Dxb-bw003-Mos-018 - Method Statement Raised Floor Work - Approved

Uploaded by

MAher Abbas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
473 views39 pages

Dxb-bw003-Mos-018 - Method Statement Raised Floor Work - Approved

Uploaded by

MAher Abbas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 39

CHECK LIST

TRANSFER
SL NO NAME OF DOCUMENT REMARKS
CHECK LIST
1 Document Submittal Form ✔
2 Method Statement ✔
RAISED FLOOR CHECKLIST

.
o CHECK VERIFY FIELD DIMENSIONS

o CHECK DRAWINGS AND CHECK SUBFLOOR FOR GRADE VARIATIONS


Level should be ensure
o CHECK STARTING POINT

o CHECK ESTABLISH CONTROL LINES FROM STARTING POINT

o CHECK SPREAD PEDESTALS

o CHECK LEVEL PEDESTALS IN THE PROPER POSITION

o CHECK ATTACH PEDESTALS TO THE SUBFLOOR WITH ADHESIVE

o CHECKING FOR AND CORRECTING UNWANTED CONDITIONS

o CHECK TILTED PEDESTAL CONDITION

o CHECK PANELS AROUND COLUMNS

o CHECK PANELS AT OBSTRUCTIONS, CURBS AND PERIMETER WALLS

o CHECK SAFETY REQUIREMENTS FOR PANEL CUTTING

o CHECK INSTALLING PROTECTIVE TRIM AROUND CUT EDGES

o CHECK EXPANSION JOINTS

o CHECK POST-INSTALLED ANCHORS

Alignment should be ensure.


Stability should be ensure.

Signature Date
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

METHOD STATEMENT AND RISK ASSESSMENT

PROJECT NAME CASS/BFD/113-2 ENHANCEMENT OF JEBEL ALI & AL QOUZ BUS DEPOTS

CLIENT/EMPLOYER ROAD AND TRANSPORT AUTHORITY

CONSULTANT AL TURATH ENGINEERING CONSULTANT LLC

MAIN CONTRACTOR BUILTWAY CONSTRUCTION LLC


PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: RAISED BW/025/AN/24
FLOOR WORK

MAIN CONTRACTOR: BUILTWAY CONSTRUCTION LLC.

NAME: DESIGNATION: PHONE.NO:

MAHMOUD AMARA PROJECT MANAGER 0527430590

JITHIN JOHN HSE ENGINEER 0524746016

CONSULTANT: ALTURATH ENGINEERING CONSULTANTS.

FAIZAL ENGINEER 0555322745

AYMAN BAROUDI SITE INSPECTOR 0502711760

CLIENT: R T A (ROADS & TRANSPORT AUTHORITY)

AHMED SHAWKY ENGINEER 0552685357


PROJECT NAME: DATE: 22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

REVISION STATUS

REV DATE PREPARED BY PREPARED BY REVIEWED BY CHECKED BY APPROVED BY


QA/QC HSE BY PROJECT MANAGER PROJECT DIRECTOR
ENGINEER ENGINEER TECHNICAL
MANAGER
011 22-05- MOHSIN JITHIN HARISH MAHMOUD ABEER
24

REVISIONS STATUS

REV: NO DATE ORIGINATOR REVIEWED BY APPROVED BY DESCRIPTION OF


SUBMITTAL
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

CONTENT

• INTRODUCTION

• SCOPE OF WORK

• PROJECT REFERENCES

• WORKING ACCESS

• LIGHTING

• PLANT & EQUIPMENT

• POWER

• WORKING PLATFORM

• PERSONAL PROTECTIVE EQUIPMENT

• SAFETY MEASURE

• RISK CONTROL

• WORK METHODOLOGY

• EMERGENCY PROCEDURE

• WAST MANAGEMENT

• APPENDIX
PROJECT NAME: DATE: 22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: RAISED BW/025/AN/24
FLOOR WORK

INTRODUCTION
The purpose of this method statement is to carry out the installation of “Rise floor work” at the Project
by the contract and safety requirements and are implemented throughout the progress of the work.

SCOPE OF WORKS

This method statement scope includes the Hard Landscape Works for the Rise floor work

as following:
1. Preparation of shop drawings and design report with all necessary details.
2. Submittal of all materials that need to be used for the project.
3. Materials procurement as per the approved materials on the project.
4. Installation of Metaleal Items as per approved latest drawings and approved
ms

PROJECT REFERENCES

1. Project Specification
2. Approved Shop Drawings
3. Approved Materials Submittal
4. Approved Method Statement
5. Project Inspection & Test Plan

REFERENCES

Project/Contract requirements

PROJECT NAME: ENHANCEMENT OF JEBEL CASS/BFD/1133-2& AL QOUZ BUS DEPOTS

International standards/Codes
PROJECT NAME: DATE: 22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: RAISED BW/025/AN/24
FLOOR WORK

WORKING ACCESS

• The access/egress for the construction vehicles for the installation of activities shall be as perthe
logistic Plan. Ensure Proper coordination.
All interfacing contractors for Logistics, access prior to commencement of all activities.
• Access/egress to the Project site will be as agreed with the Main Contractor.
• Access/egress routes will / not be blocked
• Ensure proper coordination with all interfacing contractors for logistics and access before the
commencement of all activities.
• Properly maintained to minimize interference with adjoining roads, streets, walks, and other
adjacent occupied or used facilities
• Provide Flagman at critical locations and during hazardous operations.

LIGHTING

Safety Lighting:

Safety Lighting: The minimum safety lighting as per generalrequirements will be provided
by the main contractor.

Task Lighting:

Task Lighting: Task Lighting shall be provided in addition to the safety lighting to undertake the task
with the proper level of lighting to meet acceptable safety and quality of workmanship standards.

PLANT AND EQUIPMENT

• Construction equipment shall comply with the requirements of relevant authorities, industrial
agreements and acceptable industry practice
• Appropriate plants and equipment shall be used for the execution of the activity. The plant, tools
and equipment shall be checked visually prior to use.
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

• All Operators shall be trained and certified by the 3rd party where required. The testing agency
used for lifting equipment must be certified by the Dubai Accreditation Centre
• Curtains or cardboard that can restrict vision must not be installed
• All material deliveries to site will be handled in coordination with site safety requirementsand
also by ensuring proper protection and storage space of the materials.

POWER

• The Power supply used on site for power tools shall be 220v
• Power Supply for site works shall be source by main Contractor.

WORKING PLATFORM

• Proper working platform shall be provided for car shade installation work and painting work.
• The platform can be either stationary or mobile depending on need and accessibility of project.

PERSONAL PROTECTIVE EQUIPMENT

• All operatives involved in the activity shall be provided with Project Specific MandatoryPersonal
• protective equipment (PPE).

Mandatory:

• Helmets, Safety Shoes, Goggles, Hand Gloves, High Visibility jackets as per ,Consultant and
• Main contractor Safety regulation.
• Additional PPE Requirements: (depending upon the type of activities)
• Full body harness, Ear Plugs, Respiratory protective equipment, Impact goggles / Faceshield,

SAFETY MEASURE

Preliminary Activities:
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

• Ensure Proper coordination with all interfacing contractors for access.


• Necessary permits to work from Safety.
• Prior to the commencement of any works, make sure all Method statement, Materials,Shop
drawings and Risk Assessment are approved.

Pre-Construction Activities:

• Ensure the Method statement & Risk Assessment, Material Submittal, Shop Drawing areapproved
prior to the start of this activity.
• Ensure all constraints on operations have been identified and precautions are taken to
commence the activity.
• Ensure Proper access and egress has been maintained throughout the progress.
• Ensure that work area is clear and safe.
• All necessary equipment, personnel, plant and other services required for the works to be
arranged and proper water, lighting, power to be ensured.
• Ensure sufficient lighting is provided by main contractor in place prior to starting the activity.

Note: Supervisors must Ensure HSE Plan and this MSRA are
communicated to all employeesand any sub-contractors involved in this
activity / task

Risks Y/N Risks Y/N Risks Y/N

Airborne Dusts / Fumes Y Excavations N Lifting Operations N

Slips & Trips Y Confined Space N Fire (Hot Works) Y

Manual Handling Y Traffic N Electricity Y

Hazardous Substances N Noise Y Vibration Y


Energized Tools N Heavy Equipment Y Work at Height Y
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

RISK AND CONTROLS

• Hazards / Risks : Please refer Attachment for the Risk Assessment


• Control Measures / Permits : Please refer Attachment for the Risk Assessment
• 3rd party Protection : Please refer Attachment for the Risk Assessment

PROCUREMENT OF APPROVED MATERIALS

• After the receipt of material and shop drawing approvals, the Quantity surveyor will quantify the
materials as per the approved shop drawing and the material order shall be issued to the approved
supplier.
• After the issuance of order to the supplier, the Project engineer will follow up with the supplierto
obtain the delivery schedule of the materials which shall be in line with the project schedule.

WORK METHODOLOGY
PROCEDURE

Hand Tools

• foot tape measure (min. length


• 20-oz. claw hammer with steel handle
• Centerpunch
• Countersink
• Screwdrivers
• foot Hand Level
• Pair of pliers/channel locks
• Chalk line and chalk
• Dry line
• Pop rivet gun
• Awl
• Drill bit set 1/8” to 1/2”
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

• Putty knife, 3” wide


• Utility knife
• (Pair tin shears (good quality)
• Double cup section panel lifter
• Marking pencils
• Rasp and metal files
• Screw gun tip bits

Power Tools

• Laser with target designed for access floor installation.


• Power drill 3/8”
• Adjustable hammer drill 1/2”
• Powder actuator
• Set of powder actuator pins & shots
• Bayonet saw and bi-metal blades
• Electric Miter box saw (optional)
• Metal-cutting bandsaw with cutting speed capability of 450 ft. per minute
• Bandsaw and reciprocating saw blade

Safety items required


• Safety glasses
• Work gloves
• Ear plugs or ear muffs
• Steel toe safety shoes or boots
• Sleeve protectors
• Full-face shields

SITE PREPARATION

The installation of an access floor requires a thorough understanding and control of the
building space receiving the access floor. Attendance at the pre-construction meeting is a
must. Be sure your requirements are known and understood by the General Contractor and/or
the Owner. This includes the following:
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RISEAD FLOOR WORK

• Drawings showing size and configuration of the access floor area.


• Identification of material movement paths within the building. Plan your material paths from the trucks
to the access floor area.
• Arrange for any special equipment needed. The customer must provide a dry, accessible area to
receive and unload material.
• There should be a free path from an elevator and hoists to the area receiving the access floor
material.
• Agreement on means of access to the area: elevator, stairs, street level, loading dock, etc.
• Storage Conditions: Prior to the start of installation, a dry, secure storage space must be made
available for the access floor materials. It should be closed to the weather and should be adjacent to
the area where the floor will be installed.
• Power available during installation. (110 – volt 20 amp supply, minimum requirement).
• Work schedule of the other trades. All overhead work should be completed before the access floor is
installed. If overhead work is done after access floor installation and the access floor is to be used
as a work platform, then it must be adequately protected to prevent permanent damage. This can
be done by placing 3/4" sheets of plywood on the access floor.
• Installation Conditions: The installation area must be closed to the weather with the environment at
50°F to90°F and 20%-80 % relative humidity24 hours a day during and after installation. Tate
recommends that the floor be installed as close to the normal operating environment as possible.
Access floor materials must be stored in this environment at least 24 hours before the installation
begins.
• Identification of type and location of all equipment and services that will be on stands (for
example: air handlers, and power distribution units).
• Determine whether equipment will be installed before or after the access floor.
• Upon the start of installation, the installation area should be free of other trades and their material
and must have adequate lighting and power.
• The subfloor surface must be free of moisture, dirt, grease, oil, and other debris. If a non-approved
sealer (not one approved by Tate) has been applied to the subfloor, make certain the sealer is
• compatible with the pedestal adhesive. Test apply several pedestals as early as possible to be sure
required bond can be achieved.
• The condition of the subfloor should be checked before the start of installation to see if it is
spalled, broken, or dug out. The General Contractor should float a skim coat of cement over areas
that have these conditions. If these conditions are not corrected you may not be able to correctly
adhere and level the pedestals.
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

• Subfloors other than concrete: Be careful of wood subfloors, vibration isolation pads, or concrete
floors with existing floor coverings. If you cannot avoid putting the access floor over one of these
subfloors, you should conduct overturning moment tests to ensure that the pedestals adhered to
them will meet the overturning moment specification
• Verify that the work conforms to the contract drawings and that the starting point is agreed upon
prior to commencing work.

STEP 1 – VERIFY FIELD DIMENSIONS VS. DRAWINGS AND CHECK SUBFLOOR FOR GRADE VARIATIONS

• Find the starting point in the room as shown on the drawings. This point is usually determined by
the Architect, Engineer, or General Contractor. If find that by using the designated starting point the
following conditions exist, ask for permission to move the starting point.
• Check the room dimensions with approved drawings. Set up the laser to verify that the subfloor is
within specifications. The laser will give a constant level line to use as a reference. Lasers with targets
designed for access floor installation are a must.
• Determine the exact finished floor height by locating the benchmark set by the General Contractor.
This could be a doorsill, curb, or a reference point marked on some structure such as a column.
• If the planned access floor elevation must be changed in order to meet the bottom of the door buck
or some other fixed structure, you need to verify that the pedestals are of the necessary height to
make this change. Keep in mind that the pedestals have limited adjustment ranges and that the
minimum stud-to-tube engagements must be maintained.

STEP 2 – CHECK STARTING POINT

• Panels to be cut at the perimeter will be 5" wide or less, thereby requiring supplemental support.
• You will hit objects on the subfloor that could be circumvented.
• The planned starting walls are crooked or not square.

STEP 3 - ESTABLISH CONTROL LINES FROM STARTING POINT

• Once the starting point is established, use chalk to lay out two perpendicular control lines
from the starting point (see Figure #3, control lines ‘A’ and ‘B’). These will be the control
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

lines for installing the access floor. They may be laid out with a tape measure

• For an exceptionally large floor, an electronic transit may be used to establish the control lines. If the corner
of the room is designated as the starting point, then the point should be located 24 inches from the two
adjoining walls in the designated corner.
• The control lines will then be used to check for out-of-square or ‘wavy’ wall conditions. With the lines
drawn along the entire length of each wall, check at various points along each line to determine if the
distance to the wall at any point is more than 24 inches. If this is the case, the entire control line should
be moved closer to the wall so that no measurement between the control line and wall is greater than 24
inches.

A dimension = 12’ point

B dimension = 16’
C dimension = 20’

24” or less 24” or less


at any point at any point
A
from wall from wall

= pedestal shot Chalk lines


points at 10’ intervals 10’ on centre
PROJECT NAME: DATE:1 4-04-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: RAISED BW/018/AN/24
FLOOR WORK

STEP 4 – SPREAD PEDESTALS

• Beginning 10 feet from the starting point, draw chalk lines perpendicular to each control line – at
10 foot intervals.
• This will create a grid, with lines 10 feet on center Each point of intersection in the grid will serve
as a pedestal shot point.
• The pedestals placed at the shot points will be used to set the height adjustments for all other
pedestals (with the aid of a 10-foot leveling bar). Once the lines are drawn, place all pedestals in
their approximate locations. Only the shot point pedestals need to be exactly located at this point.

STEP 5 – LEVEL PEDESTALS IN PROPER POSITION

• Using a laser, shoot in a pedestal assembly to the proper elevation at every chalk line intersection.
Once the pedestals at the intersections are adjusted to the proper elevation, the 10-foot leveling bar
will be used to position and set the height of the other pedestals

STEP 6 - ATTACH PEDESTALS TO THE SUBFLOOR WITH ADHESIVE


PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

• Glue each pedestal base that has been set in place and leveled. Using a spatula-type device, tilt the
base plate without changing its location and apply adhesive to the bottom of the base plate . apply
the adhesive, scrape the spatula against the base plate to remove all the adhesive from the spatula.
• The adhesive should be oozing from under the base on at least three sides. This will give full adhesive
coverage to the bottom of the base plate.
• When installing mechanical anchors, you should install the entire floor by first attaching the
pedestals with adhesive. This gives you the opportunity to make final adjustments to the position of
the pedestals before they are permanently in place After the panels have been installed and all
pedestal adjustments have been made, you will have to remove every other row of panels to access
the pedestals for anchor installation (see Appendix for anchor specifics).
• Do not install the pedestals and stringers too far ahead of the panels. The placement of the panels
will determine the exact pedestal locations.
• Panels should be laid within 30 minutes after pedestal adhesive is applied. Pedestal adhesive
must still be wet installing stringers and panels. ensure that the stringer grid is straight and square
throughout the installation process.
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

STEP 7 - CREATE THE ‘L’ SECTION (POSILOCK™ AND STRINGER SYSTEMS)

• In order to create a square access floor, you will first need to create a section of the access floor that
is shaped like an “L”.
• The “L” section will be used like a giant carpenter’s square for installing the rest of the panels in the
room. Correctly installing this section is essential to the creation of a straight floor where panels do not
rock and where panels are easily removed and replaced.
• Creating the long leg of the ‘L’ section
6:18 • Begin laying in panels at the starting point – lay five rows of panels along the longer wall, making sure
that the pedestals nearest to the wall stay on the control lines. the leg is fully installed, you need to
verify that it is straight by installing a dry line or by using a laser line on top of the access floor.

INSTALL A DRY LINE

• tie a dry line to a pedestal at the wall and bring it to the floor surface between two panels Wrap
the line over a spacer and run it the entire length of the leg and attach it to the corresponding
pedestal at the other end – in the same manner that it is attached at the point of origin (with a spacer
at the top).

1” spacer

control line control line

chaulk line
Use this method for PosiLock
and Stringer systems
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK
CHECKING FOR AND CORRECTING UNWANTED CONDITIONS AS YOU INSTALL

• Regarding Posi Tile® installations: In addition to the checks described below, there are two tests
that must be conducted during the course of the installation when Posi Tile® carpet tiles are to be
installed on the access floor.
Rocking panel condition

As you lay out the panels, be sure they do not rock. If you do find “rockers,” try the following:
• Check for dirt or debris on the stringer or pedestal head and remove debris.
• Check the panel for a burr on the underside of the edge and remove the burr.
• Rotate the panel one-quarter turn. The rocker may simply disappear. If the panel rocks in a new
direction after it has been turned, set the panel aside and try another panel in its place. If the new
panel also rocks, lay another panel adjacent to it.
• If the adjacent panel rocks in the same direction, adjust the height or the perpendicularity of the
appropriate pedestal.
TILTED PEDESTAL CONDITION

• Make sure that all pedestals are perpendicular to the access floor panels. If a pedestal is tilting
due to irregularities in the subfloor, use additional pedestal adhesive and a metal shim if
necessary under the low side of the base plate to make it perpendicular.

• Make sure the entire gridline is straight . If it is not, you may be able to adjust it by bumping the rows of
installed panels with your foot. If this fails, take up every third or fourth row of panels and tap the bases
in the direction of the panels that have to be adjusted. All grid lines should be straight before installing
the perimeter panels! Caution.

STEP 8 - CREATE THE SHORT LEG OF THE ‘L’ SECTION AND FILL IN THE ‘L’
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

• After installing the long leg of the ‘L’, the chaulk control line along the short wall needs to be kept
intact until the short leg is installed. Remember that the ‘L’ section of the floor dictates the
squareness of the rest of the floor. However, it is still possible (particularly in a long room) for a
curve to develop in small increments in the grid.
• Therefore, a laser line or dry line should be kept stretched along the short wall until at least a five-
panel-wide section of the floor is installed along its entire length. Lay five rows of panels along the short
wall, perpendicular to the long wall and Follow the previous step for laying panels and be sure to stay on
the control lines. After laying the complete ‘L’ section, check (and recheck) to be sure it is square!
• Install five rows of panels inside the ‘L’ – along either leg. The leg that choose to build upon will often
depend upon the immediate availability of an area or absence of obstructions.
• continue to build upon the ‘L’ in sections that are five panels wide until it is filled in laying panels in
the first section inside of the ‘L’, and should have someone spreading, leveling and preparing the
adjacent section for panels.
STEP 9 - INSTALLING PANELS AROUND LARGE OBSTRUCTIONS

• The objective here is to wrap a continuous rectangular frame around the obstruction that will be square
with the floor installed. After a continuous frame is constructed, install the cut panels around the
obstruction
Installing Section 1

• Install understructure and full panels as close as you can to the side of the obstruction
that approach.

Installing Section 2

• Install understructure and panels along an adjacent side of the obstruction – as close to the
side of the panels.

• The adjacent side that you choose is the one that faces the other leg of the original
‘L’ section.
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

Laying Out Section 3


• The next step is to construct a parallel section of floor on the other side of the obstruction (opposite
of section.
• To do this you will snap a chalk control line on the subfloor that is parallel to the edge of the section
• This will be your control line for installing the section

To lay out the control line

• On the north side of the obstruction, measure the distance from the edge of the section to the
nearest gridline that exists on the opposite side of the obstruction
• Approximately 10 feet beyond the south side of the obstruction, measure the same distance from the
edge of the section and mark the other end of line.
Installing Section 3

• Position a row of pedestals on the control line, using it as a centerline for the pedestals.
• Install at least five more rows of pedestals parallel to the control line pedestals so that 5 rows of
panels can be installed. No more than 5 rows of panels should be installed at this point – it may be
necessary to move this entire section slightly if it is too close to (or too far away from) the adjoining
section on the south side of the obstruction that about to create (section 4). Make sure that pedestals stay
centered on control line.

Installing Section 4

• Once section 3 extends five panels beyond the south side of the obstruction, you can begin to fill in
the gap between sections 2 and 3. This will be section 4.
• When the entire frame is 5 panels wide on all sides and there are no gaps at the seams where the
sections meet, you are ready to install the cut panels around the obstruction.
• After installing the cut panels you can continue with the remainder of the floor.

INSTALLING PANELS AROUND COLUMNS

• ‘cut in’ panels around columns before installing panels at other perimeter areas. This sequence
will help to prevent the floor grid from getting out of the square. (Areas of the floor around columns
may have shifted due to foot traffic and material movement during construction).
• Before installing any cut panel, you must ensure that there are no gaps between surrounding panels,
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR
and that all surrounding panels can be easily removed and replaced. Once installed, the cut panels
should not be loose.

INSTALLING PANELS AT OBSTRUCTIONS, CURBS, AND PERIMETER WALLS

• Obstruction, curb, and wall areas all fall into the ‘perimeter’ category. If there
is a perimeter area where full panels can be installed, this should be the first
perimeter area of installation.

• If there is not, you should start where the largest cut panels can be installed –
and then move to the area where the next largest cut panels can be installed (the
area with the smallest cut panels will be last).

• All cut panels should be measured and cut to fit for a specific location – cut
panels should never be interchanged!

• When the installation is completed, the Inspection Report (IR) shall be submitted to the
consultant.
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

EMERGENCY ARRANGEMENTS

a. General :

1. The Site HSE department shall be responsible to arrange and coordinate with site
execution teams in arranging Day emergency procedures
2. Emergency assembly point shall be allotted and communicated to all the operatives
in involvedin the job
3. Ensure clear access to the emergency assembly area with signages in place.
4. No construction activity shall block the access leading to the emergency assembly
point. In case of any deviation, the access has to divert and the same shall be
communicated to all the operatives on site.

b. Fire Precautions :

1. Fire extinguishers shall be put in place in each working zone and clear access
shall beprovided to the location
2. All the operatives shall be trained for fire precautions on site
3. A fire warden is appointed and trained from each team of operatives

TRAINING & SUPER VISION

Safety induction training and toolbox talk should be given by the construction manager
and the safety manager for the team, referring to all appropriate information.

a. All personnel should be made aware of the content of this method statement and risk

b. assessments and the team will be instructed to work according to its requirements record
of people receiving the induction should be recorded.
c. Necessary safety or operational training shall be provided to the operatives involved in
the activities
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

SUPERVISION

a. Adequate supervision shall be provided for the execution each activity


b. Project QAQC Engineers shall monitor the workmanship and quality of the works

Personnel Responsibilities
A full and detailed description of the roles and responsibilities of all built-way staff is included within the
Project Quality Plan. For the works as covered by this method statement, the following personnel have
specific duties

Technical Engineer
Specific responsibilities include:
• Responsible for ensuring that the various submittals are timely
undertaken (materials, method statements, workshop drawings,
subcontractor’s issues, technical issues).
• Responsible for quotations as required (materials, subcontractors).

• Responsible for the distribution of documents within built-way site personnel.

Site Engineer
Specific responsibilities include:
• Ensuring that the project is managed safely and meets the
requirements of the project documentation.
• Ensuring that subcontractors and suppliers achieve the on-site required standards

• Ensuring the Client is satisfied with our performance.


• Ensuring performance measurable are delivered.
• Shall refer to the QA/QC Department and the HSE Department
PROJECT NAME: DATE: 22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS DEPOTS

METHOD STATEMENT AND RISK DOCUMENT NO:


ASSESSMENT: BW/025/AN/24
RAISED FLOOR

for advice and guidance when required.


• ensure that operatives comply with the relevant method
statements, Toolbox Talks, and general site briefings.

HSE site representative(s)


Specific responsibilities include:

• Assisting in the production of any health, safety, and environmental documents.


• Monitoring the implementation of health, safety, and environmental requirements.
• Undertaking audits and ensuring that corrective and preventive actions are taken where required.
• Liaison with the senior site staff on health, safety and environmental-related matters.
• will ensure the appropriate safety measures to avoid any unexpected events in the protection,
storage and handling of the material, as well he will ensure that all needed permits shall be
obtained and distributed.
• In additional safety office will conduct toolbox talks with workforce raising and informing of
concerns.
• Stop any unsafe works

QA/QC site representative(s)


Specific responsibilities include

• Carry out the material inspected to ensure that the material received at the site is approved.
• Monitor the works according to the approved method statement, and if necessary will raise a Non-

Conformance report to the /PM and inform the site personnel for necessary action.
• Coordinate with Engineers and Consultants to carry our inspection of the completed works.

Maintaining a record of all QA/QC activities on site.


• Controlling and ensuring all measuring and test equipment on site is properly calibrated.
PROJECT NAME: DATE: 22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT RAISED BW/025/AN/24
FLOOR

• Ensuring that corrective and preventive actions are taken when required.
• Ensuring that staff are aware of their responsibilities in respect of quality issues.

Supervisor(s)
Specific responsibilities include:

• To ensure that all operatives and appropriate subcontractors have been briefed as to the
content of the method statement and the works.
• To adequately control the works as required.
• To ensure the works are undertaken in a safe manner.
• To ensure all operatives are adequately training in their respective works.
• Reporting any un-safe practices on site to the built way site team.
• To conduct daily safety briefing/TBT to their work groups before starting work( dalily
work base)
Technician
Review technical drawings, blueprints, and schematics to determine the requirements for rise floor.
Cut, bend, and shape metal components using a range of fabrication equipment such as saws, drill
presses, and grinders and cutting fitting, electrical, and plumping works
Assemble and construct metal products, ensuring that the final product is accurate, functional, and the
required specifications.
Conduct quality checks on finished products to ensure they safety and quality standards.
Maintains a safe and clean working environment by complying with procedures, rules, and regulations.
Regularly maintain and clean all metal fabrication tools, equipment, and machinery used in the worksite

Health, Safety & Environment


The built-way Project Safety Plan shall be strictly enforced. All works shall be regularly monitored to
ensure full compliance.
Resources – built way shall resource as appropriate the supervision of the works.
PROJECT NAME: DATE:22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/025/AN/24
RAISED FLOOR WORK

Permits – Where required, permits to work will be provided prior to the commencement of works. Permits
shall be issued by suitably trained and experienced HSE personnel only.
PPE – All required PPE shall be issued. Constant monitoring and supervision of the works shall ensure
that always the appropriate PPE is worn by operatives

HOUSEKEEPING

• The work areas shall be clean and tidy.


• No debris from construction activities is allowed to accumulate in the work area.
• Work areas shall be cleaned on daily basis at the end of the shift or on completion of the
activity
• Sufficient Waste collection bins shall be provided at each working zone
• Waste segregation area (where recyclable / landfill materials are segregated, usually as
Steel,Wood, Plastic, Concrete and Debris) shall be established to control the waste
generated on site due to construction.

Waste Management

• Environmental Goals: To implement all reasonable measures to prevent leakage, spillage


or inappropriate disposal of hazardous waste.
• To ensure that a sound approach to waste management is adopted which would include;
waste minimization, reuse, recover, recycling, treatment and proper disposal. Builtway
sites/departments will coordinate with central store in accordance to the disposing of
wastes e.g. batteries, tyres, steel, scrap vehicles and sold vehicles. Central store to ensure
appropriate measures in disposing of the wastes are documented & maintained.
• To maintain a clean and tidy site.
• Environmental Specifications for Waste Management: The HSE officer will ensure the
implementation of the following waste management procedures:
• No waste will be burned on construction sites.
22-05-24
PROJECT NAME:
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: RAISED BW/025/AN/24
FLOOR

Emergency Procedure
The site emergency arrangements are detailed in the Project HSE Plan.The construction
manager/safety manager shall be familiarized with the Emergency Response Plan & Contact
Numbers. Emergency contact numbers to be posted on site.
General
• The project HSE department shall be responsible to arrange and coordinate with
construction team to arranging the emergency procedure
• First aid room should be established to carry on first aid on site in case of any minor
injuries in case of any emergency the safety officer should be informed about the
emergency.
• Emergency assembly point shall be allocated and communicated to all the operatives
involved in the works.
• Ensure clear access to the emergency assembly area with signages in place. No
construction activity shall modern combo roofing system the access leading to the

• emergency assembly point. In case of any deviation the access has to divert the same
shall be communicated to all the operatives on site.

Name Designation Contact #

Mahmud Project Manager 0566968622

Jithin HSE Officer 0524746016

Imran First Aider 0555633746


PROJECT NAME: DATE: 22-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS DEPOTS

METHOD STATEMENT AND RISK DOCUMENT NO:


ASSESSMENT RAISED FLOOR BW/025/AN/24

CONSULTANT: ALTURATH ENGINEERING CONSULTANTS.

FAIZAL ENGINEER 0555322745

AYMAN BAROUDI SITE INSPECTOR 0502711760

CLIENT: R T A (ROADS & TRANSPORT AUTHORITY)

AHMED SHAWKY ENGINEER 0552685357

APPENDIX

Risk Assessment
ACTIVITY TITLE: Risk Assessment RAISED FLOOR

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

✓ Closed ✓ Control
monitoring by measure/risk
assigned assessment shall
foreman. be communicated
✓ Test certificate to the operatives
of machinery prior to the job
✓ Incompetent shall be commencement
operatives produced as ✓ Provide
and work when required. awareness
equipment ✓ All operatives training and
Mechanical
✓ Lack of are competent, toolbox talk
Failure
awareness for trained in the regarding the safe
Transporting of the site activity. movement
Materials by Poor perception
✓ All operatives around the truck

High
emergency

Low
1. 3C 2C - 3C 1C 1C - 1C
machines to of work
preparedness. shall safety mount vehicle
work location. ✓ Personnel Injury /
✓ Collision with Property damage induction and during the
Inexperienced/ ✓ Crush Injuries,
the fixed trained as per offloading activity
Untrained
objects, project ✓ Site speed limits
✓ Collision with requirement shall be abided by
the moving ✓ Operator and the plant
objects Machine shall be operator
3rd party certified ✓ Flag man shall be
and operator assigned with the
should possess machine to guide
valid UAE driving the plant
license to operator.
operate the ✓ Overcrowding in
vehicle the area in the
ACTIVITY TITLE: Risk Assessment RAISED FLOOR

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

vicinity to be
avoided.

✓ Supervision for the


work.
✓ Permit to work
system in place
✓ Manual handling
training
✓ Provision of easy
access to facilities
Mechanical ✓ Job Specific PPEs.
Back injuries
Failure ✓ Tool box talks the
workers prior the
Muscular
Poor perception task.
problems,
Manual ✓ Should ensure
of work Close monitoring of
2. Handling of ✓ Physical injuries 3C 2C - 3C equipment utilizing 1C 1C - 1C
Cuts, activity by a

L
Materials ✓ Property damage in the
Slips and Trips competent supervisor
Inexperienced/ lifting/handling or a
Ergonomics Untrained person is fit for the
Sprains and
Not wearing purpose.
strains
suitable PPE ✓ MSRA should be
Dehydration
communicated to
all workforce
engaged in the
activity and ensure
that all are well
aware of the
hazards and its
control measures.
ACTIVITY TITLE: Risk Assessment RAISED FLOOR

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

✓ Job rotation and ✓ Appropriate PPEs


competent like Hand Gloves,
supervision to be Eye protection
provided. shall be provided
✓ Permit to work to the employees
✓ Incompetent system. for personnel
operatives ✓ Selection of correct protection.
power tools or hand ✓ Right tools for the
and work
tools for the job. right job shall be
equipment ✓ Work involving the used.
✓ Lack of use of power tools ✓ All tools and
awareness for shall be equipment shall
the site appropriately be color coded by
emergency ✓ Falling objects, ✓ Cuts and abrasions, planned, organized competent
Install of rise ✓ Use of and appropriately person.
3. preparedness ✓ Physical injury 3C 3C - 3C 1C 1C - 1C
floor supervised. ✓ The area to be
✓ Falling Defective hand
✓ Ensure that persons kept clean and tidy
objects, tools involved in the use to prevent any
✓ Defective of power tools are Slips, Trips and
hand tools, trained and falls.

High

Low
✓ Flying objects competent. ✓ Ensure that the
✓ Slips, Trips & ✓ Eye wash station or effective
first-aid facilities procedures and
Falls
should be provided control measures
✓ in the site. are in place which
✓ Do not use any are implemented
altered hand tools in order to
for the job. manage the safe
✓ Area to be use of power
restricted only for tools.
ACTIVITY TITLE: Risk Assessment RAISED FLOOR

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

authorized person’s
entry.

✓ Hot work permit for ✓ Pre use inspection


the task. of the tool and
✓ Power tools training electric cables
for the employees shall be carried
involved. out by the
✓ Personnel ✓ PPEs for the operative.
injuries
Personal Injury or workers. ✓ Double insulated
Use of Power
✓ ✓ Lack of
Cut injuries
Property ✓ Supervision. tools shall be used
tools awareness
✓ Flying ✓ Fire extinguisher at to prevent electric
(Grinders, drill ✓ Failure to
4. objects 3C 3C - 3C workplace. shock. 1C 1C - 1C
machines, Damage.
✓ Electric follow work at ✓ Provision of ELCB ✓ Power supply to
Cutting etc.)
shock height for the Use of be taken through
✓ Slips and procedure Power Tools ELCB only.
trips ✓ Face Shield for ✓ Cable
✓ Fire workers using management shall
portable grinders be carried out to
and drills. prevent slips, trips
✓ Tool Box talks for and falls.
the workers ✓ Power supply to
high

Low
involved. be cut off while
ACTIVITY TITLE: Risk Assessment RAISED FLOOR

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

✓ If it’s necessary to repairs or


use 240v tools, then changing drill bits.
it should be ✓ Adequate PPEs
protected with a like face shields
30mA RCD/ELCB. and eye protection
shall be worn by
the workers for
the task
✓ Permit to work
system shall be
followed and
strictly enforced.
✓ Use of 110v tools
to be encouraged.

✓ Daily clean-up is to
be performed
✓ Lack of Injuries ✓ Walkways will be
awareness Cut kept clear at all
✓ Housekeeping
✓ Slips and Trips Broken bone times ✓ Personnel will
5. Waste & waste 3C 2C 3C 3C 1C 1C - 1C
✓ Sharp-edge ✓ Proper disposal of wear suitable PPE
Management disposal
cuttings Land Contamination/ wastes as per at all times
✓ Dust contractor Waste
✓ Accumulation Environment impact
of waste Management Plan.
✓ Waste management

High

Low
training
✓Lack of
✓Especially under or ✓TBTs working in
✓Dehydration. supervision. ✓Heat Stroke
Working in hot behind any plant or high temperature
7 ✓Burns. ✓Heat stroke. 3C 2C - 3C 1C 1C - 1C L
weather ✓Fatality parked vehicle. ✓ Medical assistance
✓Falling ✓Confusion.
Heat related illness ✓Rest Area ORS to be utilized
✓Fall of person ✓Heat Stress
High
✓Cool Drinking water ✓
✓ ✓Nausea
ACTIVITY TITLE: Risk Assessment RAISED FLOOR

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

✓Stroke ✓Mid-Day Break Rule


✓Exhaustion implemented
✓ Collapse Ensure all
✓Rapid weak operatives are
pulse acclimatized of the
✓Head ache. working
✓Weakness environment.
✓Mussels ✓Drinking water
Cramps availability and
✓Vomiting operatives to drink
water as frequently
✓ Unconscious as possible.
✓Take regular breaks
in hot weather.
✓When feel unwell,
inform to
supervisor.
✓Appropriate
training shall be
given to all
employees working
in high
temperature.
✓ Medical assistance
ORS to be utilized
✓Working in ✓ Weather condition ✓Provide heat
✓Poor visibility ✓Fatality
adverse must be monitored stress training and
✓Slippery floor ✓Heat related illness
Adverse weather daily, work ban emergency
8 ✓Heat stress 3C - 4C 3C 1C 1C - 1C

Low
weather condition e.g., Injury High timings response training
illness
sand storm, ✓Work Delay, implemented to workers, TWL
✓Dust struck by
high wind, ✓Property damage strictly during level monitored
lightning
extreme summertime from every 2 hours and
ACTIVITY TITLE: Risk Assessment RAISED FLOOR

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

temperature, ✓fall from June 15-September communicated to


rain, heights & 15 of the year workers
thunderstorm falling object 12:30-3:00PM for
due to high all external works,
wind ✓ heat stress
✓ prevention program
implemented, stop
all lifting operation
during
thunderstorm, all
work at heights
activity not limited
to roof work and
scaffolding works
are not allowed
during heavy rain.
✓Delay in notification / ✓First aid shall be In case of any
response provided if emergency workers
✓Movement of ✓Lack of common necessary shall report
heavy resources ✓All work will be immediately to HSE
equipment ✓Lack of or inadequate stopped and staff / department,
Emergency Unsafe Act and
9 ✓Collision of emergency 4C 2C - 4D workers assembled Manager, 1C 1C - 1C

High

Low
Response Condition
mobile equipment in nearest assembly emergency contact
equipment ✓Language barrier point no 999,998
✓Fatality
✓Personal Injury e

Implement the additional risk controls identified


Risk control-1 TBT should be conducted prior to the star of the activity Date Implemented by PM/HSE

Risk control-2 Competent and trained operators to be deployed at site. Date Implemented by PM/HSE

All Scaffolding structures shall be erected by 3rd


party certified scaffolding
Risk control-3 Date Implemented by PM/HSE
erectors and shall be inspected by 3rd party certified scaffolding inspector
implemented strictly during summertime from June 15-September 15 of the year
Risk control-4 Date Implemented by PM/HSE
12:30-3:00PM for all external works.

Risk control-5 Ensure to Illumination level as per requirements Date Implemented by PM/HSE

It is important to monitor risk controls and review risk assessments regularly. Review is required when there is a change in the process, relevant legal changes, and where a cause for concern has arisen.
Reviews could be scheduled on an annual basis. If the risk assessment has substantially changed a new risk assessment is warranted.

Review date 02.04.2024 Reviewed by Mohmud Authorized by Abeer

Notes: Include legal and advisory documentation that supports this risk assessment be listed. Such documentation includes Acts, Regulations, Standards, where applicable. If the risk assessment for an identified hazard is ranked ’Low’
but the regulatory requirements have not been complied to while establishing and/or implementing controls, the ranking for the assesses risk shall be considered ‘Very High’

Risk Assessment Steps:


Step 1: Identify Hazards Title (e.g. Physical Hazard, Fire Hazard, and Electrical Hazards).
Step 2: List Hazards Details identified (e.g. Tripping Hazard, Flammable Materials stored, Working in Electrical Cabinets).
Step 3: List Causes of Hazard (e.g. Untidy workplace, Hot work, un-isolated electrical supply).
Step 4: List Consequences of Hazard (e.g. Personnel Injury, Fire, electric shock).
Step 5: Determine Likelihood and Consequences to People, Assets, Environment, and Reputation from attached Risk
Assessment Matrix (Page 2) (this should be the most probable outcome without controls and should be listed as 2A, 3D
etc.).
Step 6. Calculate the Risk Index using the Qualitative or Semi-Quantitative Risk Assessment Matrix as deemed appropriate.
This is a product of Likelihood and Consequence and should be stated Low, Medium, High or Very High). Likelihood Descriptor to assist in Qualitative Assessment of Likelihood/ Frequency of Occurrence.
Step 7. List Existing Controls. (e.g. Tidy Site Policy, Hot Work Permit, Isolation of Electrical Supply).
Step 8. List Safety Critical Activities and Additional Controls that may be deemed necessary to reduce risk level to ALARP. A
Step 9: Recalculate Likelihood and Consequences to People, Assets, Environment, and Reputation from attached Risk Has occurred within port industry worldwide.
Assessment Matrix. B
Step 10. Recalculate the Risk Index. Has occurred regionally within port industry or judged likely to have occurred.
Step 11. If residual risk deemed to be High or Very High then risk must be reduced further before proceeding, if risk is C
medium then note that risk reduction must be planned, monitored and documented, if risk is low then risk is acceptable Has occurred in port industry within UAE or judged likely to have occurred.
without required further action. D Has occurred in port industry within UAE on an annual basis or judged likely to have occurred.
E May occur in UAE port industry multiple times annually.

* Risk Assessment Matrix – Qualitative LIKELIHOOD

Consequences P= People A= Assets E= Environment R= Reputation A B C D E


5- Catastrophic Multiple fatalities Extensive damage Massive effect International impact VERY
HIGH
Single fatality or
4 - Severe Major damage Major effect National impact HIGH
permanent disability
Major injury or health
3 – Critical Localized effect Localized effect Considerable impact MEDIUM
effects
Minor injury or health
2 – Marginal Minor effect Minor effect Minor impact
effects
Slight injury or health
1 - Negligible Slight effect Slight effect Slight impact LOW
effects