TOPIC 4 A
TOPIC 4 A
REINFORCEMENT
STEEL REINFORCEMENT
Steel is the most widely used reinforcing material for almost all types of
concrete construction. It is an excellent partner of concrete in resisting
both tension and compression stresses.
Lap splice
is the predominant method used for splicing reinforcing bars. For lap splices, contact
splices are preferred for the practical reason that, when wired together, they are more
easily secured against displacement during concrete placement.
Sample problem :
Determine the length of the splice joint for a 16 mm and 20 mm steel bars under the
following conditions:
25 x 16 mm + 150 mm = 550 mm or 55 cm
20 x 16 mm + 150 mm = 470 mm or 47 cm
Therefore, the splice joint for a 16 mm tension bar is 55 cm long and 47 centimeters for a
compression bars.
25 x 20 mm + 150 mm = 550 mm or 65 cm
20 x 20 mm + 150 mm = 550 mm or 55 cm
Therefore, the splice joint for a 20 mm tension bar is 65 cm long and 55 centimeters for a
compression bars.
HOOK AND BEND
Hooks and bends are specified to standardize the fabrication procedure and to
limit the concrete stresses in the area of the hooks.
Stirrups or Crossties
Lateral ties
DEVELOPMENT LENGTH BEND ELONGATION IN
REINFORCEMENT BARS.
the amount of reinforcement (bar) length What are bend deductions for different
needed to be embedded or projected into the angles in reinforcement bars?
column to establish the desired bond strength
between the concrete and steel. When we bend a steel bar, the length of
the bar is increased due to stretching at
the outer periphery of the bar. To
compensate for this reinforcement bar
elongation, we deduct the increased
length while calculating the cutting length
of the steel bars.
9 db
Calculation of the weight of steel bar
for 1 meter length
From the Figure, determine the number of 10 cm. CHB, and the vertical
reinforcing bars spaced at 80 cm. on center including the horizontal bars at
every after three layers.
SOLUTION (By Area Method) SOLUTION (Unit CHB Method)
1. Solve for the area of the fence 1. Solve for the area of the fence
A = 4 x 3.00
A = length x height A = 12sq.m.
A = 4.00 x. 3.00,
A = 12 sq. m. 2. Determine the number of CHB
12 x 12.5 = 150 pcs
2. Vertical reinforcement at 80 cm. o.c.
Referring to Table 3-4 by the square meter or 3. Referring to Table 3.4
area method. Multiply:
a) Vertical Reinforcement per Block @ .80 m.
12 x 1.60 = 19.2 meters long O.C.
Convert this value to the commercial length Multiply: 150 x 0.128 = 19.2 meters
of steel bars ranging from 5.00 to 13.50
meters. Select the most economical length to Select: 4 pcs 10 mm x 5.00 m. long
avoid extra cut.
b) Horizontal bars for every after 3 layers
Used: 4 pcs. 10 mm. x 5.00 m. long
Referring to Table 3-4,
3. Horizontal bars at every after 3 layers From multiply: 150 X 0.172 = 25.8 m.
Table 3-4,
c) Convert to commercial length
multiply: 12 x 2.15• = 25.80 meters.
Select: 4 pcs @ 5.00 m. and 1 - @ 6.00 m. long Select: 4 pcs. 10 mm x 5.00 and 1 @ 6.00 m.
long
4. Order: 8 - 10 mm x 5.00 m. Steel bars
4. Order: 8 - 10 mm x 5.00 m. and
1 - 10 mm x 6.00 m. Steel bars
1 - 10 mm x 6.00 m. Steel bars
TIE WIRE FOR STEEL REINFORCEMENT
Gauge number 16 galvanized wire is commonly
used as tie wire for steel bar intersections and
splicing joints. One roll is equivalent to 45
kilograms, or approximately 2,385 meters at 53
meters per kilogram.
Solution (Area method) 4. Using a 25 cm. tie wire multiply with the
number of bar intersections.
1. Determine the area of CHB wall
.25m x 36 = 9m
4 x 3 = 12 sq. m.
Convert m to kg.
2. Using a 25 cm. tie wire from Table 3-5
Multiply: 9 x (1kg/53m) = .17 kg say 1 kg tie wire
Tie Wire: 12 x .020 = .24 kg say 1 kg tie wire
INDEPENDENT FOOTING REINFORCEMENT
In estimating for the reinforcement of an independent or isolated
footing, the following rules has to be observed:
1. Know the actual dimension of the footing as to its length and width.
3. If the plan does not call for a hook or bend of the footing
reinforcement, the length of the bar is equal to the length or width of
the footing minus the protective covering at both ends.
4. If the plan calls for a hook or bend of the reinforcement the bar-
cut should include the allowance for hook and bend.
Solution
2. Find the total number of cut bars in one footing by Direct Counting .
13 x 2 = 26 pcs.
3. Get the total number of bars for the 6 footings
26 x 6 = 156 pcs.@ 1.35 m. long
4. Select the steel bars whose length is economically cut into 1.35 m. long
6.00 m. / 1.35 = 4.44 pcs.
Tie Wire
1. Find the number of bar intersections in one footing
13 x 13 = 169 ties
2. Total Ties of 6 footings
169 x 6 = 1014 ties
4. Using 25 cm. length per tie
multiply: 1014 X .25 = 253.5 m
5. One kilo of No. 16 G.I. wire is approximately 53 meter long.
253.5 m / 53 m per kg = 4.78 kgs say 5 kgs
POST AND COLUMN REINFORCEMENT
The reinforcement of posts and columns to be considered in the estimates are:
1. The Main or Vertical Reinforcement
2. The Lateral Ties or
3. The Spiral Ties for Circular Column
The quantity and length of the main reinforcement is determined by the
''Direct Counting Method'' giving special attention to the additional
length for:
''All non-prestressed bars for tied column shall be enclosed by lateral ties
of at least No.3 in size for longitudinal bars No. 10 or smaller and at least
No. 4 in size for No. 11 to 18 and bundled longitudinal bars.''
Example
Determine the spacing of the
lateral tie for a tied column as
show in Figure
Solution
Diameter of the main longitudinal bar = 20 mm .
Diameter of the lateral ties = 10mm
3. Multiply:
16 x 20 = 320 mm.
48 x 10 = 480 mm.
Shortest side of the column = 300 mm.
4. Adopt 300 mm. or 30 cm. spacing
Solution
1. Determine the spacing of the lateral ties.
16 x 20 mm. = 320 mm. or 32 cm.
48 x 10 mm.•= 480 mm.or 48 cm.
The shortest side of the column is = 30 cm.
Tie Wire
20mm
= 9 / 4m
= 2.25 pcs say 2 pcs of 4 meters
4. Number of 20 mm dia. bar x 9 meters
= 208 / 2
= 104 pcs of 20 mm dia. bar x 9 meters
SPIRAL AND COLUMN TIES
The spiral reinforcement consist of evenly spaced continuous spirals held firmly in
place by at least three vertical bar spacers. The center to center spacing of this
spirals should not exceed 6th part of the diameter core. The clear spacing between
the spirals should not exceed 7.5 cm. nor less than 5.00 cm. or one and one half
times the biggest size of the coarse aggregate or gravel.
Example
A spiral column with a cross sectional diameter of 50 cm. requires 10 mm spiral
reinforcement as shown . If there are 14 columns at 7.00 meters high each, find the
number of 10 mm steel bars needed for a 5 cm. pitch.
Solution
A. Spiral Reinforcement
B. Tie Wire
1. Find the number of vertical bars per column= 12
2. Referring to Table 3-7 for a 5 cm. pitch Multiply:
12 x 21 turns per meter = 252 ties
3. Total tie wire for 14 column bar intersections at 7.00 m. ht.
252 x 7.00 m x 14 = 24,696 pcs.
4. Total length of the wire at .30 m. long per tie wire
24,696 X .30 = 7,409 m.
5. Convert to kilogram at 53 m. long/kilo Divide:
7,409 / 53 = 139.8 say 140 kilos
BEAMS AND GIRDERS REINFORCEMENT
The ''Direct Counting Method'' is the best method in determining the
main reinforcement for beams and girders. Provided that in the selection
of the length of steel bars, the following physical condition of the beam in
relation with its support should be considered.
1. Verify from the plan if the span of the column where the beam is to
rest measures from center to center, outer to center or outer to
outer side of the column. This has to be considered in determining the
length of steel bars to be ordered.
2. Verify the position of the reinforcement splicing if it is adjusted to the
commercial length of steel bars. ''The lesser the splice the lesser the
expense
3. Identify the bars with bend and hook, for adjustment of their length
in ordering the steel bars.
BEAMS AND GIRDERS
Note: 10mm dia. = 12mm dia.
Example Solution
Compute the quantity of reinforcement bar Compute the length of main bar
needed of the 4 identical beam structure. = Over all length of beam + 0.45m
= (.3 + 3.5 + .3) + 0.45m
= 4.55 m
Length = 3.5 meters, column size = .30 x .30 Select the steel bars whose length is
economically cut into 4.55 m
try : 10.5m / 4.55m = 2.31 say 2 pcs
Note: if you use 6m length of
commercial bars, you need to
consider the length of lap splice
needed.
there are 4 main bars shown in the
plan, therefore the required materials
needed is :
= (4 x 4)/ 2
= 8 lengths - 20 mm RSB x 10.5 m long
Compute the length of short bars
@support (2 pcs)
= Column width + L/4 + 0.25m
= 0.30 + 3.5/4 + 0.25m
= 1.425 m
@midspan
= L x 0.6
= 3.5 x 0.6
= 2.1m
Solution Stirrups
Compute the number of stirrups in one beam
Select the steel bars whose length is economically
cut into 1.425m for support short bar25m for
support short bar
try : 6m / 1.425m = 4.21 say 4 pcs
Number of 6m long bar needed
= (4 x 2) / 4
= 2 length - 20mm RSB x 6m long @support 1.425m or 1425 mm
Select the steel bars whose length is Number stirrups @ .10m or 100 mm spacing
economically cut into 2.1m for midspan sho short = 13 + 13
barrt bar = 26 pcs
length of beam @ support with 0.1m spacing
try : 6m / 2.1m = 2.85 say 2 pcs
of stirrups
Number of 7.5m long bar needed = 12 spaces x 0.1m
= 1.2 m
= (4 x 1) / 2
The length of stirrups space at 0.1m is 1.2 m
= 2 length - 20mm RSB x 6m long from the support in both ends
Length of REST
= 3.5 - 1.2 + 1.2
= 1.1 m
Number stirrups @ .275m spacing
= 1.1m / .275m
= 4 pcs
Total number of stirrups needed
= (26 + 4) x 4
= 120 pcs of stirrups
Solution
Lenght of Stirrups
A = 250mm - 2(40)
A = 170 mm
B = 400mm - 2(40)
B = 320 mm