Demolition Report
Demolition Report
CAMBRIDGE COLLEGE
Prepared for
BLD 571
DEMOLITION AND DECONSTRUCTION OF BUILDINGS
Presented to
Dr. O.J Oladiran
Presented by
Oguntuyi Oluwatoyosi
170504059
INTRODUCTION
This report for the demolition and deconstruction of Cambridge College (The Building),
formerly located at 64 Adekunle Fajuyi Street GRA, Ikeja, Lagos (The Site), was prepared by
Oguntuyi Oluwatoyosi.
The purpose of this report is to summarize the deconstruction and demolition of the building at
the Site. This report contains responses from the organization conducting the demolition about
the actions undertaken at the Site, including the preparation, deconstruction and demolition of
the building. The building contained other substances, such as fluorescent light components and
other materials disposed as part of the work. The deconstruction and demolition were performed
to prepare the site for another building to be erected.
PROJECT ORGANIZATION(S)
This section summarizes the project organization and information about the organization. Project
activities were performed within the framework of the organization.
The demolition organization was selected by LABSCA through a public bid process. Metric
Ideas Nigeria, LLC, was selected as the general demolition contractor.
CORRESPONDENT INFORMATION
Name: Mr Kunle Taiwo
Contact Info: [email protected]
Designation in Company: C.E.O., Project Architect
Years of Work Experience: 37 Yrs.
Professional Body belonged to: Nigerian Institute of Architects, Project Management
Professionals
Highest Education: M.Sc.
Number of Demolition projects done: Above 30
ORGANIZATIONAL INFORMATION
Type of Organization: Private Org
Owner ship of Organization: Fully Indigenous
Staff Strength: 15 Staff members
Annual Turnover: 100 million and above
Staff Structure: 100% Retained Staff
SITE LOCATION
The building was a single-story building used as an office space for Cambridge College.
There is a six-story building belonging to the Redeemed Church Of God, Rose of Sharon Parish
near the site.
Concrete from the interior walls are hauled to a location on site to be used for fill material.
Metals were sorted during the deconstruction process and removed from the site and hauled to a
recycling facility.
Water that had accumulated in the pool during deconstruction activities was properly drained off
and the pool elements like the railings, tiles were removed, cleaned and packed away.
Fluorescent Light bulbs were removed from the site by the contractor
SITE GRADING
The rubble hauled away for fill would be brought to the root of the old foundation and the
contractor would level the site following the specifications included in the demolition plan for
the new construction to take place
INSPECTIONS
Pre-Final Inspection
In preparation for a site walk after demolition a punch list would be developed to catalogue
outstanding work items for the contractor to address prior to final closure of the project.
Final Inspection
A final inspection of the work would be done after the contractor has addressed the punch list
items from the pre-final inspection. No other unresolved issues or work items would remain at
the time of the final inspection.
This table shows the Deconstruction Process done on the Project, the process, the equipment used
and the type of materials salvaged, recycled or disposed after deconstruction