural material, either plain or fabricated, shall be stored above the
ground upon platforms, skids, or other supports. It shall be kept free from dirt,
grease, or other foreign matter, and shall be protected as far as practicable from
corrosion.
403.3.3 Fabrication
1. Edge Planing
The surface finish of bearing and based plates and other bearing
surfaces that are to come in contact with each other or with concrete
shall meet the American National Standards Institute surface
roughness requirements as defined in ANSI B-46.1-47, Surface
Roughness Waviness and Lay, Part I:
6. Fabrication of Members
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 175/437
Unless otherwise shown on the Plans, steel plates for main
members and splice plates for flanges and main tension members, not
5/7/2018 DPW H Blue Book - slide pdf.c om
secondary members, shall be cut and fabricated so that the primary
direction of rolling is parallel to the direction of the main tensile and/or
compressive stresses.
At web splices, the clearance between the ends of the plates shall
not exceed 9.5 mm. The clearance at the top and bottom ends of the
web slice plates shall not exceed 6.3 mm.
8. Bent Plates
ASTM THICKNESS, t in mm
DESIG- Up to Over 6.3 Over 12.7 Over 25.4 Over 38.1
ATION 6.3 To 12.7 To 25.4 to 38.1 to 50.08
A36 1.5t 1.5t 2t 3t 4t
A242 2t 3t 5t a--- a---
A440 2.5t 3.5t 6t a--- a---
A441 2t 3t 5t a--- a---
A529 2t 2t ---- ---- ----
Gr.42
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 2t 2t 3t 4t 5t 176/437
Gr.45 2t 2t 3t 4t ----
Gr.50 2.5t 2.5t 4t a--- ----
5/7/2018 Gr.55 3t 3t 5t a--- ----
DPW H Blue Book - slide pdf.c om
A514 2t 2t 3t 3t
a
It is recommended that steel in this thickness range be bent hot. Hot
bending however, may result in a slight decrease in the as-rolled mechanical
properties.
b
The mechanical properties
temper-operation. of ASTMmay
Hot bending A 514 steel results
adversely affectfrom a quench-and-
these mechanical
properties. If necessary to hotbend, fabricator should discuss procedure
with steel supplier.
9. Fit of Stiffeners
E d iff f id d iff i d d f
in place on the structure. The eyebars shall be straight and free from
twists and the pin holes shall be accurately located on the centerline
of the bar. The inclination of any bar to the plane of the truss shall
not exceed 1.6 mm to 305 mm.
and shall be stress relieved only with the approval of the Engineer.
A record of each furnace charge shall identify the pieces in the
12. Tests
areWhen full by
required size
thetests of fabricated
Contract, the Plansstructural memberswill
or Specifications or state
eyebars
the
number and nature of the tests, the results to be attained and the
measurements of strength, deformation or other performances that
are to be made. The Contractor will provide suitable facilities,
material, supervision and labor necessary for making and recording
the tests. The members tested in accordance with the Contract will
be paid for in accordance with Subsection 403.3.5.1. The cost of
testing, including equipment handling, supervision labor and
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 178/437
incidentals for making the test shall be included in the contract price
for the fabrication or fabrication and erection of structural steel,
5/7/2018 whichever is the applicable item in the Contract, unless otherwise
DPW H Blue Book - slide pdf.c om
specified.
Pins and rollers shall be accurately turned to the dimensions shown on the
Plans and shall be straight, smooth, and free from flaws. Pins and rollers more
228.6 mm or less in diameter may either be forged and annealed. Pins and
rollers 228.6 mm or less in diameter may either be forged and annealed or cold-
finished carbon-steel shafting.
In pins larger than 228.6 mm in diameter, a hole not less than 50.8 mm in
diameter shall be bored full length along the axis after the forging has been
allowed to cool to a temperature below the critical range under suitable conditions
to prevent injury by too rapid cooling and before being annealed.
Pin holes shall be bored true to the specified diameter, smooth and
straight, at right angles with the axis of the member and parallel with each other
unless otherwise specified. The final surface shall be produced by a finishing cut.
than 0.8 mm. Boring of holes in built-up members shall be done after the riveting
is completed.
All holes for rivets or bolts shall be either punched or drilled. Material
forming parts or a member composed of not more than five thickness of metal
may be punched 1.6 mm larger than the nominal diameter of the rivets or bolts
whenever the thickness of the material is not greater than 19 mm for structural
steel, 15.9 unless
alloy steel, mm forsubpunching
high-strength steel
and or 12.7
reaming mm for for
is required quenched and tempered
field connections.
When there are more than five thicknesses or when any of the main
material is thicker than 19 mm for structural steel, 15.9 mm for high-strength steel,
or 12.7 mm for quenched and tempered alloy steel, all holes shall either be
subdrilled or drilled full size.
When required for field connections, all holes shall either be subpunched or
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 179/437
Unless otherwise specified, holes for all field connections and field splices
of main truss or arch members, continuous beams, towers (each face), bents,
plate girders and rigid frames shall be subpunched (or subdrilled if subdrilling is
required)
with and subsequently
Subsection 403.3.7. reamed while assembled in the shop in accordance
Templates for connections which duplicate shall be so accurately located that like
members are duplicates and require no matchmarking.
Alternately,
sub-sized holes andfor reaming
any field while
connection or splice
assembled, or designated
drilling holesabove in lieu
full-size of
while
assembled, the Contractor shall have the option to drill bolt holes full-size in
unassembled pieces and/or connections including templates for use with matching
sub-sized and reamed holes means of suitable numerically-controlled (N/C)
drilling equipment subject to the specific provisions contained in this Subsection.
The Contractor shall submit to the Engineer for approval a detailed outline
of the procedures that he proposes to follow in accomplishing the work from initial
drilling through check assembly, if required, to include the specific members of the
structure that may be N/C drilled, the sizes of the holes, the location of common
index and other reference points, composition of check assemblies and all other
pertinent information.
continuous
mm between group shall,thickness
adjacent after reaming or drilling, show no offset greater than 0.8
of metal.
2. Shop Assembling
Chord Assembly,
Progressive Truss and in theAssembly.
or Girder number and length specified for
camber
assembly.diagram shall
When any show
of the otherthe camber
methods measured
of shop in
assembly
is used, the camber diagram shall show calculated camber.
not be driven. When a rivet is ready for driving, it shall be free from slag, scale
and other adhering matter. Any rivet which is sealed excessively, will be
rejected.
All rivets that are loose, burned, badly formed, or otherwise defective shall
be removed and replaced with satisfactory rivets. Any rivet whose head is
defective
and in size
shall be or whose
removed. head
Stitch is driven
rivets offloosened
that are center will
by be considered
driving defective
of adjacent rivets
shall be removed and replaced with satisfactory rivets. Caulking, recapping, or
double gunning of rivets heads will not be permitted.
1. General
2. Unfinished Bolts
3. Turned Bolts
The surface of the body of turned bolts shall meet the ANSI
roughness rating value of 125. Heads and nuts shall be hexagonal
with standard dimensions for bolts of the nominal size specified or
the next larger nominal size. Diameter of threads shall be equal to
the body of the bolt or the nominal diameter of the bolt specified.
Holes for turned bolts shall be carefully reamed with bolts furnished
to provide for a light driving fit. Threads shall be entirely outside of
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 185/437
the holes. A washer shall be provided under the nut.
4. Ribbed Bolts
5/7/2018 DPW H Blue Book - slide pdf.c om
1. Bolts
bevelled washer
adjusted to add
the next 7.9 6.3
longer mm.mm.The length determined shall be
2. Bolted Parts
The slope of surface of bolted parts in contact with the bolt head
and nut shall not exceed 1:20 with respect to a plane normal to the
bolt axis. Bolted parts shall fit solidly together when assembled and
shall not be separated by gaskets or any other interposed
compressible material. When assembled, all joint surfaces,
including those adjacent to the bolt head, nuts or washers, shall be
free of scale, except tight mill scale, and shall also be free of burrs,
dirt and other foreign material that would prevent solid seating of the
parts. Paint is permitted unconditionally in bearing-type
connections.
3. Installation
nut method in holes which are not oversized or slotted may have
the washer omitted. Hardened washers shall be used under
both the head and nut regardless of the element turned in the
case of AASHTO M 253 bolts if the material against which it
bears has a specified yield strength less than 275.76 MPa.
e. Lock Pin and Collar Fasteners. The installation of lock pin and
collar fasteners shall be by methods approved by the Engineer.
4. Inspection
b. Three bolts of the same grade, size and condition as those under
inspection shall be placed individually in a calibration device
capable of indicating bolt tension. Length may be any length
representative of bolts used in the structure. There shall be a
washer under the part turned in tightening each bolt.
c. When the inspecting wrench is a torque wrench, each of the
three bolts specified above shall be tightened in the calibration
device by any convenient means to the minimum tension
specified for its size in Table 403.2. The inspecting wrench shall
then be applied to the tightened bolt and the torque necessary to
run the nut or head 5 degrees (approximately 25.4 mm at 304.8
mm radius)
average in themeasured
torque tighteningindirection shall
the tests of be determined.
three bolts shallThe
be
taken as the job inspection torque to be used in the manner
specified below.
403.3.11 Welding
Welding shall be done in accordance with the best modern practice and the
applicable requirements at AWS D1.1 except as modified by AASHTO “Standard
Specifications for Welding of Structural Steel Highway Bridges”.
403.3.12 Erection
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 191/437
1. General
The Contractor shall provide the falsework and all tools, machinery and
5/7/2018 DPW H Blue Book - slide pdf.c om
appliances, including driftpins and fitting-up bolts, necessary for the expeditious
handling of the work and shall erect the metal work, remove the temporary
construction, and do all work necessary to complete the structure as required by
the Contract and in accordance with the Plans and these Specifications.
be
andkept clean Long
shored. and properly
members, drained.
such as Girders
columnsand
andbeams
chords,shall
shallbe
beplaced upright
supported on
skids placed near enough together to prevent injury from deflection. If the
Contract is for erection only, the Contractor shall check the material turned over to
him against the shipping lists and report promptly in writing any shortage or
damage discovered. He shall be responsible for the loss of any material while in
his care, or for any damage caused to it after being received by him.
403.3.14 Falsework
Before starting the work of erection, the Contractor shall inform the
Engineer fully as to the method of erection he proposes to follow, and the amount
and character of equipment he proposes to use, which shall be subject to the
approval of the Engineer. The approval of the Engineer shall not be considered
as relieving the Contractor of the responsibility for the safety of his method or
equipment or from carrying out the work in full accordance with the Plans and
Specifications. No work shall be done until such approval by the Engineer has
been obtained.
means or, if approved by the Engineer, by the carefully planned and supervised
application of a limited amount of localized heat, except that heat straightening of
AASHTO M 244 (ASTM A 514) or ASTM A 517 steel members shall be done only
5/7/2018 DPW H Blue Book - slide pdf.c om
under rigidly controlled procedures, each application subject to the approval of the
Engineer. In no case shall the maximum temperature of the AASHTO M 244
(ASTM A 514) or ASTM A 517 steels exceed 607.2 0C, nor shall the temperature
exceed 5100C at the weld metal or within 152.4 mm of weld metal. Heat shall not
be applied directly on weld metal. In all other steels, the temperature of the heated
area shall not exceed 648.9 0C (a dull red) as controlled by temperature indicating
crayons, liquids or bimetal thermometers.
shall beFollowing
carefully the straightening
inspected of a bend
for evidence or buckle, the surface of the metal
of fracture.
have one-half of the holes filled with erection bolts and cylindrical erection pins
(half bolts and half pins) before placing permanent fasteners. Splices and
connections carrying traffic during erection shall have three-fourths of the holes so
filled, unless otherwise permitted by the Engineer.
403.3.18 Riveting
Pneumatic hammers shall be used for field riveting except when the use of
hand tools is permitted by the Engineer. Rivets larger than 15.9 mm in diameter
shall not be driven by hand. Cup-faced dollies, fitting the head closely to insure
good bearing, shall be used. Connections shall be accurately and securely fitted
up before the rivets are driven.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 193/437
Drifting shall be only such as to draw the parts into position and not
sufficient to enlarge the holes or distort the metal. Unfair holes shall be reamed
or drilled. Rivets shall be heated uniformly to a “light cherry red” color and shall
5/7/2018
be driven while hot. They shall not be overheated or burned. Rivet heads shall
DPW H Blue Book - slide pdf.c om
be full and symmetrical, concentric with the shank, and shall have full bearing all
around. They shall not be smaller than the heads of the shop rivets. Rivets shall
be tight and shall grip the connected parts securely together. Caulking or
recupping will not be permitted. In removing rivets, the surrounding metal shall
not be injured. If necessary, they shall be drilled out.
Pilot and driving nuts shall be used in driving pins. They shall be furnished
by the Contractor without charge. Pins shall be so driven that the members will
take full bearing on them. Pin nuts shall be screwed up tight and the threads
Shoes and bearing shall not be placed on bridge seat bearing areas that
are improperly finished, deformed, or irregular. They shall be set level in exact
position and shall have full and even bearing. The shoes and bearing plates may
be set by either of the following methods:
1. Method 1
Blast cleaning shall leave all surfaces with a dense and uniform anchor
pattern of not less than one and one-half mills as measured with an approved
surface profile comparator.
Blast cleaned surfaces shall be primed or treated the same day blast
cleaning is done. If cleaned surface rust or are contaminated with foreign
material before painting is accomplished, they shall be recleaned by the
Contractor at his expense.
When paint systems No. 1 or 3 are specified, the steel surfaces shall be
blast cleaned in accordance with SSPC – SP – 10. When paint systems No. 2, 4
or 5 are specified, the steel surface shall be blast cleaned in accordance with
SSPC – SP – 6.
The paint system to be applied shall consist of one as set forth in Table
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 195/437
1. Time of Application
Particular
cleaned care shall
surfaces with be taken
salts, to prevent
acids, alkali, the
or contamination of
other corrosive
chemicals before the prime coat is applied and between applications
of the remaining coats of paint. Such contaminants shall be
removed from the surface. Under these circumstances, the
pretreatments or, in the absence of a pretreatment, the prime coat of
paint shall be applied immediately after the surface has been
cleaned.
When a skin has formed in the container, the skin shall be cut
loose from the sides of the container, removed, and discarded. If
such skins are thick enough to have a practical effect on the
composition and quality of the paint, the paint shall not be used.
composition.
poured off into Ifamixing is done by hand,
clean container. most of in
The pigment thethe
vehicle
paint shall be
shall be
lifted from the bottom of the container with a broad, flat paddle,
lumps shall be broken up, and the pigment thoroughly mixed with
the vehicle. The poured off vehicle shall be returned to the paint
with simultaneous stirring, or pouring repeatedly from one container
to another until the composition is uniform. The bottom of the
container shall be inspected for unmixed pigment. Tinting pastes or
colors shall be wetted with a small amount of thinner, vehicle, or
paint and thoroughly mixed. The thinned mixture shall be added to
the large container of paint and mixed until the color is uniform.
Note:
1. Paint system shown for severe areas are satisfactorily in less
severe areas.
2. Coastal - within 304.8 m of ocean or tidal water.
High pollution-air pollution environment such as industrial areas.
Mild-other than coastal areas not in air pollution environment.
Total thickness
Alternate System 177.80 – 254
Prime Coat 708.03 (d) 88.90 – 127
Wash Primer Tie Coat 708.03 (d) 12.70
Finish Coat 708.03 (d) 38.10 – 50.80
Total thickness 139.70 – 190.50
System 4 – Alkyd-Oil-Basic Lead-Chromate System
Prime Coat 708.03 (e) 38.10 – 50.80
Intermediate
Finish Coat Coat 708.03
708.03 (e)
(e) 38.10
38.10 –
– 50.80
50.80
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 198/437
Total thickness 114.30 – 152.40
The paint system may be specified as four coats for new
structure steel in mild climate, with a minimum thickness of
5/7/2018
152.40 mm. DPW H Blue Book - slide pdf.c om
4. Application of Paint
a. General
The oldest of each kind of paint shall be used first. Paint shall
be applied by brushing or spraying or a combination of these
methods. Daubers or sheepskins may be used when no other
method is practicable for proper application in places of difficult
access. Dipping, roller coating, or flow coating shall be used only
when specifically authorized. All paints shall be applied in
accordance with the manufacturer’s instructions.
repainted with the same number of coats of paint of the same kind
as the undamaged areas.
5/7/2018 DPW H Blue Book - slide pdf.c om
If stripe painting is stipulated in the Special Provisions or if the
Contractor chooses to do so at his option, all edges, corners,
crevices, rivets, bolts, weld and sharp edges shall be painted with
the
coatpriming
of paint.paint by brush
Such stripingbefore the steel
shall extend forreceives first full
at least 25.4 mmprime
from
the edge. When practicable, this stripe coat shall be permitted to
dry before the prime coat is applied, otherwise the stripe coat shall
set to touch before the full prime coat is applied. However, the
stripe coat shall not be permitted to dry for a period of long enough
to allow rusting of the unprimed steel. When desired, the stripe coat
may be applied after a complete prime coat.
b. Brush Application
The pressure on the material in the pot and of the air at the guns
shall be adjusted for optimum spraying effectiveness. The pressure
on the material
changes in the
in elevation of pot
the shall be adjusted
gun above the pot.when
Thenecessary
atomizing for
air
pressure at the gun shall be high enough to atomize the paint
properly but not so high as to cause excessive fogging of paint,
excessive evaporation of solvent or loss by overspray.
All rums and sags shall be brushed out immediately or the paint
d. Shop Painting
e. Field Painting
Metal which has been shop coated shall be touched up with the
same type of paints as the shop coat. This touch-up shall include
cleaning and painting of field connections, welds, rivets and all
damaged or defective paint and rusted areas. The Contractor may,
any paint, the surfaces shall be cleaned and repainted. All cement
or concrete spatter and dripping shall be removed before any paint
is applied.
drying.
Paint which
touched-up with is
thedamaged in handling
same number shall and
of the coats be scraped off and
kinds of paint as
were previously applied to the steel.
a. Instrumentation
appropriate steel base (at least 76.2 x 76.2 x 3.2 mm) are
suitable working standards. These gages are held firmly
enough to press
One should avoidthe shim tightly
excessive against
pressure thatthe steel
might surface.
indent the
plastic or, on a blast cleaned surface, might impress the steel
peaks into the undersurface of the plastic.
c. Measurement Procedures
film at three points. The gage readings indicate the paint film
thickness at the three points. The gage readings indicate the
5/7/2018 paint thickness above the peaks of the surface profile.
DPW H Blue Book - slide pdf.c om
series of measurements.
measurements spaced evenly overMake each
five section
separateof spot
the
structure 9.29 square metres in area, or of other area as may
be specified. The average of five spot measurements for each
such section shall not be less than the specified thickness. No
single spot measurement (average of three readings) in any
section shall be less than 80% of the specified thickness.
d. Special Notes
contact of the probe with the paint and also to avoid adhesion of the
magnet. The accuracy of the measurement will be affected if the
coating is tacky or excessively soft.
manner
during theall prosecution
property, both public
of the workand private,
and which the
shall leave maywork
have been
site and damaged
adjacent
highway in a neat and presentable condition, satisfactory to the Engineer. All
excavated material or falsework placed in the stream channel during construction
shall be removed by the Contractor before final acceptance.
The quantity of structural steel to be paid for shall be the number of kilos
complete in place and accepted. For the purpose of measurement for payment
components fabricated from metals listed in (1) below, such as casting, alloy
steels, steel plates, anchor bolts and nuts, shoes, rockers, rollers, pins and nuts,
expansion dams, roadway drains and souppers, welds metal, bolts embedded in
concrete, cradles and brackets, posts, conduits and ducts, and structural shapes
for expansion joints and pier protection will be considered as structural steel.
Unless otherwise provided, the mass of metal paid for shall be computed
The mass of steel shapes and plates shall be computed on the basis of
their nominal mass and dimensions as shown on the approved shop
drawings, deducting for copes, cuts and open holes, exclusive of rivets
holes. The mass of all plates shall be computed on the basis of nominal
dimensions with no additional for overrun.
The mass of railing shall be included as structural steel unless the Bill of
Quantities contains as pay item for bridge railing under Item 401, Railings.
4. Miscellaneous
The mass of erection bolts, shop and field paint, galvanizing the boxes,
crates and other containers used for shipping, together with sills, struts,
and rods used for supporting members during the transportation, bridge
hardware as defined in Subsection 402.2.2 excluding steel plates and
bearings, connectors used for joining timber members, nails, spikes and
bolts, except anchor bolts will be excluded.
5. Rivets Heads
The mass of all rivet heads, both files and shop, will be assumed as
follows:
6. High-Strength Bolts
7. Welds
The mass of shop and field fillet welds shall be assumed as follows:
19.0 5.379
22.2 7.314
5/7/2018 25.4 9.774
DPW H Blue Book - slide pdf.c om
The mass of other welds will be computed on the basis of the theoretical
volume from dimensions of the welds, with an addition of 50 mass percent
as an allowance for overrun.
8. Other Items
The quantities of other Contract Items which enter into the completed
and accepted structure shall be measured for payment in the manner
prescribed for the Items involved.
Lump sum will be the basis of payment unless noted otherwise in the
bidding documents. No measurements of quantities will be made except as
provided in Subsection 403.5.1 (4).
When a quantity and unit price for “Structural Steel, furnished and
fabricated” are shown in the Bill of Quantities, the quantity, determined
as provided above, will be paid for at the contract unit price per kilogram
which price and payment shall be full compensation for furnishing,
galvanizing, fabricating, radiographing, magnet particle inspection, shop
painting and delivering the structural steel and other metal free of
charges at the place designated in the Special Provisions and for all
labor, equipment, tools and incidentals necessary to complete the work,
save erection and except as provided in Subsection 403.5.2, 403.5.3
and 403.5.4.
3. Erected
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 208/437
When a quantity and unit price for “Structural Steel Erected” are
shown in the Bill of Quantities, the quantity, determined as provided
above, will be paid for at the said contract unit price per kilogram which
5/7/2018 DPW H Blue Book - slide pdf.c om
price and payment shall be full compensation for unloading all the
structural steel and other metal, payment of any demurrage charges,
transporting to the
radiographing, bridgeready
complete site, erecting, magneticfurnishing
for use including particle inspection and
and applying
the field paint including all labor, equipment, tools and incidentals
necessary to complete the work, save furnishing and fabrication, and
except as provided in Subsections 403.5.2, 403.5.3 and 403.5.4.
4. Lump Sum
When the Bill of Quantities calls for lump sum price for “Structural
Steel, furnished, fabricated and erected”, the Item will be paid for at the
contract lump sum price and payment shall be full compensation for
furnishing, fabricating and erecting material and for all work herein
before prescribed in connection therewith, including all labor,
equipment, tools and incidentals necessary to complete the work,
except as provided in Subsections 403.5.2, 403.5.3 and 403.5.4.
For the purpose of Subsection 403.5.1 and unless otherwise shown on the
Plans, castings, forgings, special alloy steels and steel plates, wrought iron, and
structural shapes of expansion joints and pier protection shall be considered as
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 209/437
structural steel except that when quantities and unit price for certain alloy steels,
forgings, castings or other specific categories of metal are called for in the Bill of
Quantities, the mass of such selected material, determined as provided above,
5/7/2018 DPW H Blue Book - slide pdf.c om
shall be paid for at the respective contract unit price per kilogram for “Structural
Steel (Alloy steel, forgings, castings, and/or other category), furnished and
fabricated, andnamed
fabricated” as erected” or Bill
in the “Structural Steel (Subsection 403.4.1), furnished and
of Quantities.
The quantities of all other Contract Items which enter into the completed
and accepted structure shall be paid for at the contract unit prices for the several
Pay Items as prescribed for the Items involved.
When the Bill of Quantities does not contain a pay item for structural steel,
the quantities of metal drains, scuppers, conduits, ducts and structural shapes for
expansion joints and pier protection, measured as provided above will be paid for
as Reinforcing Steel under Item 404.
404.1 Description
This Item shall consist of furnishing, bending, fabricating and placing of
5/7/2018 DPW H Blue Book - slide pdf.c om
steel reinforcement of the type, size, shape and grade required in accordance with
this Specification and in conformity with the requirements shown on the Plans or
as directed by the Engineer.
404.2 Material Requirements
Before materials are ordered, all order lists and bending diagrams shall be
furnished by the Contractor, for approval of the Engineer. The approval of order
lists and bending diagrams by the Engineer shall in no way relieve the Contractor
of responsibility for the correctness of such lists and diagrams. Any expense
incident to the revisions of materials furnished in accordance with such lists and
diagrams to make them comply with the Plans shall be borne by the Contractor.
cause for rejection, provided the minimum dimensions, cross sectional area and
tensile properties of a hand wire brushed specimen meets the physical
requirements for the size and grade of steel specified.
404.3.3 Bending
Bends and hooks in stirrups or ties may be bent to the diameter of the
principal bar enclosed therein.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 211/437
404.3.4 Placing and Fastening
5/7/2018
All steel reinforcement shall be accurately placed in the position shown on
DPW H Blue Book - slide pdf.c om
the Plans or required by the Engineer and firmly held there during the placing and
setting ofisthe
spacing concrete.
less Bars shall
than 300mm be tied
in each at all intersections
directions, except
in which case, where
alternate
intersections shall be tied. Ties shall be fastened on the inside.
In lapped splices, the bars shall be placed in contact and wired together.
Lapped splices will not be permitted at locations where the concrete section is
insufficient to provide minimum clear distance of one and one-third the maximum
size of coarse aggregate between the splice and the nearest adjacent bar.
Welding of reinforcing steel shall be done only if detailed on the Plans or if
authorized by the Engineer in writing. Spiral reinforcement shall be spliced by
lapping at least one and a half turns or by butt welding unless otherwise shown on
the Plans.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 212/437
404.3.6 Lapping of Bar Mat
Sheets of mesh or bar mat reinforcement shall overlap each other
5/7/2018 sufficiently to maintain a uniform strength and shall be securely fastened at the
DPW H Blue Book - slide pdf.c om
ends and edges. The overlap shall not be less than one mesh in width.
The quantity of reinforcing steel to be paid for will be the final quantity
placed and accepted in the completed structure.
No allowance will be made for tie-wires, separators, wire chairs and other
material used in fastening the reinforcing steel in place. If bars are substituted
upon the Contractor’s request and approved by the Engineer and as a result
thereof more steel is used than specified, only the mass specified shall be
measured for payment.
When there is no item for reinforcing steel in the Bill of Quantities, costs will
be considered as incidental to the other items in the Bill of Quantities.
405.1 Description
405.1.1 Scope
This Item shall consist of furnishing, bending, placing and finishing concrete
in all structures except pavements in accordance with this Specification and
conforming to the lines, grades, and dimensions shown on the Plans. Concrete
shall consist of a mixture of Portland Cement, fine aggregate, coarse aggregate,
admixture when specified, and water mixed in the proportions specified or
approved by the Engineer.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 213/437
405.1.2 Classes and Uses of Concrete
5/7/2018 DPW H Blue Book - slide pdf.c om
and Seal. Each class shall be used in that part of the structure as called for on
the Plans.
Class C – Thin reinforced sections, railings, precast R.C. piles and cribbing
and for filler in steel grid floors.
63 2-1/2” 100
50 2” 100 95 – 100
37.5
25 1-1/2”
1” 95 –- 100 35 –- 70 100 95100
– 100
19.0 ¾” 35 – 70 - 100 95 – 100 -
12.5 ½” - 10 – 30 90 – 100 - 25 – 60
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 214/437
9.5 3/8” 10 – 30 - 40 – 70 20 – 55 -
4.75 No.4 0-5 0-5 0 – 15* 0 – 10* 0 – 10*
5/7/2018 * The measured cement content shall be within plus (+) or minus (-) 2 mass
DPW H Blue Book - slide pdf.c om
405.2.4 Water
It shall conform to the requirements of Item 710, Reinforcing Steel and Wire
Rope.
405.2.6 Admixtures
from each seventy five (75) cubic meters of each class of concrete or fraction
thereof placed each day.
5/7/2018 DPW H Blue Book - slide pdf.c om
405.4.2 Consistency
1. Portland Cement
2. Water
Water ofmay
accuracy be measured
measuring either
the water shall by
be volume or by of
within a range weight.
error of The
not
more than 1 percent.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 217/437
3. Aggregates
Stockpiling of aggregates shall be in accordance with Subsection
5/7/2018 DPW H Blue Book - slide pdf.c om
311.2.10. All aggregates whether produced or handled by hydraulic
methods or washed, shall be stockpiled or binned for draining for at
least 12 hours prior to batching. Rail shipment requiring more than12
hours will be accepted as adequate binning only if the car bodies permit
free drainage. If the aggregates contain high or non-uniform moisture
content, storage or stockpile period in excess of 12 hours may be
required by the Engineer.
The batching plant shall include separate bins for bulk cement, fine
aggregate and for each size of coarse aggregate, a weighing hopper,
and scales capable of determining accurately the mass of each
component of the batch.
6. Admixtures
Admixtures
minus three shall be measured into the mixer with an accuracy of plus or
(3) percent.
5/7/2018
Concrete may be mixed at the site of construction, at a central point or by a
DPW H Blue Book - slide pdf.c om
spillage of concrete takes place. The batch shall be so charge into the drum that
a portion of the water shall enter in advance of the cement and aggregates. The
flow of water shall be uniform and all water shall be in the drum by the end of the
first 15 seconds of the mixing period. Mixing time shall be measured from the
time all materials, except water, are in the drum. Mixing time shall not be less
than 60 seconds for mixers having a capacity of 1.5m 3 or less. For mixers having
a capacity greater than 1.5m3, the mixing time shall not be less than 90 seconds.
If timing starts, the instant the skip reaches its maximum raised position, 4
seconds shall be added to the specified mixing time. Mixing time ends when the
discharge chute opens.
Weighing
movement equipment
of other shall
operating be insulated
equipment against
in the plant. vibration
When or
the entire
plant is running, the scale reading at cut-off shall not vary from the
weight designated by the Engineer more than one mass percent for
cement, 1-1/2 mass percent for any size of aggregate, or one (1) mass
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 220/437
Cement shall be batched and charged into the mixer so that it will
not result in loss of cement due to the effect of wind, or in accumulation
of cement on surface of conveyors or hoppers, or in other conditions
which reduce or vary the required quantity of cement in the concrete
mixture.
The entire content of a batch mixer shall be removed from the drum
before materials for a succeeding batch are placed therein. The
materials composing a batch except water shall be deposited
simultaneously into the mixer.
All concrete shall be mixed for a period of not less than 1-1/2
minutes after all materials, including water, are in the mixer. During the
period of mixing, the mixer shall operate at the speed for which it has
been designed.
Mixers shall be operated with an automatic timing device that can be
locked by the Engineer. The time device and discharge mechanics
shall be so interlocked that during normal operation no part of the batch
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 221/437
directed be continued for not less than 100 revolutions after all
ingredients, including water, are in the drum. The mixing speed shall
not be less than 4 rpm, nor more than 6 rpm.
Mixing shall begin within 30 minutes after the cement has been
added either to the water or aggregate, but when cement is charged
into a mixer drum containing water or surface wet aggregate and when
o
the temperature is above 32 C, this limit shall be reduced to 15 minutes.
The limitation in time between the introduction of the cement to the
aggregate and the beginning of the mixing may be waived when, in the
judgement of the Engineer, the aggregate is sufficiently free from
moisture, so that there will be no harmful effects on the cement.
reducedtime
mixing to 30 seconds
in the and the
truck mixer mixing
shall be ascompleted
specified in
foratruck
truckmixing.
mixer. The
The quantity of structural concrete to be paid for will be the final quantity
placed and accepted in the completed structure. No deduction will be made for
the volume occupied by pipe less than 100mm (4 inches) in diameter or by
reinforcing steel, anchors, conduits, weep holes or expansion joint materials.
The
paid for at accepted quantities,
the contract measured
unit price as of
for each prescribed
the Pay in Section
Item listed405.5,
belowshall
that be
is
included in the Bill of Quantities.
finishing concrete including all labor, equipment, tools and incidentals necessary
to complete the work prescribed in the item.
5/7/2018 DPW H Blue Book - slide pdf.c om
406.1 Description
The materials for concrete and grout shall conform to Item 405, Structural
Concrete. The concrete shall be Class P as shown in Table 405.2, unless
otherwise shown on the Plans or specified in the Special Provisions. The
proportions of the grout will be as set out in Subsection 406.3.11, Bonding Steel.
It shall conform to the requirements of Item 710, Reinforcing Steel and Wire
Rope.
All prestressing steel shall be protected against physical damage and rust
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 224/437
This shipping package or form shall be clearly marked with a statement that
the package contains high-strength prestressing steel and the care to be used in
handling, and the type, kind and amount of corrosion inhibitor used, including the
date when placed, safety orders and instructions for use.
406.2.7 Enclosures
All of the materials specified for testing shall be furnished free of cost and
shall be delivered in time for tests to be made well in advance of anticipated time
of use.
The Contractor shall furnish for testing the following samples selected from
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 225/437
each lot, if ordered by the Engineer. The selection of samples will be made at the
manufacturer s plant by the Engineer or his representative.
5/7/2018 DPW H Blue Book - slide pdf.c om
1. For pretensioning work-samples at least 2 m long shall be furnished of
each size of wire or strand proposed.
furnished,
used. completed with distribution plates of each size and type to be
406.3.1 General
Steel units shall be accurately placed at the position shown on the Plans
and firmly held during the placing and setting of the concrete.
After installation in the forms, the end of ducts shall at all times be covered
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 227/437
as necessary to prevent the entry of water of debris.
All ducts for continuous structures shall be vented over each intermediate
5/7/2018
support, and at additional locations as shown on the Plans. Vents shall be 12.7
DPW H Blue Book - slide pdf.c om
steel. Prestressing
within ten steel,
(10) calendar installed,
days, shall betensioned
subject toand grouted
all the in this manner,
requirements all
in this Item
406.3.7 Pretensioning
Concrete shall not be deposited in the forms until the Engineer has
inspected the placing of the reinforcement, enclosures, anchorages and
prestressing steel and given his approval thereof. The concrete shall be vibrated
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 228/437
with care and in such a manner as to avoid displacement of reinforcement,
conduits, or wires.
5/7/2018 Prior to placing concrete, the Contractor shall demonstrate to the Engineer
DPW H Blue Book - slide pdf.c om
406.3.9 Curing
During the waiting period, the temperature within the curing chamber shall
not be less than 10.0oC (50oF) and live steam or radiant heat may be used to
maintain the curing chamber at the proper minimum temperature. The steam
shall be atfor100
moisture percent
proper relativeofhumidity
hydration to prevent
the cement. loss ofofmoisture
Application andshall
the steam to provide
not be
Radiant
hot water, heat
or by may be
electric appliedelements.
heating by means Radiant
of pipes circulating
heat curingsteam,
shall hot
be oil or
done
under a suitable enclosure to contain the heat and moisture loss shall be
minimized by covering all exposed concrete surfaces with plastic sheeting or by
applying an approved liquid membrane curing compound to all exposed concrete
surfaces. Top surface of concrete members to be used in composite construction
shall be clear of residue of the membrane curing compound so as not to reduce
bond below design limits.
406.3.10 Post-tensioning
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 229/437
After all concrete has attained the required strength, the prestressing
reinforcement shall be stressed by means of jacks to the desired tension and the
stress transferred to the end anchorage.
All side forms for girders shall be removed before post-tensioning. The
falsework under the bottom slab supporting the superstructure shall not be
released until a minimum of 48 hours have elapsed after grouting of the post-
tension tendons nor until all other conditions of the Specifications have been met.
the jack and the minimum tension, shall be determined in accordance with Article
1.6.7 of AASHTO Standard Specifications for Highway Bridges.
Suitable shims or other approved devices shall be used to insure that the
specified anchor set loss is attained.
tensioned bysimultaneously.
not be done jacking at each end of the tendon. Such jacking of both ends need
A record shall be kept of gage pressure and elongation at all times and
submitted to the Engineer for his approval.
Prestressing steel shall be bonded to the concrete by filling the void space
between the duct and the tendon with grout
.
Grout shall consist of Portland Cement, water and an expansive admixture
approved by the Engineer.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 230/437
Water shall first be added to the mixer followed by cement and admixture.
The grout shall be mixed in mechanical mixing equipment of a type that will
produce uniform and thoroughly mixed grout. The water content shall be not more
than 19 litres (5 gallons) per sack of cement. Retempering of grout will not be
permitted. Grout shall be continuously agitated until it is pumped.
of withstanding the pumping pressures. Valves and caps shall not be removed or
opened until the grout has set.
Immediately
be blown after completion
out with compressed of air
oil free thetoconcrete pour,
the extent the metal
necessary conduit
to break upshall
and
remove any mortar in the conduit before it hardens. Approximately 24 hours after
the concrete pour, the metal conduits shall be flushed out with water and then
blown out with compressed oil free air.
Prior to placing forms for roadway slabs of box girder structures, the
Contractor shall demonstrate to the satisfaction of the Engineer that all ducts are
unobstructed and if the prestressing reinforcement has been placed, that the steel
is free and unbonded in the duct.
After the tendons have been stressed to the required tension, each conduit
encasing the prestressing steel shall be blown out with compressed oil free air.
The conduit shall then be completely filled from the low end with grout under
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 231/437
pressure. Grout shall be pumped through the duct and continuously wasted at the
outlet until no visible slugs of water or air are ejected and the efflux time of ejected
5/7/2018
grout is not less than 11 seconds. All vents and openings shall then be closed
DPW H Blue Book - slide pdf.c om
and the grouting pressure at the injection end shall be raised to a minimum of
0.6894 MPa (100 psi) and held for a minimum of 10 seconds.
4.44 C after
Batches all ingredients
of grout are within
shall be placed added,45the batch after
minutes shallmixing.
be mixed for 3 minutes.
406.3.13 Handling
Contractor deems
position, it shall be itdone
expedient to transport
at his own ornotifying
risk after store precast units in of
the Engineer other
his than this
intention
to do so.
The manufacturing tolerances for pre-cast members shall not exceed those
given for length, cross-section and straightness on the Plans, as specified in the
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 232/437
Contract or as approved by the Engineer. In addition, where beams are laid side
by side in a deck:
5/7/2018 DPW H Blue Book - slide pdf.c om
1. The difference on soffit level between adjacent units before the in-situ
concrete is placed shall not exceed 5 mm for units up to 10 mm for
longer units.
2. The width of the deck soffit shall be within ±25 mm.
3. In adjacent span, the continuity of the outside beams shall be
maintained.
4. The width of gap between individual beams shall not exceed twice the
nominal gap.
5. The alignment of transverse holes shall permit the reinforcement or
prestressing cables to be placed without distortion.
The quantities of other Contract items which enter into the completed and
accepted structure will be measured for payment in the manner prescribed for the
several items involved.
407.1 Description
2. Reinforcing Steel
3. Structural Steel
Structural
materials steelMetal
in Item 403, shallStructures.
conform to the requirements of corresponding
5. Paints
b. AASHTO M 116 Primer for the use with Asphalt in dampproofing and
waterproofing.
c. AASHTO M 117 Woven cotton fabrics saturated with bituminous
substances for use in waterproofing.
d. AASHTO
proofing. M 118 Coal-Tar pitch for roofing, dampproofing and water-
e. AASHTO M 121 Creosote for priming coat with coal-tar pitch damp-
proofing and waterproofing.
f. AASHTO M 159 Woven burlap fabric saturated with bituminous
substances for use in waterproofing.
g. AASHTO M 166 Numbered cotton duck and array duck.
h. AASHTO M 239 Asphalt for use in waterproofing membrane
construction.
d. AASHTO M 213 Preformed expansion joint filler for concrete paving and
structural construction-non-extruding and resilient bituminous types.
Concrete shall not be placed until forms and reinforcing steel have been
checked and approved by the Engineer.
If lean
to placing of concrete is required
reinforcing in the
steel bar, the Plan
lean or as directed
concrete by the
should Engineer
have prior
a minimum
compressive strength of 13.8 MPa (2,000 psi )..
In preparation for the placing of concrete all sawdust, chips and other
construction debris and extraneous matter shall be removed from inside the
formwork, struts, stays and braces, serving temporarily to hold the forms in correct
shape and alignment, pending the placing of concrete at their locations, shall be
removed when the concrete placing has reached an elevation rendering their
service unnecessary. These temporary members shall be entirely removed from
pipes for conveying concrete to the forms shall be permitted only on written
authorization of the Engineer. The Engineer shall reject the use of the equipment
for concrete transportation that will allow segregation, loss of fine materials, or in
any other way will have a deteriorating effect on the concrete quality.
Open troughs and chutes shall be of metal lined; where steep slopes are
required, the chutes shall be equipped with baffles or be in short lengths that
When placing operations would involve dropping the concrete more than
1.5 m, concrete shall be conveyed through sheet metal or approved pipes. As far
as practicable, the pipes shall be kept full of concrete during placing and their
lower end shall be kept buried in the newly placed concrete. After initial set of the
concrete, the forms shall not be jarred and no strain shall be placed on the ends of
projecting reinforcement bars.
The concrete shall be placed as nearly as possible to its final position and
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 236/437
the use of vibrators for moving of the mass of fresh concrete shall not be
permitted.
5/7/2018 DPW H Blue Book - slide pdf.c om
407.3.1.1 Placing Concrete by Pneumatic Means
Pneumatic placing of concrete will be permitted only if specified in the
Special Provisions or authorized by the Engineer. The equipment shall be so
arranged that vibration will not damage freshly placed concrete.
Concrete shall not be placed in water except with approval of the Engineer
and under his immediate supervision. In this case the method of placing shall be
hereinafter specified.
A tremie shall consist of a tube having a diameter of not less than 250 mm
constructed in sections having flanged couplings fitted with gaskets with a hopper
at the top. The tremie shall be supported so as to permit free movement of the
discharge and over the entire top surface of the work and so as to permit rapid
lowering when necessary to retard or stop the flow of concrete. The discharge
end shall be closed at the start of work so as to prevent water entering the tube
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 237/437
and shall be completely submerged in concrete at all times; the tremie tube shall
be kept full to the bottom of the hopper. When a batch is dumped into the hopper,
5/7/2018 DPW H Blue Book - slide pdf.c om
the flow of concrete shall be induced by lightly raising the discharge end, but
always keeping it in the placed concrete. The flow shall be continuous until the
work is completed.
When the concrete is placed with a bottom-dump bucket, the top of the
bucket shall be open. The bottom doors shall open freely downward and outward
when tripped. The buckets shall be completely filled and slowly lowered to avoid
backwash. It shall not be dumped until it rests on the surface upon which the
concrete is the
well above to be deposited and when discharged shall be withdrawn slowly until
concrete.
inspected and approved materials for the concrete is at hand, and labor and
equipment are sufficient to complete the pour without interruption.
5/7/2018 DPW H Blue Book - slide pdf.c om
Where a “faster
top surface of a edge” might
wingwall, anbeinset
produced at a shall
formwork construction
be usedjoint, as in theansloped
to produce edge
thickness of not less than 15 cm in the succeeding layer. Work shall not be
discontinued within 50 cm of the top of any face, unless provision has been made
for a coping less than 50 cm thick, in which case if permitted by the Engineer, the
construction joint may be made at the underside of coping.
In general, the base slab of box culverts shall be placed and allowed to set
before the remainder of the culvert is constructed. In the construction of box
culverts the side walls and top slab may be constructed as a monolith.
If the concrete in the walls and top slab is placed in two separate
operations, special care shall be exercised in order to secure bonding in the
construction joint and appropriate keys shall be left in the sidewalls for anchoring
the top slab. Each wingwall shall be constructed, if possible, as a monolith.
Construction joints where unavoidable, shall be horizontal and so located that no
joints will be visible in the exposed face of the wingwall above the ground line.
structure shall not be allowed to come upon the bents until they have been in
place at least 14 days, unless otherwise permitted by the Engineer.
The concrete in the webs and the top slab shall be placed in one
continuous operation unless otherwise specified. If it is permitted to place the
concrete in more than one operation, the requirements for T-beam shall apply.
Construction joints shall be made only where shown on the Plans or called
for in the pouring schedule, unless otherwise approved by the Engineer. Shear
keys or reinforcement shall be used, unless otherwise specified, to transmit shear
or to bond the two sections together.
placed before the grout or mortar has attained its initial set.
5/7/2018 The placing of concrete shall be carried continuously from joint to joint.
DPW H Blue Book - slide pdf.c om
The face edges of all joints which are exposed to view shall be carefully finished
true to line and elevation.
Class 1,
Class 2, Ordinary Finish
Rubbed Finish
Class 3, Floated Finish
All concrete shall be given Class 1, Ordinary Finish and additionally any
further finish as specified.
below low water elevation or 50 cm below finished ground level when such ground
level is above the water surface. Wingwalls shall be finished from the top to 50
cm below the finished slope lines on the outside face and shall be finished on top
and for a depth of 20 cm below the top on the back sides.
Unless otherwise specified, the surface of the traveled way shall be Class
3, Floated Finish.
Immediately following the removal of forms, all fins and irregular protection
shall be removed from all surface except from those which are not to be exposed
or are not to be waterproofed. On all surfaces the cavities produced by form ties
and all other holes, honeycomb spots, broken corners or edges and other defects
shall be thoroughly cleaned, and after having been kept saturated with water for a
period of not less than three hours shall be carefully pointed and made true with a
mortar of cement and fine aggregate mixed in the proportions used in the grade of
the concrete being finished. Mortar used in pointing shall not be more than one
hour old. The mortar patches shall be cured as specified under Subsection
407.3.8. All construction and expansion joints in the completed work shall be left
carefully tooled and free of all mortar and concrete. The joint filler shall be left
exposed for its full length with a clean and true edges.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 241/437
The resulting surface shall be true and uniform. All repaired surfaces, the
5/7/2018 appearance of which is not satisfactory to the Engineer, shall be “rubbed” as
DPW H Blue Book - slide pdf.c om
specified below.
Sufficient
used in thetime shall of
pointing have elapsed
road before
holes and the wetting
defects down set.
to thoroughly to allow the mortar
Surfaces to be
finished shall be rubbed with a minimum coarse carborundum stone using a small
amount of mortar on each face. The mortar shall be composed of cement and
fine sand mixed in the proportions used in the concrete being finished. Rubbing
shall be continued until all form marks, protections and irregularities have been
removed, all voids have been filled, and a uniform surface has been obtained.
The face produced by this rubbing shall be left in place at this time.
After all concrete above the surface being created has been cast, the final
After striking off and consolidating as specified above, the surface shall be
made uniform by longitudinal or transverse floating or both. Longitudinal floating
will be required except in places where this method is not feasible.
The longitudinal float, operated from foot bridges, shall be worked with a
sawing motion while held in a floating position parallel to the road centerline and
passing gradually from one side of the pavement to the other. The float shall then
be moved forward one-half of each length and the above operation repeated.
Machine floating which produces an equivalent result may be substituted for the
above manual method.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 242/437
After the longitudinal floating has been completed and the excess water
removed, but while the concrete is still plastic, the slab surface shall be tested for
trueness with a straight-edge. For the purpose, the Contractor shall furnish and
use an accurate 3 m straight-edge swing handless 1 m longer than one half the
After the concrete has been deposited in place, it shall be compacted and
the surface shall be struck off by means of strike board and floated with a wooden
or cork float. An edging tool shall be used on all edges and at all expansion joints.
The surface shall not vary more than 3 mm under a 3 m straight-edge. The
surface shall have a granular or matted texture which will not slick when wet.
1. Water Method
the curing period the concrete surface shall be cleared of the curing
medium.
2. Curing Compound
4. Forms-in-Place Method
The top surface of highway bridge decks shall be cured by either the
curing compound method or the water method. The curing compound
shall be applied progressively during the deck finishing operations. The
Pre-cast concrete members shall be cured for not less than 7 days
by the water method or by steam curing. Steam curing for pre-cast
members shall conform to the following provisions:
The Contractor may review the falsework drawings at any time provided
sufficient time is allowed for the Engineer’s review before construction is started
on the revised portion.
Assumptions used in design of the falsework shall include but not be limited
to the following:
3. Soil bearing values and soil condition (wet and dry) shall be
designated by be
footings shall thedesigned
Contractortoon the falsework
carry the loads drawings. Falsework
imposed upon them
5/7/2018 DPW H Blue Book - slide pdf.c om
The falsework drawings shall show pedestrian openings which are required
through the falsework.
will furnish to the Contractor the amounts of camber necessary to compensate for
vertical alignment or anticipated structure deflection, if these are not shown on the
drawings. The total camber used in constructing falsework shall be the sum of
the aforementioned cambers.
The Contractor shall provide tell-tales attached to the soffit forms easily
readable and in enough systematically-placed locations to determine the total
settlement of the entire portion of the structure where concrete is being placed.
All debris and refuse resulting from work shall be removed and the site left
in a neat and presentable condition.
Concrete shall not be deposited in the forms until all work in connection
with constructing the forms has been completed, all materials required for the unit
to be poured, and the Engineer has inspected and approved said forms and
materials. Such work shall include the removal of all dirt, chips, sawdust and
other foreign material from the forms.
Formwork for concrete place under water shall be watertight. When lumber
is used, this shall be planed, tongued and grooved.
Anchor devices may be cast into the concrete for later use in supporting
forms or for lifting precast members. The use of driven types of anchorage for
fastening forms of form supports to concrete will not be permitted.
Forms and falsework shall not be removed without the consent of the
Engineer. The Engineer’s consent shall not relieve the Contractor of responsibility
for the safety of the work. Blocks and bracing shall be removed at the time the
forms are removed and in no case shall any portion of the wood forms be left in
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 251/437
the concrete.
Falsework removal for continuous or cantilevered structures shall be as
5/7/2018 DPW H Blue Book - slide pdf.c om
directed by the Engineer or shall be such that the structure is gradually subjected
to its working stress.
When concrete strength tests are used for removal of forms and supports,
such removal should not begin until the concrete has attained the percentage of
the specified design strength shown in the table below.
Forms and falsework shall not be released from under concrete without first
determining if the concrete has gained adequate strength without regard to the
time element. In the absence of strength determination, the forms and falsework
are to remain in place until removal is permitted by the Engineer.
The forms for footings constructed within cofferdams or cribs may be left in
place when, in the opinion of the Engineer, their removal would endanger the
safety of the cofferdam or crib, and when the forms so left intact will not be
exposed to view in the finished structure. All other forms shall be removed
whether above or below the ground line or water level.
All forms shall be removed from the cells of concrete box girders in which
utilities are present and all formwork except that necessary to support the deck
slab shall be removed from the remaining cells of the box girder.
at the back of abutments has been placed up to the spring line. Falsework
supporting the deck of rigid frame structure shall not be removed until fills have
been placed back to the vertical legs.
with the Specifications for piling, concrete metal reinforcement, structural steel
and other items which constitute the completed structure.
408.2 Materials
All materials shall conform to the detailed requirements specified for the
component parts of the completed structure. Where special materials are
required, they shall be shown on the Plans or in the Special Provisions.
During the progress of the work the Contractor shall have a competent
foreman or superintendent experienced in steel erection in personal charge of
carrying out the work in full accordance with the Plans and Specifications.
Erection diagrams shall be approved by the Director, Bureau of Design.
Steel and timber shall be placed on skids above the ground and shall be
kept clean. The underlying ground shall be kept free from vegetation and properly
drained. Girders and beams shall be placed upright and shored. Long members,
such as columns and chords, shall be supported on skids placed close enough
together to prevent injury by deflection. The Contractor shall be responsible for
the loss of any material, which has been paid for by the Bureau, while it is in his
care, or for any damage, resulting from his work. The loading, transporting,
unloading and piling of structural material shall be so conducted that the metal
will be kept free from injury from rough handling.
408.3.3 Erection
The Contractor shall furnish and place all falsework, erect all metal work,
remove the temporary construction, and do all work required to complete the
structure as covered by the Contract, including the removal of the old structure or
structures if so stipulated, all in accordance with the Plans and these
Specifications.
The Contractor shall provide all tools, machinery, and appliances including
drift pins and fitting up bolts, necessary for the expeditious handling of the work.
place, until the tension chord splices are fully riveted and all other truss
connection pinned and bolted. Rivets in splices of butts joints of compression
members and rivets in railings shall not be driven until the span is swung. Splices
and filled connections shall have one-half of the holes filled with bolts and
cylindrical erection pin (half bolts and half pins) before riveting. Splices and
connections carrying traffic during erection shall have three-fourths of the holes so
filled. Fitting up bolts shall be of the same nominal diameter as the rivets and
cylindrical erection pins shall be 0.75 mm (1/32 inch) larger.
408.3.4 Welding
Before beginning the field riveting, the structural steel shall be adjusted to
correct grade and alignment and elevation of panel points (end of floor beams)
properly regulated. For truss spans a slight excess camber will be permitted while
the bottom chords are being riveted.
In bolted connections, the nut shall be drawn up tight and set by center
punching the threads of the bolt at the face of the nut.
Pilot and driving nuts shall be used in driving pins. Pins shall be so driven
that the members will take full bearing on them. Pin nuts shall be screwed up tight
and threads burred at the face of the nut with a center punch.
Shoes and bearing plates shall not be placed on bridge seat bearing areas
that are improperly finished or that are deformed or irregular. They shall be set
level in exact position and elevation and shall have full even bearing. Unless
otherwise specified, the shoes and bearing plates shall be set by the following
methods:
a. The bridge seat bearing area shall be heavily coated with lead paint and
then covered with three layers of 340 2 to 369 8 g (12 to 14 ounces)
least 96 hours, adequate provision being made to keep the grout well
moistened during this period. The grout shall consist of one part
Portland Cement to one part fine-grained sand.
The location of the anchor bolts in relation to the slotted holes in the
expansion shoes correspond to the temperature at the time of erection. The nuts
on the anchor bolts at the expansion end of spans shall be adjusted to permit the
free movement of span. Anchor bolt nuts shall be set by center punching the
threads of the bolts at the face of the nut.
408.3.13 Painting
Unless otherwise specified, metal work shall be given two shop coats of red
lead paint and two field coats of paint as specified under Item 411, Paint.
On steel spans, the concrete floor shall not be placed until the span has
been swung or released from the falsework.
Timber floors of the species and grade indicated on the plans shall be built
as specified under Timber Structures, Item 402.
All materials and work of erection shall be subject to the inspection of the
Engineer, who shall be given all facilities required.
Materials and workmanship not previously inspected will not inspected after
its delivery to the site of the work. Any materials inspected and accepted prior to
delivery on the work shall be subject to rejection if found defective after delivery.
409.1 Description
This work shall consist of the joining of structural steel members with welds
of the type, dimensions, and design shown on the Plans and in accordance with
the Specifications.
Welding of Structural Steel shall be done only when shown on the Plans or
authorized in writing by the Engineer.
409.3.1 Equipment
409.3.1.1 General
All items of equipment for welding and gas cutting shall be so designed and
manufactured and in such condition as to enable qualified welders to follow the
procedures and attain the results prescribed in this Specification.
Electrode holders shall grip the electrode firmly and with good electrical
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 259/437
contact.
Approved automatic welding heads may be used, with suitable auxiliary
5/7/2018 DPW H Blue Book - slide pdf.c om
handling equipment to provide automatic instead of manual control of electrode
and welding arc.
Torches and tips shall be of proper size and type of the work at hand.
Suitable regulators shall afford the welder complete control over the pressure and
rate of flow of each gas.
409.3.2 Welding
409.3.2.1 General
Surfaces to be welded shall be smooth, uniform and free from fins, tears,
and other defects which would adversely affect the quality of the weld. Edges of
material shall be trimmed by machining, chipping, grinding, or machine gas-cutting
to produce a satisfactory welding edge wherever such edge is thicker than: 13 mm
for sheared edge of material; 16 mm for toes of angles or rolled shapes (other
than wide flange sections); 25 mm for universal mill plate or edges of flange
sections.
The width of root face used, shall be not more than 1.5 mm for parts less
than 10 mm in thickness nor more than 3 mm for parts 10 mm or more in
thickness.
Butt welds shall be proportioned so that their surface contours will lie in
gradual transition curves. For butt welded joints between base metal parts of
unequal thickness, a transition shall be provided on a slope or level not greater
than 1 in 2.5 to join the offset surfaces. This transition may be provided by sloping
the surface of the weld metal or by bevelling the thicker part or by combination of
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 260/437
these two methods.
Surfaces to be welded shall be free from loose scale, slag, rust, grease or
5/7/2018
other material that will prevent proper welding. Mill scale that withstands vigorous
DPW H Blue Book - slide pdf.c om
wire brushing or a light film of drying oil or rust inhibitive coating may remain.
Surfaces within 50 mm of any weld location shall be free of any paint or other
material that would prevent proper welding or produce objectionable fumes while
welding.
409.3.2.2 Welders
All welding shall be done by approved competent and experienced and fully
qualified welders
The parts to be joined by fillet welds shall be brought into a close contact
as practicable, and no event shall be separated more than 5 mm. If the
separation is 1.5 mm or greater, the leg of the fillet weld shall be increased by the
amount of separation. The separation between faying surfaces of lap joints and of
butt
whichjoints
are landing on a
not sealed bybacking structure shall
welds throughout theirnot exceed
length shall1.5
bemm. The fit close
sufficiently of joints
to
exclude water after painting. Where irregularities in rolled shape or plates, after
straightening, do not permit contact within the above limits, the procedure
necessary to bring the material within these limits shall be subject to the approval
of the Engineer.
be drawn into a greater slope than two degrees (1 in 30). Measurement of offset
shall be between centerline of parts unless otherwise shown on the Plans.
When parts abutting edge to edge differ in thickness, the joint shall be of
such form that the slope of either surface through the transition zone does not
exceed 1 in 2.5, the thicker part being bevelled, if necessary.
Plug and slot welds may be used to transmit shear in a lap joint or to
The length of the slot for a slot weld not exceed ten times the thickness of
the weld. The width of the slot shall not be less than the thickness of the part
containing it plus 8 mm nor shall it be greater than 2.25 times the thickness of the
weld.
The ends of the slot shall be semicircular or shall have the corners rounded
to a radius not less than the thickness of the part containing it, except those ends
which extend to the edge of the part.
The minimum spacing of lines of slot welds in a direction transverse to their
length shall be 4 times the width of the slot. The minimum center to center
spacing in a longitudinal direction on any line shall be 2 times the length of the
slot.
Tack welds, located where the final welds will later be made, shall be
subject to the same quality requirements as the final weld. Tack welds shall be as
small as practicable and where encountered in the final welding, shall be cleaned
and fused thoroughly with the final weld. Defective, cracked or broken tack welds
shall be removed before final welding.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 262/437
Members or component parts of structures shall be assembled and
5/7/2018 matchmarked prior to erection to insure accurate assembly and adjustment of
DPW H Blue Book - slide pdf.c om
position on final erection. Painted assembly marks shall be removed from any
surface to be welded.
A weld designed to sustain tensile stress shall be made in such a way that
their welding is being performed at any point, all parts that would offer restraint
against shrinkage can shrink, deform or move enough to preclude serious
shrinkage stresses.
The ends of all butt welds in flanges of beams and girders shall be made
with extension bars regardless of the thickness of such flanges.
Welding shall not be done when surfaces are wet from condensation or rain
which is falling on the surfaces to be welded; nor during periods of high winds
unless the welding operator and the work are properly protected
Arc lengths and electrical potential and current shall be suited to the
thickness of material, type of groove and other circumstances attendant to the
work.
1. The maximum size for flat position welding of all passes except the root
pass shall be 8 mm.
2. The maximum size for horizontal fillet welds shall be 6 mm.
The electrode for the single pass fillet weld and for the root passes of all
multiple layer welds in all cases shall be of the proper size to insure thorough
fusion and penetration with freedom from slag inclusions.
A singleparallel
up of several layer of the weld
beads, shallmetal, whether
not exceed 3 mmdeposited-in oneexcept
in thickness pass or made
that the
bead at the root may be 6 mm in thickness if the position of welding and the
viscosity of the weld metal permit control of the latter so that it does not over flow
upon unfused base metal.
The maximum size of fillet weld which may be made in one pass shall be 8
mm except that for vertical welds made upward the maximum size made in one
pass shall be 13 mm.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 264/437
In vertical welding the first root pass shall be formed from the bottom
5/7/2018
upward. Succeeding passes may be formed by any technique that will fulfill the
DPW H Blue Book - slide pdf.c om
1. Complete fusion between the base metal and the deposited weld metal
is obtained.
3. The molten weld metal floats all slag, oxide and gases to the surface
behind the advancing arc.
Each time the arc is started either to begin a weld or to continue partly
Before welding over previously deposited metal, the slag shall be removed
and the weld and adjacent base metal shall be brushed clean. This requirement
shall apply not only to cratered areas but also when welding is resumed after any
interruption. It shall not, however, restrict the making of plug and slot welds, in
accordance with the following paragraphs.
1. For flat welds, the arc shall be carried around the root of the joint and
then weaved along a spiral path to the center of the hole, fusing and
depositing a layer of weld metal in the root and bottom of the joint. The
arc shall then be carried to the periphery of the hole, and the procedure
repeated, fusing and depositing successive layers to fill the hole to the
depth required. The slag covering the weld metal shall be kept molten,
or nearly so, until the weld is finished. If the arc is broken, except briefly
for changing electrodes, the slag must be allowed to cool and shall be
3. For overhead welds, the procedure shall be the same as for flat welds
except that the slag shall be allowed to cool and shall be completely
5/7/2018
removed after depositing each successive layer until the hole is filled to
DPW H Blue Book - slide pdf.c om
Slot welds shall be made with a technique similar to that specified above
for plug welds, except that if the length of the slot exceeds three times the width,
or if the slot extends to the edges of the part of the technique specified above for
making plug welds shall be followed for the type of flat position welds.
The following tabulation shows that the relation between weld size and the
maximum thickness of material on which various sizes of fillet welds may be used:
The maximum size of fillet weld that may be used along the edge of
material 6 mm or more in thickness shall be 1.5 mm less than the thickness of the
material.
The minimum effective length of fillet weld shall be four times its size and in
no case less than 38 mm.
2. The clear spacing in the direction of stress of stitch welds that connect
plates to other plates or to shapes shall not exceed:
5/7/2018 DPW H Blue Book - slide pdf.c om
a. For compression members ….10 times the thickness of the thinner
part but not more than 300 mm.
b. For tension members ….. 14 times the thickness of the thinner part
but not more than 300 mm.
The spacing transverse to the direction of stress shall not exceed
24 times the thickness of the thinner part connected.
Fillet welds in holes or slots may be used to transmit shear in lap joints or
to prevent the buckling or separation of lapped parts. The fillet welds in a hole or
slot may overlap
design requirements shall not be a cause for rejection, but in case excess weld
metal involves serious malformation, such work shall be rejected.
All fillet welds shall be of acceptable types. All fillet welds that carry
reversed stresses running in a direction perpendicular to their longitudinal axis
shall be of the concave type or the 0-gee type when the fillet weld is flushed with
the edge of a member. When one of these types is specifically indicated on the
Plans for a weld, it shall be of that type.
All butt welds, except produced with aid of backing material, shall have the
root of the initial layer chipped out or otherwise cleaned to sound metal and
welded in accordance with the requirements of the Specification. Butt welds
made with
have the themetal
weld use of a backing
thoroughly of the
fused withsame materials
the backing as the base metal shall
materials.
Ends of butt welds shall be extended past the edges of the parts joined by
means of extension bars providing a similar joint preparation and having a width
not less than the thickness of the thicker part jointed; or for material 19 mm or less
in thickness, the ends of the welds shall be chipped or cut down to solid metal and
side welds applied to fill out the ends to the same reinforcement as the face of the
welds. Extension bars shall be removed upon completion and cooling of the weld
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 267/437
and the ends of the weld made smooth and flush with the edges of the abutting
parts.
5/7/2018 DPW H Blue Book - slide pdf.c om
409.3.2.8 Quality of Welds
Weld metal shall be solid throughout except that very small gas pockets
and small inclusions of oxide or slag may be accepted if well dispersed and if
none exceeds 1.5 mm in greatest dimension, and if the sum of the greatest
dimensions of2 all such defects of weld metal area does not exceed 15 mm in an
area of 10 cm .
There shall be complete fusion between the weld metal and the base metal
and between successive passes throughout the joint.
Welds shall be free from overlap and the base metal free from
undercutting. All craters shall be filled to the full cross-section of the welds.
Painting shall not be done until the work has been accepted and shall be in
accordance with the Specification. The surface to be painted shall be cleaned of
spatter, rust, loose scale, oil and dirt. Slag shall be cleaned from all welds.
409.3.2.12 Identification
The operator shall place his identification mark with crayon, or paint, near
the welds made by him.
409.3.2.13 Inspection
The size and contour of welds shall be measured with suitable gauges.
The size and contour of welds shall be measured with suitable gauges.
The inspector shall identify with a distinguishing mark all welds that he has
5/7/2018
inspected and accepted. DPW H Blue Book - slide pdf.c om
The Contractor shall remove and replace, or correct as instructed, all welds
found defective or deficient. He shall also replace all methods found to produce
inferior results, with methods which will produce satisfactory work.
In the event that fault welding or the removal for rewelding of faulty welding
shall damage the base metal, the Contractor shall remove and replace the
damaged material.
410.1 Description
This Item shall consist of structural timber of the specie and size called for
on the Plans, either treated or untreated as called for in the Proposal. It shall
include the furnishing of the timber, the framing, erecting, furnishing of hardware
and the furnishing of paint and paintings if paint is called for on the Plans or in the
Special Provisions.
410.2 Material Requirements
410.2.1 Timber
Timber shall be the specie specified on the Plans. Unless otherwise noted
on the Plans or in the Special Provisions, only the best grade shall be used. It
shall be free
any defect from will
which loose knots,
impair its splits,
strengthworm holes decay,
or render warp,
it unfit for ring separation,
its intended use. Anyor
specie specified on the Plans may be used for untreated timber and if that specie
is not available, a specie of equivalent strength and durability may be used if
authorized by the Engineer. If the timber is to be treated, only those species shall
be used which are known to possess properties which make them favorable to
treatment.
410.2.2 Paint
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 270/437
410.2.3 Hardware
410.2.4 Preservatives
Wh ti b i i t d d f i th t t l il bl d
The minimum penetration of the preservative into the surface of the timber
shall be 20 mm. The minimum retention of the preservative per cubic metre of
timber shall be as follows:
The Engineer shall be notified at least 10 days in advance of the date that
the treating process will be performed in order that the untreated timber, the
treatment shall
Engineer process, andthe
inspect thetimber
finished
priortreatment timber
to treatment may all beconformance
to determine inspected. with
The
those Specifications and suitability of conditions for treatment. He shall be
permitted free access to the plant in order that temperatures, pressures and
quantities and type of treatment materials used may be observed. Samples of the
creosote or creosote petroleum oil mixture shall be furnished as required for tests.
plugs approximately 1.6 mm larger in diameter that the bit used in boring the
holes.
Any excessive checking caused by the treating process shall be cause for
rejection of the pieces in which the excessive checking occurs.
the nominal dimension of the timber even though the actual dimensions may be
scant. The measurement of timber shall include only such timber as a part of the
completed and accepted work and will not include any timber required for a
falsework, bracing or other timber required in the erection.
411.1 Description
5/7/2018 This Item shall consist of furnishing and applying all paint materials
DPW H Blue Book - slide pdf.c om
including vehicles, pigments, pastes, driers, thinners and mixed paints for steel
and wooden structures; sampling testing and packing; preparation of the surface
and application of paint to structures.
411.2.1 General
1. The paint shall show no excessive settling and shall easily redisperse
with a paddle to a smooth, homogeneous state. The paint shall show
no curdling, livering, caking or color separation and shall be free from
lumps and skins.
3. The paint shall dry to a smooth uniform finish, free from roughness grit,
unevenness and other imperfections.
4. The paint shall not skin within 48 hours in a ¾ filled tightly closed
container.
411.2.2 The paint shall conform to the requirements of the Specifications indicated
as follows:
411.2.3 Drier
This Specification covers both straight oil drier (material free from resins
and gums), and Japan drier (material containing varnish gums). The drier shall be
composed of lead manganese or cobalt or a mixture of any of these elements,
combined with a suitable fatty oil, with or without resins or gums, and mineral
spirits or turpentine, or a mixture of these solvents. The drier shall conform to the
following requirements:
1 A F f di d d d
4. Drying – It shall mix with pure raw linseed oil in the proportion of 1
volume of drier to 19 volume of oil without curdling and the resulting
mixture when flowed on glass shall dry in not more than 18 hours.
5. Color – When mixed with pure, raw linseed oil in the proportion of 1
volume of drier to 8 volume of oil, the resulting mixture shall be darker
than a solution of 6 grams of Potassium Dichromate in 13 cc of pure
Sulfuric Acid (sp.gr. 1.84).
thoroughly stirred to insure a uniform mixture, and the paint shall be suitably
stirred during use. The paint shall be mixed on the job and only enough for one
5/7/2018
day’s use shall be mixed at one time. DPW H Blue Book - slide pdf.c om
When two field coats of aluminum paint are specified, the first coat shall be
tinted with lampblack paste or Prussian blue paste in the quantity of 24 grams/liter
of paint. The exact quantity used shall be sufficient to give a contrast in color
which can be readily distinguished. When three field coats of aluminum paint are
specified, the second coat shall be tinted.
The paint shall be mixed as specified for Aluminum Paint for Structural
Steel except that the proportions shall be 270 grams of aluminum powder or paste
to one litre of vehicle.
vehicle, the name and address of the manufacturers, and the stencil of the
authorized inspecting agency. Any package or container not so marked will not
be accepted for use.
1. obtained
One 20-litre can
for 100 sample
cans of the in originalmaterial
delivered unopened container
or 10% shall be
fraction thereof.
411.3.6 Painting
411.3.6.1
The painting of structure shall include the proper preparation of the surface;
the application, protection and drying of the paint coatings, the protection of the
pedestrians, vehicular or other traffic upon or underneath the structures, the
protection of all parts of the structure (both superstructure and substructure)
against disfigurement by spatters, splashes and smirches of paint or of paint
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 275/437
materials; and the supplying of all tools, tackle, scaffolding labor, paint and
materials necessary for the entire work.
5/7/2018 DPW H Blue Book - slide pdf.c om
Paint shall not be applied during rain, storms or when the air is misty, or
when, in the opinion of the Engineer, conditions are otherwise unsatisfactory for
the work. Paint shall not be applied upon damp surfaces or upon metal which has
absorbed heat sufficient to cause the paint to blister and produce a pervious paint
film.
No wide flat brush shall be used. All brushes preferably shall be either
round or oval but if flat brushes are used, they shall not exceed 100 mm in width.
1. Hand Cleaning
The removal of rust, scale and dirt shall be done by the use of metal
brushes, scrapers, chisels, hammers or other effective means. Oil and
grease shall be removed by the use of gasoline or benzene. Bristle or
wood fiber brushes shall be used for removing loose dust.
2. Sandblasting
3. Flame Cleaning
free materials and foreign particles. Compressed air shall not be used
for this operation. Paint shall be applied promptly after the steel has
been cleaned and while the temperature of the steel is still above that of
the surrounding atmosphere, so that there will be no recondensation of
moisture on the cleaned surfaces.
When all
accepted, fabrication
all surfaces notwork is completed
painted and hasshall
before assembling beenbetentatively
given two
coats of Red Lead Shop Paint conforming to the requirements of this
Specification. (The inside of top chords for trusses and laced members
or inaccessible parts, except contact surfaces, may be painted before
assembling). Shipping pieces shall not be located for shipment until
thoroughly dry. No painting shall be done after loading the materials on
transport vehicles.
As soon as the Engineer has examined and approved all field rivets,
the heads of such rivets and field bolts, all welds and any surfaces from
which the shop coat of paint has become worn off or has otherwise
become defective, shall be cleaned and thoroughly covered with one
the creosoted materials and keep them from contact with same until ready for
erection.
411.3.6.2,
loose paint Painting
shall beStructural
removed Steel, with thechipping,
by scraping, added provisions
or brushingthat as
all may
dead be
or
necessary. Timber railings, name plates, planking and other interfering parts shall
be removed before cleaning is begun and shall be replaced after the painting has
been completed and the last coat has thoroughly dried. The application of the
coat shall be as specified under Subsection 411.3.6.2, (5), Field Painting of
Structural Steel.
Painting shall not be measured and paid for separately, but the cost thereof
shall be considered as included in the contract unit price of the items where called
for.
412.1 Description
5/7/2018 412.1.1 Scope DPW H Blue Book - slide pdf.c om
This Item shall consist of the requirement for elastomeric bearing pads
whose main function is to transfer loads or accommodate relative movement
between a bridge superstructure and its supporting structure, or both while
avoiding damaging strain and additional tension. Elastomeric bearings shall
include unreinforced pads (consisting of elastomer only) and reinforced bearings
with steel laminates.
A laminated bearing pad is required when the thickness of the plain pad is
more than 31.75 mm and the compressive strain is more than 15%.
The elastomer for the manufacture of the bearing is furnished in two types
as follows:
Steel laminates used for reinforcement shall be made from rolled mild steel
conforming to ASTM A 36, A 570 or equivalent, unless otherwise specified by the
Engineer. The laminates shall have a minimum nominal thickness of 20 gage.
Table 2 – Tolerances
Mm
Overall vertical dimensions
Design thickness 32 mm (1 ¼ in) or less -0, +3
Design thickness over 32 mm (1 ¼) -0, +6
Overall horizontal dimensions
914 mm (36 in) and less -0, +6
Over 914 mm
Thickness (36 in) layers of
of individual ±20 percent -0, +12
of design value but
elastomer (laminated bearing only) at no more than ±3 mm (1/8 in)
any point within the bearing
Variation from a plane parallel to the
theoretical surface: (as determined by
measurements at the edge of the
bearings)
Top Slope relative to the bottom of
no more than 0.005 radian
Sides 6
Position of exposed connection members 3
Edge cover of embedded laminated -0, +3
connection members
Size of holes, slots or inserts ±3
Position of holes, slots, or inserts ±3
Bearings shall be placed on surfaces that are plane to within 1.6 mm and
unless the bearings are placed in opposing pairs, horizontal to within 0.01 radians.
Any lack of parallelism between the top of bearing and the underside of the
girder that exceeds 0.01 radians shall be corrected either grinding of the surface,
grout pack bearing seats or modification of the bearing such that the intended
bearing placement is as originally designed with the least amount of bearing
Dismantling at the site shall not be done unless absolutely necessary for
inspecting or installation.
412.3.2 Sampling
For acceptance purposes, bearing from within the lot shall be selected at
random as samples for inspection and testing.
A minimum of three bearings shall be taken from the lot for testing. If the
number of bearings in the lot exceeds 50 then for each additional 50 or part
thereof, one additional bearing shall be taken for testing.
layer thickness that exceed the tolerances in Table 2, the bearing shall be
rejected.
3. If there are at least three separate surface cracks which are each at
5/7/2018 DPW H Blue Book - slide pdf.c om
least 2 mm wide and 2 mm deep. The bearing shall be rejected.
4. Record the median compressive stiffness (K) of the bearing of median
stiffness.The compressive stiffness of each bearing tested shall not differ form (K)
by more 5. than
For 10%.
each bearing that fails to meet the requirements in (1), two
additional bearings maybe sampled and shall meet the requirements in (1) or
the lot shall be rejected.
6. If the lot is not rejected, the bearing of median stiffness (K) shall be
subjected to the elastomeric material tests in (2).
Preformed sponge rubber and cork expansion joint fillers for concrete
paving and structural construction shall conform to the applicable requirements of
AASHTO M 153.
500.1 Description
Reinforced
sewerconcrete
pipe culvert, storm drain and AASHTO M 170
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 286/437
Asbestos cement pipe for culverts and storm drains AASHTO M 217
Joint Mortar – Joint mortar for concrete pipes shall consist of 1 part, by
volume of Portland Cement and two (2) parts of approved sand with water as
Oakum – Oakum for joints in bell and spigot pipes shall be made from
hemp (Cannavis Sativa) line or Benares Sunn fiber or from a combination of
these fibers. The oakum shall be thoroughly corded and finished and practically
free from lumps, dirt and extraneous matter.
material samples
materials will be obtained
quality requirements. for shall
This laboratory
be thetesting
basis for
forcompliance
acceptancewith
of
manufacturing lots as to quality.
The completed trench bottom shall be firm for its full length and width.
Where required, in the case of crop drains, the trench shall have a longitudinal
camber of the magnitude specified.
For flexible pipe, the bed shall be roughly shaped and a bedding
blanket of sand or fine granular material as specified above shall be provided as
follows:
10 mm 25 mm
25 mm 50 mm
50 mm 75 mm
For large diameter structural plate pipes the shaped bed need not
exceed the width of bottom plate.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 288/437
500.3.3 Laying Conduit
5/7/2018 DPW H Blue Book - slide pdf.c om
The conduit laying shall begin at the downstream end of the conduit line.
The lower segment of the conduit shall be in contact with the shaped bedding
throughout its full length. Bell or groove ends of rigid conduits and outside
circumferential laps of flexible conduits shall be placed facing upstream. Flexible
conduit shall be placed with longitudinal laps or seams at the sides.
Joints shall be made with (a) Portland Cement mortar, (b) Portland
Cement grout, (c) rubber gaskets, (d) oakum and mortar, (e) oakum and joint
compound, (f) plastic sealing compound, or by a combination of these types, or
any other type, as may be specified. Mortar joints shall be made with an excess
of mortar to form a continuous bead around the outside of the conduit and
finished smooth on the inside. For grouted joints, molds or runners shall be used
to retain the poured grout. Rubber ring gaskets shall be installed so as to form a
flexible water-tight seal. Where oakum is used, the joint shall be called with this
material and then sealed with the specified material.
When Portland Cement mixtures are used, the completed joints shall be
protected against rapid drying by any suitable covering material.
Conduits shall be inspected before any backfill is placed. Any pipe found
to be out of alignment, unduly settled, or damaged shall be taken up and relaid or
replaced.
500.3.6 Backfilling
Materials for backfilling on each side of the conduit for the full trench width
and to an elevation of 300 mm above the top of the conduit shall be fine, readily
compactible soil or granular material selected from excavation or from a source
When the top of the conduit is flushed with or below the top of the trench,
backfill material shall be placed at or near optimum moisture content and
compacted in layers not exceeding 150 mm (compacted) on both sides to an
elevation 300 mm above the top of the conduit. Care shall be exercised to
thoroughly compact the backfill under the haunches of the conduit. The backfill
shall be brought up evenly on both sides of the conduit for the full required
length. Except where negative projecting embankment-type installation is
specified, the backfill material shall be placed and compacted for the full depth of
the trench.
When the top of the conduit is above the top of the trench, backfill shall be
placed at or near optimum moisture content and compacted in layers not
exceeding 300 mm (compacted) and shall be brought up evenly on both sides of
the conduit for its full length to an elevation 300 mm above the top of the conduit.
The width of the backfill on each side of the conduit for the portion above the top
of the trench shall be equal to twice the diameter of the conduit or 3.5 m,
whichever is less. The backfill material used in the trench section and the portion
above the top of the trench for a distance on each side of the conduit equal to the
horizontal inside diameter and to 300 mm above the top of the conduit shall
conform to the requirements for backfill materials in this Subsection. The
remainder of the backfill shall consist of materials from excavation and borrow
that is suitable for embankment construction.
Compaction
achieved to the density
by use of mechanical specified
tampers or byinrolling.
Item 104, Embankment, shall be
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 290/437
All conduits after being bedded and backfill as specified in this Subsection
shall be protected by one metre cover of fill before heavy equipment is permitted
5/7/2018
to cross during construction of the roadway. DPW H Blue Book - slide pdf.c om
Under this method, for rigid conduit, the embankment shall be completed
as described in Subsection 500.3.6, Backfilling, to a height above the conduit
equal to the vertical outside diameter of the conduit plus 300 mm. A trench equal
in width to the outside horizontal diameter of the conduit and to the length shown
on the plans or as directed by the Engineer shall then be excavated to within 300
mm of the top of the conduit, trench walls being as nearly vertical as possible.
The trench shall be loosely filled with highly compressible soil. Construction of
When the Bid Schedule contains an estimated quantity for “Furnishing and
Placing Backfill Material, Pipe Culvert”, the quantity to be paid for will be the
number of cubic metre complete in place and accepted, measured in final
position between limits as follows:
2. When the original ground line is less than 300 mm above the top
of the pipe, the measurement will also include the placing of all
backfill materials, above the original ground line adjacent to the
pipe for a height of 300 mm above the top of pipe and for a
distance
horizontalon each side
dimension of the
of the pipe not greater than the widest
pipe.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 291/437
When the Bid Schedule does not contain as estimated quantity for
“Furnishing and Placing Backfill Material, Pipe Culvert” payment for placing
backfill material around pipe culverts will be considered as included in the
payment for excavation of the backfill material.
501.1 Description
Subdrainage pipe of the type and size specified shall be embedded firmly
in the bedding material.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 293/437
Perforated pipe shall normally, be placed with the perforations down and
the pipe sections shall be joined securely with the appropriate coupling fittings or
5/7/2018 DPW H Blue Book - slide pdf.c om
bands.
Non-perforated pipe shall be laid with the bell end upgrade and with open
joints wrapped with suitable material to permit entry of water, or unwrapped as
may be specified. Upgrade end sections of all subdrainage pipe installations shall
be closed with suitable plugs to prevent entry of soil materials.
After the pipe installation has been inspected and approved, granular
backfill material shall be placed to a height of 300 mm above the top of pipe.
Care shall be taken not to displace the pipe or the covering at open joints. The
Trenches for blind drains shall be excavated to the width and depth shown
on the Plans. The trench shall be filled with granular backfill material to the depth
required by the Plans. Any remaining upper portion of trench shall be filled with
either granular or impervious material in accordance with Item 103, Structure
Excavation.
Underdrains and outlets shall be measured by the linear meter for pipe of
the type and size specified. Blind drains shall be measured by the linear meter
including all excavation and backfill materials required.
Concrete for these structures shall meet the requirements of Item 405,
Structural Concrete. Other materials shall meet the following specifications:
Corrugated Metal Units – The units shall conform to Plan dimensions and
the metal to AASHTO M 36. Bituminous coating, when specified, shall conform to
ASTM D 1187, Asphalt-base Emulsion for use as Protective Coating for Metal.
Joint Mortar- Unless otherwise indicated on the Plans, joints mortar shall
be composed of one part Portland Cement and two parts fine aggregate by
volume to which hydrated lime has been added in an amount equal to 10 percent
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 295/437
of the cement by weight. All materials for mortar shall meet the requirements of
of the cement by weight. All materials for mortar shall meet the requirements of
Item 405, Structural Concrete.
5/7/2018 DPW H Blue Book - slide pdf.c om
Frames, Gratings, Covers and Ladder Rungs – Metal units shall conform
to the plan dimensions and to the following specification requirements for the
designated materials.
Metal gratings and covers which are to rest on frames shall bear on them
evenly. They shall be assembled before shipment and so marked that the same
pieces may be reassembled readily in the same position when installed.
Inaccuracy of bearings shall be corrected by machining, if necessary. A frame
and a grating or cover to be used with it shall constitute one pair.
units and shall be separate casting poured from the same material as the casting
they represent.
A sufficient number of cylinders shall be cast from the concrete for each
unit permitforcompression
cylinders each test. Iftests at 7, 14 requirement
the strength and 28 days,isand
mettoatallow
7 or for
14 at leastthe
days, 3
units shall be certified for use 14 days from the date of casting. If the strength is
not met at 28 days, all units made from that batch or load will be rejected.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 296/437
Cracks in units, honeycombed or patched areas in excess of 2,000 square
5/7/2018
millimeters, excessive water absorption and failure to meet strength requirements
DPW H Blue Book - slide pdf.c om
shall be the causes for rejection. Pre-cast reinforced concrete manhole risers and
tops shall conform to the requirements of AASHTO M 199.
The plants will be inspected periodically for compliance with specified
manufacturing methods, and material samples will be obtained for laboratory
testing for compliance with material quality requirements. This may be the basis
for acceptance of manufacturing lots as the quality.
Metal frames shall be set in full mortar bed. Pipe sections shall be flushed
on the inside of the structure wall and projected outside sufficiently for proper
connection with next pipe section. Masonry shall fit neatly and tightly around the
pipe.
Standard manholes, inlets and catch basins, both new and reconstructed
as applicable, will be measured by the unit. Any additional concrete, reinforcing
steel, or masonry required for authorized increases in heights of structures paid
of under this Item and in excess of the standard height shown on the Plans will
be measuredSteel,
Reinforcing and paid for under Item
as applicable. 405, Structural
Structures noted on Concrete
the Plansand
as Item 404,
“junction
boxes” will be measured for payment as manholes.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 297/437
The number of concrete covers, pairs of metal frames and gratings, and
pairs of metal frames and covers will be measured as acceptably completed.
5/7/2018 DPW H Blue Book - slide pdf.c om
This item shall consist of furnishing all materials, tools, and equipment
including labor required in undertaking the proper application of steel grating with
frame as shown on the plans and in accordance with this specification.
Classes of grates that are commonly use in drainage work are sump,
trench and box.
Trench grates shall be used to collect surface rainwater run off from areas
that cannot be graded to direct flow into a single pit.
Box grates or road drainage shall be used to transfer road surface storm
water into an underground drainage system. Normally used in conjunction with
kerb entry, the addition of the grate significantly increases the hydraulic capacity
of the inlet, particularly on steep slopes.
For locations trafficked by fast moving fully laden trucks and forklifts with
wheel loads to 5.0T. This includes all public roads from residential to
freeway.
The steel grating shall be made of fabricated mild steel provided with hot
dip galvanized in accordance with ASTM A153/AASHTO M 232 for superior
corrosion protection. Steel grating shall be machine-made grating comprised of
steel flat bars standing on edge equispaced from each other. To prevent them
from falling over and to provide restraint in buckling, a twisted cross rod (6mm) is
forge-welded1 into the top of the flat bars.
The steel frame clear openings of drainage grates shall be 15mm larger
than nominal sizes of industry standard sized pits. These pits increase in size in
increments of 150mm. This shall be done to allow frames to be placed over
standard panel formwork and cast in while pouring the pit walls, to speeds up
installation and ensure the frame is fully embedded in the concrete.
Grates shall consist of 25mm to 65mm x 3mm, 4.5mm or 5mm thick flat
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 300/437
bars with length of not more than 6.1m spaced at 30mm o.c. with 6mm twisted
rod spaced at 100mm o.c.. Angular frame (L 75mm x 75mm x 9mm thick) shall
5/7/2018
be coated with hot dipped galvanized for superior corrosion protection finish and
DPW H Blue Book - slide pdf.c om
Dimension
Tolerances: Thickness = ± 0.20mm
Width = ± 0.80mm
Metal gratings which are to rest on frames shall bear on them evenly.
They shall be assembled before shipment and so marked that the same pieces
may be reassembled readily in the same position when installed. Inaccuracy of
bearings shall be corrected by machining, if necessary. The steel grating and its
corresponding frame shall constitute one pair.
The quantity to be measured and paid for will be the number of pairs of
metal frames and gratings completed and accepted. Concrete and reinforcing
steel (AASHTO M 31) will be measured and paid for under Item 405, Structural
Concrete and Item 404, Reinforcing Steel, respectively.
Excavation and backfill will be measured and paid for as provided in Item
102, Excavation.
504.1 Description
This item shall consist of cleaning and reconditioning existing pipes and
appurtenant structures in reasonably close conformity with this Specification and
Pipe Cleaned in Place – All foreign materials within the barrel shall be
removed and disposed off by methods which will prevent damage to the pipe.
Measurement
removed, will be made
re-laid or stockpile by the linear
as designated in meter
the Billofofpipe acceptably
Quantities, cleaned,
irrespective
of the kind or size involved.
Pipe removed, cleaned, and re-laid will be measured in their final position.
constructed in accordance
dimensions shown with this Specification and to the lines and grades and
on the Plans.
505.2.1 Stones
Stones for riprap shall be one of the following classes as shown on the
Plans or determined by the Engineer.
Class D -
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281
Stones ranging from minimum of 100kg to a 305/437
culverts
the and other structures may be substituted for stone with the approval of
Engineer.
When required, the riprap shall be placed on a filter layer to prevent fine
embankment materials to be washed out through the voids of the face stones.
The grading of the filter material shall be as specified on the Plans, or in the
505.2.3 Mortar
Mortar for grouted riprap shall consist of sand, cement and water
conforming to the requirements given under Item 405, Structural Concrete, mixed
in the proportion of one part cement to three parts sand by volume, and sufficient
water to obtain the required consistency.
505.3.1 Excavation
The bed for riprap shall be excavated to the required depths and properly
compacted, trimmed and shaped.
The riprap shall be founded in a toe trench dug below the depth of scour
as shown on the Plans or as ordered by the Engineer. The toe trench shall be
filled with stone of the same class as that specified for the riprap, unless
otherwise specified.
505.3.2 Placing
Stones placed below the water line shall be distributed so that the
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 306/437
machines. They
into the slope andshall be laid
against thewith close, broken
adjoining stones. joints
Each and shall
stone bebe
shall firmly
laid bedded
with its
longest axis perpendicular to the slope in close contact with each adjacent stone.
The riprap shall be thoroughly rammed into place as construction progresses and
the finished surface shall present an even, tight surface. Interstices between
stones shall be filled with small broken fragments firmly rammed into place.
The
than 100 surface
mm at anyofpoint.
riprap shall not vary from the theoretical surface by more
505.3.3 Grouting
Grout shall be placed from bottom to top of the surface swept with a stiff
broom. After grouting is completed, the surface shall be cured as specified in
Item 405, Structural Concrete for a period of at least three days.
The stones shall also be laid in a manner that the vertical and horizontal
alignments of the exposed face shall, as possible be maintained in a straight line.
505.3.4 Weepholes
The stone shall be clean, hard, and durable and shall be subject to the
Engineer’s approval. Adobe stone shall not be used unless otherwise specified.
Sizes and Shapes – Unless other sizes are shown on the Plans, stones
have a thickness of not less than 150 mm, and widths of not less than one and
one-half times their respective thickness, and lengths of not less than one and
one half times their respective widths. Each stone shall be of good shape and be
free of depressions and projections that might weaken or prevent it from being
properly bedded.
Finish for Exposed Faces – Face stones shall be pitched to the line along
the beds and joints. The maximum projection of rock faces beyond the pitch lines
shall not be more than 50 mm.
506.2.2 Mortar
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 309/437
mm (No. 8) sieve, not less than 15 nor more than 40 percent shall pass the 0.3
mm (No. 50 ) sieve, and not more than 10 percent shall pass the 0.15 mm
(No.100) sieve.
The mortar for the masonry shall be composed of one part of Portland
Cement and two parts of fine aggregate by volume and sufficient water to make
the mortar of such consistency that it can be handled easily and spread with a
trowel. Mortar shall be mixed only in those quantities required for immediate use.
Care shall be taken to prevent the bunching of small stone or stones of the
same size. Large stones shall be used in the corners.
The exposed faces of individual stones shall be parallel to the faces of the
walls in which the stones are set.
The stones shall be so handled as not to jar displace the stones already
set. Suitable equipment shall be provided for setting stones larger than those that
can be handled by two men. The rolling or turning of stones on the walls will not
be permitted. If a stone is loosened after the mortar has taken initial set, it shall
be removed, the mortar cleaned off, and the stone relaid with fresh mortar.
shall not extend an unbroken line through more than 5 stones. Joints may vary
from 20 mm to 50 mm in thickness. They shall not extend in an unbroken line
5/7/2018
through more than two stones. They may be at angles with the vertical from 0 0 to
DPW H Blue Book - slide pdf.c om
450. Face stone shall bond at least 150 mm longitudinally and 50 mm vertically.
At no place shall corners of four stones be adjacent to each other.
Cross beds for vertical faced walls shall be level, and for battered walls
may vary from level to normal to the batter line of the face of the wall.
506.3.3 Headers
506.3.4 Backing.
Backing shall be built mostly of large stones as shown in the approved
Plans or as directed by the Engineer. The individual stones composing the
backing and hearting shall be well bonded with the stones in the face wall and
with each other. All openings and interstices in the backing shall be filled
completely with mortar or with spalls surrounded completely by mortar.
506.3.5 Pointing
Both bed and vertical joints shall be finished as shown on the Plans or as
directed by the Engineer. The mortar in joints on top of surface of masonry shall
be crowned slightly at the center of the masonry to provide drainage.
506.3.6 Coping
506.3.7 Weepholes
506.3.9 Curing
In hot or dry weather, the masonry shall be satisfactory protected from the
sun and shall be kept wet for a period of at least three days after completion.
the Engineer.
openings Nothan
of less deductions shallmeter
one square be made for weepholes, drain pipes or other
in area.
507.1 Description
The stone shall be cleaned, hard, and durable and shall be subject to the
Engineer’s approval. Adobe stone shall not be used unless otherwise specified.
Stones to be used shall be more than 0.015 cubic metre in volume and not less
than 75 percent of the total volume of rock embankment and shall consist of
The foundation bed shall be excavated to the lines and grades as shown
in the plans as directed by the Engineer, and shall be thoroughly compacted in
accordance with Item 104.3.3.
The inside surface of the forms shall be cleaned of all dirt, water and
foreign materials. Forms shall be thoroughly coated with form oil prior to use. The
form oil shall be commercial quality form oil or other approved coating which will
permit the ready release of forms and will not discolor the concrete.
507.3.3 Placing
One layer of concrete Class “B” shall be placed at the prepared bed prior
to placing of stones. Clearance between stones shall not be less than 2-1/2
inches or the maximum size of concrete aggregate for Class “B”.
Concrete Class “B” shall be placed after each layer of stone and shall be
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 313/437
After removal of forms, any cavities, voids and honeycomb spots shall be
filled up with mortar composed of one part cement and two parts sand.
All debris and refuse resulting from work shall be removed and the site
left in a neat and presentable condition.
volume. Stones
used. Adobe obtained
stone from
shall not be excavation performed
used, unless otherwiseunder this contract may be
specified.
Stones shall be laid flat and securely placed with broken joint lines. The
larger stones shall generally be located in the lower part of the structure and
voids shall be eliminated to the extent possible. Spalls smaller than the minimum
stone size specified in Section 506.2, Material Requirements, shall be used to
check the larger stones solidly in position and to substantially fill voids between
the major stones as laid in the embankment. The exposed face of the rock mass
shall be reasonably uniform, with no projections of more than 150 mm, beyond
the neat lines shown on the Plans or as directed by the Engineer.
Backfill adjacent to the hand-laid rock embankment shall be filled entirely
with acceptable material coming from excavation items and compacted.
The quantity to be paid for will be the number of cubic meter of hand-laid
rock embankment measured in place, completed and accepted.
Measurement , will be paid for at the contract price per cubic meter for Hand-
Laid Rock Embankment, which price and payment shall constitute full
5/7/2018 compensation for furnishing, selecting, and transporting stones, for placing
DPW H Blue Book - slide pdf.c om
stones by hand, for backfilling, and for all labor, equipment, tools and incidentals
necessary to complete the Item including foundation excavation.
This shall consist of furnishing, driving and cutting off of sheet piling
covered by this Specification.
Steel sheet piles shall be of the type, weight and Section Modulus
indicated on the Plans or Special Provisions, and shall conform to the
requirement of Item 400, Piling, Subsection 400.2.7, Sheet Piles, Painting shall
conform to the requirements for Item 411, Paint, Subsection 411.6.2, Painting
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 316/437
Structural Steel.
5/7/2018 509.3 Construction Requirements DPW H Blue Book - slide pdf.c om
510.1 Description
This Item shall consist of the furnishing and placing of concrete slope
protection including all necessary excavation, a bed course and reinforced
concrete to the required thickness and extent to protect slopes against erosion.
Construction details shall be as shown on the Plans.
510.2.2 Formwork
510.2.4 Concrete
510.3.1 Excavation
510.3.3 Concrete
5/7/2018
The Contractor shall provide and place concrete in accordance with the
DPW H Blue Book - slide pdf.c om
The quantity of granular material in the bed course to be paid for shall be
measured by the cubic meter in-place and accepted as shown on the Plans.
511.1 Description
This Item shall consist of furnishing, forming wire mesh baskets, and
placing rocks installed at the locations designated, in accordance with this
Specification and in conformity with the lines, grades, dimensions, and
arrangements shown on the Plans or as directed by the Engineer.
sizes, uniformly partitioned into internal cells, interconnected with other similar
units, and filled with stones at the project site to form flexible, permeable,
monolithic structures such as retaining walls, sea walls, channel linings,
revetments and weirs for erosion control. The lengths shall be multiples of 2, 3
or 4 times the width of the gabion and heights shall be 0.50 m to 1.00 m or as
shown on the plans. The horizontal width shall not be less than one meter.
Gabion furnished shall be of uniform width.
The width,
more than 5% fromheight
the and length
ordered of prior
size the gabion as manufactured shall not differ
to filling.
511.2.2 Wire
511.2.2.3 Style 3 double-twisted mesh shall be manufactured from the same type
of metallic-coated steel wire as style 1 with an additional PVC coating
extruded into the metallic-coated steel wire. The PVC coating shall
The PVC coating shall not show cracks or breaks after the wires are
Lacing wire and stiffeners shall be made of wire having the same
coating material as the double-twisted wire mesh conforming to
Specification ASTM A 641, A 856/A 856 M or A 809 with a tensile
strength in accordance with subsection 509.2.7.
The minimum size of the galvanized and PVC coated wire to be used in
the fabrication of the gabion and mattresses shall be as follows:
Diameter, mm
Gabion Mattresses
Metallic PVC Metallic PVC
The minimum weight of zinc per unit area of uncoated wire surface shall
be in accordance with ASTM A 975 or as follows:
Rock used in the gabions and mattresses shall consist of hard, durable
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 322/437
rock pieces that will not deteriorate when submerged in water or exposed to
severe weather conditions. Rock pieces shall be generally uniformly graded in
5/7/2018
sizes ranging from 100 mm to 200 mm. Filled gabions shall have a minimum
DPW H Blue Book - slide pdf.c om
No rock size shall exceed 2/3 the mattress depth and at least 85% by
weight of the stone shall have a size greater than 80 mm. No stones shall be
able to pass through the mesh.
511.3.1 Fabrication
a nominal
made mesh
of steel wireopenings of 83 forming
double twisted by 114 amm. Mattresses
uniform shall
hexagonal meshbe
type 6 x 8 having a nominal mesh openings of 64 by 83 mm.
Tolerances on the hexagonal, double-twisted wire mesh opening shall
not exceed 10% on the nominal dimension D values, 64 mm for
mattresses and 83 mm for gabions. The edges shall be formed into a
securely connected selvedge adequate to prevent raveling.
2. When the gabion length exceeds its width, it shall have securely tied
diaphragms connected at all edges to form individual cells of equal
length and width.
body of the gabions, into cells the length of which does not exceed
the horizontal width. The gabion shall be furnished with the necessary
diaphragms secured in proper position on the base in such a manner
that no additional tying at this junction will be necessary.
Selvedge wire used through all the edges (perimeter wire) shall not
be less than 3.80 mm diameter and shall meet the same
specifications as the wire mesh.
4. The cells in any row shall be filled in stage so that local deformation
may be avoided. That is at no time shall the cell be filled to a depth
exceeding 30 cm more than the adjoining cell.
Construction equipment
Jointing is normally shall by
affected notoverlapping
be allowed not
into less
unprotected
than 300fabric.
mm,
but it is preferable to joint by sewing or industrial stapling. Joint edges
should be facing downwards to avoid protruding through the surface
material.
600.1 Description
This Item shall consist of the construction of curb and gutter either Precast or
Cast in place, made of concrete in accordance with this Specification at the
location,
the Plansand in required
or as conformity
by with the lines, grades, dimensions and design, shown on
the Engineer.
Bed course materials as shown on the Plans shall consist of cinders, sand,
slag,
all thegravel, crushed
particles stone,
will pass or other
through 12.5 approved porous
mm (1/2 inch) material of such grading that
sieve.
600.2.2 Concrete
Concrete shall be of the class indicated on the Plans and shall conform to the
requirements of Item 405, Structural Concrete.
Bed course material shall be placed and compacted to form a bed of the
required thickness as shown on the Plans.
600.3.2.1 Placing
Mixing, ofplacing,
requirements finishing
Item 405, and Concrete,
Structural curing of asconcrete
modifiedshall conform
by the to the
requirements
below.
The concrete shall be placed in the forms in layers of 100 or 125 mm each,
and to the depth required. It shall be tamped and spaded until mortar entirely covers
the top and surfaces of the forms. The top of the concrete shall be finished to a
smooth and even surface and the edges rounded to the radii shown on the Plans.
Before the concrete is given the final finishing, the surface of the gutter shall be
tested with a 3-m straight-edge and any irregularities of more than 10 mm in 3 m
shall be corrected.
The curb and gutter shall be constructed in uniform sections of not more than
50 m in length except where shorter sections are required to coincide with the
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 327/437
The form shall be removed within 24 hours after the concrete has been
placed. Minor defects shall be repaired with mortar containing one part of Portland
Cement and two parts of fine aggregate. Plastering shall not be permitted and all
rejected portions shall be removed and replaced at the Contractor’s expense. The
exposed surface shall be finished while the concrete is still fresh by rubbing the
surfaces with a wetted soft brick or wood until they are smooth. The surfaces shall
be wetted thoroughly, either by dipping the brick or wood in water, or by throwing
water on the surfaces with a brush. After the concrete has been rubbed smooth
using water, it shall then be rubbed with a thin grout containing one part of Portland
Cement and one part of fine aggregates. Rubbing with grout shall continue until
uniform color is produced. When completed, the concrete shall be covered with
suitable material and kept moist for a period of 3 days, or a membrane-forming
material may be applied as provided in Item 405, Structural Concrete. The concrete
shall be suitably protected from the weather until thoroughly hardened.
After the concrete has set sufficiently, the spaces on the back of the curb
which were excavated
with suitable for placing
material which thetamped
shall be curb shall be refilled
in layers of notto the than
more required
150 elevation
mm until
consolidated.
600.3.3.1 Placing
The precast concrete curb and gutter shall be set in 20mm of cement mortar
as specified in Subsection 600.2.4 to the line level and grade as shown on the
approved Plans.
The precast curb shall not be more than 20cm in width at the top portion and
not be more than 25cm at the base. The precast curb and gutter shall be 1.0 m in
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 328/437
length and shall be put side by side consecutively with joint in between.
5/7/2018
Joints between consecutive curb and gutter shall be filled with cement mortar
DPW H Blue Book - slide pdf.c om
to the full section of the curb and gutter. Expansion joints shall be formed at
intervals shown on the Plans. Where a curb and gutter is placed next to a concrete
pavement, expansion joints in the curb and gutter shall be located opposite
expansion joints in the pavement.
Minor defects shall be repaired with mortar containing one part of Portland
rubbed with a thin grout containing one part of Portland Cement and one part of fine
aggregate. Rubbing with grout shall continue until uniform color is produced.
1. In preparation for the handling of precast curb and gutter, all fabricated curb
and gutter of one (1) meter in length shall be provided or inserted with 2-1ӯ
PVC pipes for fitting at their required locations. The PVC pipes shall be
placed 25 mm from both edge during the fresh concrete is in plastic state.
2. Precast curb and gutter shall be lifted on upright position and not at the points
of support and shall be the same during transporting and storage.
3. Extreme care shall be exercised in handling and moving precast curb and
gutter to avoid cracking.
4. No precast
in the formscurb
with and gutter shall
the required timebestipulated
used thatprior
doestonot reach its final position
installation.
5. Precast curb and gutter shall be transferred to the construction site. Fresh
curb and gutter shall not be placed against in-situ concrete which has been in
a position for more than 30 minutes.
6. Precast curb and gutter may only be transported to the delivery point in truck
agitators or truck mixer operating at the speed designated by the
manufacturer of the equipment, provided that the consistency and workability
of the mix concrete upon discharge at the delivery point is suitable for
adequate placement.
gutter, backfilling, dumping and disposal of surplus materials, and for all labor,
equipment, tools and incidentals necessary to complete the Item.
600
600 (1)
(2) Concrete
Concrete Curb
Gutter(Cast
(Castininplace)
place) Linear
Linear Meter
Meter
600 (3) Curb and Gutter (Cast in place) Linear Meter
600 (4) Concrete Curb (Precast) Piece
600 (5) Concrete Gutter (Precast) Piece
600 (6) Curb & Gutter (Precast) Piece
601.1 Description
601.2.2 Asphalt
601.2.4 Forms
Bed course material consists of cinders, sand, slag, gravel, crushed stone or
other approved permeable granular material of such grading that all particles shall
pass a 12.5 mm (1/2 inch) sieve.
Excavation shall be made to the depth and width required that will permit the
installation and bracing of the forms. The foundation shall be shaped and
compacted to a firm and even surface conforming to the section shown on the Plans.
All materials from soft areas shall be removed and replaced with suitable materials.
The bed course shall be compacted in layers not exceeding 100 mm to the
depths, lines and levels shown on the Plans.
The prepared bed course material shall receive an application of prime coat in
accordance with the requirements of Item 301, Bituminous Prime Coat.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 331/437
The asphalt mixture shall be placed on the previously primed and prepared
5/7/2018
bed only when, in the opinion of the Engineer, the bed is sufficiently dry and weather
DPW H Blue Book - slide pdf.c om
conditions are suitable. The mixture shall be placed in one or more layers of uniform
thickness to the total depth shown on the Plans. Each layer shall be smoothed by
raking or screeding and shall be thoroughly compacted by rolling with a hand
operated roller of a type satisfactory to the Engineer. After compaction, the
surfacing shall be of the thickness and section shown on the Plans and shall be
All forms shall be staked securely in position at the correct line and level.
Preformed joint filler shall be set in position shown on the Plans before placing of the
concrete is started. The top of the joint filler shall be placed 5 mm below the top
surface of the finished sidewalk.
602.1 Description
Concrete shall be the class designated on the Plans and shall be composed
of materials conforming to the requirements of Item 405, Structural Concrete.
Steel. Reinforcing steel shall conform to the requirements of Item 404, Reinforcing
Timber shall be of the species and grade shown on the Plans. Treated
timber, if required, shall conform to the requirements of Item 410, Treated and
Untreated Timber.
The metal material shall conform to the requirements shown on the Plans, or
as stipulated in the Special Provisions.
Paints, if required, shall conform to the requirements shown on the Plans, or
as stipulated in the Special Provisions.
603.1 Description
Materials for the desired type of guardrail shall meet the requirements
specified in the following specifications:
Splices and end connections shall be of the type and design specified or as
shown on the Plans, and shall be of such strength as to develop the full design
strength of the rail elements.
Unless otherwise specified, all fittings, bolts, washers and other accessories
shall be galvanized in accordance with the requirements of AASHTO M 111 or
ASTM A 153, whichever may apply. All galvanizing shall be done after fabrication.
Steel post shall be of the section and length as specified, or as shown on the
Plans. They shall be of a copper bearing steel when so specified. Steel shall
conform to the requirements of AASHTO M 183 for the grade specified. The posts
shall be galvanized or shop painted as may be specified.
Paints for steel and wood shall be specified and conform to the requirements
specified in Item 411, Paint.
603.3.1 Posts
Posts shall be set vertically in the position shown on the Plans and, where
embedded in a concrete foundation block, shall remain undisturbed for a minimum of
48 hours. The space around the post shall be backfilled to the ground line with
approved material in layers not exceeding 100 mm and each layer shall be
moistened and thoroughly compacted.
Galvanized surfaces which have been abraded so that the base material is
exposed, threaded portions of all fittings and fasteners and cut ends of bolts shall be
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 336/437
painted with three coats of white paint to within 200 mm of the ground line. The first
200 mm of posts above the ground shall be painted with two coats of black paint.
Painting shall be done only when the timber is dry and clean. Each coat of paint
shall be thoroughly dry before the next coat is applied. Paint shall be applied in
heavy coats, completely covering every part of the surface and shall be worked well
shall be thoroughly dry before the second is applied. Stain shall not be applied in
damp weather.
For beam type guardrails, metal works not galvanized shall be given one
shop coat of red lead, zinc chromate paint or an approved fast-drying rust-inhibitive
primer and two field coats of white or aluminum paint. Untreated wood posts shall
be given three coats of paints of the color indicated on the Plans, or as specified.
Painting shall conform to the requirements of Item 411, Paint.
The accepted
of Measurement, quantities
shall be paid of
forguardrail, determined
at the contract in Subsection
unit price per linear603.4,
meter Method
for the
type specified, complete in place, which price and payment shall be full
compensation for furnishing and placing all materials, including all labor, equipment,
tools and incidentals necessary to complete the Item. When so specified, end
anchorages and terminal sections will be paid for at the contract unit price for each
of the kind specified and completed in place.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 337/437
Payment will be made under:
5/7/2018 DPW H Blue Book - slide pdf.c om
604.1 Description
This Item shall consist of furnishing and constructing posts and barbed wire or
chain link fences in accordance with the details, and at the locations, shown on the
Plans, or as required by the Engineer.
Barbed wire shall conform to the requirements of ASTM A 121, Class I. The
barbed wire shall consist of 2 strands of 12.5 gauge wire, twisted with 2 points, 14
Chain link fence fabric shall be fabricated from 10 gauge galvanized wire
conforming to AASHTO M 181 and shall be of the type shown on the Plans. Before
ordering the chain link fence fabric, the Contractor shall submit a sample of the
material to the Engineer for testing and for approval.
The post shall be erected vertically in position inside the formwork of the
foundation block prior to the placing of concrete and shall be adequately supported
by bracing to prevent movement of the post during the placing and setting of the
concrete. The posts shall be erected to the height and location shown on the Plans,
or as ordered by the Engineer.
The chain link fence fabric shall be set to line and elevation and pulled taut
between each post before spot welding, or other method of fixing, is carried out.
Where splicing of the fence fabric is necessary, or at joints, the lapping of the chain
link fence fabric shall be for a minimum of 100 mm and shall occur only at the post.
No horizontal splicing will be permitted. The fence fabric shall be fixed to the posts
as shown
and/or on the Plans.
construction shall be Any surface
restored protective layer damaged during welding
properly.
The quantity to be paid for shall be the number of linear meter measured
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 339/437
center to center of posts, of fencing erected in place and accepted.
5/7/2018
604.5 Basis of Payment DPW H Blue Book - slide pdf.c om
605.1 Description
The road signs shall comply in all respects with the “Philippine International
Road Signs Manual” published by the Department of Public Works and Highways,
Manila. The categories of road signs are designated in the Manual, namely, danger
warning signs, regulatory signs and informative signs, or guide signs. These are
referred to in the Contract as warning signs and informatory signs, respectively.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 340/437
Road signs shall be classified as standard or non-standard. Standard signs
consist of all warning signs, regulatory signs and informatory signs with the
exception of direction signs, place identification signs and the line. Non-standard
5/7/2018
signs consist of all informatory signs which are not classified as standard signs.
DPW H Blue Book - slide pdf.c om
The size of warning and regulatory signs is the length of the side of triangular
signs (measured from the points of intersection of the extension of the edges), the
horizontal width of octagonal signs and the diameter of circular signs.
Wide flange posts and frames shall be fabricated from structural steel
conforming to ASTM A 283 Grade D. In lieu of wide flange steel posts, the
Contractor may use tubular steel posts conforming to ASTM A 501. All posts shall
be thoroughly cleaned, free from grease, scale and rust and shall be given one coat
of rust-inhibiting priming paint and two coats of gray paint in accordance with Item
411, Paint.
Nuts, bolts, washers and other metal parts shall be hot-dip galvanized after
fabrication in accordance with the requirements of AASHTO M 111.
The concrete for the foundation blocks shall be Class A in accordance with
Item 405, Structural Concrete and shall be of the size shown on the Plans.
Holes shall be excavated to the required depth to the bottom of the concrete
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 342/437
foundation as shown on the Plans.
5/7/2018 Backfilling shall be carried out by using suitable material approved by the
DPW H Blue Book - slide pdf.c om
Engineer and shall be compacted in layers not exceeding 150 mm in depth. Surplus
excavated material shall be disposed of by the Contractor as directed by the
Engineer.
Sign panels shall be installed in accordance with the details shown on the
Plans. Any chipping or bending of the sign panels shall be considered as sufficient
cause to require replacement of the panels at the Contractor’s expense.
The exposed portion of the fastening hardware on the face of the signs shall
be painted with enamels matching the background color.
All newly erected traffic road signs shall be covered until ordered removed by
the Engineer.
The quantities of standard reflective warning and regulatory road signs shall
be the number of such signs of the size specified, including the necessary posts and
supports erected and accepted.
606.1 Description
This item shall consist of placing markings on the finished pavement. The
work shall include the furnishing of premixed reflectorized traffic paint or reflectorized
pavement marking paint conforming to the requirements of AASHTO M 248,
whichever is called for in the Contract, sampling and packing, preparing the surface,
and applying the paint to the pavement surface, all in accordance with this
Specification.
The paint shall be applied to the size, shape and location of the markings
shown on the Plans, or as required by the Engineer.
Premixed reflectorized traffic paint is a paint in which the glass beads are
mixed in the paint during the process of manufacture, so that upon application and
drying, the paint line is capable of retroreflection of the light beams.
Premixed reflectorized traffic paints which are available in both white and
yellow are paints that provide reflective marking for concrete, bituminous, bricks or
stone surface of highways, bridges, tunnels, streets, parking lots and airports.
606.2.1 Classification
Type I – Alkyd
Type II – Chlorinated Rubber Alkyd
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 344/437
5/7/2018
606.2.2 Material Requirements DPW H Blue Book - slide pdf.c om
The paint shall consist of pigments, vehicles and glass beads so combined as
to produce a paint that will conform to the following requirements.
e. Resistance to Water – The dried paint film shall not show blistering, peeling,
wrinkling and discoloration when immersed in water for 18 hours.
f. The paint shall also conform to the physical properties specified in Table 1.
Minimum Maximum
Specific Gravity 1.5 -
Drying Time, No Pick Up,
Minutes - 40
Consistency (Kreb Units) at 20 C 65 95
percent by weight 40 - 41 -
Glass Beads, percent by
Weight 31.0 35.0 35.0
31 0
Beads Diameter: The percentage of beads that will pass through the US
Standard Sieves shall be as follows:
Sieve No. (um) Mass Percent Passing
The painting of lane markers and traffic strips shall include the cleaning of
the pavement surfaces, the application, protection and drying of the paint coatings,
the protection of pedestrians, vehicular or other traffic, the protection of all parts of
thesmirches
or road structure andor
of paints itsof
appurtenances against
paint materials, disfigurement
and the byall
supplying of spatters, splashes
tools, labor and
traffic paint necessary for the entire work.
The paint shall not be applied during rain or wet weather or when the air is
misty, or when in the opinion of the Engineer, conditions are unfavorable for the
work. Paint shall not be applied upon damp pavement surfaces, or upon pavement
which has absorbed heat sufficient to cause the paint to blister and produce a
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 346/437
606.2.4 Sampling
The paint shall be sampled in accordance with PNS 484/ISO 1512 or other
Philippine Standard Method of Sampling Paints and Varnishes.
The paints shall be tested in accordance with the methods specified in PNS
461 or other Philippine Standard Method of Tests for Paints and Varnishes.
The paints shall be packed, packaged and marked in accordance with PNS
140.
The quantity of pavement markings to be paid for shall either be the length as
shown on the Plans of painted traffic line of the stated width or the area as shown on
the plans of symbols, lettering, hatchings, and the like, completed and accepted.
Separate items shall be provided for premixed reflectorized traffic paint and
reflectorized thermoplastic pavement markings.
607.1 Description
This Item shall consist of furnishing and installing reflective pavement studs
on the surface of the pavement in accordance with this Specification and at the
locations shown on the Plans, or as required by the Engineer.
Reflective studs shall be either the “Flush Surface” or “Raised Profile” type
having the following characteristics.
The “Flush Surface” reflector shall be the short base type having a maximum
base area of 180 mm x 140 mm. The base shall be formed in cast-iron with
adequate webbing to insure a firm key to the road when installed. The pad shall be
highly resilient and durable rubber reinforced with canvass and shall have a design
life of at least 5 years. The pad shall be so designed as to produce a self-wiping
action of the reflectors when depressed. The reflectors shall be made of impact and
abrasion-resisting glass and shall be hermetically sealed into a copper socket.
The “Raised Profile” reflectors shall consist of an acrylic plastic shell filled
with
of a an adherent
shallow epoxyofcompound
frustrum a pyramid molded from
with base methyl methacyclate
dimensions into100
approximately the shape
mm x
100 mm and thickness of not more than 20 mm. The shell shall contain two
prismatic reflectors each inclined at an angle of 30o to the horizontal and having an
area not less than 20 cm2. The reflectors shall attain the following standards for
their photometric and physical properties:
Each reflector for testing shall be located with the center of the reflecting face
at a diameter of 1.5 m from a uniformly bright light source having an effective
diameter of 5 mm. The width of the photocell shall be 1.2 mm and shall be shielded
from stray light. The distance from the centers of the light source and photocell shall
be 5 mm. Failure of more than 4% of the reflective faces shall be a cause for
rejection of the complete batch.
The reflectors shall support a vertical load or kgf(10kN) when tested in the
following manner. A reflector shall be centered horizontally over the open end of a
vertically positioned hollow metal cylinders, 75 mm internal diameter, 25 mm high
and wall thickness of 6 mm. The load shall be applied to the top of the reflector
through a 6 mm diameter by a 6 mm high metal plug centered on top of the reflector.
Failure shall constitute either breakage or significant deformation of the marker at
any load less than 1000 kgf.
607.2.2 Adhesive
The stud shall be installed into the pavement in accordance with the
manufacturer’s instructions but shall also comply with the following requirements.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 349/437
The walls of the cavity shall be splayed back at the angle of approximately
o
The depth of the activity shall be such that when the stud base and reflectors
have been installed the elevation of the floor of the lens socket shall not be greater
than 2.0 mm or less than 1.0 mm above the pavement surface.
When the studs are installed into a cement concrete pavement, the stud shall
be grouted into position with asphalt concrete containing fine aggregate only or with
a cement mortar as described in Subsection 607.2.3 above.
608.1 Description
This Item shall consist of topsoil furnished, transported and spread, or topsoil
removed from designated areas, hauled and spread, in accordance with this
Specification at the location shown on the Plans or as required by the Engineer.
Topsoil furnished shall consist of fertile friable soil of loamy character without
admixture of undesirable subsoil, refuse or foreign materials. It shall be obtained
from well-drained arable land and shall be reasonably free from roots, hard clay,
coarse gravel, stones larger than 50 mm in size, coarse sand, noxious seeds, sticks,
brush, litter and other deleterious substances. Topsoil shall be capable of sustaining
healthy plant life and shall be subject to the approval of the Engineer.
Topsoil shall contain not less than five (5) percent organic matter as
determined by loss or ignition of samples oven-dried to constant weight.
608.3.2 Placing
5/7/2018 The topsoil shall be evenly spread on the areas and to the line and level
DPW H Blue Book - slide pdf.c om
shown on the Plans and compacted with a light roller to a depth of not less than 100
mm. Spreading shall not be done when the ground topsoil is excessively wet, or
otherwise in a condition detrimental to such work. The roadway surfaces shall be
The quantities to be paid for shall be the number of cubic meters of Topsoil
removed, furnished and hauled complete in place and accepted.
609.1 Description
This Item shall consist of planting sprigs of living grass plants in accordance
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 352/437
609.2.1 Sprigs
609.2.2 Fertilizers
Ground limestone shall contain not less than 85 percent of calcium and
magnesium carbonates and shall be of such fineness that 100 percent shall pass
through a 2.00 mm sieve and not less than 35 percent through a 0.150 mm sieve.
Granulated slag may be substituted in lieu of ground limestone subject to the
approval of the Engineer of an adjusted application rate that will provide the
equivalent total neutralizing power of the specified limestone.
609.2.4 Topsoil
The Contractor shall notify the Engineer at least 5 days before sprigs are to
be harvested and the source shall be approved by the Engineer before harvesting
begins.
Not more than 24 hours shall elapse between harvesting and planting sprigs,
except that when
time extension mayweather or other
be granted, uncontrollable
provided the sprigs condition interrupts
are still moist the work,
and viable. a
Sprigs
that have heated in stockpiles, permitted to dry out or otherwise seriously damaged
during harvesting or delivery shall be rejected and be disposed off as directed.
After grading of areas has been completed and before applying fertilizer and
ground limestone, areas to be sprigged shall be raked or otherwise cleared of stone
larger than 50 mm in diameter, sticks, stumps and other debris which might interfere
with sprigging, growth of grasses or subsequent maintenance of grass-covered
areas. If any damage by erosion or other causes has occurred after grading of
areas and before beginning the application of fertilizer and ground limestone, the
Contractor shall repair such damage. This may include filling gullies, smoothing
irregularities and repairing other incidental damage.
609.3.3 Topsoiling
After planting or sprigs has been completed and prior to compacting, the
surface shall be cleared of stones larger than 50 mm in diameter, large clods, roots
and other litter brought to the surface during sprigging.
If mulching of sprigged areas is shown on the Plans, the sprigged area shall
be covered with mulch in accordance with the requirements of Subsection 609.2.5,
Mulch Material, within 24 hours from the time sprigging has been completed,
weather and soil conditions permitting.
If mulching is not shown on the Plans, the sprigged area shall be compacted
within 24 hours from the time sprigging has been completed, weather and soil
conditions permitting, by cultipackers, rollers or other satisfactory equipment
operated
is in suchatcondition
right angles
thattoit the slopes.upCompaction
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281
The Contractor shall protect sprigged areas against traffic by warning signs or
The quantity of sprigging to be paid for shall be the number of units of 100
square meters, measured on the ground surface, completed and accepted.
610.1 Description
The sod shall be cut into uniform squares approximately 300 mm x 300 mm,
but not larger than is convenient for handling and transporting.
The thickness of the sod shall be uniform as possible approximately 40 mm or
more depending on the nature of the sod, so that practically all of the dense root
system of the grasses will be retained, but exposed, in the sod strip and that the sod
can be handled without undue tearing or breaking.
The areas to be sodded shall be free from stones, roots or other undesirable
foreign materials.
Thedepth,
earth bed upon which the sod is tomoist,
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281
loosened if not naturally sufficiently be placed shallsod
and the be moistened to the
shall be placed 357/437
beginning at the bottom of the slope and working upwards. When placing sod in
ditches, or in the construction of sod ditch checks or similar appurtenances, the
As the sod is being laid it shall be lightly tamped with suitable wooden or
metal tampers sufficiently to set or press the sod into the underlying soil.
At points where it is anticipated that water may flow over a sodded area, the
upper edges of the sod strips shall be turned into the soil to be below the adjacent
area and a layer of earth place over this juncture and thoroughly compacted. At the
limits of sodded areas, the end strips shall be turned in and treated similarly.
On all slopes steeper than one vertical to four horizontal, sod shall be pegged
with stakes 200-300 mm in length, spaced as required by the nature of the soil and
steepness of slope. Stakes shall be driven into the sod at right angles to the slope
until flush with the bottom of the grass blades.
After staking has been completed, the surface shall be cleared of loose sod,
excess soil or other foreign material, whereupon a thin layer of topsoil shall be
scattered over the sod as a top dressing and the areas shall then be thoroughly
moistened by sprinkling with water.
610.3.5 Watering
611.1 Description
This Item shall consist of furnishing and planting deciduous shade, flowering
trees and evergreen trees less than 150 mm in diameter on the areas and in the
arrangements indicated on the Plans or as indicated by the Engineer, including the
digging and preparation of pocket holes, furnishing and placing the necessary
topsoil, mulch, water, fertilizer and other incidentals necessary to complete the Item.
611.2.1 Topsoil
611.2.2 Mulching
Anchor stakes shall be of the same quality as bracing stakes and of the size
611.2.3 Trees
All trees furnished under this Item shall be 150 mm or less in diameter and
shall be true to name and type and shall follow standard names of trees in
accordance with the Bureau of Forestry Standards as adopted by the Department of
Public Works and Highways.
When specified in the Provisions, certain varieties of plants will be furnished by
the government.
The Contractor shall submit complete and detailed information concerning the
sources of supply for each item of plant materials before planting operations.
All existing laws and regulations requiring inspection for plant diseases and
infections shall be complied with and each delivery shall be accompanied by
necessary certificates of clearance to be presented to the Engineer.
location. These plants shall be hauled by the ball only and not by the plant itself.
The
be a slightest
cause forindication
rejection of
of manufactured
such plants. earth balls or hauling of the plants itself will
All plants, nursery-grown or collected, shall be dug with care and skill
immediately before shipping and avoiding all possible injury to the plants, loss or
damage of the roots, particular attention being given to fibrous roots in this respect.
After the plants are dug, their roots shall not be permitted to dry out. They shall not
be exposed to hot temperatures. All plants shall be dug in dormant state and shall
be so held until planted.
After delivery and inspection, the plants shall be sprayed with an approved
anti-desiccant prior to planting, heeling-in or storing, except in the case of collected
stock which shall not be heeled-in or stored, but shall be sprayed with anti-desiccant
immediately and planted within 36 hours after digging.
The spray shall cover both upper and lower surfaces of the branches and
foilage to the point of run-off. Spray nozzles shall be the type to produce a fine
mist.
The ball of soil and roots of balled and burlapped plants, if not immediately
planted after delivery and inspection, shall be adequately protected by topsoil
5/7/2018 covering until removed for planting in a manner appropriate to the conditions and
DPW H Blue Book - slide pdf.c om
Before digging pocket holes or beds, the Contractor shall lay out, by suitable
staking, the location of all pocket holes and beds. The layout of planting shall be
approved by the Engineer.
The ends of all broken and damaged roots, 6 mm diameter or larger, shall be
pruned with a clean cut removing no more than the injured portion. All plants shall
be pruned to balance the top with the root system keeping the natural shape of the
species. All dead woods shall be removed. All cuts and wounds, 12 mm or over in
diameter, shall be painted with tree wound dressing immediately after the pruning.
Pocket holes shall be dug at the locations shown on the Plans or as directed
by Engineer. The holes shall be dug to the depth and cross-section specified and
should be of sufficient size to provide for not less than 150 mm of top soil backfill
beneath and around the root system. The holes shall be dug with the sides vertical.
Surplus excavation from the bed and pocket holes shall be disposed off as directed
by the Engineer.
611.3.7 Backfill
The pocket holes shall be backfilled with topsoil as each plant is set. The
topsoil shall be well-tamped by the worker’s feet, rods or other approved tamping
devices as it is shovelled into the holes. The backfill in holes on slopes shall be
built-up on the lower side to catch and hold water. During planting the topsoil
surrounding the plant be slightly depressed to hold water.
611.3.8 Planting
The plants to be planted shall be the specie, variety and size specified. The
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 362/437
operation of the actual planting shall not be performed at any time when the soil is
not in a friable or workable condition. The Engineer shall also approve the location
5/7/2018
of each individual plant taking into consideration its size and shape, in order that the
DPW H Blue Book - slide pdf.c om
topsoil shall be settled in and about the plant roots by application of water but at no
After filling halfway on the earth ball, the burlap shall be loosened and the top
half cut off and removed after which the balance of the pocket hole shall be
backfilled and tamped.
After planting and prior to mulching, fertilizers shall be applied evenly over
the top of the backfilled area. Care shall be used so that the fertilizer does not get
into contact with the stem, trunk, branches or leaves of the plants.
The trees to be used for this purpose shall be the varieties the root systems of
which grow downward rather than sideward to avoid situations where the roots
spread sideward and consequently destroy the road and sidewalk slabs.
Trees shall be planted in a neat row, within the road right-of-way (ROW) and
as close as possible to the ROW limit, with sufficient allowance so that the trees
when fully grown will not encroach on the adjoining property or touch electric and
other overhead utility lines. The center-to-center spacing between trees shall be 10-
20 metres (m). For road sections with a generally north-south alignment, the trees
on one side of the road shall be staggered vis-à-vis the trees on the other side of the
road. This arrangement will help to ensure that enough sunlight will fall on the road
and thus help to keep the road dry even during the rainy season.
For roads without curbs, the trees shall be planted with a minimum clear
distance of 0.60 m beyond the edge of the shoulder, but in no case less than 3.0 m
from the edge of the pavement. For roads with curbs, particularly in urban areas,
the trees shall be planted with a minimum setback of 1.00 m beyond the face of the
curb.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 363/437
Where there are longitudinal drainage canals, the trees shall be planted on
5/7/2018
the outer side of such canals. On the roadway curves and intersections, the
DPW H Blue Book - slide pdf.c om
maintenance of trees
road maintenance shall beand
program faithfully
shall undertaken
be includedasinanthe
integral parttherefore
reports of the regular
as a
regular work item under Activity No. 209 of the Highway Maintenance Activity
Standards.
The tree planting shall be undertaken not only along national roads
programmed for construction or improvement, but also along existing national roads
especially those outside developed urban areas where there are no trees or only a
few trees have been planted. For such existing roads, the required tree planting
shall be undertaken by the District Engineering Office concerned. The tree planting
shall be undertaken in both contractual projects and projects by administration.
611.3.9 Mulching
Within 24 hours after planting, mulching material shall be spread to cover the
plant hole and the area 150 mm outside the periphery of the plant hole. The depth
and application for wood chips shall be a minimum of 150 mm. For ground or
crushed corn cobs, sawdust or peat moss the minimum depth shall be 100 mm.
All plants shall be watered during the planting operations, subject to direction
and approval of the Engineer. From time to time during the life of the Contract,
sufficient water shall be applied so that not only will the topsoil backfill about each
plant be kept moist, but also for moisture to extend into the surrounding soil.
The Contractor shall, during the life of the Contract, properly care for all plants
furnished, planted or stored, performing such watering, weeding, cultivating or other
ordinary maintenance work as shall be necessary to keep the stock in a live and
healthy condition. Plants which have died back into the crown or beyond a normal
pruning line shall be replaced by the Contract at no additional expense to the
Government.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 364/437
611.3.11 Bracing
All deciduous and evergreen trees shall be braced immediately after planting.
5/7/2018 DPW H Blue Book - slide pdf.c om
Deciduous trees from 1.20 m to 1.80 m in height shall have one vertical support
stake. Deciduous trees from 1.80 m to 2.50 m in height shall have two vertical
100 mm of the trunk at one-half of the height of the tree. If two are required, they
shall
for be driven on opposite sides of the tree with the stake tops on opposite sides
fastening.
All trees, deciduous or evergreen over two and one-half meters shall be
braced by the tripod method as directed by the Engineer.
Before
that have diedcompletion
back into and
the final
crownacceptance of the
or beyond the project,
normal all trees not
pruning linehealthy or
shall be
replaced by the Contractor at his own expense with trees of the specified species or
variety, size and quality and meeting the Specification.
The quantity to be paid for shall be the number of trees of each specie or
variety called for in the Plans furnished, planted and accepted with the necessary
mulch, topsoil, water, fertilizer and other incidentals to complete the Item.
612.1 Description
Gradation:
Sieve Mass Percent Passing
mm
0.850 100
0.600 75-95
0.425 -
0.300 15-35
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281
0.180 - 366/437
0.150 0-5
0.150 05
5/7/2018 DPW H Blue Book - slide pdf.c om
612.3.2 Qualitative
Property Requirements
White Yellow
Specific Gravity, max. 2.15
Drying Time, minutes, max. 10.0
Bond Strength to Portland
Cement Concrete after
heating for four (4) hours
±5 min. @ 218oC, MPa, max. 1.24
Cracking Resistance @ low
temp.
four (4)after heating
hours for@ 218
±5 min.
o
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 367/437
±2 C. No cracks
Impact Resistance after
heating for four (4) hours
5/7/2018
±5 min. @ 218 ±2oC and DPW H Blue Book - slide pdf.c om
The material shall not exude fumes which are toxic, obnoxious or injurious to
persons or property when heated during applications.
be laid to thickness of not less than 1.5 mm unless authorized by the Engineer. In
all cases the surface produced shall be uniform and appreciably free from bubbles
and steaks. Where the Contractor Documents require or the Engineer direct that
ballotini shall be applied to the surface of the markings, these shall be applied
uniformly to the surface of hot thermoplastic immediately after laying such that the
quality of ballotini firmly embedded and retained in the surface after completion
complies with the requirements of Sub-section 606.2.2, Material Requirements.
Road markings of a repetitive nature, other center lines, lane lines, etc., shall
unless
the sizeotherwise directed
and spacing by the Engineer
requirements shown onbethe
setPlans.
out with stencils which comply with
The Contractor shall protect pedestrians, vehicles and other traffic adjacent to
the working area against damage or disfigurement by construction equipment, tools
and materials or by spatters, splashes and smirches or paint or other construction
materials and during the course of the work, provide and maintain adequate signs
and signals for the warning and guidance of traffic.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 369/437
612.5 Sampling
5/7/2018 A minimum weight of 10 kg. of Reflectorized Thermoplastic paint shall be
DPW H Blue Book - slide pdf.c om
The quantity of pavement markings to be paid for shall be the area as shown
on the Plans of painted traffic line of the stated width and the area as shown on the
plans of symbols, lettering, hatching and the like, completed and accepted.
Type Specifications
Portland Cement AASHTO M 85 (ASTM C 150)
Blended Hydraulic Cements AASHTO M 240 (ASTM C 595)
Masonry Cement AASHTO M 150-74 (ASTM C 91)
Unless otherwise permitted by the Engineer, the product of only one mill of
any one brand and type of Portland Cement shall be used on the project.
The Contractor shall provide suitable means of storing and protecting the
cement against dampness. Cement which, for any reason, has become partially set
or which contains lumps of caked cement will be rejected. Cement salvaged from
discarded or used bags shall not be used.
701.1 General
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 372/437
Type NA and SA are air-entrained hydrated limes that are suitable for use in
any of the above uses where air-entrainment are desired.
Type S and SA hydrated lime develop high, early plasticity and higher water
retentivity and by a limitation on their unhydrated oxide content.
It is the intent of this Specification to use either the Type N or S for soil
stabilization and as filler requirement to bituminous plant mixtures. It is expected to
provide pavements with greater resistance to the detrimental effects of water,
especially flooding during the rainy season.
Percentage
a. Percentage Residue
The residue retained on a 0.600 mm (No. 30) sieve shall not be more
than 0.57% and not more than 15% on a 0.075 mm (No. 200) sieve.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 373/437
b. Plasticity
5/7/2018
The putty made from Type S, special hydrate, or type SA, special air-
DPW H Blue Book - slide pdf.c om
entraining hydrate, shall have plasticity figure of not less than 200 when
hydrate or from putty made from the hydrate which has been soaked for a
period of 16 to 24 hours.
Hydrated lime for construction purposes shall conform to the following grading
requirements:
701.5 Sampling
At least one percent of the package shall be sampled but in no case shall less
than five packages be sampled. Individual packages shall be taken from various
parts of the unit being sampled. Each package so taken shall be opened and not
less than 0.5 kg shall be taken by means of a sampling tube that takes a core of the
material of not less than 2.5 cm in diameter and that is of sufficient length to permit
the taking of the sample from the top to the bottom of the mass being sampled. The
material removed shall be thoroughly mixed and quartered. Triplicate samples of
not less than 2.5 kg each shall be taken and sealed in properly labelled, air-tight,
moisture proof containers.
701.7 Packing
be loaded and certify that it was clean and free of contaminating material
and loaded.
c. The Contractor shall furnish with each shipment two copies of the delivery
ticket. The delivery tickets shall contain the following information:
At 15.5 C (60 F)
Net Weight _______________________________________________
Identification No. (Truck, Car, Tank, etc.) ________________________
d. The Contractor or the supplier as his agent, shall deliver to the Engineer
or his representative a certification signed by an authorized representative
of the supplier to cover the quality and quantity of material and the
condition of container for each shipment. The certification shall be
essentially in the following form and may be stamped, written or printed
on the delivery tickets.
Producer ________________________
Signed __________________________
Failure to sign the certification will be a cause to withhold use of the material
until it can be sampled, tested and approved.
If this review indicates that the certifications are not reliable, the acceptance of
bituminous materials by certification will be discontinued and the contents of each
shipping container will be sampled at point of delivery, tested and accepted prior to
5/7/2018 DPW H Blue Book - slide pdf.c om
incorporation into the work. This procedure will be followed until the engineering
a. All the foregoing requirements of Item 702 shall apply for the type of
bituminous material involved.
b. Additionally, the Contractor or the supplier as his agent, shall furnish the
Engineer or his representative along with and the time of delivery of the
initial shipment of fortified bituminous material to the project, and thereafter
with the subsequent shipments when ordered by the Engineer, 1 litre (1
quart) sealed sample of the bituminous material taken at the time of
loading at the refinery and prior to introduction of the additive, along with a
separate 0.5 litre (1 pint) sample of the anti-stripping additive involved.
seconds
KinematictoViscosity
achieve aof
150-300 mm2 /s (150-
300) centi-stokes
Table 702.1 shall apply unless temperatures ranges applicable to specific lots
of material delivered to the job are supplied by the producer.
5/7/2018
c. Tar for mop or seal coats: DPW H Blue Book - slide pdf.c om
702.8 Tars
Dust oils and clarified dust oil shall conform to the following requirements:
703.1.1 Concrete
703.1.2 Granular backfill filter material for underdrains and filler for paved
waterways shall be permeable and shall meet the requirements of AASHTO M 6,
except that soundness tests will not be required and minor variations in grading and
content of deleterious substances may be approved by the Engineer.
Coarse aggregate for concrete shall meet the requirements of AASHTO M 80.
703.3 Aggregate for Portland Cement Treated and Stabilized Base Course
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 381/437
The crushed and uncrushed granular material shall consist of hard durable
stones and rocks of accepted quality, free from an excess of flat, elongated, soft or
5/7/2018 disintegrated pieces or other objectionable matter. The method used in obtaining
DPW H Blue Book - slide pdf.c om
Coarse aggregate is the material retained on the 2.00 mm (No. 10) sieve and
shall have a percentage of wear of not more than 50 for subbase and not more than
45 for Base and Surface Courses as determine by AASHTO Method T 96.
Fine aggregate is the material passing the 2.00 mm (No. 10) sieve and shall
consist of natural or crushed sand and fine mineral particles. The fraction passing
the 0.075 mm (No. 200) sieve shall not be greater than 0.66 (two-thirds) of the
fraction passing the 0.425 mm (No. 40) sieve. For base courses, the fraction
passing the 0.425 mm (No. 40) sieve shall have a liquid limit not greater than 25 and
a plasticity index not greater than 6, while for subbase course, the liquid limit shall
not be greater than 35 plasticity index not greater than 12.
For surface courses, the fraction passing the 0.425 mm (No. 40) sieve shall
have a liquid limit not greater than 35 and a plasticity index not less than 4 or greater
than 9.
All materials shall be free from vegetable matter and lumps or balls of clay.
When crushed aggregate is specified, not less than 50 mass percent of the
particles retained on the 4.75 mm (No. 4) sieve shall have at least one fractured
face.
meet the gradation required under the composition of mixture for the specific type
under contract. Only one kind shall be used on the project except by permission of
the Engineer.
703.5.2 Fine Aggregate
Fine aggregate passing the 2.36 mm (No. 8) sieve shall consist of natural
sand, stone, stone screenings or slag screenings or a combination thereof and
unless otherwise stipulated shall conform to the quality requirements of AASHTO M
29 (ASTM D 1073). Fine aggregate shall be of such gradation that when combined
with other required aggregate fractions in proper proportion, the resultant mixture will
meet the gradation required under the composition of mixture for the specific type
under contract.
Aggregate shall conform to Subsections 703.5.1 and 703.5.2 above and the
following requirements. Relatively pure carbonate aggregates or any aggregates
known to polish shall not be used for the coarse aggregate fraction (material retained
on the 2.36 mm (No. 8) sieve. In addition, the coarse aggregate fraction shall have
at least 75 mass percent of weight of particles with at least two fractured faces and
90 mass percent with one or more fractured faces, except that lightweight
aggregates need not meet this requirement. The abrasion loss (AASHTO T 96)
shall not exceed 40 mass percent.
Aggregate shall be uniformly graded from coarse to fine. Target values for
the intermediate sieve sizes shall be established within the limits shown in Table
5/7/2018
703.1. DPW H Blue Book - slide pdf.c om
Table 703.1
Range of Gradation Target Values
If crushed gravel is used, not less than 50 mass percent of the material
retained on the 4.75 mm (No. 4) sieve shall be particles having at least one fractured
face.
That portion of the composite material passing a 4.75 mm (No. 4) sieve shall
have a sand equivalent of not less than 35, as determined by AASHTO T 176,
Alternate Method No. 2.
The aggregate shall show a durability index not less than 35 (coarse and fine)
as determined by AASHTO T 210.
The material shall be free of clay balls and adherent films of clay or other
matter that would prevent thorough coating with the bituminous material.
The provisions of Subsections 703.5.1, 703.5.2 and 703.5.3 shall apply. The
several aggregate fraction for the mixture shall be sized, graded and combined in
such proportions
requirements that703.2
of Table the resulting composite
as specified blend meets one of the grading
in the Schedule.
The in
combined several
such aggregate fractions
proportions for the
that the mixture
resulting shall be sized,
composite blendsgraded
meet and
the
respective grading requirements of Table 703.3 adjusted to reflect variation in
aggregate densities.
The material for the top dressing shall consist of dry sand, stone screenings
or slag screenings so graded that at least 95 mass percent shall pass the 4.75 mm
(No. 4) sieve and not more than 40 percent shall pass the 0.300 mm (No. 50) sieve.
Table 703.2
Gradation Ranges – Hot Plant Mix Bituminous Pavements
(Mass percent passing square sieves, AASHTO T 11 and T 27)
Sieve GRADING
Designation, A B C D E F G
mm
37.5 (1-1/2 inch) 100 - - - - - -
25 ( 1 inch) 95-100 100 100 - - - -
19 (3/4 inch) 75-95 95-100 95-100 100 - 100 -
12.5 (1/2 inch) - 68-86 68-86 95-100 100 - 100
9.5 (3/8 inch) 54-75 56-78 56-78 74-92 95-100 - 95-100
4.75 (No. 4) 36-58 38-60 38-60 48-70 75-90 45-65 30-50
2.36 (No. 8) 25-45 27-47 27-47 33-53 62-82 33-53 5-15
1.18 (No. 16) - 18-37 18-37 22-40 38-58 - -
0.600 (No. 30) 11-28 11-28 13-28 15-30 22-42 - -
0.300 (No. 50) - 6-20 9-20 10-20 11-28 10-20 -
0.075 (No. 200) 0-8 0-8 4-8 4-9 2-10 3-8 2-5
retained on the 2.00 mm (No. 10) sieve shall have at least one fractured face.
Gradation shall conform to Grading F of Table 703.2.
5/7/2018 DPW H Blue Book - slide pdf.c om
gravel. Only one type of aggregate shall be used on the project unless alternative
types are approved. Aggregates shall meet the quality requirements of AASHTO M
78-74.
When tested in accordance with AASHTO T 182, (ASTM D 1664) aggregate
shall have a retained bituminous film above 95 mass percent.
Aggregates which do not meet this requirement may be used for bituminous
surface treatments and seal coats provided a water resistant film.
When crushed gravel is used, not less than 50 mass percent of the particles
retained on the 4.75 mm (No. 4) sieve shall have at least one fractured face.
Aggregates shall meet the gradation requirements called for in the Bid Schedule.
Table 703.3
Table 703.4
Gradation Requirements for Cover Coats
(Mass percent passing square mesh sieves, AASHTO T 27)
Sieve
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 Grading designation with corresponding size 386/437
703.11 Blotter
Table 703.5
Gradation Requirements for Bituminous Surface Treatments
(Mass percent passing square mesh sieves, AASHTO T 27)
2.36
0.150 No. 100
No. 8 -- -- 0-5
- 0-10
- 10-40
- 60-100
0-10
Table 703.6
Bed course material for sidewalks, paved waterways and curbing shall consist
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 387/437
of cinders, sand, slag, gravel, crushed stone or other approved material of such
gradation that all particles will pass through a sieve having 37.5 mm (1-1/2 inches)
5/7/2018
i g DPW H Blue Book - slide pdf.c om
That portion of the material passing a 0.425 mm (No. 40) sieve shall have a
plasticity index of not over 6, as determined by AASHTO T 90.
Table 703.7
25
4.75 1” 4
No. 30 –- 70 30 –- 70 40100
– 80
0.075 No. 200 0 - 15 0 - 15 5 – 20
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 388/437
Crushed slag shall consist of clean, tough, durable pieces of blast furnace
slag, reasonably uniform in density and quality and reasonably free from glassy
pieces.
5/7/2018 DPW H Blue Book - slide pdf.c om
That portion of the material passing a 0.425 mm (No. 40) sieve shall have a
plasticity index of not over 6, as determined by AASHTO T 90.
The material shall be visually free from vegetable matter or lumps or balls of
clay and shall meet the requirements for one of the gradings given in Table 703.8 as
called for in the Bid Schedule.
Table 703.8
* Gradation varies with top size of material and should be based on size of largest
material used. For instance, if largest size is 50 mm (2 inches), gradation should
be under heading B; if 25 mm (1 inch), under A.
aggregate. The material shall meet one of the grading requirements of Table 703.9.
Table 703.9
Grading Requirements for Aggregates for Emulsified Asphalt Treated Base
(Mass percent passing square mesh sieves, AASHTO T 11 & T 27)
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 389/437
Sieve Designation
Standard mm Alternate US Standard Grading A Grading B Grading C
5/7/2018 DPW H Blue Book - slide pdf.c om
If crushed gravel is used, not less than 65 mass percent of the coarse
aggregate particles retained on a 4.75 mm (No. 4) sieve shall be particles having at
The aggregate shall show a durability factor not less than 35 (coarse and fine)
as determined by AASHTO T 210 (Production of Plastic Fines in Aggregates).
The material shall be free of clay balls and adherent films of clay or other
matter that would prevent thorough coating with bituminous material.
703A.1 Description
Mineral filler shall consist of finely divided mineral matter such as rock dust,
slag dust, hydrated lime, hydraulic cement, fly ash or other suitable mineral matter.
It shall be free from organic impurities and at the time of use, shall be sufficiently dry
to flow freely and shall be essentially free from agglomerations.
portions may be taken from holes dug into the material at 5 or more locations to
provide a field sample of at least 5 kg (10 lb).
From the unit to be sampled, select at least one percent of the packages at
random for sampling, but in no case shall fewer than 5 packages be selected. Take
a sample portion from a hole dug into the top of each package selected for sampling.
A sampling tube may be used that takes a core not less than 25 mm (1 inch)
diameter. Insert the tube into the package to substantially sample the entire length
of the package. Combine the sample portions taken to obtain a field sample of at
least 5 kg (10 lb).
Gradation
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 T 37 391/437
Plasticity Index T 90
5/7/2018 DPW H Blue Book - slide pdf.c om
Sewer Brick -
AASHTO M 91, Grade SM
Sewer Brick -
ASTM C 32, Grade SM
Building Brick -
AASHTO M 114, Grade SW, or ASTM C 62,
Grade SW
The grade will be shown on the Plans or in the Special Provisions.
Solid blocks shall conform with the requirements of ASTM C 139 or ASTM C
145, grade as specified. Hollow blocks shall conform to the requirements of ASTM
C 90, grade as specified.
Poured filler for joints shall conform to the requirements of AASHTO M 173.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 392/437
Pipesand
approved joint with
mortarwater
shall as
consist of one to
necessary partobtain
Portland
the Cement
requiredand two parts
consistency.
Portland Cement and sand shall conform respectively to Section 700.1 and 703.1. If
shown in the Special Provisions, air entrainment conforming to Section 708.2 shall
be provided. Mortar shall be used within 30 minutes after its preparation.
Ring gaskets for rigid pipe shall conform to the requirements of AASHTO M
198. Continuous flat gaskets for flexible metal pipe shall conform to the
requirements of ASTM D 1056 with grade SCE 41 used for bands with projections or
flat bands and grade SCE 43 for corrugated bands. Gaskets thickness for bands
with projections or flat bands shall be 12.5 mm (1/2 inch) greater than the nominal
depth of the corrugation and shall be 9.5 mm (3/8 inch) for corrugated bands.
705.4 Oakum
Oakum for joints in bell and spigot pipe shall be made from hemp (Cannabis
Sativa) line, or Benares Sunn fiber, or from a combination of these fibers. The
oakum shall be thoroughly corded and finished and practically free from lumps, dirt
and extraneous matter.
For masonry walls not exceeding 1.8 m (6 feet) in height, a mortar composed
of one part masonry cement and two parts fine aggregate by volume maybe
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 393/437
substituted for the above mixture of Portland Cement, lime and fine aggregate. For
other construction, masonry cement may be used if and as shown on the Plans.
5/7/2018 DPW H Blue Book - slide pdf.c om
Hydrated lime shall meet the requirements for Residue, Popping and Pitting,
and Water retention shown for Type N lime in Section 701.3 (ASTM C 207).
Sheet copper for water stops of flashings shall meet the requirements of
AASHTO M 138 (ASTM B 152) for Type ETP, light cold-rolled, soft anneal, unless
otherwise specified in the Special Provisions.
Rubber water stops may be molded or extruded and have a uniform cross-
section, free from porosity or other defects, conforming to the nominal dimensions
shown on the Plans. An equivalent standard shape may be furnished, if approved
by the Engineer.
The water stop may be compounded from natural rubber, synthetic rubber or
a blend of the two, together with other compatible materials which will produce a
finished water stop meeting the requirements of Table 705.1. No reclaimed material
shall be used. The Contractor shall furnish a certificate from the producer to show
the general compositions of the material and values for the designated properties.
The Contractors shall also furnish samples, in length adequate for making
designated tests, as ordered by the Engineer.
Table 705.1
Table 705.2
ASTM
Property Method Requirements
Tensile strength D 638 Minimum 9.646 MPa
(1,400 psi)
Elongation at breaking D 638 Minimum 260 percent
Hardness (shore) D 2240 60 – 75
Specific gravity (Federal test Method No. Maximum – 0.02 from
1
The cold bend test will be made by subjecting a 25 x 150 x 3 mm (1 x 6 x
1/8 inch) strip of plastic water stop to a temperature of –28.8 0C (-200F) for 2
hours. The strip will immediately thereafter be bent 180 degrees around a rod
of 6.35 mm (1/4 inch) diameter by applying sufficient force to hold the sample in
intimate contact with the rod. The sample will then be examined for evidence
of cracking. At least three individual samples from each lot will be tested and
the result reported.
It shall meet the requirements of Federal Specification SS-S-169 for the type
and class specified.
This pipe shall conform to the requirements of AASHTO M 175 for the
specified diameters and strength classes.
This pipe shall conform to the requirements of AASHTO M 176 (ASTM C 654)
for the specified diameters.
Designs for fully lined or half lined pipes of the specified strength classes shall
be submitted by the manufacturer for approval. The application requirements of
AASHTO M 170 and AASHTO M 65 shall govern. Liner or liner elements, shall be
clay of first quality, sound, thoroughly and perfectly burned without warps, cracks or
other imperfections and fully and smoothly salt glazed.
This pipe shall conform to the requirements of AASHTO M 65, for pipe with
full circular cross-section, for the specified diameters and strength class. When
specified,
and the bell feature.
self-centering shall have integral spacer lugs to provide for an annular opening
706.8 Vitrified Clay Pipe
This pipe shall conform to the requirements of Section 706.7 for the specified
diameters and strength classes for circular, unperforated or perforated pipe as
shown on the Plans.
This pipe shall conform to the requirements of AASHTO M 217 (ASTM C 428)
5/7/2018 DPW H Blue Book - slide pdf.c om
This pipe shall conform to the requirements of AASHTO M 177 ASTM D 1861
or D 1862.
This pipe shall conform to the requirements of Sections 706.12 for the
specified diameters. Unless otherwise specified, either Type I or Type II Couplings
may be furnished.
706.14 Reinforced Concrete Arch Culvert, Storm Drain and Sewer Pipe
706.15 Reinforced Concrete Elliptical Culvert, Strom Drain and Sewer Pipe
706.16 Reinforced Concrete D-load Culvert, Storm Drain and Sewer Pipe
2680).
5/7/2018 DPW H Blue Book - slide pdf.c om
Corrugated steel pipe and pipe arches fabricated by resistance spot welding
shall comply with the applicable requirements of AASHTO M 36 and M 218.
707.2.4 Special sections, such as elbows and fabricated flared and sections,
shall conform to the applicable requirements of AASHTO M 36 and M 218.
Coupling bands shall conform to AASHTO M 36 and M 218, except that use
of bands with projections (dimple bands) will be limited to end sections and to pipe
laid on grades under 10 percent.
Bands of special design that engage factory reformed ends of corrugated pipe
may be used.
707.3 Bituminous Coated Corrugated Iron or Steel Pipe and Pipe Arches
5/7/2018 DPW H Blue Book - slide pdf.c om
the type specified. Flared end sections shall conform to the requirements of
AASHTO M 243 for the coating specified.
The Engineer may waive the imperviousness test for coated pipe if no
separation of coating from metal is observed.
This pipe shall conform to the requirements of AASHTO M 36 and M 218 for
the specified diameters and types. Galvanized metal part-circle pipe may be used if
permitted by the Special Provisions and shown in the Bid Schedule.
This pipe shall conform to the requirements of Section 707.6 and shall be
coated with bituminous material conforming to the requirements of AASHTO M 190,
type of coating as specified.
These conduits and bolts and nuts for connecting plates shall conform to the
requirements of AASHTO M 167.
707.11 Full Bituminous Coated Structural Plate Pipe, Pipe Arches and Arches
These conduits shall conform to the requirements of Section 707.10 and shall
be coated with bituminous material conforming to the requirements of AASHTO M
243, type coating as specified.
707.12 Aluminum Alloy Structural Plate for Pipe, Pipe Arches and Arches
These conduits and the bolts and nuts for connecting plates shall conform to
the requirements of AASHTO M 219.
707.13 Full Bituminous Coated Aluminum Alloy Structural Plate Pipe, Pipe
Arches and Arches
These conduits shall conform to the requirements of Section 707.12 and shall
be coated with bituminous materials conforming to the requirements of AASHTO M
Slotted pipe shall be the angle slot pipe or the grate slot type. The type of
slotted pipe to be installed shall be at the option of the Contractor.
Slot angles for the angle slot drain shall conform to the requirements of ASTM
S 36.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 401/437
5/7/2018 DPW H Blue Book - slide pdf.c om
conform to the provisions in ASTM A 501. Said bolts, nuts and spacers shall be
galvanized in accordance with the provisions of AASHTO M 111.
708.1 Description
This Item specifies the classification, sampling, testing, packing and marking
of concrete admixtures. It also specifies the physical requirements for concrete with
each type of chemical admixtures.
B B
PHYSICAL Type A Type B Type C Type D Type E Type F Type G
PROPERTY
Water Content,
percent of 95 - - 95 95 88 88
control, maximum
Time of setting,
allowable
deviation from
control, hour
Initial Minimum - 1.0 later 1.0 1.0 later 1.0 - 1.0 later
earlier earlier
Maximum 1.0 3.5 later 3.5 3.5 later 3.5 1.0 3.5 later
earlier earlier earlier earlier
nor 1.5 nor 1.5
later
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 later 403/437
Final : Minimum - - 10 - 10 - -
5/7/2018 DPW H Blue Book - slide pdf.c om
A
The values in the table include allowance for normal variation in test results. The
objects of the 90% compressive strength for Type B admixture is to require a
level of performance comparable to that of the reference concrete.
B
It is recommended that whenever practicable, tests may be made using cement,
pozzolan, aggregates, air-entraining admixture, and the mix proportions and
batching sequence when used in non-air-entraining and air-entrained concrete
because the specific effects produced by chemical admixtures may vary with the
properties and proportion of the other ingredients of the concrete. For instance,
types “F” and “G” admixtures may exhibit such higher water reduction in concrete
mixtures having higher cement factors than 307 + -3 kg/m3. Mixtures having a
high range water reduction generally display a higher rate of slump loss. When
high range admixtures are used to impart increased workability (15 cm to 20 cm
slump), the effect may be of limited duration, reverting to the original slump in 30
to 60 min depending on factors normally affecting rate of slump loss.
C
The compressive and flexural strength of the concrete containing the admixture
under test at any test age shall be not less 90% of that attained at any previous
test age. The objective of this limit is to require that the compressive or flexural
strength of the concrete containing the admixture under test shall not decrease
with age.
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 404/437
5/7/2018 DPW H Blue Book - slide pdf.c om
708.5 Sampling
708.5.1 The chemical admixtures for concrete shall be sampled either by grab or
composite sampling. A grab sample is one obtained in a single operation.
A composite sample is one obtained by combining three or more grab
samples.
708.5.2.1 The grab samples taken for quality tests shall represent a unit
shipment or a single production lot. Each grab sample shall have a
volume of at least 0.5L (1 pint), a minimum of 3 grab samples shall be
taken.
708.5.2.3 Admixtures in bulk storage tanks shall be sampled equally from the
upper, intermediate and lower levels by means of drain cocks in the
sides of the tanks or a weighed sampling bottle fitted with a stopper
that can be removed after the bottle is lowered to the proper depth.
708.5.3.1 The grab samples taken shall represent not more than 2 Mg (2 tons) of
admixture and shall have a mass of at least 1 kg (2 lb). A minimum of
four grab samples shall be taken.
708.6 Testing
708.7 Packing
708.8 Marking
709.1 Description
This Item covers all paint materials including Vehicles, Pigment, Pastes,
Driers, Thinners and Mixed Paints for steel and wooden structures.
709.2.1 General
curdling, livering, caking or color separation and shall be free from lumps
and skins.
b. The paint as received shall brush easily, possess good levelling properties
and shall show no running or sagging when applied to a smooth vertical
surfaces.
c. The paint shall dry to a smooth uniform finish free from roughness grit,
uneveness and other imperfections.
d. The paint shall not skin within 48 hours in three quarters filled closed
container.
e. The paint shall show no thickening, curdling, gelling or hard caking after
six (6) months storage in full, tightly covered container at a temperature of
0 0
21 C (70 F).
709.2.2 The paint shall conform to the requirements of the indicated specifications
as follows:
Red Lead Ready-Mixed Paint AASHTO M 72
Type I, II, III and IV
Aluminum Paint AASHTO M 69 Type I and II
White & Tinted Ready-Mixed Paint AASHTO M 70
Foliage Green
Black Paint for Bridge
BridgesPaint
and Timber AASHTO M 67
Structures AASHTO M 68
Basic Lead Silicon Chromate, Ready-
Mixed Primer AASHTO M 229
709.2.3 The constituents parts of the paint shall meet the following specifications:
709.2.4 Drier
These specifications cover both straight oil drier (material free from resins and
“gums”), and Japan drier (material containing varnish “gums”). The drier shall be
composed of lead manganese, or cobalt, or a mixture of any of these elements,
combined with a suitable fatty oil, with or without resins of “gums” and mineral spirits
of turpentine, or a mixture of these solvents. The drier shall conform to the following
requirements:
When two field coats of aluminum paint are specified, the first coat shall be
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 408/437
5/7/2018 DPW H Blue Book - slide pdf.c om
This paint shall be mixed as specified for Aluminum Paint for Structural Steel
except that the proportions shall be 0.272 kg of aluminum powder or paste per litre of
vehicle (2-1/2 lb/gal).
Other paint composition may be used when and as stipulated in the Special
Provisions.
The sleeves for dowel bars shall be metal of an approved design to cover 50
mm (2 inches), plus or minus 6.3 mm of the dowel, with a closed end, and with a
suitable stop to hold the end of the sleeve at least 25 mm (1 inch) from the end of the
dowel bar. Sleeves shall be of such design that they do not collapse during
construction.
The wire rope or wire cable shall conform to the requirements of AASHTO M
30 for the specified diameter and strength class.
Galvanized barbed wire of the coating class specified shall conform to the
Galvanized woven wire fence of the coating class specified shall conform to
the requirements of ASTM A 116. Aluminum coated woven wire fence shall
conform to the requirements of ASTM A 584.
Chain link fabric and the required fittings and hardware shall conform to
AASHTO M 181, for the kind of metal, coating, size of wire and mesh specified.
Galvanized coiled spring steel tension wire shall be 7 (0.177 inch) gauge,
conforming to ASTM A 641 hard temper, with Class 3 coating unless otherwise
specified or shown on the drawings.
Aluminized coil spring steel tension wire shall also be 7 (0.177 inch) gauge,
hard temper, having a minimum coating mass of 0.12 kg/m 2 (0.40 oz/ft2) of
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 411/437
5/7/2018 DPW H Blue Book - slide pdf.c om
The timber rail shall be cut from the specified grade of dry, well seasoned and
dressed timber stock of the species specified, which shall meet the applicable
requirements of AASHTO M 168.
Rustic rails shall be straight, sound and free of injurious defects and shall
have been cut from live trees not less than 30 days but not more than 1 year before
use. They shall have been stripped of bark before seasoning or shall have been
stored under water. Immediately before the logs are used in the work, all knots and
projections shall be trimmed and smooth and, if water cured, all barks shall be
peeled. Slight curvature of “wind” to give a pleasing appearance to the structure will
be permitted. Logs of only one specie shall be used in the construction of any one
continuous length of guardrail.
Wood posts shall conform to the details and dimensions indicated on the
Plans. All wood posts shall be sound, seasoned wood, peeled and with ends cut
square or as indicated. The posts shall be straight and all knots trimmed flush with
surface. Where treated posts are called for, the kind and type of treatment shall
conform to that indicated on the Plans. When red cedar posts or bracing is
furnished, the requirements for peeling may be omitted.
All dimensions timber and lumber required for fences or gates shall be sound,
straight and reasonably free from knots, splits and shakes. It shall be of the species
and grades indicated on the Plans and shall be dressed and finished on four sides.
Steel box rail elements shall conform to the applicable standards contained in
AASHTO-AGC-ARTBA” Guide to Standardized Highway Barrier Rail Hardware”.
712.1.1 General
b. High-Strength Low Alloy Structural Steel with 344.5 MPa (50,000 psi)
Minimum Yield Point to 100 mm (4 inches) thick, AASHTO M 222 (ASTM
A 588 in Supplementary Requirement S1 of AASHTO M 222 mandatory).
b. High-Strength
Minimum Yield Low
PointAlloy Structural
to 100mm Steelthick,
(4 inches) with AASHTO
344.5 MPa (50,000 psi)
M 222.
Bolts, nuts circular washers shall conform to High-Strength Bolts for Structural
Steel Joints, including Suitable Nuts and Plain Hardened Washer, AASHTO M 164
(ASTM A 325).
High-strength bolts for structural steel joints including suitable nuts and plain
hardened washers shall conform to either AASHTO M 164 (ASTM A 325) or
AASHTO M 253. When M 164 type 3 bolts are specified, they along with suitable
nuts and washers shall have an atmospheric corrosion resistance approximately two
times that of carbon steel with copper.
Bolts and nuts manufactured to AASHTO M 164 (ASTM A 325) are identified
by proper marking as specified on the top of the bolt heads and on one face of the
nuts for three different types.
Bolt and nut dimensions shall conform to the dimensions shown in Table
712.1 and to the requirements for Heavy Hexagon Structural Bolts and for Heavy
Semi-Finished Hexagon Nuts given in ANSI Standard B 18.2.1 and B 18.2.2,
respectively.
Circular washers shall be flat and smooth and their nominal dimensions shall
conform to the dimensions given in Table 712.2 except that for lock pin and collar
fasteners, flat washers need not be used, unless slotted or oversized holes are
specified.
When necessary, washer may be clipped on one side to a point not closer
than 0.875 (7/8) of the bolt diameter from the center of the washer.
Subject to the approval of the Engineer, high strength steel lock-pin and collar
fasteners may be used as an alternate for high strength bolts or rivets as shown on
the Plans. The shank and head of the high strength steel lock-pin and collar
fasteners shall meet the requirements of the preceding paragraph. Each fasteners
shall provide a solid shank body of sufficient diameter to provide tensile and shear
strength equivalent to or greater than the bolt or rivet specified, shall have a cold
forged head on one end, of type and dimensions as approved by the Engineer, a
shank length suitable for material thickness fastened, locking grooved, break neck
groove and pull grooves (all annular grooves) on the opposite end. Each fasteners
shall provide a steel locking collar of proper size for shank diameter used which by
means of suitable installation tools, is cold swaged into the locking grooves forming a
head for the grooved end of the fastener after the pull groove section has been
removed. The steel locking collar shall be a standard product of an established
manufacturer of lock-pin and collar fasteners, as approved by the Engineer.
When copper bearing steel is specified, the steel shall contain not less than
0.2 percent of copper.
712.2 Forgings
Steel forgings shall conform to the specifications for Steel Forgings, Carbon
and Alloy, for General Industrial Use, AASHTO M 102, (ASTM A 668, Classes C, D,
F & G).
Pins and rollers more than 228.6 mm (9 inches) in diameter shall be annealed
carbon-steel forgings conforming to AASHTO M 102, Class C1.
a
Dimensions in mm (inches)
b
May be exceeded by 6 mm (1/4 inch)
c
4 mm (3/16 in) nominal
d
6 mm (1/4 in) nominal
712.4 Castings
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 417/437
5/7/2018 DPW H Blue Book - slide pdf.c om
Gray Iron Castings – AASHTO M 105 Class No. 30 shall be furnished unless
otherwise specified. Iron castings shall be true to pattern in form and dimensions,
free from pouring faults, sponginess, cracks, blow holes, and other defects in
position affecting their strength and value for the service intended. Casting shall be
boldly filleted at angles and the arises shall be sharp and perfect. All castings must
be sandblasted or otherwise effectively cleaned of seals and sand so as to present a
smooth, clean and uniform surface.
All steel for grid floors shall conform to the requirements of AASHTO M 183 or
AASHTO M 222. Steel grid floors can be weathering steel, galvanized or painted.
Unless the floors are of weathering steel or galvanized, the material shall have a
minimum copper content of 0.2%.
Standard weight pipe shall be furnished unless otherwise shown on the Plans
or in the Special Provisions.
When galvanized structural steel shapes, plates, bars and their products are
specified, they shall be galvanized in accordance with the requirements of AASHTO
M 111.
In fracture occurs outside the middle half of the gage length, the test shall be
repeated.
Finished studs shall be of uniform quality and conditions, free from injurious
laps, fins, seams, cracks, twists, bends or other injurious defects. Finish shall be
produced by cold drawing, cold rolling or machining.
The Contractor shall furnish the manufacturer’s certification that the studs as
delivered are in accordance with the material requirements of this Item. Certified
copies of in-plant quality control test reports shall be furnished to the Engineer upon
request.
Table 712.3 – Welded Stud Shear Connector
Standard Dimensions and Tolerances mm (inches)
Shank Head
Diameter (c) Length* (L) Diameter (H) Thickness (T)
19.05 + 0.00 101.6 + 1.575 (+0.062) 31.75 + 0.40 9.53
(3/4) - 0 381 (4) – 3 175 (1-1/4) ± (1/64) (3/8) min
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 419/437
5/7/2018 DPW H Blue Book - slide pdf.c om
713.1.2 Paints
713.1.3 Preservatives
Yard lumber shall be of the kinds and grade called for on the Plans. Round
poles and posts shall be of the kinds indicated on the Plans.
714.1 Description
This Item covers criteria for acceptance of Questionable Water either natural
or wash water for use in concrete.
714.2 Requirements
objectionable,
concrete madeorwithcause
it (orsuspicion, it shall not
other information) be used
indicated unless
that service
it is not records
injurious of
to the
quality, shall be subject to the acceptance criteria as shown in Table 714.1 and
Table 714.2 or as designated by the purchaser.
When wash water is permitted, the producer will provide satisfactory proof or
data of non-detrimental effects if potentially reactive aggregates are to be used.
Use of wash water will be discontinued if undesirable reactions with admixtures or
aggregates occur.
Table 714.1
Acceptance Criteria For Questionable Water Supplies
Limits
Compressive strength, min. %
Control at 7 days 90
Time of Setting deviation from control from 1:00 earlier to 1:30 later
Time of Setting (Gillmore Test)
Initial No marked change
Final Set No marked change
Appearance Clear
Color Colorless
Odor Odorless
Total Solids 500 parts/million max.
PH value 4.5 to 8.5
Table 714.2
Chemical Limitation for Wash Water
Limits
Chemical Requirements, Minimum
http://slide pdf.c om/re a de r/full/dpwh-blue -book-559a bba c 69281 421/437
5/7/2018 DPW H Blue Book - slide pdf.c om
Alkalies as (Na
Total Solids,
2O + 0.658 K2O), ppm
ppm 600
50000
A
Wash water reused as mixing water in concrete may exceed the listed
concentrations of sulfate if it can be shown that the concentration calculated in
the total mixing water, including mixing water on the aggregate and other
sources, does not exceed that stated limits.
Water will be tested in accordance with, and shall meet the suggested
requirements of AASHTO T 26.
715.1 Description
This Item covers geotextile fabrics for use in subsurface drainage, hydraulic
filter, erosion control, sediment control, pavement structures as a waterproofing and
stress relieving membrane, and as a permeable separator to prevent mixing of
dissimilar materials such as foundations and select fill materials.
Fibers used in the manufacture of geotextiles, and the threads used in joining
geotextiles by sewing, shall consist of long-chain synthetic polymers, composed of
at least 85 percent by mass polyolefins, polyesters, or polyamids. They shall be
formed into a network such that the filaments or yarns rertain dimensional stability
relative to each other, including selvedges. These materials shall conform to the
715.4 Certification
The manufacturer shall file with the purchaser a certificate stating the name
of the manufacturer, the chemical composition of the filaments or yarns, and other
pertinent information so as to fully describe the geotextile. The manufacturer shall
include in the certificate a guarantee stating that the geotextile that is furnished
meets the requirements of the specification. The certificate shall be attested to by
a person having legal authority to bind the company. Either mismarking or
misrepresentation by the manufacturer shall be reason to discontinue acceptance
under these
regarding thespecifications.
discontinuance ofNotice sent towill
acceptance thebemanufacturer bybe
considered to thenotice
purchaser
to all
wholesalers, jobbers, distributors, agents and other intermediaries handling the
manufacturer’s product.
715.6.1 During periods of shipment and storage, the fabric shall be protected
from direct sunlight, ultra-violet rays, temperatures greater than 60 0C (1400F), mud,
dust, and debris. To the extent possible, the fabric shall be maintained wrapped in
a heavy-duty protective covering. Each shipping document shall include a notation
certifying that the geotextile is in accordance with the manufacturer’s certificate and
guarantee previously filed with the purchaser.
Label the fabric and its container with the manufacturer’s name fabric type or
trade name, lot number and quantity.
715.7 Installation
715.7.1 Separation Geotextile
In trenches, after placing the backfill material, the geotextile shall be folded
over the top of the filter material to produce a minimum overlap of 12 inches for
trenches greater than 12 inches wide. In trenches less than 12 inches in width, the
overlap shall be equal to the width of the trench. The geotextile shall then be
covered with the subsequent course. Successive sheets of geotextile shall be
overlapped a minimum of 12 inches in the direction of flow.
Theby
approved geotextile shall beThe
the Engineer. placed and anchored
geotextile on a smooth
shall be placed in suchgraded surface
a manner that
placement of the overlying materials will not excessively stretch or tear the fabric.
Anchoring of the terminal ends of the geotextile shall be accomplished through the
use of key trenches or aprons at the crest and toe of slope. In certain applications
to expedite construction, 18 inches long anchoring pins placed on 2 to 6 feet
centers depending on the slope of the covered area have been used successfully.
The fabric shall be placed into the asphalt sealant with minimum wrinkling
prior to the time the asphalt has cooled and lost tackiness. As directed by the
Engineer, wrinklers or folds in excess of 1 inch shall be slit and laid flat. Brooming
and/or pneumatic rolling will be required to maximize fabric contact with the
pavement surface. Overlap of fabric joints shall be sufficient to ensure full closure
of the joint, but should not exceed 6 inches. Transverse joints shall be lapped in
the direction of paving to prevent edge pickup by the paver. A second application
of asphalt sealant to fabric overlaps will be required if in the judgment of the
Engineer additional asphalt sealant is needed to ensure proper bonding of the
double fabric layer.
715.8.1 The geotextile shall be measured by the number of square meters from
the pavement lines shown on the plans, or from the pavement lines established in
writing by the Engineer.
715.8.4 Excavation, backfill, bedding, and cover material are separate pay items.
1022,3 NR NR H H M M
152 NR NR H M M M
305 NR H M M M M
457 H M M M M M
H = High
M = Medium
NR = Not recommended
1
Maximum aggregate size not to exceed one-half the compacted cover thickness
2
For low volume unpaved road (ADT<200 vehicles)
3
The 102 mm minimum cover is limited to existing road bases intended for use in
new construction
421