Annexure 1 Priced Bill of Quantities
Annexure 1 Priced Bill of Quantities
3. Temporary Works
Site office, storage, labour camp,
1. Temporary Facilities other temp building, access road. 58,578,150
Hoarding maintenance
Required surveys, surveying
2. Site Survey equipment 2,124,000
T/C, Hoist, Pump, CPB, Pipes, 4 Luffing T/C, Hoist, Pump, CPB and pipes
Mobile cranes, small equipment &
procured by the client. All operations and
4. Heavy Equipments & Tools tools,T/C RC foundation, T/C 489,629,278
operators, operation & maintenance mentainace cost for above is included in
expenses preliminaries.
Electricians, mechanic, chainman,
5. Indirect Labour office boy, hoist operators, cleaning 86,507,537
labour
6. Site Cleaning Rubbish disposal fee & equipment 63,640,055
Concrete test, mornitoring system,
7. Testing test equipment 12,447,536
Electricity tariff + water supply related
8. Temporary Utilities Temporary water & power utilities 239,106,355
materials & installation for actual w/o cap
Total 3,155,386,749
OASIS REALTY, MUMBAI
BILL OF QUANTITIES
PROVISIONAL SUM
Earthing system.
Destressing, removal of existing piles
system, MS struct members
Toilets
b) Structural Glazing
d) Stone Cladding
e) Windows
f) Canopies
special systems
Low Side
Low Side
PS11 DG Installation
1,000,000 6,400,000 1,600,000 9,000,000 9,000,000
PS12 Elevators - Installation
35,000,000 45,000,000 161,000,000 241,000,000 241,000,000
PS13 Landscape and External works
15,000,000 86,000,000 300,000,000 401,000,000 401,000,000
Soft scaping works
OASIS REALTY, MUMBAI
BILL OF QUANTITIES
PROVISIONAL SUM
External works
Total Amount
780,700,000 1,699,200,000 6,006,100,000 7,749,384,615 736,615,385 8,486,000,000
OASIS REALTY, MUMBAI
BILL OF QUANTITIES
PROVISIONAL SUM
b) Structural Glazing
d) Stone Cladding
e) Windows
f) Canopies
Total Amount
726,800,000 791,700,000 605,500,000 1,553,538,462 570,461,538 2,124,000,000
Total for Provisional Sums 1,507,500,000 2,490,900,000 6,611,600,000 9,302,923,077 1,307,076,923 10,610,000,000
Note:
The above provisional sum package list is subject to modification based on the joint pre-qualification evaluation of the proposed sub-
contractors, vendors and suppliers to determine their resources and overall capabilities to undertake such works under Provisional
Sums which may result into appointment of multiple sub - contractors to execute the scope for any provisional sum package. Furthermore
the above provisional sum package list may be further sub-divided as required by the Client to facilitate the EPCG scheme wherein the
Client shall obtain specific tax benefits which are available under the aforesaid scheme.
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING “OBEROI WORLI - 2“AT WORLI, MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
ANNEXURE - 1 PRICED BILL OF QUANTITIES
HIGHER
Lobby,
PODIUM
meeting COMMON RESIDENTIA
Basement (TOWER
Sr room & PODIUM L TOTAL Weighted Rate Amount
DESCRIPTION UNIT & Office Hotel PARKING-
No Ball room (GROUND, (FL-1, 11 TO QUANTITY in INR in INR
foundation RESIDENTI
(mixed P1,P2,P3) FL ABOVE)
AL) FL-02
use)
TO FL 10
SUBSTRUCTURE
ANTI TERMITE AND EARTH FILL / RUBBLE SOLING
1 54,663 - - - - - - 54,663 895 48,936,009
WORKS
2 PCC & PLUM CONCRETE WORKS 6,310 - - - - - - 6,310 5,321 33,577,310
3 REINFORCED CEMENT CONCRETE WORKS 64,763 - - - - - - 64,763 7,523 487,214,418
4 CENTERING / SHUTTERING / FORMWORK 91,014 - - - - - - 91,014 1,175 106,959,821
5 REINFORCEMENT STEEL 11,207 - - - - - - 11,207 58,480 655,388,572
6 STRUCTURAL STEEL 310 - - - - - - 310 117,745 36,500,950
SUPERSTRUCTURE
1 REINFORCED CEMENT CONCRETE WORKS - 11,685 26,709 22,695 12,274 24,906 157,247 255,516 8,073 2,062,657,627
2 CENTERING / SHUTTERING / FORMWORK - 44,610 100,584 90,046 36,553 75,551 561,340 908,684 1,138 1,033,650,832
3 REINFORCEMENT STEEL & POST TENSION STEEL - 2,585 4,277 3,775 2,319 4,626 29,709 47,291 58,481 2,765,626,462
4 STRUCTURAL STEEL - 83 185 337 85 160 260 1,110 121,132 134,456,820
5 COUPLER - - - - - - - 64,000 212 13,560,000
HIGHER
Lobby, meeting COMMON PODIUM RESIDENTIA
Sr Basement & room & PODIUM (TOWER L TOTAL Rate Amount
DESCRIPTION UNIT Office Hotel
No foundation Ball room (mixed (GROUND, PARKING- (FL-1, 11 TO QUANTITY in INR in INR
use) P1,P2,P3) RESIDENTIAL) FL ABOVE)
FL02 TO FL10
The Bill of Quantities shall be read in conjunction with the Conditions of Contract, conditions of particular
applications, Specifications and special provisions, Drawings and Employer’s requirements, General
Conditions and Preliminaries and the Contractor shall provide against the bill rates or in the prices for
the full scope of the work covered by the Contract, no claim or variations shall be considered on account
1 of the Tender’s failure to comply with this provision. The various documents collectively referred to
herein as the Bill of Quantities shall jointly constitute the Bill of Quantities referred to in the Conditions of
Contract and these preambles are to be read in conjunction with item descriptions in the Bill of
Quantities.Any discrepancy discovered should be reported to the Engineer before commencing work. In
case of any descripencies, decision of the Engineer shall be final and binding.
2 This Bill is wholly PROVISIONAL and is subject to final remeasurement on completion of the Works.
Wherever descriptions stated in the Bills are not comprehensive. Reference should be made to the
‘Technical Specification of Materials and Workmanship’ for details of types of materials and quality of
3 workmanship; The contractor shall, when pricing the rates of this bill, take into consideration including
and allow for the costs or expenses of all requirements stipulated in the Preambles, General Conditions
and Preliminaries, Tender Drawings and technical specification of the tender.
Unless otherwise described in the Preamble to the Bill of Quantities or specifically in Bill of Quantities,
the method or mode of measurement shall be as per Measurement of Building and Civil Engineering
5
Works IS : 1200 (Part – I – XXV) latest edition of Bureau of Indian Standards shall be followed in order of
preference. In case of any dispute in this matter, the Engineer's decision shall be binding and conclusive.
SUBSTRUCTURE
1 ANTI TERMITE AND EARTH FILL / RUBBLE SOLING WORKS 54,663 - - - - - - 54,663 48,936,009
Excavation & Dressing in all types of soil/ rock including hard murum, soft rock, hard rock by chiseling /
using mechanical equipment, including stacking the useful boulders / rock within the premises as
directed. (Measurements shall be by levels only ) or including shoring, pumping or bailing out water,
back filling excavated materials in the sides of the trenches and /or spreading, leveling surplus earth
inside the plinth or at any place as directed, in layers, watering and consolidating the earth with power
roller and disposing off the surplus soil/rock outside site premises, to nearest approved dumping ground
including spreading, compacting, etc., as per the local authority rules and paying necessary fees as per Cum 7,542 7,542 1,676 12,640,392
the prevalent rules and regulations etc complete including all leads, lifts and incidental work associated
with completion of this work.
NOTE: Before excavating / dressing in Soil / ROCK, levels of excavation have to be jointly
recorded by the contractor and site engineer, without joint record of measurements the excavation
shall not be classified as SOIL or HARD ROCK. In absence of such joint records, decision of
Engineer shall be final and binding on the Contractor.
EARTH FILL (BACKFILLING) : Supply and filling in foundations and the area wherever specified with
approved good quality filling materials in plinths, sides of retaining wall all round the building ( i.e
backfilling ) area development etc. wherever specified in layers of not exceeding 150 mm thick including
breaking clods,storing,transportation ,double handling, watering, compacting each layer with vibratory
compactor and at unaccessible places with wooden/steel rammers to achieve 90 to 95% proctor density
at optimum moisture content, all leads and lifts, bailing/ pumping out of water to keep site dry while - -
backfilling; cost shall include conveyance of all materials, labour, machinery etc. complete as
directed.The rate to include loading,unloading, hire and fuel charges for tools and plants and other
incidental charges etc., complete as directed.( Rate to include the test to be performed as directed and
specfied including payment of land compensation, forest royalty, sales tax and other duties & taxes as
may be necessary)
With selected earth / murrum available from excavation within plot boundry Cum 15,274 15,274 809 12,356,666
With material brought by contractor from approved borrow areas from outside (Murrum) Cum 7,637 7,637 1,233 9,416,421
With material brought by contractor from approved borrow areas from outside (Sand) Cum QRO - 6,966 -
- -
RUBBLE SOLING : Providing and fixing 230 mm thk. dry rubble soling of approved quality stone to
required level, camber & gradient, hand packed & vertically set including filling in interstices with chips Cum 5,000 5,000 2,163 10,815,000
and binding with stone grits, ramming, watering, consolidating etc. complete as per specifications.
PCC M 15 : Providing and laying Ready Mix Concrete ( RMC) from approved list of manufacturers or
cast in situ concrete for Raft or any other foundation, of approved grade as mentioned in the drawing
including (Shuttering if required) dewatering, the cost of finishing, vibrating, compacting, -
tamping,levelling, finishing and curing, at all levels with all leads and lifts etc. complete as per drawings &
technical specifications etc complete.
PLUM CONCRETE : Providing and laying Ready Mix Concrete ( RMC) from approved list of
manufacturers or cast in situ concrete, of approved grade with Plum Concrete consisting of
black trap or other approved stones 200 to 300 mm in size, clean, without skin or adhering
encrustation's shape being as cubical or round as possible laid in single or in alternate layers as -
per directions and as instructed by Engineer including (Shuttering if required) dewatering, the
cost of finishing, vibrating, tamping,levelling, finishing and curing, at all levels with all leads and
lifts etc. complete as per drawings & specifications etc complete.
HIGHER
Lobby, meeting COMMON PODIUM RESIDENTIA
Sr Basement & room & PODIUM (TOWER L TOTAL Rate Amount
DESCRIPTION UNIT Office Hotel
No foundation Ball room (mixed (GROUND, PARKING- (FL-1, 11 TO QUANTITY in INR in INR
use) P1,P2,P3) RESIDENTIAL) FL ABOVE)
FL02 TO FL10
PREAMBLE : All RCC works shall be in strict conformity with IS 456, specification & as per
approved mixed design appended herewith. Unless other wise specified all items of RCC are of
RMC as per the grade specified, The rate shall be inclusive of dewatering, hoisting by normal
labour or by means of mechanised equipment. Consolidation by rodding, tamping, vibrating by
an approved mechanical vibrator etc. protecting, curing including hacking, roughening of
concrete surface for receiving plaster or any other finish including costs of all tests on all
materials & concrete as & when directed by the Consultants.
The rate for RCC work shall include for forming projections, placing cover blocks , sinking of
floors for sumps wherever directed, forming opening or niches, core cuts for Services and
providing dowel bars and also coordinating with other agencies for laying conduits, boxes,
pipes, clamps etc. as directed at site.
The rates quoted shall include forming construction joints / expansion strips as directed by the
-
Consultant including keys, slopes, falls, stunt ends, temporary stops etc. complete
(Methodology, sequencing, material to be used for such joints shall be approved by the
Engineer/consultant before execution of the work).
The cost of testing throughout the period of concreting, and for the testing of concrete
including non – destructive test and remedial work ordered by the Engineer
consequent upon the results of falling below the minimum specified crieteria.
The rates shall also account for any admixtures (approved by the consultants) the contractor
may use in order to enhance the workability, to achieve accelerated strength, etc. The rate
shall include use of plasticizers, retarders, chilled water & ice to limit the water/cement ratio and
the
temperature at the time of setting to the specified levels. Complete care shall be taken
to achieve dense,pumpable and fully water-tight concrete.
RMC or CASE IN SITU : Providing, batching, mixing, transporting through transit mixers,
pumping and laying controlled Reinforced Cement Concrete OR Ready Mix Concrete at all levels
and heights of specified grade specified below using ordinary Portland cement of grade 43 / 53
from approved manufacturer, river sand, 20mm and down size coarse aggregates, necessary
-
Mineral admixtures approved by Engineer/Consultants , including all leads and lifts, pumping
using line pump or boom placer, vibrating/ compaction, scaffolding curing as directed as per
drawings and technical specification etc complete but excluding cost of shuttering and
reinforcement works
M40 Grade : Raft / Pile Foundations Cum 37,205 37,205 6,538 243,246,290
M40 Grade : Slabs / Beams Cum 14,084 14,084 6,010 84,642,556
M80 Grade : Wall / Column / Link Beams ( Retaining Wall / Shear Walls / Columns/ Link Beams) Cum 13,474 13,474 11,097 149,520,978
M40 Grade : Sloping Ramp Cum 1,631 1,631 6,010 9,804,594
-
4 CENTERING / SHUTTERING / FORMWORK 91,014 91,014 - 106,959,821
Providing and erecting shuttering formwork, straight, curved or any other shape as per detailed drawing,
at any level including strutting, propping, removing the shuttering after stipulated period, re-propping,
using marine resistant Plywood / Smooth finished MS plates / Aluminium shuttering material with
adjustable steel props of acceptable staging system, with sufficient bracing as approved by
Engineer/Consultant ,de-shuttering oil as specified and as per pattern including all types of grooves,
coreholes, pockets, cut-outs, including all cost of labour and material lifting, storage, scaffolding,
transportation, at all levels with all leads and lifts etc. complete. [Measurement will be paid for the area of
shuttering coming in contact with concrete only] as shown in Drawing and as per detailed specifications. -
Scheme and methodology to be used for shuttering shall be approved by Engineer/consultant before
starting of work.
( Note : Cost to include shuttering / key required for forming of a Construction joint, designing of proper
form work and staging system to suit the requirements,Submission of design calculations and shop
drawings for approval,sealing the joints with heavy duty brown self adhesive tape, aligning to line and
levels including M.S. Ties, PVC Spacer,applying deshuttering chemical,Deshuttering as approved by the
consultant etc., complete at all levels, double/ tripple heights and profiles )
Footing / Retaining Walls / Shear Walls / Columns etc Sqm 33,835 33,835 1,156 39,113,260
Columns and Drop Pardi Sqm 13,696 13,696 728 9,970,688
Beams and Slabs Sqm 34,435 34,435 1,331 45,832,985
Staircase Sqm 1,305 1,305 1,331 1,736,955
Sloping structures and Ramp Sqm 5,000 5,000 1,331 6,655,000
Other Miscellenous RCC Items like Pardi, Canopy,Chajjas, Others etc. (Provisional Sum) Sqm 2,743 2,743 1,331 3,650,933
-
5 REINFORCEMENT STEEL 11,207 - - - - - - 11,207 - 655,388,572
PREAMBLE : Reinforcement shall be measured only in lengths of bars as actually placed in position on
standard weight basis (The Bar Bending Schedule shall be approved and authorised by Engineer, prior
to pouring of concrete shall be considered for measurements) No allowance shall be made in the weight
-
for rolling margin. Spacer bar of any shape & profile, cover block, wastage and binding wire will not be
measured and shall be included in the quoted rates. Quoted rate shall be deemed to have considered
the above stipulation. Quoted rate to include lead, lift, placing at all levels and as directed by Engineer.
Providing and fixing steel reinforcement ( FE 500, Deformed bars) for RCC including transporting, de-
coiling, straightening, cutting, bending, fabricating and placing in position at all levels and binding with
approved quality G.I. annealed coated binding wire. The rate shall include cost of binding wire, tack
welding with chairs, spacers and pins, rolling margin difference which will not be measured separately for
payment. Quantity of steel shall be as per drawing and with authorized overlaps and Bar chair only shall
-
be measured and paid for. The rate also includes protecting the reinforcing bars – in their virgin form or
in the fabricated form, or when placed and tied up in position or as dowels left for future continuation of
work or at construction joint – against corrosion due to exposure to weather if left exposed and un-
encased for more than two weeks from the date of delivery to the site.The rates shall be inclusive of
placing reinforcement at any level including all leads and lifts etc complete.
Preparing shop drawings, obtaining consultants approval, supplying, fabricating, delivering at site,
hoisting and fixing in position, including all temporary staging and supporting work and making all
structural steel work in accordance with the design, drawings prepared by the consultants. The rate of
Structural Steel work shall include assembly, welding, jointing, building up new sections, cost of
fasteners (nuts, bolts and washers), pre-heating the sections to temperatures up to 250 Degree Cent. if
thickness of the section is equal to or more than 25 mm and fabrication out of the following types of
structural steel material for trusses, purlins, girders, brackets, etc. with connections using plates,
-
channels and angles, gusset plate, foundation bolts, cleats, fasteners etc. as per drawing, steel
conforming to IS : 226 and IS : 2062 with minimum yield strength of 250 Mpa and upto 355 Mpa.
The rate shall also include one coat of approved zinc rich primer after properly cleaning the steel surface
with wire brush and mild acid solution followed by washing with water and drying the surface completely.
All expose structural steel members to be coated with fire
retarding paint.
Sections such as angles, T sections, channels and I sections of any sizes. MT 50 50 117,745 5,887,250
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING AT MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
ANNEXURE - 1 PRICED BILL OF QUANTITIES
Bill 03 - Civil Works - Detailed Break-up
HIGHER
Lobby, meeting COMMON PODIUM RESIDENTIA
Sr Basement & room & PODIUM (TOWER L TOTAL Rate Amount
DESCRIPTION UNIT Office Hotel
No foundation Ball room (mixed (GROUND, PARKING- (FL-1, 11 TO QUANTITY in INR in INR
use) P1,P2,P3) RESIDENTIAL) FL ABOVE)
FL02 TO FL10
Hollow rectangular or square sections of any size and thickness MT 50 50 117,745 5,887,250
- -
Supplying, fabricating and installing inserts in concrete in the form of mild steel angles, channels, beams,
rods, flats, plates, holding down bolts, angle frames, etc. with anchors in the form of rods or flats
MT 60 60 117,745 7,064,700
including welding anchors, lifting hooks, rungs, templates etc., also including forming partial pockets in
the concrete along with the embedments of the bolts, inserts etc.
SUPERSTRUCTURE -
1 REINFORCED CEMENT CONCRETE WORKS - 11,685 26,709 22,695 12,274 24,906 157,247 255,516 - 2,062,657,627
PREAMBLE : All RCC works shall be in strict conformity with IS 456, specification & as per
approved mixed design appended herewith. Unless other wise specified all items of RCC are of
RMC as per the grade specified, The rate shall be inclusive of dewatering, hoisting by normal
labour or by means of mechanised equipment. Consolidation by rodding, tamping, vibrating by
an approved mechanical vibrator etc. protecting, curing including hacking, roughening of
concrete surface for receiving plaster or any other finish including costs of all tests on all
materials & concrete as & when directed by the Consultants.
The rate for RCC work shall include for forming projections, placing cover blocks , sinking of
floors for sumps wherever directed, forming opening or niches, core cuts for Services and
providing dowel bars and also coordinating with other agencies for laying conduits, boxes,
pipes, clamps etc. as directed at site.
The rates quoted shall include forming construction joints / expansion strips as directed by the
1.00 - -
Consultant including keys, slopes, falls, stunt ends, temporary stops etc. complete
(Methodology, sequencing, material to be used for such joints shall be approved by the
Engineer/consultant before execution of the work).
The cost of testing throughout the period of concreting, and for the testing of concrete
including non – destructive test and remedial work ordered by the Engineer
consequent upon the results of falling below the minimum specified crieteria.
The rates shall also account for any admixtures (approved by the consultants) the contractor
may use in order to enhance the workability, to achieve accelerated strength, etc. The rate
shall include use of plasticizers, retarders, chilled water & ice to limit the water/cement ratio and
the
temperature at the time of setting to the specified levels. Complete care shall be taken
to achieve dense,pumpable and fully water-tight concrete.
RMC or CASE IN SITU : Providing, batching, mixing, transporting through transit mixers,
pumping and laying controlled Reinforced Cement Concrete OR Ready Mix Concrete at all levels
and heights of specified grade specified below using ordinary Portland cement of grade 43 / 53
from approved manufacturer, river sand, 20mm and down size coarse aggregates, necessary
1.00 - -
Mineral admixtures approved by Engineer/Consultants , including all leads and lifts, pumping
using line pump or boom placer, vibrating/ compaction, scaffolding curing as directed as per
drawings and technical specification etc complete but excluding cost of shuttering and
reinforcement works
M40 Grade Concrete for PT : Beams - Post Tensioned Cum 179 - - 179 6,106 1,092,974
M80 Grade : Wall / Column / Link Beams / Drop Panels ( Retaining Wall / Shear Walls / Core walls /
Cum 5,852 - - 5,852 11,097 64,939,644
Columns/ Link Beams etc.)
- - -
RC Drop Panels : M 80 Grade (FL 04 to FL 09) Cum - 280 - 280 11,162 3,125,360
RC Drop Panels : M 70 Grade (FL 10 to FL 30) Cum - 1,190 - 1,190 9,642 11,473,980
RC Link Beams : M 80 Grade (FL 04 to FL 09) Cum - 200 - 200 11,130 2,226,000
RC Link Beams : M 70 Grade (FL 10 to FL 30) Cum - 710 - 710 9,610 6,823,100
- - -
RC Drop Panels :M 60 Grade (FL31 to FL 53) Cum - - 1,000 1,000 8,992 8,992,000
RC Link Beams : M 60 Grade (FL31 to FL 53) Cum - - 870 870 8,959 7,794,330
- - -
M80 Grade : RC Walls (FL Ground, P1,P2 & P3) Cum 4,422 4,422 11,097 49,070,934
M80 Grade : RC Columns (FL Ground, P1,P2 & P3) Cum 2,046 2,046 11,097 22,704,462
M80 Grade : Drop Panels (FL Ground, P1,P2 & P3) Cum 645 645 11,162 7,199,490
M40 Grade : Slabs & Sloping Ramps (FL Ground, P1,P2 & P3) Cum 3,743 3,743 6,106 22,854,758
M40 Grade : Beams (FL Ground, P1,P2 & P3) Cum 720 720 6,074 4,373,280
M80 Grade : Linked Beams (FL Ground, P1,P2 & P3) Cum 20 20 11,130 222,600
M40 Grade : Staircases (FL Ground, P1,P2 & P3) Cum 178 178 6,171 1,098,438
Other Miscellenous RCC Items like Pardi, Canopy,Chajjas, Others etc (Provisional Sum) Cum 500 500 6,171 3,085,500
- - -
M80 Grade : RC Walls (FL 02 to FL 10) Cum 9,353 9,353 11,097 103,790,241
M80 Grade : RC Columns (FL 02 to FL 10) Cum 3,409 3,409 11,097 37,829,673
M80 Grade : Drop Panels (FL 02 to FL 10) Cum 1,470 1,470 11,162 16,408,140
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING AT MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
ANNEXURE - 1 PRICED BILL OF QUANTITIES
Bill 03 - Civil Works - Detailed Break-up
HIGHER
Lobby, meeting COMMON PODIUM RESIDENTIA
Sr Basement & room & PODIUM (TOWER L TOTAL Rate Amount
DESCRIPTION UNIT Office Hotel
No foundation Ball room (mixed (GROUND, PARKING- (FL-1, 11 TO QUANTITY in INR in INR
use) P1,P2,P3) RESIDENTIAL) FL ABOVE)
FL02 TO FL10
M40 Grade : Slabs & Sloping Ramps (FL 02 to FL 10) Cum 8,744 8,744 6,106 53,390,864
M40 Grade : Staircases (FL 02 to FL 10) Cum 316 316 6,171 1,950,036
- - -
M80 Grade : RC Walls (FL 01 & FL 11 to FL 18 ) Cum 14,521 14,521 11,097 161,139,537
M50 Grade : RC Walls (FL 58 to FL Above ) Cum 20,027 20,027 6,946 139,107,542
M80 Grade : RC Columns (FL 01 & FL 11 to FL 18 ) Cum 4,669 4,669 11,097 51,811,893
M50 Grade : RC Columns (FL 58 to FL Above ) Cum 5,127 5,127 6,946 35,612,142
M80 Grade : Drop Panels (FL 01 & FL 11 to FL 12 ) Cum 126 126 11,162 1,406,412
M40 Grade : Slabs (FL 01 & FL 11 to FL Above ) Cum 41,163 41,163 6,106 251,341,278
M40 Grade : Beams (FL 01 & FL 11 to FL Above ) Cum 17,797 17,797 6,074 108,098,978
M80 Grade : Linked Beams (FL 01 & FL 11 to FL Above ) Cum 3,869 3,869 11,130 43,061,970
M40 Grade : Staircases (FL 01 & FL 11 to FL Above ) Cum 2,875 2,875 6,171 17,741,625
- -
-
2 CENTERING / SHUTTERING / FORMWORK - 44,610 100,584 90,046 36,553 75,551 561,340 908,684 - 1,033,650,832
Providing and erecting shuttering formwork, straight, curved or any other shape as per detailed drawing,
at any level including strutting, propping, removing the shuttering after stipulated period, re-propping,
using marine resistant Plywood / Smooth finished MS plates / Aluminium shuttering material with
adjustable steel props of acceptable staging system, with sufficient bracing as approved by
Engineer/Consultant ,de-shuttering oil as specified and as per pattern including all types of grooves,
coreholes, pockets, cut-outs, including all cost of labour and material lifting, storage, scaffolding,
transportation, at all levels with all leads and lifts etc. complete. [Measurement will be paid for the area of
shuttering coming in contact with concrete only] as shown in Drawing and as per detailed specifications. - -
Scheme and methodology to be used for shuttering shall be approved by Engineer/consultant before
starting of work.
( Note : Cost to include shuttering / key required for forming of a Construction joint, designing of proper
form work and staging system to suit the requirements,Submission of design calculations and shop
drawings for approval,sealing the joints with heavy duty brown self adhesive tape, aligning to line and
levels including M.S. Ties, PVC Spacer,applying deshuttering chemical,Deshuttering as approved by the
consultant etc., complete at all levels, double/ tripple heights and profiles )
Other Miscellenous RCC Items like Pardi, Canopy,Chajjas, Others etc (Provisional Sum) Sqm 350 - - 350 1,331 465,850
- -
RC Walls (FL Ground, P1,P2 & P3) Sqm 8,604 - - 8,604 1,644 14,144,976
RC Columns (FL Ground, P1,P2 & P3) Sqm 6,152 6,152 728 4,478,656
Drop Panels (FL Ground, P1,P2 & P3) Sqm 3,905 3,905 1,331 5,197,555
Slabs & Sloping Ramps (FL Ground, P1,P2 & P3) Sqm 13,614 13,614 1,331 18,120,234
Beams (FL Ground, P1,P2 & P3) Sqm 2,765 2,765 1,331 3,680,215
Linked Beams (FL Ground, P1,P2 & P3) Sqm 77 77 1,331 102,487
Staircases (FL Ground, P1,P2 & P3) Sqm 1,086 1,086 1,331 1,445,466
Other Miscellenous RCC Items like Pardi, Canopy,Chajjas, Others etc (Provisional Sum) Sqm 350 350 1,331 465,850
- - -
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING AT MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
ANNEXURE - 1 PRICED BILL OF QUANTITIES
Bill 03 - Civil Works - Detailed Break-up
HIGHER
Lobby, meeting COMMON PODIUM RESIDENTIA
Sr Basement & room & PODIUM (TOWER L TOTAL Rate Amount
DESCRIPTION UNIT Office Hotel
No foundation Ball room (mixed (GROUND, PARKING- (FL-1, 11 TO QUANTITY in INR in INR
use) P1,P2,P3) RESIDENTIAL) FL ABOVE)
FL02 TO FL10
Slabs &Sloping Ramps (FL 02 to FL 10) Sqm 31,664 31,664 1,241 39,295,024
- - -
Linked Beams (FL 01 & FL 11 to FL Above ) Sqm 11,037 11,037 993 10,959,741
3 REINFORCEMENT STEEL & POST TENSION STEEL - 2,585 4,277 3,775 2,319 4,626 29,709 47,291 - 2,765,626,462
PREAMBLE : Reinforcement shall be measured only in lengths of bars as actually placed in position on
standard weight basis (The Bar Bending Schedule shall be approved and authorised by Engineer, prior
to pouring of concrete shall be considered for measurements) No allowance shall be made in the weight
- -
for rolling margin. Spacer bar of any shape & profile, cover block, wastage and binding wire will not be
measured and shall be included in the quoted rates. Quoted rate shall be deemed to have considered
the above stipulation. Quoted rate to include lead, lift, placing at all levels and as directed by Engineer.
Providing and fixing steel reinforcement ( FE 500, Deformed bars) for RCC including transporting, de-
coiling, straightening, cutting, bending, fabricating and placing in position at all levels and binding with
approved quality G.I. annealed coated binding wire. The rate shall include cost of binding wire, tack
welding with chairs, spacers and pins, rolling margin difference which will not be measured separately for
payment. Quantity of steel shall be as per drawing and with authorized overlaps and Bar chair only shall
-
be measured and paid for. The rate also includes protecting the reinforcing bars – in their virgin form or
in the fabricated form, or when placed and tied up in position or as dowels left for future continuation of
work or at construction joint – against corrosion due to exposure to weather if left exposed and un-
encased for more than two weeks from the date of delivery to the site.The rates shall be inclusive of
placing reinforcement at any level including all leads and lifts etc complete.
For Columns & Drop Panels ( GF to FL 03) MT 715 - - 715 58,322 41,700,230
- -
- -
- -
RC Walls (FL Ground, P1,P2 & P3) MT 960 - - 960 58,322 55,989,120
RC Columns (FL Ground, P1,P2 & P3) MT 628 - - 628 58,322 36,626,216
Slabs (FL Ground, P1,P2 & P3) MT 468 - - 468 58,322 27,294,696
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING AT MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
ANNEXURE - 1 PRICED BILL OF QUANTITIES
Bill 03 - Civil Works - Detailed Break-up
HIGHER
Lobby, meeting COMMON PODIUM RESIDENTIA
Sr Basement & room & PODIUM (TOWER L TOTAL Rate Amount
DESCRIPTION UNIT Office Hotel
No foundation Ball room (mixed (GROUND, PARKING- (FL-1, 11 TO QUANTITY in INR in INR
use) P1,P2,P3) RESIDENTIAL) FL ABOVE)
FL02 TO FL10
Beams (FL Ground, P1,P2 & P3) MT 126 - - 126 58,322 7,348,572
Other Miscellenous RCC Items like Pardi, Canopy,Chajjas, Others etc (Provisional Sum) MT 30 - - 30 58,322 1,749,660
- - - - - -
- - - - - -
- -
POST TENSIONING :- Manufacture, supply, install & profile stressing end, cement grout, all post
tensioning tendons of 1905 & 1205 confirming to IS : 4268 Class -II low relaxation stand including
sheeting of 90ID made of thick G.I. Sheeting material and full anchorage assembly with UTS of 183 KN /
strand. Supply & execution of post tensioning work shall be carried out by a specialist agency, with their
own eqiopments, accessories & skilled manpower as per approved construction drawings. The rate
MT 10 25 25 60 183,668 11,020,080
quoted shall be inclusive of cost of strand, duct & their testing, supply, fixing, profiling of tendons
stressing, grouting complete as shown in the drawing & as per specification herein above. The unit rate
of post tensioning shall also be inclusive of all labour, equipment, accessories & technical supervision of
the post tension system supplier, who will monitor, insure & certify the correctness of the prestressing
operations.
- -
Preparing shop drawings, obtaining consultants approval, supplying, fabricating, delivering at site,
hoisting and fixing in position, including all temporary staging and supporting work and making all
structural steel work in accordance with the design, drawings prepared by the consultants. The rate of
Structural Steel work shall include assembly, welding, jointing, building up new sections, cost of
fasteners (nuts, bolts and washers), pre-heating the sections to temperatures up to 250 Degree Cent. if
thickness of the section is equal to or more than 25 mm and fabrication out of the following types of
structural steel material for trusses, purlins, girders, brackets, etc. with connections using plates,
-
channels and angles, gusset plate, foundation bolts, cleats, fasteners etc. as per drawing, steel
conforming to IS : 226 and IS : 2062 with minimum yield strength of 250 Mpa and upto 355 Mpa.
The rate shall also include one coat of approved zinc rich primer after properly cleaning the steel surface
with wire brush and mild acid solution followed by washing with water and drying the surface completely.
All expose structural steel members to be coated with fire
retarding paint.
The supplied structural steel shall be main manufacturer's production.
Rolled sections such as angles, T sections, channels and I sections of any sizes. MT 15 35 65 15 30 50 210 120,748 25,357,080
Hollow rectangular or square sections of any size and thickness MT 15 35 65 15 30 50 210 120,748 25,357,080
Chequered plate to be fixed over structural steel framework. MT 15 35 65 15 30 50 210 120,748 25,357,080
- -
Supplying, fabricating and installing inserts in concrete in the form of mild steel angles, channels, beams,
rods, flats, plates, holding down bolts, angle frames, etc. with anchors in the form of rods or flats
MT 8 10 12 10 10 10 60 127,857 7,671,420
including welding anchors, lifting hooks, rungs, templates etc., also including forming partial pockets in
the concrete along with the embedments of the bolts, inserts etc.
* Note: The rates used for this calculation are the sum of the rates for materials and labors. The relevant break-ups shall be provided, wherever required, at the time of billing.
OASIS REALTY, MUMBAI
BILL OF QUANTITIES
PROVISIONAL SUM
PROVISIONAL SUM
PS02 Water Proofing - for Super Structure Nina Tristar Speciality Con.
PS11 DG Installation
PS14 Security System - Supply & Installation Jonshon Control Samsung SDS Honeywell
1 The Bill of Quantities shall be read in conjunction with the Conditions of Contract, conditions of particular applications, Specifications and special provisions, Drawings and Employer’s requirements, General 0 0 0
2 This Bill is wholly PROVISIONAL and is subject to final remeasurement on completion of the Works. 0 0 0
3 Wherever descriptions stated in the Bills are not comprehensive. Reference should be made to the ‘Technical Specification of Materials and Workmanship’ for details of types of materials and quality of workman 0 0 0
4 Unless otherwise noted,the rates and prices bid in the priced Bill of Quantities shall include cost for all Constructional Plant, Equipment, Material with wastage, Labour, Power, Fuel (P.O.L.), Temporary & Ancillary works, Supervision, Shop Drawings, Necessary Design / Trial mix, Testing, Necessary clearances
The Clauses of this preamble will also apply to any additional or varied work which the tenderer may be required to execute under this contract except where specifically amended or supplemented by the instructions given to him to carry out such work.
0 / approvals,
0 Erection (including
0
5 Unless otherwise described in the Preamble to the Bill of Quantities or specifically in Bill of Quantities, the method or mode of measurement shall be as per Measurement of Building and Civil Engineering Work 0 0 0
at ANTI TERMITE TREATMENT : Providing PRE-CONSTRUCTIONAL ANTI-TERMITE treatmentSqm (As per IS:1616 Part II) by diluting and injecting chemical emulsion of Clorophyriphose Emulsifiable concentrate 20% with 1% concentration (at the rate of 5 litres of emulsion concentrates of 0.5% of Aldrin per square meter of surface area ) and creating a continuous chemical barrier under and
QRO
The contractor shall render the building termite free for 10 years and give a guarantee to this effect on stamp paper as directed by the Project Manager.
0 129 12 141 64 6 70 0 0 0
Excavation & Dressing in all types of soil/ rock including hard murum, soft rock, hard rock by chiseling / using mechanical equipment, including stacking the useful boulders / rock within the premises as directed. (Measurements shall be by le
NOTE: Before excavating / dressing in Soil / ROCK, levels of excavation have to be jointly
ex recorded by the contractor and site engineer, without joint record of measurements the excavation Cum QRO 0 0 0 0 1676 151 1827 0 0 0
shall not be classified as SOIL or HARD ROCK. In absence of such joint records, decision of
Project Manager shall be final and binding on the Contractor.
OASIS 16 of 25
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING “OBEROI WORLI - 2“AT WORLI, MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
bf EARTH FILL (BACKFILLING) : Supply and filling in foundations and the area wherever specified with approved good quality filling materials in plinths, sides of retaining wall all round the building ( i.e backfilling ) area development etc. wherever0specified in layers
0 of not exceeding
0 0 including breaking
150 mm thick 0 0 0 ,double handling,0 watering, compacting
clods,storing,transportation 0 eac
bf With selected earth / murrum available from excavation within p Cum 15274 15274 551 50 601 258 23 281 9179674 4291994 13471668
bf With material brought by contractor from approved borrow areas Cum 7637 7637 975 88 1063 258 23 281 8118131 2145997 10264128
bf With material brought by contractor from approved borrow areas Cum QRO 0 6708 604 7312 258 23 281 0 0 0
0 0 0 0 0 0 0 0 0
rb RUBBLE SOLING : Providing and fixing 230 mm thk. dry rubble soling of approved quality stoneCum QROlevel, camber & gradient, hand packed & vertically set including filling in interstices with chips and binding with stone grits, ramming,
to required 0 1905 consolidating
watering, 171etc. complete
2076 258
as per specifications. 23 281 0 0 0
0 0 0 0 0 0 0 0 0
2 PCC & PLUM CONCRETE WORKS 2413 2413 0 0 0 0 11843004 2200656 14043660
PCC M 15 : Providing and laying Ready Mix Concrete ( RMC) from approved list of manufacturers or cast in situ concrete for Raft or any other foundation, of approved grade as mentioned in the drawing including (Shuttering if required) dewatering, 0 vibrating, compacting,
the cost of finishing, 0 0
tamping,levelling, finishing 0 at all levels with0 all leads and lifts0etc. complete as per
and curing, 0 drawi
PLUM CONCRETE : Providing and laying Ready Mix Concrete ( RMC) from approved list of manufacturers or cast in situ concrete, of approved grade with Plum Concrete consisting of black trap or other approved stones 200 to 300 mm in size, clean,0 without skin or0adhering encrustation's
0 shape0being as cubical
0 or round as possible
0 0 or in alternate layers
laid in single 0 as per directions
0 and a
OASIS 17 of 25
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING “OBEROI WORLI - 2“AT WORLI, MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
PREAMBLE : All RCC works shall be in strict conformity with IS 456, specification & as per approved mixed design appended herewith. Unless other wise specified all items of RCC are of RMC as per the grade specified, The rate shall be inclusive of dewatering, hoisting by normal labour or by means of mechanised equipment. Consolidation by rodding, tamping, vibrating by an approved m
The rate for RCC work shall include for forming projections, placing cover blocks , sinking of floors for sumps wherever directed, forming opening or niches, core cuts for Services and providing dowel bars and also coordinating with other agencies for laying conduits, boxes, pipes, clamps etc. as directed at site.
The rates quoted shall include forming construction joints / expansion strips as directed by the Consultant including keys, slopes, falls, stunt ends, temporary stops etc. complete (Methodology, sequencing, material to be used for such joints shall be approved by the project manager/consultant before execution of the work).
The cost of testing throughout the period of concreting, and for the testing of concrete
including non – destructive test and remedial work ordered by the Project Manager
consequent upon the results of falling below the minimum specified crieteria. 0 0 0 0 0 0 0 0 0
The rates shall also account for any admixtures (approved by the consultants) the contractor
may use in order to enhance the workability, to achieve accelerated strength, etc. The rate
shall include use of plasticizers, retarders, chilled water & ice to limit the water/cement ratio and the
temperature at the time of setting to the specified levels. Complete care shall be taken
to achieve dense,pumpable and fully water-tight concrete.
RMC or CASE IN SITU : Providing, batching, mixing, transporting through transit mixers, pumping and laying controlled Reinforced Cement Concrete OR Ready Mix Concrete at all levels and heights of specified grade specified below using ordinary
0 Portland cement
0 of grade 43
0 / 53 from approved
0 0 river sand,0 20mm and down 0size coarse aggregates,
manufacturer, 0 0
necessary Mineral ad
c M40 Grade : Raft / Pile Foundations Cum 36252 36252 6091 548 6639 786 71 857 240677028 31067964 271744992
c M40 Grade : Slabs / Beams Cum 16301 16301 5614 505 6119 786 71 857 99745819 13969957 113715776
c M80 Grade : Wall / Column / Link Beams ( Retaining Wall / Shear Walls / Columns/ Link Beams)
Cum 16179 16179 10630 957 11587 1109 100 1209 187466073 19560411 207026484
0 0 0 0 0 0 0 0 0
4 CENTERING / SHUTTERING / FORMWORK 94164 94164 0 0 0 0 78947024 52449348 131396372
Providing and erecting shuttering formwork, straight, curved or any other shape as per detailed drawing, at any level including strutting, propping, removing the shuttering after stipulated period, re-propping, using marine resistant Plywood / Smooth f
Scheme and methodology to be used for shuttering shall be approved by project manager/consultant before starting of work. 0 0 0 0 0 0 0 0 0
( Note : Cost to include shuttering / key required for forming of a Construction joint, designing of proper form work and staging system to suit the requirements,Submission of design calculations and shop drawings for approval,sealing the joints with heavy duty brown self adhesive tape, aligning to line and levels including M.S. Ties, PVC Spacer,applying deshuttering chemical,Deshuttering as ap
f Footing / Retaining Walls / Shear Walls / Columns etc Sqm 32828 32828 728 66 794 511 46 557 26065432 18285196 44350628
Footing 5407 5407 816 73 889 511 46 557 4806823 3011699 7818522
Retaining Wall 15334 15334 721 65 786 511 46 557 12052524 8541038 20593562
Core Wall 2023 2023 1707 154 1861 511 46 557 3764803 1126811 4891614
Conventional Wall 10064 10064 496 45 541 511 46 557 5444624 5605648 11050272
f Columns and Drop Pardi Sqm 12048 12048 262 24 286 511 46 557 3445728 6710736 10156464
f Beams and Slabs Sqm 45226 45226 920 83 1003 511 46 557 45361678 25190882 70552560
f Staircase Sqm 1319 1319 920 83 1003 511 46 557 1322957 734683 2057640
f Other Miscellenous RCC Items like Pardi, Canopy,Chajjas, Others Sqm 2743 2743 920 83 1003 511 46 557 2751229 1527851 4279080
0 0 0 0 0 0 0
5 REINFORCEMENT STEEL 11207 0 0 0 0 0 0 11207 0 0 0 0 607489638 130337410 737827048
OASIS 18 of 25
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING “OBEROI WORLI - 2“AT WORLI, MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
PREAMBLE : Reinforcement shall be measured only in lengths of bars as actually placed in position on standard weight basis (The Bar Bending Schedule shall be approved and authorised by Client's Project Manager, prior to pouring of concrete shall 0be considered for
0 measurements)
0 0 shall be made
No allowance 0 in the weight 0for rolling margin. Authorised
0 0 splices, couplers0of any d
laps and
r For Foundation ( Raft) MT 6381 6381 49872 4488 54360 10670 960 11630 346871160 74211030 421082190
r For Walls MT 1916 1916 49544 4459 54003 10670 960 11630 103469748 22283080 125752828
r For Columns & Drop Panels MT 1171 1171 49544 4459 54003 10670 960 11630 63237513 13618730 76856243
r For Beams and Slabs MT 1687 1687 49544 4459 54003 10670 960 11630 91103061 19619810 110722871
r For Staircase MT 52 52 49544 4459 54003 10670 960 11630 2808156 604760 3412916
0 0 0 0 0 0 0 0 0
6 STRUCTURAL STEEL 310 310 0 0 0 0 33454580 6331440 39786020
Preparing shop drawings, obtaining consultants approval, supplying, fabricating, delivering at site, hoisting and fixing in position, including all temporary staging and supporting work and making all structural steel work in accordance with the design
The rate shall also include one coat of approved zinc rich primer after properly cleaning the steel surface with wire brush and mild acid solution followed
0 by washing
0 with0 water and
0 drying the
0 surface0 completely.
0 All expose0 structural
0 steel members
0 to
retarding paint.
The supplied structural steel shall be main manufacturer's production.
r Sections such as angles, T sections, channels and I sections of MT 50 50 99007 8911 107918 18738 1686 20424 5395900 1021200 6417100
r MS Plates / Chequred Plate of any thickness MT 50 50 99007 8911 107918 18738 1686 20424 5395900 1021200 6417100
r Hollow pipes of any diameter and thickness MT 50 50 99007 8911 107918 18738 1686 20424 5395900 1021200 6417100
r Hollow rectangular or square sections of any size and thickness MT 50 50 99007 8911 107918 18738 1686 20424 5395900 1021200 6417100
r Chequered plate to be fixed over structural steel framework. MT 50 50 99007 8911 107918 18738 1686 20424 5395900 1021200 6417100
0 99007 8911 107918 18738 1686 20424 0 0 0
r Supplying, fabricating and installing inserts in concrete in th MT 60 60 99007 8911 107918 18738 1686 20424 6475080 1225440 7700520
0 0 0 0 0 0 0 0 0 0
SUPERSTRUCTURE 0 0 0 0 0 0 0 0 0 0
1 REINFORCED CEMENT CONCRETE WORKS 0 11249 26890 22960 11902 24933 150916 248850 0 0 0 0 2109465892 259407059 2368872951
OASIS 19 of 25
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING “OBEROI WORLI - 2“AT WORLI, MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
PREAMBLE : All RCC works shall be in strict conformity with IS 456, specification & as per approved mixed design appended herewith. Unless other wise specified all items of RCC are of RMC as per the grade specified, The rate shall be inclusive of dewatering, hoisting by normal labour or by means of mechanised equipment. Consolidation by rodding, tamping, vibrating by an approved m
The rate for RCC work shall include for forming projections, placing cover blocks , sinking of floors for sumps wherever directed, forming opening or niches, core cuts for Services and providing dowel bars and also coordinating with other agencies for laying conduits, boxes, pipes, clamps etc. as directed at site.
The rates quoted shall include forming construction joints / expansion strips as directed by the Consultant including keys, slopes, falls, stunt ends, temporary stops etc. complete (Methodology, sequencing, material to be used for such joints shall be approved by the project manager/consultant before execution of the work).
The cost of testing throughout the period of concreting, and for the testing of concrete
including non – destructive test and remedial work ordered by the Project Manager
consequent upon the results of falling below the minimum specified crieteria. 1 3971 31290 25837 61098 0 0 0 0 0 0 0 0 0
The rates shall also account for any admixtures (approved by the consultants) the contractor
may use in order to enhance the workability, to achieve accelerated strength, etc. The rate
shall include use of plasticizers, retarders, chilled water & ice to limit the water/cement ratio and the
temperature at the time of setting to the specified levels. Complete care shall be taken
to achieve dense,pumpable and fully water-tight concrete.
RMC or CASE IN SITU : Providing, batching, mixing, transporting through transit mixers, pumping and
1 laying controlled Reinforced Cement Concrete OR Ready Mix Concrete at all levels and heights of specified grade specified below
0 using ordinary
0 Portland cement
0 of grade 43
0 / 53 from approved
0 0 river sand,0 20mm and down 0size coarse aggregates,
manufacturer, 0 0
necessary Mineral ad
c M40 Grade : Slabs / Beams Cum 4817 0 0 4817 5614 505 6119 882 79 961 29475223 4629137 34104360
c M40 Grade : Staircases Cum 331 0 0 331 5614 505 6119 947 85 1032 2025389 341592 2366981
c M40 Grade Concrete for PT : Beams - Post Tensioned Cum 179 0 0 179 5614 505 6119 882 79 961 1095301 172019 1267320
c M80 Grade : Wall / Column / Link Beams / Drop Panels ( Retain Cum 5922 0 0 5922 10630 957 11587 1109 100 1209 68618214 7159698 75777912
0 0 0 0 0 0 0 0 0 0
c RC Walls : M 80 Grade (FL 04 to FL 09) Cum 0 2062 0 2062 10630 957 11587 1109 100 1209 23892394 2492958 26385352
c RC Walls : M 70 Grade (FL 10 to FL 30) Cum 0 7428 0 7428 9353 842 10195 998 90 1088 75728460 8081664 83810124
c RC Columns : M 80 Grade (FL 04 to FL 09) Cum 0 500 0 500 10630 957 11587 1109 100 1209 5793500 604500 6398000
c RC Columns : M 70 Grade (FL 10 to FL 30) Cum 0 1870 0 1870 9353 842 10195 996 90 1086 19064650 2030820 21095470
c RC Drop Panels : M 80 Grade (FL 04 to FL 09) Cum 0 310 0 310 10630 957 11587 1174 106 1280 3591970 396800 3988770
c RC Drop Panels : M 70 Grade (FL 10 to FL 30) Cum 0 1290 0 1290 9353 842 10195 1062 96 1158 13151550 1493820 14645370
c RC Link Beams : M 80 Grade (FL 04 to FL 09) Cum 0 200 0 200 10630 957 11587 1142 103 1245 2317400 249000 2566400
c RC Link Beams : M 70 Grade (FL 10 to FL 30) Cum 0 710 0 710 9353 842 10195 1030 93 1123 7238450 797330 8035780
c RC Beams : M 40 Grade (FL 04 to FL 09) Cum 0 170 0 170 5614 505 6119 850 77 927 1040230 157590 1197820
c RC Beams : M 40 Grade (FL 10 to FL 30) Cum 0 780 0 780 5614 505 6119 882 79 961 4772820 749580 5522400
c RC Slabs : M 40 Grade (FL 04 to FL 09) Cum 0 2510 0 2510 5614 505 6119 882 79 961 15358690 2412110 17770800
c RC Slabs : M 40 Grade (FL 10 to FL 30) Cum 0 8310 0 8310 5614 505 6119 882 79 961 50848890 7985910 58834800
c RC Staircase : M 40 Grade(FL 04 to FL 09) Cum 0 170 0 170 5614 505 6119 947 85 1032 1040230 175440 1215670
c RC Staircase : M 40 Grade (FL 10 to FL 30) Cum 0 580 0 580 5614 505 6119 947 85 1032 3549020 598560 4147580
0 0 0 0 0 0 0 0 0 0
c RC Walls : M 60 Grade (FL31 to FL 53) Cum 0 0 6920 6920 8719 785 9504 966 87 1053 65767680 7286760 73054440
c RC Columns : M 60 Grade (FL31 to FL 53) Cum 0 0 1200 1200 8719 785 9504 966 87 1053 11404800 1263600 12668400
c RC Drop Panels :M 60 Grade (FL31 to FL 53) Cum 0 0 1000 1000 8719 785 9504 1031 93 1124 9504000 1124000 10628000
c RC Link Beams : M 60 Grade (FL31 to FL 53) Cum 0 0 910 910 8719 785 9504 998 90 1088 8648640 990080 9638720
c RC Beams : M 40 Grade (FL31 to FL 53) Cum 0 0 600 600 5614 505 6119 850 77 927 3671400 556200 4227600
c RC Slabs : M 40 Grade (FL31 to FL 53) Cum 0 0 11560 11560 5614 505 6119 882 79 961 70735640 11109160 81844800
c RC Staircase : M 40 Grade (FL31 to FL 53) Cum 0 0 770 770 5614 505 6119 947 85 1032 4711630 794640 5506270
0 0 0 0 0 0 0 0 0 0
c M80 Grade : RC Walls (FL Ground, P1,P2 & P3) Cum 4752 4752 10630 957 11587 1109 100 1209 55061424 5745168 60806592
c M80 Grade : RC Columns (FL Ground, P1,P2 & P3) Cum 1588 1588 10630 957 11587 1109 100 1209 18400156 1919892 20320048
c M80 Grade : Drop Panels (FL Ground, P1,P2 & P3) Cum 563 563 10630 957 11587 1174 106 1280 6523481 720640 7244121
c M40 Grade : Slabs (FL Ground, P1,P2 & P3) Cum 3777 3777 5614 505 6119 882 79 961 23111463 3629697 26741160
OASIS 20 of 25
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING “OBEROI WORLI - 2“AT WORLI, MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
Providing and erecting shuttering formwork, straight, curved or any other shape as per detailed drawing, at any level including strutting, propping, removing the shuttering after stipulated period, re-propping, using marine resistant Plywood / Smooth f
Scheme and methodology to be used for shuttering shall be approved by project manager/consultant before starting of work. 15291 120472 99477 235240 0 0 0 0 0 0 0
( Note : Cost to include shuttering / key required for forming of a Construction joint, designing of proper form work and staging system to suit the requirements,Submission of design calculations and shop drawings for approval,sealing the joints with heavy duty brown self adhesive tape, aligning to line and levels including M.S. Ties, PVC Spacer,applying deshuttering chemical,Deshuttering as ap
f Walls (Core / Shear / Other) Sqm 10039 0 0 10039 496 45 541 511 46 557 5431099 5591723 11022822
f Columns and Drop Pardi Sqm 5967 0 0 5967 262 24 286 511 46 557 1706562 3323619 5030181
f Beams and Slabs Sqm 26776 0 0 26776 920 83 1003 511 46 557 26856328 14914232 41770560
f Staircase Sqm 1478 0 0 1478 920 83 1003 511 46 557 1482434 823246 2305680
f Other Miscellenous RCC Items like Pardi, Canopy,Chajjas, Others Sqm 350 0 0 350 920 83 1003 511 46 557 351050 194950 546000
0 0 0 0 0 0 0 0 0 0
f RC Walls : (FL 04 to FL 09) Sqm 0 7434 0 7434 630 57 687 511 46 557 5107158 4140738 9247896
Core Wall 1520 1520 1523 137 1660 511 46 557 2523200 846640 3369840
AL Wall 5914 5914 400 36 436 511 46 557 2578504 3294098 5872602
f RC Walls : (FL 10 to FL 30) Sqm 0 25890 0 25890 613 55 668 511 46 557 17294520 14420730 31715250
Core Wall 4300 4300 1523 137 1660 511 46 557 7138000 2395100 9533100
AL Wall 14465 14465 400 36 436 511 46 557 6306740 8057005 14363745
Conventional Wall 7125 7125 496 45 541 511 46 557 3854625 3968625 7823250
f RC Columns : (FL 04 to FL 09) Sqm 0 1726 0 1726 983 88 1071 511 46 557 1848546 961382 2809928
f RC Columns : (FL 10 to FL 30) Sqm 0 6557 0 6557 649 58 707 511 46 557 4635799 3652249 8288048
f RC Drop Panels : (FL 04 to FL 09) Sqm 0 431 0 431 1018 92 1110 511 46 557 478410 240067 718477
f RC Drop Panels : (FL 10 to FL 30) Sqm 0 1778 0 1778 1018 92 1110 511 46 557 1973580 990346 2963926
f RC Link Beams : (FL 04 to FL 09) Sqm 0 706 0 706 1018 92 1110 511 46 557 783660 393242 1176902
OASIS 21 of 25
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING “OBEROI WORLI - 2“AT WORLI, MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
OASIS 22 of 25
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING “OBEROI WORLI - 2“AT WORLI, MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
PREAMBLE : Reinforcement shall be measured only in lengths of bars as actually placed in position on standard weight basis (The Bar Bending
691 Schedule
5446 4497and authorised by Client's Project Manager, prior to pouring
shall be approved 10634 of concrete shall 0 0 measurements)
be considered for 0 0 shall be made
No allowance 0 in the weight 0for rolling margin. Authorised
0 0 splices, couplers0of any d
laps and
Providing and fixing steel reinforcement ( FE 500, Deformed bars) for RCC including transporting, de-coiling, straightening, cutting, bending, fabricating and placing in position at all levels and binding with approved quality G.I. annealed0 coated binding
0 wire. The rate0 shall include cost
0 of binding wire,
0 tack welding
0 with chairs, spacers
0 0 margin difference
and pins, rolling 0 which will not 0be meas
r For Walls ( GF to FL 03) MT 750 0 0 750 49544 4459 54003 10670 960 11630 40502250 8722500 49224750
r For Columns & Drop Panels ( GF to FL 03) MT 715 0 0 715 49544 4459 54003 10670 960 11630 38612145 8315450 46927595
r For Beams and Slabs ( GF to FL 03) MT 1070 0 0 1070 49544 4459 54003 10670 960 11630 57783210 12444100 70227310
r For Staircase ( GF to FL 03) MT 40 0 0 40 49544 4459 54003 10670 960 11630 2160120 465200 2625320
0 0 0 0 0 0 0 0 0 0
r RC Walls : (FL 04 to FL 09) MT 0 345 0 345 49544 4459 54003 10670 960 11630 18631035 4012350 22643385
r RC Walls : (FL 10 to FL 30) MT 0 1238 0 1238 49544 4459 54003 10670 960 11630 66855714 14397940 81253654
r RC Columns : (FL 04 to FL 09) MT 0 180 0 180 49544 4459 54003 10670 960 11630 9720540 2093400 11813940
r RC Columns : (FL 10 to FL 30) MT 0 632 0 632 49544 4459 54003 10670 960 11630 34129896 7350160 41480056
r RC Drop Panels : (FL 04 to FL 09) MT 0 28 0 28 49544 4459 54003 10670 960 11630 1512084 325640 1837724
r RC Drop Panels : (FL 10 to FL 30) MT 0 513 0 513 49544 4459 54003 10670 960 11630 27703539 5966190 33669729
r RC Link Beams : (FL 04 to FL 09) MT 0 12 0 12 49544 4459 54003 10670 960 11630 648036 139560 787596
r RC Link Beams : (FL 10 to FL 30) MT 0 42 0 42 49544 4459 54003 10670 960 11630 2268126 488460 2756586
r RC Beams : (FL 04 to FL 09) MT 0 79 0 79 49544 4459 54003 10670 960 11630 4266237 918770 5185007
OASIS 23 of 25
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING “OBEROI WORLI - 2“AT WORLI, MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
OASIS 24 of 25
PROJECT - SHELL AND CORE WORKS AT PROPOSED RESIDENTIAL AND COMMERCIAL BUILDING “OBEROI WORLI - 2“AT WORLI, MUMBAI
BILL OF QUANTITIES FOR SHELL AND CORE WORK
Preparing shop drawings, obtaining consultants approval, supplying, fabricating, delivering at site, hoisting and fixing in position, including all temporary staging and supporting work and making all structural steel work in accordance with the design
The rate shall also include one coat of approved zinc rich primer after properly cleaning the steel surface with wire brush and mild acid solution followed
0 by washing
0 with0 water and
0 drying the
0 surface0 completely.
0 All expose0 structural
0 steel members
0 to
retarding paint.
The supplied structural steel shall be main manufacturer's production.
r Rolled sections such as angles, T sections, channels and I sect MT 15 35 65 15 30 50 210 102010 9181 111191 18738 1686 20424 23350110 4289040 27639150
r MS Plates / Chequred Plate of any thickness MT 15 35 65 15 30 50 210 102010 9181 111191 18738 1686 20424 23350110 4289040 27639150
r Hollow pipes of any diameter and thickness MT 15 35 65 15 30 50 210 102010 9181 111191 18738 1686 20424 23350110 4289040 27639150
r Hollow rectangular or square sections of any size and thickness MT 15 35 65 15 30 50 210 102010 9181 111191 18738 1686 20424 23350110 4289040 27639150
r Chequered plate to be fixed over structural steel framework. MT 15 35 65 15 30 50 210 102010 9181 111191 18738 1686 20424 23350110 4289040 27639150
r For Outrigger Floor on 29th Floor ( Provisional Sum) MT 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
r Supplying, fabricating and installing inserts in concrete in th MT 8 10 12 10 10 10 60 109119 9821 118940 18738 1686 20424 7136400 1225440 8361840
0 0 0 0 0 0 0 0 0 0
5 Coupler (Matarial and Threading) for Whole Structure 0 0 0 0 0 0 0 64000 0 0 0 0 14776000 0 14776000
40mm EA 8000 426 38 464 0 0 0 3712000 0 3712000
36mm EA 8000 360 32 392 0 0 0 3136000 0 3136000
32mm EA 8000 260 23 283 0 0 0 2264000 0 2264000
28mm EA 8000 224 20 244 0 0 0 1952000 0 1952000
25mm EA 8000 154 14 168 0 0 0 1344000 0 1344000
20mm EA 8000 113 10 123 0 0 0 984000 0 984000
16mm EA 8000 96 9 105 0 0 0 840000 0 840000
12mm EA 8000 62 6 68 0 0 0 544000 0 544000
0 0 0 0
OASIS 25 of 25