SMA SI3324 4248 User Manual
SMA SI3324 4248 User Manual
User Manual
Table of Contents
1 Notes on this Manual. . . . . . . . . . . . . . . . . . .7
1.1 Validity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
1.2 Symbols Used . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
14 Contact. . . . . . . . . . . . . . . . . . . . . . . . . . . . .65
15 Glossary . . . . . . . . . . . . . . . . . . . . . . . . . . .67
For further operating information, please consult the Sunny Island 3324/4248 user
manual.
1.1 Validity
This installation manual for the Sunny Island 3324/4248 is valid for all firmware
versions up to and including 1.84/1.94.
You can call up the firmware version of your inverter by entering the "31-2 FWVers"
parameter in the Sunny Island 3324/4248 display (see section 10.4 "System and
Fault Messages" (page 53)).
This product may only be used in the intended area of application, i.e. it is only
approved for use in 50 Hz grids.
Do not use the Sunny Island 3324/4248 for purposes other than those indicated in
this installation manual. Use of the inverter for inappropriate purposes voids the
warranty.
For further questions, you can call the Sunny Island hotline at +49 561 95 22 399.
Here you will find further details on the operation and behavior of the inverter.
Energy sources can also be connected on the DC side, as long as the specified limits
are not exceeded (see section 12 "Technical Data" (page 61)).
The Sunny Island 3324/4248 is able to control a starter contact for a generator and
automatically connect or disconnect it to an AC-grid (see section 5 "Generator
Settings" (page 29)).
The Sunny Island 3324/4248 can also switch off particular loads if the batteries do
not have sufficient electrical energy available.
Page 10
Sunny
WebBox
Loads
Sunny
WebBox
OM
OM
OM
RT
ORY
M
USBC
ER
Betrieb Betrieb
NETC
Windy Operation Operation
SMAC
REPO
Erdschluss Erdschluss
MEM
Boy
SYSTE
Earth Earth
Fault Fault
POW
Störung Störung
Failure Failure
SWR
3000 Betrieb
Photovoltaik-Str Operation
Photovoltaic
ingwechselrich Erdschluss
string
inverter ter Earth
Fault
Störung
Failure
The Sunny Island 3324/4248
SI3324/4248-14:FE2406
Utility
*)
AC Output
AC input Com
Generator
G_Ready Load_S
Sunny
Island
Auto *)
G_Req Can
Start N
DC Input TBAT
= Charge- = DC/DC
= controller = converter
Description:
The following figure provides an overview of possible system configurations:
User Manual
SMA Technologie AG The Sunny Island 3324/4248
2.2 At a Glance
The following figure provides an overview of all control elements and connections of
the Sunny Island 3324/4248 (shown with cover removed).
MM MM
DC circuit
Display
LEDs showing
inverter
MM
150V
200V
S5
S7
MM
operation: red
S9
S11
S13
S15
ENS2
ENS1
Keys
Socket for
MM MM
Piggy-Back
(communication)
MM
DC-
Positive
Equipment DC-
Ground Negative
MM MM
Additional
connections (e.g.
MM
PE N L PE N L
G_REQ
LOAD_S
G_REQ
LOAD_S
G_RUN+
SHIELD
G_RUN-
SHIELD
S_OUT+
S_IN+
S_OUT-
S_IN-
TBAT1
FAN-
TBAT2
FAN+
TXD
S_GND
RXD
CTS
CAN_L
C_GND
CAN_H
Shield
MM
AC-OUTPUT AC-INPUT
MM MM
communication,
MM MM
control relays,...)
MM MM
The "Sunny Data" and "Sunny Data Control" software, which you can use to make
settings in and read/analyze data from your inverter, can be downloaded for free
from the SMA Technologie AG website at www.SMA.de (see section 14 "Contact"
(page 65)).
• Windy Boy inverters (for feeding in from wind turbines or hydropower systems):
WB 1100/WB 1700/WB 2500/WB 2800i/WB 3000/WB 3300/WB 3800/
WB 6000
• Hydro-Boy inverters (for feeding in from fuel cell systems)
The type plate is located on the left side of the housing (when the Sunny Island 3324/
4248 hangs vertically on the wall bracket).
You can call up the firmware version of your Sunny Island 3324/4248 under the "31-
2 FWVers" parameter (see section 10.4 "System and Fault Messages" (page 53)).
3 Safety Instructions
3.1 Important Notes Regarding Operation
Please follow all operating and safety instructions in this manual. Failure to follow
these instructions could result in damage to the inverter and cause personal injury.
Carefully read through the safety instructions before installing and commissioning
the inverter.
Ensure that the safety instructions and manual are stored in an easily accessible
location.
• electrical installation
• repair, maintenance, or
• modification
Only qualified personnel may alter the settings of the Sunny Island
3324/4248. The settings are protected by the installer password.
All of the instructions in the installation manual must be observed.
When touching the inverter, please note that some parts of the
Sunny Island 3324/4248 housing heat up during operation. These
temperatures may exceed 60°C. There is a danger of burn injury.
Only qualified personnel may mount and install the battery and
the Sunny Island 3324/4248. Handling batteries is dangerous, e.g.
batteries can produce very high currents if they are short-circuited.
All of the safety instructions and general instructions in the
installation manual must be observed.
Use only rechargeable lead acid batteries. The use of other types
of battery can lead to personal injury and material damage.
Take care to ensure that no metal parts fall onto the battery. This
could short-circuit the battery or other electrical components, which
could cause a fire or an explosion.
In these cases, you should set the Sunny Island 3324/4248 to Stop
mode (see section 9.3 "Switching Off" (S. 83)) and disconnect it
from the batteries via the DC circuit breaker.
4 Operation / Commisioning
Before the first commissioning of the Sunny Island 3324/4248, read this "Operation"
section and become familiar with the inverter.
Key Function
cancel, NO response, leave current menu, stop the inverter
ESC
(hold)
↑ navigate up one menu level, increase data value
↓ navigate down one menu level, decrease data value
select a function, select a value, confirm changes, YES
ENTER
response
The DC circuit breaker switches the Sunny Island 3324/4248 on and off. Note that
all voltage sources (batteries, (stand-alone) grid, generator) must be disconnected
from the Sunny Island 3324/4248 before the inverter is free of voltage (see section
4.2 "Activation and Deactivation" (page 20)).
4.1.2 Display
Information about the Sunny Island 3324/4248 is shown on the two-line LCD display.
Two lines are always shown when navigating up and down the menus.
During normal operation, the Sunny Island 3324/4248 shows the relative output
power, the operating mode of the inverter, the generator status (e.g. "L" see section
4.6 "Generator Request" (page 26)), fault messages and the status of the load
shedding and generator control relay.
Load shedding: the left "O" indicates the status of the load shedding relay of the
Sunny Island 3324/4248. "O" stands for "Off" or "Open". If the relay closes, the "O"
is filled.
Generator Start: the "O“ on the right-hand side indicates the status of the
generator control relay in the same manner. It is closed if the Sunny Island 3324/
4248 intends to start the generator.
• correct connections,
• voltages and
• polarities
Proceed as follows:
2. The Sunny Island 3324/4248 begins the SMA SMA SMA SMA
initialization phase (INIT), during which it
performs a number of self-tests to check that
there are no faults in the system.
If the inverter does not display the "To start press <ENTER>" message but
displays an error message instead, this error must be corrected before the
inverter can be put into operation. For this purpose, refer to section 11
"Troubleshooting/Problem Solving" (page 55). Once all corrective measures
have been taken, switch off the Sunny Island 3324/4248, then wait for 30
seconds before starting again from point 1.
You can now call up the various menus using the control elements (see section 4.1
"Control Elements" (page 17)) in order to view the measurement values and the
parameter settings.
4.2.2 Stopping
Proceed as follows to set the Sunny Island 3324/4248 to standby mode:
Even in standby mode, the Sunny Island 3324/4248 still requires about 4 W
of power from the battery.
4.2.3 Deactivation
To switch off the Sunny Island 3324/4248, proceed as follows:
1. Set the Sunny Island 3324/4248 to standby mode (see section 4.2.2 "Stopping"
(page 21)).
2. Switch the DC circuit breaker of the Sunny Island 3324/4248 to the "OFF"
position.
If anything is still shown on the display several seconds after switching the DC circuit
breaker, other voltage sources are active on the AC side.
• After waiting 5 minutes switch the DC circuit breaker on again. The Sunny Island
3324/4248 runs through the INIT phase.
• Once the INIT phase is finished, the message "To start press ENTER" is displayed.
Press the "ENTER" key.
Once the inverter is switched on again, it is important that the batteries are
charged. If an autostart generator exists in the system, the Sunny Island 3324/
4248 will start the generator after a few minutes.
• Monitor the generator start and check that the Sunny Island 3324/4248 switches
to "CHARGE" operating mode (battery charging mode).
• Check that all other energy generators in your system are also working correctly.
If the Sunny Island 3324/4248 immediately switches off with the fault
"VBatLow" (low battery voltage) after restarting, switch off all loads connected
to the AC output. The loads can be reconnected once the Sunny Island 3324/
4248 enters the "CHARGE" operating mode. (Provided that a generator
capable of providing the required power is connected to the system.)
1. Meters: The "10-Meters" main menu has the following submenus: Sunny Island
3324/4248 measurements ("11-Inverter Meters"), battery measurements ("12-
Battery Meters") and generator measurements ("13-Generator Meters").
Individual measurement values can be seen in the next two menu levels.
2. Settings: Under the main menu "20-Settings" are four different submenus
allowing various system parameters to be viewed and changed. This affects
password entry ("21-Password Settings") and all system parameters relating to
the Sunny Island 3324/4248 ("22-Inverter Settings"), the batteries ("23-Battery
Settings") and the generator ("24-Generator Settings").
3. Diagnose: Under the main menu "30-Diagnose" are two different submenus
allowing various diagnostic parameters to be viewed. These are system data
("31-System Information"), and fault messages ("32-Error Information").
You will find a tabular list of all parameters in section 10 "Parameter Lists" (page 47).
Home Screen
The display always shows the first two digits of a On-screen display of e.g.
parameter. The menu structure and the parameter
assignment of parameters are explained in "24-3 GenOperation“:
section 4.3 "Menu Structure Overview"
(page 23). GenOperation ‹24
An "Enter" arrow is displayed next to parameters Auto ↵
which you are able to alter .
If you press the <ENTER> key, the "Enter" arrow begins to blink and you can then
use the arrow keys (↑ or ↓) to change the current parameter value.
As soon as the desired value appears in the display, press the <ENTER> key to save
the new value, or press the <ESC> key to discard the changes and exit the menu.
If you wish to exit the current menu level (e.g. "24-3 GenOperation" parameter) then
press the <ESC> key. In this example, the cursor then jumps back to the "23-Battery
Settings" menu level.
In the Sunny Island 3324/4248 display, it is possible to read whether and why the
generator is working. Some of the generator menu parameters mentioned here can
only be viewed or altered after entering the installer password.
The following table describes the status of the generator voltage and generator
frequency, as they are shown in the display:
Display Description
The generator voltage and frequency lie within the defined limits
*
(see Generator Settings: parameters 24-4 to 24-8, installer level).
The generator voltage and/or frequency lie outside the defined
limits (see Generator Settings: parameters 24-4 to 24-8, installer
?
level). The Sunny Island 3324/4248 will not connect the
generator to the stand-alone grid while this situation exists.
The maximum permissible generator reverse power ("24-11
PGenReverse" parameter, installer level) has been exceeded. The
Sunny Island 3324/4248 has removed the generator from the
! stand-alone grid. The generator cannot be reconnected to the
stand-alone grid for a period of 20 minutes. This lockout can be
removed by setting the "24-3 GenOperation" parameter to
"Release".
The following table provides information as to the reasons why the generator is being
requested. One of the following six letters will appear in the display:
Display Description
The generator has been requested as a result of the battery
B(attery)
management system.
The generator has been started as a result of a temperature
H(eat)
dependent request.
The generator has been started as a result of a load dependent
L(oad)
request.
The generator was started for one of the following reasons:
The generator status and the reason for the request are shown (alternating) in the
"Generator status" in the display.
If (e.g.) the display changes every 2 seconds from "*" to "B" then this means
that the generator voltage and frequency lie within the specified limits and that
the generator was requested by the battery management system.
If the generator has been manually set to "Stop" then no generator status information
is shown in the display. The field remains empty.
The list of errors comprises ten errors, and remains intact even if the Sunny Island
3324/4248 is deactivated. If more errors occur, the oldest error in the list is
overwritten. The error which was added most recently is marked with an arrow.
5 Generator Settings
5.1 Generator Types
In stand-alone grid systems, (diesel) generators are often used. Choosing the right
generator is heavily dependent on the system's operating conditions. There are two
basic generator categories:
This type of generator is recommended for use in conjunction with a Sunny Island
3324/4248. Please contact your installer or system manufacturer for
recommendations regarding a specific generator.
You require the installer password in order to set parameters "24-4 to 24-16".
The following section describes the settings for the following particularly important
commissioning parameters in detail:
All adjustable parameters of the Generator Settings are listed in tabular form in
section 10.3 "Adjustable System Parameters" (page 51).
The parameter settings are intended for generators that cannot be automatically
started. Since in these cases the Sunny Island 3324/4248 GenRequest relay is not
used for directly starting the generator, it can here provide a signal transmitter for
the stand-alone grid user.
A signal light can be connected to the "GenRequest" contact that signals the
stand-alone grid user to start the generator when this is required. The signal
light is then switched off again via the "GenRequest" contact when the
generator is no longer needed. Note that, with these settings, although the
signal light has gone out the Sunny Island 3324/4248 will not automatically
disconnect from the generator. You must stop the generator manually.
2. "Direct" Setting
If the system uses a generator that can be automatically started using a contact (two-
wire autostart generator directly connected to the Sunny Island 3324/4248), set this
parameter to the "Direct" setting. The closing of the GenRequest relay (see the
installation manual for connection information) provides the start command to the
generator from the Sunny Island 3324/4248. When the generator is no longer
required, the start contact opens and the start command is revoked.
Possible reasons for a generator start command are:
Note that in this configuration the Sunny Island 3324/4248 will only connect
the generator when it requested the generator by closing the "GenRequest"
contact.
If you wish to start the generator manually, activate the generator using the
"24-3 GenOperation" parameter.
3. "GenMan" Setting
The "GenMan" setting must be used for all generators that require more than a single
contact for starting. In addition to setting the parameter, the generator must also be
integrated into the system using the (optional) GenMan device - SMA order number
'SI GenMan' . Information on installation and parameter settings can be found in the
GenMan handbook.
The reasons for a generator request from the Sunny Island 3324/4248 are the same
as those listed under "Direct" with these two exceptions:
• The Sunny Island 3324/4248 will only connect the generator when the "GenRun"
signal from the GenMan unit is received indicating that the generator is ready.
• With this setting it is not absolutely necessary that the inverter itself has set the
"GenRequest" relay before it connects the generator. In normal operation, the
inverter will usually set the "GenRequest" relay to request the generator and then
connect the generator once the "GenRun" signal has been received from the
GenMan. The decisive signal for connecting the generator is however the
"GenRun" signal. This allows the generator to be manually started at the
GenMan.
To make the best use of the run time and service life of the generator, the value here
should be set to about 85 % of the nominal generator current. Please refer to the
generator manufacturer's recommendations.
Five different settings are possible for the "24-3 GenOperation" parameter. Take
note of the messages in the display (see section 4.6 "Generator Request" (page 26)):
2. "Start" Setting
This setting causes an immediate generator request. The "Start" setting is indicated by
an "S" in the display (see section 4.6 "Generator Request" (page 26)).
Do not forget to stop the generator when you no longer need it.
To do this, set the "24-3 GenOperation" parameter to "Stop" or
"Auto".
3. "Stop" Setting
This setting immediately stops the generator, as long as the "24-1 GenControl"
parameter is set to "Direct" or "GenMan".
The Sunny Island 3324/4248 can not start the generator and will
not connect an externally started generator if you have switched
it off using the "Stop" setting.
Please also note that a generator stopped using the "Stop" setting
can also be started by other components in the stand-alone
system. For example, the GenMan independently starts the
generator as soon as the generator starter battery voltage sinks
below a particular value.
4. "Run1h" Setting
This parameter setting can be useful when the batteries should be relieved by the
generator for a foreseeable period of time. As soon as the "24-3 GenOperation"
parameter is set to "Run1h", the generator is requested for a period of one hour. The
"Run1h" setting is indicated by a "T" in the display (see section 4.6 "Generator
Request" (page 26)).
After one hour has passed, the Sunny Island 3324/4248 automatically sets the "24-
3 GenOperation" parameter back to "Auto".
Exception:
If "Run1h" was selected from the "Stop" mode, after one hour the Sunny Island
3324/4248 returns to this mode (see also 3. "Stop" Setting).
5. "Release" Setting
The "Release" setting releases the 20 minute lockout time triggered when the reverse
power limits are exceeded.
The "24-11 PGenReverse" parameter limits the power that may be fed back into the
generator for up to five seconds.
If the reverse power exceeds this value then the generator/grid is disconnected and
the Sunny Island 3324/4248 switches to stand-alone grid operation. The generator
or grid cannot now be reconnected for a period of 20 minutes. Setting the "24-3
GenOperation" parameter to "Release" removes this lockout. After "Release" has
6 Battery Management
The service life of batteries in off-grid applications can vary greatly. With proper
handling the batteries can last as long as 15 years. The main causes of premature
aging are incorrect charging and frequent deep discharge. For these reasons, the
Sunny Island 3324/4248 has an intelligent charge control and reliable deep
discharge protection. When these features are properly used, the battery service life
can be greatly extended in comparison with simpler devices.
All types of lead acid batteries are supported. The battery management system
draws a distinction between sealed lead acid batteries with liquid electrolyte (FLA,
Flooded Lead Acid) and the sealed lead acid batteries with semi-solid electrolyte
(VRLA, Valve Regulated Lead Acid). All Gel and Absorbed Glass Mat batteries
belong to the last group (AGM, Absorbent Glass MateSeparator).
The battery capacity is to be entered as the nominal capacity for a ten hour discharge
(C10). If this is not available from the battery manufacturer's data sheet, then
calculate this from the data for different discharge times (120 h, 100 h, 20 h, 5 h,
1 h) in the following manner:
C10 C120/1.28
C10 C100/1.25
C10 C20/1.09
C10 C10
C10 C5/0.88
C10 C1/0.61
The I stands for the bulk phase. At this level, the charging is only limited by the
defined maximum battery current ("23-4 AmpdcBatMax" parameter) or by the
maximum generator current ("24-2 AmpacGenMax" parameter). During this phase
the battery voltage increases as the batteries are charged.
Once the battery voltage has reached the value defined for the second phase V0,
then the constant voltage charging (absorption phase) begins. At this level, the
battery voltage is maintained at a constant level, resulting in a continually decreasing
battery current. The Sunny Island 3324/4248 remains in this phase for the period of
time defined for this phase (parameters "12-6 TabsorbLeft").
Once this phase is finished, the Sunny Island 3324/4248 enters the float charge that
again provides constant current charging but at a greatly reduced charging voltage.
If charging is done from a generator, then this is stopped on entry to this phase, thus
ending charging of the batteries at this point. The Sunny Island 3324/4248 remains
in this phase until either more than 30 % of the nominal capacity has been used (all
discharges are summed) or the generator is automatically restarted (see section 5.2
"Generator Parameters" (page 29)).
For the second charging level V0, the constant voltage charging (absorption phase)
for a limited period of time, the Sunny Island 3324/4248 automatically chooses
between three different voltages and charging times. These are the boost charge, full
charge and equalizing charge. The following figure shows a process diagram of the
charging process.
TcycleEquals days or 16
charging throughputs
Floating Charge
V = VchargeFloat
V > VchargeEqual V > VchargeFull
for TabsorbEqual for TabsorbFull
Silent Mode
Bms Silent Request = on
The Sunny Island 3324/4248 most often chooses the boost charge in order to bring
the batteries to a reasonable level in a short period of time. This process is optimized
to keep the generator run times as short as possible.
The Sunny Island 3324/4248 initiates a full charge every 14 days or after every
eight charging throughputs, with the aim of fully recharging the batteries to remove
any negative effects caused by insufficient charging. Various studies have shown that
regular full charging every two to four weeks can double the battery service life in
off-grid systems.
For this reason, the Sunny Island 3324/4248 automatically performs regular
equalization charging every 60 days or after every 30 charging throughputs. The
equalization charging uses controlled overcharging of the battery bank to ensure
that even the weak cells are fully charged. Equalization charging leads to a further
significant increase of battery service life by a factor of up to 50 %.
The charging capability of lead acid batteries is heavily dependent on the battery
temperature. For temperatures below 20°C the charging voltage must be slightly
increased, and for temperatures above 20°C it must be slightly reduced. This is
necessary to avoid overcharging and insufficient charging at all battery
temperatures. For this reason, the Sunny Island 3324/4248 is equipped with
automatic temperature compensation of the charging voltage. At temperatures
below 20°C, the charging voltage is raised by 4 mV/°C and cell (96 mV/°C for a
48 V battery) and reduced by the same amount at temperatures above 20°C. The
maximum permissible battery temperature is also monitored and the system switches
off with a fault if the limit is exceeded ("23-18 TBatMax" parameter).
100 %
Normal
Warning
(Start
Generator)
BatVoltage, BatCurrent < BatVoltage, BatCurrent >
SocLim2 for t > 2/6/30 SocLim2 SocLim2
minutes for t > 15 minutes
Low
(Load
Shedding)
0%
As long as the Sunny Island 3324/4248 has not detected a deep discharge then it
is in the battery state (BatState) Normal.
As soon as the first level of deep discharge is reached, the Sunny Island 3324/4248
switches to the Warning state. This can be used to start a generator.
If the batteries are further discharged despite the warning, then the battery state now
jumps to the next deep discharge level Low. If desired, this level can be used to
trigger the Sunny Island 3324/4248 relay contact to switch off all or some of the
loads.
If this is not done and the batteries are still further discharged then the battery state
reaches the last level Critical.
If no charging current flows into the batteries within five minutes of entering this state,
then the Sunny Island 3324/4248 automatically switches to standby mode to avoid
any further deep discharge.
If the battery voltage does not recover within 30 minutes, then the Sunny Island
3324/4248 switches completely off. A complete switch-off can be recognized by the
fact that the DC circuit breaker is switched on but the display remains dark and no
voltage is present at the AC output terminals.
Once fully switched off, the Sunny Island 3324/4248 can only be manually restarted
(see section 4.2.4 "Restarting the Automatic Shutdown" (page 22)).
If Sunny Boy inverters are connected to the AC output side of a stand-alone grid, the
Sunny Island 3324/4248 must be able to limit their output power. This situation can
occur when (e.g.) the Sunny Island 3324/4248 batteries are fully charged and the
(solar) power available from the PV generator exceeds the power required by the
connected loads.
To prevent the excess energy from overcharging the batteries, the Sunny Island
3324/4248 recognizes this situation and changes the frequency of the AC output.
This frequency adjustment is analyzed by the Sunny Boy. As soon as the grid
frequency increases beyond the value specified by "Fac-Start delta" the Sunny Boy
limits its output power accordingly.
When FSPC is activated and the generator is operating in the stand-alone grid, the
generator determines the frequency and the Sunny Boys react to changes in the
generator frequency. Generators normally operate at 50 Hz under load. For this
reason, in most cases the Sunny Boys will deliver their entire power to the stand-alone
grid, even when the generator is running.
The "Automatic FRequency Adjustment (AFRA)" function of the Sunny Island 3324/
4248 allows the use of grid-coupled clocks in these types of stand-alone systems.
By counting all positive zero-crossing points (full waves) at the inverter output of the
Sunny Island 3324/4248, in both battery charging operation and inverter
operation, the inverter constantly measures the actual frequency. These values are
compared with the desired frequency values every twelve hours. If a time difference
of five seconds or more exists then a frequency increase or -decrease is activated.
This frequency adjustment remains active if the time difference is more than one
second.
9.1 Housing
Check that the Sunny Island 3324/4248 housing is mechanically sound. If damage
(e.g. cracks, holes, missing covers) endangers the operating safety, the Sunny Island
3324/4248 must be deactivated immediately.
Larger particles of dirt should be removed from the inverter with a soft brush, or
similar object. Dust can be removed with a damp cloth. Solvents, abrasives or
corrosive materials must not be used for cleaning!
If the fans are covered with loose dust, you can clean them with the aid of a vacuum
cleaner (recommended) or a soft brush. Clean the fans only when at a standstill. If it
is necessary to replace the fans, please contact your installer.
9.3 Display
It is best to clean the control elements with a soft, damp cloth. Solvents, abrasives or
corrosive materials must not be used for cleaning!
9.4 Functioning
Check regularly whether error messages are present. If an error message is
displayed, for which you cannot identify any apparent cause, the stand-alone grid
must be inspected by a qualified electrician. To ensure optimal operation, the
operator should regularly check the entries in the Sunny Island 3324/4248 error list
at short intervals (monthly, or even weekly), especially during the first months after
commissioning. This can help to discover hidden faults in the installation or errors in
the configuration.
9.5 Battery
10 Parameter Lists
The following tables contain information regarding all menu items to which the Sunny
Island 3324/4248 user has access.
There are other measurement values and parameters additional to those shown here,
but which are to be set by qualified personnel. Only once the installer password has
been entered, can these measurement values and parameters be viewed and
altered. This is described in the Sunny Island 3324/4248 installation manual.
Take note of the previous value of each parameter before you change it!
1. Meters: The "10-Meters" main menu has the following submenus: Sunny Island
3324/4248 measurements ("11-Inverter Meters"), battery measurements ("12-
Battery Meters") and generator measurements ("13-Generator Meters").
Individual measurement values can be seen in the next two menu levels.
2. Settings: Under the main menu "20-Settings" are four different submenus
allowing various system parameters to be viewed and changed. This affects
password entry ("21-Password Settings") and all system parameters relating to
the Sunny Island 3324/4248 ("22-Inverter Settings"), the batteries ("23-Battery
Settings") and the generator ("24-Generator Settings").
3. Diagnose: Under the main menu "30-Diagnose" are two different submenus
allowing various diagnostic parameters to be viewed. These are system data
("31-System Information"), and fault messages ("32-Error Information").
You will find a tabular list of all parameters in section 10 "Parameter Lists" (page 47).
Home Screen
Battery Meters
No. Name Range/unit Default Description
12-1 BatVoltage 0 to 80 VDC N/A Battery voltage
12-2 BatCurrent -200 to +200 ADC N/A Battery current
12-3 BatTemp -40 to +200°C N/A Battery temperature
12-4 BatState Normal Warning N/A Battery state
Low
Critical
12-5 BatChargeMode Boost N/A Battery charging process
Full
Float
Equalize
12-6 TabsorbLeft 0 to max min N/A An absorption period is assigned to every
charging process. The Sunny Island 3324/
4248 must keep the generator running
during this time, even when this is only
partially loaded. The value of
"TabsorbLeft" shows the time remaining for
the absorption phase.
12-7 BatChargeVolt SI 4248 Desired value of the battery charging
44 to 62.4 VDC voltage
SI 3324
27 to 31.2 VDC
Generator Meters
No. Name Range/ Default Description
unit
13-1 VacGenerator 0 to 260 VAC N/A Inverter input voltage
(AC input)
13-2 AmpacGenerat -60 to +60 AAC N/A Inverter input current
(AC input)
13-3 FacGenerator 0 to 70 Hz N/A Inverter input frequency
(AC input)
13-4 PacGenerator -20 to +20 kWAC N/A Inverter input power
(AC input)
All parameters marked with a (B) can be set while the system is running.
All parameters can be set using a connected PC/laptop with the Sunny Data
Control software, a Sunny WebBox or a Sunny Boy Control.
Inverter Settings
No. Name Range/ Default Description
unit
22-1 VacNominal 200 to 253 VAC 230 Setting of the inverter nominal output
(B) voltage
Battery Settings
No. Name Range/ Default Description
unit
23-1 VdcBatNominal SI4248 48 Nominal battery voltage
(see section 11.4) 42 to 48 VDC
SI3324 24
20 to 24 VDC
23-2 BatType VRLA VRLA The type of battery used in the system.
(see section 11.4) FLA VRLA = Gel/Absorbed Glass Mat
battery
FLA = battery with liquid electrolyte
These parameters must be set when first
commissioning the system. After this, the
value can only be changed after you
have set the "23-5 New Battery"
parameter to the value "Reset". The Sunny
Island 3324/4248 will then again run
through the INIT phase.
23-3 AmpHoursBat 100 to 6000 Ah 100 Battery capacity. These parameters must
(see section 11.4) be set when first commissioning the
system. After this, the value can only be
changed after you have set the "23-5
New Battery" parameter to the value
"Reset". The Sunny Island 3324/4248 will
then again run through the INIT phase.
23-4 AmpdcBatMax SI4248 10 Maximum battery charging current
(B) 0 to 100 ADC
SI3324 10
0 to 140 ADC
Generator Settings
Range/
No. Name Default Description
unit
24-1 GenControl Manual Manual The generator start option to be used in
(B) Direct your system (see section 5.2.1 "Selection
GenMan of Generator Control Method"
(page 30)).
Manual: Manual start or no generator
connected
Direct: Generator start using the Sunny
Island 3324/4248 "GenRequest" control
relay
GenMan: Generator start using the
(optional) GenMan
24-2 AmpacGenMax 2 to 56 AAC 10 Max. generator current that the Sunny
(B) Island 3324/4248 will demand from the
generator (see section 5.2.2 "Setting the
Output Current Limit" (page 32)).
Note: If the system load exceeds this
value, the Sunny Island 3324/4248 will
not switch to the generator, to avoid
overloading it. Ensure that a sensible
value is entered here!
24-3 GenOperation Auto Auto Auto: Automatic start of the generator is
(B) Start activated.
Stop Start: The generator is immediately
Run1h started (the display shows "S").
Release Remember to stop the generator again
when you no longer require it (by
selecting either "Stop" or "Auto").
Stop: The generator is immediately
stopped. Remember to set the generator
back to "Auto" if you want the Sunny
Island 3324/4248 to once more assume
control.
Run1h: The generator is immediately
started and will run for one hour (the
display shows "T"). After this, the Sunny
Island 3324/4248 returns to the
previously active mode.
Release: Interrupts the lockout time (20
min) for the generator after a
"ReversePower" fault has occurred.
Fault messages
No. Name Range/ Default Description
unit
32-1 Last N/A N/A The last fault that occurred in the system
32-2 Hist N/A N/A The last ten faults that occurred in the
system
All parameters marked with a (B) can be set while the system is running.
All parameters can be set using a connected PC/laptop with the Sunny Data
Control software, a Sunny WebBox or a Sunny Boy Control.
11 Troubleshooting/Problem Solving
11.1 List of Fault Displays
The meaning of fault messages displayed by the Sunny Island 3324/4248 are
explained in the following table:
Energy consumption is higher than that Switch off the energy consumers/loads.
provided by the power generator (e.g.
PV generator).
CHS-Open Device fault Please contact your instller or the SMA
hotline (see section 14 "Contact"
(page 65)).
CHS-Short Device fault Please contact your instller or the SMA
hotline (see section 14 "Contact"
(page 65)).
CTR-Open Device fault Please contact your instller or the SMA
hotline (see section 14 "Contact"
(page 65)).
CTR-Short Device fault Please contact your instller or the SMA
hotline (see section 14 "Contact"
(page 65)).
FailSet Device fault Please contact your instller or the SMA
hotline (see section 14 "Contact"
(page 65)).
HotACout The Sunny Island Please contact your installer.
3324/4248 will
not start because
voltage already
exists on the AC
output terminals.
1. The Sunny Island 3324/4248 does not switch to the running generator, even
though the generator control relay has closed (Gen_Request) (the "24-1
GenControl" parameter is set to "Direct", see page 30).
2. The Sunny Island 3324/4248 does not switch to the running generator, the
generator control relay (Gen_Request) is open .
- The generator was manually started, even though the "24-1 GenControl"
parameter is set to "Direct" (see page 30) or "GenMan" (see page 31).
- Set the "24-3 GenOperation" parameter to "Run1h" (see page 33). The
Sunny Island 3324/4248 switches to the generator for a period of one
hour. After one hour, the generator is automatically switched off by the
Sunny Island 3324/4248 and the "24-3 GenOperation" parameter is set
to the previous state.
- You can also set the "24-3 GenOperation" parameter to "Start" (see
page 32). The Sunny Island 3324/4248 will immediately switch to the
generator. You must note that the Sunny Island 3324/4248 will no longer
switch off the generator. Only when you manually reset the "24-3
GenOperation" parameter back to "Auto" can the Sunny Island 3324/
4248 again assume control of the generator.
- The generator reverse power has been exceeded. A "!" is shown in the
display. Set the "24-3 GenOperation" parameter to "Release" (see page 33),
the Sunny Island 3324/4248 will switch to the generator.
3. The DC circuit breaker on the Sunny Island 3324/4248 is set to "On" but the
display remains dark.
- The inverter has switched off to protect the batteries from deep discharge (see
also section 6.3 "Deep Discharge Protection / Battery State" (page 39)). To
restart the Sunny Island 3324/4248, see section 4.2.4 "Restarting the
Automatic Shutdown" (page 22).
4. The Sunny Island 3324/4248 only briefly switches to the generator and
constantly changes from battery charging mode (Charge mode) to inverter
mode (Invert mode).
- The "24-2 AmpacGenMax" parameter (see section 5.2.2 "Setting the Output
Current Limit" (page 32)) is too high. Set the "24-2 AmpacGenMax"
parameter to a value that is 85 % of the nominal generator current.
- The limits for the maximum permissible AC voltage or the minimum permissible
frequency of the generator are too strict. Increase the limits for voltage and/
or frequency according to the technical data of your generator.
- The Sunny Boy inverter is controlled via the frequency (see section 7
"Frequency Shift Power Control (FSPC)" (page 41)).
- The "AFRA" function of the Sunny Island 3324/4248 is activated (see the
Sunny Island 3324/4248 user manual, section "Automatic Frequency
Adjustment").
6. The "VAC-Low" fault (output voltage too low) occurs when the Sunny Island
3324/4248 is started.
12 Technical Data
SI 3324 SI 4248
Output data:
Nominal AC voltage (VAC, nom) (adjustable) 230 V (202 to 253 V) 230 V (202 to 253 V)
Max. current (peak value) for 100 ms 100 A (100 ms) 100 A (100 ms)
Harmonic distortion of output voltage < 3 % <3%
(KVAC)
Battery data
Battery voltage (VBat, nom) (adjustable) 24 VDC (21 to 32 VDC) 48 VDC (41 to 63 VDC)
Max. battery charging current (IBat, max) 140 ADC 100 ADC
SI 3324 SI 4248
Certification
CE CE
Protection degree
Per DIN EN 60529: IP 30 IP 30
USA NEMA1 (indoor) NEMA1 (indoor)
inverter protection
Short-circuit, overload, Short-circuit, overload,
overtemperature overtemperature
Interfaces
2 LEDs 2 LEDs
4 buttons 4 buttons
two-line display two-line display
1 relay for load shedding 1 relay for load shedding
1 relay for controlling a 1 relay for controlling a
diesel generator diesel generator
RS485/RS232 galvanically RS485/RS232 galvanically
isolated (optional) isolated (optional)
Mechanical data
Width x height x depth (390 x 590 x 245) mm (390 x 590 x 245) mm
Weight 39 kg (approx.) 39 kg (approx.)
Ambient conditions
Ambient temperature from -25°C to +50°C from -25°C to +50°C
Miscellaneous
Guarantee (EU) 2 years 2 years
Accessories
Ext. battery temperature sensor included included
Generator management (GenMan) optional optional
13 CE Declaration of Conformity
CE Declaration of Conformity
for off-grid inverters
We declare that the above specified device is compliant with the regulations of the European
Community, in terms of the design and the version fabricated by SMA. This especially applies
for the EMC Regulation defined in 89/336/EWG and the low voltage regulation defined in
73/23/EWG.
Note:
This declaration of conformity becomes invalid in case
· the product is modified, complemented or changed,
· and/or components, other than those belonging to the SMA accessories, are installed in the product,
· as well as in case of incorrect connection or inproper usage
without explicit written confirmation by SMA.
Niestetal, 13.03.2006
SMA Technologie AG
SMA Technologie AG
Hannoversche Straße 1-5
34266 Niestetal
Tel. +49 561 9522 – 0
Fax +49 561 9522 – 100
www.SMA.de
[email protected]
14 Contact
If you have any questions or queries, please contact us. A team of qualified engineers
and technicians is at your disposal.
Help us to help you by having the following information ready when you call us:
• Type of inverter
• Serial number of the Sunny Island 3324/4248
• Firmware version
• Fault message shown in the display
• Battery size and battery type
• Type and size of additional energy sources (generators, PV systems, PV inverters)
• Communications products used
Address:
SMA Technologie AG
Hannoversche Straße 1 - 5
34266 Niestetal
Germany
21 Glossary
Absorption phase
Constant Voltage phase: A charging phase using constant charging voltage. The
charging current constantly decreases in this phase.
AC
Abbreviation for "Alternating Current"
AC coupling
The AC side connection between loads, generators and storage devices.
AGM battery
Absorbent Glass Mat separator battery. This is a battery where the electrolyte (a
mixture of water and sulfuric acid) is bound to a glass fiber mat. This is a type of a
sealed lead acid battery. A gas mixture (hydrogen and oxygen) is always generated
when lead-acid batteries are charged and in normal operation this internally
recombines to form water. This removes the need for regularly refilling the battery
cells with water, which is why these batteries are often described as "low
maintenance" or even "maintenance free". AGM batteries are available from many
different manufacturers for a wide range of applications. They usually have very
good high current properties but are not very charge-cycle resistant.
Ah
Abbreviation for "Ampere hours". Unit of electrical charge, one ampere hour is the
charge provided by a constant current of 1 A over a period of one hour.
Backup system
Backup systems are power supply systems that provide an extra level of security for
standard power supply systems. The public grid is usually the standard power supply
system and the backup system is provided by an additional stand-alone grid in the
case of a power outage. In addition to the backup systems, diesel generators in PV
battery systems are also described as backup generators. Here they perform the
same task as a backup system for the public grid.
Battery
A battery is an electrochemical storage device that can release previously stored
chemical energy as electrical energy. A distinction is made between non-
rechargeable primary elements (often used in consumer markets) and rechargeable
secondary elements (accumulators). In stand-alone grid systems, lead acid batteries
are almost always used and, very rarely, Nickel/Cadmium batteries are used as
secondary rechargeable elements.
Battery bank
See Battery system
Battery inverter
See Battery power converter
Battery management
The battery management is responsible for the optimum charging of the battery bank
and for protection against deep discharge. This is the only way of ensuring that the
battery service life reflects the manufacturer's specifications.
Battery system
Serial and possibly also parallel connection of several identical batteries. Battery
banks of 12 V, 24 V, 48 V and 60 V are typical.
Boost charge
Rapid charging: Allows the batteries to be charged to a level of approx. 85 – 90 %
in the shortest time and the most efficient manner.
Bulk phase
I-Phase: The charging phase in which charging can be done using the maximum
allowable charging current.
Capacity
Describes the storage capability of a cell or battery, specified in Ah (ampere hours).
The capacity of a battery is heavily dependent on the charging cycle, the amount of
current drawn and the temperature.
Central inverter
An inverter concept, in which all PV modules are connected to each other (in series
and/or parallel) and which uses a single inverter for feeding energy into the mains
supply grid. The low cost of the inverter is usually offset by the much higher
installation efforts required and possible yield losses due to variations in shadowing
of different solar modules.
Charge level
Describes the current amount of charge that can be drawn from the battery, in
percent of the nominal capacity (100 % = battery full, 0 % = battery empty).
Charge mode
See Battery charging mode
C-rate
The nominal capacity specification is always provided with the discharge time on
which the capacity is based. The nominal capacity is the product of the constant
charging current IN and the discharge time tN, that passes between commencement
of discharging the fully charged battery until the final discharge voltage VS is
reached. In permanently on-site batteries, the C10 capacity is usually specified. i.e.
a battery with C10 = 200 Ah can be discharged for 10 hours at a nominal current of
0.1 × C10 = I10 = 20 A.
DC
Abbreviation for "Direct Current"
Derating
A controlled reduction in performance, usually dependent on component
temperatures. Derating is used instead of performing a complete shutdown of the
system.
DSP
Abbreviation for Digital Signal Processor. A DSP is a microprocessor chip especially
developed for digital signal processing and control.
Electrolyte
Allows the conduction of ions within a battery. In lead acid batteries, the electrolyte
is diluted sulfuric acid and is also a reactant in the electrochemical reaction. Nickel/
Cadmium batteries use an alkaline electrolyte (potassium hydroxide).
EPROM
See Flash EEPROM
Equalize charge
Equalize charge: Allows multiple series-connected battery cells to be charged to a
unified charge level of 95 – 100 %. Without regular equalization charging, the
charge states of the various cells slowly drift apart, which can lead to premature
battery bank failure.
Firmware
Firmware is software that is stored in a chip in various electronic devices, such as
Sunny Island, hard disk recorders, DVD burners and players, newer television sets,
household appliances and computers - in contrast to software that is stored on a hard
drive, CD-ROM or other media. These days, firmware is usually stored in Flash
memory or an EEPROM.
FLA
Flooded Lead Acid battery: A lead acid battery with liquid electrolyte, also often
described as a sealed lead acid battery.
Flash EEPROM
The abbreviation EEPROM stands for Electrically Erasable Programmable Read-Only
Memory. Flash memory is a digital storage chip, the exact designation is Flash
EEPROM. In contrast to "normal" EEPROM storage, individual bytes (the smallest
addressable storage units) cannot be deleted.
EEPROM is a non-volatile, electronic storage component that is used in the Sunny
Island, the computer industry (among others) and usually in Embedded Systems.
Flash EEPROMs are used where information must be permanently stored in the
smallest amount of space, e.g. for storing the firmware.
Float charge
Maintenance charge: Allows the batteries to be slowly charged to a charge level of
100 % without the negative effects of overcharging. Complete charging to 100 %
using float charge takes several days. For this reason, float charging is more
important for grid backup systems and less important for stand-alone grids.
Full charge
Recharging of the batteries to a level of approx. 95 % on a regular basis (at least
once a month). This efficiently avoids premature aging of the batteries caused by
inadequate charging.
Gel battery
A type of battery in which the electrolyte (a mixture of water and sulfuric acid) is
bound into a gel. This is a type of sealed lead acid battery. A gas mixture (hydrogen
and oxygen) is always generated when lead acid batteries are charged, and in
normal operation this internally recombines to form water. This removes the need for
regularly refilling the battery cells with water, which is why these batteries are often
described as "low maintenance" or even "maintenance free" (see also AGM
batteries). Gel batteries are available from many different manufacturers for a wide
range of applications. There are Gel batteries for high-current applications but also
for cycle operation with very high cycle resistance.
Grid-coupled system
PV system that is connected to the power supply grid of an external energy supplier.
Independent disconnection device
The "Independent disconnection device between a grid parallel power generating
system and the public low voltage grid" (DIN VDE 0126-1-1) is an equivalent
replacement for a normal public disconnection device with isolation function that is
accessible to the distribution grid operator at any time. This is a mandatory safety
device that prevents power from a solar power system being fed into an external
power grid when the external power generator is not functioning. In the Sunny Boy/
Sunny Mini Central, this function is assumed by the "SMA grid guard Version 2".
Inverters
A device for converting the direct current (DC) from the PV generator into alternating
current (AC), which is used by most normal household devices and especially for
feeding energy into an existing supply grid. Inverters for PV systems usually include
one or more MPP trackers, store operating data and monitor the grid connections of
the PV system (see also MSD).
Inverter mode
See Inverter operation
Inverter operation
Operating mode of a battery inverter where it supplies the stand-alone grid from the
battery energy. In this operating mode, the battery inverter is especially responsible
for the control of frequency and voltage in the stand-alone grid.
Maximum Power Point "MPP"
The working point (current/voltage characteristic curve) of a PV generator where the
maximum power can be drawn. The actual MMP changes constantly depending
(e.g.) on the level of solar irradiation and the ambient temperature.
MPP tracker
Regulation of the power drawn so that a PV generator remains as close as possible
to the MPP. This working point varies with the solar irradiation and the temperature
conditions of the modules. MPP tracking optimizes the extraction of electrical power
and is a feature of inverters and charge controllers.
MSD
See Independent disconnection device
Multi-string inverter
An inverter that combines the advantages of several string inverters (separate MPP
tracking of individual strings) and a central inverter (lower performance specific
costs).
NiCd
Nickel/Cadmium battery, contains Nickel, Cadmium, and potassium hydroxide as
the electrolyte. They require a significantly higher charging voltage, have a lower
level of efficiency and are significantly more expensive than lead acid batteries. Their
robustness, cycle resistance and low-temperature capabilities allow them to be used
in certain special applications.
Overload capability
The overload capability of an inverter describes the ability of the inverter to supply
short-term (seconds or minutes) excessive loads, that can be significantly higher than
the nominal capacity in battery inverters. The overload capability is important to
allow electrical machines with a nominal power output close to the nominal power
output of the stand-alone grid inverter to be started, since these machines typically
require six times the nominal current when starting.
Parallel connection
Parallel connection of the batteries (all positive poles together and all negative poles
together) increases the capacity of the battery bank while keeping the voltage
constant. Example: Two 24 V/100 Ah batteries connected in parallel still have a
voltage of 24 V, but have a capacity of 100 Ah + 100 Ah = 200 Ah.
Piggy-Back (Board)
A printed circuit board that is plugged into another board to increase performance
or expand capabilities. A piggy-back board can also replace a single chip. In this
case, the chip is removed and the board is plugged into the empty socket.
PLC
Abbreviation for Power Line Communication: Describes the process of data transfer
over the grid supply cables. The PLC power module is used to amplify the signal and
is connected in Multi-String and Sunny Mini Central inverters. Powerline
communication is not suitable for Sunny Island inverters.
PV
Photovoltaics (PV) is the conversion of solar irradiation into electrical energy using
special semiconductors called solar cells.
PV array
See PV generator.
PV generator
Technical device for the conversion of light energy into electrical energy. All the
series and parallel mounted and electrically connected solar modules in a PV system
are known as the PV generator.
PV module
See Solar module.
PV array
See PV generator.
PV system
Describes a solar power system for generating electrical power. Describes the
complete collection of components needed for the acquisition and utilization of solar
energy. As well as the PV generator, this includes the Sunny Boy or Sunny Mini
Central, for example, in the case of grid-coupled systems.
Self discharge
Loss of battery charge while it is stored or not used. A higher ambient temperature
has a strong influence on self discharge.
Series connection
In this case the positive pole of each battery is connected to the negative pole of the
next battery. There is only one circuit where current can flow. Series connection
increases the voltage of the entire battery bank. If four 12 V batteries with a capacity
of 100 Ah each are connected in series, the total voltage is 4 × 12 V = 48 V, while
the total capacity remains at 100 Ah.
SOC
State of Charge: The charge level of the batteries, see Charge level. If (e.g) 25 Ah
is taken from a 100-Ah battery, the charge level (SOC) is then 75 %.
Solar energy
"Sun energy", this means energy from sunlight or other solar irradiation (heat and/
or UV radiation).
Solar module
Electrical connection of several solar cells encapsulated in a housing to protect the
sensitive cells from mechanical stress and environmental effects.
Solar cell
An electronic component that generates electrical energy when irradiated with
sunlight. Since the voltage produced by a solar cell is very small (approx. 0.5 V),
several solar cells are combined to form a solar module. The most common
semiconductor material presently used for solar cells is silicon, which is manufactured
in different forms (monocrystalline, polycrystalline, amorphous). In addition to
different mechanical variations, that are usually designed to increase the level of
efficiency, completely new materials are currently being tested (Cadmium Telluride,
Cadmium Indium Sulphide, Titanium Dioxide and many others.)
String
Describes a group of solar modules connected in series. A PV system usually consists
of a number of strings, which avoids yield losses due to variations in shading over
different modules.
String inverter
An inverter concept that avoids the disadvantages of the central inverter concept. The
PV is split into individual strings, each of which is connected to the external mains
supply with its own string inverter. This greatly simplifies installation and greatly
reduces the yield losses caused by manufacturing deviations or variations in
shadowing of the solar modules.
VRLA
Valve Regulated Lead Acid battery: Lead-acid battery with semi-solid electrolyte or
sealed lead acid battery. Examples of this type of battery are Gel batteries and AGM
batteries (Absorbent Glass Mat).
Exclusion of liability
The general terms and conditions of delivery of SMA Technologie AG shall apply.
The content of these documents is continually checked and amended, where necessary. However,
discrepancies cannot be excluded. No guarantee is made for the completeness of these documents. The latest
version is available on the Internet at www.SMA.de or from the usual sales channels.
Guarantee or liability claims for damages of any kind are exlcuded if they are caused by one or more of the
following:
• Improper or inappropriate use of the product
• Operating the product in an unintended environment
• Operating the product whilst ignoring relevant, statutory safety regulations in the deployment location
• Ignoring safety warnings and instructions contained in all documents relevant to the product
• Operating the product under incorrect safety or protection conditions
• Altering the product or supplied software without authority
• The product malfunctions due to operating attached or neighboring devices beyond statutory limit values
• In case of unforeseen calamity or force majeure
Software licensing
The use of supplied software produced by SMA Technologie AG is subject to the following conditions:
This software may be copied for internal company purposes and may be installed on any number of
computers. Supplied source codes may be changed or adapted for internal company purposes on your own
responsibility. Drivers may also be transferred to other operating systems. Source codes may only be published
with the written permission of SMA Technologie AG. Sub-licensing of software is not permissible.
Limitation of liability: SMA Technologie AG rejects any liability for direct or indirect damages arising from the
use of software developed by SMA Technologie AG. This also applies to the provision or non-provision of
support activities.
Supplied software not developed by SMA Technologie AG is subject to the respective licensing and liability
agreements of the manufacturer.
Trademarks
All trademarks are recognized even if these are not marked separately. Missing designations do not mean that
a product or brand is not a registered trademark.
SMA Technologie AG
Hannoversche Straße 1-5
34266 Niestetal
Germany
Tel. +49 561 9522-0
Fax +49 561 9522-100
www.SMA.de
E-mail: [email protected]
© 2005 SMA Technologie AG. All rights reserved.
SMA Technologie AG
Sales
Solar Technology
SMA Technologie AG
www.SMA.de
Hannoversche Strasse 1–5
34266 Niestetal, Germany
Tel. : +49 561 9522 4000
Fax: +49 561 9522 4040
E-Mail: [email protected]
Freecall: +800 SUNNYBOY
Freecall: +800 7 8 6 6 9 2 6 9
Seite 80 SI3324/4248-14:FE2406
Innovation in Systems Technology User Manual
for the Success of Photovoltaics