RCC Detailing for Toilet Block Building
RCC Detailing for Toilet Block Building
-
LD+10Db
B2 230 380 2-T12 1-T12 2-T12 1-T12 1-T10 2L-T8@75,200,75 C/C
S1 S1 B4
B5
230
230
380
380
2-T12
2-T12
1-T12
1-T12
2-T12
2-T12
1-T12
1-T10
1-T10
1-T10
2L-T8@75,200,75 C/C
2L-T8@75,200,75 C/C
-
-
L1/7 L1/7 L2/7 L2/7
B7
B5
B6
B6 230 380 2-T12 1-T12 2-T12 1-T12 1-T12 2L-T8@75,200,75 C/C - COL. COL. COL.
B7 230 380 2-T12 1-T12 2-T12 1-T10 1-T10 2L-T8@75,200,75 C/C -
SCHEDULE OF SLAB [AT FIRST LEVEL] TYPICAL DETAILS SHOWING STIRRUPS SPACING.
REINFORCEMENT ALONG
[ WHERE (D) = BEAM DEPTH ]
SLAB TYPE SLAB Thk. REMARK
4 B3 5 B4 6
SHORT SPAN LONG SPAN L1/3
EXTRA AT EXTRA AT EXTRA AT
T8 @ 125 C/C T8 @ 125 C/C TOP BARS
S1 125 TWO WAY CONTINUOUS A CONTINUOUS CONTINUOUS
ALT BENT UP ALT BENT UP SUPPORT. SUPPORT. SUPPORT.
FIRST SLAB LEVEL PLAN PLINTNH BEAM LEVEL SCHEDULE (M25 : Fe500) (LEVEL: 0 m)
SIZE BOTTOM REINFORCEMENT TOP REINFORCEMENT
BEAM SHEAR STIRRUPS SFR REMARKS
NUMBERS B D STRAIGHT CURTAILED EXTRA EXTRA STRAIGHT EXTRA EXTRA L1/7 L2/7
PB1 1 PB2 2 PB3 3 PB4 LEFT RIGHT LEFT SUPP RIGHT SUPP A BOTTOM BARS
SPACER BAR (PIN) OF MAX.
BOTTOM CURTAILED
PB1 230 380 2-T12 - - - 3-T12 - - 5-2L-T8@100 C/C - CANTILEVERED BAR DIA. OR 16MM DIA.
COL. COL.
PB2 230 380 2-T12 - - - 2-T12 1-T12 - 2L-T8@75,200,75 C/C - -
PB13
PB11
PB15
- - - - - 5-2L-T8@100 C/C -
PB14
PB7 230 380 2-T12 4-T12 CANTILEVERED L1/4 L2/4 L2/4 L3/4
SLAB THK
PB8 230 380 2-T12 - - - 2-T12 2-T12 - 2L-T8@75,200,75 C/C - -
PB5 PB6 PB9 230 380 2-T12 - - - 2-T12 - 2-T12 2L-T8@75,200,75 C/C - -
300
300
300
300
300
300
3M
1 2 3
300 300 300 300 300 300 GROUND PLINTH
300X300 300X300 300X300 8-T12
T12
8-T12
T12
8-T12
T12
8-T12
T12
8-T12
T12
8-T12
T12
G.L.
M25 : Fe500 , COVER = 40mm M25 : Fe500 , COVER = 40mm M25 : Fe500 , COVER = 40mm M25 : Fe500 , COVER = 40mm M25 : Fe500 , COVER = 40mm M25 : Fe500 , COVER = 40mm
-1.5 M
TO
300
300
300
300
300
300
0M
300 T12
300 T12
300 T12
300 T12
300 T12
300 T12
LINE DIAGRAM
8-T12 8-T12 8-T12 8-T12 8-T12 8-T12 TOP BARS
COLUMN MARKED C1 C2 C3 C4 C5 C6
PINS
SHORT DIR T10@150 C/C T10@150 C/C T10@150 C/C T10@150 C/C T10@150 C/C T10@150 C/C EXTRA BARS AT CONT.
M25:Fe500
LONG DIR T10@150 C/C T10@150 C/C T10@150 C/C T10@150 C/C T10@150 C/C T10@150 C/C STIRRUPS NOTES :
FOOTING 1. ALL MATERIALS AND METHODS OF CONSTRUCTION SHALL BE AS PER IS:456-2000
D,d 350 350 350 350 350 350 BOTTOM CURTAILED BARS 2. ALL CONCRETE SHALL BE MACHINE MIXED, MECHANICALLY VIBRATED AND
PINS PROPERLY CURED.
SIZE 900 x 900 1000 x 1000 900 x 900 1000 x 1000 1000 x 1000 1000 x 1000 3. Ø MILD STEEL REINFORCEMENT - Fe= 250 N/mm2
BOTTOM CONT. BARS TOR STEEL REINFORCEMENT - Fe= 500 N/mm2
M15
P.C.C 150 THK 1200 x 1200 1300 x 1300 1200 x 1200 1300 x 1300 1300 x 1300 1300 x 1300
REINFORCEMENT SHALL CONFIRM TO DUCTILITY REQUIREMENTS OF IS: 13920
4. LAPPING / ANCHORAGE / DEVELOPEMENT LENGTH (Ld)
FOOTING MARKED F1 F2 F3 F4 F5 F6 SECTION AT A-A FOR A) BEAM & SLAB 60 x BAR DIAMETER
B) COLUMN 50 x BAR DIAMETER
LAPS SHALL BE STAGGERED AND NOT MORE THAN 50 % BARS TO BE LAPPED
PROVIDE LINKS T8 @
4 5 6 100 C/C AT JUNCTION OF
AT ANY SECTION. ANY DEVIATION IN LAP LOCATIONS SHALL BE GOT APPROVED
COLUMN AND BEAMS FIRST SLAB LEVEL FROM OUR OFFICE.
300X300 300X300 300X300 5. BEAMS OF WIDTH 6" (150mm) PROVIDE ONLY 2 BARS IN ONE LAYER AND
BEAMS OF WIDTH 9" (230mm) PROVIDE ONLY 3 BARS IN ONE LAYER AND
NOMINAL COVER TO REINFORCEMENT MILD
I FOOTINGS 50
SLAB LEVEL BEAM
FOUNDATION LEVEL PLAN CONFINING LINKS
T8 @ 70 C/C II
COLUMNS
(TO LINKS OF COLUMN)
40
iii SLABS 20
LENGTH
iv
LAP
(TO STIRRUPS OF BEAM)
H/4 LINKS v LIFT WALLS 40
T8 @ 100C/C
H/2 LINKS
T8 @ 150C/C FOR MAIN REINF. UP TO 12mm DIA. BAR FOR MILD EXPOSURE THE NOMINAL
TOP BARS
NOTES - COVER MAY BE REDUCED BY 5mm FOR SLABS AND BEAMS ONLY.
EXTRA AT ENDS SUPPORT 1) FOUNDATION TO REST ON 7. BEAMS WITH DEPTH MORE THAN 750mm, PROVIDE SIDE-FACE REINFORCEMENT.
SOFT STRATA
8. FOR CANTILEVER BEAM TOP REINFORCEMENT TO BE ANCHORED BEHIND FOR
H/2
SITE CONDITION
8'-6"[2600 MM] 4] 12" [300 MM]
HEIGHT AS PER
COLUMN AND BEAMS
1] 6" [ 150 MM ] 16'-9"[5100 MM]
6) BASIC REFERENCE CODE IS IS 456-2000 2] 8" [ 200 MM ] 11'-3"[3400 MM] 5] 15" [380 MM] 21'-3"[6500 MM]
PROVIDE LINKS 7) REINFORCEMENT TOR STEEL 550 Fe= N/mm2
BOTTOM BARS T8 @ 150 C/C 3] 9" [ 230 MM ] 13'-3"[4000 MM] 6] 18" [450 MM] 25'-3"[7700 MM]
PROVIDE 4 NOS 8) GRADE OF CONCRETE: ALL COLUMNS SHOULD BE TIED IN BOTH DIRECTIONS BY TIE BEAMS/PLINTH
LINKS T8 @ 70 C/C
COL. i) FOOTINGS= M25 ii) COLUMNS = M25 BEAMS AT GROUND LEVEL/PLINTH LEVEL, EVEN IF HEIGHT OF COLUMNS IS
BELOW TOP OF
WITHIN MAXIMUM ALLOWABLE HEIGHT LIMITS.
FOOTING
FOOTING [TYPICAL]
DEPTH
LD LD iii) BEAMS= M25 iV) SLABS = M25 11. AT ANY LEVEL WHERE COLUMN SIZE GETS REDUCED IN EITHER DIMENSIONS,
FOR ALL FOOTINGS FOOTING
TIE OR PLINTH BEAMS ARE ESSENTIAL.
300 UPTO T16 DIA 9) CONSTANT COLUMN 12. IF FOOTINGS OVERLAP EACH OTHER, NECESSARY REVISION SHOULD BE
BAR & 450 ABOVE OBTAINED FROM OUR OFFICE.
3
T16 DIA BAR 10) MAX. DENSITY OF BRICK MASONARY ASSUMED=2000KG/M
150THK. P.C.C. 13. ANY R.C.C. WORK PRIOR TO CASTING HAS TO BE CHECKED AND CONFIRMED
50
TYPICAL BEAM END-SPAN DETAILS 600 THK SOLING INCLUDING 11) WHEN BOTTOMS OF TWO ADJACENT FOOTINGS ARE
BY OUR OFFICE.
HAND PACKING WITH MAXIMUM 14. COLUMNS ORIENTATION AS PER ARCHITECTURAL CENTER LINE PLAN.
AGGREGATE SIZE OF 150 MM NOT AT SAME LEVEL. THE LEVEL DIFFERENCE SHALL 15. DESIGN IS VALID FOR NUMBER OF FLOORS AS INDICATED IN THE DRAWING.
BE MADE-UP BY P.C.C [M15] . 16. SHUTTERING SHALL NOT BE REMOVED BEFORE THE PERIOD MENTIONED
SOFT STRATA BELOW FOR OPC IF AMBIENT TEMPERATURE DOES NOT FALL BELOW 15°C &
MAXIMUM LEVEL DIFFERENCE IS ALLOWED EQUAL TO
ADEQUATE CURING IS DONE.:
EDGE TO EDGE DISTANCE BETWEEN TWO FOOTINGS.
TYPICAL SECTION THROUGH FOOTING & COLUMN A] PROPS TO SLABS: 1) SPANNING UP TO 3.5M = 7 DAYS
2) SPANNING OVER 3.5M = 14 DAYS
B] PROPS TO BEAMS AND ALL CANTILEVERS = 21 DAYS
R.C.C.BEAM
R.C.C.SLAB
DOOR
3.90m 3.0m
2.10m
BRICK WALL
WALL THICKNESS
0.23m
1.20m WC WC WC WC
1.3mx1.3m 1.3mx1.3m 1.3mx1.3m 1.3mx1.3m 1.20m
2.7m
WALL THICKNESS
0.23m
2.2m
GENTS TOILET LADIES TOILET
A 3.0m A
meter
1.3m
TOILET BLOCK