Scheduler Trainer
Scheduler Trainer
Scheduler Training
2020
2015
SYNCHRO Scheduling Training: Contents
CONTENTS
Overview ................................................................................................................. 1
1.1. Why SYNCHRO? ................................................................................................... 1
1.2. Why 4D? ............................................................................................................. 1
1.3. Who uses SYNCHRO? ........................................................................................... 1
1.4. How does SYNCHRO Scheduler apply to you? ........................................................ 1
1.5. Course Description ............................................................................................... 1
Workspace Layout ................................................................................................... 2
2.1. Windows in SYNCHRO ......................................................................................... 2
2.2. Workspace Management ...................................................................................... 3
Options and Set-Up ................................................................................................. 5
3.1. Customise Columns .............................................................................................. 5
3.2. Date & Duration Display ....................................................................................... 6
3.3. Auto Save ............................................................................................................ 7
3.4. Rescheduling Options ........................................................................................... 8
3.5. Critical Path Options ............................................................................................. 9
3.6. Task ID Options ................................................................................................ 10
3.7. WBS Layout ....................................................................................................... 11
3.8. Gantt Display Options ......................................................................................... 12
3.9. Project →Scheduling .......................................................................................... 13
Calendars ............................................................................................................... 14
4.1. Project Calendar ................................................................................................ 14
4.2. Adding Calendars ............................................................................................... 14
4.3. Modifying Calendar Work Hours .......................................................................... 15
Gantt Chart Navigation ......................................................................................... 16
Creating Tasks ....................................................................................................... 17
6.1. Creating WBS (Parent-Child) relationships ........................................................... 18
6.2. Copy & Paste Tasks ............................................................................................ 20
6.3. Changing Task Calendars ................................................................................... 21
6.4. Task Properties → General ................................................................................. 22
Linking Tasks ......................................................................................................... 23
7.1. Link Tasks in a Chain with Automatic Rescheduling Enabled ................................. 23
7.2. Link Tasks in a Chain with Automatic Rescheduling Disabled................................. 25
7.3. Introducing Lag between Tasks .......................................................................... 26
7.4. Creating Links from Task Properties>Links .......................................................... 27
7.5. Creating Links from Task Bars............................................................................. 29
Schedule Sorting ................................................................................................... 30
Task Modification .................................................................................................. 32
9.1. Changing Duration ............................................................................................. 32
9.2. Changing Start Times ......................................................................................... 32
9.3. Changing Finish Times ....................................................................................... 33
Activity Codes ........................................................................................................ 34
10.1. Creating Activity Codes ....................................................................................... 34
10.2. Assigning Activity Codes ..................................................................................... 34
10.3. Sorting by Activity Codes .................................................................................... 35
Resources .............................................................................................................. 37
11.1. Companies ........................................................................................................ 37
11.2. Creating Resources ............................................................................................ 37
11.3. Sub-Resources ................................................................................................... 38
11.4. Assigning Resources to Tasks ............................................................................. 38
Task Costs.............................................................................................................. 40
12.1. Resource Costs .................................................................................................. 40
12.2. Direct Costs ....................................................................................................... 41
SCH|i
SYNCHRO Scheduling Training: Contents
SCH|ii
SYNCHRO Scheduling Training: Overview
Overview
1.1. Why SYNCHRO?
The SYNCHRO team at Bentley is passionate about improving construction project performance because we understand the
impact construction has on global resources, and we recognize the importance of the industry to quality of life and economic
prosperity. We have also experienced how significantly digital technology improves results over the tried and true methods
that have been standard in the industry for generations. Imagine crystal clear communications and engaged team
collaboration. Imagine the ability to easily create a shared vision of the project among your stakeholders, the ability to
identify spatial and resource clashes in the planning phase rather than the costly construction phase, imagine a project
schedule that gives you confidence to deliver according to plan!
It is time to Synchronise your projects. As always, we welcome your feedback at any time, we look forward to seeing your
results and we hope you will share your experience with SYNCHRO with others to spread the word. Thank you for investing
your time in learning SYNCHRO Scheduler, together we will make a positive change in how projects are planned and
delivered.
Scheduler|1
SYNCHRO Scheduling Training: Workspace Layout
Workspace Layout
This section will present the various windows in SYNCHRO and how to reorganize and manage your workspace.
Toolbars
Resources Task List & Gantt Chart Window Properties
• Quick Access Toolbar: contains commonly used icons. The Quick Access toolbar can be customized by left clicking on the down arrow
and selecting More Commands.
• Ribbon: contains commands, sorted by category. In the top right corner of the Ribbon is the Help menu which can be used to find
more information about a particular feature.
• Toolbars: contain shortcuts and useful commands found in SYNCHRO. Right click in the blue space below the Ribbon to view and
select available toolbars. Select Customise to create your own custom toolbar of commonly used commands.
• Gantt: window is split into the Task List on the left which displays the list of tasks and properties in columns and the Gantt Chart on
the right which displays the task bars with logic links.
• Resources: contains the list of Resources (including those imported and those created in SYNCHRO)
• Resource Groups: contains the list of Resource Groups (can be used e.g. for Work Package Planning, or for simulated growth in
SYNCHRO Pro)
• Task Properties: contains data related to the selected Task(s) including Task Status (in the General panel), assigned Resources, and
Budgeted Costs.
• Resource Properties: contains data related to the selected Resource(s) including Costs, assigned to Tasks, and User Fields.
Scheduler|2
SYNCHRO Scheduling Training: Workspace Layout
Select (left mouse click) the Gantt Tab to display the Gantt Chart.
If you are using SYNCHRO Pro, close the 3D window.
2.2.1. Resizing Windows
Place the cursor over the divider between the Task List and the Gantt Chart so the double arrow icon
appears.
Select it with a left mouse click, hold down and drag to the right so you can see all of the column headings in the
Task List. All windows in SYNCHRO can be resized by this method
2.2.2. Undocking and Relocating Windows
To undock a single tab, left click on the tab and keep holding the mouse button while moving the mouse. The tab
will be undocked as a new window. To undock a window, double click in the window header.
If you are using multiple monitors, you can then move the new window to another screen.
To resize the undocked window, hover over a corner until a diagonal arrow appears, then left click and drag to the
desired size.
Scheduler|3
SYNCHRO Scheduling Training: Workspace Layout
To re-dock the window in the previous location, simply double click the window header.
If you close any of these windows, you can re-open them by selecting the appropriate icons in the Windows ribbon.
To reset the window layout to the default, select Windows ribbon → Window Placement panel → Reset Placement
This command is particularly useful if you cannot locate a particular window or the layout is changed when
switching from multiple monitors to only one.
Scheduler|4
SYNCHRO Scheduling Training: Options and Set-Up
2. Under Task Parameters in Durations, select Planned Duration, Under Relationships select Predecessors, Successors.
Under Scheduling select Downstream Total Float and move them from Available Columns to Selected Columns by
using the button. Remove the Duration and 3D Resources columns by using the button. Move the
columns using the Up and Down buttons so the Customise Column window looks as shown below and then select
OK. This will create extra columns in the task list. You can add or remove other columns in a similar manner.
Scheduler|5
SYNCHRO Scheduling Training: Options and Set-Up
3. To resize the columns, hover between the column titles until the double arrow icon appears, then hold down the left
mouse button and drag to the left or right.
Scheduler|6
SYNCHRO Scheduling Training: Options and Set-Up
You can leave the Options dialog open for the next
section
Scheduler|7
SYNCHRO Scheduling Training: Options and Set-Up
NOTE:
• When Enable Automatic Rescheduling is disabled, reschedule will not be proposed when a link is unscheduled.
• To reschedule manually, disable Automatic Rescheduling and press F9 (This will be used later in the tutorial.)
• The Confirm Rescheduling results option, when selected, will prompt the user to confirm that project
rescheduling should take place whenever a change is made to the schedule that affects other tasks. This option
only applies when Automatic Rescheduling is enabled.
• “Snap To” defines how the tasks are rescheduled. When a task is rescheduled it will snap to the specified time
increment. For example, if Snap To is set to Day and you have two tasks of 1.5 days linked in a chain with Finish
to Start relationship, the second task will not be able to start immediately after the first task (half way through
the day). Instead its start time will “snap” to the beginning of the next full day. Therefore, the second task would
finish 3.5 days after the start of the first. On the other hand, if Snap To is set to Minute, the second task can start
at the beginning of the next minute after the first finishes. Therefore, it will start immediately after the first and
will finish 3 days after the start of the first.
• The Link Calendar to use during rescheduling options allows the user to choose how SYNCHRO calculates the link
delays each time the project is rescheduled. (See the Help in SYNCHRO for a thorough description of each
option)
• The On scheduling progressed Tasks use options allow the user to choose how SYNCHRO calculates the
schedule. Each scheduling calculation may produce different planned dates and/or float depending on the tasks’
actual dates and if any tasks are out-of-sequence. (See the Help in SYNCHRO for a more thorough description of
each option)
You can leave the Options dialog open for the next section
Scheduler|8
SYNCHRO Scheduling Training: Options and Set-Up
NOTE:
Critical Path update options determine when the Critical Path display will be updated:
• Don’t Update – The Critical Path is not displayed.
• Update Manually – Update the Critical Path displayed by selecting Plan ribbon→ Schedule panel→ Compute Critical
Path or Ctrl + F5.
• Update Automatically (slowest) – The Critical Path displayed is updated automatically.
Critical Path method options determine how the critical path is calculated:
• Longest path - the critical path is calculated as the longest chain of tasks with zero float.
• Least total float – the critical path is calculated as the longest chain of tasks that match the float criteria you define
using the following:
o Maximum for critical Tasks defines the maximum total float allowed for a task to be considered critical.
o Maximum for subcritical Tasks defines the maximum total float allowed for a task to be considered near-
critical.
o Duration units define the units being specified in previous options.
Scheduler|9
SYNCHRO Scheduling Training: Options and Set-Up
Scheduler|10
SYNCHRO Scheduling Training: Options and Set-Up
2. To customise the WBS colour scheme, select the WBS Layout Colours button in the Gantt Display Options window.
The WBS Colours window will be displayed. In this window, you can:
• Enable/disable the Default WBS colours.
• Select New to design your own layout.
• Modify colours/order of Levels for a layout.
Scheduler|11
SYNCHRO Scheduling Training: Options and Set-Up
Scheduler|12
SYNCHRO Scheduling Training: Options and Set-Up
NOTE: The Blue dotted line displayed in the Gantt Chart is the Data Date. The Red dotted line with the red triangle is
the Focus Time used primarily in 4D Projects. In Scheduler it can be used to display the Spotlight Gantt Indicator,
show values for a specific date in the EVA Graph, and to create a dynamically updated Task Filter
5. The Schedule setting defines whether a task should be scheduled to its Early Dates (ASAP – As Soon as Possible) or
scheduled to its Late Dates (ALAP – As Late as Possible). For the purpose of this training leave it set to the default –
ASAP.
6. The Schedule From/To settings tell the software the time frame that you want the schedule calculations to pass
through. Set Schedule From to Data Date and Schedule To to Early Project Finish
NOTE:
• Schedule From defines the date to use when Schedule is set to ASAP and when scheduling tasks which are
constrained to Start as soon as possible.
• Schedule To defines the date to use when Schedule is set to ALAP and when scheduling tasks which are
constrained to Start as late as possible.
• It is NOT necessarily recommended that constraints be used, but if they are this is how the associated tasks
will be scheduled.
Scheduler|13
SYNCHRO Scheduling Training: Calendars
Calendars
In this section, you will learn how to create and modify project calendars.
Calendars are used to assign working time and non-working time to an activity. Every project will
have a default calendar that is used when new tasks are created or scheduled. Other calendars
can be added to define different working periods for different Tasks or Resources. For example,
you can have one calendar that defines a regular 5 day work week and another calendar that
defines a 7 day work week for required weekend work.
Scheduler|14
SYNCHRO Scheduling Training: Calendars
The Normal Working Day will be an 8 hour day with 2 work periods for the 7 day work week calendar for all dates as
shown.
Scheduler|15
SYNCHRO Scheduling Training: Gantt Chart Navigation
The training material contains a template file with calendars created, Task List columns set up, and a basic Work Breakdown
structure entered. We will open this file and continue from there. See Appendix A for more about using templates.
NOTE: If you need to access the training material, select the Support tab in the SYNCHRO application (next to Gantt) and click
on SYNCHRO Training.
Scheduler|16
SYNCHRO Scheduling Training: Creating Tasks
Creating Tasks
In this section, you will learn how to create new tasks in a Work Breakdown Structure, how to copy and paste tasks, and how
to change task calendars, as well as where to find task properties.
1. Use the Calendar dropdown box from the Fast Options toolbar to select a calendar to use for all new tasks. Select a
5 day work week as shown.
2. With all the tasks expanded, in the Task List select the first empty Name cell (after Interiors Level 02) by left clicking
on the cell so it is highlighted. This allows you enter a new activity name.
NOTE: To edit the current activity name, highlight the cell and left click, or right click and choose Rename Task from
the context menu. Selecting F2 on the keyboard when the cell is highlighted also enables editing of the cell.
3. Type “MEP Rough-in” in this Name cell then press Enter on the keyboard.
4. You will see the following cells populated:
• ID (derived from the values given in Options → Default for New Objects →Task ID)
NOTE: Don’t worry if the IDs in your schedule don’t match the ones shown in the training
• Name (manually entered)
• Planned Duration (Defaults to 1 day)
• Start (Same as Data Date)
• Finish (Start plus Planned Duration)
• Gantt bar created
5. To edit the duration of the task, left click in the Planned Duration cell and type 5. Days are the default units so
simply press Enter to set the duration to 5d.
NOTE: To override the default units when entering a duration value, simply append one of the following
characters to specify the required duration:
m for Minutes
h for Hours
d for Days
w for Weeks
6. Create 2 more tasks below MEP Rough-in by typing “Framing/Drywall” and “Trim-out” in the empty rows below.
7. If you want to set the same duration for multiple tasks, you can use the drag down method. In the duration cell for
MEP Rough-in hover over the grey box in the bottom right hand corner and a crosshair icon will appear.
8. Select this crosshair icon with a left mouse click, hold and drag over the duration cell below until both durations
read 5d.
9. Set the Planned Duration of Trim-out to 3d by typing in the cell.
Scheduler|17
SYNCHRO Scheduling Training: Creating Tasks
The new tasks were created at the top level of the Work Breakdown Structure. One way to create parent-child
relationships is to use the Move → Indent command.
1. Left click the MEP Rough-in task, hold Shift on the keyboard and select the Trim-out task. The 3 new tasks should be
highlighted yellow in the Task List.
2. From the Plan tab → Move panel, from drop down menu select Indent.
3. The Indent command is now the default Move command. Press Indent (no need to open the drop-down menu) two
more times until the task Interiors Level 02 changes colour to indicate that it is now a summary task, and its Gantt
bar changes to a summary bar.
Scheduler|18
SYNCHRO Scheduling Training: Creating Tasks
Another way to create a parent-child relationship is to use the Create → As Child command.
NOTE: The Create → As Child command is only available when the Task Grouping is set to WBS (in Plan→Gantt
Display Options)
6. A New Task will be inserted in the row below the selected task and indented one level so that the selected task
becomes a summary.
7. Rename the new task to Footings, Area 1 and enter 4d for the Planned Duration.
8. To create another child task of the Footings summary, we will add another new task below the Footings , Area 1
task. With Footings, Area 1 highlighted, select Plan ribbon → Create panel → Below. The new task will be at the
same level as the selected task.
NOTE: The Above, Below, and As Child commands for creating new tasks are also available under Insert New Task via
a right click in the Task List,
9. Insert one more task Below so that there are 3 child tasks beneath the Footings summary.
10. Use the same method for renaming tasks as you used for copying duration values.
- Hover over the grey box in the bottom right hand corner of the Footings, Area 1 Name cell until a
crosshair icon appears.
- Select this with a left mouse click, hold and drag over the name cells below and they will be named in
numerical order Footings, Area 1, 2 and 3.
- The result should be as shown:
NOTE: All task names that end in a number can be incremented this way.
Scheduler|19
SYNCHRO Scheduling Training: Creating Tasks
1. Left click the MEP Rough-in task, hold Shift on the keyboard and select the Trim-out task so all 3 adjacent tasks are
highlighted yellow in the Task List.
2. Right click on one of the selected tasks and choose Copy Task(s) from the context menu or Ctrl+C on the keyboard
3. Right click on Task Interiors Level 02 (it should now be highlighted) and choose Paste Task(s) from the context menu.
All 3 copied tasks will be inserted above
4. Select the 3 pasted tasks and use Move>Indent so that the tasks are indented beneath Interiors Level 01
5. Repeat steps 3 and 4, instead pasting above the Task Interiors Level 01
6. The final result should look as below. Notice that the durations were copied as well as the task names.
Scheduler|20
SYNCHRO Scheduling Training: Creating Tasks
1. It is best to choose the calendar to be used before creating the tasks. From the Fast Options toolbar under the
ribbon, select 7 day work week for the default Calendar.
2. Select the task Steel Level 00-01 and insert 2 child tasks under it. Edit the names and durations of the new tasks as
follows:
When the project is scheduled, these tasks will continue through the weekend
if they happen to fall on one even though the other tasks with the Project
Calendar will stop over the weekend.
3. On the right hand side of the screen, open Task Properties → General tab. If
the Task Properties window is not open, you can open it from the Windows
ribbon →Properties Panels panel.
4. Here you can confirm the task calendar for the selected task.
NOTE: The task calendar can be changed after the task is created using the Calendar drop-down in Task Properties
→ General tab. Changing the calendar in the Fast Options toolbar does not affect tasks that have already been
created. If the new calendar has a different number of hours per day, the task duration will be updated accordingly
to retain the same amount of work time, in minutes. For example, if the task was originally planned as 4 days with a
calendar that has 10-hour work days, and the task Calendar is changed to one with 8 hour days, the new duration
will be 5 days in order to retain a duration of 40 working hours.
Scheduler|21
SYNCHRO Scheduling Training: Creating Tasks
All of the tasks we have created thus far are Work Type tasks. SYNCHRO also has the
capacity to create other types of tasks, including key dates (milestones) and
hammocks. Key Dates are divided into Start Key Date and Finish Key Date types.
NOTE: Use Options>Gannt Chart>Rescheduling>Parameters to control whether Start
Key Dates can be scheduled for the end of a work day and Finish Key Dates can be
scheduled for the Start of a work day.
Scheduler|22
SYNCHRO Scheduling Training: Linking Tasks
In Section 8, you will learn how to add logic links to the schedule to drive the key date’s planned date. For key dates that
are contractually mandated, you may add a Constraint.
NOTE: Constraints may cause the task Float to be calculated incorrectly
6. In the Task List, select the Start Key Date Project Start
7. In Task Properties → General, change the Constraint Type to
Mandatory Start. The Constraint Early Date will be automatically
populated from the Planned Start (but this could be changed if necessary by typing the new date or pressing the “…”
button to open a calendar)
Linking Tasks
In this section, you will learn how to create logic links between tasks and add a lag or lead to a link.
Links between tasks allow the scheduler to specify the order in which tasks must take place; for example, walls must be built
before they can be painted. Rather than specifying a start date for each task, the links allow those dates to be calculated
automatically based on the logic. Links also make sure that if one task is modified (e.g. changed duration or delayed start) all
other tasks update accordingly. There are several ways that tasks can be linked to each other in the project schedule. This
section will discuss the options that are available.
Consider two tasks with a link between A->B. A is called the Predecessor and B is the Successor. There are four link types as
described below
• Finish to Start (FS) – A must finish before B can start. This is the most common link type. E.g. Excavate Foundation FS
Pour Foundation; Frame walls FS Drywall
• Start to Finish (SF) – B cannot finish until A starts. This type is rarely used.
• Start to Start (SS) – A must start before B can start.
• Finish to Finish (FF) – A must finish before B can finish
1. Open the file SCH Training – Links.SP from the training material. File Location:
C:\Users\Public\Documents\Shared SYNCHRO Projects\Tutorial Files\SYNCHRO Scheduler Training\ .sp Files
The remaining tasks have been added for you.
2. Select task - Mobilize Site Offices, then hold down Ctrl on your keyboard and select task - Mobilize Equipment so
they are both highlighted in that particular sequence
3. Ensure that the link type is FS (Finish to Start) in the Fast Settings toolbar.
4. Select Plan → Links → Link As Chain. With each link change the Reschedule Task dialog box will open since both
the Automatic Rescheduling and Confirm Rescheduling results options are enabled. The Gantt Chart will show a
preview of the proposed new position of the Task Bar outlined in black.
TIP: Ctrl + L is the keyboard shortcut for Link As Chain.
Scheduler|23
SYNCHRO Scheduling Training: Linking Tasks
5. If the preview is acceptable click Yes and the project will be rescheduled.
NOTE: If the Automatic Rescheduling is enabled and Confirm Rescheduling results is not enabled, the project will
reschedule with no warning with each link change.
Scheduler|24
SYNCHRO Scheduling Training: Linking Tasks
7. When an alert instance is selected, the Gantt chart is refocused to the tasks and the
link.
8. Manually reschedule by pressing F9. The Reschedule command is also available in the Plan ribbon → Schedule
panel →Reschedule.
9. The Reschedule Options window will be raised. This
window allows you to edit the various schedule related
settings including Data Date.
NOTE: The Parameters and Critical Path tabs contain
further settings which may need to be updated on your
own projects depending on the source of the schedule and
your company’s default scheduling methods.
For this training, leave the settings as shown, enable Do not
ask again to hide the dialog on future reschedules and press
Reschedule
10. The schedule will be recalculated, the unscheduled links
will be corrected, and the alerts will be removed.
NOTE: Remember to press F9 to reschedule periodically
and/or run a Reschedule Report to find any unscheduled
links. If you wish to show the Reschedule Options dialog
again, it can be enabled in Options>Gantt
Chart>Rescheduling>Parameters by unchecking Disable
Rescheduling Options dialog
Scheduler|25
SYNCHRO Scheduling Training: Linking Tasks
NOTE:
• If you want to remove an individual link, right click on the predecessor
or successor in Task Properties → Links, then select Delete.
• If you want to remove all links on that task, right click in either the
Predecessors or Successors box and select Remove All.
Scheduler|26
SYNCHRO Scheduling Training: Linking Tasks
NOTE: The Add / Remove Links dialog can also be accessed by double clicking in either the Predecessors or
Successors columns in the Task List.
3. Enable Search by Name and type “Ex” in the Search bar to find the Excavation tasks. The list filters automatically
as you type.
4. Double click on the task Mass Excavation from the list (or select and then click Add)
5. The Predecessor Link options above will be populated. Change Link Type to FF (Finish to Finish) using the drop
down menu.
Scheduler|27
SYNCHRO Scheduling Training: Linking Tasks
6. In the top right of the Add / Remove Links window, select Successors. You can now add Sucessors to Shoring
Install which is still listed as the Target Task.
7. Select Footing Excavation and select Add. Modify the Link Type to a FF and the Lag to 2 days.
8. You can change the Target Task from within this dialog to continue adding Predecessors / Successors to other
tasks. To do so, clear “Ex” from the Search bar and type, “Footing” instead.
9. Select the task Footings, Area 2 from the task list (outside the dialog box)and select Footings, Area 3 from the
Target Task list within the dialog.
10. Notice that you are still adding Successors, so double click to add- keep the link settings as default (FS, 0d Lag).
11. Switch to adding Predecessors.
12. Select Footings, Area 1 then Add - keep the link settings as default, then Close the Add/Remove Links window
13. Press F9 on the keyboard to reschedule. The result should look like this:
Scheduler|28
SYNCHRO Scheduling Training: Linking Tasks
3. Move to the far right of this task bar and it will change into a chain-link icon.
4. Hold down the left button on the chain-link, and then drag the mouse until you see a black link line with an arrow
that you will snap to the front of the next task. This creates a Finish to Start link.
NOTE: Depending on where the linked has been “snapped from” and “snapped to” will determine the Link Type (FS,
FF, SS or SF).
5. Link the task Slab, 01 to the task Slab, 02 in the same manner with a FS relationship
6. Press F9 on the keyboard to reschedule
NOTE: Please see Options → Gantt Chart → Links for various available Link options
Scheduler|29
SYNCHRO Scheduling Training: Schedule Sorting
Schedule Sorting
In this section you will learn how to sort the Task List by any column.
1. Open SCH Training - Sorting.sp. The rest of the links have been added for you. Default location for tutorial files:
C:\Users\Public\Documents\Shared SYNCHRO Projects\Tutorial Files\SYNCHRO Scheduler Training\ .sp Files
The schedule can be sorted several different ways. Under Plan ribbon → Display panel →Gantt Display Options → Task
Grouping →WBS has been chosen for the primary sort. If Activity Codes had been created and assigned to each activity the
schedule could be sorted by the Activity Codes. (This will be covered in section 10)
To sort on a column, simply left click in the column heading you want to sort - sort Ascending will
be applied. A small triangle icon on the right of the column will indicate the sort direction. Left
click again to sort Descending. A third left click will remove sorting on that column. For example,
you can sort ascending and descending by Task ID, by Start or by Finish.
A right click in the column header opens the context menu from which specific sorts can also be
selected such as Ascending Critical Path or Sort via WBS Level. The Ascending Critical Path option
ensures that all tasks on the Critical Path are sorted to the top of the Task List. Use the Sort via
WBS Level option to prevent sorting of the Summary (parent) tasks. Use the Sort... command to
open the Sort dialog to sort the Gantt Chart by multiple criteria or edit the current sorting criteria.
2. Right click in the Task list header and choose Custom. (Task Grouping can be set in this context menu or in Gantt
Display Options). If Custom Grouping is selected, but no Groups are specified, the Tasks will be shown in a flat list.
3. In the Task List, left click in the Start column to sort ascending. The tasks are now sorted in order of start date like a
waterfall.
Scheduler|30
SYNCHRO Scheduling Training: Schedule Sorting
4. Right click in the column header and choose Sort. The Sort dialog opens displaying the current sort.
5. Select Add to sort by another parameter.
6. From the Sort by dropdown, you can select from any of the visible columns.
Scheduler|31
SYNCHRO Scheduling Training: Task Modification
Task Modification
In this section, you will learn how to edit task durations and start and finish times.
1. Select the task Footings, Area 1 and click in the Planned Duration cell
2. Either type 2d (2 days) or double click in the duration cell, highlight the number 4 and use the down arrow until the
duration reads 2d
1. Select the task - Curtain Wall, S under Envelope then open Task Properties →
General tab.
2. Change the Constraint Type to Start On or After.
3. The Early Date (to start on or after) is automatically set to the Planned Start. To
change the date, select the “…” to open the calendar, then select 2 May 16.
4. Press F9 to reschedule.
5. A marker has been placed in the Gantt Chart to indicate that this task is
constrained. Additionally an asterisk (*) has been added to the the Start column to
indicate the constraint.
Scheduler|32
SYNCHRO Scheduling Training: Task Modification
Scheduler|33
SYNCHRO Scheduling Training: Activity Codes
Activity Codes
In this section, you will learn how to create Activity Codes, assign them to tasks, and sort the
schedule by Activity Codes.
Activity codes are used to organize tasks by grouping, sorting, and/or filtering. Each task can have
an unlimited number of activity codes assigned to it. This allows greater flexibility for organizing,
sorting, and filtering.
Scheduler|34
SYNCHRO Scheduling Training: Activity Codes
NOTE: Activity Codes will only be assigned to bottom level tasks, never to
summaries (even if selected).
4. To check the codes assigned to a task, select a task, for example Shoring
Install. Then open Task Properties → Codes tab. The Code and associated
code value will be shown in the table
The sort priority for the Gantt Chart can be defined by prioritizing of the codes and code values. To prioritize,
select the code or code value and use the arrows towards the bottom of the Codes window to rearrange.
Scheduler|35
SYNCHRO Scheduling Training: Activity Codes
4. Select Phase and use the up arrow to move it to the top of the list. Select Level and use the down arrow to move
it to the bottom of the list so the priority is Phase, followed by Responsibility, then Level. The task sorting in the
Gantt Chart will update accordingly:
Scheduler|36
SYNCHRO Scheduling Training: Resources
Resources
In this section you will learn how to create resources and assign them to tasks.
There are 4 types of Resources available in SYNCHRO – Equipment, Human, Location, and Material – which can be assigned
to individual tasks to manage resource utilization and cost.
11.1. Companies
Companies are responsible for providing resources for the project tasks. Companies can
be added by opening the Navigator ribbon →Project Data panel → Companies window.
1. Right click in the Companies list panel and select Add from the context menu.
2. A new company named New Company will be added. Rename New Company to Dirt
Works
3. Highlight the company Dirt Works. Open up Companies → General tab and change
the Type to Subcontractor. It is possible to specify a working calendar for each
Resource; for this Company, leave the Calendar as 5 day work week.
NOTE: Contact information for the Company can be added in the Contact tab below
4. Add a second Company called Carl’s Concrete and set the Type to Subcontractor
Scheduler|37
SYNCHRO Scheduling Training: Resources
11.3. Sub-Resources
There are times when a resource needs to be broken down into sub-resources. For example, the concrete crew is
comprised of carpenters, labourers, iron workers, and finishers. To track the work each discipline performs on a task the
Concrete Crew resource must be broken down into sub resources.
1. In the Task List under Phase A, highlight the tasks - Mass Excavation; Footing Excavation; and Shoring Install
2. Highlight Backhoe in the Resources window and drag and drop it onto the three highlighted tasks to assign it
3. In the Activity Codes window, uncheck Phase and Level so that Responsibility is the only Activity Code being used to
sort the Gantt Chart.
Scheduler|38
SYNCHRO Scheduling Training: Resources
4. Select all 6 tasks under the Code Responsibility.CON in the Task List
5. In the Resources window, highlight Concrete Crew and drag and drop onto the selected tasks to assign.
NOTE: The sub-resources can also be assigned individually by selecting them at the bottom of the Resources tree
6. Left click to select just one of the Responsibility.CON tasks
7. Open Task Properties window → Resources tab on the right of the screen to verify that the Concrete Crew and all
its sub-resources have been assigned to the task.
Scheduler|39
SYNCHRO Scheduling Training: Task Costs
Task Costs
In this section, you will learn how to assign costs to resources and directly to tasks, and how to view the project costs and
Earned Value graph.
Costs can be assigned to each task. This is either done by assigning cost to the Resource, thus a task’s cost is computed
based on resource utilization, or by assigning a Direct cost to a task.
First check the correct currency is selected. Select Options → General → Currency. Select the desired currency and
formats.
NOTE: The currency settings affect the display only. Switching between currencies simply updates the currency symbol ($, £,
€, etc) displayed next to the cost amount – it does NOT convert the value.
7. A new cost will appear that is named the same as the Resource by default
Scheduler|40
SYNCHRO Scheduling Training: Task Costs
8. Change the Type to Daily; and put in $240 under the Amount.
9. For practice, using the same method as above assign the following cost to the Finisher as noted follows: Type =
Daily; and Amount = $280.
The Costs for the other Concrete Crew resources have already been assigned.
10. Select task Slab, 00, and open Task Properties →Cost Totals. You will see the costs from all the assigned resources
including the Type (Daily, Hourly, Fixed),
Amount (e.g. Daily rate), Units total (e.g.
# of days) and the Amount total
(=Amount x Units total). The total task
cost is listed in the top row Budgeted
Totals – if there are Direct costs
(discussed next in section) or Risk costs,
these will be summed with the Resource
costs to make the Budgeted Total.
A direct cost can also be assigned as a fixed cost. The Fixed cost is the total lump sum cost for that task regardless of
task duration.
9. In the Task List highlight the task Temp Power Install under Site Prep. Assume for the purposes of this training
that this task is going to be subcontracted out for a fixed lump sum price.
10. Under Budgeted Direct Costs, right click in the cost window.
11. Right select Add and a “Budgeted Direct Cost” item will appear.
Scheduler|41
SYNCHRO Scheduling Training: Task Costs
12. Right select to Rename the “Budgeted Direct Cost” to Temp Power Install.
13. Modify the Type to Fixed under the drop-down menu.
14. Change the amount from $0 to $1000.
15. In Task Properties → Cost Totals you will see that the Budgeted Total is $1000. The Cost Total fields have been
populated as shown below.
Scheduler|42
SYNCHRO Scheduling Training: Task Costs
1. To review the Total Project Budgets open the Navigator ribbon → Project Data panel → Project → Costs tab. You
will see there are Budget Totals for both the Resources and the Direct costs
Scheduler|43
SYNCHRO Scheduling Training: Task Costs
1. Open the Windows ribbon → Usage panel → EVA Graph. The EVA Graph window will open below the Gantt Chart
2. Using the check boxes in the Legend, turn off all lines except PV (Planned Value).
The budgeted costs or Planned Value (PV) for the selected task(s) and subtasks (if any) will display in the EVA
graph.
NOTE: Zoom and pan for the EVA graph can controlled in the Gantt Chart or the EVA graph.
3. Right click in the Gantt Chart and choose Collapse To → Level 2
4. Select the Construction summary task to see the Planned Value line for the entire project.
5. Drag the red focus time marker through the project timeline to see the Planned Value at any point in time.
6. Right click in the EVA Graph and choose Show as % of BAC (Budget at Completion) – this hides sensitive cost
information by showing the EVA as a percent of the total cost (approaching 100% at the end of the project)
7. Select EVA Graph in the Windows ribbon to hide the EVA Graph window.
Scheduler|44
SYNCHRO Scheduling Training: Baselines
Baselines
In this section, you will learn how to save a baseline and compare a baseline to the current schedule
A baseline is a snapshot in time that can be created to analyse “what-if” scenarios or compare planned against actual in
SYNCHRO. Baselines can be made up of all tasks or just a few tasks. It depends on what needs to be compared.
4. The Baseline Tasks window will be shown. The name automatically includes the Data Date. You can choose to
leave the name as it is or rename to something more descriptive. For this training, rename to Revised Schedule.
5. Select Baseline all Tasks and click OK.
NOTE: If any WBS summaries are collapsed in
the Gantt Chart, any of their children tasks
will not be included in the Baseline when the
“Select only visible Tasks” option is chosen
Scheduler|45
SYNCHRO Scheduling Training: Baselines
6. The new baseline will be listed in the Navigator ribbon → Scheduling panel→ Baselines and Scenarios window. In
the current schedule, the critical path tasks are white outlined in red, whereas tasks not on the critical path are
green as shown below. The Baseline is directly over the current schedule, with critical tasks in solid blue, and non-
critical tasks outlined in blue but hollow.
NOTE: The Baseline bar colour can be changed by opening General in the Baselines Tab and selecting a new colour.
The Critical task colour is controlled in Options → Gantt Chart → Colours → Critical Path.
10. To turn off the Baseline display in the Gantt Chart, in the Baselines and Scenarios window list, deselect Revised
Schedule. Below it is easier to differentiate between the display of critical and non-critical tasks in the current
schedule.
11. To turn off the Critical Path display, toggle off Compute Critical Path in the Plan ribbon → Schedule panel. This
command can be used to calculate and display the critical path at any time.
Scheduler|46
SYNCHRO Scheduling Training: Baselines
You will then see a difference between the original plan and the revised.
3. Open Customise Columns. Add the BL Start column and the BL Finish column to compare the initial early dates
to the current planned early dates.
4. You can also see how the baseline and current planned costs compare in the EVA graph. Select the Construction
summary task in the Task List.
5. In the EVA Graph, enable both the PV and BL curves to see the comparison of project costs over time:
Scheduler|47
SYNCHRO Scheduling Training: Baselines
6. Select Windows → Usage panel → EVA Graph to hide the EVA window
7. To create a comparison report between the revised and the baseline schedule, in the Project Controls ribbon→
Compare Schedules panel, select Comparison Report.
8. Under Original Data, choose which schedule to compare to the current by selecting Baseline and choose
Original Schedule from the drop-down list of baselines.
9. Under Data to Compare, you have the option of choosing which data comparisons should be included in the
report. Deselect WBS and Progress Monitoring, for example, to exclude those from the comparison and select
OK.
Scheduler|48
SYNCHRO Scheduling Training: Baselines
Scheduler|49
SYNCHRO Scheduling Training: Baselines
Scheduler|50
SYNCHRO Scheduling Training: Baselines
2. The following dialog will appear. For this training, select No to continue without creating a Baseline of the
current schedule.
NOTE: The Restore Baselined Tasks command will restore any tasks that were deleted since the baseline was
created, delete any tasks created after the baseline was saved, and restore the start dates of all tasks as stored
in the baseline. Resource assignments are not stored with baselines – the current resource assignments will
remain for tasks that are in the current as well as baseline schedule.
The Restore only start times for Baselined Tasks command will update the current schedule with the start dates
of the baselined tasks stored in the selected Baseline but does not affect tasks that were deleted or created
since the baseline was saved.
3. To turn off display of the Baseline, in the Baselines and Scenarios window, click in the white space to un-highlight
the selected Baseline.
Scheduler|51
SYNCHRO Scheduling Training: Schedule Updating & Monitoring
NOTE:
When Do not show again is enabled, the selected date
defaults (Data Date, Planned Start/Finish, Predicted Finish,
or Estimated Finish) will be saved. The next time a Task
Status is changed, the status will be updated without raising
the dialog and the date default saved in Options>Gantt
Chart>Progress will be used for the Actual Start/Finish.
Scheduler|52
SYNCHRO Scheduling Training: Schedule Updating & Monitoring
The dark green rectangle with black outline indicates the actual date and the thin green line marks the planned
duration dates for comparison. If you don’t see the green rectangle, you can turn its visibililty in the Gantt Display
Options.
10. Select the task Masonry – E and change the Status to Started in Task Properties → General → Progress.
11. The Task Start Time window will appear. Select Choose Date, set the start to 28 Apr 2015 and press OK.
12. The completed portion of the Task bar changes colour to blue up to the Data Date. The dark green line indicates the
Planned duration of the Task..
NOTE: The % Complete can alternatively be displayed as a Duration Complete, Remaining % or Remaining Duration
by changing the settings under Options → Gantt Chart → Progress.
13. In Options → Gantt Chart → Rescheduling → Parameters, ensure that On scheduling progressed Tasks use is set to
Retained Logic.
Scheduler|53
SYNCHRO Scheduling Training: Schedule Updating & Monitoring
Scheduler|54
SYNCHRO Scheduling Training: Schedule Updating & Monitoring
1. Open the saved file SCH Training -Actual Costs.sp. File Location: C:\Users\Public\Documents\Shared SYNCHRO
Projects\Tutorial Files\SYNCHRO Scheduler Training\ .sp Files
2. Right click in the Task List header and choose Customise Columns
3. From Available Columns, select Budgeted Direct Cost. Use the single arrow button to move Budgeted Direct Cost to
the Selected Columns – use the Up button, to bring it below Name.
4. Use this same method to add Actual Direct Cost, Budgeted at Completion(BAC), and Actual Total Cost in the order as
displayed below:
Scheduler|55
SYNCHRO Scheduling Training: Schedule Updating & Monitoring
7. In Task Properties → General →Progress, change the task Status to Finished. When prompted, select Planned Start
and Planned Finish, then press OK.
8. In Task Properties tab → Cost Totals tab, you will see that the Actual Costs have been updated for the Resource cost
only.
9. To update the direct task cost: in the Task List, left click in the Actual Direct Cost cell for the Curtain Wall, S task and
type 8500. Commas and currency symbols will be added automatically. The Actual Total Cost cell will be updated
accordingly. Actual Direct Cost for all the other Finished tasks has already been input this way.
10. Select the Task Masonry, N under Envelope. This task is in progress. Actual Resource Cost so far can be calculated by
inputting the Actual Resource Utilization
11. In Task Properties→Resources, select Masonry Crew. Under Actual Utilization input 24h for Actual Units. The Actual
Cost and Remaining Units will be updated automatically.
Scheduler|56
SYNCHRO Scheduling Training: Schedule Updating & Monitoring
12. To input the Actual Direct Cost so far, in Task Properties →Monitoring and Actual Costs tab, right click in the
Reports window (as shown to the right) and select Add Actual Expense. An Expense Report will be added to the list
panel with the Data Date as the Report Date.
13. With the Expense Report selected and highlighted, right click in the Costs panel below and select Add.
14. Rename the New Cost to Masonry Materials and enter $3,500 for the Amount.
NOTE: Additional itemized costs can be added to a single Expense Report, and additional Expense Reports can be
added with differing Report Dates allowing the user to keep a detailed log of task expenses.
Scheduler|57
SYNCHRO Scheduling Training: Schedule Updating & Monitoring
s
• Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS) in red quantifies the budgeted value of the
planned work to date on the selected task or group of tasks. The total Planned Value of the task at the end of the
task is also referred to as the Budget at Completion (BAC). The intersection of the Focus Time line with the red PV
line reflects the Planned Value at that point in time for a selected task or group of tasks. This cost is shown in red on
the left of the EVA Graph. Moving the Focus Time gives a cost forecast reading at that specific moment in time for
the selected task or group of tasks.
• Earned Value (EV) or Budgeted Cost of Work Performed (BCWP) in grey quantifies the budgeted value of the work
performed to date on the selected task or group of tasks. The intersection of the Focus Time line and the grey EV
line reflects the Earned Value at that point in time for the selected task or group of tasks.
• Actual Cost (AC) or Actual Cost of Work Performed (ACWP) in blue quantifies the actual cost incurred for the work
performed to date on the selected task or group of tasks.
• Baselined Cost (BL) in green quantifies the Planned Value saved with the selected Baseline on the selected task or
group of tasks.
Scheduler|58
SYNCHRO Scheduling Training: Schedule Updating & Monitoring
5. Select the WBS Summary task - Construction so you can see the result in the EVA Graph of all Construction tasks.
• If the Planned Value is greater than the Earned Value as of the Data Date, the project is behind schedule; if PV is less
than EV, the project is ahead of schedule. This is known as Schedule Variance.
• If the Earned Value is greater than the Actual Cost as of the Data Date, the project is under budget; if EV is less than
AC, the project is over budget. This is known as Cost Variance.
Scheduler|59
SYNCHRO Scheduling Training: Schedule Updating & Monitoring
14.4. Monitoring
Should a task fall behind schedule, the progress can be updated and its impact on the project plan can be reviewed.
6. In Task Properties →Monitoring and Actual Costs tab, a Progress Report of Type Delay is created
7. The variance shown in the Progress Report is also reflected under the Analysis panel in Task Properties →
Monitoring and Actual Costs
8. The EVA Graph now displays the delay. If a task is on time the red PV line and the grey EV line would be at the
same point on the Data Date. In this case they are not. Since the EV is less than the PV, it is understood that the
task is behind schedule.
Scheduler|60
SYNCHRO Scheduling Training: Filters
Filters
In this section, you will learn about the many types of task filters in SYNCHRO and how to apply them.
It is possible to hide elements of the project plan using pre-set filters or by creating custom filters.
Scheduler|61
SYNCHRO Scheduling Training: Filters
• When a Filter Tasks By… option is selected, specific tabs are shown
beneath the General tab for that selection. You need to open these tabs
to set specific criteria for your filter.
• If you choose more than one Filter Tasks By … selection, all the tabs
related to the selections will be available.
• When multiple filter selections are chosen you must also select Any or
All under Exclude Tasks if they fail…
• The Any Filter selection filters tasks that meet all of the selected filters
(OR logic) and the All Filters selection filters tasks that meet one or more
of the selected filters (AND logic).
For training we will select one Filter Task by... selection at a time.
Scheduler|62
SYNCHRO Scheduling Training: Filters
NOTE: Task Name is selected by default under Filter By. You can also choose to filter by Task ID
You will only see the tasks which contain the word “Install” and their WBS summaries
4. In Filters →General tab deactivate Name / ID selection (all the tasks will appear in the Gantt Chart).
Scheduler|63
SYNCHRO Scheduling Training: Filters
9. You will see the selected tasks show up in the Tasks tab in the Filters window.
10. Check on Gantt Filter to enable it. The Site and Footings tasks (and their parent tasks) only will show in the Gantt
Chart
11. To Filter by WBS, in the Filters→Tasks tab enable Include SubTasks. Now the selected tasks and all their sub-tasks are
displayed. New subtasks added after the filter is created will also be displayed.
Scheduler|64
SYNCHRO Scheduling Training: Filters
Scheduler|65
SYNCHRO Scheduling Training: Filters
8. You will see only the tasks that are planned to start and finish between the Focus Time and the Building
Watertight milestone.
9. Check the box to Include Overlapping Tasks. This option will include in the filter tasks that overlap either the
From or To dates. In this case, the Masonry, E and Curtain Wall, S tasks finish within the Date Range, but start
before the From date.
TIP: Select Custom Date in the To and From dropdowns to specify fixed dates.
10. In Filters → General tab→ Filter Tasks By… deactivate Date Range selection
Scheduler|66
SYNCHRO Scheduling Training: Filters
1. With Gantt Filter selected, Filters → General tab→ Filter Tasks By…,activate Look Ahead (the Gantt Chart
selection will change.)
2. Open the Look Ahead tab below.
3. With Current Time (Data Date) selected change Look Ahead Duration to 28d.
5. Change the Look Ahead Duration to 1d (1 day) and enable Focused Time instead of Current Time (Data Date).
6. Move the red Focus Time bar to the start of the project by Clicking in the Timeline. In the Gantt Chart you will
only see the tasks that are active within 1 day of where the Focus Time is located. This is based on the Look
Ahead Duration specified.
7. Move the red Focused Time bar through the schedule to see how the filter updates.
8. In Filters → General tab→ Filter Tasks By… Deactivate Look Ahead.
Scheduler|67
SYNCHRO Scheduling Training: Filters
1. With Gantt Filter selected, Filters → General tab→ Filter Tasks By…, activate
Resources (the Gantt Chart will clear).
2. Open Resources tab below.
3. Ensure Include matches is selected.
4. Select the MEP Crew resource as shown to the right.
You will see just the tasks associated with the MEP Crew resource as shown
below.
Scheduler|68
SYNCHRO Scheduling Training: Filters
1. With the Gantt Filter selected, activate Filter Tasks by… Activity Codes in the
General tab.
2. Open the Codes tab
3. Select Include matches.
4. Enable Level L01 and Responsibly INT.
5. Select Match – All Codes to display tasks that are coded L01 AND INT.
Note: Choose Match - Any Code to display tasks that are coded L01 OR INT.
Scheduler|69
SYNCHRO Scheduling Training: Filters
1. With Gantt Filter selected, Filters → General tab→ Filter Tasks By…, activate Critically/ Schedule.
2. Select the Filters → Schedule tab. This filter contains many options for filtering tasks based on scheduling criteria.
For this example, we will leave Critical selected.
3. In the Options → Gantt Chart →Rescheduling → Critical Path.
4. Here you can define how to calculate the Critical Path. Ensure that Longest Path is selected for this training and
select OK to close the Options dialog
NOTE: You can alternatively select Least Total Float and enter values for the maximum float for a task to be classified
as critical and subcritical.
5. To ensure that the critical path calculation is up to date, select Plan tab→ Schedule panel →Compute Critical Path.
Rescheduling the project will also recalculate the critical path.
6. Only tasks on the critical path will be displayed in the Gantt Chart
Scheduler|70
SYNCHRO Scheduling Training: Filters
NOTE: The Critical Path display colours are controlled in the Configure tab Options → Gantt Chart → Colours →
Critical Path.
7. Deactivate the Gantt Filter so all activities are visible in the Gantt Chart.
Scheduler|71
SYNCHRO Scheduling Training: Printing
Printing
In this section, you will learn how to print the Gantt Chart and the EVA graph.
3. Select the required printer from the list (use PDF for training), edit the properties accordingly, and click OK.
4. Select File → Print.
5. Verify the printer selection and edit the preferences accordingly.
6. Select the Layout Tab.
Here you can choose what to print in the View to Print drop down. Note that there are some default selections –
including Gantt, Resource Usage, Resources, and Task Usage. If other windows are open on screen such as the
3D view or EVA graph, etc. – then these specific views will become available to print.
Scheduler|72
SYNCHRO Scheduling Training: Printing
Scheduler|73
SYNCHRO Scheduling Training: Printing
Scheduler|74
SYNCHRO Scheduling Training: Printing
1. To run a health check report on a project, in the Reports tab → Schedule panel → Schedule Health Check.
2. The Report can be printed or exported in a variety of formats, either directly to a printer or to the screen to preview
the results before they are printed. Choose the desired format from the Direct to... dropdown menu. Choices
include: Printer, Preview, PDF, and Excel (among others)
3. To generate a report select Start.
Scheduler|75
SYNCHRO Scheduling Training: Printing
Scheduler|76
SYNCHRO Scheduling Training: Appendix A: Using a Template
Scheduler|77
SYNCHRO Scheduling Training: Appendix A: Using a Template
6) Select Import (you will see a report of what is importing) then select Finish .
7) If the template is updated after it was imported, and you wish to bring those changes into your current
file: select the template SP in Navigator ribbon →Project Data panel → External Data, right click and
choose Synchronise From.
8) See Appendix D for more information about using Synchronise From. You can Skip any attributes not
contained in the template, or that you do not wish to update from the template.
Scheduler|78
SYNCHRO Scheduling Training: Appendix B: Task Constraints
Scheduler|79
SYNCHRO Scheduling Training: Appendix C: Importing Schedules/Plans
2. Select Browse to locate and select the Microsoft Project XML file, then select Open.
3. Select Next.
Scheduler|80
SYNCHRO Scheduling Training: Appendix C: Importing Schedules/Plans
6. Select Finish.
Scheduler|81
SYNCHRO Scheduling Training: Appendix C: Importing Schedules/Plans
1. Import directly from the P6 database via an API connection. The SYNCHRO user must have the API installed locally
and be able to access P6 either locally or via a remote connection. The user must have proper permissions to import
P6 data. If the schedule is updated in P6, simply use the External Data → Synchronise FROM command to bring
those changes into SYNCHRO. If the schedule is updated in Syncrho, simply use the External Data → Synchronise TO
command to send those change to P6.
2. Import a P6 XML file. The P6 XML file can exported from any P6 database by anyone with access to P6. SYNCHRO
and P6 do not have to be installed on the same computer. No API installation is necessary. If the schedule is
updated in P6, the P6 user should export a new XML, then the SYNCHRO user should use the External Data →
Synchronise FROM command to bring those changes into SYNCHRO. If the schedule is updated in SYNCHRO, use
Synchronise TO to update the XML before import to P6.
Scheduler|82
SYNCHRO Scheduling Training: Appendix C: Importing Schedules/Plans
5. Select Next.
6. Continue with Step 4 in section 19.1
Scheduler|83
SYNCHRO Scheduling Training: Appendix D: Synchronisation
Appendix D: Synchronisation
One of the benefits of SYNCHRO is the ability to quickly and easily bring in updates from an external scheduling program and
see those changes reflected in the 4D model. If changes or progress updates have been made to the original source schedule;
e.g. in P6 or Microsoft Project, the updates can be brought into SYNCHRO using the Synchronise From command in
Navigator → Project Data panel →External Data.
NOTE: All files imported or exported will be listed here. If you’ve imported multiple schedules, make sure you
select the correct one.
Scheduler|84
SYNCHRO Scheduling Training: Appendix D: Synchronisation
The Synchronisation options (Synchronise, Consolidate, Integrate, or Skip) are explained in the chart below.
SYNCHRONISE
If you choose to Synchronise, the existing schedule in SYNCHRO will be completely replaced with the updated external schedule.
Outcome: External schedule takes precedence over SYNCHRO schedule when Synchronising according to the following rules:
• Attributes ADDED externally → ADDED in SYNCHRO
• Attributes DELETED externally →DELETED in SYNCHRO
• Attributes MODIFIED externally → MODIFIED in SYNCHRO
• Attributes MODIFIED in SYNCHRO → OVERRIDDEN
• Attributes ADDED in SYNCHRO → DELETED
NOTE: The option to Synchronise is not available for P6 global objects (such as Calendars, Resources, Risks and Activity Codes)
since these cannot be deleted. Synchronise is the default choice for Primavera P3.
CONSOLIDATE
If you choose to Consolidate, any schedule changes made externally will be made in SYNCHRO, and attributes added in SYNCHRO
will be maintained, NOTHING IS DELETED.
Outcome: Merges the External and SYNCHRO Schedules when Synchronising. External schedule takes precedence over SYNCHRO
schedule for all Attributes originally created in the external schedule.
• Attributes ADDED externally → ADDED in SYNCHRO
• Attributes DELETED externally → MAINTAINED in SYNCHRO
• Attributes MODIFIED externally → MODIFIED in SYNCHRO
• Attributes MODIFIED in SYNCHRO → OVERRIDDEN
• Attributes ADDED in SYNCHRO → MAINTAINED
INTEGRATE
If you choose to Integrate, any modifications made in SYNCHRO to the selected external schedule will be overridden. However,
any additions to the schedule in SYNCHRO will be maintained.
Outcome: External schedule takes precedence over SYNCHRO schedule for all Attributes originally created in the external
schedule.
• Attributes ADDED externally → ADDED in SYNCHRO
• Attributes DELETED externally → DELETED in SYNCHRO
• Attributes MODIFIED externally → MODIFIED in SYNCHRO
• Attributes MODIFIED in SYNCHRO → OVERRIDDEN
• Attributes ADDED in SYNCHRO or imported from a different source → MAINTAINED
NOTE: Integrate only affects selected source schedule being Synchronised. Thus the option to Integrate is most commonly used
when multiple schedules have been imported into SYNCHRO, so that no project data is lost upon Synchronisation. Integrate is
the default choice for Resources and Resource Assignments. The option to Integrate is unavailable for Microsoft Project XML.
SKIP
If you choose to Skip, the associated attribute will not be modified or updated. The attributes in SYNCHRO will be maintained.
Scheduler|85
SYNCHRO Scheduling Training: Appendix D: Synchronisation
Use the following flowchart to determine whether to Skip, Synchronise, Consolidate, or Integrate each attribute. For each
attribute (eg. Links, Calendars, etc) substitute the attribute name wherever “[tasks]” appears in the flow chart.
Start
Yes
Yes Yes
Integrate
Were [tasks] deleted in the No
Consolidate
source program?
Yes
Yes
SUMMARY: Any attribute that you have added or modified in SYNCHRO since importing will need to be considered. For
example, if you have not created any tasks, calendars etc. in SYNCHRO but have just created Resources and Resource
Assignments, those are the only two options that you will be required to Consolidate or Integrate instead of Synchronise to
ensure that Synchronisation works correctly and that all assignments are retained
Scheduler|86
SYNCHRO Scheduling Training: Appendix D: Synchronisation
For example, if you have added new tasks and links, created resources from 3D objects, and assigned resources to tasks,
you should not use Synchronise for these options or else the changes made in SYNCHRO will be overridden with the
changes in the updated schedule
Select the Synchronise button.
The Synchronisation Report indicates what has been updated. You can save this report for future reference if
desired by selecting Select All followed by Copy to Clipboard.
Select Finish to exit the report.
Scheduler|87