0% found this document useful (0 votes)
31 views6 pages

BLG A

Uploaded by

billy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views6 pages

BLG A

Uploaded by

billy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

March 01, 2010

Project: PROPOSED RENTAL SPACE BUILDING


Location: SAN PEDRO ST BRGY LAGAO GSC
Company: OctoStar
UNIT COST
ITEM UNIT QTY LABOR &
EQUIPMENT
General Requirements & Preliminaries
1 Mobilization and Demobilization lot 1
I 2 Temporary Facilities lot 1
3 Safety lot 1
Total
Lay-out and staking
1 Clearing and grubbing lot 1 69,600.00
II
2 Lay-out lot 1 23,200.00
Total
Excavation and Backfilling
1 Excavation lot 1 92,800.00
III
2 Backfilling & Compaction lot 1 174,000.00
Total
Concrete Works
1 Foundation
a Concreting 3500 psi Ready mix Concrete m³ 17.5 1,512.06
b Reinforcement Steel kg 1477.32 19.43
c Form Works lot 1 4,350.00
2 Tie beam
a Concreting 3500 psi Ready mix Concrete m³ 13.5 1,512.06
b Reinforcement Steel kg 1974.02 19.43
c Form Works lot 1 7,830.00
3 Pedestal
a Concrete 3000 psi Ready Mix Concrete m³ 10.5 1,512.06
b Reinforcement Steel kg 2552.82 19.43
IV c Form Works 4,466.00
d 20mmØ x 400mm high tensile Anchor Bolt
12mm Thick MS Gusset plate
IV

4 Slab on Grade (power trowel finish)


a Concreting 3500 psi Ready mix Concrete m³ 108 1,512.06
b Reinforcement Steel kg 2627 19.43
c Form Works lot 1 7,830.00
5 Capping Beam
a Concreting 3500 psi Ready mix Concrete m³ 3.5 1,512.06
b Reinforcement Steel kg 752.88 19.43
c Form Works lot 1 2,088.00
6 Consumables lot 1
Total
Masonry
1 6" thick CHB Machine Built 350 psi
a CHB m² 168 252.73
b Reinforcement Steel kg 802.9 22.66
V
2 Louver type block Machine Built. lot 1 30,084.60
3 Plastering m² 326 29.28
4 Miscellaneous lot 1 2,030.00
Total
Wall Framing & Wall Cladding
1 Framing
a MS Cee purlins 1.2mm x 2" x 6' l 68 324.80
MS Square tubing 4mm x 4" x 4" l 15 1,015.00
VI PPGI Rib type roofing lm 326 164.43
2 Painting (2 coat epoxy primer) lot 1 6,081.88
3 Scaffolding lot 1 2,030.00
4 Consumables lot 1 3,246.33
Total
Roof and Roof Framing
1 Truss
a 5/16 thick 3" x 3" MS Angle bar top and bottom l 147 1,078.80
b 1/4 thick 3" x 3" MS Angle bar web l 72 816.06
c 12mm thick MS Plate Gusset shts 2 7,308.00
d 8mm thick MS Plate Gusset shts 10 4,854.60
e 12mm round bar l 48 111.36
16mm Turn buckle pcs 24 31.32
b 20mm Machine bolt with nut and washer pcs 100 121.80
2 Girt
a 6mm thick 2" x 2" MS Angle Bar (topand bottom) l 54 511.56
b 6mm thick 2" x 2" MS Angle Bar (web) l 34 511.56
c 6mm thick 2½" x 2½" MS Angle Bar l 783.58
3 Purlins -
1.2mm thick 2" x 6" Cee Purlins l 169 324.80
VII
12mmØ Round bar sagrod l 48 129.92
VII

¼" thick 2" x 2" MS Angle bar, angle cleats l 5 596.82


4 Roofing -
2mm thick Metal plas roofing lm 1344 231.42
2mm thick Metal plas ridge roll shts 18 669.90
2mm Thick Metal Plas Gutter shts 58 669.90
5 Facia Frame -
6mm Thick 1½" x 1½" MS Angle bar l 77 454.72
6 Bracing -
16mmØ Round bar l 59 209.09
7 Painting (2 coat epoxy primer) lot 1 17,376.80
8 Scaffolding lot 1 10,000.00
9 Consumables lot 1 38,280.00
10 Installation (Equipment only) lot 1 104,400.00
Total
Doors and Windows
1 Doors
a Rool Up Door sets 3
VIII 2 Windows
a Pre Fab Metal Fixed Louver (1.2mm thick) sets 14
b Air Vent Monitor sets 3
Total
Building Permit
1 Plan Preparation (Sign & Sealed) lot 1 20,000.00
2 Processing (Excluding Government Fee) lot 1 15,000.00
XI
a Building Permit
b Occupancy
Total
Total Cost
VAT
TOTAL PROJECT COST

Estimated by:
Eng'r. Jason Ace T. Timbreza
Project Supervisor

Checked by: Approved by:

Engr. Andrew P. Elopre


Project Manager
UNIT COST
TOTAL
MATERIALS

- 15,000.00 - -
- 15,000.00 - -
-
- - -
- -
69,600.00
23,200.00
92,800.00
- -
92,800.00 92,800.00 -
174,000.00 174,000.00 -
266,800.00 -
-
-
5,040.20 114,664.55 4,345.00 26,461.05 88,203.50
64.75 124,355.72 55.82 28,697.47 95,658.24
14,500.00 18,850.00 12,500.00 4,350.00 14,500.00
- -
5,040.20 88,455.51 4,345.00 20,412.81 68,042.70
64.75 166,166.21 55.82 38,346.05 127,820.16
26,100.00 33,930.00 22,500.00 7,830.00 26,100.00
- -
5,040.20 68,798.73 4,345.00
64.75 214,887.61 55.82
12,760.00 11,000.00
5,040.20 707,644.08 4,345.00
64.75 221,131.82 55.82
26,100.00 33,930.00 22,500.00
-
5,040.20 22,932.91 4,345.00
64.75 63,374.85 55.82
6,960.00 9,048.00 6,000.00
- -
1,888,169.99 392,897.38 420,324.61

722.10 163,772.28 622.50


64.75 70,184.80 55.82
85,956.00 116,040.60 74,100.00
83.66 36,818.41 72.12
5,800.00 7,830.00 5,000.00
394,646.09 ok

-
928.00 85,190.40 800.00
2,900.00 58,725.00 2,500.00
469.80 206,758.98 405.00
17,376.80 23,458.68 14,980.00
5,800.00 7,830.00 5,000.00
11,600.00 14,846.33 10,000.00 813.67 14,032.66
396,809.39 ok 14,846.33

3,596.00 687,195.60 3,100.00


2,720.20 254,610.72 2,345.00
24,360.00 63,336.00 21,000.00
16,182.00 210,366.00 13,950.00
371.20 23,162.88 320.00
104.40 3,257.28 90.00
406.00 52,780.00 350.00 12,180.00 10,500.00

1,705.20 119,705.04 1,470.00


1,705.20 75,369.84 1,470.00
2,238.80 - 1,930.00
-
928.00 211,723.20 800.00
371.20 24,053.76 320.00
1,705.20 11,510.10 1,470.00

661.20 1,199,681.28 570.00


1,914.00 46,510.20 1,650.00
1,914.00 149,866.20 1,650.00
-
1,299.20 135,051.84 1,120.00
-
597.40 47,582.91 515.00
49,648.00 67,024.80 42,800.00
- 10,000.00
127,600.00 165,880.00 110,000.00
- 104,400.00
3,663,067.65 ok 3,650,887.65

164,720.00 494,160.00 142,000.00


- -
5,800.00 81,200.00 5,000.00
8,700.00 26,100.00 7,500.00
601,460.00 ok

20,000.00
15,000.00

35,000.00 ok
7,338,753.12 338,704.64 362,348.80
880,650.37 880,650.37 - ###
8,219,403.49 (55,865.60) 8,275,269.09 ###

pproved by:

Engr. Ernie L. Untal


General manager

You might also like