100% found this document useful (1 vote)
588 views8 pages

5110 - 5100 - ICP-OES - PM - Checklist PSG (Recovered)

Uploaded by

andri purnomo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
588 views8 pages

5110 - 5100 - ICP-OES - PM - Checklist PSG (Recovered)

Uploaded by

andri purnomo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Agilent 5110 and 5100 ICP-OES

Preventive Maintenance Checklist

Agilent Preventive Maintenance provides factory recommended service for your analytical systems to
assure reliable operation and the accuracy of your results. Delivered by highly-trained and certified
service engineers using genuine Agilent parts and supplies, Agilent Preventive Maintenance provides
everything you need to reduce unplanned downtime and keep your systems operating at their peak.

For more information about Agilent Technologies services please visit our web site using the following
URL http://www.agilent.com/en-us/services/analytical-instrument-services

Customer Information
 Customers should provide all necessary operating supplies upon request of the engineer.
 For customers using HF applications, the instrument should be returned to its standard sample
introduction system.
 A customer representative should be available to the engineer while performing the preventive
maintenance procedures.
 Any parts, not included in the Parts Lists section of this document, are not part of the recommended
Preventive Maintenance service, nor are they included in the price of this service.
 If a system requires the use of additional or special procedures and/or parts for the instrument
service, then these must be ordered separately and charged as a repair, which may incur additional

Service Engineer’s Responsibilities


 Only complete/printout pages that relate to the system being serviced.
 Complete empty fields with the relevant information.
 Complete the relevant checkboxes in the checklist using a “X” or tick mark “” in the checkbox.
 Complete Not Applicable check boxes to indicate services not delivered, as needed.
 Complete the PM service in the order of the tasks listed.
 Complete the Service Review section together with the customer.

Issued: 3 February 2017, Revision: 1.1 Copyright1 2017 Agilent Technologies


Page 1 of 8
Agilent 5110 and 5100 ICP-OES
Preventive Maintenance Checklist

System Information

Instrument system name and ID ICP 5100/5110 VDV

Instrument system site and location BTKL PP KELAS 1 PALEMBANG

List system component product numbers List the serial numbers of each component
1. ICP 5100/5110 OES 1. MY15130012
2. SPS 4 AUTOSAMPLER 2. MY15250007
3. 3.

4. 4.

5. 5.

6. 6.

7. 7.

8. 8.

9. 9.

10. 10.

ICP-OES Configuration table Circle the type or write in the type if other

Nebulizer Type SeaSpray | OneNeb | other

Spray Chamber Cyclonic Single Pass | Cyclonic Double Pass | other

Torch Radial |Dual View| other

Injector Diameter 2.4mm | 1.8mm | 1.4mm | 0.8mm | other

Injector Material Quartz | Ceramic | other

Issued: 3 February 2017, Revision: 1.1 Copyright2 2017 Agilent Technologies


Page 2 of 8
Agilent 5110 and 5100 ICP-OES
Preventive Maintenance Checklist

General Preparation
 Discuss any specific questions or issues with the customer prior to starting.
 Review the instrument logbook.
 Perform general external inspection of system for cleanliness.
 Check for proper installation of safety-related parts, assemblies, sensors etc.
 Check for required firmware/software updates and verify with customers if they would like it
installed.
 For HF application systems, if standard sample introduction system was not installed, ask the
customer to install it.
 Run Instrument Performance test and record results in Instrument Performance Test Results Table -
Pre PM.

Inspect and clean the system


 Look for any obvious external damage or problems.
 Inspect water cooling hoses, gas lines and power cord for excessive wear or damage.
 Perform a general internal inspection of the system for excessive dust accumulation, clean if
necessary.
 Inspect sample introduction components and record any required maintenance in the Service
Engineer Comments and notify the customer as the required actions required.
 Record the instrument operating conditions in the ICP-OES Status Results Table.
 Replace the polychromator purge filter.
 Replace the radial pre-optics window
 Replace the axial pre-optics window for SVDV and VDV instruments.
 Check exhaust flow for the correct positive extraction at the exhaust duct to insure they meet
minimum specifications.
 Replace air inlet dust filter.
 Replace high capacity air inlet dust filter element if installed.
 Remove and clean instrument water inlet filter.

G8481A Cooling water system


 Section NOT Applicable
 Drain cooling fluid and remove any particles from the chiller reservoir
 Remove, clean and reinstall water inlet metal mesh filter.
 Re fill with Polyclear cooling fluid.
 Clean the cooling system Air filter and the condenser by compressed air or vacuum cleaner.

Issued: 3 February 2017, Revision: 1.1 Copyright3 2017 Agilent Technologies


Page 3 of 8
Agilent 5110 and 5100 ICP-OES
Preventive Maintenance Checklist

SPS 3 Auto Sampler


 Section NOT Applicable
 Power cycle the autosampler and verify successful initialization.
 Inspect X and Z axis belts for wear. Replace is necessary.
 Clean X and Z axis slide shafts.
 Using customer’s racks and the Agilent software move the sample probe to the 4 outermost corners
and rinse port, ensure that the probe is approximately centered in the vial.

SPS 4 Auto Sampler


 Section NOT Applicable
 Clean the spill tray, rack location mat, end frames and chassis with a damp soft cloth and diluted
mild detergent.
 Clean the auto sampler cover panels, if cover kit is installed, with domestic window cleaner
 Check the X-axis and Z-axis drive belts for cracks, splits, damaged teeth, excessive fraying, color
changes or degradation from fumes.
 Check the X-axis, Theta-axis and Z-axis FFC cables for cracks, incorrect positioning, damaged edges
or damaged connectors.
 Pump Tubing Replacement. Replace peristaltic pump tubing. Replace all tubing that goes from the
rinse station to the pump and from the pump to the waste/rinse bottles

AVS 4, 6, 7
 Section NOT Applicable
 Replace valve rotor seal
 Check fittings for signs of leaks
 Check tubing including autosampler tubing for kinks or excessive wear
 Check high flow pump for signs of leaks

Instrument Adjustment
 Check position of Zn peak, adjust if required.
 Check Argon Ratio, adjust to specified value if required.
 Perform Detector Calibration.
 Perform Instrument Calibration.
 Run Instrument Performance Test and record results in Instrument Performance Test Results Table -
Post PM.
 For systems using ICP Expert version 7.3 and above run the following Instrument tests and record
the result in the Instrument Test Results Table
 Subsystem Communications Test
 Air Flow

Issued: 3 February 2017, Revision: 1.1 Copyright4 2017 Agilent Technologies


Page 4 of 8
Agilent 5110 and 5100 ICP-OES
Preventive Maintenance Checklist

 Water Flow
 Gas Flows
 RF Generator
 Camera Test
 Optics Test
 Nebulizer Test

Instrument Performance Test Results Table


Note: These measurements do not form part of any specification and are for reference only.

Pre PM Sensitivity Check Post PM Sensitivity Check


Radial Axial * Radial Axial*

Zn 213.857 nm SRBR 3980.6 9636.0

Mn 257.610 nm SRBR 10974.2 33048.0

Al 396.152 nm SBR 16.0 16.0

K 766.491 nm SBR 9.1 9.1


* Axial result is not applicable for G8016AA, G8012AA Radial View instruments.

Instrument Test Results Table


Note: The Instrument Test results are for systems using ICP Expert version 7.3 and above only.

Instrument Test Result

Subsystem Communications Test PASS

Air Flow PASS

Water Flow PASS

Gas Flows PASS

RF Generator PASS

Camera Test PASS

Optics Test PASS

Nebulizer test PASS

Issued: 3 February 2017, Revision: 1.1 Copyright5 2017 Agilent Technologies


Page 5 of 8
Agilent 5110 and 5100 ICP-OES
Preventive Maintenance Checklist

ICP-OES Status Results Table


Note: These measurements do not form part of any specification and are for reference only.

Measurement Standby Mode Plasma On

Mains Voltage 220.349 VAC 215.536 VAC


Mains Current 0.208 A 0.104 A

Instrument Temperature 22.2 °C 23.9 °C

RF Air Flow (sensor speed) 25 Hz 12 Hz

Plasma Exhaust Temperature No measurement 64.3 °C

Water Flow Oscillator No measurement 1.34 L/min

Water Flow Detector 0.92 L/min 0.92 L/min

Water Inlet Temperature 20.7 °C 20.8 °C

Polychromator Temperature 35 °C 35 °C

CCD Temperature -40 °C -40 °C

Thermal Stabilizer 35 °C 35 °C

Argon Supply Pressure 554.63 kPa 536.75 kPa


Purge Gas Supply Pressure*1 600.68 kPa 573.63 kPa
Option Gas Supply Pressure*1 -0.58 kPa -0.79 kPa

Nebulizer Flow No measurement 0.8 L/min

Nebulizer Back Pressure No measurement 333.51 kPa

Plasma Gas Flow No measurement 15.02 L/min

Auxiliary Gas Flow No measurement 1.2 L/min

RF Power No measurement 1200 W

RF Supply Current No measurement 8.678 A

RF Supply Voltage No measurement 184.279 V

*1 If option installed

Issued: 3 February 2017, Revision: 1.1 Copyright6 2017 Agilent Technologies


Page 6 of 8
Agilent 5110 and 5100 ICP-OES
Preventive Maintenance Checklist

ICP-OES Parts List Table

Part description Part Number Product /Model # where used Quantity Consumed
G8010A, G8011A,
Axial Pre-Optic Window G8010-68014
G8014A/G8015A
Radial Pre-Optic Window G8010-68015 All

Polyclear Cooling Fluid G3292-80010 G8481A

Purge Gas Filter G8010-60136 All

Air inlet filter G8000-68002 All

High Capacity Air Filter G8010-60189 Optional


Rotor seal for 6-7 port valve for
G8494-60002 G8494A/G8495
AVS6/7
Rotor seal for 4 port valve for
G8493-60002 G8493A
AVS4
Rinse solution to rinse station
G8410-80123 SPS 4
2.5mm id x 1m
Barb connector 2.5mm-1.5mm ID G8410-80124 SPS 4
PVC waste tubing,8mm od x 5mm
G8410-80122 SPS 4
id, 2m

Additional Parts may be required from engineers stock:


X axis drive belt 5410047500 SPS 3

Z axis drive belt 5410047400 SPS 3


Peristaltic pump tubing, PVC
3710049000 SPS 4
SolvaFlex, 3 bridged,

Restore system
For HF applications, ask the customer to reinstall their sample introduction system.

Leave system in an idle state: on and purging.

Guidance: If the PM service is performed prior to a qualification service, then use the qualification
procedure as a guide for final instrument set up and checkout.

Service Review
 Affix the PM sticker to the system or instrument logbook based on the customer's request.
 Complete the Service Engineer Comments section below if there are additional comments.

Issued: 3 February 2017, Revision: 1.1 Copyright7 2017 Agilent Technologies


Page 7 of 8
Agilent 5110 and 5100 ICP-OES
Preventive Maintenance Checklist

 Review the service and any test results with the customer.
 If the Instrument firmware was updated, record the details of the change in the Service Engineer's
Comments box below or if necessary, in the customer's IQ records.

Service Completion

Service request number __________________ Date service completed ________________________

Agilent signature __________________ Customer signature ________________________

Issued: 3 February 2017, Revision: 1.1 Copyright8 2017 Agilent Technologies