Capital Maintenance of Unit 1 Ganvi 1
Capital Maintenance of Unit 1 Ganvi 1
22.50 MW (2x11.25 MW) power house has been commissioned during the month of
December, 2000. The power house has been in operation for the last 21 years. The OEM of power
house is BHEL which has designed, manufactured and erected the generator, Excitation System,
Governor, MIV etc.
1 LOCATION
State Himachal Pradesh
District Shimla
River/Khad Ganvi stream(Tributary of river Satluj)
Power House On left bank of Ganvi stream
2 HYDROLOGY
a) at Diversion site:111.30 sq.km
b) at Discharge site: 90% available
c)Discharge at diversion site:116.50 sq.km
Catchment area
d)Design discharge i/c requirement:10.42 cumecs for
flushing out shingle & sediments
Design Flood:413 cumecs
3 INTAKE WORKS
Trench Weir type Drop type trench weir
Trash Rack To prevent entry of boulders and trash
4 WATER CONDUCTOR SYSTEM
A) R.C.C Box Length 7.623 m
width 2.0 m
slope 1.4
B)Intake tunnel 142.893 m long
Length and Size 2.35m D-shaped
Design Discharge 8.50 cumecs i/c flushing discharge
C) Power Channel
Length and size 97.13 m long
2.35x2.35(part of channel covered with cement concrete
sleeper)
Design discharge 8.50 cumecs i/c flushing discharge
D) Desilting Tank
Vortex tube type having two chambers 87.00 long,6.00 m
Type and size
wide
Length of transitions 15.00 m each
Design discharge 8.50 cumecs i/c flushing discharge
G)Forebay Length=16.45 m
5 PENSTOCK
Number One(Bifurcated near Power House)
Type Steel Penstock
Dia Main 1400 mm
Dia Branches 1000 mm
Length 698.746 m(i/c two branches)
Plate Thickness 8mm to 30 mm
Design discharge 7.25 cumecs
6 POWER HOUSE
Type Underground Power House
Size 77.50mx11.0m
Installed Capacity 22.5 MW
Gross Head 385 m
Net Head 375 m
Type of turbines Vertical axis, Pelton
7 POWER POTENTIAL
90% dependable year=93.34MU
Energy Generation
50% dependable year=124.12MU
8 TAIL RACE TUNNEL
3.30x4.35m D-shaped varying in heigths
Size & Shape
Length=108.317m
BRIEF DETAILS
During the Annual Maintenance of Unit No. 1, groove formation was observed on the surface of the
Turbine Guide Bearing (TGB) Journal of the Turbine Shaft of the machine. Accordingly, this office
hired the services of the expert for assistance in the problem of TGB Journal and alignment and
balancing works of Unit No. 1. Best efforts were made at the power house site to attend the problem
of TGB Journal in the best possible way and the annual maintenance of the Unit No. 1 was
completed by 15.04.2023. The works done during the annual maintenance are more or less
sufficient to run the machine for this peak season. However, in order to run the machine smoothly
for the time to come, it is important that the grooves in TGB Journal be machined at appropriate
factory/works.
Previously, 01 No. Spare turbine shaft was procured from the OEM i.e. M/s BHEL Haridwar and
the same was installed in Unit No. 2 in the year 2017. The Turbine Shaft thus dismantled from Unit
No. 2 is kept at service bay of the power house. This shaft has not been repaired and is required to
repaired at the earliest.
In order to rectify the problem in TGB Journal of the Turbine Shaft of the Unit No. 1, the turbine
shaft of Unit No. 1 needs to be dismantled and replaced with the turbine shaft dismantled from Unit
No. 2. However, this dismantled from the Unit No. 2 is also required to be repaired first.
The dismantling of the turbine shaft is lengthy and complex procedure and involves dismantling of
the Upper Guide Bearing (UGB) Journal Housing, Complete Rotor Assembly and generator shaft.
The dismantling of the rotor, UGB Housing provides an opportunity to perform the capital
maintenance of Unit No. 1. Capital Maintenance of Unit No. 1 was done in the year ………