Da Rfo12 Pow With Dupa 01 18 2024
Da Rfo12 Pow With Dupa 01 18 2024
Project :
DEPARTMENT OF AGRICULTURE REGIONAL FIELD OFFICE XII - Phase 1
Location: TUPI, SOUTH COTABATO
Subject: Scope of Works
1 General Requirement
2 Site Development
2.1 Construction of Service Road , Parking & Pavements
2.2 Curbs and Gutter Wheel Stop
2.3 Perimeter Fence
2.4 Guard House (1 no)
2.5 External/Site water, drainage, sewage, electrical and fire protection works
2.6 Construction of Utility Building
2.7 Construction of Water Tank House
3 Construction of Central Administrative Building
PROGRAM OF WORKS
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE REGIONAL FIELD
Project :
OFFICE XII - Phase 1
Location : TUPI, SOUTH COTABATO
Source of Fund :
Date :
EQUIPMENT
DESCRIPTION REQUIRED DESCRIPTION REQUIRED
Plate Compactor (5 hp) 2 Welding Machine, Electric Driven 2
One Bagger Mixer 2 Cutting Outfit 1
Concrete Vibrator 1 Truck Mounted Crane 1
Bar Cutter 1 Backhoe, 1.2cum 1
Bar Bender 1 Dumptruck, 12cu yd 2
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL DIRECT COST
PART I FACILITIES FOR THE ENGINEER - -
A.1.4 (1) Project Photographs 1.00 l.s 24,000.00 24,000.00
TOTAL OF PART I 24,000.00
PART II OTHER GENERAL REQUIREMENTS - -
B.9 Mobilization/ Demobilization 1.00 l.s. 446,100.00 446,100.00
B.3 Permits, Licenses, Clearances, etc. 1.00 l.s 1,115,552.29 1,115,552.29
B.1 (1) Temporary facilities for Contractor 1.00 l.s. 758,463.73 758,463.73
B.7 (2) Occupational Safety and Health Program 1.00 l.s 969,962.67 969,962.67
B.20 Temporary Enclosure / board-up 1.00 l.s 410,400.00 410,400.00
B.4 (10) Miscellaneous Survey and Staking 1.00 l.s 623,074.33 623,074.33
SPL (1) Material Testing 1.00 l.s 90,000.00 90,000.00
SPL (2) As-built plans and Shop Drawings 1.00 l.s 45,000.00 45,000.00
TOTAL OF PART II - - 4,458,553.02
PART III SITE DEVELOPMENT - -
PART A CIVIL/EARTHWORKS - -
100 (1) Clearing ang grubbing 2,720.00 sq.m 33.00 89,760.41
1601 (1) Back Fill & Compaction 544.00 cu.m 843.96 459,113.43
105 (1) a Sub Grade/Base Preparation 2,720.00 sq.m 240.90 655,248.12
SPL (3) Service Road , Parking construction & Pavements 3,294.00 sq.m 1,684.13 5,547,522.00
807 (10) Curbs and Gutter Wheel Stop 930.00 l.m. 469.26 436,407.98
807 (13) Perimeter Fence( including foundation,chb wall , other miscellaneous 455.00 l.m. 8,486.69 3,861,446.05
807 (14) Steel gate (entrace and Exit) 4.00 no 200,255.56 801,022.25
1706 (1) Hauling and Disposal 1.00 l.s. 300,000.00 300,000.00
SPL (4) Guard House ( including ,civil/structural, architectural and System) 1.00 ea. 346,190.71 346,190.71
1002 (24) Site Facility Water Distribution 1.00 lot 1,126,031.92 1,126,031.92
1001 (9) Site/External Drainage System 1.00 lot 5,697,070.91 5,697,070.91
1001 (8) Site /External Sewer Line 1.00 lot 201,078.31 201,078.31
624 (9) Site Electrical Works
1100 (10) CONDUITS, BOXES & FITTINGS (Conduit Works/Conduit Roughing-I 1.00 lot 1,587,473.86 1,587,473.86
1100(33) Wires and Wiring Devices 1.00 lot 1,206,932.15 1,206,932.15
1102(1) Panel Boards w/ Main Branch Breakers 1.00 lot 125,600.00 125,600.00
1109 (1) GROUNDING SYSTEM 1.00 lot 339,529.17 339,529.17
1202 (1) Site Fire Protection Works 1.00 lot 5,092,095.65 5,092,095.65
TOTAL OF PART A - - 27,872,522.91
PART B UTILITY BUILDINGS - -
1 Civil/earthworks 1.00 lot 176,937.78 176,937.78
2 Structural Works 1.00 lot 3,859,240.07 3,859,240.07
3 Architectural Works 1.00 lot 5,783,957.44 5,783,957.44
4 Sanitary/Plumbing Works 1.00 lot 3,000,553.62 3,000,553.62
5 Electrical Works 1.00 lot 3,855,572.72 3,855,572.72
6 Auxiliary Works 1.00 lot 286,234.95 286,234.95
7 Mechanical Works 1.00 lot 436,121.40 436,121.40
TOTAL OF PART B 17,398,617.97
PART C WATER TANK HOUSE - -
1 Civil/earthworks 1.00 lot 149,613.77 149,613.77
2 Structural Works 1.00 lot 1,499,314.60 1,499,314.60
3 Architectural Works 1.00 lot 1,591,245.21 1,591,245.21
4 Sanitary/Plumbing Works 1.00 lot 2,642,999.40 2,642,999.40
5 Fire Protection Works 1.00 lot 5,635,743.99 5,635,743.99
TOTAL OF PART C 11,518,916.96
TOTAL OF PART III 56,790,057.84
PART IV CENTRAL ADMINISTRATIVE BUILDING
1 Earthworks/CivilWorks 1.00 lot 2,152,866.77 2,152,866.77
2 Structural Works 1.00 lot 15,815,424.34 15,815,424.34
3 Architectural Works 1.00 lot 23,385,103.81 23,385,103.81
4 Electrical Works 1.00 lot 7,537,865.87 7,537,865.87
5 Auxiliary Works 1.00 lot 5,431,111.35 5,431,111.35
6 Sanitary/Plumbing Works 1.00 lot 512,047.73 512,047.73
7 Fire Protection Works 1.00 lot 1,784,556.49 1,784,556.49
8 Mechanical Works 1.00 lot 12,246,108.39 12,246,108.39
TOTAL OF PART IV 68,865,084.75
Total 130,137,695.60
BREAKDOWN OF EXPENDITURES
PART C.3- ARCHITECTURAL WORKS 1,268,162.53 270,182.81 52,899.87 1,591,245.21 254,599.23 92,292.22 1,938,136.67
PART C.4 PLUMBING WORKS
1201 (1) 1 Pumps Potable and Non - Potable including valves and accessories 1.00 lot 2,168,296.580 2,168,296.58 452,097.92 452,097.92 22,604.90 22,604.90 2,642,999.40 2,642,999.40 16% 422,879.90 153,293.97 3,219,173.27
PART C.4- PLUMBING AND SANITARY WORKS 2,168,296.58 452,097.92 22,604.90 2,642,999.40 422,879.90 153,293.97 3,219,173.27
PART C.5 FIRE PROTECTION WORKS
1202 (2) 1 Fire and Jockey Pump including valves and accessories 1.00 lot 5,367,375.200 5,367,375.20 255,589.32 255,589.32 12,779.47 12,779.47 5,635,743.99 5,635,743.99 16% 901,719.04 326,873.15 6,864,336.18
PART C.5- FIRE PROTECTION WORKS 5,367,375.20 255,589.32 12,779.47 5,635,743.99 901,719.04 326,873.15 6,864,336.18
PART III-C- WATERTANK 9,955,223.71 1,271,136.03 292,557.22 11,518,916.96 1,843,026.71 668,097.18 14,030,040.86
PART III - SITE DEVELOPMENT 46,389,198.37 7,774,148.69 2,626,710.78 56,790,057.84 9,086,409.25 3,293,823.35 69,170,290.45
11250 x 8400mm (see drawing) window, 12mm thick Tempered clear glass
1008 (1)d W-9 on aluminum framed fixed panel and 6mm thick on aluminum framed 1.00 set 717,362.800 717,362.80 - - 717,362.80 717,362.80 16% 114,778.05 41,607.04 873,747.89
operable window
7700 x 3100mm x 12mm thick Tempered clear glass on aluminum framed
1008 (1)d W-10 1.00 set 350,000.000 350,000.00 - - 350,000.00 350,000.00 16% 56,000.00 20,300.00 426,300.00
fixed/operable panel window
5.400 x 3650mm x 12mm thick Tempered clear glass on aluminum framed
1008 (1)d W-11 1.00 set 230,000.000 230,000.00 - - 230,000.00 230,000.00 16% 36,800.00 13,340.00 280,140.00
fixed/operable panel window
8.0 Roofing Works - - -
Long span pre-painted roof (Hi-rib 50) including bended materials,
1014 (1) b2 a. 924.00 sq.m. 2,943.001 2,719,332.58 477.12 440,862.42 149.88 138,486.24 3,570.00 3,298,681.24 16% 527,789.00 191,323.51 4,017,793.75
insulation, fastening accessories, etc.
9.0 Carpentry Works - - -
1003 (4) a. Built-in counters/cabinets (pantry, toilets, etc.) 1.00 lot 196,625.000 196,625.00 - - 196,625.00 196,625.00 16% 31,460.00 11,404.25 239,489.25
1003 (17) b Reception (counter, logo, vertical wood slats, curved blades, etc.) 1.00 lot 472,754.700 472,754.70 143,259.00 143,259.00 14,325.90 14,325.90 630,339.60 630,339.60 16% 100,854.34 36,559.70 767,753.63
10.0 Miscellaneous Items/ Other works - - - -
1039 (1) a. 50 x 75mm Aluminum tubular vertical sun baffles, painted 257.00 lm 935.000 240,295.00 212.50 54,612.50 21.25 5,461.25 1,168.75 300,368.75 16% 48,059.00 17,421.39 365,849.14
401 (1) b. 50mmø Stainless steel hand rail 10.00 lm 7,199.850 71,998.50 1,732.50 17,325.00 692.65 6,926.50 9,625.00 96,250.00 16% 15,400.00 5,582.50 117,232.50
1003 (23) c. Toilet partitions/cubicles with door panel & accessories 4.00 unit 47,520.000 190,080.00 - - 47,520.00 190,080.00 16% 30,412.80 11,024.64 231,517.44
1003 (23) d. Urinal partitions 4.00 unit 7,788.000 31,152.00 - - 7,788.00 31,152.00 16% 4,984.32 1,806.82 37,943.14
PART IV-C- ARCHITECTURAL WORKS 18,619,838.63 3,981,933.26 783,331.93 23,385,103.81 3,741,616.61 1,356,336.02 28,483,056.44
GENERAL REQUIREMENTS -
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
GENERAL REQUIREMENTS -
Sub - Total for A 103,865.45
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
1. Dump Truck, 12cu yrd 2 66.00 1,544.00 203,808.00
2. Payloader, 1.2 cum 1 66.00 1,940.00 128,040.00
Minor Tools (10% of Labor Cost) 10,386.55
F. Materials
-
-
-
-
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
-
-
Minor Tools (10% of Labor Cost) -
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF
AGRICULTURE REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
GENERAL REQUIREMENTS -
F. Materials 158,000,000.00
a. Building Permits lot 1 108,038.00 108,038.00
b. Occupancy lot 1 158,000.00 158,000.00
c. Contractor's Tax lot 1 849,514.29 849,514.29
-
-
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Mobile Crane/Telescopic Boom, 50T 1 8.00 2,535.00 20,280.00
Minor Tools (10% of Labor Cost) 2,198.52
GENERAL REQUIREMENTS -
D. Output = 1 LOT
E. Direct Unit Cost (C ÷ D) 44,463.73
F. Materials
A. Labor
a. Safety Practitioner 0 1248.00 152.44 -
b. SafetyOfficer 1 1248.00 121.84 152,056.32
c. Health Personnel (Full Time) 1 1248.00 121.84 152,056.32
d. Labor (cleaning) 0 1248.00 61.43 -
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
1. Safety Shoes no 20 850.00 17,000.00
2. Safety Hard hat no 20 400.00 8,000.00
3. Body Harness no 10.00 450.00 4,500.00
4. Rain boots no 20 400.00 8,000.00
5. Safety Vest no 20 100.00 2,000.00
6. Safety gloves no 15.00 76.18 1,142.77
7. Temperature Gun no 1.00 1,000.00 1,000.00
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF
AGRICULTURE REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
GENERAL REQUIREMENTS -
8. Safety Ladder no 5.00 4,500.00 22,500.00
9. Cleaning materials mos. 10.00 1,500.00 15,000.00
10. Caution Tape rolls 2.00 1,500.00 3,000.00
A. Labor
a. Security Guard 2 1289.32 121.84 314,181.82
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
GENERAL REQUIREMENTS -
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 8% of G 27,648.00
I. Contractor's Profit (CP) 0% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) 18,662.40
K. Total Unit Cost (G + H + I + J) 391,910.40
A. Labor
a. Construction Foreman 1 59.45 121.84 7,242.95
b. Skilled Laborer 0 0.00 91.47 -
c. Unskilled Laborer 2 60.00 61.43 7,371.60
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
GENERAL REQUIREMENTS -
Item No./Description : B.20 Temporary Enclosure / board-up
Unit of Measurement : LOT
Output : 1
Quantity : 1.00 LOT
A. Labor
a. Construction Foreman 1 18.54 121.84 2,258.94
b. Skilled Laborer 2 21.00 91.47 3,841.74
c. Unskilled Laborer 6 21.00 61.43 7,740.18
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials M 480
GENERAL REQUIREMENTS -
Item No./Description : B.4 (10) Miscellaneous Survey and Staking
Unit of Measurement : LOT
Output : 1
Quantity : 1.00 LOT
A. Labor
a. Geodetic Engineer 1 768.00 144.23 110,768.64
b. Skilled Laborer 1 768.00 91.47 70,248.96
c. Unskilled Laborer 4 768.00 61.43 188,712.96
F. Materials
A. Labor
a. Construction Foreman 121.84 -
b. Skilled Laborer 91.47 -
c. Unskilled Laborer 61.43 -
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF
AGRICULTURE REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
GENERAL REQUIREMENTS -
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
1. Materials samples
CHB, 4" interior pcs 20.00 30.00 600.00
CHB, 6" Exterior pcs 20.00 32.00 640.00
Reinforcing Steel Bar, Grade 60 kg 181.00 45.00 8,145.00
Concrete Trial Mix cum 2.00 5,100.00 10,200.00
2. Testing fee -
Masonry testing set 3.00 1,540.00 4,620.00
Reinforcng steel bar set 10.00 1,070.00 10,700.00
Concrete Trial Mix set 3.00 1,330.00 3,990.00
Misc. MEPF Material Testing lot 1.00 51,105.00 51,105.00
-
A. Labor
a. Cad Operator 1 335.76 121.84 40,909.09
b. Skilled Laborer 91.47 -
c. Unskilled Laborer 61.43 -
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF
AGRICULTURE REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
GENERAL REQUIREMENTS -
Minor Tools (10% of Labor Cost) 4,090.91
F. Materials
SITE DEVELOPMENT -
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
1. Dump Truck, 12cu yrd 2 13.00 1,544.00 40,144.00
2. Backhoe, 1.2 cum 1 13.00 2,132.00 27,716.00
F. Materials
Consumables lot 5% -
-
-
SITE DEVELOPMENT -
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)
A. Labor
B. Equipment
1. Plate Compactor, 6HP 1 28.00 2,847.00 79,716.00
2. Walk behind roller, 8 HP 1 28.00 3,203.00 89,684.00
Minor Tools (10% of Labor Cost) 1,857.58
F. Materials
Backfill Materials cum 544 495.00 269,280.00
-
-
-
-
A. Labor
SITE DEVELOPMENT -
c. Unskilled Laborer 5 67.12 61.43 20,616.79
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
-
Motorized Grader, 125.0 hp 1 67.12 2,670.00 179,218.05
Minor Tools (10% of Labor Cost) 4,107.45
Item No./Description : SPL (3) Service Road , Parking construction & Pavements
Unit of Measurement : sqm
Output : 1
Quantity : 3294.00 sqm
A. Labor
SITE DEVELOPMENT -
Name and Capacity No of Unit/s Hourly Rate Amount (PhP)
B. Equipment
a. Concrete Bagger Mixer, 3 to 4cum 1 128.00 229.00 29,312.00
b. Plate Compactor, 4.5HP 1 128.00 1,779.00 227,712.00
c. Concrete paver/screeder, 6m 1 128.00 280.00 35,840.00
d. Concrete vibrator 1 128.00 36.35 4,652.31
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
SITE DEVELOPMENT -
B. Equipment
a. Concrete Bagger Mixer, 3 to 4cum 1 132.00 229.00 30,228.00
b. Formworks (sqm) 96 132.00 40.00 5,280.00
-
F. Materials lm 930.00
a. Cement bag 201.00 240.00 48,240.00
b. Sand cum 8.40 800.00 6,720.00
c. Gravel cum 14.00 1,030.00 14,420.00
d. Rebar kg 2,530.94 52.80 133,633.46
e. GI Tie Wire #16 kg 38.00 68.18 2,590.91
f. Concrete hardener liter 210.00 215.00 45,150.00
g. Consumables 3,413.74
-
-
-
-
A. Labor
CHB Footing, column and beam
a. Construction Foreman 1 51.00 121.84 6,213.84
b. Skilled Laborer 6 51.00 91.47 27,989.82
c. Unskilled Laborer 6 51.00 61.43 18,797.58
CHB Installation
a. Construction Foreman 1 107.00 121.84 13,036.88
b. Skilled Laborer 6 107.00 91.47 58,723.74
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
SITE DEVELOPMENT -
c. Unskilled Laborer 6 107.00 61.43 39,438.06
CHB Plastering
a. Construction Foreman 1 213.00 121.84 25,951.92
b. Skilled Laborer 6 213.00 91.47 116,898.66
c. Unskilled Laborer 6 213.00 61.43 78,507.54
Painting Works
a. Construction Foreman 1 128.00 121.84 15,595.52
b. Skilled Laborer 6 128.00 91.47 70,248.96
c. Unskilled Laborer 6 128.00 61.43 47,178.24
GI Pipe with Wire Mesh Screen Fence x 1.2m High
a. Construction Foreman 1 76.00 121.84 9,259.84
b. Skilled Laborer 2 76.00 91.47 13,903.44
c. Unskilled Laborer 2 76.00 61.43 9,337.36
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Concrete Bagger Mixer, 3 to 4cum 1 264.00 229.00 60,456.00
b. Scaffolding/shoring 1 51.00 100.00 5,100.00
c. Welding Machine, 300 amp 1 76.00 371.00 28,196.00
Minor Tools (10% of Labor Cost) 55,108.14
F. Materials m 455.00
1. CHB Wall (1.4m high)
a. CHB, 6" pc 7,962.50 32.00 254,800.00
b. Reinforcing Bar, 12mmØ kg 3,030.30 52.80 159,999.84
c. Cement bag 668.85 240.00 160,524.00
d. Sand cum 38.22 800.00 30,576.00
2. CHB Plastering
a. Cement bag 364.00 240.00 87,360.00
b. Sand cum 36.40 800.00 29,120.00
3. RC Column (300x200mm)
a. Cement bag 185.00 240.00 44,400.00
b. Sand cum 7.00 800.00 5,600.00
c. Gravel cum 14.00 1,030.00 14,420.00
d. Reinforcing Bar, 12mmØ kg 2,159.62 52.80 114,027.72
e. Reinforcing Bar, 10mmØ kg 1,406.08 51.00 71,709.88
f. GI tie wires kg 71.31 68.18 4,862.31
g. Phenolic Board, 3/4 (3-uses) pc 76.00 1,350.00 102,600.00
4. RC Beam (200mmmx300mm)
a. Cement bag 369.00 240.00 88,560.00
b. Sand cum 14.00 800.00 11,200.00
c. Gravel cum 28.00 1,030.00 28,840.00
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
SITE DEVELOPMENT -
d. Reinforcing Bar, 12mmØ kg 888.89 52.80 46,933.29
e. Reinforcing Bar, 10mmØ kg 1,346.87 51.00 68,690.51
f. GI tie wires kg 44.72 68.18 3,048.76
g. Phenolic Board, 3/4 (3-uses) pc 61.00 1,350.00 82,350.00
5. CHB Footing, 600mm x 250mm thick
a. Cement bag 922.00 240.00 221,280.00
b. Sand cum 35.00 800.00 28,000.00
c. Gravel cum 70.00 1,030.00 72,100.00
d. Reinforcing Bar, 12mmØ kg 1,333.33 52.80 70,399.93
e. Reinforcing Bar, 10mmØ kg 2,244.79 51.00 114,484.19
f. GI tie wires kg 71.56 68.18 4,879.25
6. Painting Works -
a. Primer can 63.70 1,077.00 68,604.90
b. Skimcoat bag 318.50 530.00 168,805.00
c. Elastomeric Paint can 127.40 760.00 96,824.00
7. GI Pipe with Wire Mesh Screen Fence x 1.2m High
a. GI Pipe, 40mmØ, Sch. 20 pcs 228.00 600.00 136,800.00
b. Flat Bar, 25mm x 3mm x 6m pcs 456.00 350.00 159,600.00
c. Wire Mesh 2"x2"x 2.6mm thick roll 237.00 350.00 82,950.00
d. Alkyd Metal Primer can 162.67 1,200.00 195,205.15
e. Alkyd Paint can 40.49 1,100.00 44,540.27
8. Consumables 10% 287,409.50
-
-
Sub - Total for F 3,161,504.51
G. Direct Unit Cost (E + F) 3,861,446.05
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 8% of G 308,915.68
I. Contractor's Profit (CP) 8% of G 308,915.68
J. Value Added Tax (VAT) 5% of (G + H + I) 223,963.87
K. Total Unit Cost (G + H + I + J) 4,703,241.29
A. Labor
a. Construction Foreman 1 192.00 121.84 23,393.28
b. Skilled Laborer 2 192.00 91.47 35,124.48
c. Unskilled Laborer 2 192.00 61.43 23,589.12
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Welding Machine, 300 amp 1 192.00 371.00 71,232.00
Minor Tools (10% of Labor Cost) 8,210.69
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
SITE DEVELOPMENT -
Sub - Total for B 79,442.69
C. Total (A + B) 161,549.57
D. Output = 1 no
E. Direct Unit Cost (C ÷ D) 161,549.57
A. Labor
a. Construction Foreman 1 42.18 121.84 5,138.64
b. Skilled Laborer 3 40.00 91.47 10,976.40
c. Unskilled Laborer 7 41.00 61.43 17,630.41
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
1. Dump Truck, 12cu yrd 3 40.00 1,544.00 185,280.00
2. Payloader, 1.2 cum 1 40.00 1,940.00 77,600.00
F. Materials
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
SITE DEVELOPMENT -
A. Labor
a. Construction Foreman 1 160.00 121.84 19,494.40
b. Skilled Laborer 3 160.00 91.47 43,905.60
c. Unskilled Laborer 6 160.00 61.43 58,972.80
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Concrete Bagger Mixer, 3 to 4cum 1 64.00 229.00 14,656.00
b. Scaffolding/shoring 1 64.00 100.00 6,400.00
c. Rebar Bender 1 64.00 129.81 8,307.69
d. Rebar Cutter 1 64.00 64.90 4,153.85
e. Concrete vibrator, 450 lpm 1 64.00 36.35 2,326.15
-
Minor Tools (10% of Labor Cost) 12,237.28
F. Materials
1. RC Roof Slab
a. Ready Mix Concrete, 4,000 psi cum 0.89 5,076.50 4,523.16
b. Reinforcing Bar kg 296.70 52.80 15,665.92
c, GI Tie wires kg 5.93 68.18 404.60
d. Formworks sqm 5.94 -
Phenolic Board pcs 3.00 1,350.00 4,050.00
Good Lumber bdft 81.00 55.00 4,455.00
2. RC Wall x 2.8m high -
a. Ready Mix Concrete, 4,000 psi cum 2.40 5,076.50 12,183.60
b. Reinforcing Bar kg 186.48 52.80 9,846.14
c, GI Tie wires kg 3.73 68.18 254.29
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
SITE DEVELOPMENT -
d. Formworks sqm 28.00 -
Phenolic Board pcs 10.00 1,350.00 13,500.00
Good Lumber bdft 270.00 55.00 14,850.00
3. RC Wall Footing -
a. Ready Mix Concrete, 4,000 psi cum 0.45 5,076.50 2,284.42
b. Reinforcing Bar kg 45.98 52.80 2,427.74
c, GI Tie wires kg 0.92 68.18 62.70
4. 6mm thick clear glass on aluminum powder coated sliding
set 1.00 49,680.00 49,680.00
door
5. Interior Painting (Wall and Ceiling) sqm 15.50 -
a. Primer can 0.78 1,077.00 834.68
b. Skimcoat bag 7.75 530.00 4,107.50
c. Latex Paint can 2.33 950.00 2,208.75
d. Paint thinner can 0.58 676.00 392.93
6. Exterior Painting (Wall and ceiling) sqm 21.00 -
a. Primer can 1.05 1,077.00 1,130.85
b. Skimcoat bag 10.50 530.00 5,565.00
c. Elastomeric Paint can 3.15 760.00 2,394.00
d. Paint thinner can 0.79 676.00 532.35
7. Cementitious Waterproofing for roof deck sqm 6.00 550.00 3,300.00
8. 12 Watts, Surface mounted LED downlight pcs 3.00 1,061.50 3,184.50
9. 1 Gang Single pole single throw switch, 15A, 230, 60 Hz pcs 1.00 118.69 118.69
10. 2 Gang Single pole single throw switch, 15A, 230, 60 Hz pcs 1.00 188.43 188.43
11. PVC pipe 20mmØ pcs 2.00 71.50 143.00
12. 20mmØ lock-nut, adaptors and bushing pcs 3.00 48.40 145.20
13. Utility box pcs 3.00 48.40 145.20
14. 3.5mm2 THHN Wires m 18.00 41.75 751.50
15. Concrete floor finish with floor hardener sqm 2.00 -
a, Cement bag 0.06 260.00 15.60
b, Sand cum 0.01 850.00 5.10
c. Concrete hardener bag 0.40 1,025.00 410.00
-
-
-
-
Item No./Description : 1100 (10) CONDUITS, BOXES & FITTINGS (Conduit Works/Conduit Roughing-In)
Unit of Measurement : l.s.
Output per hour : 1.00
Quantity : 1.00 l.s.
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Wiring Device P -
Weather Proof Outlet set 24 P 1,000.12 P 24,002.88
Lighting Fixtures P -
Street Lamp Post set 20 P 31,295.00 P 625,900.00
Parking Lamp Post set 9 P 18,529.50 P 166,765.50
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
PANEL BOARDS
PP - SDP assy 1 P 104,500.00 P 104,500.00
Note:
*Delivery cost are included in the unit cost.
PVC Pipe
32mm Ø x 3m PVC Pipe pcs 42 P 199.10 P 8,362.20
Bare Copper Wire and Grounding Rod and Accessories
50mm2, soft drawn bare copper wires m 126 P 715.22 P 90,117.72
Ground rod, 20mm dia., 3m length, copper clad stee pcs 34 P 2,216.50 P 75,361.00
Ground Plate pcs 2 P 5,280.00 P 10,560.00
Exothermic welding m-hr 25 P 2,640.00 P 66,000.00
Consumables ( Tape , Gi Wire , Paint ) lot 1 P 33,418.11 P 33,418.11
Testing and Commissioning m-hr 25 P - P -
UTILITY BUILDINGS -
Consumables lot 5% -
-
-
UTILITY BUILDINGS -
UTILITY BUILDINGS -
Prepared by: Evaluated by:
Item No./Description: 1034 (1) b Vapor Barrier (6mils polyethylene plastic cover)
Unit of Measurement: sqm
Output: 1
Quantity: 326.00 sqm
UTILITY BUILDINGS -
-
Minor Tools (10% of Labor Cost) 978.00
A. Labor
a. Construction Foreman 1 0.25 121.84 30.46
b. Skilled Laborer 1 0.25 91.47 22.87
c. Unskilled Laborer 2 0.25 61.43 30.72
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
1. Dump Truck, 15cu yrd 1 1.43 1,716.00 2,447.55
2. Payloader, 1.2 cum 1 0.25 1,940.00 485.00
F. Materials
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
UTILITY BUILDINGS -
A. Labor
a. Construction Foreman 1 18.77 121.84 2,287.29
b. Skilled Laborer 4 17.00 91.47 6,219.96
c. Unskilled Laborer 12 17.00 61.43 12,531.72
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
1. Concrete Vibrator, 850 lpm 1 14.00 40.38 565.38
2. Concrete Pump/Pumpcrete 1 14.00 2,076.00 29,064.00
3. Concrete screeder 1 14.00 1,039.13 14,547.75
Minor Tools (10% of Labor Cost) 2,103.90
F. Materials
Ready Mixed Concrete 4000psi at 28 days cum 89.62 4,504.76 403,716.76
Consumables 5% 20,185.84
UTILITY BUILDINGS -
A. Labor
a. Construction Foreman 1 14.15 121.84 1,724.04
b. Skilled Laborer 4 14.00 91.47 5,122.32
c. Unskilled Laborer 12 14.00 61.43 10,320.24
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
1. Concrete Vibrator, 850 lpm 1 11.45 40.38 462.40
2. Concrete Pump/Pumpcrete 1 11.45 2,076.00 23,770.20
3. Concrete screeder 1 11.45 1,039.13 11,897.98
Minor Tools (10% of Labor Cost) 1,716.66
F. Materials
Ready Mixed Concrete 4000psi at 28 days cum 73.14 4,955.24 362,426.11
Consumables 5% 18,121.31
A. Labor
a. Construction Foreman 1 24.00 121.84 2,924.16
b. Skilled Laborer 3 24.00 91.47 6,585.84
c. Unskilled Laborer 12 24.00 61.43 17,691.84
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
1. Rebar Bender 1 22.00 243.39 5,354.57
2. Rebar Cutter 1 22.00 202.82 4,462.09
Minor Tools (10% of Labor Cost) 2,720.18
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
UTILITY BUILDINGS -
F. Materials
Reinforcing Steel Bar, Grade 60 kg 4005.70 46.36 185,718.82
Wastage 18,571.88
A. Labor
a. Construction Foreman 1 110.40 121.84 13,451.14
b. Skilled Laborer 3 108.00 91.47 29,636.28
c. Unskilled Laborer 12 108.00 61.43 79,613.28
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
1. Rebar Bender 1 108.00 243.39 26,286.06
2. Rebar Cutter 1 108.00 202.82 21,904.79
Minor Tools (10% of Labor Cost) 12,270.07
F. Materials
Reinforcing Steel Bar, Grade 60 kg 18500.47 48.00 888,022.56
Wastage 88,802.26
UTILITY BUILDINGS -
A. Labor
a. Construction Foreman 1 121.84 -
b. Skilled Laborer 3 91.47 -
c. Unskilled Laborer 12 61.43 -
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
1. Rebar Bender 1 243.39 -
2. Rebar Cutter 1 202.82 -
Minor Tools (10% of Labor Cost) -
F. Materials
G.I. Wire/Tie Wire kg 20.68 2,238.50 46,292.18
A. Labor
Installation
a. Construction Foreman 1 64.00 121.84 7,797.76
b. Skilled Laborer 4 64.00 91.47 23,416.32
c. Unskilled Laborer 16 64.00 61.43 62,904.32
Stripping
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
UTILITY BUILDINGS -
a. Construction Foreman 1 46.51 121.84 5,667.08
b. Skilled Laborer 2 46.51 91.47 8,509.00
c. Unskilled Laborer 12 46.51 61.43 34,287.15
Name and Capacity No of Unit/s No. of Days/s Daily Rate Amount (PhP)
B. Equipment 600sqm
H Frame assembly, 1.7 x 1.2m 234 6.00 6.66 9,356.26
U Head 468 6.00 1.62 4,560.19
Base Jack 468 6.00 1.57 4,402.94
Diagonal brace 1232 6.00 2.24 16,558.08
Horizontal brace 1232 6.00 2.30 16,972.03
Primary beam support, 122 aluminum beam 520 6.00 2.46 7,687.68
Secondary beam support, 122 aluminum beam 540 6.00 2.46 7,983.36
GI Pipe 40Ø x 6m 80 6.00 7.06 3,386.88
Props 308 6.00 7.06 13,039.49
Wing nut 4928 1.00 44.80 220,774.40
Joint Pin 936 6.00 0.17 943.49
Clamp 468 1.00 28.00 13,104.00
Ladder 60 6.00 5.21 1,874.88
Catwalk 117 6.00 3.14 2,201.47
Turn buckles props 468 6.00 4.98 13,995.07
Minor Tools (10% of Labor Cost) 14,258.16
A. Labor
Installation
a. Construction Foreman 1 46.00 121.84 5,604.64
b. Skilled Laborer 2 46.00 91.47 8,415.24
c. Unskilled Laborer 4 46.00 61.43 11,303.12
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Welding Machine, 500Amp, Electric 1 46.00 391.00 17,986.00
Scaffolding 1 46.00 50.00 2,300.00
UTILITY BUILDINGS -
Sub - Total for B 22,818.30
C. Total (A + B) 48,141.30
D. Output 1 kg 3,650.74
E. Direct Unit Cost (C ÷ D) 13.19
F. Materials kg
Steel Roof Framing (Trusses) kg 3650.74 54.48 198,878.14
A. Labor
Installation
a. Construction Foreman 1 37.00 121.84 4,508.08
b. Skilled Laborer 2 37.00 91.47 6,768.78
c. Unskilled Laborer 4 37.00 61.43 9,091.64
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Welding Machine, 500Amp, Electric 1 37.00 391.00 14,467.00
Scaffolding 1 37.00 50.00 1,850.00
F. Materials
UTILITY BUILDINGS -
A. Labor
Installation
a. Construction Foreman 1 31.00 121.84 3,777.04
b. Skilled Laborer 1 31.00 91.47 2,835.57
c. Unskilled Laborer 2 31.00 61.43 3,808.66
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Installation
a. Construction Foreman 1 35.00 121.84 4,264.40
b. Skilled Laborer 1 35.00 91.47 3,201.45
c. Unskilled Laborer 2 35.00 61.43 4,300.10
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Welding Machine, 500Amp, Electric 1 35.00 391.00 13,685.00
Scaffolding 1 35.00 50.00 1,750.00
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
UTILITY BUILDINGS -
Minor Tools (10% of Labor Cost) 1,176.60
F. Materials
New CHB Wall-150mm (6") CHB Walls Including plastering, stiffener column and lintel
Item No./Description: 1046 (1) a2
beams
Unit of Measurement: sqm
Output: 4
Quantity: 706.50 sqm
A. Labor
CHB Installation
a. Construction Foreman 1 144.00 121.84 17,544.96
b. Skilled Laborer 4 144.00 91.47 52,686.72
c. Unskilled Laborer 6 144.00 61.43 53,075.52
Plastering Works
a. Construction Foreman 1 360.00 121.84 43,862.40
b. Skilled Laborer 4 360.00 91.47 131,716.80
c. Unskilled Laborer 4 360.00 61.43 88,459.20
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
1 Bagger Concrete Mixer 1 144.00 172.00 24,768.00
Scaffolding/Formworks 1 360.00 50.00 18,000.00
Minor Tools (10% of Labor Cost) 38,734.56
UTILITY BUILDINGS -
b. Sand cum 4.00 800.00 3,200.00
c. Gravel cum 6.00 1,030.00 6,180.00
d. Reinforcing Bar, 16mmØ kg 767.07 52.80 40,501.53
e. Reinforcing Bar, 10mmØ kg 749.29 51.00 38,213.82
f. GI tie wires kg 30.33 68.18 2,067.77
g. Phenolic Board, 3/4 (3-uses) pc 13.00 1,350.00 17,550.00
4. Siffener Beam (150mmmx400mm)
a. Cement bag 110.00 240.00 26,400.00
b. Sand cum 4.00 800.00 3,200.00
c. Gravel cum 8.00 1,030.00 8,240.00
d. Reinforcing Bar, 12mmØ kg 263.74 52.80 13,925.26
e. Reinforcing Bar, 10mmØ kg 299.72 51.00 15,285.53
f. GI tie wires kg 11.27 68.18 768.34
g. Phenolic Board, 3/4 (3-uses) pc 15.00 1,350.00 20,250.00
Consumables 4.14% 42,046.41
Item No./Description: 1032 (1) a Latex semi-gloss paint finish on plastered wall
Unit of Measurement: sqm
Output: 1
Quantity: 551.60 sqm
A. Labor
a. Construction Foreman 1 170.06 121.84 20,720.11
b. Skilled Laborer 3 170.00 91.47 46,649.70
c. Unskilled Laborer 2 170.00 61.43 20,886.20
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
UTILITY BUILDINGS -
K. Total Unit Cost (G + H + I + J) 428.74
A. Labor
a. Construction Foreman 1 211.59 121.84 25,780.61
b. Skilled Laborer 6 211.59 91.47 116,127.02
c. Unskilled Laborer 4 211.59 61.43 51,992.88
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Scaffolding 1 211.59 100.00 21,159.40
Item No./Description: 1021 (1) FF-5, Straight to finish concrete with hardener
Unit of Measurement: sqm
Output: 1
Quantity: 326.00 sqm
A. Labor
a. Construction Foreman 1 30.33 121.84 3,695.97
b. Skilled Laborer 2 30.33 91.47 5,549.41
c. Unskilled Laborer 4 30.33 61.43 7,453.82
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
UTILITY BUILDINGS -
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Concrete Trowel 2 30.33 113.95 6,912.21
A. Labor
a. Construction Foreman 1 32.32 121.84 3,938.26
b. Skilled Laborer 3 32.32 91.47 8,869.82
c. Unskilled Laborer 6 32.32 61.43 11,913.70
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Scaffolding 1 32.32 50.00 1,616.16
UTILITY BUILDINGS -
Consumables 10.00% 3,526.00
Item No./Description: 1016 (1)a WP-3; Integral with Epoxy Tank Lining
Unit of Measurement: sqm
Output: 1
Quantity: 1.00 sqm
UTILITY BUILDINGS -
Unit of Measurement: ea
Output: 1
Quantity: 1.00 ea
UTILITY BUILDINGS -
7. Alkyd Paint can 2.12 1,100.00 2,332.00
-
Consumables 5.00% 5,048.08
Unit of Measurement: ea
Output: 1
Quantity: 1.00 ea
Item No./Description: 1011 (1)a Metallic Rolled up Door RD-1 (2.4 x 2.5m)
Unit of Measurement: ea
Output: 1
Quantity: 1.00 ea
UTILITY BUILDINGS -
b. Skilled Laborer 2 12.00 91.47 2,195.28
c. Unskilled Laborer 2 12.00 61.43 1,474.32
Item No./Description: 1005 (7) a Steel Louver Window W-13 (3.5m x 0.6m)
Unit of Measurement: ea
Output: 1
Quantity: 1.00 ea
UTILITY BUILDINGS -
K. Total Unit Cost (G + H + I + J) 25,322.22
Item No./Description: 1005 (7) b Steel Louver Window W-14 (6.3m x 0.6m)
Unit of Measurement: ea
Output: 1
Quantity: 1.00 ea
Item No./Description: 1010 (1) Laminated Wooden Door WD-01 (2.1m x 0.90m) with hardware
Unit of Measurement: ea
Output: 1
Quantity: 1.00 ea
UTILITY BUILDINGS -
C. Total (A + B) 2,417.71
D. Output 1 ea 1.00
E. Direct Unit Cost (C ÷ D) 2,417.71
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials ea 1.00
1.Laminated Wooden Door WD-01 (2.1m x 0.90m) with ea 1.00 9,382.29 9,382.29
2.Door Jamb ea 1.00 8,000.00 8,000.00
3. Consumables
Item No./Description : 1100 (10) CONDUITS, BOXES & FITTINGS (Conduit Works/ Conduit Roughing-In)
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Wiring Device
Simplex Convenience Outlet set 6 P 198.00 P 1,188.00
One gang Switch set 11 P 118.69 P 1,305.59
Two gang Switch set 16 P 188.43 P 3,014.88
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF
AGRICULTURE REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
-
UTILITY BUILDINGS
18 Watts , 2 Pcs , Dust Proof Luminaire LED Light set 29 P 2,656.50 P 77,038.50
Emergency Light set 9 P 2,750.00 P 24,750.00
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
PANEL BOARDS
PP - STP assy 1 P 104,500.00 P 104,500.00
Main : 150AT/250AF,3P, 400V, 18KAIC
In NEMA 1 Surface mounted
PPH assy 1 P 114,950.00 P 114,950.00
Main : 60AT/100AF,3P, 230V, 14KAIC
In NEMA 1 Surface mounted
ENCLOSED CIRCUIT BREAKER
NEMA 3R
20A,2P,ECB,230V assy 6 P 3,740.00 P 22,440.00
30A,3P,ECB,230V assy 12 P 4,620.00 P 55,440.00
Note:
*Delivery cost are included in the unit cost.
PVC Pipe
32mm Ø x 3m PVC Pipe pcs 12 P 199.10 P 2,389.20
Bare Copper Wire and Grounding Rod and Accessories
50mm2, soft drawn bare copper wires m 12 P 585.20 P 7,022.40
Ground rod, 20mm dia., 3m length, copper clad stee pcs 12 P 5,280.00 P 63,360.00
Ground Plate pcs 12 P 5,280.00 P 63,360.00
Exothermic welding m-hr 12 P 2,640.00 P 31,680.00
Inspection Pit set 12 P 6,380.00 P 76,560.00
Restoration works m-hr 12 P - P -
PA-BGM
Testing and Commissioning M-Hr 25 P - P -
ROUGHING INSTALTION
EMT Pipe w/ coupling
15mm Ø L 30 P 235.40 P 7,062.00
EMT Elbow
15mm Ø pcs 14 P 37.40 P 523.60
EMT Lock Nut and Bushing
15mm Ø pcs 20 P 17.27 P 345.40
Boxes , Pull Box and Flexible Conduit and Connectors
2x4 utility box #16 pcs 4 P 48.40 P 193.60
4x4 junction box w/ cover #16 pcs 6 P 49.50 P 297.00
4x4 square box with cover #16 pcs 4 P 63.80 P 255.20
15mm diameter Flexible Metalic Conduit m 7 P 89.10 P 623.70
15mm diameter Flexible connector pcs 14 P 23.10 P 323.40
Pull Box pcs 2 P 4,950.00 P 9,900.00
PA-BGM Wire
#16 AWG TF Shielded Pair m 90 P 44.00 P 3,960.00
Prepared by:
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF
AGRICULTURE REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
-
WATER TANK HOUSE
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
Person/s
A. Labor
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
Person/s
A. Labor
a. Construction Foreman 1 3.54 121.84 431.58
b. Skilled Laborer 4 3.53 91.47 1,291.56
c. Unskilled Laborer 12 3.53 61.43 2,602.17
F. Materials
Ready Mixed Concrete 3000psi at 28 days cum 18.54 4,504.76 83,518.29
Consumables 5% 4,175.91
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
Person/s
A. Labor
a. Construction Foreman 1 50.00 121.84 6,092.00
b. Skilled Laborer 3 50.00 91.47 13,720.50
c. Unskilled Laborer 7 50.00 61.43 21,500.50
Item No./Descript : SPL (5) Site Preparation, Layout & Stake Out
Unit of Measurem : SQM
Output :
Quantity : 1145.00 SQM
Consumables lot 5% -
-
-
A. Labor
a. Construction Foreman 1 15.57 121.84 1,896.96
b. Skilled Laborer 4 15.54 91.47 5,685.78
c. Unskilled Laborer 12 15.54 61.43 11,455.47
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
1. Concrete Vibrator, 850 lpm 1 12.68 40.38 511.99
2. Concrete Pump/Pumpcrete 1 12.68 2,076.00 26,319.06
3. Concrete screeder 1 12.65 1,039.13 13,144.93
Minor Tools (10% of Labor Cost) 1,903.82
F. Materials
Ready Mixed Concrete 3000psi at 28 days cum 92.3 4,504.76 415,789.52
Consumables 5% 20,789.48
A. Labor
a. Construction Foreman 1 17.94 121.84 2,185.80
b. Skilled Laborer 4 17.84 91.47 6,527.30
c. Unskilled Laborer 12 17.84 61.43 13,150.93
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
1. Concrete Vibrator, 850 lpm 1 14.55 40.38 587.56
2. Concrete Pump/Pumpcrete 1 14.55 2,076.00 30,203.77
3. Concrete screeder 1 14.55 1,039.13 15,118.25
Minor Tools (10% of Labor Cost) 2,186.40
F. Materials
Ready Mixed Concrete 2500psi at 28 days cum 106 3,352.38 355,352.38
Consumables 5% 17,767.62
A. Labor
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Name and Capacity No of Unit/s No. of Days/s Daily Rate Amount (PhP)
B. Equipment 600sqm
H Frame assembly, 1.7 x 1.2m 234 60.00 6.66 93,562.56
U Head 468 60.00 1.62 45,601.92
Base Jack 468 60.00 1.57 44,029.44
Diagonal brace 1232 60.00 2.24 165,580.80
Horizontal brace 1232 60.00 2.30 169,720.32
Primary beam support, 122 aluminum beam 520 60.00 2.46 76,876.80
Secondary beam support, 122 aluminum beam 540 60.00 2.46 79,833.60
GI Pipe 40Ø x 6m 80 60.00 7.06 33,868.80
Props 924 60.00 7.06 391,184.64
Wing nut 4928 1.00 44.80 220,774.40
Joint Pin 936 60.00 0.17 9,434.88
Clamp 468 1.00 28.00 13,104.00
Ladder 60 60.00 5.21 18,748.80
Catwalk 117 60.00 3.14 22,014.72
Turn buckles props 468 60.00 4.98 139,950.72
Minor Tools (10% of Labor Cost) 96,340.95
A. Labor
Installation
a. Construction Foreman 1 107.50 121.84 13,097.80
b. Skilled Laborer 2 102.00 91.47 18,659.88
c. Unskilled Laborer 4 102.00 61.43 25,063.44
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
F. Materials kg
Steel Roof Framing (Trusses) kg 8957.96 54.48 487,995.54
A. Labor
Installation
a. Construction Foreman 1 91.00 121.84 11,087.44
b. Skilled Laborer 2 91.00 91.47 16,647.54
c. Unskilled Laborer 4 91.00 61.43 22,360.52
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Welding Machine, 500Amp, Electric 1 91.00 391.00 35,581.00
Scaffolding 1 91.00 50.00 4,550.00
F. Materials
A. Labor
Installation
a. Construction Foreman 1 76.00 121.84 9,259.84
b. Skilled Laborer 1 76.00 91.47 6,951.72
c. Unskilled Laborer 2 76.00 61.43 9,337.36
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Installation
a. Construction Foreman 1 85.00 121.84 10,356.40
b. Skilled Laborer 1 85.00 91.47 7,774.95
c. Unskilled Laborer 2 85.00 61.43 10,443.10
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Welding Machine, 500Amp, Electric 1 85.00 391.00 33,235.00
Scaffolding 1 85.00 50.00 4,250.00
F. Materials
Seismic Gap ( Joint fillers , Rubber Gusket , aluminum frames , including all
Item No./Description: SPL (6) accessories)
Unit of Measurement: lm
Output: 1
Quantity: 12.00 lm
A. Labor
Installation
a. Construction Foreman 121.84 -
b. Skilled Laborer 91.47 -
c. Unskilled Laborer 61.43 -
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
F. Materials
New CHB Wall-100mm (4") CHB Walls Including plastering, stiffener column and lintel
Item No./Description: 1046 (1) a1
beams
Unit of Measurement: sqm
Output: 4
Quantity: 1283.00 sqm
A. Labor
CHB Installation
a. Construction Foreman 1 264.00 121.84 32,165.76
b. Skilled Laborer 4 264.00 91.47 96,592.32
c. Unskilled Laborer 6 264.00 61.43 97,305.12
Plastering Works
a. Construction Foreman 1 520.00 121.84 63,356.80
b. Skilled Laborer 6 520.00 91.47 285,386.40
c. Unskilled Laborer 4 520.00 61.43 127,774.40
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
1 Bagger Concrete Mixer 1 264.00 172.00 45,408.00
Scaffolding/Formworks 1 520.00 50.00 26,000.00
Minor Tools (10% of Labor Cost) 70,258.08
A. Labor
a. Construction Foreman 1 18.27 121.84 2,226.15
b. Skilled Laborer 3 18.00 91.47 4,939.38
c. Unskilled Laborer 6 18.00 61.43 6,634.44
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
A. Labor
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
A. Labor
a. Construction Foreman 1 312.18 121.84 38,036.01
b. Skilled Laborer 6 308.00 91.47 169,036.56
c. Unskilled Laborer 6 308.00 61.43 113,522.64
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Item No./Description: 1053(1) FF-3; 7mm thk 500x500mm Carpet tiles in PVC & fiberglass backing
Unit of Measurement: sqm
Output: 1
Quantity: 124.00 sqm
A. Labor
a. Construction Foreman 1 63.69 121.84 7,760.42
b. Skilled Laborer 2 60.00 91.47 10,976.40
c. Unskilled Laborer 4 60.00 61.43 14,743.20
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
1. 7mm thk 500x500mm Carpet tiles in PVC & fiberglass sqm 124.00 1,728.57 214,342.86
A. Labor
a. Construction Foreman 1 24.00 121.84 2,924.16
b. Skilled Laborer 1 24.00 91.47 2,195.28
c. Unskilled Laborer 2 24.00 61.43 2,948.64
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
A. Labor
a. Construction Foreman 1 6.21 121.84 756.98
b. Skilled Laborer 1 6.20 91.47 567.11
c. Unskilled Laborer 1 6.20 61.43 380.87
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
B. Equipment
Concrete Trowel 1 6.00 113.95 683.70
Item No./Description: 1018 (2) FF-6, 300 x 300mm Vitrified ceramic tiles
Unit of Measurement: sqm
Output: 1
Quantity: 35.00 sqm
A. Labor
a. Construction Foreman 1 45.27 121.84 5,515.70
b. Skilled Laborer 1 45.30 91.47 4,143.59
c. Unskilled Laborer 2 45.30 61.43 5,565.56
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Item No./Description: 1018 (2) 300 x 600mm Vitrified ceramic wall tiles with tile grout & sealer on joint
Unit of Measurement: sqm
Output: 1
Quantity: 138.00 sqm
A. Labor
a. Construction Foreman 1 115.36 121.84 14,055.51
b. Skilled Laborer 2 115.30 91.47 21,092.98
c. Unskilled Laborer 4 115.30 61.43 28,331.52
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
1. 300 x 600mm Vitrified ceramic wall tiles with tile grout pc 828.00 171.23 141,778.57
2. Tile Adhesive bag 87.00 550.00 47,850.00
3. Tile Grout bag 69.00 80.00 5,520.00
4. Cement bag 47.00 240.00 11,280.00
5. Sand cum 4.00 800.00 3,200.00
A. Labor
a. Construction Foreman 1 240.00 121.84 29,241.60
b. Skilled Laborer 5 240.00 91.47 109,764.00
c. Unskilled Laborer 5 240.00 61.43 73,716.00
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Scaffolding 5 240.00 50.00 60,000.00
A. Labor
a. Construction Foreman 1 22.24 121.84 2,709.67
b. Skilled Laborer 2 22.00 91.47 4,024.68
c. Unskilled Laborer 2 22.00 61.43 2,702.92
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
a. Construction Foreman 1 35.72 121.84 4,351.97
b. Skilled Laborer 4 34.00 91.47 12,439.92
c. Unskilled Laborer 4 34.00 61.43 8,354.48
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Scaffolding 4 34.00 50.00 6,800.00
Item No./Description: 1030 (1) CF-6, 600 x 600 x 20mm thick Fine feassured acoustic tiles
Unit of Measurement: sqm
Output: 1
Quantity: 440.00 sqm
A. Labor
a. Construction Foreman 1 121.84 -
b. Skilled Laborer 4 91.47 -
c. Unskilled Laborer 4 61.43 -
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Scaffolding 2 8.00 50.00 800.00
Item No./Description: 1045(1) CF-7; 4mm thick PUDF 1200 x 1200mm Aluminum composite panels
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
a. Construction Foreman 1 121.84 -
b. Skilled Laborer 4 91.47 -
c. Unskilled Laborer 4 61.43 -
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Scaffolding 1 100.04 100.00 10,004.00
Item No./Description: 1032 (1)a Latex semi-gloss paint finish on plastered wall
Unit of Measurement: sqm
Output: 1
Quantity: 2802.00 sqm
A. Labor
a. Construction Foreman 1 376.85 121.84 45,915.40
b. Skilled Laborer 5 375.50 91.47 171,734.93
c. Unskilled Laborer 10 375.50 61.43 230,669.65
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
A. Labor
a. Construction Foreman 1 262.75 121.84 32,013.46
b. Skilled Laborer 6 262.00 91.47 143,790.84
c. Unskilled Laborer 4 262.00 61.43 64,378.64
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Scaffolding 1 262.00 100.00 26,200.00
Item No./Description: 411 (2) Semi-gloss paint finish on gypsum board ceiling
Unit of Measurement: sqm
Output: 1
Quantity: 641.00 sqm
A. Labor
a. Construction Foreman 1 79.17 121.84 9,646.19
b. Skilled Laborer 5 80.00 91.47 36,588.00
c. Unskilled Laborer 10 80.00 61.43 49,144.00
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
A. Labor
a. Construction Foreman 1 51.31 121.84 6,252.04
b. Skilled Laborer 4 51.00 91.47 18,659.88
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Item No./Description: 1032 (1) c Automotive lacquer paint finish on metal doors
Unit of Measurement: sqm
Output: 1
Quantity: 23.00 sqm
A. Labor
a. Construction Foreman 1 18.82 121.84 2,293.55
b. Skilled Laborer 2 18.82 91.47 3,443.71
c. Unskilled Laborer 2 18.82 61.43 2,312.75
Name and Capacity No of Unit/s Ho. Of Hours Hourly Rate Amount (PhP)
B. Equipment
Consumables 19,338.00
SD-1: 1200 x 2100mm Steel door with 6mm thick vision glass
Item No./Description: 1010(2)b
window, double leaf, double swing
Unit of Measurement: set
Output: 1
Quantity: 1.00 set
SD-6: 1100 x 2100mm Steel door with 1hr fire rating, single leaf,
Item No./Description: 1006(5)
single swing
Unit of Measurement: set
Output: 1
Quantity: 1.00 set
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description: 1043 (2) PVC-1: 800 x 2100mm PVC door with louver, single leaf, single swing
Unit of Measurement: set
Output: 1
Quantity: 1.00 set
GD-1; 2100 x 2100mm x 12mm thick Tempered glass door, double swing, double leaf
Item No./Description: 1007 (1) b with aluminum patch fittings
Unit of Measurement: set
Output: 1
Quantity: 1.00 set
GD-2; 1070 x 2100mm x 12mm thick Tempered frosted glass door, single swing, double
Item No./Description: 1007 (1) b leaf with aluminum patch fittings
Unit of Measurement: set
Output: 1
Quantity: 1.00 set
GD-3; 1900 x 2100mm x 12mm thick Tempered frosted glass door, double swing, double
Item No./Description: 1007 (1) b leaf with aluminum patch fittings
Unit of Measurement: set
Output: 1
Quantity: 1.00 set
GD-4; 1960 x 2100mm x 12mm thick Tempered frosted glass door, double swing, single
Item No./Description: 1007 (1) b leaf with aluminum patch fittings
Unit of Measurement: set
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
W-1; 2350 x 1200mm x 6mm thick Tempered clear glass, aluminum framed casement
Item No./Description: 1008 (1) b window
Unit of Measurement: set
Output: 1
Quantity: 1.00 set
W-2; 1200 x 1200mm x 6mm thick Tempered clear glass, aluminum framed sliding
Item No./Description: 1008 (1) a window
Unit of Measurement: set
Output: 1
Quantity: 1.00 set
W-3; 3500 x 1200mm x 6mm thick Tempered clear glass, aluminum framed sliding
Item No./Description: 1008 (1) a window
Unit of Measurement: set
Output: 1
Quantity: 1.00 set
W-6; 1200 x 600mm x 6mm thick Tempered clear glass, aluminum framed awning
Item No./Description: 1008 (1) c window
Unit of Measurement: set
Output: 1
Quantity: 1.00 set
W-8; 3550 x 5400mm window, 12mm thick Tempered clear glass on aluminum framed
Item No./Description: 1008 (1)d fixed panel and 6mm thick on aluminum framed operable window
ESTABLISHMENT OF REGIONAL INTEGRATED LABORATORY BUILDING OF THE DEPARTMENT OF AGRICULTURE
REGIONAL FIELD OFFICE XII - Phase 1
TUPI, SOUTH COTABATO
DETAILED UNIT PRICE ANALYSIS (DUPA)
W-10; 7700 x 3100mm x 12mm thick Tempered clear glass on aluminum framed
Item No./Description: 1008 (1)d fixed/operable panel window
Unit of Measurement: set
Output: 1
Quantity: 1.00 set
Item No./Description: 1003 (17) Reception (counter, logo, vertical wood slats, curved blades, etc.)
Item No./Description: 1039 (1) 50 x 75mm Aluminum tubular vertical sun baffles, painted
Unit of Measurement: lm
Output: 1
Quantity: 257.00 lm
Item No./Description: 1003 (23) Toilet partitions/cubicles with door panel & accessories
Unit of Measurement: unit
Output: 1
Quantity: 4.00 unit
Item No./Description : 1100 (10) CONDUITS, BOXES & FITTINGS (Conduit Works/Conduit Roughing-In)
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Wiring Device
Simplex Convenience Outlet set 3 P 198.00 594.00
Duplex Convenience Outlet set 168 P 248.60 41,764.80
Floor Mounted Duplex Outlet set 16 P 2,651.00 42,416.00
Floor Mounted Simplex Outlet set 2 P 2,651.00 5,302.00
Special Purpose Outlet set 5 P 852.72 4,263.60
One gang Switch set 14 P 118.69 1,661.66
Two gang Switch set 8 P 188.43 1,507.44
Three gang Switch set 3 P 239.14 717.42
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
PANEL BOARDS
DP - CAB assy 1 P 235,400.00 235,400.00
Main : 500AT/600AF,3P, 400V, 18KAIC
In NEMA 1 Surface mounted
PP - CAB assy 1 P 79,640.00 79,640.00
Main : 75AT/100AF,3P, 400V, 14KAIC
In NEMA 1 Surface mounted
PP - CAB2 assy 1 P 79,640.00 79,640.00
Main : 75AT/100AF,3P, 400V, 14KAIC
In NEMA 1 Surface mounted
LP - CAB assy 1 P 35,354.00 35,354.00
Main : 30AT/100AF,3P, 400V, 14KAIC
In NEMA 1 Surface mounted
MP - CAB assy 1 P 70,455.00 70,455.00
Main : 60AT/100AF,3P, 400V, 14KAIC
In NEMA 1 Surface mounted
MP - CAB RD assy 1 P 137,940.00 137,940.00
Main : 300AT/400AF,3P, 400V, 14KAIC
In NEMA 1 Surface mounted
ENCLOSED CIRCUIT BREAKER
MCB
10A,2P,230V assy 27 P 2,183.50 58,954.50
NEMA 3R
30A,3P,ECB,230V assy 1 P 8,195.00 8,195.00
40A,3P,ECB,230V assy 2 P 8,195.00 16,390.00
60A,3P,ECB,230V assy 1 P 9,845.00 9,845.00
70A,3P,ECB,230V assy 2 P 11,269.50 22,539.00
100A,3P,ECB,230V assy 2 P 12,364.00 24,728.00
Note:
*Delivery cost are included in the unit cost.
PVC Pipe
32mm Ø x 3m PVC Pipe pcs 92 P 199.10 18,317.20
Bare Copper Wire and Grounding Rod and Accessories
50mm2, soft drawn bare copper wires m 276 P 715.22 197,400.72
Ground rod, 20mm dia., 3m length, copper clad pcs 66 P 2,216.50 146,289.00
Ground Plate pcs 3 P 5,280.00 15,840.00
Exothermic welding m-hr 25 P 2,640.00 66,000.00
-
Consumables ( Tape , Gi Wire , Paint ) lot 1 P 136,967.08 136,967.08
Structured Cabling
Testing and Commissioning M-Hr 60 -
ROUGHING INSTALTION
EMT Pipe w/ coupling
20mm Ø L 442 P 270.60 119,605.20
EMT Elbow
20mm Ø pcs 99 P 110.33 10,922.67
EMT Lock Nut and Bushing
20mm Ø pcs 206 P 20.35 4,192.10
Boxes , Pull Box and Flexible Conduit and Connectors
2x4 utility boxe #16 pcs 99 P 48.40 4,791.60
4x4 junction box w/ cover #16 pcs 4 P 49.50 198.00
4x4 square box with cover #16 pcs 10 P 63.80 638.00
15mm diameter Flexible Metalic Conduit m 206 P 89.10 18,354.60
15mm diameter Flexible connector pcs 412 P 23.10 9,517.20
Pull Box pcs 1 P 13,750.00 13,750.00
Voice and Data Cables
4-PAIR CAT-6/6A UTP m 1,327 P 44.77 59,409.79
4 Core Multi Mode Fiber Optic Cable m 0 P 522.50 -
ROUGHING INSTALTION
EMT Pipe w/ coupling
20mm Ø L 162 P 270.60 43,837.20
32mm Ø L 0 P 929.50 -
EMT Elbow
20mm Ø pcs 72 P 110.33 7,943.76
32mm Ø pcs 0 P 312.40 -
EMT Lock Nut and Bushing
20mm Ø pcs 72 P 20.35 1,465.20
32mm Ø pcs 0 P 51.70 -
Boxes , Pull Box and Flexible Conduit and Connectors
2x4 utility box #16 pcs 6 P 48.40 290.40
4x4 junction box w/ cover #16 pcs 30 P 49.50 1,485.00
4x4 square box with cover #16 pcs 8 P 63.80 510.40
15mm diameter Flexible Metalic Conduit m 60 P 89.10 5,346.00
15mm diameter Flexible connector pcs 180 P 23.10 4,158.00
Pull Box pcs 1 P 4,950.00 4,950.00
CCTV Cables
4-PAIR CAT-6/6A UTP m 487 P 44.77 21,802.99
4C Multi- Mode Fiber m 0 P 136.40 -
CCTV Equipment
CCTV CEILING MOUNTED IN. set 19 P 18,150.00 344,850.00
CCTV CEILING MOUNTED PTZ set 5 P 40,242.40 201,212.00
CCTV WALL MOUNTED EX set 4 P 23,551.00 94,204.00
CCTV WALL MOUNTED IN set 2 P 16,940.00 33,880.00
Network Video Recorder pcs 1 P 97,900.00 97,900.00
Switch Core 12 - Port pcs 1 P 10,450.00 10,450.00
Switch Network 48 - Port pcs 1 P 37,950.00 37,950.00
UPS pcs 1 P 38,500.00 38,500.00
Monitor pcs 2 P 9,350.00 18,700.00
PA-BGM
Testing and Commissioning M-Hr 35 P - -
ROUGHING INSTALTION
EMT Pipe w/ coupling
15mm Ø L 111 P 235.40 26,129.40
EMT Elbow
15mm Ø pcs 16 P 37.40 598.40
EMT Lock Nut and Bushing
15mm Ø pcs 142 P 17.27 2,452.34
Boxes , Pull Box and Flexible Conduit and Connectors
2x4 utility boxe #16 pcs 22 P 48.40 1,064.80
4x4 junction box w/ cover #16 pcs 49 P 49.50 2,425.50
4x4 square box with cover #16 pcs 4 P 63.80 255.20
15mm diameter Flexible Metalic Conduit pcs 142 P 89.10 12,652.20
15mm diameter Flexible connector pcs 284 P 23.10 6,560.40
Pull Box pcs 1 P 4,950.00 4,950.00
pcs -
PA-BGM Wire pcs -
#16 AWG TF Shielded Pair pcs 334 P 44.00 14,696.00
pcs -
PA-BGM DEVICE AND EQUIPMENT pcs -
Remote Microphone pcs 1 P 23,980.00 23,980.00
Voice Announcement pcs 1 P 36,850.00 36,850.00
Digital Announcer Pre- Recorded Voice pcs 1 P 1,650.00 1,650.00
Volume Controller m 1 P 2,046.00 2,046.00
Audio Controller pcs 1 P 2,046.00 2,046.00
Ceiling mounted Loud Speaker pcs 44 P 1,023.00 45,012.00
PPR Pipes PN 20
40 mmØ x 4mtrs lgth 1.00 1,852.51 1,852.51
32 mmØ x 4mtrs lgth 3.00 1,288.65 3,865.95
25 mmØ x 4mtrs lgth 3.00 847.00 2,541.00
20 mmØ x 4mtrs lgth 7.00 491.26 3,438.82
Coupling
40 mmØ pc/s 3.00 50.16 150.48
32 mmØ pc/s 4.00 44.88 179.52
25 mmØ pc/s 3.00 25.08 75.24
20 mmØ pc/s 9.00 11.88 106.92
Tee Connector
40 mmØ x 40 mmØ pc/s 1.00 99.00 99.00
40 mmØ x 32 mmØ pc/s 2.00 87.12 174.24
32 mmØ x 32 mmØ pc/s 4.00 58.08 232.32
32 mmØ x 25 mmØ pc/s 12.00 50.16 601.92
25 mmØ x 25 mmØ pc/s 16.00 47.52 760.32
25 mmØ x 20 mmØ pc/s 18.00 34.32 617.76
20 mmØ x 20 mmØ pc/s 22.00 31.68 696.96
Elbow
40 mmØ pc/s 4.00 204.60 818.40
32 mmØ pc/s 12.00 77.00 924.00
25 mmØ pc/s 22.00 60.50 1,331.00
20 mmØ pc/s 48.00 26.40 1,267.20
Female Adaptor
25 mmØ pc/s 10.00 200.86 2,008.60
20 mmØ pc/s 16.00 125.84 2,013.44
Male Adaptor
25 mmØ pc/s 4.00 220.95 883.80
20 mmØ pc/s 4.00 138.42 553.68
Gate Valve (Brass)
32 mmØ pc/s 1.00 1,003.75 1,003.75
25 mmØ pc/s 2.00 829.40 1,658.80
20 mmØ pc/s 4.00 548.90 2,195.60
Appurtences
Lavatory Counter Wall Hung set 1.00 8,230.20 8,230.20
Lavatory Counter Top set 4.00 10,396.10 41,584.40
Urinal with Flush valve set 3.00 12,595.00 37,785.00
Water Closet Flush Type set 5.00 17,600.00 88,000.00
Kitchen Sink with Faucet set 1.00 6,025.80 6,025.80
Grease Trap (4GPM) set 1.00 8,196.10 8,196.10
Testing and Commisioning m-hr 20.00