Macmillan Building and Surveying Series: Ivor H. Seeley
Macmillan Building and Surveying Series: Ivor H. Seeley
B.Cooke
M.Sc., C Eng., M.I.CE., M.CI.O.B., F.R.I.CS.
Principal Lecturer in Building.
Uverpool John Moore's University
Third Edition
M
MACMILLAN
© B. Cooke 1981, 1984, 1992
2. PRE-TENDER PLANNING 8
2.1 Tendering Policy - The Decision to Tender 8
2.2 Initial Pre-tender Meeting 11
2.3 Site Visit Report Information 17
2.4 Objectives of Method Statements 24
2.5 Examples on the Preparation of Method Statements 27
2.6 Sources of Estimating Information 39
2.7 Obtaining ~otations from Subcontractors and Suppliers 42
2.8 Build-up of the Estimate 45
2.9 Build-up of Contract Preliminaries 50
2.10 Adjudication of an Estimate 58
2.11 Analysis of Tender Performance and Bidding Theory 61
2.12 Analysis of Tender Performance - Worked Example 66
3. PRE-CONTRACT PLANNING 73
3.1 Pre-contract Arrangements Prior to Commencing a Project 73
3.2 A. Organisation Structure for a Project 78
B. Organisation Structure for a City Centre Development 81
3.3 Site Layout Planning 88
3.4 Placing of Orders for Subcontractors and Suppliers 93
3.5 Requirement Schedules 100
3.6 The Master Programme 109
3.7 Budgetary Control Procedures III
3.8 Cash Flow Analysis - Calculation 120
v
4.3 Programme Sequence for the Erection of Twenty-four
Reinforced Concrete Columns 147
4.4 Short Term Programme for a Laboratory Block 149
4.5 Network Programme for a Bridge Project 153
4.6 Network Analysis - Lead and Lag Terminology 163
4.7 Network Analysis - Crash Cost Application 168
4.8 Precedence Diagrams - Terminology and Relationships 173
4.9 Precedence Networks - Case Study 180
4.10 Cost Envelopes - Principles 185
4.11 Cost Envelope - Worked Example 189
4.12 Ladder Diagrams and Labour Resource Allocation 196
4.13 Ladder Diagram and Resource Allocation - Case Study -
Reinforced Concrete Column Sequence 196
4.14 Time Cost Optimisation Techniques and Least Cost
Scheduling 196
4.15 Time Cost Optimisation Example Project Information 202
4.16 Approach to the Analysis of the Problem 204
4.17-20 Stages of Analysis 204
4.21 Report to Management 211
vii
ACKNOWLEDGEMENTS
viii
PREFACE
ix
Contract management papers in the Institute of Quantity Surveyors
examinations. Undergraduates on building degree courses will
also find the reference useful as an insight into contractual
procedures.
B. COOKE
Stockport,
Spring 1992