Module 5
Module 5
Here are six reasons why you should use project management.
A good project manager considers the big picture and sets realistic
and achievable goals, budgets, and timelines. Without careful
management, a project can quickly get off track before it has even
begun.
4. Managed process
5. Quality control
Quality control is an essential component of project management.
Your project could meet all parameters for time and budget, but if
the quality standards aren’t met, the project will be deemed a
failure.
That’s where project managers come in. They not only manage
deadlines and objectives, but they also keep an eye on how well
project tasks are executed. Project managers help outline
deliverables and define their quality standards so that everyone
knows exactly what they’re aiming for.
6. Reduced costs
https://www.projectcubicle.com/project-management-processes-process-groups-knowledge-
areas/
The Project Life Cycle and Phases of Project Management Life Cycle
A delay may occur concurrently with other delays and all of them may impact the
project completion date. Delays caused by the client such as late submission of
drawings and specifications, frequent change orders, and inadequate site
information generate claims from both the main contractors and subcontractors
which many times entail lengthy court bettles with huge financial repercussions.
Delays caused by contractors can generally be attributes to poor managerial skills.
Lack of planning and a poor understanding of accounting and financial principles
have led to many a contractor’s downfall.
Many construction projects have faced various problems and delay of time is one of
the major problems. The delay in dispute settlement has manifold effects such as it
will give detrimental to the relationship between owner and contractor. Moreover, it
will also contribute to the cost and time overruns. The most serious problem is it
sends bad signals to foreign investors thereby slowing down the national progress. It
is generally said that the contract language is considered difficult to comprehend and
they are therefore a major source of disputes. Although our research are in the same
state, but my research would be more concentrate on campus construction project
and the problems faced in university construction site would be slightly different from
other area.
A. Types of delay
1. Critical or noncritical
2. Excusable or non-excusabl
3. Compensable or non-compensable
4. Concurrent or non-concurrent
All delays that are identified in the analysis will be either excusable or non
excusable. Delay can be further categorized into compensable or non-compensable
delays.
4. The physical constraint of the project, i.e. how to build the job from a practical
perspective.
All delays are either excusable or non-excusable. An excusable delay is a delay that
is due to an unforeseeable event beyond the contractor’s or the subcontractor’s
control. Normally, based on common general provisions in public agency
specifications, delays resulting from the following events would be considered
excusable:
2. Fires
3. Floods
4. Acts of God
5. Owner-directed changes
In the most cases, a contract specifically notes the kinds of delays that are non-
compensable, for which the contractor does not receive any additional money but
may be allowed a time extension.
E. Concurrent Delays
The concept of concurrent delay has become a very common presentation as part of
some analysis of construction delays. The concurrency argument is not just from the
standpoint of determining the project’s critical delays but from the standpoint of
assigning responsibility for damages associated with delays to the critical path.
Owners will often cite concurrent delays by the contractor as a reason for issuing a
time extension without additional compensation. Contractors will often cite
concurrent delays by the owner as a reason why liquidated damages should not be
assessed for its delays. Unfortunately, few contract specifications include a definition
of concurrent delay and how concurrent delays affect a contractor’s entitlement to
additional compensation for time extension or responsibility for liquidated damages.
F. Effects of Delay
1. Time overrun;
2. Cost overrun;
3. Dispute;
4. Arbitration;
6. Litigation.
Clauses have the virtue of informing both parties to a contract in advance what the
damages payable for an identified breach will be at the time of entering the contract.
This can be equal advantage to the party who must pay the damages as it is to the
party receiving the damages. The upper limit of the damages payable is fixed and a
party can take this into account in the initial negotiations. It is not uncommon for a
contractor who knows he or she cannot complete within the required time to add the
liquidated damages equivalent of the time overrun to the tendered price.
Conclusion
Delays occur in every construction project and the magnitude of these delays varies
considerably from project to project. Some projects are only a few days behind the
schedule; some are delayed over a year. So it is essential to define the actual
causes of delay in order to minimize and avoid the delays in any construction project.
There is a wide range of views for the causes of time delays for engineering and
construction projects. Some are attributable to a single party, others can be ascribed
to several quarters and many relate more to systemic faults or deficiencies rather
than to group or groups. The successful execution of construction projects and
keeping them within estimated cost and prescribed schedules depend on a
methodology that requires sound engineering judgment.
1. Principle of Success:
3. Principle of Commitment:
4. Principle of Structure:
This refers to the structure your project will take with respect to
project goal, resources, and time. These three pillars provide the
structure to the project and must be decided even before the project
starts. By knowing the reason for the project and what it aims to
achieve, you can identify how to go about it and this provides the first
structure. The second structure is to identify how much time it will
take to reach the objectives and the final structure is to identify the
resources.
5. Principle of Definition:
6. Principle of Transparency:
7. Principle of Communication:
8. Principle of Progress: