0% found this document useful (0 votes)
24 views33 pages

DDocument Performance Monitoring

Uploaded by

sreeagile.es
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views33 pages

DDocument Performance Monitoring

Uploaded by

sreeagile.es
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 33

MINISTRY OF ELECTRICITY AND WATER - KUWAIT

SUPPLY & INSTALLATION OF QURAIN W 300/132 / 11 KV SUBSTATION

PROJECT ENGINEERING DEPARTMENT OVERALL PROGRESS REPORT

Prepared by:
Date: 4-Feb-08
Covering Period: Jan-08
Remarks:

Drawing Class Task Description Responsible No of Documents % Complete

1 Design Briefs PEC 38 92%


5 300kV GIS Drawings Itami 68 86%
7 132kV GIS Drawings Itami 56 82%
9 33kV SWG PEC 2 85%
11 11kV Switchgear Drawings Al Ahleia 1 85%

300MVA & 30MVA Transformers & Reactor


12 Drawings Ako 63 85%
13 11/0.415kV Aux Transformer Drawings OCREV 6 85%
14 NER & Changeover Switch drawings TBA 3 85%
15 Control Panel drawings Al Ahleia 9 85%
16 Protection panel Drawings Al Ahleia 4 68%
17 415V LVAC Drawings Al Ahleia 7 85%
18 110V Battery & Charger drawings DC Supplier 18 85%
20 Power Cable Layout and Cable Schedule PEC 19 91%
21 Marshalling Panel PEC 8 85%
22 Substation Layout & Sections PEC 1 85%
23 Earthing Drawings, MTO & schedules PEC 12 95%
24 Key and Single Line Diagrams PEC 4 85%
25 Schematics Diagrams PEC 37 85%
26 Termination Diagrams PEC 86 50%
28 Control Cable Ladder Rack Layouts PEC 8 95%
30 GA Drawings PEC 42 91%
31 RC Detail Drawings CCC #REF! 0%
32 Steelwork CCC 1 0%
36 Lighting and Small Power CCC 1 0%
37 HVAC CCC 1 0%
38 Fire Fighting KFF 1 0%
39 PA Drawings PEC 10 98%

Overall Hours Spent 6854.5


Overall Completeness 78%
Overall Productivity 97%

file:///conversion/tmp/activity_task_scratch/763687361.xls
file:///conversion/tmp/activity_task_scratch/763687361.xls
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er
Drawing Class 01

Design Briefs and Specifications

1114 01 001 3404/1114-01-001 Design Brief for Protection Relay, Inst. & Metering PEC
1114 01 002 3404/1114-01-002 300/kV CT and VT Design Brief PEC
1114 01 003 3404/1114-01-003 132/33kV CT and VT Design Brief PEC
1114 01 004 3404/1114-01-004 11kV& 415V CT and VT Design Brief PEC
1114 01 005 3404/1114-01-005 Design Brief for Earthing System PEC
1114 01 006 3404/1114-01-006 415 AC Distribution Bd. Interlocking Scheme PEC
1114 01 007 3404/1114-01-007 Substation Testing & Commissioning Proceedure PEC
Design Brief for Calculation of Battery and Battery Charger Capacities for 220/110V DC
1114 01 008 3404/1114-01-008 Systems PEC
1114 01 009 3404/1114-01-009 Design Brief for Intertrip Equipment Eq. Supplier
1114 01 010 3404/1114-01-010 Protection Relay Settings PEC
1114 01 600 N/A General Technical Specification PEC
General Specification for Control Equipment Associated with Switchgear, Control and
1114 01 601 N/A Relay Panels PEC
1114 01 602 N/A Paint Specification PEC
1114 01 603 N/A General Specification for Supply of Equipment
1114 01 604 N/A Specification for Cabling and Ferruling Identification Scheme PEC
1114 01 605 N/A Specification for 11kV Switchgear PEC
1114 01 606 N/A Specification for DC System PEC
1114 01 607 N/A Specification for 33kV, 11kV and 3kV Power Cables PEC
1114 01 608 N/A Specification for 300/132/33/11kV Telemetry Transfer Terminal Block Cabinets PEC
1114 01 609 N/A Specification for Control Cables PEC
1114 01 610 N/A Specification for Fibre Optic cables PEC
1114 01 611 N/A Specification for 415V LVAC Distribution Board PEC
1114 01 612 N/A Specification for 11kV Pilot Wire Marshalling Cabinet PEC
1114 01 613 N/A Drawing and Document Submission Procedure PEC
1114 01 614 N/A Specification for Erection Works PEC
1114 01 615 N/A Specification for 300 kV Oil Filled Cables & Accessories PEC
1114 01 616 N/A Specification for 132 kV Oil Filled Cables & Accessories PEC
1114 01 617 N/A Specification for 750 kVA Transformers PEC
1114 01 618 N/A Specification for Neutral Earthing Resistor PEC
1114 01 619 N/A Specification for Neutral Earthing Changeover Switch PEC
1114 01 620 N/A Specification for Control and Relay panels PEC
1114 01 801 3404/1114-01-801 VOLUME 1 -300kV Building GROUND FLOOR SLAB & BEAMS CCC
1114 01 802 3404/1114-01-802 VOLUME 2 -300kV Building LOW & HIGH LEVEL ROOF BEAMS & SLABS CCC
1114 01 803 3404/1114-01-803 VOLUME 3 -300kV Building Building STABILITY, COLUMNS & WALLS CCC
1114 01 804 3404/1114-01-804 VOLUME 4 -300kV Building RAFT FOUNDATIONS CCC
1114 01 805 3404/1114-01-805 VOLUME 5 - 132kV Building GROUND FLOOR SLAB & BEAMS CCC
1114 01 806 3404/1114-01-806 VOLUME 6 -132kV Building LOW & HIGH LEVEL ROOF BEAMS & SLABS CCC
1114 01 807 3404/1114-01-807 VOLUME 7 - 132kV Building Building STABILITY, COLUMNS & WALLS CCC
1114 01 808 3404/1114-01-808 VOLUME 8 -132kV Building RAFT FOUNDATIONS CCC
1114 01 809 3404/1114-01-809 VOLUME 9 -GENERAL EXTERNAL WORKS CCC
1114 01 810 3404/1114-01-810 VOLUME 10 - OHL WORKS EXTERNAL FOUNDATIONS Hyundai

1114 01 821 3404/1114-01-821 O/H cranes - design file CCC


1114 01 822 3404/1114-01-822 E/I works - design file CCC
1114 01 823 3404/1114-01-823 HVAC works - design file CCC
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er

Drawing Class 05

300kV Switchgear Drawings

1114 05 001 3404/1114-05-001 H1T0283 Layout of 300kV GIS ITAMI


1114 05 002 3404/1114-05-002 H1T0268 Foundation of 300kV GIS ITAMI
1114 05 003 3404/1114-05-003 HIT0250 Gas System for 300kV GIS ITAMI
1114 05 004 3404/1114-05-004 Outline Feeder ITAMI
1114 05 005 3404/1114-05-005 OutlineTransformer Feeder ITAMI
1114 05 006 3404/1114-05-006 Outline Bus Section ITAMI
1114 05 007 3404/1114-05-007 Outline Bus Coupler ITAMI
1114 05 008 3404/1114-05-008 Transformer Neutral Point Lighting Arrestor & Isolator Outline ITAMI
1114 05 009 3404/1114-05-009 Internal Details of Circuit Breaker ITAMI
1114 05 010 3404/1114-05-010 Internal Details of Isolator ITAMI
1114 05 011 3404/1114-05-011 Internal Details of Isolator and Earthing Switch ITAMI
1114 05 012 3404/1114-05-012 Internal Details of Isolator and Fault Making Earthing Switch ITAMI
1114 05 013 3404/1114-05-013 Cable Connection of 300kV GIS ITAMI
1114 05 014 3404/1114-05-014 Testing Bushing Arrangement for 300kV Power Cables ITAMI
1114 05 015 3404/1114-05-015 Testing Bushing Arrangement for GIS ITAMI
1114 05 016 3404/1114-05-016 Opreating Mechanism Housing For CB ITAMI
1114 05 017 3404/1114-05-017 Outline of Operating Mechanism for Bus Selector DS ITAMI
1114 05 018 3404/1114-05-018 Outline of Operating Mechanism for ES and Line DS ITAMI
1114 05 019 3404/1114-05-019 Outline of Operating Mechanism for Fault Making Earth Switch ITAMI
1114 05 020 3404/1114-05-020 Outline of Motor Driven Spring Operating Mechanism for Neutral Point Earth Switch ITAMI
1114 05 021 3404/1114-05-021 Outline of Manual Operating Mechanism for VT Isolator ITAMI
1114 05 022 3404/1114-05-022 Outline of GAS Monitoring Module ITAMI
1114 05 023 3404/1114-05-023 Name Plate for Gas Circuit Breaker ITAMI
1114 05 024 3404/1114-05-024 Name Plate for Isolator ITAMI
1114 05 025 3404/1114-05-025 Name Plate for Earthing Switch ITAMI
1114 05 026 3404/1114-05-026 Name Plate for Fault Making Earthing Switch ITAMI
1114 05 027 3404/1114-05-027 Name Plate for Voltage Transformer ITAMI
1114 05 028 3404/1114-05-028 Name Plate for Current Transformer ITAMI
1114 05 029 3404/1114-05-029 Line Feeder Nameplate (Fault Indication Details) ITAMI
1114 05 030 3404/1114-05-030 Transformer Nameplate (Fault Indication Details) ITAMI
1114 05 031 3404/1114-05-031 Bus Section Nameplate (Fault Indication Details) ITAMI
1114 05 032 3404/1114-05-032 Bus Coupler Nameplate (Fault Indication Details) ITAMI
1114 05 033 3404/1114-05-033 Out line of Local Control Panel Line Feeder ITAMI
1114 05 034 3404/1114-05-034 Out line of Local Control PanelTransformer Feeder ITAMI
1114 05 035 3404/1114-05-035 Out line of Local Control Panel Bus Section ITAMI
1114 05 036 3404/1114-05-036 Out line of Local Control Panel Bus Coupler ITAMI
1114 05 037 3404/1114-05-037 Inside arrangement of Local Control Panel Line Feeder ITAMI
1114 05 038 3404/1114-05-038 Inside arrangement of Local Control PanelTransformer Feeder ITAMI
1114 05 039 3404/1114-05-039 Inside arrangement of Local Control Panel Bus Section ITAMI
1114 05 040 3404/1114-05-040 Inside arrangement of Local Control Panel Bus Coupler ITAMI
1114 05 041 3404/1114-05-041 Line Feder - Wiring Diagram of 300kV Local Control Panel ITAMI
1114 05 042 3404/1114-05-042 Transformer Feeder - Wiring Diagram of 300kV Local Control Panel ITAMI
1114 05 043 3404/1114-05-043 Bus Section - Wiring Diagram of 300kV Local Control Panel ITAMI
1114 05 044 3404/1114-05-044 Bus Coupler - Wiring Diagram of 300kV Local Control Panel ITAMI
1114 05 045 3404/1114-05-045 Connection Between GIS and Transformer(HV) ITAMI
1114 05 046 3404/1114-05-046 Connection Between GIS and Transformer(Neutral) ITAMI
1114 05 047 3404/1114-05-047 Name Plate for Isolator ITAMI

H1T0660 Single Line of 300kV GIS


H31L528 Schematic diagram of motor driveMechanism Type MDDC
H31L527 Schematic Diagram of Motor Charged Spring Drive Mechanism Type MBE-05M
5 Schematic Diagram of GCB
6 Wiring Diagram of GCB
H31L610 Wiring diagram of motor driveMechanism Type MDDC
Wiring Diagram of Motor Charged Spring Drive Mechanism Type MBE-05M(for Output
H31L608 Shaft On Left Side)
Wiring Diagram of Motor Charged Spring Drive Mechanism Type MBE-05M(for Output
H31L609 Shaft On Right Side)
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er

Drawing Class 07

132kV Switchgear Drawings

1114 07 001 3404/1114-07-001 H1T0279 Layout of 132kV GIS ITAMI


1114 07 002 3404/1114-07-002 H1T0267 Foundation of 132kV GIS ITAMI
1114 07 003 3404/1114-07-003 Outline of Line Feeder Unit ITAMI
1114 07 004 3404/1114-07-004 Cross Section of Line Feeder Unit ITAMI
1114 07 005 3404/1114-07-005 Outline of Transformer Feeder Unit (1) ITAMI
1114 07 006 3404/1114-07-006 Cross Section of Transformer Feeder Unit(1) ITAMI
1114 07 007 3404/1114-07-007 Outline of Transformer Feeder Unit (2) ITAMI
1114 07 008 3404/1114-07-008 Cross Section of Transformer Feeder Unit(2) ITAMI
1114 07 009 3404/1114-07-009 Outline of Bus Section Unit ITAMI
1114 07 010 3404/1114-07-010 Cross Section of Bus Section Unit ITAMI
1114 07 011 3404/1114-07-011 Outline of Bus Coupler Unit ITAMI
1114 07 012 3404/1114-07-012 Cross Section of Bus Coupler Unit ITAMI
1114 07 013 3404/1114-07-013 H2Z1664 Cable Connection of 132kV GIS (1) ITAMI
1114 07 014 3404/1114-07-014 H2Z1667 Cable Connection of 132kV GIS (2) ITAMI
1114 07 015 3404/1114-07-015 Outline of Voltage Transformer with Isolating Device ITAMI
1114 07 016 3404/1114-07-016 H31L880 Outline of Motor Operating Mechanism for DS and ES ITAMI
1114 07 017 3404/1114-07-017 H31L879 Outline of Motor Operating Mechanism for DS ITAMI
1114 07 018 3404/1114-07-018 H31L881 Outline of Motor Charged Spring Operating Mechanism for FES ITAMI
1114 07 019 3404/1114-07-019 Outline of Manual Operating Mechanism for VT Isolator ITAMI
1114 07 020 3404/1114-07-020 H31L599 Nameplate for Gas Circuit Breaker ITAMI
1114 07 021 3404/1114-07-021 H31L600 Nameplate for Isolator / Earthing Switch ITAMI
1114 07 022 3404/1114-07-022 H31L661 Nameplate for Isolator Switch ITAMI
1114 07 023 3404/1114-07-023 H31L601 Nameplate for Fault Making Earthing Switch ITAMI
1114 07 024 3404/1114-07-024 Nameplate for Voltage Transformer ITAMI
1114 07 025 3404/1114-07-025 H1T0249 Gas System Scheme ITAMI
1114 07 026 3404/1114-07-026 H31L663 Nameplate for Current Transformer ITAMI
1114 07 027 3404/1114-07-027 Nameplate (Fault Indication Detail) Line Feeder ITAMI
1114 07 028 3404/1114-07-028 Nameplate (Fault Indication Detail) Transformer Feeder (1) ITAMI
1114 07 029 3404/1114-07-029 Nameplate (Fault Indication Detail) Transformer Feeder (2) ITAMI
1114 07 030 3404/1114-07-030 Nameplate (Fault Indication Detail) Bus Section ITAMI
1114 07 031 3404/1114-07-031 Nameplate (Fault Indication Detail) Bus Coupler ITAMI
1114 07 032 3404/1114-07-032 Outline of Local Control Panel Line Feeder ITAMI
1114 07 033 3404/1114-07-033 Outline of Local Control Panel Transformer Feeder (1) ITAMI
1114 07 034 3404/1114-07-034 Outline of Local Control Panel Transformer Feeder (2) ITAMI
1114 07 035 3404/1114-07-035 Outline of Local Control Panel Bus Section ITAMI
1114 07 036 3404/1114-07-036 Outline of Local Control Panel Bus Coupler ITAMI
1114 07 037 3404/1114-07-037 Inside Arrangement of Local Control Panel Line Feeder ITAMI
1114 07 038 3404/1114-07-038 Inside Arrangement of Local Control Panel Transformer Feeder (1) ITAMI
1114 07 039 3404/1114-07-039 Inside Arrangement of Local Control Panel Transformer Feeder (2) ITAMI
1114 07 040 3404/1114-07-040 Inside Arrangement of Local Control Panel Bus Section ITAMI
1114 07 041 3404/1114-07-041 Inside Arrangement of Local Control Panel Bus Coupler ITAMI
1114 07 042 3404/1114-07-042 Voltmeter for Feeder Voltage Transformer ITAMI
1114 07 043 3404/1114-07-043 Wiring Diagram of Local Control Panel For Line Feeder ITAMI
1114 07 044 3404/1114-07-044 Wiring Diagram of Local Control Panel For Transformer Feeder(1) ITAMI
1114 07 045 3404/1114-07-045 Wiring Diagram of Local Control Panel For Transformer Feeder(2) ITAMI
1114 07 046 3404/1114-07-046 Wiring Diagram of Local Control Panel For Bus Section ITAMI
1114 07 047 3404/1114-07-047 Wiring Diagram of Local Control Panel For Bus Coupler ITAMI
1114 07 048 3404/1114-07-048 H31L602 Construction of Rupture Disc ITAMI
1114 07 049 3404/1114-07-049 Ladder with Wheels ITAMI
1114 07 050 3404/1114-07-050 H31L604 Bottle of SF6 Gas ITAMI
1114 07 051 3404/1114-07-051 H31L605 Pneumatic Rubber Maintenance Truck ITAMI
1114 07 052 3404/1114-07-052 H31L606 SF6 Gas Service Set ITAMI
1114 07 053 3404/1114-07-053 HVAC Test Arrangement of GIS ITAMI
1114 07 054 3404/1114-07-054 HV - DC Test Arrangement of Power Cable ITAMI
H1T0612 Single line diagram ITAMI
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er
Drawing Class 09

33KV Switchgear

1114 09 001 3404/1114-09-001 Arrangement Eq. Supplier


1114 09 002 3404/1114-09-002 Sectional View Eq. Supplier
1114 09 003 3404/1114-09-003 Outline of 33kV Gas Circuit Breaker Eq. Supplier
1114 09 004 3404/1114-09-004 Outline of Earthing Switch Eq. Supplier
1114 09 005 3404/1114-09-005 Front View of 33kV Switchgear Eq. Supplier
1114 09 006 3404/1114-09-006 Rear View of 33kV Switchgear Eq. Supplier
1114 09 007 3404/1114-09-007 Indoor Termination on the 33kV Switchgear Side for XLPE Cable Eq. Supplier
1114 09 008 3404/1114-09-008 Cable Sealing End Assembly Eq. Supplier
1114 09 009 3404/1114-09-009 Cable Feeder Back Wiring Eq. Supplier

Drawing Class 11

11KV Switchgear

1114 11 001 3404/1114-11-001 11kV Switchgear Arrangement Al-Ahliea

Drawing Class 12

300MVA Transformers

1114 12 001 3404/1114-12-001 300MVA 300/132/33kV Transformer Outline Drawing MELCO Ako
1114 12 002 3404/1114-12-002 300MVA 300/132/33kV Transformer Rating Plate MELCO Ako
1114 12 003 3404/1114-12-003 300MVA 300/132/33kV Transformer Aux Circuit Wiring Diagram MELCO Ako
1114 12 004 3404/1114-12-004 300MVA 300/132/33kV Transformer Foundation Drawing MELCO Ako
1114 12 005 3404/1114-12-005 300MVA 300/132/33kV Transformer Shipping Sketch MELCO Ako
1114 12 006 3404/1114-12-006 300MVA 300/132/33kV Transformer HV Line Bushing Outline MELCO Ako
1114 12 007 3404/1114-12-007 300MVA 300/132/33kV Transformer LV Line & Neutral Bushing Outline MELCO Ako
1114 12 008 3404/1114-12-008 300MVA 300/132/33kV Transformer 33kV TW Bushing Outline MELCO Ako
1114 12 009 3404/1114-12-009 300MVA 300/132/33kV Transformer HV Side GIB Connection MELCO Ako
1114 12 010 3404/1114-12-010 300MVA 300/132/33kV Transformer LV Cable Connection Box MELCO Ako
1114 12 011 3404/1114-12-011 300MVA 300/132/33kV Transformer 33kV TW Cable Box MELCO Ako
1114 12 012 3404/1114-12-012 300MVA 300/132/33kV Transformer Earthing Terminal MELCO Ako
1114 12 013 3404/1114-12-013 300MVA 300/132/33kV Transformer Valve Location & Function Plate MELCO Ako
1114 12 014 3404/1114-12-014 300MVA 300/132/33kV Transformer Filter Breather for Main Tank Conservator MELCO Ako
1114 12 015 3404/1114-12-015 300MVA 300/132/33kV Transformer Filter Breather for Tap Changer Conservator MELCO Ako
1114 12 016 3404/1114-12-016 300MVA 300/132/33kV Transformer Butterfly Valve MELCO Ako
1114 12 017 3404/1114-12-017 300MVA Transformer Marshalling Kiosk MELCO Ako
1114 12 018 3404/1114-12-018 Assembly Diagram of Transformer Marshalling Kiosk MELCO Ako
1114 12 019 3404/1114-12-019 300MVA 300/132/33kV Transformer Oil Temperature Indicator MELCO Ako
1114 12 020 3404/1114-12-020 300MVA 300/132/33kV Transformer Winding Temperature Indicator MELCO Ako
1114 12 021 3404/1114-12-021 Connection Diagram of Transformer Marshalling Kiosk MELCO Ako
1114 12 022 3404/1114-12-022 Factory Test and Inspection Procedure MELCO Ako
1114 12 023 3404/1114-12-023 Site Test Procedure and Report 300MVA Transformer Load-Tap-Changing MELCO Ako
1114 12 024 3404/1114-12-024 Description of Valve Arrangement MELCO Ako
1114 12 025 3404/1114-12-025 Lifting and Pulling Dimensions of Main Tank MELCO Ako
1114 12 026 3404/1114-12-026 Outline of Pressure Relief Device MELCO Ako
1114 12 027 3404/1114-12-027 Outline Drawing of LTC Protective Relay MELCO Ako
1114 12 028 3404/1114-12-028 Outline of Buchholz Relay MELCO Ako
1114 12 029 3404/1114-12-029 General Valve Arrangement of Transformer MELCO Ako
1114 12 030 3404/1114-12-030 300MVA 300/132/33kV Transformer Main Component Details MELCO Ako

Drawing Class 12

45MVAr Shunt Reactors

1114 12 050 3404/1114-12-050 Shunt Reactor Outline MELCO Ako


1114 12 051 3404/1114-12-051 Protective Device Connection Diagram MELCO Ako
1114 12 052 3404/1114-12-052 Connection Detail of Radiator MELCO Ako
1114 12 053 3404/1114-12-053 Shipping Sketch MELCO Ako
1114 12 054 3404/1114-12-054 Rating Plate MELCO Ako
1114 12 055 3404/1114-12-055 Foundation Drawing MELCO Ako
1114 12 056 3404/1114-12-056 Line & Neutral Bushing Outline MELCO Ako
1114 12 057 3404/1114-12-057 Valve Location & Function Plate MELCO Ako
1114 12 058 3404/1114-12-058 33kV Line Cable Box MELCO Ako
1114 12 059 3404/1114-12-059 Oil Temp - Oil Level Curve MELCO Ako
1114 12 060 3404/1114-12-060 Neutral Cable Box MELCO Ako
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er
Drawing Class 12

30MVA Transformers

1114 12 100 3404/1114-12-100 30MVA 132/11.5kV Transformer Outline Drawing MELCO Ako
1114 12 101 3404/1114-12-101 30MVA 132/11.5kV Transformer Rating Plate MELCO Ako
1114 12 102 3404/1114-12-102 30MVA 132/11.5kV Transformer Aux Circuit Wiring Diagram MELCO Ako
1114 12 103 3404/1114-12-103 30MVA 132/11.5kV Transformer Foundation Drawing MELCO Ako
1114 12 104 3404/1114-12-104 30MVA 132/11.5kV Transformer Shipping Sketch MELCO Ako
1114 12 105 3404/1114-12-105 30MVA 132/11.5kV Transformer HV Line Bushing Outline MELCO Ako
1114 12 106 3404/1114-12-106 30MVA 132/11.5kV Transformer LV Line & Neutral Bushing Outline MELCO Ako
1114 12 107 3404/1114-12-107 30MVA 132/11.5kV Transformer HV Cable Box MELCO Ako
1114 12 108 3404/1114-12-108 30MVA 132/11.5kV Transformer LV Cable Connection Box MELCO Ako
1114 12 109 3404/1114-12-109 30MVA 132/11.5kV Transformer Earthing Terminal MELCO Ako
1114 12 110 3404/1114-12-110 30MVA 132/11.5kV Transformer Valve MELCO Ako
1114 12 111 3404/1114-12-111 30MVA 132/11.5kV Transformer Filter Breather for Main Tank Conservator MELCO Ako
1114 12 112 3404/1114-12-112 30MVA 132/11.5kV Transformer Filter Breather for Tap Changer Conservator MELCO Ako
1114 12 113 3404/1114-12-113 30MVA 132/11.5kV Transformer Butterfly Valve MELCO Ako
1114 12 114 3404/1114-12-114 30MVA Transformer Marshalling Kiosk MELCO Ako
1114 12 115 3404/1114-12-115 Assembly Diagram of Transformer Marshalling Kiosk MELCO Ako
1114 12 116 3404/1114-12-116 30MVA 132/11.5kV Transformer Oil Temperature Indicator MELCO Ako
1114 12 117 3404/1114-12-117 30MVA 132/11.5kV Transformer Winding Temperature Indicator MELCO Ako
1114 12 118 3404/1114-12-118 Connection Diagram of Transformer Marshalling Kiosk MELCO Ako
1114 12 119 3404/1114-12-119 Factory Test and Inspection Procedure MELCO Ako
1114 12 120 3404/1114-12-120 Site Test Procedure and Report 30MVA Transformer Load-Tap-Changing MELCO Ako
1114 12 121 3404/1114-12-121 Description of Valve Arrangement MELCO Ako
1114 12 122 3404/1114-12-122 Lifting and Pulling Dimensions of Main Tank MELCO Ako
1114 12 123 3404/1114-12-123 Outline of Pressure Relief Device MELCO Ako
1114 12 124 3404/1114-12-124 Outline Drawing of LTC Protective Relay MELCO Ako
1114 12 125 3404/1114-12-125 Outline of Buchholz Relay MELCO Ako
1114 12 126 3404/1114-12-126 General Valve Arrangement of Transformer MELCO Ako
1114 12 127 3404/1114-12-127 132/11.5kV 30MVA Transformer Main Component Details MELCO Ako

Drawing Class 13

750KVA Transformers

1114 13 001 3404/1114-13-001 Outline Drawing Ocrev


1114 13 002 3404/1114-13-002 Winding Detail Ocrev
1114 13 003 3404/1114-13-003 Terminal Box Ocrev
1114 13 004 3404/1114-13-004 Foundation Drawing Ocrev
1114 13 005 3404/1114-13-005 HV Cable Box Ocrev
1114 13 006 3404/1114-13-006 LV Cable Box Ocrev
1114 13 007 3404/1114-13-007 HV Bushing Ocrev
1114 13 008 3404/1114-13-008 LV Bushing Ocrev
1114 13 009 3404/1114-13-009 Rating Plate Ocrev
1114 13 010 3404/1114-13-010 Wiring Diagram Ocrev

Drawing Class 14

11kV Neutral Earthing Resistors

1114 14 001 3404/1114-14-001 11kV, 8 Ohm's NER and COS -General Arrangement Eq. Supplier
1114 14 002 3404/1114-14-002 11kV Neutral COS - General Arrangement Eq. Supplier
1114 14 003 3404/1114-14-003 11kV, 8 Ohm's NER - General Arrangement Eq. Supplier

Drawing Class 15

300/132/33/11kV Control Panels

1114 15 001 3404/1114-15-001 45MVAr Shunt Reactor Control & Relay Panel GA Drawings Al-Ahliea
1114 15 002 3404/1114-15-002 300kV Control Panel GA Drawings Al-Ahliea
1114 15 003 3404/1114-15-003 132kV Control Panel GA Drawings Al-Ahliea
1114 15 004 3404/1114-15-004 33kV Control & Relay Panel GA Drawings Al-Ahliea
1114 15 005 3404/1114-15-005 300kV Disturbance Recorder Panel Al-Ahliea
1114 15 050 3404/1114-15-050 Wiring Diagram 300kV Disturbance Recorder Panel Al-Ahliea
1114 15 051 3404/1114-15-051 Wiring Diagram 300kV Control Panel 0/H Line Feeder Al-Ahliea
1114 15 052 3404/1114-15-052 Wiring Diagram 300/132kV Transformer Control Panel Al-Ahliea
1114 15 053 3404/1114-15-053 Wiring Diagram 300kV Bus Coupler Control Panel Al-Ahliea
1114 15 054 3404/1114-15-054 Wiring Diagram 300kV Synchronising Common & Station Alarms Al-Ahliea
1114 15 055 3404/1114-15-055 Wiring Diagram 300kV Bus Section Control Panel Al-Ahliea
1114 15 056 3404/1114-15-056 Wiring Diagram 132kV Control Panel Cable Feeder Al-Ahliea
1114 15 057 3404/1114-15-057 Wiring Diagram 300/132kV Transformer Control Panel Al-Ahliea
1114 15 058 3404/1114-15-058 Wiring Diagram 132kV Bus Coupler Control Panel Al-Ahliea
1114 15 059 3404/1114-15-059 Wiring Diagram 132kV Synchronising Common & Station Alarms Al-Ahliea
1114 15 060 3404/1114-15-060 Wiring Diagram 132kV Bus Section Control Panel Al-Ahliea
1114 15 061 3404/1114-15-061 Wiring Diagram 33kV Control & Relay Panel Al-Ahliea
1114 15 062 3404/1114-15-062 11kV Switchgear Panel Al-Ahliea
1115 15 063 3404/1114-15-063 11kV Control & Relay Panel Al-Ahliea

1114 15 101 3404/1114-15-101 General arrangement of 11KV pilot marshalling cabinet. Al-Ahliea
1114 15 102 3404/1114-15-102 General arrangement of 132KV pilot marshalling cabinet. Al-Ahliea
1114 15 103 3404/1114-15-103 General arrangement of 300KV pilot marshalling cabinet. Al-Ahliea
1114 15 104 3404/1114-15-104 Schematic diagram of pilot marshalling cabinets. Al-Ahliea
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er

Drawing Class 16

300/132kV Protection System

1114 16 001 3404/1114-16-001 300kV Relay Panel Arrangement Drawing List Al-Ahliea
1114 16 002 3404/1114-16-002 132kV Relay Panel Arrangement Drawing List Al-Ahliea
1114 16 003 3404/1114-16-003 300kV BusBar Protection GA Drawings Al-Ahliea
1114 16 050 3404/1114-16-050 Wiring Diagram 300kV Relay Panel 0/H Line Feeder Al-Ahliea
1114 16 051 3404/1114-16-051 Wiring Diagram 300/132kV Transformer Relay Panel Al-Ahliea
1114 16 052 3404/1114-16-052 Wiring Diagram 300kV Bus Coupler Relay Panel Al-Ahliea
1114 16 053 3404/1114-16-053 Wiring Diagram 300kV Bus Section Relay Panel Al-Ahliea
1114 16 054 3404/1114-16-054 Wiring Diagram 132kV Relay Panel Cable Feeder Al-Ahliea
1114 16 055 3404/1114-16-055 Wiring Diagram 300/132kV Transformer Relay Panel Al-Ahliea
1114 16 056 3404/1114-16-056 Wiring Diagram 132kV Bus Coupler Relay Panel Al-Ahliea
1114 16 057 3404/1114-16-057 Wiring Diagram 132kV Bus Section Relay Panel Al-Ahliea
1115 16 058 3404/1114-16-058 300kV BusBar Protection GA Drawings Al-Ahliea

Drawing Class 17

Distribution Boards

1114 17 001 3404/1114-17-001 Outline dimensions (unit layout) of 415 V distribution board front view Al-Ahliea
1114 17 002 3404/1114-17-002 Outline dimensions (unit layout) of 415 V distribution board rear view Al-Ahliea
1114 17 003 3404/1114-17-003 Outline dimensions (unit layout) of 415 V distribution board inside front view Al-Ahliea
1114 17 004 3404/1114-17-004 Outline dimensions (unit layout) of 415 V distribution board rear inside view Al-Ahliea
1114 17 005 3404/1114-17-005 Unit data sheet Al-Ahliea
1114 17 006 3404/1114-17-006 Physical connection diagram Al-Ahliea

Drawing Class 18

Batteries and Chargers

1114 18 001 3404/1114-18-001 220V DC Control Battery Charger Arrangement (BC) Eq. Supplier
1114 18 002 3404/1114-18-002 220V DC Control Battery Charger Circuit Diagram (BC) Eq. Supplier
1114 18 003 3404/1114-18-003 220V DC Control Dist Board Arrangement (DC) Eq. Supplier
1114 18 004 3404/1114-18-004 220V DC Control Distribution Board Circuit Diagram (DC) Eq. Supplier
1114 18 005 3404/1114-18-005 220V DC Control Spare Charger Circuit Diagram Eq. Supplier
1114 18 006 3404/1114-18-006 220V DC Trip Battery Charger Arrangement (BT) Eq. Supplier
1114 18 007 3404/1114-18-007 220V DC Trip Battery Charger Circuit Diagram (BT) Eq. Supplier
1114 18 008 3404/1114-18-008 220 V DC Trip Distribution Board Arrangement (DT) Eq. Supplier
1114 18 009 3404/1114-18-009 220V DC Trip Distribution Board Circuit Diagram (DT) Eq. Supplier
1114 18 010 3404/1114-18-010 220V DC Tripping System Spare Charger Eq. Supplier
1114 18 011 3404/1114-18-011 110V DC Emergency Lighting Batt Charger/Dist Arrangement (BE) Eq. Supplier
1114 18 012 3404/1114-18-012 110V DC Emergency Lighting Battery Charger/Distribution Board Circuit Diagram (BE) Eq. Supplier
1114 18 013 3404/1114-18-013 220V DC Battery Layout Eq. Supplier
1114 18 014 3404/1114-18-014 110V DC Battery Layout Eq. Supplier

Drawing Class 20

Power Cables and Schedules

1114 20 001 3404/1114-20-001 Power cable layout within substation building PEC
1114 20 002 3404/1114-20-002 Power cable layout sections within substation building PEC
1114 20 003 3404/1114-20-003 Power cable layout & reservations within site boundary PEC
1114 20 004 3404/1114-20-004 132KV Power cable routes external to substation PEC
1114 20 005 3404/1114-20-005 Power cable schematic PEC
1114 20 006 3404/1114-20-006 Power cable layout within site boundary - sections PEC
1114 20 007 3404/1114-20-007 132KV Power cable schedule PEC
1114 20 008 3404/1114-20-008 33KV Power cable schedule PEC
1114 20 009 3404/1114-20-009 11KV Power cable schedule PEC
1114 20 010 3404/1114-20-010 415V AC Power cable schedule PEC
1114 20 011 3404/1114-20-011 220V/110V DC Power cable schedule PEC
1114 20 012 3404/1114-20-012 Earthing cable schedule PEC
1114 20 013 3404/1114-20-013 Power cable support structure details PEC
1114 20 014 3404/1114-20-014 Power cable support structure details PEC
1114 20 015 3404/1114-20-015 Power cable and accessories MTO PEC
1114 20 016 3404/1114-20-016 Proposed drum lengths for power cables PEC
1114 20 017 3404/1114-20-017 300 kV Power cable layout & reservations outside site boundary PEC
1114 20 018 3404/1114-20-018 300 kV Power cable layout outside site boundary - sections PEC
1114 20 019 3404/1114-20-019 300 kV Power cable layout & reservations within cable compound (OHL connection) PEC
1114 20 020 3404/1114-20-020 Power Cable Cleats and Accessories PEC

Drawing Class 21

Telemetry Equipment

1114 21 001 3404/1114-21-001 Telemetry Transfer Terminal Block Cabinets - 300kV General Arrangement Eq. Supplier
1114 21 002 3404/1114-21-002 Telemetry Transfer Terminal Block Cabinets - 132kV General Arrangement Eq. Supplier
1114 21 003 3404/1114-21-003 Telemetry Transfer Terminal Block Cabinets - 33kV General Arrangement Eq. Supplier
1114 21 004 3404/1114-21-004 Telemetry Transfer Terminal Block Cabinets - 11kV General Arrangement Eq. Supplier
1114 21 005 3404/1114-21-005 Telemetry Transfer Terminal Block Cabinets - 300kV Terminal Allocation Schedule Eq. Supplier
1114 21 006 3404/1114-21-006 Telemetry Transfer Terminal Block Cabinets - 132kV Terminal Allocation Schedule Eq. Supplier
1114 21 007 3404/1114-21-007 Telemetry Transfer Terminal Block Cabinets - 33kV Terminal Allocation Schedule Eq. Supplier
1114 21 008 3404/1114-21-008 Telemetry Transfer Terminal Block Cabinets - 11kV Terminal Allocation Schedule Eq. Supplier
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er

Drawing Class 22

Equipment Layouts

1114 22 001 3404/1114-22-001 Electrical Plot Plan PEC


1114 22 002 3404/1114-22-002 Equipment Layout - Sections PEC

Drawing Class 23

Internal/External earthing Layouts

1114 23 001 3404/1114-23-001 External Earthing Layout Substation Building Area PEC
1114 23 002 3404/1114-23-002 External Earthing Layout Outdoor Area PEC
1114 23 003 3404/1114-23-003 Internal Earthing Layout 132kV Switchgear Room PEC
1114 23 004 3404/1114-23-004 Internal Earthing Layout 300kV Switchgear Room (1/2) PEC
1114 23 005 3404/1114-23-005 Internal Earthing Layout 300kV Switchgear Room (2/2) PEC
1114 23 006 3404/1114-23-006 Internal Earthing Layout-Basements PEC
1114 23 007 3404/1114-23-007 Internal/External Earthing Layout Sections Sheet 1 PEC
1114 23 008 3404/1114-23-008 Internal/External Earthing Layout Sections Sheet 2 PEC
1114 23 009 3404/1114-23-009 Earthing Layout for Basement Power cable supports,GIBSupports & csble laadder rack PEC
1114 23 010 3404/1114-23-010 Earthing Layout - Roof Equipment PEC
1114 23 011 3404/1114-23-011 Arrangement of Earthing Potential Grid for Outdoor Equipment PEC
1114 23 012 3404/1114-23-012 Earthing Compression Terminal - Lugs for Stranded Copper Cables PEC
1114 23 013 3404/1114-23-013 Earthing System Installation Details PEC
1114 23 014 3404/1114-23-014 Earthing System Material Take Off PEC

Drawing Class 24

Single Line Diagrams

1114 24 001 3404/1114-24-001 300/132/11kV key line diagram PEC


1114 24 002 3404/1114-24-002 Single line diagrams drawing list PEC
1114 24 003 3404/1114-24-003 415V A.C. single line diagram PEC
1114 24 004 3404/1114-24-004 220/110V D.C. single line diagram PEC

Drawing Class 25

300/132kV Schematic Diagrams

1114 25 001 3404/1114-25-001 300kV O/H Line Feeder PEC


1114 25 002 3404/1114-25-002 300kV Under Ground Cable Schematic Diagram PEC
1114 25 003 3404/1114-25-003 300kV Bus Coupler Schematics PEC
1114 25 004 3404/1114-25-004 300kV Side - 300MVA Transformer Schematics PEC
1114 25 005 3404/1114-25-005 300kV Bus Section 1/3 Schematics PEC
1114 25 006 3404/1114-25-006 300kV Bus Section2/4 Schematics PEC
1114 25 007 3404/1114-25-007 300kV Synchronising and Station Alarm Panel Schematics PEC
1114 25 008 3404/1114-25-008 300kV Interlocking Schematics PEC
1114 25 009 3404/1114-25-009 300kV Bus voltage selection and Synchronising Schematic Diagram PEC
1114 25 010 3404/1114-25-010 300kV Synchronising Bus Wiring Schematic PEC
1114 25 011 3404/1114-25-011 300MVA Transformer OLTC Cable Connection Diagram PEC
1114 25 012 3404/1114-25-012 300kV Disturbance Recorder Panels Schematics PEC
1114 25 013 3404/1114-25-013 300MVA Transformer Differential Protection Schematic PEC
1114 25 014 3404/1114-25-014 300MVA Transformer Overall Interlocking Diagram PEC
1114 25 015 3404/1114-25-015 300kV Switchgear Gas Trip/Intertrip Schematic PEC
1115 25 016 3404/1114-25-016 300kV Busbar Protection Schematics PEC

1114 25 101 3404/1114-25-101 132kV Cable Feeder Schematics PEC


1114 25 102 3404/1114-25-102 132kV Side 300MVA Transformer Schematics PEC
103 3404/1114-25-103 132kV Side 30MVA Transformer Schematics PEC
1114 25 104 3404/1114-25-104 132kV Bus Coupler Schematics PEC
1114 25 105 3404/1114-25-105 132kV Bus Section 1/2 Schematics PEC
1114 25 106 3404/1114-25-106 132kV Bus Section 3/4 Schematics PEC
1114 25 107 3404/1114-25-107 132kV Synchronising and common Alarm Panel Schematics PEC
1114 25 108 3404/1114-25-108 132/33kV Interlocking Diagram PEC
1114 25 109 3404/1114-25-109 132kV Bus Voltage Selection Schematic Diagram PEC
1114 25 110 3404/1114-25-110 132kV Synchronising Bus Wiring Schematic PEC
1114 25 111 3404/1114-25-111 132kV Switchgear Gas Trip/Intertrip Schematic PEC
1115 25 112 3404/1114-25-112 132kV Busbar Protection Schematics PEC

1114 25 201 3404/1114-25-201 33kV Side 300 MVA Transformer Schematics PEC
1114 25 202 3404/1114-25-202 33kV Swgr Schematic Diagram PEC

1114 25 301 3404/1114-25-301 Schematic and Cable Diagram Symbol List PEC
1114 25 302 3404/1114-25-302 11kV Cable Feeder Schematic Diagram PEC
1114 25 303 3404/1114-25-303 11kV Side of 30MVA Transformer Schematic Diagram PEC
1114 25 304 3404/1114-25-304 11kV Bus Section Schematic Diagram PEC
1114 25 305 3404/1114-25-305 11kV Side of Auxiliary Transformer Schematic Diagram PEC
1114 25 306 3404/1114-25-306 11kV Arc Fault Protection Schematic PEC
1114 25 307 3404/1114-25-307 300/132/11kV Substation Ancillary Schematic Diagram PEC
1114 25 308 3404/1114-25-308 11kV Interlocking Schematic Diagram PEC
1114 25 309 3404/1114-25-309 11kV Transformer Tap Change Control Interconnection Schematic PEC
1114 25 310 3404/1114-25-310 Fire Alarms Interface Schematic / Interconnection Diagram PEC
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er

Drawing Class 26
1114 26 001 3404/1114-26-001 300kV Control Cable Schedule PEC
1114 26 002 3404/1114-26-002 300kV Cable Terminations Spare Feeder Bay 1 PEC
1114 26 003 3404/1114-26-003 300kV Cable Terminations 300MVA Transformer Bay 2 PEC
1114 26 004 3404/1114-26-004 300kV Cable Terminations OHL Feeder Bay 3 PEC
1114 26 005 3404/1114-26-005 300kV Cable Terminations OHL Feeder Bay 4 PEC
1114 26 006 3404/1114-26-006 300kV Cable Terminations 300MVA Transformer Bay 5 PEC
1114 26 007 3404/1114-26-007 300kV Cable Terminations Bus Coupler Bay 6 PEC
1114 26 008 3404/1114-26-008 300kV Cable Terminations Bus Section 1 Bay 7 PEC
1114 26 009 3404/1114-26-009 300kV Cable Terminations Bus Section 2 Bay 8 PEC
1114 26 010 3404/1114-26-010 300kV Cable Terminations 300MVA Transformer Bay 9 PEC
1114 26 011 3404/1114-26-011 300kV Cable Terminations OHL Feeder Bay 10 PEC
1114 26 012 3404/1114-26-012 300kV Cable Terminations OHL Feeder Bay 11 PEC
1114 26 013 3404/1114-26-013 300kV Cable Terminations 300MVA Transformer Bay 12 PEC
1114 26 014 3404/1114-26-014 300kV Cable Terminations U/G Cable Feeder Bay 13 PEC
1114 26 015 3404/1114-26-015 300kV Cable Terminations Busbar Protection Panels PEC
1114 26 016 3404/1114-26-016 300kV Cable Terminations Telemetry Equipment PEC
1114 26 017 3404/1114-26-017 300kV Cable Terminations Intertripping Cabinet PEC
1114 26 018 3404/1114-26-018 300kV Cable Terminations Disturbance Recorder PEC

1114 26 101 3404/1114-26-101 132kV Control Cable Schedule PEC


1114 26 102 3404/1114-26-102 132kV Cable Terminations Cable Feeder Bay 1 PEC
1114 26 103 3404/1114-26-103 132kV Cable Terminations Cable Feeder Bay 2 PEC
1114 26 104 3404/1114-26-104 132kV Cable Terminations Cable Feeder Bay 3 PEC
1114 26 105 3404/1114-26-105 132kV Cable Terminations Cable Feeder Bay 4 PEC
1114 26 106 3404/1114-26-106 132kV Cable Terminations 300MVA Transformer Bay 5 PEC
1114 26 107 3404/1114-26-107 132kV Cable Terminations 30MVA Transformer Bay 6 PEC
1114 26 108 3404/1114-26-108 132kV Cable Terminations Cable Feeder Bay 7 PEC
1114 26 109 3404/1114-26-109 132kV Cable Terminations Cable Feeder Bay 8 PEC
1114 26 110 3404/1114-26-110 132kV Cable Terminations 300MVA Transformer Bay 9 PEC
1114 26 111 3404/1114-26-111 132kV Cable Terminations Cable Feeder Bay 10 PEC
1114 26 112 3404/1114-26-112 132kV Cable Terminations Cable Feeder Bay 11 PEC
1114 26 113 3404/1114-26-113 132kV Cable Terminations Bus Coupler Bay 12 PEC
1114 26 114 3404/1114-26-114 132kV Cable Terminations Bus Section 1 Bay 13 PEC
1114 26 115 3404/1114-26-115 132kV Cable Terminations Bus Section 2 Bay 14 PEC
1114 26 116 3404/1114-26-116 132kV Cable Terminations Cable Feeder Bay 15 PEC
1114 26 117 3404/1114-26-117 132kV Cable Terminations Cable Feeder Bay 16 PEC
1114 26 118 3404/1114-26-118 132kV Cable Terminations 30MVA Transformer Bay 17 PEC
1114 26 119 3404/1114-26-119 132kV Cable Terminations 300MVA Transformer Bay 18 PEC
1114 26 120 3404/1114-26-120 132kV Cable Terminations Cable Feeder Bay 19 PEC
1114 26 121 3404/1114-26-121 132kV Cable Terminations Cable Feeder Bay 20 PEC
1114 26 122 3404/1114-26-122 132kV Cable Terminations 300MVA Transformer Bay 21 PEC
1114 26 123 3404/1114-26-123 132kV Cable Terminations 30MVA Transformer Bay 22 PEC
1114 26 124 3404/1114-26-124 132kV Cable Terminations Cable Feeder Bay 23 PEC
1114 26 125 3404/1114-26-125 132kV Cable Terminations Cable Feeder Bay 24 PEC
1114 26 126 3404/1114-26-126 132kV Cable Terminations Cable Feeder Bay 25 PEC
1114 26 127 3404/1114-26-127 132kV Cable Terminations Cable Feeder Bay 26 PEC
1114 26 128 3404/1114-26-128 132kV Cable Terminations Busbar Protection Panels PEC
1114 26 129 3404/1114-26-129 132kV Cable Terminations Telemetry Equipment PEC
1114 26 130 3404/1114-26-130 132kV Cable Terminations Intertripping Cabinet PEC
1114 26 131 3404/1114-26-131 Basement Cable Nodes Layout PEC
1114 26 132 3404/1114-26-132 Cable Routing Design PEC

3404/1114-26-201 33kV Control Cable Schedule


1114 26 201 3404/1114-26-202 33kV Switchgear Cable Terminations Bay 1 PEC
1114 26 202 3404/1114-26-203 33kV Switchgear Cable Terminations Bay 2 PEC
1114 26 203 3404/1114-26-204 33kV Switchgear Cable Terminations Bay 3 PEC
1114 26 204 3404/1114-26-205 33kV Switchgear Cable Terminations Bay 4 PEC
1114 26 205 3404/1114-26-206 33kV Cable Terminations Telemetry Equipment PEC

1114 26 301 3404/1114-26-301 11kV Control Cable Schedule PEC


1114 26 302 3404/1114-26-302 11kV Cable Terminations Cable Feeder Bay 01 PEC
1114 26 303 3404/1114-26-303 11kV Cable Terminations Cable Feeder Bay 02 PEC
1114 26 304 3404/1114-26-304 11kV Cable Terminations Cable Feeder Bay 03 PEC
1114 26 305 3404/1114-26-305 11kV Cable Terminations Cable Feeder Bay 04 PEC
1114 26 306 3404/1114-26-306 11kV Cable Terminations Cable Feeder Bay 05 PEC
1114 26 307 3404/1114-26-307 11kV Cable Terminations 30MVA Tr. 1 Bay 06 PEC
1114 26 308 3404/1114-26-308 11kV Cable Terminations Cable Feeder Bay 07 PEC
1114 26 309 3404/1114-26-309 11kV Cable Terminations Cable Feeder Bay 08 PEC
1114 26 310 3404/1114-26-310 11Kv Cable Terminations 750kVA Tr. 1 Bay 10 PEC
1114 26 311 3404/1114-26-311 11kV Cable Terminations Bus Coupler Bay 11 PEC
1114 26 312 3404/1114-26-312 11kV Cable Terminations Bus Section Bay 12 PEC
1114 26 313 3404/1114-26-313 11kV Cable Terminations 750kVA Tr. 2 Bay 13 PEC
1114 26 314 3404/1114-26-314 11kV Cable Terminations Cable Feeder Bay 14 PEC

1114 26 315 3404/1114-26-315 11kV Cable Terminations Cable Feeder Bay 15 PEC
1114 26 316 3404/1114-26-316 11kV Cable Terminations 30MVA TR. 2 Bay 16 PEC
1114 26 317 3404/1114-26-317 11kV Cable Terminations Cable Feeder Bay 17 PEC
1114 26 318 3404/1114-26-318 11kV Cable Terminations Cable Feeder Bay 18 PEC
1114 26 319 3404/1114-26-319 11kV Cable Terminations Cable Feeder Bay 19 PEC
1114 26 320 3404/1114-26-320 11kV Cable Terminations Cablle Feeder Bay 20 PEC
1114 26 321 3404/1114-26-321 11kV Cable Terminations Cable Feeder Bay 21 PEC
1114 26 322 3404/1114-26-322 11kV Cable Terminations 30MVA Tr. 3 Bay 22 PEC
1114 26 323 3404/1114-26-323 11kV Cable Terminations Cable Feeder Bay 23 PEC
1114 26 324 3404/1114-26-324 11kV Cable Terminations Cable Feeder Bay 24 PEC
1114 26 325 3404/1114-26-325 11kV Cable Terminations Cable Feeder Bay 25 PEC
1114 26 326 3404/1114-26-326 11kV Cable Terminations Telemetry Equipment PEC
1114 26 327 3404/1114-26-327 11kV Cable Terminations - Pilot Wire Marshalling Cabinet PEC
1114 26 328 3404/1114-26-328 Ancillary Control Cable Schedule PEC
1114 26 329 3404/1114-26-329 Cable Terminations Ancillary Equipment PEC
1114 26 330 3404/1114-26-330 Control Cable Drum Schedule PEC
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er

Drawing Class 28

Cable Ladder Rack Layouts

1114 28 001 3404/1114-28-001 300kV Control Cable Ladder Rack Layout PEC
1114 28 002 3404/1114-28-002 132kV Control Cable Ladder Rack Layout PEC
1114 28 003 3404/1114-28-003 132/11kV Basement Control Cable Ladder Rack Layout PEC
1114 28 004 3404/1114-28-004 300kV Trench Control Cable Ladder Rack Layout PEC
1114 28 005 3404/1114-28-005 132/300kV Control Cable Ladder Rack Layout PEC
1114 28 006 3404/1114-28-006 Control Cable Ladder Rack Layout Sections PEC
1114 28 007 3404/1114-28-007 Control Cable Ladder Rack Layout Sections PEC
1114 28 008 3404/1114-28-008 Control Cable Ladder Rack support structure details PEC
1114 28 009 3404/1114-28-009 300kV Cable Trench Control Cable Layout PEC
1114 28 010 3404/1114-28-010 132kV Basement Control Cable Layout PEC
1114 28 011 3404/1114-28-011 300kV Control Cable Route PEC
1114 28 012 3404/1114-28-012 132kV Control Cable Route PEC
1114 28 013 3404/1114-28-013 Control Cable Layout Rack Fill Sections PEC
1114 28 014 3404/1114-28-014 Layout of 415V Cables for 300 MVA Transformer Auxiliary Supplies PEC
1114 28 015 3404/1114-28-015 Basement Control Cable Layout - Node Sections PEC
1114 28 020 3404/1114-28-016 Basement Cable Nodes Layout PEC
1114 28 021 3404/1114-28-017 Cable Routing Design PEC

Drawing Class 30

1114 30 001 3404/1114-30-001 300/132/11kV S/S - Site Plan PEC

ment Civil General Arrangement (300 kV GIS Building)

1114 30 002 3404/1114-30-002 300kV Building Foundation Plan - sheet 1 of 2 PEC


1114 30 003 3404/1114-30-003 300kV Building Foundation Plan - sheet 2 of 2 PEC
1114 30 004 3404/1114-30-004 300kV Building Trench Wall Elevations PEC
1114 30 005 3404/1114-30-005 300kV Building Ground Floor Plan - sheet 1 of 2 PEC
1114 30 006 3404/1114-30-006 300kV Building Ground Floor Plan - sheet 2 of 2 PEC
1114 30 007 3404/1114-30-007 300kV Building Transformer Bays - General Arrangement PEC
1114 30 008 3404/1114-30-008 300kV Building Roof Plan - sheet 1 of 2 PEC
1114 30 009 3404/1114-30-009 300kV Building Roof Plan - sheet 2 of 2 PEC
1114 30 010 3404/1114-30-010 300kV Building Sections - 1 PEC
1114 30 011 3404/1114-30-011 300kV Building Sections - 2 PEC
1114 30 012 3404/1114-30-012 300kV Building Sectional Details PEC
1114 30 013 3404/1114-30-013 300kV Building Elevations - 1 PEC
1114 30 014 3404/1114-30-014 300kV Building Elevations - 2 PEC
1114 30 015 3404/1114-30-015 300kV Building Finishes Schedule CCC
1114 30 016 3404/1114-30-016 300kV Building Door Schedule CCC
1114 30 017 3404/1114-30-017 300kV Building Door Surround Details CCC
1114 30 018 3404/1114-30-018 300kV Building GIS room - O/H Crane Gantry Beam & Corbal Details CCC
1114 30 019 3404/1114-30-019 300kV Building Cable Corridor - O/H Crane Gantry Beam & Corbal Details CCC
1114 30 020 3404/1114-30-020 300kV Building Cable trench cover details PEC

Civil General Arrangement (132 kV GIS Building)

1114 30 031 3404/1114-30-031 132kV Building Foundation & Basement Plan - sheet 1 of 2 PEC
1114 30 032 3404/1114-30-032 132kV Building Foundation & Basement Plan - sheet 2 of 2 PEC
1114 30 033 3404/1114-30-033 132kV Building Basement Wall Elevations PEC
1114 30 034 3404/1114-30-034 132kV Building Ground Floor Plan - sheet 1 of 2 PEC
1114 30 035 3404/1114-30-035 132kV Building Ground Floor Plan - sheet 2 of 2 PEC
1114 30 036 3404/1114-30-036 132kV Building 30 MVA Transformer Bays - General Arrangement PEC
1114 30 037 3404/1114-30-037 132kV Building 45 MVA Reactors Bays - General Arrangement PEC
1114 30 038 3404/1114-30-038 132kV Building Roof Plan - sheet 1 of 2 PEC
1114 30 039 3404/1114-30-039 132kV Building Basement Stairs GA PEC
1114 30 040 3404/1114-30-040 132kV Building Sections 1 PEC
1114 30 041 3404/1114-30-041 132kV Building Sections 2 PEC
1114 30 042 3404/1114-30-042 132kV Building Sectional Details PEC
1114 30 043 3404/1114-30-043 132kV Building Elevations - 1 PEC
1114 30 044 3404/1114-30-044 132kV Building Elevations - 2 PEC
1114 30 045 3404/1114-30-045 132kV Building Finishes Schedule CCC
1114 30 046 3404/1114-30-046 132kV Building Door Schedule CCC
1114 30 047 3404/1114-30-047 132kV Building External Door Surround Details CCC
1114 30 048 3404/1114-30-048 132kV Building Internal Door Surround Details CCC
1114 30 049 3404/1114-30-049 132kV Building Basement Stairs GA CCC
1114 30 050 3404/1114-30-050 132kV Building O/H Crane Gantry Beam & Corbal Details CCC

GENERAL Drawings

1114 30 061 3404/1114-30-061 Civil Details - 1 CCC


1114 30 062 3404/1114-30-062 Civil Details - 2 CCC
1114 30 063 3404/1114-30-063 Roads - General Arrangement CCC
1114 30 064 3404/1114-30-064 Boundry Wall - General Arrangement CCC
1114 30 065 3404/1114-30-065 External Gate Details CCC
1114 30 066 3404/1114-30-066 External Works CCC
1114 30 067 3404/1114-30-067 External cable trenches - General Arrangement PEC
1114 30 068 3404/1114-30-068 Interconnecting cable duct banks - General Arrangement PEC
1114 30 069 3404/1114-30-069 OHL switchyard foundations - General Arrangement PEC
1114 30 070 3404/1114-30-070 Road Crossing Details CCC
1114 30 071 3404/1114-30-071 Retaining Walls CCC
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er
SKETCH Drawings (for site use only)

1114 SK 090 3404/1114-30-090 300kV Building GIS room - floor fixing details PEC
1114 SK 091 3404/1114-30-091 300kV Building CE supports - fixing details PEC
1114 SK 092 3404/1114-30-092 300kV Building GIB cover plate details PEC
1114 SK 093 3404/1114-30-093 300kV Building Cable Trench Walls - Unistrut Location Details PEC
1114 SK 094 3404/1114-30-094 132kV Building Basement Walls - Unistrut Location Details PEC
1114 SK 095 3404/1114-30-095 132kV Building Basement Ceiling - Unistrut Location Details PEC
1114 SK 096 3404/1114-30-096 300kV Building GIS room - floor screed details PEC
1114 SK 097 3404/1114-30-097 132kV Building GIS room - floor screed details PEC
1114 SK 098 3404/1114-30-098 132kV Building 33 kV SWG room - floor screed details PEC
1114 SK 099 3404/1114-30-099 132kV Building 11 kV SWG room - floor screed details PEC

RC
Drawings -
300 kV Drawing Class 31
Building

1114 31 101 3404/1114-31-101 -300kV Building Foundations - formwork details CCC


1114 31 102 3404/1114-31-102 - Foundations - R.C. Details CCC
1114 31 103 3404/1114-31-103 -300kV Building Cable trench walls - R C details CCC
1114 31 104 3404/1114-31-104 -300kV Building Ground Beams - R C details - sheet 1 of 2 CCC
1114 31 105 3404/1114-31-105 -300kV Building Ground Floor Slab - Formwork Details CCC
1114 31 106 3404/1114-31-106 -300kV Building Ground Floor Slab - Bottom Reinforcement Details - sheet 1 of 2 CCC
1114 31 107 3404/1114-31-107 -300kV Building Ground Floor Slab - Bottom Reinforcement Details - sheet 2 of 2 CCC
1114 31 108 3404/1114-31-108 -300kV Building Ground Floor Slab - Top Reinforcement Details - sheet 1 of 2 CCC
1114 31 109 3404/1114-31-109 -300kV Building Ground Floor Slab - Top Reinforcement Details - sheet 2 of 2 CCC
1114 31 110 3404/1114-31-110 -300kV Building Roof Slab - Formwork Details CCC
1114 31 111 3404/1114-31-111 -300kV Building Roof Slab - R C Details - sheet 1 of 2 CCC
1114 31 112 3404/1114-31-112 -300kV Building Roof Slab - R C Details - sheet 1 of 2 CCC
1114 31 113 3404/1114-31-113 - Columns - R C Details - sheet 1 of 2 CCC
1114 31 114 3404/1114-31-114 - Columns - R C Details - sheet 2 of 2 CCC
1114 31 115 3404/1114-31-115 -300kV Building Roof Beams - R C Details Sheet 1 CCC
1114 31 116 3404/1114-31-116 -300kV Building F/F room - Ground floor slab - formwork details CCC
1114 31 117 3404/1114-31-117 -300kV Building F/F room - Ground floor slab - R C details CCC
1114 31 118 3404/1114-31-118 -300kV Building F/F room - Ground beams / walls - R C details CCC
1114 31 119 3404/1114-31-119 -300kV Building F/F room - Roof slab - Formwork & R C details CCC
1114 31 120 3404/1114-31-120 -300kV Building Building External Stairs and Walls - R C Details CCC
1114 31 121 3404/1114-31-121 -300kV Building Transformer Bay Raft - Formwork & R C Details CCC
1114 31 122 3404/1114-31-122 - 300kV BuildingTransformer Bay Walls - Formwork & R C Details Sheet 1 CCC

RC Drawings - 132 kV Building

1114 31 131 3404/1114-31-131 132kV Building Basement Columns Axis CCC


1114 31 132 3404/1114-31-132 132kV Building Basement Raft 132kV Building Formwork Details CCC
1114 31 133 3404/1114-31-133 132kV Building Basement Raft 132kV Building R C Details 132kV Building sheet 1 of CCC
1114 31 134 3404/1114-31-134 132kV Building Basement Raft 132kV Building R C Details 132kV Building sheet 2 of CCC
1114 31 135 3404/1114-31-135 132kV Building Basement Walls 132kV Building R C Details 132kV Building sheet 1 of CCC
1114 31 136 3404/1114-31-136 132kV Building Basement Walls 132kV Building R C Details 132kV Building sheet 2 of CCC
1114 31 137 3404/1114-31-137 132kV Building Ground Floor Slab 132kV Building Formwork Details CCC
1114 31 138 3404/1114-31-138 132kV Building Ground Floor Slab 132kV Building Bottom Reinforcement Details 132kV CCC
1114 31 139 3404/1114-31-139 132kV Building Ground Floor Slab 132kV Building Bottom Reinforcement Details 132kV CCC
1114 31 140 3404/1114-31-140 132kV Building Ground Floor Slab 132kV Building Top Reinforcement Details 132kV Bu CCC
1114 31 141 3404/1114-31-141 132kV Building Ground Floor Slab 132kV Building Top Reinforcement Details 132kV Bu CCC
1114 31 142 3404/1114-31-142 132kV Building Ground Floor Beams 132kV Building R C Details 132kV Building Sheet CCC
1114 31 143 3404/1114-31-143 132kV Building Ground Floor Beams 132kV Building R C Details 132kV Building Sheet CCC
1114 31 144 3404/1114-31-144 132kV Building Ground Floor Beams 132kV Building R C Details 132kV Building Sheet CCC
1114 31 145 3404/1114-31-145 132kV Building Ground Floor Column Axis CCC
1114 31 146 3404/1114-31-146 132kV Building Columns 132kV Building R C Details Sheet 1 of 3 CCC
1114 31 147 3404/1114-31-147 132kV Building Columns 132kV Building R C Details Sheet 2 of 3 CCC
1114 31 148 3404/1114-31-148 132kV Building Columns 132kV Building R C Details Sheet 3 of 3 CCC
1114 31 149 3404/1114-31-149 132kV Building High Level Roof Slab 132kV Building Formwork Details CCC
1114 31 150 3404/1114-31-150 132kV Building High Level Roof Slab 132kV Building R C Details CCC
1114 31 151 3404/1114-31-151 132kV Building Low Level Roof Slab Formwork Details CCC
1114 31 152 3404/1114-31-152 132kV Building Low Level Roof Slab 132kV Building R C Details 132kV Building sheet CCC
1114 31 153 3404/1114-31-153 132kV Building Low Level Roof Slab 132kV Building R C Details 132kV Building sheet CCC
1114 31 154 3404/1114-31-154 132kV Building High Level Roof Beams 132kV Building R C Details Sheet 1 CCC
1114 31 155 3404/1114-31-155 132kV Building Low Level Roof Beams 132kV Building R C Details 132kV Building she CCC
1114 31 156 3404/1114-31-156 132kV Building Low Level Roof Beams 132kV Building R C Details 132kV Building she CCC
1114 31 157 3404/1114-31-157 132kV Building External Stairs and Walls 132kV BuildingR C Details CCC
1114 31 158 3404/1114-31-158 132kV Building Ventilation Housings 132kV Building R C Details CCC
1114 31 159 3404/1114-31-159 132kV Building F/F Room Floor Slab 132kV Building Formwork & R C Details CCC
1114 31 160 3404/1114-31-160 132kV Building Transformer Bay Raft 132kV Building Formwork & R C Details CCC
1114 31 161 3404/1114-31-161 132kV Building Transformer Bay Walls 132kV Building Formwork & R C Details Sheet CCC
1114 31 162 3404/1114-31-162 132kV Building Reactor Bay Raft 132kV Building Formwork & R C Details CCC
1114 31 163 3404/1114-31-163 132kV Building Reactor Bay Walls 132kV Building Formwork & R C Details Sheet 1 CCC

R C Drawings - GENERAL

1114 31 170 3404/1114-31-170 Guard House - G A & R C Details CCC


1114 31 171 3404/1114-31-171 300 MVA transf. Oil Drain Tank - G A & R C Details CCC
1114 31 172 3404/1114-31-172 30 MVA transf. Oil Drain Tank - G A & R C Details CCC
1114 31 173 3404/1114-31-173 45 MVA Reactor Oil Drain Tank - G A & R C Details CCC
1114 31 174 3404/1114-31-174 Septic Tank & Soakaway - G A & R.C Details CCC
1114 31 175 3404/1114-31-175 Reserve Water Foundation - G A & R.C Details CCC
1114 31 176 3404/1114-31-176 Boundary Wall - R C Details CCC
1114 31 177 3404/1114-31-177 External cable Trenches & Covers - R C details CCC
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er

Drawing Class 32

Steelwork Details

1114 32 181 3404/1114-32-181 300kV BuildingTransformer Sunshade - Structural Details CCC


1114 32 182 3404/1114-32-182 132kV Building Transformer / Reactor Sunshade - Structural Details CCC

Drawing Class 35

Cranes

Drawing Class 36

Lighting and Small Power

1114 36 301 3404/1114-36-301 300kV Building Ground Floor Emergency & Exit Lights CCC
1114 36 302 3404/1114-36-302 300kV Building Ground Electrical Installation Plan CCC
1114 36 303 3404/1114-36-303 300kV Building Schedule of Points DB - 5(Ground Floor) CCC
1114 36 304 3404/1114-36-304 132kV BuildingBasement Electrical Installation Plan CCC
1114 36 305 3404/1114-36-305 132kV Building Ground Electrical Installation Plan CCC
1114 36 306 3404/1114-36-306 132kV Building Basement Emergency & Exit Lights CCC
1114 36 307 3404/1114-36-307 132kV BuildingGround Floor Emergency & Exit Lights CCC
1114 36 308 3404/1114-36-308 132kV BuildingGuardhouse Electrical Installation CCC
1114 36 309 3404/1114-36-309 132kV BuildingExternal Lighting CCC
1114 36 310 3404/1114-36-310 132kV Building Details of Lighting Pole Bracket & Foundation CCC
1114 36 311 3404/1114-36-311 132kV BuildingSchedule of Points DB - 1(Basement) CCC
1114 36 312 3404/1114-36-312 132kV BuildingSchedule of Points DB - 2(Ground Floor) CCC
1114 36 313 3404/1114-36-313 132kV Building- Schedule of Points DB - 3(Ground Floor) CCC
1114 36 314 3404/1114-36-314 132kV Building- Schedule of Points DB - 4 (External Lighting) CCC
1114 36 315 3404/1114-36-315 132kV Building Schedule of Points DB - 6 (Guard House) CCC
1114 36 316 3404/1114-36-316 132kV Building - Schedule of Points EDB (Emergency Lighting) CCC
1114 36 317 3404/1114-36-317 132kV Building A/C DB Schematic Diagram CCC
1114 36 318 3404/1114-36-318 132kV Building Schematic Diagram - Ventilation System sheet 1 of 3 CCC
1114 36 319 3404/1114-36-319 132kV Building Schematic Diagram - Ventilation System sheet 2 of 3 CCC
1114 36 320 3404/1114-36-320 132kV Building Schematic Diagram - Ventilation System sheet 3 of 3 CCC
1114 36 321 3404/1114-36-321 132kV Building Door Panel of Ventilation D.B CCC
1114 36 322 3404/1114-36-322 132kV Building Arrangement of Equipment Vent D.B CCC
1114 36 323 3404/1114-36-323 132kV Building Ventilation System Distribution Board - sheet 1 of 2 CCC
1114 36 324 3404/1114-36-324 132kV Building Ventilation System Distribution Board - sheet 2 of 2 CCC
1114 36 325 3404/1114-36-325 300kV Building - Electrical Schematic Diagram of LT Board - sheet 1 of 3 CCC
1114 36 326 3404/1114-36-326 300kV Building - Electrical Schematic Diagram of LT Board - sheet 2 of 3 CCC
1114 36 327 3404/1114-36-327 300kV Building - Electrical Schematic Diagram of LT Board - sheet 3 of 3 CCC
1114 36 328 3404/1114-36-328 300kV Building - Electrical Installation Works Design File & Drawings CCC

Drawing Class 37

HVAC HVAC

1114 37 201 3404/1114-37-201 132kV Building - HVAC Layout Basement Floor CCC
1114 37 202 3404/1114-37-202 132kV Building - HVAC Layout Ground Floor CCC

Drawing Class 38

Fire Fighting

1114 38 401 3404/1114-38-401 Water Spray System Complete Data Sheets minimax
1114 38 402 3404/1114-38-402 Water Fire Fighting System P & I Diagram minimax
1114 38 403 3404/1114-38-403 Fire Fighting Room Equipment Layout minimax
1114 38 404 3404/1114-38-404 Fire Fighting Room Foundation Plan minimax
1114 38 405 3404/1114-38-405 Water Spray System at 300 MVA Transformers Piping Arrangement minimax
1114 38 406 3404/1114-38-406 Water Spray System at 45 MVAr Reactors Piping Arrangement minimax
1114 38 407 3404/1114-38-407 Water Spray System at 30 MVA Transformers Piping Arrangement minimax
1114 38 408 3404/1114-38-408 Arrangement of Reserve Water Tank Site Plan minimax
1114 38 409 3404/1114-38-409 Fire Fighting System Deluge Valve Station DN100 minimax
1114 38 410 3404/1114-38-410 Complete Data Sheets of Dry Powder Extinguishing System minimax
1114 38 411 3404/1114-38-411 Complete Data Sheets of Portable Fire Extinguisher minimax
1114 38 412 3404/1114-38-412 Arrangement of Portable Fire Extinguisher minimax
1114 38 413 3404/1114-38-413 Complete Data Sheets of Cable Protection and Penetration Seals minimax
1114 38 414 3404/1114-38-414 Fire Alarm System Complete Data Sheets minimax
1114 38 415 3404/1114-38-415 Fire Alarm System Single Line Diagram minimax
1114 38 416 3404/1114-38-416 Layout of Detectors & Conduits Basement Ceiling minimax
1114 38 417 3404/1114-38-417 Layout of Detectors & Conduits Ground Floor Ceiling minimax
1114 38 418 3404/1114-38-418 Water Spray System Layout of Conduits minimax
1114 38 419 3404/1114-38-419 Fire Alarm Panel General Layout minimax
1114 38 420 3404/1114-38-420 Fire Alarm Panel Wiring Diagram minimax
1114 38 421 3404/1114-38-421 Fire Alarm Panel Terminal List minimax
1114 38 422 3404/1114-38-422 Fire Alarm system Cable List minimax
1114 38 423 3404/1114-38-423 Controlling Water Spray System Wiring Diagram minimax
1114 38 424 3404/1114-38-424 Controlling Water Spray System Terminal List minimax
1114 38 425 3404/1114-38-425 Water Spray System Cable List minimax
Fire Alarm System Connection Diagram of Heat Detectors & Response Indicators in
1114 38 426 3404/1114-38-426 220kV Battery Charger& D.B.Board-Trip & Control minimax
1114 38 427 3404/1114-38-427 Fire Alarm System Connection Diagram of Heat Detectors & Response Indicators in 110V & 48V Battery Charger minimax
1114 38 428 3404/1114-38-428 Fire Fighting Design File & Drawings - vol 1 Mechanical minimax
1114 38 429 3404/1114-38-429 Fire Fighting Design File & Drawings - vol 2 Electrical minimax

Drawing Class 39

Building Licence

1114 39 001 3404/1114-39-001 300/132/11kV S/S - Site Plan CCC


1114 39 002 3404/1114-39-002 300kV Building Foundation Plan CCC
1114 39 003 3404/1114-39-003 300kV Building Ground Floor Plan CCC
1114 39 004 3404/1114-39-004 300kV Building Sections CCC
1114 39 005 3404/1114-39-005 300kV Building Elevations CCC
1114 39 006 3404/1114-39-006 132kV Building- Foundation and Basement Plan CCC
1114 39 007 3404/1114-39-007 132kV Building Ground Floor Plan CCC
1114 39 008 3404/1114-39-008 132kV Building Sections CCC
1114 39 009 3404/1114-39-009 132kV Building Elevations CCC
1114 300/132/11kV Qurain 'W' Substation
Project
Equipment Series_
_Numb Client_Drg_No Drg_Title Originator
_Class Number
er
1114 39 010 3404/1114-39-010 132kV Building Basement - Ventilation Calculations CCC
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

DRAWINGS CLASS 01 - [DESIGN BRIEFS]

1114-01-001 Design Brief for Protection Relay, Inst. & Metering PEC 40 10 50 70 85 95 100 40
1114-01-002 300/kV CT and VT Design Brief PEC 40 10 50 70 85 95 100 40
1114-01-003 132/33kV CT and VT Design Brief PEC 40 10 50 70 85 95 100 40
1114-01-004 11kV& 415V CT and VT Design Brief PEC 40 10 50 70 85 95 100 40
1114-01-005 Design Brief for Earthing System PEC 40 10 50 70 85 95 100 40
1114-01-006 Design brief for 300kV oil filled cables and accessories PEC 30 10 50 70 21
1114-01-007 300kV oil filled cables Factory Test Procedure PEC 10 10 50 70 85 95 100 10
Design Brief for Calculation of Battery and Battery Charger Capacities for
1114-01-008 220/110V DC Systems PEC 40 10 50 70 85 95 100 40
1114-01-009 Design Brief for Intertrip Equipment PEC 10 10 50 70 85 95 100 10
1114-01-010 Protection Relay Settings PEC 80 10 50 40
1114-01-011 Design Brief for 11kV, 3kV and 1kV XLPE Cables PEC 10 10 50 70 85 95 100 10
1114-01-012 Design Brief for 132kV and 33kV XLPE Cables PEC 10 10 50 70 85 95 100 10
1114-01-013 Design Brief for LV power, control and pilot cables PEC 10 10 50 70 85 95 100 10
1114-01-014 132kV oil filled cables hydrallic design PEC 10 10 50 70 7
1114-01-015 300kV oil filled cables - continuous current rating calculation PEC 10 10 50 70 85 95 100 10
1114-01-016 Design Brief for 33kV Switchgear and RC Surge Suppressor PEC 10 10 50 70 85 95 100 10
1114-01-017 Test&Acceptance
Factory test Procedurefor
Inspection Schedule forfire
132kV and and
Fighting 33kVFire
XLPE cables
Alarm PEC 10 10 50 70 85 95 100 10
1114-01-020 equipment PEC 10 10 50 70 85 95 100 10
1114-01-600 General Technical Specification
Specification for Control Equipment Associated with Switchgear, PEC 10 10 50 70 85 95 100 10
1114-01-601 Control and Relay Panels PEC 10 10 50 70 85 95 100 10
1114-01-602 Paint Specification PEC 10 10 50 70 85 95 100 10
1114-01-603 General Specification for Supply of Equipment PEC 10 10 50 70 85 95 100 10
1114-01-604 Specification for Cabling and Ferruling Identification Scheme PEC 10 10 50 70 85 95 100 10
1114-01-605 Specification for 11kV Switchgear PEC 0 10 50 70 85 95 100 0
1114-01-606 Specification for DC System PEC 10 10 50 70 85 95 100 10
1114-01-607 Specification for 33kV, 11kV and 3kV
300/132/33/11kV Power Cables
Telemetry Transfer Terminal Block PEC 10 10 50 70 85 95 100 10
1114-01-608 Cabinets PEC 10 10 50 70 85 95 100 10
1114-01-609 Specification for Control Cables PEC 10 10 50 70 85 95 100 10
1114-01-610 Factory Acceptance Test procedure PEC 10 10 50 70 85 95 100 10
1114-01-611 Specification for 415V LVAC Distribution Board PEC 10 10 50 70 85 95 100 10
1114-01-612 Specification for 11kV Pilot Wire Marshalling Cabinet PEC 10 10 50 70 85 95 100 10
1114-01-613 Drawing and Document Submission Procedure PEC 10 10 50 70 85 95 100 10
1114-01-615 Specification for 300 kV Oil Filled Cables & Accessories PEC 10 10 50 70 85 95 100 10
1114-01-616 Specification for 132 kV Oil Filled Cables & Accessories PEC 10 10 50 70 85 95 100 10
1114-01-617 Specification for 750 kVA Transformers PEC 10 10 50 70 85 95 100 10
1114-01-618 Specification for Neutral Earthing Resistor PEC 10 10 50 70 85 95 100 10
1114-01-619 Specification for Neutral Earthing Changeover Switch PEC 10 10 50 70 85 95 100 10
1114-01-620 Specification for Control and Relay panels PEC 10 10 50 70 85 95 100 10

Total allocated hours = 640


Total Earned hours = 588
Percentage Complete = 0.92
No of Documents= 0.00

Start = 10% Check=50%


Issue = 70% 763687361.xls 15 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

DRAWING CLASS 05 ( 300kV GIS)

1114-05-001 Layout of 300kV GIS TDTSC(ITAMI) 20 10 50 70 85 17


1114-05-002 Foundation of 300kV GIS TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-003 Gas System for 300kV GIS TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-004 Outline Feeder TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-005 OutlineTransformer Feeder TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-006 Outline Bus Section TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-007 Outline Bus Coupler TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-008 Transformer Neutral Point Lighting Arrestor & Isolator Outline TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-009 Internal Details of Circuit Breaker TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-010 Internal Details of Isolator TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-011 Internal Details of Isolator and Earthing Switch TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-012 Internal Details of Isolator and Fault Making Earthing Switch TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-013 Cable Connection of 300kV GIS TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-014 Testing Bushing Arrangement for 300kV Power Cables TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-015 Testing Bushing Arrangement for GIS TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-016 Opreating Mechanism Housing For CB TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-017 Outline of Operating Mechanism for Bus Selector DS TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-018 Outline of Operating Mechanism for ES and Line DS TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-019 Outline of Operating
Motor DrivenMechanism for Fault Mechanism
Spring Operating Making Earth
forSwitch
Neutral Point Earth TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-020 Switch TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-021 Outline of Manual Operating Mechanism for VT Isolator TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-022 Outline of GAS Monitoring Module TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-023 Name Plate for Gas Circuit Breaker TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-024 Name Plate for Isolator TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-025 Name Plate for Earthing Switch TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-026 Name Plate for Fault Making Earthing Switch TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-027 Name Plate for Voltage Transformer TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-028 Name Plate for Current Transformer TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-029 Line Feeder Nameplate (Fault Indication Details) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-030 Transformer Nameplate (Fault Indication Details) TDTSC(ITAMI) 2 10 50 70 85 1.7
1114-05-031 Bus Section Nameplate (Fault Indication Details) TDTSC(ITAMI) 2 10 50 70 85 1.7
1114-05-032 Bus Coupler Nameplate (Fault Indication Details) TDTSC(ITAMI) 2 10 50 70 85 1.7
1114-05-033 Out line of Local Control Panel Line Feeder TDTSC(ITAMI) 2 10 50 70 85 1.7
1114-05-034 Out line of Local Control PanelTransformer Feeder TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-035 Out line of Local Control Panel Bus Section TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-036 Out line of Local Control Panel Bus Coupler TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-037 Inside arrangement of Local Control Panel Line Feeder TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-038 Inside arrangement of Local Control PanelTransformer Feeder TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-039 Inside arrangement of Local Control Panel Bus Section TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-040 Inside arrangement of Local Control Panel Bus Coupler TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-041 Line Feder - Wiring Diagram of 300kV Local Control Panel TDTSC(ITAMI) 5 10 50 70 3.5
1114-05-042 Transformer Feeder - Wiring Diagram of 300kV Local Control Panel TDTSC(ITAMI) 5 10 50 70 3.5
1114-05-043 Bus Section - Wiring Diagram of 300kV Local Control Panel TDTSC(ITAMI) 5 10 50 70 3.5
1114-05-044 Bus Coupler - Wiring Diagram of 300kV Local Control Panel TDTSC(ITAMI) 5 10 50 70 3.5
1114-05-045 Connection Between GIS and Transformer(HV) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-046 Connection Between GIS and Transformer(Neutral) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-047 Name Plate for Isolator TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-048 Name plate for current Transformer (2) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-049 Name plate for current Transformer (3) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-050 Name plate for current Transformer (4) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-051 Name plate for current Transformer (5) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-052 Name plate for current Transformer (6) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-053 Name plate for current Transformer (7) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-054 Name plate for current Transformer (8) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-055 Name plate for current Transformer (9) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-056 Outline of VT TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-057 HV-DC Test Bushing Arrangement for 300kV Power Cable (2) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-058 Outlone of Bus Section 2 TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-059 Outline of Surge Arrestor TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-05-060 Name Plate of Surge arrestor TDTSC(ITAMI) 5 10 50 70 85 4.25

Start = 10% Check=50%


Issue = 70% 763687361.xls 16 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

1114-05-061 H1T0660 Single Line of 300kv TDTSC(ITAMI) 5 10 50 70 85 95 100 5


1114-05-062 H31L528 Schematic Diagram of motor driv mechanism: Type MDC TDTSC(ITAMI) 5 10 50 70 85 95 100 5
1114-05-063 H31L527 Schematic Diagram of motor driv mechanism: Type MDC TDTSC(ITAMI) 5 10 50 70 85 95 100 5
1114-05-064 H1S8395 SHEMATIC DIAGRAM OF GCB TDTSC(ITAMI) 5 10 50 70 85 95 100 5
1114-05-065 H2X5736 WIRING DIAGRAM OF GCB TDTSC(ITAMI) 5 10 50 70 85 95 100 5
1114-05-066 H31L610 WIRING DIAGRAM OF MOTOR DRIVE MECHANISM
CHARGED : TYPE MDC
SPRING DRIVE TDTSC(ITAMI) 5 10 50 70 85 95 100 5
1114-05-067 H31L608 MECHANISM
WIRING DIAGRAM : TYPE
OFMBE-05M
MOTOR (FOR OUTPUT
CHARGED SHAFT
SPRING OF LEFT SIDE)
DRIVE TDTSC(ITAMI) 5 10 50 70 85 95 100 5
1114-05-068 H31L609 MECHANISM : TYPE MBE-05M (FOR OUTPUT SHAFT OF RIGHT SIDE) TDTSC(ITAMI) 5 10 50 70 85 95 100 5
1114-05-069 300kV GIS Routine Test Procedure TDTSC(ITAMI) 5 10 50 70 85 4.25

Total allocated hours = 348


Total Earned hours = 298.8
Percentage Complete = 0.86

DRAWING CLASS 07 ( 132kV GIS)

1114-07-001 Layout of 132kV GIS TDTSC(ITAMI) 20 10 50 70 85 17


1114-07-002 Foundation of 132kV GIS TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-003 Outline of Line Feeder Unit TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-004 Cross Section of Line Feeder Unit TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-005 Outline of Transformer Feeder Unit (1) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-006 Cross Section of Transformer Feeder Unit(1) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-007 Outline of Transformer Feeder Unit (2) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-008 Cross Section of Transformer Feeder Unit(2) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-009 Outline of Bus Section Unit TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-010 Cross Section of Bus Section Unit TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-011 Outline of Bus Coupler Unit TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-012 Cross Section of Bus Coupler Unit TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-013 Cable Connection of 132kV GIS (1) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-014 Cable Connection of 132kV GIS (2) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-015 Outline of Voltage Transformer with Isolating Device TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-016 Outline of Motor Operating Mechanism for DS and ES TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-017 Outline of Motor Operating Mechanism for DS TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-018 Outline of Motor Charged Spring Operating Mechanism for FES TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-019 Outline of Manual Operating Mechanism for VT Isolator TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-020 Nameplate for Gas Circuit Breaker TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-021 Nameplate for Isolator / Earthing Switch TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-022 Nameplate for Isolator Switch TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-023 Nameplate for Fault Making Earthing Switch TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-024 Nameplate for Voltage Transformer TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-025 Gas System Scheme TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-026 Nameplate for Current Transformer TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-027 Nameplate (Fault Indication Detail) Line Feeder TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-028 Nameplate (Fault Indication Detail) Transformer Feeder (1) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-029 Nameplate (Fault Indication Detail) Transformer Feeder (2) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-030 Nameplate (Fault Indication Detail) Bus Section TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-031 Nameplate (Fault Indication Detail) Bus Coupler TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-032 Outline of Local Control Panel Line Feeder TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-033 Outline of Local Control Panel Transformer Feeder (1) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-034 Outline of Local Control Panel Transformer Feeder (2) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-035 Outline of Local Control Panel Bus Section TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-036 Outline of Local Control Panel Bus Coupler TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-037 Inside Arrangement of Local Control Panel Line Feeder TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-038 Inside Arrangement of Local Control Panel Transformer Feeder (1) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-039 Inside Arrangement of Local Control Panel Transformer Feeder (2) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-040 Inside Arrangement of Local Control Panel Bus Section TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-041 Inside Arrangement of Local Control Panel Bus Coupler TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-042 Voltmeter for Feeder Voltage Transformer TDTSC(ITAMI) 5 10 50 70 85 4.25

Start = 10% Check=50%


Issue = 70% 763687361.xls 17 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

1114-07-043 Wiring Diagram of Local Control Panel For Line Feeder TDTSC(ITAMI) 5 10 50 2.5
1114-07-044 Wiring Diagram of Local Control Panel For Transformer Feeder(1) TDTSC(ITAMI) 5 10 50 2.5
1114-07-045 Wiring Diagram of Local Control Panel For Transformer Feeder(2) TDTSC(ITAMI) 5 10 50 2.5
1114-07-046 Wiring Diagram of Local Control Panel For Bus Section TDTSC(ITAMI) 5 10 50 2.5
1114-07-047 Wiring Diagram of Local Control Panel For Bus Coupler TDTSC(ITAMI) 5 10 50 2.5
1114-07-048 Construction of Rupture Disc TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-049 Ladder with Wheels TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-050 Bottle of SF6 Gas TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-051 Pneumatic Rubber Maintenance Truck TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-052 SF6 Gas Service Set TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-053 HVAC Test Arrangement of GIS TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-054 HV - DC Test Arrangement of Power Cable TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-055 H2Z5006 HV-DC Test arrangement of Power Cable (2) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-056 H2Z5251 Outline of Bus Section Unit(2) TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-057 H1T0612 Single line Diagram TDTSC(ITAMI) 5 10 50 70 85 4.25
1114-07-058 Factory test procedure for 132KV GIS TDTSC(ITAMI) 5 10 50 70 3.5

Total allocated hours = 305


Total Earned hours = 249.75
Percentage Complete = 0.82

Start = 10% Check=50%


Issue = 70% 763687361.xls 18 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

DRAWING CLASS 09( 33kV SWITCHGEAR)

1114-09-001 Arrangement AL-AHLIEA 5 10 50 70 85 4.25 25-Jul


1114-09-002 Sectional View AL-AHLIEA 5 10 50 70 85 4.25 25-Jul

Total allocated hours = 10


Total Earned hours = 8.5
Percentage Complete = 0.85

DRAWING CLASS 11 ( 11kV SWITCHGEAR)

1114-11-001 11kV Switchgear General Arrangement AL-AHLIEA 80 10 50 70 85 68


1114-11-002 11kV Switchgear SLD AL-AHLIEA 80 10 50 70 85 68
1114-11-003 11kV Switchgear Double Bus Bar AL-AHLIEA 80 10 50 70 85 68

Total allocated hours = 240


Total Earned hours = 204
Percentage Complete = 0.85

DRAWING CLASS 12 ( 300MVA & 30MVA TRANSFORMERS & 45MVAr SHUNT REACTOR)

300 MVA TRANSFORMER


1114-12-001 300MVA 300/132/33kV Transformer Outline Drawing TDTSC (AKO) 30 10 50 70 85 25.5
1114-12-002 300MVA 300/132/33kV Transformer Rating Plate TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-003 300MVA 300/132/33kV Transformer Aux Circuit Wiring Diagram TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-004 300MVA 300/132/33kV Transformer Foundation Drawing TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-005 300MVA 300/132/33kV Transformer Shipping Sketch TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-006 300MVA 300/132/33kV Transformer HV Line Bushing Outline TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-007 300MVA 300/132/33kV Transformer LV Line & Neutral Bushing Outline TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-008 300MVA 300/132/33kV Transformer 33kV TW Bushing Outline TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-009 300MVA 300/132/33kV Transformer HV Side GIB Connection TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-010 300MVA 300/132/33kV Transformer LV Cable Connection Box TDTSC (AKO) 5 10 50 71 85 4.25
1114-12-011 300MVA 300/132/33kV Transformer 33kV TW Cable Box TDTSC (AKO) 5 10 50 72 85 3.25
1114-12-012 300MVA 300/132/33kV Transformer Earthing Terminal TDTSC (AKO) 5 10 50 73 85 3.25
1114-12-013 300MVA 300/132/33kV Transformer Valve Location & Function Plate TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-014 300MVA 300/132/33kV Transformer Filter Breather for Main Tank Conservato TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-015 300MVA 300/132/33kV Transformer Filter Breather for Tap Changer Conserv TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-016 300MVA 300/132/33kV Transformer Butterfly Valve TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-017 300MVA Transformer Marshalling Kiosk TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-018 Assembly Diagram of Transformer Marshalling Kiosk TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-019 300MVA 300/132/33kV Transformer Oil Temperature Indicator TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-020 300MVA 300/132/33kV Transformer Winding Temperature Indicator TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-021 Connection Diagram of Transformer Marshalling Kiosk TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-022 Factory Test and Inspection Procedure TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-023 Site Test Procedure and Report 300MVA Transformer Load-Tap-Changing TDTSC (AKO) 5 10 50 70 85 95 100 5
1114-12-024 Description of Valve Arrangement TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-025 Lifting and Pulling Dimensions of Main Tank TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-026 Outline of Pressure Relief Device TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-027 Outline Drawing of LTC Protective Relay TDTSC (AKO) 5 10 50 70 85 4.25

45 MVAr SHUNT REACTOR 0


1114-12-050 Shunt Reactor Outline TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-051 Protective Device Connection Diagram TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-052 Connection Detail of Radiator TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-053 Shipping Sketch TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-054 Rating Plate TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-055 Foundation Drawing TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-056 Line & Neutral Bushing Outline TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-057 Valve Location & Function Plate TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-059 33kV line cable box TDTSC (AKO) 5 10 50 70 85 4.25

Start = 10% Check=50%


Issue = 70% 763687361.xls 19 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

1114-12-061 Factory Test and Inspection procedure for 45MVAR Shunt Reactor TDTSC (AKO) 15 10 50 70 85 12.75

30 MVA TRANSFORMER
1114-12-100 30MVA 132/11.5kV Transformer Outline Drawing TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-101 30MVA 132/11.5kV Transformer Rating Plate TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-102 30MVA 132/11.5kV Transformer Aux Circuit Wiring Diagram TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-103 30MVA 132/11.5kV Transformer Foundation Drawing TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-104 30MVA 132/11.5kV Transformer Shipping Sketch TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-105 30MVA 132/11.5kV Transformer HV Line Bushing Outline TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-106 30MVA 132/11.5kV Transformer LV Line & Neutral Bushing Outline TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-107 30MVA 132/11.5kV Transformer HV Cable Box TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-108 30MVA 132/11.5kV Transformer LV Cable Connection Box TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-109 30MVA 132/11.5kV Transformer Earthing Terminal TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-110 30MVA 132/11.5kV Transformer Valve TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-111 30MVA 132/11.5kV Transformer Filter Breather for Main Tank Conservator TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-112 30MVA 132/11.5kV Transformer Filter Breather for Tap Changer Conservator TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-113 30MVA 132/11.5kV Transformer Butterfly Valve TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-114 30MVA Transformer Marshalling Kiosk TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-115 Assembly Diagram of Transformer Marshalling Kiosk TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-116 30MVA 132/11.5kV Transformer Oil Temperature Indicator TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-117 30MVA 132/11.5kV Transformer Winding Temperature Indicator TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-118 Connection Diagram of Transformer Marshalling Kiosk TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-119 Factory Test and Inspection Procedure TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-120 Site Test Procedure and Report 30MVA Transformer Load-Tap-Changing TDTSC (AKO) 5 10 50 70 85 95 100 5
1114-12-122 Lifting and Pulling Dimensions of Main Tank TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-123 Outline of Pressure Relief Device TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-124 Outline Drawing of LTC Protective Relay TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-125 Outline of Buchholz Relay TDTSC (AKO) 5 10 50 70 85 4.25
1114-12-126 General Valve Arrangement of Transformer TDTSC (AKO) 5 10 50 70 85 4.25

Total allocated hours = 350


Total Earned hours = 297
Percentage Complete = 0.85

DRAWING CLASS 13 (11/0/415kV, 750kVA TRANSFORMER)

1114-13-001 Outline Drawing OCREV 10 10 50 70 85 8.5


1114-13-005 HV Cable Box OCREV 10 10 50 70 85 8.5
1114-13-006 LV Cable Box OCREV 10 10 50 70 85 8.5
1114-13-009 Rating Plate OCREV 10 10 50 70 85 8.5
1114-13-010 Wiring Diagram OCREV 10 10 50 70 85 8.5
1114-13-011 Factory Test Procedure for 750KVA Auxiliary Transformer OCREV 10 10 50 70 85 8.5

Total allocated hours = 60


Total Earned hours = 51
Percentage Complete = 0.85

DRAWINGS CLASS 14 ( NER & CHANGE OVER SWITCH)

1114-14-001 11kV, 8 Ohm's NER and COS -General Arrangement NER Supplier 5 10 50 70 85 4.25
1114-14-002 11kV Neutral COS - General Arrangement NER Supplier 5 10 50 70 85 4.25
1114-14-003 11kV, 8 Ohm's NER - General Arrangement NER Supplier 5 10 50 70 85 4.25

Total allocated hours = 15


Total Earned hours = 12.75
Percentage Complete = 0.85

DRAWINGS CLASS 15 - [CONTROL PANELS]

Start = 10% Check=50%


Issue = 70% 763687361.xls 20 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

1114-15-001 45MVAr Shunt Reactor Control & Relay Panel GA Drawings AL-AHLIEA 25 10 50 70 85 21.25
1114-15-002 300kV Control Panel GA Drawings AL-AHLIEA 25 10 50 70 85 21.25
1114-15-003 132kV Control Panel GA Drawings AL-AHLIEA 25 10 50 70 85 21.25
General arrangement of Transformer tap change control panel for three(3)
1114-15-004 30MVA transformer AL-AHLIEA 25 10 50 70 85 21.25
1114-15-005 300kV Disturbance Recorder Panel AL-AHLIEA 25 10 50 70 85 21.25
General arrangement of Transformer tap change control panel for four(4)
1114-15-006 AL-AHLIEA 25 10 50
300MVA transformer 70 85 21.25
1114-15-050 General arrangement of 11KV Control & Relay Panel AL-AHLIEA 25 10 50 70 85 21.25
1114-15-101 General arrangement of 11KV pilot marshalling cabinet. AL-AHLIEA 25 10 50 70 85 21.25
1114-15-102 General arrangement of 132KV pilot marshalling cabinet. AL-AHLIEA 25 10 50 70 85 21.25

Total allocated hours = 225


Total Earned hours = 191.25
Percentage Complete = 0.85

Start = 10% Check=50%


Issue = 70% 763687361.xls 21 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

DRAWINGS CLASS 16 - [PROTECTION PANELS]

1114-16-001 300kV Relay Panel Arrangement AL-AHLIEA 60 10 50 70 85 51


1114-16-002 132kV Relay Panel Arrangement AL-AHLIEA 60 10 50 70 85 51
1114-16-003 300kV BusBar Protection GA Drawings AL-AHLIEA 60 10 50 30
1114-16-004 132kV BusBar Protection GA Drawings AL-AHLIEA 60 10 50 30

Total allocated hours = 240


Total Earned hours = 162
Percentage Complete = 0.68

DRAWINGS CLASS 17 ( LVAC DISTRIBUTION BOARD)

1114-17-001 List of Documents for 415V AC Distribution Board AL-AHLIEA 10 10 50 70 85 8.5


1114-17-002 General arrangement of 415V AC Distribution board-front view/side
board-internal view
equipment AL-AHLIEA 5 10 50 70 85 4.25
1114-17-003 arrangement AL-AHLIEA 5 10 50 70 85 4.25
1114-17-004 DG disconnecting box general arrangement AL-AHLIEA 5 10 50 70 85 4.25
1114-17-005 415V AC Distribution board single line diagram AL-AHLIEA 5 10 50 70 85 4.25
1114-17-006 415V AC Distribution board circuit diagram AL-AHLIEA 5 10 50 70 85 4.25
1114-17-007 415V AC Distribution board terminal schedule AL-AHLIEA 5 10 50 70 85 4.25

Total allocated hours = 40


Total Earned hours = 34
Percentage Complete = 0.85

DRAWINGS CLASS 18 ( DC BATTRIES AND CHARGERS)

1114-18-001 220V DC Control Battery Charger Arrangement (BC) DC Supplier 15 10 50 70 85 12.75


1114-18-002 220V DC Control Battery Charger Circuit Diagram (BC) DC Supplier 15 10 50 70 85 12.75
1114-18-003 220V DC Control Dist Board Arrangement (DC) DC Supplier 15 10 50 70 85 12.75
1114-18-004 220V DC Control Distribution Board Circuit Diagram (DC) DC Supplier 15 10 50 70 85 12.75
1114-18-005 220V DC Single line diagram control charger (BC) and distribution (DT) DC Supplier 15 10 50 70 85 12.75
1114-18-006 220V DC Control Battery Layout DC Supplier 15 10 50 70 85 12.75
1114-18-007 220V DC Control Spare Charger Circuit Diagram DC Supplier 15 10 50 70 85 12.75
1114-18-008 220V DC Trip Battery Charger Circuit Diagram (BT) DC Supplier 15 10 50 70 85 12.75
1114-18-009 220V DC Trip Battery Charger Circuit Diagram (BT) DC Supplier 15 10 50 70 85 12.75
1114-18-010 220V DC Trip Distribution Board Arrangement (DT) DC Supplier 15 10 50 70 85 12.75
1114-18-011 220V DC Trip Distribution Board Circuit Diagram (DT) DC Supplier 15 10 50 70 85 12.75
1114-18-012 220V DC Single line diagram Tripping System Charger (BT) and Distribution DC Supplier 15 10 50 70 85 12.75
1114-18-013 220V DC Tripping Battery Layout DC Supplier 15 10 50 70 85 12.75
1114-18-014 220V DC Tripping system spare charger circuit diagram DC Supplier 15 10 50 70 85 12.75
1114-18-015 110V DC Emergency Lighting Batt charger/Dist Arrangement (BE) DC Supplier 15 10 50 70 85 12.75
1114-18-016 110V DC Emergency Lighting Batt charger/Dist Board Circuit Diagram (BE) DC Supplier 15 10 50 70 85 12.75
1114-18-017 110V DC Single Line Diagram Emergency Lighting System Charger / Distribut DC Supplier 15 10 50 70 85 12.75
1114-18-018 110V DC Battery Layout DC Supplier 15 10 50 70 85 12.75
1114-18-019 DC System Factory Test Procedure DC Supplier 15 10 50 70 85 12.75

Total allocated hours = 285


Total Earned hours = 242.25
Percentage Complete = 0.85

DRAWINGS CLASS 20 ( POWER CABLE LAYOUT)

1114-20-001 Power cable layout within substation building PEC 10 10 50 70 85 8.5


1114-20-002 Power cable layout sections within substation building PEC 10 10 50 70 85 8.5
1114-20-003 132KV Power cable routes external to substation PEC 10 10 50 70 85 8.5
1114-20-004 132KV Power cable routes section external to substation PEC 10 10 50 70 85 8.5
1114-20-005 Power cable schematic PEC 20 10 50 70 85 17
1114-20-007 132KV Power cable schedule PEC 10 10 50 70 85 8.5
1114-20-008 33KV Power cable schedule PEC 10 10 50 70 85 8.5
1114-20-009 11KV Power cable schedule PEC 10 10 50 70 85 95 9.5

Start = 10% Check=50%


Issue = 70% 763687361.xls 22 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

1114-20-010 415V AC Power cable schedule PEC 10 10 50 70 85 95 9.5


1114-20-011 220V/110V DC Power cable schedule PEC 10 10 50 70 85 95 9.5
1114-20-012 300KV Power cable schedule PEC 10 10 50 70 85 95 9.5
1114-20-013 Power cable support structure details PEC 10 10 50 70 85 95 9.5
1114-20-014 Power cable support structure details PEC 10 10 50 70 85 95 9.5
1114-20-015 Power cable and accessories MTO PEC 10 10 50 70 85 95 9.5
1114-20-016 300kv Power cable schedule-AHMADI PEC 10 10 50 70 85 95 9.5
1114-20-017 300 kV Power cable layout & reservations outside site boundary PEC 10 10 50 70 85 95 9.5
1114-20-018 300 kV Power cable layout outside site boundary
& reservations - sections
within cable compound (OHL PEC 10 10 50 70 85 95 9.5
1114-20-019 connection) PEC 10 10 50 70 85 95 9.5
1114-20-020 Power Cable Cleats and Accessories PEC 10 10 50 70 85 95 9.5

Total allocated hours = 200


Total Earned hours = 182
Percentage Complete = 0.91

DRAWINGS CLASS 21 ( MARSHALLING PANELS)

1114-21-001 Telemetry Transfer Terminal Block Cabinets - 300kV General Arrangement AL-AHLIEA 10 10 50 70 85 8.5
1114-21-002 Telemetry Transfer Terminal Block Cabinets - 132kV General Arrangement AL-AHLIEA 10 10 50 70 85 8.5
1114-21-003 Telemetry Transfer Terminal Block Cabinets - 33kV General Arrangement AL-AHLIEA 10 10 50 70 85 8.5
1114-21-004 Telemetry Transfer Terminal Block Cabinets - 11kV General Arrangement AL-AHLIEA 10 10 50 70 85 8.5
1114-21-005 Telemetry Transfer Terminal Block Cabinets - 300kV Terminal Allocation Sch AL-AHLIEA 10 10 50 70 85 8.5
1114-21-006 Telemetry Transfer Terminal Block Cabinets - 132kV Terminal Allocation Sch AL-AHLIEA 10 10 50 70 85 8.5
1114-21-007 Telemetry Transfer Terminal Block Cabinets - 33kV Terminal Allocation Sche AL-AHLIEA 10 10 50 70 85 8.5
1114-21-008 Telemetry Transfer Terminal Block Cabinets - 11kV Terminal Allocation Sche AL-AHLIEA 10 10 50 70 85 8.5

Total allocated hours = 80


Total Earned hours = 68
Percentage Complete = 0.85

DRAWINGS CLASS 22 ( SUBSTATION LAYOUT & SECTIONS)

1114-22-001 Electrical Plot Plan PEC 30 10 50 70 85 25.5

Total allocated hours = 30


Total Earned hours = 25.5
Percentage Complete = 0.85

DRAWINGS CLASS 23 ( EARHING DRAWINGS, MTO & SCHEDULES)

1114-23-001 External Earthing Layout Substation Building Area PEC 10 10 50 70 85 95 9.5 6-Aug
1114-23-002 External Earthing Layout Outdoor Area PEC 10 10 50 70 85 95 9.5 6-Aug
1114-23-003 Internal Earthing Layout 132kV Switchgear Room PEC 10 10 50 70 85 95 9.5 6-Aug
1114-23-004 Internal Earthing Layout 300kV Switchgear Room (1/2) PEC 10 10 50 70 85 95 9.5 6-Aug
1114-23-005 Internal Earthing Layout 300kV Switchgear Room (2/2) PEC 10 10 50 70 85 95 9.5 6-Aug
1114-23-006 Internal Earthing Layout-Basements PEC 10 10 50 70 85 95 9.5 6-Aug
1114-23-007 Internal/External Earthing Layout Sections Sheet 1 PEC 10 10 50 70 85 95 9.5 6-Aug
1114-23-008 Internal/External
Earthing Earthing
Layout for Layout
Basement Sections
Power cableSheet 2
supports,GIBSupports & csble PEC 10 10 50 70 85 95 9.5 6-Aug
1114-23-009 laadder rack PEC 10 10 50 70 85 95 9.5 6-Aug
1114-23-012 Earthing Compression Terminal - Lugs for Stranded Copper Cables PEC 10 10 50 70 85 95 9.5
1114-23-013 Earthing System Installation Details PEC 10 10 50 70 85 95 9.5 6-Aug
1114-23-014 Earthing System Material Take Off PEC 10 10 50 70 85 95 9.5

Total allocated hours = 120


Total Earned hours = 114
Percentage Complete = 0.95

Start = 10% Check=50%


Issue = 70% 763687361.xls 23 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

DRAWINGS CLASS 24 ( KEY & SINGLE LINE DIAGRAMS)

1114-24-001 300/132/11kV key line diagram PEC 30 10 50 70 85 25.5


1114-24-002 Single line diagrams drawing list PEC 30 10 50 70 85 25.5
1114-24-003 415V A.C. single line diagram PEC 30 10 50 70 85 25.5
1114-24-004 220/110V D.C. single line diagram PEC 30 10 50 70 85 25.5

Total allocated hours = 120


Total Earned hours = 102
Percentage Complete = 0.85

DRAWINGS CLASS 25 ( SCHEMATIC DIAGRAMS)

300kV SCHEMATICS
1114-25-001 300kV O/H Line Feeder PEC 30 10 50 70 85 25.5
1114-25-002 300kV Under Ground Cable Schematic Diagram PEC 30 10 50 70 85 25.5
1114-25-003 300kV Bus Coupler Schematics PEC 30 10 50 70 85 25.5
1114-25-004 300kV Side - 300MVA Transformer Schematics PEC 30 10 50 70 85 25.5
1114-25-005 300kV Bus Section 1/3 Schematics PEC 30 10 50 70 85 25.5
1114-25-006 300kV Bus Section2/4 Schematics PEC 30 10 50 70 85 25.5
1114-25-007 300kV Synchronising and Station Alarm Panel Schematics PEC 30 10 50 70 85 25.5
1114-25-008 300kV Interlocking Schematics PEC 30 10 50 70 85 25.5
1114-25-009 300kV Bus voltage selection and Synchronising Schematic Diagram PEC 30 10 50 70 85 25.5
1114-25-010 300/132kV Schematic and cable diagram symbol list PEC 30 10 50 70 85 25.5
1114-25-011 300MVA Transformer OLTC Cable Connection Diagram PEC 30 10 50 70 85 25.5
1114-25-012 300kV Disturbance Recorder Panels Schematics PEC 30 10 50 70 85 25.5
1114-25-014 300MVA Transformer Overall Interlocking Diagram PEC 30 10 50 70 85 25.5
1114-25-015 300kV Switchgear Gas Trip/Intertrip Schematic PEC 30 10 50 70 85 25.5
1114-25-016 300kV Busbar Protection Schematic Drawings PEC 30 10 50 70 85 25.5

132kV SCHEMATICS
1114-25-101 132kV Cable Feeder Schematics PEC 30 10 50 70 85 25.5
1114-25-102 132kV Side 300MVA Transformer Schematics PEC 30 10 50 70 85 25.5
1114-25-103 132kV Side 30MVA Transformer Schematics PEC 30 10 50 70 85 25.5
1114-25-104 132kV Bus Coupler Schematics PEC 30 10 50 70 85 25.5
1114-25-105 132kV Bus Section 1/2 Schematics PEC 30 10 50 70 85 25.5
1114-25-106 132kV Bus Section 3/4 Schematics PEC 30 10 50 70 85 25.5
1114-25-108 132/33kV Interlocking Diagram PEC 30 10 50 70 85 25.5
1114-25-109 132kV Bus Voltage Selection Schematic Diagram PEC 30 10 50 70 85 25.5
1114-25-111 132kV Switchgear Gas Trip/Intertrip Schematic PEC 30 10 50 70 85 25.5
1114-25-112 132KV Load shedding schematics PEC 30 10 50 70 85 25.5

1114-25-201 33kV Side 300 MVA Transformer Schematics PEC 30 10 50 70 85 25.5


1114-25-202 33kV Swgr Schematic Diagram PEC 30 10 50 70 85 25.5
1114-25-301 Schematic and Cable Diagram Symbol List PEC 30 10 50 70 85 25.5

11kV SCHEMATICS
1114-25-302 11kV Cable Feeder Schematic Diagram PEC 30 10 50 70 85 25.5
1114-25-303 11kV Side of 30MVA Transformer Schematic Diagram PEC 30 10 50 70 85 25.5
1114-25-304 11kV Bus Section Schematic Diagram PEC 30 10 50 70 85 25.5
1114-25-305 11kV Buscoupler Schematic Diagram PEC 30 10 50 70 85 25.5
1114-25-306 11kV side of Auxiliary Transformer Schematic Diagram PEC 30 10 50 70 85 25.5
1114-25-307 300/132/11kV Substation Ancillary Schematic Diagram PEC 30 10 50 70 85 25.5
1114-25-308 11kV Interlocking Schematic Diagram PEC 30 10 50 70 85 25.5
1114-25-309 11kV Transformer Tap Change Control Interconnection Schematic PEC 30 10 50 70 85 25.5
1114-25-311 11KV Arc Fault Protection Schematic Diagram PEC 30 10 50 70 85 25.5

Total allocated hours = 1110


Total Earned hours = 943.5

Start = 10% Check=50%


Issue = 70% 763687361.xls 24 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

Percentage Complete = 0.85

DRAWINGS CLASS 26( TERMINATION DIAGRAMS)

1114-26-001 300kV Control Cable Schedule PEC 20 10 50 10


1114-26-002 300kV Cable Terminations Spare Feeder Bay 1 PEC 20 10 50 10
1114-26-003 300kV Cable Terminations 300MVA Transformer Bay 2 PEC 20 10 50 10
1114-26-004 300kV Cable Terminations OHL Feeder Bay 3 PEC 20 10 50 10
1114-26-005 300kV Cable Terminations OHL Feeder Bay 4 PEC 20 10 50 10
1114-26-006 300kV Cable Terminations 300MVA Transformer Bay 5 PEC 20 10 50 10
1114-26-007 300kV Cable Terminations Bus Coupler Bay 6 PEC 20 10 50 10
1114-26-008 300kV Cable Terminations Bus Section 1 Bay 7 PEC 20 10 50 10
1114-26-009 300kV Cable Terminations Bus Section 2 Bay 8 PEC 20 10 50 10
1114-26-010 300kV Cable Terminations 300MVA Transformer Bay 9 PEC 20 10 50 10
1114-26-011 300kV Cable Terminations OHL Feeder Bay 10 PEC 20 10 50 10
1114-26-012 300kV Cable Terminations OHL Feeder Bay 11 PEC 20 10 50 10
1114-26-013 300kV Cable Terminations 300MVA Transformer Bay 12 PEC 20 10 50 10
1114-26-014 300kV Cable Terminations U/G Cable Feeder Bay 13 PEC 20 10 50 10
1114-26-015 300kV Cable Terminations Busbar Protection Panels PEC 20 10 50 10
1114-26-016 300kV Cable Terminations Telemetry Equipment PEC 20 10 50 10
1114-26-017 300kV Cable Terminations Intertripping Cabinet PEC 20 10 50 10
1114-26-018 300kV Cable Terminations Disturbance Recorder PEC 20 10 50 10

1114-26-101 132kV Control Cable Schedule PEC 20 10 50 10


1114-26-102 132kV Cable Terminations Cable Feeder Bay 1 PEC 20 10 50 10
1114-26-103 132kV Cable Terminations Cable Feeder Bay 2 PEC 20 10 50 10
1114-26-104 132kV Cable Terminations Cable Feeder Bay 3 PEC 20 10 50 10
1114-26-105 132kV Cable Terminations Cable Feeder Bay 4 PEC 20 10 50 10
1114-26-106 132kV Cable Terminations 300MVA Transformer Bay 5 PEC 20 10 50 10
1114-26-107 132kV Cable Terminations 30MVA Transformer Bay 6 PEC 20 10 50 10
1114-26-108 132kV Cable Terminations Cable Feeder Bay 7 PEC 20 10 50 10
1114-26-109 132kV Cable Terminations Cable Feeder Bay 8 PEC 20 10 50 10
1114-26-110 132kV Cable Terminations 300MVA Transformer Bay 9 PEC 20 10 50 10
1114-26-111 132kV Cable Terminations Cable Feeder Bay 10 PEC 20 10 50 10
1114-26-112 132kV Cable Terminations Cable Feeder Bay 11 PEC 20 10 50 10
1114-26-113 132kV Cable Terminations Bus Coupler Bay 12 PEC 20 10 50 10
1114-26-114 132kV Cable Terminations Bus Section 1 Bay 13 PEC 20 10 50 10
1114-26-115 132kV Cable Terminations Bus Section 2 Bay 14 PEC 20 10 50 10
1114-26-116 132kV Cable Terminations Cable Feeder Bay 15 PEC 20 10 50 10
1114-26-117 132kV Cable Terminations Cable Feeder Bay 16 PEC 20 10 50 10
1114-26-118 132kV Cable Terminations 30MVA Transformer Bay 17 PEC 20 10 50 10
1114-26-119 132kV Cable Terminations 300MVA Transformer Bay 18 PEC 20 10 50 10
1114-26-120 132kV Cable Terminations Cable Feeder Bay 19 PEC 20 10 50 10
1114-26-121 132kV Cable Terminations Cable Feeder Bay 20 PEC 20 10 50 10
1114-26-122 132kV Cable Terminations 300MVA Transformer Bay 21 PEC 20 10 50 10
1114-26-123 132kV Cable Terminations 30MVA Transformer Bay 22 PEC 20 10 50 10
1114-26-124 132kV Cable Terminations Cable Feeder Bay 23 PEC 20 10 50 10
1114-26-125 132kV Cable Terminations Cable Feeder Bay 24 PEC 20 10 50 10
1114-26-126 132kV Cable Terminations Cable Feeder Bay 25 PEC 20 10 50 10
1114-26-127 132kV Cable Terminations Cable Feeder Bay 26 PEC 20 10 50 10
1114-26-128 132kV Cable Terminations Busbar Protection Panels PEC 20 10 50 10
1114-26-129 132kV Cable Terminations Telemetry Equipment PEC 20 10 50 10
1114-26-130 132kV Cable Terminations Intertripping Cabinet PEC 20 10 50 10
1114-26-131 300KV building Nodes Layout PEC 20 10 50 10
1114-26-132 132KV building Nodes Layout PEC 20 10 50 10
1114-26-133 Cable Routing Design PEC 20 10 50 70 14

1114-26-201 33kV Control Cable Schedule PEC 20 10 50 10


1114-26-202 33kV Switchgear Cable Terminations Bay 1 PEC 20 10 50 10
1114-26-203 33kV Switchgear Cable Terminations Bay 2 PEC 20 10 50 10
1114-26-204 33kV Switchgear Cable Terminations Bay 3 PEC 20 10 50 10
1114-26-205 33kV Switchgear Cable Terminations Bay 4 PEC 20 10 50 10
1114-26-206 33kV Cable Terminations Telemetry Equipment PEC 20 10 50 10

Start = 10% Check=50%


Issue = 70% 763687361.xls 25 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

1114-26-301 11kV Control Cable Schedule PEC 20 10 50 10


1114-26-302 11kV Cable Terminations Cable Feeder Bay 01 PEC 20 10 50 10
1114-26-303 11kV Cable Terminations Cable Feeder Bay 02 PEC 20 10 50 10
1114-26-304 11kV Cable Terminations Cable Feeder Bay 03 PEC 20 10 50 10
1114-26-305 11kV Cable Terminations Cable Feeder Bay 04 PEC 20 10 50 10
1114-26-306 11kV Cable Terminations Cable Feeder Bay 05 PEC 20 10 50 10
1114-26-307 11kV Cable Terminations 30MVA Tr. 1 Bay 06 PEC 20 10 50 10
1114-26-308 11kV Cable Terminations Cable Feeder Bay 07 PEC 20 10 50 10
1114-26-309 11kV Cable Terminations Cable Feeder Bay 08 PEC 20 10 50 10
1114-26-310 11Kv Cable Terminations 750kVA Tr. 1 Bay 10 PEC 20 10 50 10
1114-26-311 11kV Cable Terminations Bus Coupler Bay 11 PEC 20 10 50 10
1114-26-312 11kV Cable Terminations Bus Section Bay 12 PEC 20 10 50 10
1114-26-313 11kV Cable Terminations 750kVA Tr. 2 Bay 13 PEC 20 10 50 10
1114-26-314 11kV Cable Terminations Cable Feeder Bay 14 PEC 20 10 50 10
1114-26-315 11kV Cable Terminations Cable Feeder Bay 15 PEC 20 10 50 10
1114-26-316 11kV Cable Terminations 30MVA TR. 2 Bay 16 PEC 20 10 50 10
1114-26-317 11kV Cable Terminations Cable Feeder Bay 17 PEC 20 10 50 10
1114-26-318 11kV Cable Terminations Cable Feeder Bay 18 PEC 20 10 50 10
1114-26-319 11kV Cable Terminations Cable Feeder Bay 19 PEC 20 10 50 10
1114-26-320 11kV Cable Terminations Cablle Feeder Bay 20 PEC 20 10 50 10
1114-26-321 11kV Cable Terminations Cable Feeder Bay 21 PEC 20 10 50 10
1114-26-322 11kV Cable Terminations 30MVA Tr. 3 Bay 22 PEC 20 10 50 10
1114-26-323 11kV Cable Terminations Cable Feeder Bay 23 PEC 20 10 50 10
1114-26-324 11kV Cable Terminations Cable Feeder Bay 24 PEC 20 10 50 10
1114-26-325 11kV Cable Terminations Cable Feeder Bay 25 PEC 20 10 50 10
1114-26-326 11kV Cable Terminations Telemetry Equipment PEC 20 10 50 10
1114-26-327 11kV Cable Terminations - Pilot Wire Marshalling Cabinet PEC 20 10 50 10
1114-26-328 Ancillary Control Cable Schedule PEC 20 10 50 10
1114-26-329 Cable Terminations Ancillary Equipment PEC 20 10 50 10
1114-26-330 Control Cable Drum Schedule PEC 20 10 50 10

Total allocated hours = 1740


Total Earned hours = 874
Percentage Complete = 0.50

DRAWINGS CLASS 28 ( CONTROL CABLES LADDER RACK LAYOUTS)

1114-28-001 300kV Control Cable Ladder Rack Layout PEC 30 10 50 70 85 95 28.5


1114-28-002 132kV Control Cable Ladder Rack Layout PEC 30 10 50 70 85 95 28.5
1114-28-003 300kV Trench Control Cable Ladder Rack Layout PEC 30 10 50 70 85 95 28.5

Start = 10% Check=50%


Issue = 70% 763687361.xls 26 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

1114-28-004 132kV Basement Control Cable and oil pressure pipe trays Layout PEC 30 10 50 70 85 95 28.5
1114-28-005 Details of control cable ladder rack support structure details PEC 30 10 50 70 85 95 28.5
1114-28-006 Cable ladder material take off PEC 30 10 50 70 85 95 28.5
1114-28-007 Control cable ladder rack layout sections PEC 30 10 50 70 85 95 28.5
1114-28-008 Embedded Concrete Inserts Layouts and Sections in 300kV Trench PEC 30 10 50 70 85 95 28.5

Total allocated hours = 240


Total Earned hours = 228
Percentage Complete = 0.95

DRAWINGS CLASS 30 ( GA DRAWINGS)

1114-30-001 300/132/11kV S/S - Site Plan PEC 12 10 50 70 85 95 11.4

300kV GIS BUIDLING


1114-30- 300kV Building Foundation Plan - Sheet 1 of 2 PEC 12 10 50 70 85 95 11.4
002/1
1114-30- 300kV Building Foundation Plan - Sheet 2 of 2 PEC 12 10 50 70 85 95 11.4
002/2
1114-30- 300kV Building Trench Wall Elevations - Sheet 1 of 2 PEC 12 10 50 70 85 95 11.4
003/1
1114-30- 300kV Building Trench Wall Elevations - Sheet 2 of 2 PEC 12 10 50 70 86 95 9.6
003/2
1114-30- 300kV Building Ground Floor Plan - sheet 1 of 2 PEC 12 10 50 70 87 95 9.6
004/1
1114-30- 300kV Building Ground Floor Plan - sheet 2 of 2 PEC 12 10 50 70 88 95 9.6
004/2
1114-30- 300kV Building Transformer Bays - Sheet 1 of 4 PEC 12 10 50 70 85 95 11.4
005/1
1114-30- 300kV Building Transformer Bays - Sheet 2 of 4 PEC 12 10 50 70 85 95 11.4
005/2
1114-30- 300kV Building Transformer Bays - Sheet 3 of 4 PEC 12 10 50 70 85 95 11.4
005/3
1114-30- 300kV Building Transformer Bays - Sheet 4 of 4 PEC 12 10 50 70 85 95 11.4
005/4
1114-30-006 300kV Building Roof Plan PEC 12 10 50 70 88 95 9.6
1114-30-007 300kV Building Sections - 1 PEC 12 10 50 70 88 95 9.6
1114-30-008 300kV Building Sections - 2 PEC 12 10 50 70 88 95 9.6
1114-30-009 300kV Building Elevations PEC 12 10 50 70 88 95 9.6
1114-30-015 300kV Building Cable trench (chequer-plate ?) cover details PEC 12 10 50 70 85 95 11.4

132kV GIS BUIDLING


1114-30- 132kV Building Foundation & Basement Plan - Sheet 1 of 2 PEC 12 10 50 70 85 95 11.4
030/1
1114-30- 132kV Building Foundation & Basement Plan - Sheet 2 of 2 PEC 12 10 50 70 85 95 11.4
030/2
1114-30- 132kV Building Basement Wall Elevations - Sheet 1 of 2 PEC 12 10 50 70 85 95 11.4
031/1
1114-30- 132kV Building Basement Wall Elevations - Sheet 2 of 2 PEC 12 10 50 70 85 95 11.4
031/2
1114-30- 132kV Building Ground Floor Plan - sheet 1 of 2 PEC 12 10 50 70 85 95 11.4
032/1
1114-30- 132kV Building Ground Floor Plan - sheet 2 of 2 PEC 12 10 50 70 85 95 11.4
032/2
1114-30-033 132kV Building 30 MVA Transformer Bays PEC 12 10 50 70 85 95 11.4
1114-30-034 132kV Building 45 MVA Reactors Bays PEC 12 10 50 70 85 95 11.4
1114-30-035 132kV Building Roof Plan PEC 12 10 50 70 85 95 11.4
1114-30-036 132kV Building Basement Stairs GA PEC 12 10 50 70 85 95 11.4
1114-30-037 132kV Building Sections 1 PEC 12 10 50 70 85 95 11.4
1114-30-038 132kV Building Sections 2 PEC 12 10 50 70 85 95 11.4
1114-30-051 External cable trenches - General Arrangement PEC 12 10 50 70 85 95 11.4

GENERAL DRAWINGS
1114-30-067 External cable trenches - General Arrangement PEC 12 10 50 70 85 95 11.4
1114-30-068 Interconnecting cable duct banks - General Arrangement PEC 12 10 50 70 85 95 11.4
1114-30-069 OHL switchyard foundations - General Arrangement PEC 12 10 50 70 85 95 11.4

SKETCH DRAWINGS ( FOR SITE USE ONLY)


1114-30-090 300kV Building GIS room - floor fixing details PEC 0

Start = 10% Check=50%


Issue = 70% 763687361.xls 27 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

1114-30-091 300kV Building CE supports - fixing details PEC 0


1114-30-092 300kV Building GIB cover plate details PEC 0
1114-30-093 300kV Building Cable Trench Walls - Unistrut Location Details PEC 0
1114-30-094 132kV Building Basement Walls - Unistrut Location Details PEC 0
1114-30-095 132kV Building Basement Ceiling - Unistrut Location Details PEC 0
1114-30-096 300kV Building GIS room - floor screed details PEC 0
1114-30-097 132kV Building GIS room - floor screed details PEC 0
1114-30-098 132kV Building 33 kV SWG room - floor screed details PEC 0
1114-30-099 132kV Building 11 kV SWG room - floor screed details PEC 0

1114-30-300 PEC 12 10 50 70 8.4

TOTAL HOURS 396


Total Earned hours = 360.6
Percentage Complete = 0.91

DRAWINGS CLASS 31( RC DETAILS DRAWINGS)


RC DRAWINGS - 300 kV BUILDING
1114-31-101 -300kV Building Foundations - formwork details CCC 0

TOTAL HOURS 0
Total Earned hours = 0
Percentage Complete = 0.00

DRAWINGS CLASS 32 ( STEEL WORK)


1114-32-181 300kV BuildingTransformer Sunshade - Structural Details CCC 0

TOTAL HOURS 0

Start = 10% Check=50%


Issue = 70% 763687361.xls 28 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

Total Earned hours = 0


Percentage Complete = 0.00

DRAWINGS CLASS 36 ( LIGHTING AND SMALL POWER)


1114-36-301 300kV Building Ground Floor Emergency & Exit Lights CCC 0

TOTAL HOURS 0
Total Earned hours = 0
Percentage Complete = 0.00

DRAWINGS CLASS 37 ( HVAC)


1114-37-201 132kV Building - HVAC Layout Basement Floor CCC 0

Start = 10% Check=50%


Issue = 70% 763687361.xls 29 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

TOTAL HOURS 0
Total Earned hours = 0
Percentage Complete = 0.00

DRAWINGS CLASS 38 ( FIRE FIGHTING)

1114-38-401 Water Spray System Complete Data Sheets KFF 0


0

TOTAL HOURS 0

Total Earned hours = 0


Percentage Complete = 0.00

DRAWINGS CLASS 39 ( PA DRAWINGS)

1114-39-001 300/132/11kV S/S - Site Plan PEC 12 10 50 70 85 95 11.4


1114-39-002 300kV Building Foundation Plan PEC 12 10 50 70 85 95 11.4
1114-39-003 300kV Building Ground Floor Plan PEC 12 10 50 70 85 95 11.4
1114-39-004 300kV Building Roofing Plan PEC 12 10 50 70 85 95 11.4

Start = 10% Check=50%


Issue = 70% 763687361.xls 30 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
PROGRESS MONITORING REPORT
FOR MoE 3377 132/11kV Saad Al Abdulla 'ABCD' SUBSTATIONS
CRD No Subcontractor Drawing Title Originator Allocated Actual Progress Earned Actual Productivity
Drawing Number Man Hours 10% 50% 70% 85% 95% 100% Hours Hours
Start Check Issue Approved Const. As-Built

1114-39-005 300kV Building Sections PEC 12 10 50 70 85 95 100 12


1114-39-006 300kV Building Elevations PEC 12 10 50 70 85 95 100 12
1114-39-007 132kV Building- Foundation and Basement Plan PEC 12 10 50 70 85 95 100 12
1114-39-008 132kV Building Ground Floor Plan PEC 12 10 50 70 85 95 100 12
1114-39-009 132kV Building Roofing Plan PEC 12 10 50 70 85 95 100 12
1114-39-010 132kV Building Sections PEC 12 10 50 70 85 95 100 12
1114-39-011 132kV Building Elevations PEC 12 10 50 70 85 95 100 12

TOTAL HOURS 132


Total Earned hours = 129.6
Percentage Complete = 0.98

OVERALL TOTAL ALLOCATED HOURS


6911 8555
OVERALL TOTAL EARNED HOURS
5366.5 6643
OVERALL PROGRESS % 0.78 0.78

Start = 10% Check=50%


Issue = 70% 763687361.xls 31 of 33
Apvd with comments =85%
Approved =90% Construction = 95% As Builts = 100%
Equipment Class
1 General (Design Briefs)
5 300 kV Switchgear
7 132 kV Switchgear
9 33 kV Switchgear
### 11 kV Switchgear
### 300 MVA Transformers and Shunt Reactors
### 250 KVA Auxiliary Transformers
### Neutral Earthing Resistors and Neutral Isolator Cabinets
### Control Panels
### Protection Panels
### 415 V AC Distribution Panels
### Batteries, Battery Chargers and DC Distribution Boards
### Power Cables
### Marshaling Cabinets Telemetry
### General Equipment,Arrangement Drawings and plot Plans
### Substation Earthing System
### Keyline Diagrams and Single Line Diagrams
### Schematic Drawings
### Control & Small Power Cable Schedules, Termination Schedules, Control Cable Routing Layout/Sections
### Floor Fixing Layouts & Details
### Ladder Rack Layouts
### Wiring Diagrams
### General Arrangement Layouts (Civil)
### Structural RC Details (Civil)
### Structural RSteelwork (Civil)
### Drainage Well Installation
### Cranes
### LSP & Co-ordinated Conduit Drawings
### Air Conditioning System (CED)
### Fire Fighting
### Building Licences Drawings
Number prefix
X Common drawing for both substations Jahra X and Kifan W
J Jahra X 300 kV substation
K Kifan W 300 kV substation

PA ‘preliminary arrangement’ drgs.


BL ‘building license’ drgs. (submitted to client)
DW ‘drainage well’ drgs. (submitted to client)
SC ‘subcontract’ drawings.
SK ‘sketch' drgs.
UC ‘Unistrut channel’ Insert drgs.
FC ‘floor channel’ drgs.
FS ‘floor screed’ drgs.
GF ‘external gantry foundation’ drgs. (submitted to client)
Layout/Sections RX ‘road crossing’ drgs. (submitted to client)
LD ‘loading diagrams’