Practical Experience Based Part 2 1709541362
Practical Experience Based Part 2 1709541362
Table of Contents
Recommendations & Approvals ................................................................................................................ 8
Dedications .................................................................................................................................................. 9
About Author ............................................................................................................................................. 10
1. Controllers.......................................................................................................................................... 13
1.1. Measurement.............................................................................................................................. 13
1.2. Controller .................................................................................................................................... 13
1.3. Types of Controllers: ................................................................................................................... 14
1.4. Manual Controlling Systems. ...................................................................................................... 14
1.4.1. Incoming water tank level control. ..................................................................................... 15
1.4.2. Outgoing water tank level control ...................................................................................... 16
1.4.3. The manual control system of a Car Driver ........................................................................ 17
1.4.4. The drawback of Manual Control ....................................................................................... 19
1.5. Electrical Gates............................................................................................................................ 19
1.5.1. “AND” Gate ......................................................................................................................... 19
1.5.2. “OR” Gate ............................................................................................................................ 21
1.5.3. “NOR” or “NOT” Gate. ........................................................................................................ 22
1.5.4. Symbols of Gates................................................................................................................. 24
1.5.5. Actual Process Loop & interlocks used in a plant. .............................................................. 25
1.5.6. Gates used (Symbols) in a Pump Motor Protection Systems. ............................................ 26
1.6. ON - OFF Automatic Controller. .................................................................................................. 29
1.6.1. Automatic ON-OFF tank level controller using AND & OR Gates. ...................................... 29
1.6.2. Circuit Diagram ON-OFF Level control Loop ....................................................................... 30
1.6.3. Actual / As-built ON-OFF Tank Level control system. ......................................................... 32
1.6.4. Actual / As built ON-OFF Tank Level Control & Indications Circuits. .................................. 33
1.6.5. Pros & Cons (Advantages & Disadvantages) of ON-OFF tank level control system. ........... 33
1.7. Automatic Water Level Controller .............................................................................................. 33
1.7.1. Example of Automatic control of Incoming Gas to Boiler................................................... 34
1.7.2. Example of Outgoing Automatic Water Level Controller; .................................................. 35
1.7.3. Advantages of Automatic Control System .......................................................................... 36
2. Automatic PID Controller ................................................................................................................. 37
2.1. Function of P, PI, & PID Controller & its Behavior ...................................................................... 37
2.1.1. Proportional Controller “P” in (%) ...................................................................................... 37
2.1.2. Proportional band Action (PB) & Movement of Control Valve ........................................... 38
Table of Figures
Figure 1: Process Variable (PV) .................................................................................................................. 13
Figure 2: DP Cell (Process Sensor)............................................................................................................... 13
Figure 3: DP Transmitter ............................................................................................................................. 13
Figure 4: History Recorder .......................................................................................................................... 13
Figure 5: PID Automatic Controller ............................................................................................................. 13
Figure 6: Concept of Automatic Controller ................................................................................................. 14
Figure 7: Incoming Water Flow Control of a Tank Level ............................................................................. 15
Figure 8: Incoming Gas Supply to Boiler to Control the Steam Temperature ............................................ 16
Figure 9: Outgoing Water Flow control of a Tank Level ............................................................................. 17
Figure 10: Car Driver Controls the Speed & Change the Lain of Road ....................................................... 18
Figure 11 : Use of "AND Gates" in Series & Parallel Circuit ....................................................................... 20
Figure 12: Use of "OR Gates" in Series & Parallel Circuit ........................................................................... 22
Figure 13; “NOT” or “NOT” Gets Function with 1 & 3 Switches ................................................................. 23
Figure 14: Relays are Used in AND Gate & OR Gate ................................................................................... 24
Figure 15: Yamatake Japan Co. Used Symbols in Logic............................................................................... 25
Figure 16: Symbols of Gates used in Logics ............................................................................................... 25
Figure 17: Actual Flow Diagram of Level Control & P/M Protections (Interlocks) Used in a Plant ............ 25
Figure 18: Pump Motor Protection Interlocks (Logics) Diagram................................................................ 27
Figure 19: ON-OFF Automatic Water Tank Level Logic Control .................................................................. 29
Figure 20: ON-OFF Automatic Tank Level Control System. ........................................................................ 30
Figure 21: Automatic ON-OFF Level Control Circuit in Interlocks Drawing ................................................ 31
Figure 22: As Built ON-OFF Level Control System with Incications used in a Plant ................................... 32
Figure 23: Instrument Control Drawings of ON-OFF Tank Level Control System. ...................................... 33
Figure 24: Automatic Temperature Control with Inlet Gas Control Valve.................................................. 34
Figure 25: Automatic Temperature Control with Outgoing Water Level Control Valve ............................ 35
Figure 26: “P” Controller Behavior Against Different PB in %................................................................... 37
Figure 27: "P" & “PI” Action Verses PB & Control Valve Movement .......................................................... 38
Figure 28: PB Action Creates “OFF SET” Between “SP” & “PV” .................................................................. 39
Figure 29: PI Controller Action Against PV .................................................................................................. 40
Figure 30: Derivative Action in PID Controller ............................................................................................ 41
Figure 31: Automatic PID Pressure Control System .................................................................................... 42
Figure 32: Function of PID Control Loop of a Controlling Process System ................................................. 43
Figure 33: PID Pneumatic Temperature Controller .................................................................................... 44
Figure 34: Function or Working Principle of Pneumatic PID Controller ..................................................... 45
Figure 35: YEW System 1100 Controller Modules ...................................................................................... 46
Figure 36: Yamatake Co. PID Controller Modules....................................................................................... 46
Figure 37: Actual Control Loop with PID Controller Modules & S/A Control Valve.................................... 47
Figure 38: Compact Type One Unit PID Controller ..................................................................................... 48
Figure 39: Level Control Loop ..................................................................................................................... 48
Figure 40: Behavior of Level Control Valve Verses "PV" ............................................................................. 48
Figure 41: PC Based DCS PID Controller Configuration............................................................................... 49
Figure 42: PID Controller Functions Tuning with a PC ................................................................................ 49
Figure 43: Closed Process Loop of Feed Water, Drum Level & Condenser Level in a Power Plant ............ 50
Figure 44: 2 Flow Control Valves Opening Behind Each Other With 1 PID Controller ............................... 51
Figure 45: 2 Control Valves Working Opposite to Each Other in Condenser Hot Well Level Control ........ 53
Figure 46: PID Used as Master Controller & Slave Controller is called Cascade Control System ............... 56
Figure 47: 3/2 NC, Solenoid valve is Energized "ON" ................................................................................. 61
Figure 48: 3/2 (NC) Solenoid is De-Energized "OFF" or DC Power Failed .................................................. 62
Figure 49: 3/2 (NO) Solenoid valve is Energized "ON" ............................................................................... 64
Figure 50: 3/2 (NO) Solenoid Valve is DE=Energized “OFF” / DC Power Failed .......................................... 65
Figure 51: Single stage Air Lock Relay ......................................................................................................... 67
Figure 52: Single Stage Lock-UP Relay ........................................................................................................ 67
Figure 53: Double Stage Lock-UP Relay ...................................................................................................... 67
Figure 54: Air Lock Relay (Single Stage) ...................................................................................................... 68
Figure 55: Lock-Up Relay (Single Stage) for S/A Actuators) ....................................................................... 68
Figure 56: Lock-Up Relay (Double Stage) for D/A Actuators ...................................................................... 68
Figure 57: Air Lock Relay (Single Stage) Test Loop for Single Acting Actuators ......................................... 70
Figure 58: Lock-Up Relay (Double Stage) for Double Acting Actuators ...................................................... 72
Figure 59: Open Loop of Blow Down & Closed Loop of Steam, Feet Water & Condensate Water ............ 74
Figure 60: Boiler Blow Down Control Valve Liver Broken ........................................................................... 75
Figure 61: All 3 Fail Safe Systems on Single Acting Actuators Actions (Without Air Supply) ...................... 77
Figure 62: All 3 Fail Safe Systems on Double Acting Actuators Actions (Without Air Supply) .................... 78
Figure 63: Use of BPCS & SIS ....................................................................................................................... 79
Figure 64: BPCS Controlling System With Warning Annunciation System ................................................. 80
Figure 65: Function Chart of BPCS & SIS ..................................................................................................... 81
Figure 66: Actual Hook -Up of Level Switches in Make-Up Tank ................................................................ 81
Figure 67: BPCS & SIS Using Their Own Instruments Separately. ............................................................... 82
Figure 68: Safety Layers of Different Systems in a Plant ............................................................................ 84
Figure 69: Modular Rack (Plug & Play) with Power Supply........................................................................ 86
Figure 70: Modular Rack Base with Plug & Play & Connections ................................................................. 86
Figure 71: Modular Rack with Digital & Analog I/O Cards ......................................................................... 86
Figure 72: Plug & Play CPU & Memory of PLC .......................................................................................... 86
Figure 73: Large Size Electro Mechanical Relays ........................................................................................ 87
Figure 74: Electro-Mechanical Type Programmer With Largo Size Micro Switches ................................. 87
Figure 75: Large Size Electro Mechanical Timers Relays............................................................................. 87
Figure 76: Large Size Solenoid Valves ......................................................................................................... 87
Figure 77: LADDER Language for PLC (Similar to Electrical Circuits)........................................................... 87
Figure 78: PLC Repeatable Cycle of Any Small Unit .................................................................................... 88
Figure 79: Periodically Regeneration of DM Plant. ..................................................................................... 88
Figure 80: SCADA is Gathering Real Time Data from remote locations...................................................... 89
Figure 81: Structure-of-SCADA-System-for Environmental-Monitoring..................................................... 90
Figure 82: Structural Arrangement of DCS In a Plant ................................................................................. 91
Figure 83: Real Structure of DCS in a Plant ................................................................................................ 92
Figure 84: Function Blocks is DCS Language. .............................................................................................. 93
Figure 85: Graphics in DCS Monitor will Show Plant structure, Mimic, & Analog Readings. ..................... 94
Figure 86: Human Machine Interface (HMI) ............................................................................................... 94
Figure 87: Conventional Type Turbine Control Desk & Panel ..................................................................... 95
Figure 88: DCS Controlling System of a Power Plant .................................................................................. 96
Figure 89: Structure Of DCS System of Any Plant With SIS ......................................................................... 97
Figure 90: 3 Line Gas Pressure Control System of Gas Scrubber Station ................................................. 100
Figure 91: Main & Ignition Burner Start-Up Procedure & Tripping Functions. ....................................... 103
Figure 92: Ignitor & Ignition System Circuit Operates with Different Voltage ........................................ 104
Figure 93: Water Tube & Fire Tube Boilers ............................................................................................... 106
Figure 94: Process Variables Loop of Boiler .............................................................................................. 106
Figure 95: Use of DM Plant in Closed Process Flow Loop of Steam in a Power Plant .............................. 107
Figure 96: De-Manualized Water Plant or DM Plant ............................................................................... 108
Figure 97: De-Mineralized & Regeneration Process of DM Plant ............................................................. 110
Figure 98: Chlorine Liquid Gas Injection Into sea Water Process ............................................................. 113
Figure 99: Letters & Nos. Used in Tag Nos. in P&ID.................................................................................. 117
Figure 100: Instrument Symbols in P& ID ................................................................................................. 118
Figure 101: Most Commonly used Symbols & Tag. Nos. of Instruments in P&ID .................................... 118
Figure 102: Symbols of Signals in P&ID..................................................................................................... 119
Figure 103: Valves Symbol in P&ID ........................................................................................................... 119
Figure 104: Valves Function symbols in P&ID ........................................................................................... 120
Figure 105: Different Types of Pumps Symbols in P&ID ........................................................................... 120
Figure 106: Tag Nos. & Symbols used in P&ID .......................................................................................... 121
Figure 107:Chlorine Gas Leakage and Neutralizing System ...................................................................... 126
Figure 108: Natural Gas Pressure Control System in Gas Scrubber Station. ............................................ 127
Figure 109: Risk Assessment Form............................................................................................................ 133
Dedications
I dedicate this book, with special thanks to my beloved Parents, Wife and Children with
their support I learned to be honest, hardworking and follow the right path in life.
The books published are:
Industrial Instrument Training Course (Part - 1 & 2).
Standard Calibration Procedures (SCP).
Practical training plan & calibration execution of field instruments &
practices in the field.
How to write Technical specifications of spare parts of a Power Plant.
Special thanks to Eng. Ahmad Ashknani (IMD Superintendent of Doha West Power
Station Kuwait) motivated me to write in my books using my skill and experience.
Special thanks to Eng. Salah Al-Mail (IMD Superintendent of Doha East Power Station
& Shuwaikh Power Station Kuwait) whom I worked closely at Boilers, Turbines and
Auxiliaries maintenance. In office coordinator.
About Author
Farooq Ali Chaudhry
Senior Instrument Supervisor (Inst. Trainer)
DEPS & SHKPWS – Kuwait
Mr. Farooq Ali Chaudhry has completed his Electrical Associate Engineering in
1974 from Government Collage of Technology Lahore Pakistan.
Experience started from Jan. 1978 to May 1979 at MEW project DEPS for 7 units
including common unit of Distillation Plants (MSF) with IHI CO. This was alongside
with Japanese engineers of sub. Contractor: YAMATAKE INSTRUMENT CO. Japan
– which is one of the well-known industrial instrumentation companies around the
globe. Each plant has a capacity of 6 Million Gallons / Day. Calibrated, Configured
and installed all field and control room instruments with auxiliaries, commissioned
and put in service for production.
Completed 1.5 Year with Sub. contractor YAMATAKE Co. Japan in DEPS Kuwait.
Joined MEW from May 1979 working at Doha East Power & water Station Kuwait,
with a total tenure of 38.5 years and retired January 2019.
During this period Mr. Farooq Ali Chaudhry has worked on 7 units of Toshiba
Turbo-Generators with all auxiliaries, each generator having 150 MW capacities.
Worked on 4 units of FCB Boilers (Each having capacity of 650 Tons/Hr.) & 7
Units of Toshiba Turbo-Generators (Each having capacity of 150 MW.) - with all
their auxiliaries,
Worked 1 year with DESCON Engineering Co. at their Client ICI Khewra (Salt Mine
Area) Pakistan Project. Completed their Extension of Soda Ash Plant in Pakistan.
From Aug. 1990 till Sep. 1991 (Installation, Commission & startup).
Rejoined as Senior Instrument Supervisor & Trainer (for Instrument Engineers
& Technicians) in MEW IMD Section at Shuwaikh Power & Water Station Kuwait
as manpower supply through Al- Dhow Contracting Co from January 2019 till Jan.
2022. (3 Years) Here we have 3 Boilers, 3 Distiller Units. Each unit having a
capacity of each 6 Million Gallons / Day and RO Plant (2 Chains) having a capacity
of 30 Million Gallons / Day.
Engaged with IMD Section Superintendent and Section Engineers by providing
technical support in keeping much complex record of spare parts and streamlining
spare parts processes in MEW DEPS & SHKPWS.
To spread the knowledge, he has gained throughout his service to MEW DEPS.
He decided to pass it on to the coming generation from January 2014 onwards.
This included theoretical and practical trainings to new MEW Kuwaiti employee
may it be Instrument Engineers or Technician.
Total experience is 44 years in this field at Doha East Power & Water Station and
Shuwaikh Power & Water Station Kuwait.
Mr. Farooq Ali Chaudhry has been rewarded and appreciated “Many Times” by
MEW Directors of DEPS & SHKPS for being internally motivated to training young
Instrument Engineers & Technicians making an effort to develop several training
programs (Theoretically & Practically) and refining them throughout.
Part - 2
Advanced Industrial Instrument
Training
(Practical Experience Based)
1. Controllers
1.1. Measurement
Measurement is the process of detecting “PV” & convert it to readings or signals.
1. Process variable (PV) is detected by sensing element,
2. Sensing Element Transfer affects movement process assembly, which
converts the physical change into electrical current output signal 4~20 mADC.
3. The transmitter transmits 4~20mADC to the control room to record the
process's value on the recorder, called measurement.
4. Measuring signal 4~20mADC (PV) is converted into 1~5 V DC & connected to
the controller to operate the final control element (Control valve).
1.2. Controller
The controller is a device that detects 2 inputs signals and transmits 1 output
signal.
1. 1st input signal (4~20 mADC) from the Transmitter converts into 1~5VDC.
2. This transmitted process value (PV) can be recorded in the History Recorder
3. 2nd input signal is from Set Point (SP) (Internally generated(1~5VDC) from the
controller.
4. The controller will calculate the difference (error) between 1st input signal
(Measured Values from Transmitter) & 2nd the input signal from Set Point (SP).
5. According to the error, the controller must send an output signal (4~20mADC)
to move (Open or Close) the final control device.
6. A positioner is fixed on the final control device (control valve).
7. The positioner will move (open or close) according to the Input signal and bring
back the process variable (PV) near the set point.
8. Controller's main function is to keep the Process Value (PV) near the Set
Point. So the process will be called Controlled Process Variable.
He will control the water level and Close or Open the valve according to the set point in
his mind.
Open & Close the Valve action will be opposite to the incoming water level control.
He will Close the valve when the level decreases from the Set Point Value to maintain
the tank level.
He will open the valve when the level increases from the Set Value.
4. Set Point No.2: Road Lanes by looking at the road tracks and mirrors.
5. Deciding of control: A car driver keeps 2 Set Points (Speed & Road Lane) in his
mind and decides the following.
(a) A car driver can increase or decrease the car's speed according to
the road speed sign boards.
(b) He also can decide to change the lane of the road, if the road is empty
and there is no high speed traffic behind of the car.
(c) For this purpose, he has 3 back mirrors to see the back lanes and can
judge whether he can change the lane.
Figure 10: Car Driver Controls the Speed & Change the Lain of Road
All 3 switches are OFF meant contacts are opened (0) & electrical circuit is uncompleted.
As Result Lamp is not Glowing. There 3 options to switch ON.
1. SW-1: Switched “ON” 1st switch. The lamp will not Glow because still circuit is
uncompleted.
2. SW-2: Switched “ON” 2nd switch, still lamp will not Glow, because still circuit
is uncompleted.
3. SW-3: Switched “ON” 3rd switch, The Lamp Will Glow because the circuit is
completed.
Result:
All 3 switches ON, (SW-1 “ON” AND SW-2 “ON” AND SW-3 “ON” then the lamp will
Glow. These are called “AND” Gates in the series circuit.
In this option, all 3 switches are “ON” which means contacts are Closed “1”
1. SW-1: Switched “OFF” 1st Switch, Lamp is still Glowing, because the circuit is
completed by the other 2 switches.
2. SW-2: Switched “OFF” 2nd Switch, Lamp is still Glowing, because the circuit is
completed by other 1 switches.
3. SW-3: Switched “OFF” 3rd switch; now Lamp is not Glowing, because all
switches “OFF” & circuit is uncompleted.
Result:
All 3 switches are “OFF” (SW-1 “OFF” AND SW-2 “OFF” AND SW-3 “OFF”). The lamp
will be “OFF.” These are also called “AND” Gates but in a parallel circuit.
In the series circuit “AND” gate, when 3 switches are “ON” it means contacts are Closed
(1) & electrical circuit is completed. So in Result LED Lamp is Glowing.
So in the above situation 3 switches in a series circuit are (ON), will be converted
into “OR” Gate.
If we switch “OFF” to anyone from 3 switches from the series circuit, the LED Lamp
will be OFF, because the circuit will be uncompleted.
Result:
As you can see SW-1, is “OFF.” As a result of option (1), the lamp also became “OFF”
because the circuit broke from SW-1. It is called the “OR” gate in a series circuit.
In a parallel circuit when 3 switches are “OFF” it means contacts became Opened (0) &
electrical circuit is uncompleted. So in Result LED Lamp is not Glowing.
So in the above situation 3 switches in a parallel circuit are (of) and will be converted
into “OR” Gate.
If we switch “ON” to anyone from 3 switches from the Parallel circuit, the LED Lamp
will be ON, because the circuit will be completed.
Result:
As you can see SW-1, is “ON.” As a result of Option (2), the lamp also became “ON”
because the circuit completed from SW-1 and LED Lamp Glows. It is called the “OR”
gate in a Parallel circuit.
Result:
When all 3 switches “OFF” means input (0), then the LED Lamp will be “ON.” if anyone
switch will is “ON” (1), then relay (R) will energized & relay contact (R-1) will be opened
in result LED Lamp will be “OFF.” We can see the NOR Gate function in the above
figure.
Use of Relay:
We can use a Relay instead of LED Lamp to get many output contacts, as shown below.
These relays are used to protect electrical equipment with interlocks to save from
any incident in a Plant.
Figure 15: Yamatake Japan Co. Used Symbols in Logic Figure 16: Symbols of Gates used in Logics
Figure 17: Actual Flow Diagram of Level Control & P/M Protections (Interlocks) Used in a Plant
BRC Pump Motor is Virtical mounted in the Distilation Plant (MSF), having 4100KW
electrical power. It is the biggest pump motor in the Plant.
We have 3 types of interlocks used in any pump motor protection system as shown in
figure 18 in Logic Drawing.
Any one of these switches is active. It will Trip the P/M. These window are called “First
Out” alarm windows. These window are in RED colours.
Alarm will receice 5~10 Second (As setTimer) before tripping Pump Motor.
Output of “OR” gates should be OFF digit (0) when all reading will be less than the
setpoint values.
1. Winding Temperature (3 Nos) Very High / High High (HH) Trip at 110 oC.
2. Thrust Bearing Temperatures (1/2 Nos) Very High/High High (HH) Trip at 75 oC.
3. Motor bearing Temperatures (2 Nos) Very High/High High (HH) Trip at 75 oC.
4. Cooling Water for bearing temperatures (3 / 4 Nos) Flow Very Low / Low Low
(LL). Trip at speific set point of flow switch.
5. Last staag Brine Level Vey Low / Low Low (LL) Trip at speific Set Point of Level
Switch.
BRC Pump / Motor have 4 starting interlocks as shown in figure 18. Output of gates
are used with digit (1) when active (ON).
(c) Both gates “OR & AND”are used as permissive to start a Pump Motor..
In Permissive to Start Interlocks, we are using both gates (OR gates & AND gates).
“OR” gate is used through an other gate is called “NOR / NOT Gate”. This gate will
convert “OR” gate in to “AND” gate.
1. When there will be no “OR” gate active, then output of all “OR” gates will be (0)
2. So “NOR / NOT” gate will convert in to “AND” Gate to give output (1) when all
“AND” gates will be ON (1) then we can start a pump motor.
3. In case of any one of “OR” gate will be active (1), then “NOR / NOT” gate input
will be (1) and output of “NOR / NOT” Gate will be (0)
4. Then from 4 “AND“ gates, only 3 “AND” gates will be ON (1) but 1 “AND” gate
will be OFF (0)
5. So we can not start a Pump Motor until that one RED alarm will not be cleard
or normalized from the tripping interlocks.
In case of a Horizontal installed Pump Motor or any other Pump Motor, we can add 2
more permissive to start /Trip interlocks.
1. The Inlet valve should be open.
2. Inlet Pressure should not be Very Low.
3. Sometimes No Minimum Flow Valve is designed in the process control. In this
situation, a Motorized Discharge valve is provided. The motorized discharge
valve will open as soon as we start the Pump Motor. It is a safety of pump.
4. Motorized discharge valve must be open, minimum 20% to 30% in 1st 10~15
Sec to keep the pump motor running. If it fails to open with in 10~15 Sec, then
Pump Motor should trip for its safety of Pump.
When the water level drops and reaches a low level switch (LLS). This Low level
switch (LLS) will send signal to the Shut-Off valve to open and keep it open until the water
level is raised & touched the High-Level switch (HLS).
This high level switch (HLS) gives a signal to close the Shut-Off valve and keep it closed
until the water level again drops to Low level switch (LLS).
This automatic valve opening and closing process will continuously work. Every
time valve will open and close whenever water is lowered and raised till the level
switches react for ON-OFF Control to Shut-Off valves.
Both switches are used in series with each other & used close (ON) contacts. One relay
and one solenoid valve are used in the loop. (Solenoid valve operates with essential DC
power supply) The solenoid valve is fixed with a shut-off valve to open and close the air
supply for the Actuator.
Whenever the solenoid valve is energized air supply will move from the solenoid valve
to open the shut-off valve and when de-energized air supply will stop and the shut-off
valve should be closed.
2 Float type Level switches for Hugh & Low level (DPDT contacts) & 2 relays are
used in this circuit.
Two different types of power supplies are used separately from each other.
Figure 22: As Built ON-OFF Level Control System with Incications used in a Plant
Figure 23: Instrument Control Drawings of ON-OFF Tank Level Control System.
An automatic temperature controller controls the temperature near the Set Point with
the help of a control valve.
The automatic controller will sense a difference between process variable (PV) and
Set point (SP).
According to the difference, it will send an output signal to the control valve.
Figure 24: Automatic Temperature Control with Inlet Gas Control Valve
An automatic level controller controls the level in a tank near the Set Point with the
help of a control valve.
The automatic controller will sense the difference between process variable (PV) and
Set point (SP).
According to the difference, it will send an output signal to the control valve.
Figure 25: Automatic Temperature Control with Outgoing Water Level Control Valve
4. If “PB” is narrow, gain output will be high & control valve movement will be faster.
5. If “PB” is wider, the gain output will be less & control valve movement will be
slower.
6. As a result, “PV” will follow the control valve action around the set point (SP).
3. If “PB” will be “100%,” then the output of the controller will be minimum (“0%”)
means (4 mADC). So there will be a 0% output signal that will reach the positioner
to operate the control valve because the valve must be closed at (4 mADC). (This
means a Maximum of 100% damping in the control valve will not move).
4. If “PB” will be “50%” then “50% signal” 12mADC will reach the positioner to
operate the control valve and damping will be in the middle.
Figure 27: "P" & “PI” Action Verses PB & Control Valve Movement
Figure 28: PB Action Creates “OFF SET” Between “SP” & “PV”
Result:
Proportional (P) works like Dampener.
If we increase (PB), Damping will be increased & if we decrease “PB,” Damping will be
decreased.
So it will control the sensitivity of a Control Valve.
1. To increase the cycle time, we add integral time (I) in Minutes in the automatic
controller.
2. The unit of integral is (Repeat /Minute or Minute/ Repeat).
3. Time is involved in opening and closing the control valve. This means the time
duration to open & close the control valve to complete a cycle.
Result:
1. It increases the cycle time to open and close the control valve.
2. It eliminates “OFF-SET” Between “PV” & “SP.”
3. It will take a large stabilizing time for PV
4. So it will make an “Alignment” between of Process Variable (PV) and Set Point
(SP)
Result:
1. In this PID Temperature controller, we can see all PID pneumatic devices.
2. Temperature sensor in the shape of 2 helical spirals. One sensor is used to
measure the actual temperature in the process value & other is ambient
temperature compensation.
3. These sensors will move a pointer on the temperature scale.
4. There is a Set Point knob. An operator can manually adjust it manually and set
the set point needle on the scale.
5. Auto Manual unit (A/M) can change control from Manual to Auto or Auto to
Manual.
6. There is an air pressure regulator to regulate the air supply to the PID Controller.
7. Pneumatic Relay converts temperature signal into Air pressure output signal
(0.2~1.0 Bar or 3~15 PSI) through Nozzle & Flapper, which will operate the
pneumatic positioner and this positioner will operate control valve to control the
process value.
FAROOQ ALI CHAUDHRY 44
Industrial Instrument Training Course (P-2)
1. There are many modules used in a control loop. In the steam flow loop are square
root, multiplier & divider modules. The output of these modules is the input of PID
controller modules as shown below.
2. The module-type rack-mounted PID controller module function is the same as the
pneumatic PID controller.
3. In the electronic module system, Input / Output signals are (1~5V or 4~20
mADC) only instead of Pneumatic input output signals (3~15PSI or 0.2~1.0
Bar).
4. Input signal (4~20mADC) transfer from the field to the control room and it converts
into DC Volts 1~5VDC because the controller accepts only DCV Signal
5. The SP signal is (1~5VDC), also the input of the PID Controller.
6. The Output signal generated by the PID controller is 1~5VDC.
7. The output signal is converted by V/I Converter (From 1~5V into 4~20mADC) &
transmit to I/P Converter. The output of I/P (0.2~1.0 Bar) will operate a pneumatic
positioner to move the control valve.
Or
8. The output signal is converted by V/I Converter (From 1~5V into 4~20mADC) &
transmitted to SMART Positioner to operate the control valve.
Figure 37: Actual Control Loop with PID Controller Modules & S/A Control Valve
4. Avery manufacturing company make their own designs with all same functions we
discussed above.
Figure 39: Level Control Loop Figure 40: Behavior of Level Control Valve Verses "PV"
To maintain the tank level along with SP, PID Controller will move the control valve very
slowly and in narrow bandwidth as shown in the above Figure of behavior.
Figure 43: Closed Process Loop of Feed Water, Drum Level & Condenser Level in a Power Plant
These 2 valves are used with 1 PID controller in a thermal power station. 2 Feed water
flow control valves maintain the feed water tank level. Also 2 gas flow control valves
are used in boiler burners to maintain the steam temperature.
1. Here we will study the (1) Feed Water flow control system, where 2 feed water
flow control valves are used. I have shown only 1 control valve in figure 42.
2. In figure 44, we can see that 2 flow control valves are used to vary the accurate
flow.
3. 1st valve is called the Low Range control valve, which will be opened at Low
flow from 0~25% flow from the total flow of any process.
4. 2nd valve is called the High Range control valve, which will start to open when
the Low range flow control valve is opened at nearly 90%. At this position both
valves will be in service up to maximum load.
5. High range flow control valve will have closed when flow reduces back to less
than 25% as shown in the below picture.
Figure 44: 2 Flow Control Valves Opening Behind Each Other With 1 PID Controller
6. As we know the flow is non-linear. In the same way, when we open a control
valve up to 25%, water flow moves up to 50% of the total flow.
There are many plants where we can use 2 level control valves with 1 PID controller to
maintain the level of liquid.
1. In a thermal power plant, many control loops work in a closed loop process.
2. The condenser Hot Well level control system is the best example in every thermal
power plant to maintain the level. As shown (No. 3) in figure No. 42.
3. Two Control valves in a single control loop with one PID controller but working
in the opposite direction.
4. When one valve opened, then 2nd valve should be closed and vise versa.
5. One level control valve is a hot condenser well make-up level control valve.
6. 2nd level control valve is called Spill Over level control valve as shown in figure
45.
7. This is a Condenser Hot-Well level control loop (under the turbine) where we
have to control the level by 2 control valves.
8. We have Make-up Control Valve taking water from the make-up tank to fill the
Condenser Hot-Well and maintain the level.
Figure 45: 2 Control Valves Working Opposite to Each Other in Condenser Hot Well Level Control
9. The condensate pump always transfers condensate water from the condenser Hot-
Well to the boiler feed water tank and the feed water tank has its own level
controlling system.
10. In this situation, the feed water level controller sometimes does not allow the water
to be received from the hot well to the feed water tank.
11. To access water in the hot well should be removed to maintain the hot well level.
12. For this reason, we need another control valve to remove the access water and
send it back to the make-up tank.
13. This control valve is called Spill Over Level Control Valve.
14. So the Make-up control valve & Spillover control valve is working opposite
each other.
15. Here we can see in figure 44 that a level transmitter is attached with 1 PID
controller having an output 4~20 mADC.
16. The Output of the PID control loop is wired in a series of control valves and
SMART positioners.
17. At 12.00mADC both control valves are configured fully closed.
18. One control valve is configured to operate 0~100% from 12~4mADC.
19. Another valve is configured to operate 0~100% from 12~20mADC.
20. Spillover control valve, SMART positioner is configured at 12~4mADC to open
0~100% (At 12.00 mADC full Closed & at 4.00 mADC full open). So less than
12.00mADC, it will start to open the control valve.
21. Make-up control valve, SMART positioner is configured at 12~20mADC to open
from 0~100%. ((At 12.00 mADC full Closed & at 20.00 mADC full open). So
more than 12.00mADC it will start to open.
22. The graph chart shows that both valves are fully closed when PID output is
12.00mADC.
23. When the Hot-Well level is 50%, the Controller output should be 50% (12mADC)
so both valves should have configured a fully closed position. (100% Closed).
24. When the hot-well level is 50%, the Controller output should be 50% (12mADC.
25. More than 12mADC, the Make-up valve should start to open to maintain the level
in the Hot-Well.
26. Less than 12mADC, Spill Over valve should be open to sending back the water
to the make-up tank to maintain the hot-well level.
5. Whenever there is any change in steam pressure, the main steam pressure
controller sends an output signal as a Master Set Point (MSP) to Air Flow
Controller and Fuel Gas Flow Controller
6. It will increase or decrease the Air flow and Fuel gas flow simultaneously to comply
with the demand of the master controller,. as shown in figure 46.
7. In figure 46, (1), we can see that the main steam pressure is used as Master
Controller.
8. The output of the master controller, controls the Air flow & Fuel Gas flow
controllers related to the boiler to produce steam when demand is required.
9. So Air Flow & Gas Flow controllers will work as Slave Controllers.
Figure 46: PID Used as Master Controller & Slave Controller is called Cascade Control System
10. If Electrical Load demand increases in the Electrical Ring System, then
automatically all cascade controllers will increase their demand to maintain
steam pressure.
11. It will increase steam pressure & flow to run the Turbine Generator at a constant
speed (3000RPM) as required by the central command of electricity.
3 Element means the drum level will be controlled by 3 different types of process
variables.
1. Total Steam Flow.
2. Total FW P/P Discharge Flow.
3. Feed Water Flow after the control valve.
4. A Selector switch is provided between 1 element & 3 elements control
system as Shown in figure 46 (2).
5. Whenever the boiler runs smoothly, the operator can transfer Drum level control
on 3 element control system.
6. As soon as the drum level changes, quick action will be taken by 3 process
variables to maintain the drum.
7. An operator can change it to the single element control system in any emergency.
1. Continuous Production
2. The plant should run safely.
3. No Tripping, No Shut-Down
4. No incident & accident.
There are 3 types of failure-safe systems that are used in any plant
1. Electrical Essential Control power supplies (24 VDC or 110 VDC) Fail Safe
Systems.
(a) All Relays installed in a relay cubical, working on 24 or 110 VDC, used for
interlocks of pump motors & Other Equipment protections.
(b) All Solenoid valves working on 24VDC or 110 VDC are installed in the field to
operate the Shut-Off Valves & Control valves.
All the above failure safe systems are used in the plants and are very important for
safety of the plant from any tripping, trouble, incident, accident or shut down.
All above power supplies, Solenoid valves & Positioners are used only on Shut-Off
valves & Control Valves to operate or hold in the same position.
To achieve the above Aims / Targets, some instruments are used in the plant to protect
any failure or stop production.
Let’s discuss every instrument on by one used for a failure-safe system.
Let’s discuss the actions of “Energized” (ON) and “De-Energized” (OFF) solenoid
valves.
Here we can see in figure 47. Manufacturing of “NC” solenoid valve plunger and
spring function.
Spring is fixed on top of the Plunger.
1. When De-energized solenoid valve, the spring will push the Plunger downward
to close/block the “IN” Port.
2. That is why it is called “NC” Normally a closed Solenoid valve, as shown in
figure 48.
3. When Energized solenoid valve, a magnetic field plunger will be pulled up the
ward and open the air path from the” IN” port to the “OUT” port as shown in
figure 47.
We will see actions of Shut-Off & Control Valves when the Solenoid valve is
“Energized or De-Energized.
Mostly 3/2 (NC) Solenoid valves are used on the single-acting Shut-Off valves & control
valves.
“NC” Solenoid valve will not allow the air supply to pass through it. This means the air
supply is blocked at the “IN” port & “OUT to EXH” ports are already opened to release
the air supply from the actuator to the vent into air.
So “NC” solenoid valve will not allow passing the air supply to operate the Shut-Off &
control valve without a DC power supply.
When the “NC” Solenoid is Energized, the spool will change the position from “NC” to
“NO.”
It means “IN” to “OUT” ports will be opened, and it will block the “EXHAUST” and
control valve working with the air supply. As shown in below figure 46.
The function of the Solenoid valve when control power is available (Energized).
When the essential control power supply is available & switch is “ON,” the Solenoid is
Energized.
The plunger moved from bottom to upward due to the magnetic force (Plunger will be
pulled up) and the air path will be opened from the “IN” to “OUT” port.
So the Exhaust port will be blocked.
When the “IN” & “OUT” port is opened the air supply pressure moves towards the
Control valve or Shut-Off valve to open or close.
When the solenoid is Energized, the spool will have changed its position from 1st
position to 2nd Position (From NC to NO), as shown in figure 48.
We have seen on the last page (3/2 “NC” solenoid valve) when the power supply is
available and the solenoid valve is Energized. It opens the path of air & Shut-Off Valve or
Control valve operates with air pressure.
As soon as the Essential DC power supply fails or Switch OFF, the solenoid valve will
be De-Energized.
The spool position will change & come back to its original position, “NC.”
The air supply from the “IN” port will be blocked and opened “OUT to EXHAUST”
port to vent the air from the actuator.
The control valve will be working with spring action. As shown in figure 48.
The function of the Solenoid valve when control power fails (De-Energized).
When essential control DC power supply “Failed” or switch is “OFF “the DC power
supply, Solenoid will be De-Energized.
So spool will change his position from “NO” to “NC.”
So Plunger will be downward by spring force and the air path will be blocked from
the “IN” to “OUT” port.
While the “OUT & EXHAUST” port is already opened the trapped air will flow from the
Control valve or Shut-Off valve to vent in the air.
So there will be No air pressure available on the control or shut-off valve's actuator.
Then movement in the control valve & Shut-Off valve will take place with Spring Force,
So control valve or shut-off valve will work with Spring Action.
When the solenoid is de-energized, Spool will return from 2nd position (NO) to 1st
position (NC) as shown in figure 48.
This type of valve also has 3 ports (IN / OUT / EXHAUST) and 2 positions, called a 3/2
(NO) solenoid valve.
It can be used on single acting actuators working as shut-off valves or control valves.
3/2 Normal Opened “NO” Solenoid valve action is opposite to the 3/2 Normally
closed "NC" solenoid valve.
This solenoid valve is Normally Opened (NO), which means it will operate the shut-off &
Control valve with air pressure without a DC power supply.
When the solenoid is Energized, the spool changes the position from “NO” to “NC,”
which means it will block the air supply from “IN port” to “OUT port.”
It will open the “EXHAUST” control valve working with Spring Force. As shown in figure
49.
Here we can see in figure 49. Manufacturing of “NC” solenoid valve plunger and
spring function.
Spring is fixed at the bottom of the plunger.
1. When De-energized solenoid valve, the spring will push the Plunger upward to
open the “IN” Port to the “OUT” port. That is why it is called “NO” Normally
opened Solenoid valve as shown in figure 50.
2. When Energized solenoid valve, the magnetic field plunger will be pushed
downward and block/close the air path from the” IN” port as shown in figure
49.
We will see actions of Shut-Off & Control Valves when the Solenoid valve is
“Energized or De-Energized.
The function of the Solenoid valve when control power fails. (De-Energized).
When the solenoid is De-Energized “EXHAUST” port will be closed.
Air will be passed from “IN” to “OUT” ports of the solenoid valve, and it will operate the
Shut-Off valve or Control Valve as shown in figure 50.
This is the 1st position of the 3/2 Normally Opened “NO” solenoid valve.
So air supply pressure will be in action to operate the Shut-Off Valve or Control Valve.
Figure 50: 3/2 (NO) Solenoid Valve is DE=Energized “OFF” / DC Power Failed
Results:
1. The use of the solenoid valves depends upon the system and plant requirements.
2. It depends upon the manufacturer & designer, and how he designed the
Electrical DC Essencial power fail-safe system in the plant that production should
not be stopped.
3. Designer ensured how to operate the control & Shut-off valves to run the plant
process safely without an electrical power supply.
We have 2 instruments to use on air fail safe systems. Whenever air supply fails. This
instrument will react and it will save the plant process or production.
1. Air lock Relay (Single Stage)
2. Lock-up Relay (Single Stage & Double Stage)
Figure 51: Single stage Air Lock Relay Figure 52: Single Stage Lock-UP Relay Figure 53: Double Stage Lock-UP Relay
1. This type of Lock-Up Relay has 2 stages. Used with Double Acting Actuators.
2. Having 5 Ports. (2 IN / 2 Out & 1 Signal Pressure).
3. It has Set Point adjustment screw, set at decreasing air pressure.
4. Both stages work simultaneously to decrease air pressure at Set Point.
5. Set Point Value” is adjusted on Loss of air supply or decreasing air pressure
Lock-Up Relay or Air Lock Relay is a pneumatic switch, working as (ON-OFF Switch),
Having Set Point value and Reset values.
All types of Lock-Up relays or airlock relays work on decreasing air pressure.
It will block the air supply to the control valve or shut-off valves, when there is a loss of
air supply or air supply pressure reduces than Set Value.
Result:
Pneumatic Lockup Relay, switch “OFF” when loss of air supply or air pressure is less
than Set Point value.
It means Block the air Supply to control valves.
Air pressure More than Set Point Value Means Reset (ON) the Lock-up relay.
It means Opening the Air supply to control valves.
Here we can see the different parts and working principles of single stage and double
stage Lock-Up relays.
Figure 54: Air Lock Relay (Single Figure 55: Lock-Up Relay (Single Stage) for Figure 56: Lock-Up Relay (Double Stage)
Stage) S/A Actuators) for D/A Actuators
1. There is a Set Pint Adjustment Screw and spring for forcing downwards to the
upper diaphragm.
2. Increasing or decrees the set point means increases or decreases the pressure
downwards on the upper diaphragm.
3. There are 2 diaphragms used in it, Upper diaphragm & Lower diaphragm.
4. The Signal port always in between both diaphragms.
5. Any pressure entering the signal port pressurizes upward to the upper diaphragm
and downward to the lower diaphragm.
6. Lower diaphragm pushes the bottom plunger, which is Normally Closed (NC).
Air supply from “IN” ports to “OUT” ports will be blocked
7. As pressure increases in signal port, it pushes upward the upper diaphragm and
opens the “IN” to “OUT” ports to allow the air pressure to move towards control
valves or shutoff valves.
8. This function is for both Lock-Up relays. (single stage or double stage)
9. As soon as there is a loss of air supply or reduces air pressure (Air Supply Failed)
in the signal port.
10. Signal pressure force on the upper diaphragm & lower diaphragm will be
reduced. It will be less than Set point spring force.
11. As result of reducing signal pressure on the diaphragms, “IN” port and “OUT”
port will be blocked/closed.
12. It will block the air supply from the Lock-up relay to the shut-off or control valve.
13. Also, it will not allow the trapped air to be released from the control or shutoff valve.
14. So, any control valve or shut-off valve is either open or closed or working in any
middle position. It will be blocked in the same position when air Failed.
15. There will be no movement of valve until air supply pressure is resumed /
available and should be more than the set point pressure.
5.2.2. Test loop Air Lock Relay or Lock-Up relay. (Single stage).
Used for single acting shut-off valve or control valves.
Figure 57: Air Lock Relay (Single Stage) Test Loop for Single Acting Actuators
Here you can see the test loop of Air Lock Relay in Figure 57.
1. An air lock relay or Lock-up relay is a Normally Closed (NC) pneumatic relay,
Without air supply pressure.
2. Most manufacturers adjust the Setpoint pressure on consumer request. It will be
less than the designed pressure of Actuator.
For example;
1. An actuator's designed operating pressure is 4.00 Bar. Air lock or Lock-up relay
can be set at 3 bar or 3.5 bar.
2. It is a critical air pressure to operate the control valve with full load. Less than
this pressure control valve cannot operate with a full load.
3. Less than 3 Bar or 3.5 Bar, an air lock relay or lock-up relay will react & block
the air supply, and the control valve will be held on the same position.
4. The main air supply isolating valve and air pressure regulator is installed. OUT
out of the regulator is attached to a “T” joint.
5. A pressure gauge is fixed on one point of “T” joints. 2nd point of “T” joint is
attached with a flexible tube to the Signal Port and 3rd point of the “T” is
attached to the “IN” port of Air Lock Relay or Lock-Up relay.
6. A flexible tube is attached to the “OUT” port of Air Lock Relay or Lock-up relay to
an actuator (Air to Closed / Spring to Open) as shown in Figure 57.
7. Open the main air isolating valve. Start to increase pressure from the regulator and
view the pressure gauge. Pressure on the gauge will start to increase.
8. As soon as it reaches the designer's set point value (3 Bar or 3.5 Bar), the
pneumatic relay will suddenly open its ports (IN to OUT) and the air supply will
move to the actuator.
9. The actuator spindle will start to move downward to close the valve.
10. Increase the air supply from the regulator up to max. Designed pressure at 4.0
bar. Actuator will be fully closed.
11. Now reduce the air pressure slowly from the regulator. Actuator will start to
open slowly.
12. As soon as air pressure reached less than the set point pressure.
13. Air lock relay or lock-up relay will be in action and block the output pressure
to actuator.
14. This pressure will be trapped in between the lock-up relay & actuator.
15. So actuator will be blocked or stopped at the same position.
16. The actuator position can be 50% or 75%. or any position. It will be ON hold.
Even main air pressure reduced up to “0” Bar.
17. Ensure that there should be no air leakage from the actuator
18. The control valve will hold the same position until the air supply should be
resumed and more than the set point pressure.
19. It is called Reset of Air Lock Relay or Lock-Up relay.
All test function steps are the same as in Air Lock Relay or Lock-Up relay in the
figure: 57.
There are 2 input ports, 2 output ports & a Signal pressure port with a set point
adjustment screw.
All double acting shut-off and control valves will be held in the same position. When air
pressure will be less than the set point value or loss of air supply (Air supply Failed).
It will be Reset when air supply pressure is resumed or air pressure exceeds the set point
pressure.
Calibration procedures are also the same as we discussed in 5.2.2 (Calibration
Procedure)
Figure 58: Lock-Up Relay (Double Stage) for Double Acting Actuators
We have different positioners that control the control valves to control the process
variable.
1. All positioners have Feedback Lever to control the control valve's travel position
(0%~100%).
2. SMART positioner receives signal 4~20mADC directly from PID controller to
operate control valve.
Or
3. Pneumatic Positioner receives pneumatic signal 0.2 ~1.0 Bar from I/P
converter.
4. I/P converter receives signal 4~20mADC from PID Controller.
5. We can configure the SMART positioner functions according to the requirement
of the plant.
6. We can also select the pneumatic positioners, actuators, and other
accessories according to the designed process loop and configure them
according to the plant's requirements.
7. In case of Positioner failure or Feedback Lever Broken or attachment of lever
disconnect from the stem, Positioner Itself will take Action.
8. The positioner will try to control the process according to the plant requirement and
designer configuration to save production.
9. This type of configuration will not trip the plant and not stop the production
Examples of open loop and closed loop flow process with fail-safe system.
Figure 59: Open Loop of Blow Down & Closed Loop of Steam, Feet Water & Condensate Water
2. This valve is installed at an open loop to drain water from the boiler when
conductivity is higher than the designed value.
3. Most requests from the chemical section to blow down the water from the boiler.
4. They are responsible for maintaining the conductivity level in the condensate water
and feed water in the boiler.
5. Boiler condensate water is very costly and taken from the Demineralized
plant.
6. DM Plant removes all minerals and salts from this water to save boiler tubes,
pipes and turbine blades from rust. So cannot waste too much water.
7. This positioner reacts when the Feedback liver comes out from the connector
and is raised. It will keep the valve full closed so that condensate water should
not waist as shown in figure 60.
Example 2: Closed Loop (Steam, condensate & Feed water flow) Figure 58.
1. We can see a Process Closed Loop of Steam Flow, Condensate Water Flow
and Feed Water Flow to run the Turbo-Generator to produce Electricity as
shown in figure 59.
4. 1st action: Full close the control valve. In this situation the flow of the system
will be stopped. So turbine can be tripped and production will be stopped. This
action cannot have approved by the designer for fail-safe system.
5. 2nd action: Full open the control valve. In this situation, there will be maximum
flow in the system. This situation can disturb all process loops (Levels and
flow), but an operator can quickly transfer control from Auto to Manual and
control the entire process manually. He can save the tripping of Turbo-
Generator. So Electrical production will not stop.
6. 3rd Action in case of Air Fail or DC Power Supply Failed. (Control valve will
Hold in same position). In this situation there will be very less disturbance.
7. An operator can quickly handle this and the situation can be normalized with the
help of Instrument or Electrical Sections to Restore Air Supply or DC Electrical
Power Supply.
8. So in the above situations 1st action can’t be approved in closed loop system.
9. Only 2nd and 3rd action of failsafe systems can be approved for continuous
production.
To understand the strategy of the manufacturer or designer, he can choose the best
choice of positioner’s action to save the production.
We have to understand the close and open loops of the power station. As shown in
the figure: 59.
Mostly manufacturers & designer have only 4 options.
1. Full open the control valve.
2. Full close the control valve.
3. Hold the control valve in the Same position.
4. Use SMART Positioner, which can configure the all functions & options.
As we understand the all 3 Fail Safe Systems are used on Shut-Off Valves and Control
Valves for continuous production & No tripping of plant.
In the case of any one from 3 failure systems. (Solenoid Valves, Air Lock relays or
Lock-Up relays and Positioners) are installed in the field on Shut-Off valves and
Control Valves. as mentioned below.
1. Control Power 110 VDC Fail Safe System. (Means Solenoid Valves will be De-
energized)
2. Air Fail Safe system (Means there is No Air supply on Control valves & Shut-off
valves).
3. Air Lock Relays or Lock-up Relays are used at single-acting or Double Acting
actuators to open/close or hold in same position.
4. Positioner Fail Safe System. (Means Feedback Lever broken or Positioner
malfunction).
Figure 61: All 3 Fail Safe Systems on Single Acting Actuators Actions (Without Air Supply)
Figure 62: All 3 Fail Safe Systems on Double Acting Actuators Actions (Without Air Supply)
The above 2 pictures show all three instruments used with single acting and double
acting actuators at control valves. (Positioner, Solenoid Valve and Lock-up Relay)
Result:
1. Fail Actions in Control valves: Air Supply Failed, Electrical Power Supply Failed
or Positioner Failed in single acting & Double acting control valve actuators; valves
should be held in the same position
2. Fail Actions in Shut-off valves: Shut-Off valves don’t use positioners on single
acting or double-acting actuators. So only possible to fully open or full closed
the Shut-Off Valve.
3. Positioner Failed: Positioner configuration will decide to operate the control
valve.
4. Fail Safe System is a Stand-Alone System. It works with all shut-off valves
and all control valves.
5. So there is No link with Basic Process Control System (BPCS) & Safety
Instrumented System (SIS).
The pictures show that every system works separately and has its own instruments.
1. Basic Process Control System (BPCS) has its own power supply unit, CPU, Digital
I/O cards & Analog I/O.
2. Annunciation system (Warning system) using his own power supply unit, CPU,
Digital I/O cards.
3. Both above systems don’t have any link with each other
4. Even field instruments also used separately as shown in figure: 64 & 67.
5. BPCS system is a Flexible Analog Process Control System
6. This system allows changing the process conditions frequently. It controls the
basic parameters of process.
7. It will control all types of analog processes (Like: Pressure, Temperature, flow &
Level) in safe limitation areas.
8. It can give best performance from minimum to maximum limitations in safe
conditions.
9. This system deals with P, PI & PID controllers.
10. This controlling system can be easy to change the conditions control system.
11. From AUTO to MANUAL to control the process manually or MANUAL to AUTO
to control the process on AUTO.
12. It can change the SET POINT (SP) or BYPASS the PID control system.
13. Most chances of failure of the BPCS is malfunctioning any controller or control
valve.
14. Also possible human mistakes or errors.
15. This system runs all the time to control the process and has no fault diagnostic
provision.
16. BPCS works normally and controlling plants under normal flexible limitations all
the time.
17. It has the flexibility to control the process variables.
18. Figure 64 shows the real idea of BPCS, warning and Critical alarms systems(SIS).
19. In figure 65 a real as built picture of make-up tanks in the power plant have safe
area of level PID controlling system (BPCS), then Low & High Level swathes for
warning, and critical alarms (Very Low & Very high) for reaction of safety
instrumented system (SIS)
Figure 65: Function Chart of BPCS & SIS Figure 66: Actual Hook -Up of Level Switches in Make-Up Tank
Figure 67: BPCS & SIS Using Their Own Instruments Separately.
3. Boiler Steam Pressure: The pressure will be controlled by BPCS within safe
limitations. But as soon as pressure reaches high limits, it will give a high pressure
alarm in the Control room. If steam pressure is still out of control and reaches very
high limits, SIS will trip some burners or boiler; also it will trip the feed water
pump to save the plant.
4. All types of safety layers shown in figure 68 with their own instruments.
1. Many failures can be happening in the plant and may not be self-diagnostic.
2. Mechanical safety device: If SIS does not act and all SIL level fails & still steam
pressure is out of control and reaches the mechanical safety set point value.
3. A mechanical safety device will activate and open the Safety Relief valve to
vent the steam pressure in the air to save the plant from overpressure or blasting
any pipe.
4. It can happen when mechanical relief valve is stuck-up and does not function.
6. If the Mechanical Relief valve never checks its operation, then incident /
accident can be happened and haram full for human life.
7. If all safety features fail and all mechanical devices fail to operate, then there
will be an accident.
9. There can be any type of fire in the plant. (There are many types of fire in any
plant). Like: Electrical fire, Oil Fire, Wood fire …. etc.
10. All types of firefighting systems should be in service to remove fire from the plant.
11. Firefighting Equipment and fighting systems also should be tested periodically.
12. Any plant needs to work in safe conditions to save the plant & human lives.
14. Every year all safety instruments, mechanical devices and firefighting
systems should be overhauled and tested & keep record.
PLCs were first developed in automobile manufacturing to provide flexible, rugged and
easily programmable controllers to replace hard-wired relay logic systems. Since then,
they have been widely adopted as high-reliability automation controllers suitable for
harsh environments.
PLC can range from small modular devices with inputs and outputs (I/O) cards in a
housing integral with the power supplies, Network, CPU with Memory and Digital &
Analog I/O Cards, in to large rack-mounted modular devices with thousands of I/O
signals. It has been programing to control machine operation are typically stored in
the memory.
Figure 69: Modular Rack (Plug & Play) with Power Supply. Figure 70: Modular Rack Base with Plug & Play & Connections
Figure 71: Modular Rack with Digital & Analog I/O Cards Figure 72: Plug & Play CPU & Memory of PLC
PLC have largely replaced electro mechanical type instruments Like large size of
relays, drum sequencers, the large size of solenoid valves, big size of micro switches,
electro mechanical timers and large size of step programmers (cam switch type) etc. of
any small unit. As shown below.
This all hardware can be replaced with PLC system.
Figure 75: Large Size Electro Mechanical Timers Relays Figure 76: Large Size Solenoid Valves
Figure 78: PLC Repeatable Cycle of Any Small Unit Figure 79: Periodically Regeneration of DM Plant.
PLC will only process one Program over and over by the interval of time.
Like: Regenerations in Demineralized Water plant, when conductivity cross more than
1Micro Moh.
Chlorination plant for shock chlorine injection in sea water intake 3 to 4 times every
day.
8. SCADA System
SCADA System means Supervisory Control And Data Acquisition System.
SCADA (supervisory control and data acquisition) is a category of software applications for
controlling industrial processes, gathering data in real-time from remote locations to control
equipment and conditions.
SCADA systems are used by industrial organizations and companies in the public and
private sectors to control and maintain efficiency.
It is used to distribute data for smarter decisions, and communicate system issues to
help operators and other employees to analyze the data and make important decisions.
SCADA system has 4 stages.
1st stage: Contains the field measuring devices such as flow, level, pressure and
temperature, sensors, and controlling the all processes through the final control
elements, such as control valves or Shut-Off Valves.
2nd stage: Contains the input/output (I/O) modules, and their associated distributed
electronic processors and controllers.
3rd stage: Contains the supervisory computers, which collect information from the
processor, controllers through the network station, and provide all the information to
HMI for operator.
4th stage: is the production control stage, which does not directly control the process,
but it is related with data logging, monitoring production and targets.
Figure 80: SCADA is Gathering Real Time Data from remote locations
Structure of SCADA
4. It differs from the centralized control system wherein a single controller at central
location handles the control function,
5. DCS each process, element, machine or group of machines is controlled by a
dedicated controller.
6. DCS consists of many local controllers in various sections of plant control area and
are connected via a high speed communication network. As shown here.
7. DCS creates new world of technology. DCS control systems use different
languages through the PC. The most commonly used language in DCS is
Function Block. As shown in the below pictures.
8. Operating Stations (OS) is the PC through which an operator can operate a big
Power Plant or all types of Plants.
9. DCS takes less space, performs more complex tasks, and is more
customizable than the electro-mechanical technologies they have replaced.
10. Analog Input / Output cards receive analog input signals (All types of analog
signals like: 4~20mADC, from transmitters, T/C, RTD and all types of Transducers)
from the field and transfer all information through the network controllers and fiber
optical cables to the OS & DCS Server, which saves & transfers the data to OS
(Operator) or HMI. These analog readings can be viewed on the LED monitor. The
process variable (PV) can be controlled through the analog output cards from the
Plant Operating Station (POS) or HMI to the field controlling instruments.
11. Digital Input / Output cards: Same way digital input/output signal also transfers
through the digital input/output cards. So the digital output signal transfers through
the network controllers to the DCS Server & OS (Operator) So We Can Open /
Close any shut-off valve and safety protection systems from the HMI through the
DCS Server, also we can Start / Stop any pump motor through the same way.
12. So all graphics and readings can be viewed on the LED Monitor and also can
be control “PV” from the “OS” (from Operator) or HMI.
13. DCS Server has all the technical software that belonged to the plant. It is used
to store all types of data of the all DCS system of a plant.
14. Engineering Station (ES) is used to create a graphic, change in any system's
configuration, diagnostic troubles and any modification in the DCS system.
15. Operating Station (OS), Operator used to control and operate a big plant like a
Power Plant / or any heavy industry, having multiple controlling systems with many
I/O cards. (Analog input / Output cards & Digital input / Output cards).
16. So all graphics and readings can be viewed on the LED Monitor and also can
be controlled “PV” from the “OS” (from Operator) or HMI.
Figure 85: Graphics in DCS Monitor will Show Plant structure, Mimic, & Analog Readings.
17. Each I/O card has 8 channels up to 64 Channels. (Depend upon the design &
use of the system requirements)
4. HMI (Human Machine Interface) controls small plants like chlorination plants or
DM plants.
The difference between Conventional Control Room and a DCS control Room of a Power
Plant is shown in the pictures below.
An operator cans start the plant from 1 computer. Large size of monitor is provided to
help operators.
DCS Controls different types of systems / Loops / sections of a Plant Including PLC &
SCADA systems with Wireless facilities.
5. DCS eliminates the following from the conventional Relay Room & Control room.
6. Conventional Desk / Panels and all types of switches installed on the desk and
panel.
7. All analog cubical (Module based analog cubical).
8. Different types and size of Indicators.
9. Lighting Indicating units.
10. Different types and size of Recorders.
11. All types of Flow Counters.
12. TPL Switches (Start/ Stop motors)
13. Big size of annunciation panels.
14. Big sizes of analog Controllers & set point stations.
15. Electromechanical Relays & timers.
16. Different types of alarm cards.
17. Mimics and many more instruments installed on desk and panel.
18. So all above instruments are configured in DCS software program,
19. No more hardware is required in DCS.
1. If we want to change the duty of lines from (Line A) to (Line C) then slowly
increase the Set Point of (Line C) controller and match or a little higher than (Line
A) controller.
2. Now start to reduce the set point slowly of the (Line A) controller same as (Line
C) controller.
3. Keep close eye on (Line C).
4. The control valve of (line C) should start to open slowly and maintain the gas
pressure equal to Re-adjusted SP as 1st priority.
5. Then (line A) the control valve should start to close slowly and be fully closed.
6. Automatically both lines should shift the gas pressure load smoothly without
any trouble.
7. Then (line A) will go to 3rd priority and stay in standby mode.
8. Automatically (Line C) will become in service and pick all the load.
9. After changing duty, Now Line “C” will be the 1st priority & Line A will be the
3rd priority.
Figure 90: 3 Line Gas Pressure Control System of Gas Scrubber Station
1. After Start of FD fans, complete all steps till reach to start 1st burner.
2. BFW P/P should be in service at minimum flow.
3. Drum Level should be normal.
4. Boiler / Furnace Purge should be completed before start 1st burner.
5. Step no. 5 is most important for safety of boiler. If any fuel gas is accumulated
in boiler, serious accidents can happen.
6. Boiler protections & Safety system should be completed.
7. Main Fuel Gas Lines and Main Fuel Oil protection & safeties should be
completed.
2. Main Gas pressure can be controlled between (0.5 ~ 1.5 Bar or more) according
to the No. of Burners for Wind Box Pressure and Air Flow.
3. Pressure Regulating valve / Self Regulating valve regulates 0.5 ~ 0.6 Bar before
starting 1st burner.
5. Best ratio of Gas flow and Air flow is required for best Flame.
7. If pressure still increases, the safety vent valve will open at 1.7 Bar and vent the
gas into the air.
8. Low gas pressure switch installed at main gas line and set point, set at 0.2 Bar
Decreasing.
9. High Gas Pressure switches installed at main gas line and set point, set at 1.2 bar
increasing.
10. If pressures decreased up to 0.2 Bar or increasing 1.2 Bar, these switches will
not allow starting any burner as shown in figure 91.
Figure 91: Main & Ignition Burner Start-Up Procedure & Tripping Functions.
11. There is Low / High Gas pressure switch in the ignition line. In case of low or
high gas pressure, Ignition will not start.
13. There is Low Air pressure switch in the air line. If the air pressure is Low, then
also burner will not start
2. After purge completion, shut-off valves will open for 5 to 10 seconds to fill the main
and ignition gas lines.
Figure 92: Ignitor & Ignition System Circuit Operates with Different Voltage
Figure 93: Water Tube & Fire Tube Boilers Figure 94: Process Variables Loop of Boiler
12.2.2. Result
This is the main reason we need a plant that can remove all salts from the water. The
name of that plant is De-Mineralized plant or DM Plant.
Figure 95: Use of DM Plant in Closed Process Flow Loop of Steam in a Power Plant
1. 1st chain will be in service while “2nd” chain will be on Regeneration mode.
After regeneration 2nd chain will be standby.
2. When 1st chain has exhausted it will go to Regeneration and after regeneration it
will be on standby Mode.
3. 2nd chain will be in Service until it has exhausted.
4. These cycles will automatically change until the output conductivity is
maintained at 0.05~1 Micro Mohs / mS/cm.
5. Before every chain, there are more vessels to filter & remove the hard particles
and de-mineralize the water. As shown in figure 96.
1st stage: Cat-Ion Tank. The feed water or raw water (Water from MSF or RO plant) is
passed through the first vessel which contains strong base cation resin in the form of
Hydrogen Ions (H +), where upon all the positively charged ions (sodium, calcium,
iron and copper etc.) are exchanged for Hydrogen ions.
So (H +) Ions are removed in 1st stage (From Cat-Ion Tank)
2nd Stage: An-Ion Tank: The outgoing water from Cat-ion tank (after 1st stage) passed
through another vessel containing strong base anion resin in the form of Hydroxyl
like: (OH -), where upon all the negatively charged ions (chloride, sulfates, nitrates,
etc) are exchanged for hydroxide Ions which then combine with the hydrogen ions to
form water
So (OH -) Ions are removed in 2nd stage (From AN-Ion Tank)
3rd Stage: Mixed Bed: Mixed Bed is a single vessel unit, which combines Cat-ion
resin and An-ion resin/exchangers in a single column.
Mixed bed demineralizer is considered more efficient in many ways when it comes to
requiring high-purity Demineralized Water.
It is used as a polishing unit to purify water to higher levels, treated through 2 Beds
of ions (Cat-ion & An-ion).
So both Ions (H + Ions & OH - Ions) are removed in 3rd Stage
Result:
Finally, “0%” Salt water comes out from DM Plant having conductivity 0.05~1
mS/cm (Micro Moh.)
Regeneration is a process of restoring the power of Cat-Ion resin & An-Ion resin or
enhancing active ion concentration level.
Depending upon the frequency of use and DM Water (De-Mineralized water) output
condition.
In this situation, the DM plant can’t maintain water conductivity of less than 1mS/cm.
The resin becomes exhausted and cannot de-ionize the raw water, in other words,
their power of removing ionic materials reduces and active ion concentration reaches a
low level.
So Restoring their process power (Cat-ion, An-ion and Mixed Bed) or enhancing
active ion concentration level is called Regeneration.
In this process exhausted ions (Cat-ion and An-Ion) are recharged with Hydrogen Ions
(H + Ions) means Hydrochloric Acid (HCL) & Hydroxyl Ions (OH - Ions) means Alkali -
Caustic Soda (Na-OH).
Never use Pure Acid and Pure Alkali in regeneration process.
During regenerations Diluted Acid and Diluted Alkaline should be used to maintain PH
& Conductivity so that Cat-Ion Resin and An-Ion Raisin should not be damaged as
shown in figure 97.
To control them and keep them away from the pumping plant, having a huge seawater
suction for power plant cooling. We are using toxic gas is called Chlorine gas.
This gas is yellow color, Havier than Air and very high toxic for any life. It should be
handle very carefully.
The growth of these marine organisms can reduce the thermal exchange rate, restrict
water movement, clog the pipeline, or erode and perforate the pipeline's wall.
Under extreme circumstances, power plant may have to shut down to clean and
repair the pipeline system.
In such case, many marine organisms had to be removed from the pipeline during a
single cleaning process.
Many techniques have been developed in the world. One of them is adding chlorine to
sea water is a widely accepted method to simply and efficiently prohibit fouling.
The use of chlorine to avoid fouling occurrence has the supposed benefit of rapid
decay of chlorine toxicity.
One major drawback of chlorine is that interactions between chlorine and seawater
can induce complex chemical reactions that produce compounds with higher
toxicity.
So chlorine is used as an anti-fouling reagent in sea water in power plants.
The outgoing sea water from Power Plant has residual chlorine 0.2mg/l, which is
acceptable.
Figure 98: Chlorine Liquid Gas Injection Into sea Water Process
6. By heating the water in evaporator liquid chlorine will convert into gas form.
7. This chlorine gas will be transferred through the Pressure and Vacuum regulator
to the chlorinator.
8. Manual or automatic flow controller will transfer this chlorine gas to the sea water
pipeline through the injector creating a vacuum to suck the Chlorine gas from
chlorinator.
9. Then this chlorine solution injects to the sea water, where Sea Water Supply Pump
are located in sea bay.
10. In case of chlorine Gas leakage, an automatic sensing system is installed.
11. A vacuum pump will suck all the yellow toxic Chlorine gas and send it to a
neutralization tank to neutralize.
12. In reaction to the naturalization process, gases will be produced, which are
removed by a fan and vent into the air.
So all above tag Nos. Showing the properties being measured in the plant.
Figure 101: Most Commonly used Symbols & Tag. Nos. of Instruments in P&ID
Signals symbols:
Valves symbols
Examples of P&ID;
We can see the Tag Nos. and symbols are used in these P&ID.
It means to check, line-up & test all systems including Safeties of a plant through
some procedures, before start-up is called Commissioning.
As we know, any newly installed plant or after annual maintenance of any plant, every
section (IMD, EMD, MMD and OPERATION) prepares and tests their work.
Operation Section prepares the process loop and line up the all isolating valves including
sequence test of logic control circuits & analog control loops with the help of all sections
through some written procedure.
Electrical Section test and prepare their breakers, complete all connections of motors
and field equipment and all other electrical equipment after repair and cancel the annual
maintenance work permit.
Mechanical Section test and prepare their equipment Like: After repair, assembling of
all pump motors, installing of all mechanical devices, removed during annual maintenance
and cancels the annual maintenance work permit.
Instrument Section Also checks and line up the field instrument after repair and
calibration. Power supplies of supervisory & logic instruments should be “ON”. All
instrument loops should be healthy. All instruments should be ready to put in service
without any trouble.
Controlling Loops, critical alarms, Interlock and Sequence test of all instruments
in the plant. like: pump motors and other systems to be tested with co-ordination
of all sections.
All type of annunciation window should be normalized and the annual maintenance
work permit should be canceled.
Above mentioned process is called the commissioning of any plant.
Whenever working in danger area where danger can be harmful to the persons.
1. Calculate the risk and fill the risk assessment form to reduce the danger.
2. Take approval from the safety department.
3. Always use PPE (Personal Protection Equipment)
Let us understand the safety measures and precautions in dangerous areas and take
safety clearance from safety department if required.
1. Face protector.
2. Heat Resistance Gloves.
3. Away from steam if there is leakage,
16.4.6. Welding
1. Use safety goggles or a screen during welding.
2. Never see directly to Arc during welding. (Arclight is dangerous for the eyes).
3. Never use welding near gas lines, or oil lines.
Chlorine gas is very toxic, yellow in color and heavier than air. We can see it near the
ground level because of its color. It suddenly affects the throat.
16.4.8. Natural Gas leakage (In Gas Scrubber stations & gas lines
near boilers)
Natural Gas is lighter than air, Not visible, Mixes in the air very soon; only we can smell.
Figure 108: Natural Gas Pressure Control System in Gas Scrubber Station.
16.4.10. Chemicals
1. Use PPE
2. Use a face protector shield
3. Use proper Gloves (Anti- Chemical)
4. Always away from drained /spilled/splashed chemicals on the ground.
5. Use the suction pump to collect splashed chemicals.
6. Spray water facility should be provided to wash affected body from chemicals.
1. Don’t go near the sea. (Sea bay is very deep and has a very huge suction).
2. Don’t move around the trash rack.
3. Don’t catch the reeling near the sea. (May be too much rusty)
4. Care full from the traveling screen.
5. Don’t wear slippery shoes.
1. At the initiation stage, take approval from the operation engineer and request WP
to work on the desired instrument.
2. If any instrument is working on PID controller, then request to transfer control from
Auto to Manual in case of running unit.
3. If any widow of alarm is not received in the control room, then check the
annunciation lamps working in the window.
4. Check the complete loop of switch is healthy.
5. If any switch is working with the interlock, then take approval to bypass interlock if
possible.
6. Check the isolating valve near the process line and before the instrument is
opened and working properly.
7. Check the impulse lines or capillary lines are clean.
Description of
Likely Hood Examples
(A)
Not Likely Very little risk is present; only under exceptional
(1) conditions would an accident or incident occur.
Severity Example of
of Hazard Injury
Very Low Scratch, minor cut, Injury allows normal work after First
(1) Aid treatment, Typical there is no lost time.
Low More severe, sprain, strain, minor burns, and normal work
(2) may not be immediately possible following treatment.
There may be some loss of time.
Medium Burns severe fractures, minor amputations, and
(3) temporarily disabling back injuries. The accident almost
definitely reportable loss of time or Serious injury.
High Permanent disability, serious loss of body part.
(4)
Very High One or more fatalities (Dead Body)
(5)
The End