Generator Sizing and UPS Systems
Generator Sizing and UPS Systems
• Emergency standby.
• Prime power.
• Limited time prime.
• Continuous power.
TYPES OF GENERATORS
INDUSTRY STANDARD RATINGS
(ISO-8528-1:2005)
• This is an industry standard that
defines the performance parameters
required in various onsite power
applications.
TYPES OF GENERATORS
EPA EMISSION RATINGS
(GOVERNMENTAL REGULATIONS
ON ENGINE EMISSIONS)
• An engine requires a certain quantity of air for combustion to achieve its rated
power.
• Altitude, temperature and humidity will all affect the air density.
• The environment or site conditions also impact an engine or generator rating, thus
impacting the rating of the entire generator. These Conditions include:
• Ambient Temperature,
• Altitude,
• Corrosive Atmospheres,
• Humidity,
• Dust.
AMBIENT TEMPERATURE
• The National Electrical Manufacturers Association (NEMA) generator ratings are
based on the generators “temperature rise” limit.
• Outside the United States,(IEC) has limits on temperature rise for generators; these
may be found in IEC 6034-22 (1996) and IEC 6034-1 (2004).
• Temperature rise is the increase in winding temperature above the ambient
temperature.
• Ambient temperature is the temperature of the cooling air as it enters the
ventilating openings of the machine.
• This temperature rise occurs because of the flow of current in the windings and
internal losses that occur in the machine during operation.
AMBIENT TEMPERATURE
• The most common classes of generators are the “F” and “H” class.
• For all classes, NEMA assumes operation at 40°C ambient or lower.
• The temperature rise limits also allow for a 10°C margin for hot-spots.
• A hot-spot is the spot in stator windings with the highest temperature.
• Table-2 shows temperature rise for F and H class generators at various ratings.
ALTITUDE
• The higher the altitude, the lower the air density.
• The altitude/temperature de-rating chart can be found for proper de-rating
information for generators and each specific engine.
TRANSIENT RESPONSE FOR
GENERATOR
• Whenever a load is applied to or removed from a generator set, the engine speed
rpm, voltage and frequency are temporarily changed from its steady-state
condition.
TRANSIENT RESPONSE
STANDARDS - ISO 8528
VOLTAGE DROP
EFFECT OF VOLTAGE DROP
• Electric Motor: The torque is proportional to the square of the supply voltage.
Therefore, if the voltage drops the starting torque will also decrease, making it more
difficult to start up motors, the maximum torque will also decrease .
• Incandescent Lamp: The more the voltage drops the weaker the beam becomes.
• Electronic Appliances: They are very sensitive to
variations in voltage and that is why they are often fitted with internal stabilizer
EXCEPTIONS TO THE IEC
60364-5-52 STANDARD
The following temporary conditions are excluded from the voltage drop restrictions
in the table above:
1. Voltage transients.
2. Voltage variation due to abnormal operation.
VOLTAGE DROP
CALCULATION
EXAMPLE ON VOLTAGE
DROP
SOLUTIONS OF VOLTAGE
DROP
• For closed areas we assume that each 1 HP can cover 10 m^2 at height of 3 m.
• For open areas we assume that each 1 HP can cover 8 m^2 at height of 3 m.
• For closed areas we can divide volume of room by 30 = required HP.
• For open areas we can divide volume of room by 25 = required HP.
• Circuit breaker usually= I rated*1.25 but in air conditioning due to presence of high
starting current we can say 2.5* I rated.
• Disconnecting switch is usually same rating as circuit breaker or higher.
• Example of available single phase air conditioning: 1.5,2.25,2.5,3,4,5 HP.
• Higher than 5 is a three phase air conditioning.
HVAC IN BUILDINGS
• d
LOAD ESTIMATION
• Before we start a project as hotel or residential building or an office,.. Etc, we have
to estimate the load or the total Kva in our project before we start creating the
project.
• We have to do a contract with the electrical distribution company that I would like
certain amount of power for my project, so the electrical distribution company will
prepare this amount of power before the project is finished, so that I can start
operating it as soon as possible without delay.
• So in order to this, we have to estimate the required load in my project.
• Also we need to know the number of transformers and the rooms required for them
in the plan so we need to estimate the load at first.
• Load estimation by electrical engineer and mechanical engineer as HVAC system.
• Also if we have light current system, then we need to add these loads to system.
LOAD ESTIMATION
• By using the code, we can get how many VA per m^2 per one floor.
• So Total load= number of floors* area of one floor * kVA/m^2.
• Each floor assumed to have 3 meters in height.
kVA/100 m^2 For Less Than 15 Floors kVA/100 m^2 For Greater Than 15 Floors
Residential Administration Residential Administration
Low: 1.5-2 6-12 8-10 12
Medium: 2.5-4
High: 6-10
• If a UPS fault causing either the voltage or frequency at the inverter output to exceed
acceptable levels, or an overload beyond the UPS’s capacity appears, the static
switch changes over without power interruption to ‘Load on Bypass’.
• Once the overload is cleared or other problems rectified, the static switch transfers
the load back to the inverter output and normal operation continues.
• It can be single mains, dual mains, single mains without bypass.
VOLTAGE AND FREQUENCY
INDEPENDENT (VFI)
• When power fails, the batteries drive the inverter, which continues to run the IT load.
• When power is restored, either from the utility or a generator, the rectifier delivers DC
to the inverter and recharges the batteries, the inverter runs full time.
• Utility input is completely isolated from the output, and bypass is only used for
maintenance safety or if there is an internal electronics failure
VOLTAGE INDEPENDENT
(VI)
• Voltage independent (VI), or line interactive UPSs have a controlled output voltage,
but the same output frequency as the input.
• Utility power feeds directly to the output and IT equipment, and the rectifier keeps
the batteries charged.
• The inverter is paralleled with the output, compensating for voltage dips and acting
as an active filter for voltage spikes and harmonics
VOLTAGE INDEPENDENT
(VI)
• When incoming power fails, or the voltage goes out of range, the bypass quickly
disconnects from the input and the battery drives the inverter.
• When input power is restored, the bypass re-engages the input, re-charges the
batteries and keeps output voltage constant.
• UPS vendors who use paralleled power sources claim no loss of reliability.
• The result is around 98% energy efficiency.
VOLTAGE AND FREQUENCY
DEPENDENT (VFD)
• VFD concepts have the inverter producing power within 2 ms after being activated.
• The bypass is normally just as with VI, so equipment operates directly from the utility
or generator.
• Since the inverter isn't working until power fails, there is no voltage control or power
consumed, enabling efficiencies as high as 99%.
ADVANTAGES OF UPS
• No delay between switching from the primary power source to the UPS.
• Can better support critical instruments compared to generators.
• Consumers can choose the type and size of UPS, depending on the amount of
power they need to supply to a device.
• UPSs are silent.
• Maintenance of UPS systems is cheaper compared to generators.
DISADVANTAGES OF UPS
• The inability to run heavy appliances- because UPSs are run off of batteries.
• If substandard batteries are used, users may end up replacing the batteries often.
• UPSs may need professional installations.
UPS SPECS
UPS SPECS