Draft HQ Report
Draft HQ Report
2 Prioritizatio Verify the undertaking of There are records on stakeholder Conduct and Supplement Noted KURA HQ
n of works RICS and its place in engagement ARICS with road maps
selection There are no records of ARICS that depict road condition
and prioritization of conducted for the road and their extents
works. Stakeholder
participation.
Confirm proper scoping Scoping of works conducted HQ to provide geotagged Noted and is KURA HQ
of works and appropriate Key intervention measures captured photos showing road under
intervention measures were: conditions before implementati
- Cut to spoil/fill for vertical interventions on with RMS
alignment Provide map showing road
- Filling with gravel or approved maintenance action
materials for sub-grade and sub- required depending on
base layers; and shoulders existing condition
- Hand packing for base layers
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
- Installation of kerbs for edge
restraint on the carriageway
- Installation of kerbs for edge
restraint on the carriageway
- Ac 50mm surfacing for
carriageway
- 60mm Concrete Paving blocks
walkway 1.0m width
- Excavation of drains
- Lining of drains using
masonry/reinforced concrete
- Installation of culverts and Invert
Block Drains (IBDs) where
applicable
- Road marking.
There is no documentation of road
conditions before intervention
3 Planning of Development of the An annual workplan prepared and Seeking approval of work None Not
Works annual work plan submitted to KRB plans commendable Applicable
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
Verify the availability PPRA’s Standard Documents for Use of standard None Not
and use of Small Works applied documents commendable Applicable
guidelines/manuals for Manuals for cost estimating (2019) Apply updated cost
planning available at KURA HQ Offices. estimation manual once
Cost estimating manuals require released
updating In the meantime, apply
consumer indices to
reflect price changes
4 APRP Confirm eligibility of the There is no project under HQ region - None Not
project for funding using that was listed in the APRP. Only the Applicable
the Road Maintenance amount allocated to the region was
Levy Fund stated
Appropriateness of Open drains suitable for the area Commendable None Not
designs with regard to Laying of kerbs with drainage slots Applicable
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
economy and efficiency appropriate
Side slabs for drains appropriate
The designs were suitable
economically and were efficient
6 Tendering Advertisement of A complete contract document was Commendable. None Not
and tenders, Check for an signed. Applicable
Procurement efficient tendering Performance bond was provide
process and the Contract documents has main
completeness of contract sections for small works- conditions
documents, Publicity of contract, specifications, special
boards. specifications, and bill of quantities
Tender was for women category,
which is appropriate to enhance
competition.
1 No Publicity boards provided in the
contract and Engineers instructions
Adequacy of the BoQ Bill descriptions are adequate as Commendable None Not
descriptions compared to standard Applicable
specifications
Comparison of unit rates Unit rates applied in this Contract Commendable. None Not
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
adopted in the BoQ with were within the prevailing market Applicable
the market rates rates as displayed in the BOQ
attached in the Annexures section of
this report.
7 Project Verify works supervision Engineers staff included RE, ARE, Supervision of the project None Not
Managemen and availability of Roads Inspector and Supervisor. was well facilitated. Applicable
t/ adequate supervision Project provided a station wagon
Constructio resources (staff, vehicles, vehicle 4WD provided with adriver
n Stage funding etc) and maintained with fuel under bill
01.07
Bill item 01.03 allows for allowances
for RE’s miscellaneous accoumt @
150,000.00
Bill item 01.05 allows for allowances
for RE’s staff @ 1,000,000.00
Bill Item 01.01 allows for material
testing @ Kshs. 200,000.
Handling of advances, No variation orders encountered Commendable None Not
guarantees, insurances, Approval for expending supervision Applicable
site instructions, claims, PC sums sought by RE and granted
variation orders and cost by PE
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
No claims issued on project
Advance payments not applicable
Comment on the There are no payments done yet for - None Not
payment timelines to this project Applicable
contractors/suppliers
Comment on the delivery Works are ongoing Commendable. None Not
of works within the Applicable
planned time and cost
Confirm certification of Completed works certified by RE, Due to low quality precast Noted KURA HQ
the works done; work ARE and Site Agent units (kerbs, IBDs,
approval forms, Following tests were conducted at channels) in the market,
approved material tests, onset of the project: kerbs (see photo),
RE approvals for use of - Concrete classes manufacturer’s certificates
materials on site, - Asphaltic Concrete Mix Analysis. to accompany all
measurement sheets Details for following tests missing deliveries on site
- Manufacturer certificates for If kerbs are made on site,
Kerbs, IBDs, concrete confirmatory
- Confirmatory tests for concrete tests to be carried out
during casting of concrete in Equip RE office with
culverts Rebound Hammer to test
quality of concrete before
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
leaving manufacturer/
contractor’s yard
Verify proper field Sufficient supervision team including Keeping records Noted KURA HQ
inspection by road the RE, ARE, Inspectors and site Commendable
overseers and agent Equip RE office with
methodology Daily worksheets available. equipment for works
Equipment for confirmatory tests not inspection.
availed to RE staff Expand survey equipment
in specifications, Clause
132 to include Rebound
Hammer
Measurement of Measurement sheet availed for Commendable. None Not
individual bill items and individual bill items Applicable
valuation Appraisal done
Inspection and Daily inspection by the inspection Commendable None Not
acceptance of works team as evident in the daily Applicable
worksheet
No acceptance report as the project is
at 35%
Comment on proper Quite commendable filing and record Filing Commendable None Not
filling of records and Applicable
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
ease of retrieval of keeping.
documents
8 Quality of Check on the There is sufficient supervision of on- Expand test results to Noted KURA HQ
Ongoing/Co performance, standards, going work by the supervision team cover pre-casted units
mpleted adherence to tolerance Materials used in the field subjected
works and durability of the to testing for quality in the lab prior
works to use in the field
Review construction Method of construction and other Commendable None Not
methods used, supplies procedures given by contractor Applicable
and work procedures approved by the engineer.
Carry out confirmatory There are no culverts constructed yet - None Not
tests for completed and There are no kerbs or IBDs or Applicable
ongoing works channels on site yet
The work is relatively new
Perform visual The works are ongoing Commendable None Not
inspection of completed Stone hand packing is done Applicable
works and rate the works sufficiently and ongoing (Figure 4-
as either good, fair or 106)
poor
9 Quality Review of quality control Existing approach for quality control Confirmatory tests for Noted KURA HQ
Control systems in place focusses on initial selection of Precast units to be carried
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
materials. at the source by Engineer.
Need to expand material testing Engineer to issue Site
program to confirmatory tests on Instructions and ensure
site- earthworks and concrete. compliance with: testing
For precast units, carry out the tests of precast units at the
at the source, before delivery. manufacturers yard
Compare the quality Inspection and acceptance report Commendable None Not
control records i.e., adequate with respect to the Applicable
inspection and specifications provided in the scope
acceptance reports with of work.
specifications
Comment on sampling Most material tests are conducted at Expand test results. Noted KURA HQ
and testing of materials, the start of the contract works. RE to expand issuance of
and use of test results to Material Test results carried out at instructions to include
ensure works quality the start of the contract may not fully tests for precast units
address quality of works throughout
the project period.
10 Environmen Review the There was no provision for Conduct feasibility studies Under KURA HQ
tal and environmental impact environmental impact and mitigation and ESIA and details to be implementati
Social Audit mitigation measures measures. captured in EMP on
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
issues applied However, no negative effects of this
project on the environment were
noted during the field visits and
audit.
Assess on-site health and No provisions for trainings on The on-site health and Noted KURA HQ
safety measure occupational health and safety. safety measures should be
applied
Provide for training SUM
in Bill 25 under Cross
Cutting Issues.
Gender considerations in Monthly labour returns showing the Commendable and should None Not
employment number of males and females who be upheld. Applicable
were involved in the project were
available.
Documentation of major There was no documentation of on Environmental Noted KURA HQ
environmental and social major environmental and social Management Plan to
issues expected and issues expected. capture key environmental
appropriate remedial Noise and dust expected due to and social issues should
measures proximity of houses to the road be provided for by the
Contractor to show how
he/she would deal with
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
arising environmental and
social issues.
Detailed EMP to be
captured in MPR
11 Road Safety Adherence to the designs Project scope and activities did not Commendable None Not
given in terms of road alter road geometry Applicable
geometries
Comment on clarity of Road reserves clear Commendable None Not
road reserves and Applicable
clearance of site
Verify the construction Furniture provided for in Bill 20. Commendable None Not
of necessary road Applicable
furniture
12 Roads 2000 Training on R2000 Specifications allow for Training of Create awareness R2000 Noted KURA HQ
Strategy Strategy for both field site staff strategy by facilitating
and senior personnel training of personnel on
the same.
Add training and
awareness creation as a
cross-cutting issue- Bill 25
Integration of cross Labour sourced from project area Commendable None Not
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
cutting issues Materials sourced from project area. Applicable
Employment levels and 30% gender rule not met as depicted Adhere to the 30% Noted KURA HQ
adherence to 30% in the Contractor’s monthly and daily employment to women
employment to women labour returns.
Extent of use of local Extensive use of local labor and Commendable None Not
labour and materials materials observed. Applicable
13 Post- Issuance of take over The works are omgoing - None Not
Constructio certificate, defects Applicable
n liability period and
Managemen control of road services
t and utilities
14 Prior Audit . The project was not audited - None Not
recommend previously Applicable
ations
15 Performance Aspects of good work Kerb- kerb gaps that allow road Commendable None Not
practice/weaknesses both surface drainage. Applicable
on the agency and Kerbs used were of relatively good
contractor. quality.
The road surfacing was well done
and were in good condition as shown
in the photos in the Annexure
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-1.
HQ
15-
334
spec
ific
findi
ngs
S/No
section.
Filing system and documentation
good
1.1.2 Rehabilitation Of Five Star Road, Access Road to Hamayun Estate & Drainage Works on
Muhoho Road
Project Name Rehabilitation of Five Star Road, Access Road to Hamayun Estate
and Drainage Works in Muhohoh Road
Tender No KURA/RMLF/HQ/337/2021-2022
Name of Contractor Zila Systems Limited
Road Name & ID Five Star Road, Access Road to Hamayun Estate and Drainage Works
in Muhohoh Road
Road ID HQ-18
Project Works Rehabilitation
Category Youth
Project Funding RMLF Conditional Allocation
Planned Length 1.8 km
Budget Kshs. 165,000,000.00
Achieved Road Length 1.8
Date of Procurement 23/02/2022
Contract Award Date 19/04/2022
Start Date 22nd May, 2022
Completion Date 22nd Nov, 2022
Contract Period 6 months with 3 months DLP
R.E In charge -
Time elapsed 5 months
% Time elapsed 83%
% Progress of works 88%
Contract Sum Kshs. 163,567,656.00
Savings/Overrun Kshs. 1,432,344.00
Certified Amount to date Kshs. 70,776,872.00
% Of contract sum certified 43.3%
Date of Report Sept-22
KURA/RMLF/HQ/337/2021-2022
1.1.2.1 Location Of Contract
Verify the availability Several manuals such as FIDIC and Emphasis should None Not Applicable
and use of AASHTO 1999 were applied in planning, be made to the use
guidelines/manuals for contract management and supervision. of certified
planning e.g.; methods of
Supervision and measurements and
Contract Evaluation quotation.
manual, AASHTO
1999, FIDIC Red
Book etc.
Compare the unit rates The rates adopted were within the market Commendable None Not Applicable
Tabl Reporting Area Audit Observations Recommendation Management Action by
e Comments
2-2.
HQ
18-
337
spec
ific
findi
ngs
S/No
adopted to the market price.
rates
3 APRP Confirm eligibility of The projects under HQ region were not Commendable None Not Applicable
the project for funding listed in the APRP. Only the amount
using the Road allocated to the region was stated
Maintenance Levy The project was funded through savings.
Fund
Check for works No records for such works. Commendable None Not Applicable
outside APRP or
County Government
work plans
Explain the budget A savings of Kshs. 1,432,344.00 was Commendable None Not Applicable
Overruns/Savings realized fom this project
Check for multiple No multiple funding. Commendable None Not Applicable
funding or duplication Project is only funded through savings.
of works
Check for omitted No works observed to have been omitted Commendable None Not Applicable
road works in the
APRP/County Gvt
work plans
Comment on the status There is no carry over work for this project. Commendable. None Not Applicable
of carry over works
and any overlaps with
Tabl Reporting Area Audit Observations Recommendation Management Action by
e Comments
2-2.
HQ
18-
337
spec
ific
findi
ngs
S/No
FY 2020/2021 works
4 Project Appropriateness of The designs provided were appropriate and Commendable. None Not Applicable
Preparation designs with regard to adequate.
economy and The contractor also provided an appropriate
efficiency work programme.
Project Adherence to project Formation levels were provided Commendable None Not Applicable
Design preparation process The designs were customized to fit the
and design steps project
Invert levels for culverts were provided and
documented
5 Tendering Advertisement of A complete contract documented stamped Commendable. None Not Applicable
and tenders, Check for an and signed was filed.
Procureme efficient tendering Performance bond provided.
nt process and the Contract documents has main sections for
completeness of small works- conditions of contract,
contract documents, specifications, special specifications, and
Publicity boards. bill of quantities
Adequacy of the BoQ Bill descriptonas are adequate as Commendable None Not Applicable
descriptions compared to standard specifications
Tabl Reporting Area Audit Observations Recommendation Management Action by
e Comments
2-2.
HQ
18-
337
spec
ific
findi
ngs
S/No
Comparison of unit Item BoQ Range Market Unit rates applied
rates adopted in the Rate in this Contract
BoQ with the market AC 26064 2000- 30000 were within the
rates 39000 prevailing market
Kerbs 1200 400- 1000 rates
1500
Marking 1200 150- 1500
2500
Concrete 12000 1200- 13000
25000
6 Project Verify works Work supervision team not provided. The Supervision Noted Director
Manageme supervision and Resources to be used by the supervision team should be
nt/ availability of team not provided. well equipped and
Constructio adequate supervision The contractor had the equipment required resourced.
n Stage resources (staff, in this project. (4 tippers, Concrete The contractor was
vehicles, funding etc.) vibrators, water tank, Wheel loader, Motor well equipped.
loaders, Hydraulic crawler, Self-propelled
single dum, Paver, Pot hole cutter)
The equipment was leased from the ministry
of transport.
Handling of advances, No evidence of claims, advances, variation Commendable None Not Applicable
guarantees, insurances, orders and cost in this project.
site instructions,
Tabl Reporting Area Audit Observations Recommendation Management Action by
e Comments
2-2.
HQ
18-
337
spec
ific
findi
ngs
S/No
claims, variation 1% performance guarantee of Kshs
orders and cost 1,635,676.56 provided and confirmed by
Century Microfinance Bank expiring on
25/05/2023.
Site instructions provided.
Comment on the IPC documents availed and fully supported Commendable None Not Applicable
payment timelines to DLP period active
contractors/suppliers
Comment on the No progress reports provided. Progress reports None Not Applicable
delivery of works should be well
within the planned documented.
time and cost
Confirm certification Work approval forms provided and signed Commendable None Not Applicable
of the works done; by the RE, ARE, Road inspector and the site
work approval forms, agent
approved material Material test approved by the RE
tests, RE approvals for Measurement sheets duly filled and
use of materials on documented
site, measurement
sheets
Verify proper field Daily worksheet signed by the inspection Commendable None Not Applicable
inspection by rad team
overseers and Sufficient inspection team including the RE,
Tabl Reporting Area Audit Observations Recommendation Management Action by
e Comments
2-2.
HQ
18-
337
spec
ific
findi
ngs
S/No
methodology ARE, road inspector, surveyor and the site
agent
Site instructions sufficiently issued
Measurement of Measurement sheets provided sufficiently Commendable None Not Applicable
individual bill items and all individual items valued
and valuation
Inspection and Substantial inspection done and minutes Commendable None Not Applicable
acceptance of works documented
DLP active
Comment on proper Proper filing of documents in a box file Commendable None Not Applicable
filling of records and
ease of retrieval of
documents
7 Quality of Check on the The road is completed and under use by Commendable None Not Applicable
Ongoing/C performance, residence
ompleted standards, adherence The drainages are well done
works to tolerance and DLP is active
durability of the works
Review construction Method of construction and other Commendable None Not Applicable
methods used, procedures given by contractor and
supplies and work approved by the RE
procedures
Carry out Rebound hammer test on Cabro is at Ensure Noted KURA-HQ
Tabl Reporting Area Audit Observations Recommendation Management Action by
e Comments
2-2.
HQ
18-
337
spec
ific
findi
ngs
S/No
confirmatory tests for 25N/mm2 compared to the required strength confirmation of
completed and of 49N/mm2 quality of pre-
ongoing works Compressive strength of culvert wings at casted units before
22N/mm2 compared to the required strength procurement for
of 25N/mm2 use in the field
Provide the RE
with rebound
hammer for
confirmation of
quality of concrete
used in the field
Perform visual Carriage way is rated as good with good Commendable None Not Applicable
inspection of traffic flow (Photo 4-60)
completed works and Road marking is still pending, DLP is active
rate the works as (Photo 4-62)
either good, fair or Well defined footpath and is aesthetic
poor (Photo 4-644)
Stone pitching done and culverts installation
Broken Kerbs (Photo 4-66)
Cleaning of existing culverts and drains
(Photo 4-61)
8 Quality Review of quality The Contractor leased all the necessary The contractor was Noted KURA-HQ
Control control systems in equipment for this project. well equipped with
Tabl Reporting Area Audit Observations Recommendation Management Action by
e Comments
2-2.
HQ
18-
337
spec
ific
findi
ngs
S/No
place All material test were carried out at the machinery.
beginning of the project except for pre- Carry out test for
casted units. pre-casted units
The contractor engaged a qualified engineer. before
procurement to be
used in the field
Compare the quality Daily inspection by supervision team as Commendable None Not Applicable
control records i.e., evident in the daily worksheet
inspection and Substantial inspection conducted
acceptance reports
with specifications
Comment on sampling Concrete samples were submitted for class Material testing to Noted KURA-HQ
and testing of 15/20 and class 25/20 and were subjected to cover the pre-
materials, and use of 7 and 28 days for strength casted units
test results to ensure There were no samples submitted for pre-
works quality casted units
9 Environme Review the Copies of EIA and NEMA report and EIA and NEMA Noted KURA-HQ
ntal and environmental impact analysis were not provided. reports should be
Social mitigation measures documented in a
Audit applied detailed EMP
issues Assess on-site health There are no records of safety gears like Apply onsite Noted KURA-HQ
and safety measures safety boots given to workers safety measures
Use of reflectors by workers is Provide for on-site
Tabl Reporting Area Audit Observations Recommendation Management Action by
e Comments
2-2.
HQ
18-
337
spec
ific
findi
ngs
S/No
commendable health and safety
measures in the
BoQ
Gender considerations The monthly labour returns show that both Commendable None Not Applicable
in employment male and female were employed in work
force
Documentation of No documentation on environmental and Major Noted KURA-HQ
major environmental social issues documented. environmental and
and social issues No remedial Measure documented. social issues
expected and expected and
appropriate remedial appropriate
measures remedial measures
should be
documented
10 Road Adherence to the The designs adopted did not alter with the Commendable None Not Applicable
Safety designs given in terms road geometry
of road geometries
Comment on clarity of The road reserve is clear except for some Involve the county Under KURA-HQ
road reserves and encroachment government and implementation
clearance of site other stakeholders
to deal with
encroachment
Verify the Furniture is provided for in the BoQ bill 20 Ensure that road Noted KURA-HQ
Tabl Reporting Area Audit Observations Recommendation Management Action by
e Comments
2-2.
HQ
18-
337
spec
ific
findi
ngs
S/No
construction of Furniture installed include road signs and marking is done
necessary road road kerbs before the end of
furniture Road marking is pending DLP
11 Roads Training on R2000 No evidence on trainings and sensitization Trainings and Noted KURA-HQ
2000 Strategy for both field campaigns conducted. sensitization
Strategy and senior personnel campaigns should
be conducted by
the contractor.
Provide for R2000
training in the
BoQ under Bill 25
Integration of cross Labour and materials were sourced locally Integrating Noted KURA-HQ
cutting issues Publicity signboard was installed as activities; training
instructed and creation of
No records of HIV/AIDS training or awareness for
creation of awareness HIV/AIDS to be
conducted
Employment levels The monthly labour returns indicated that Adhere to the 30% Noted KURA-HQ
and adherence to 30% both male and female were employed in threshold
employment to women work force but the 30% threshold was not employment to
me women
Extent of use of local Local materials and labour were employed Commendable None Not Applicable
labour and materials
Tabl Reporting Area Audit Observations Recommendation Management Action by
e Comments
2-2.
HQ
18-
337
spec
ific
findi
ngs
S/No
12 Prior Audit The project was not previously audited. - None Not Applicable
recommend
ations
13 Exemplary Aspects of good work Goof filling and record keeping Commendable None Not Applicable
Performanc practice e.g.,
e documentation of
works done and
organization of files
1.1.3 Improvement Of Baraka Lane-Off Eastern Bypass
KURA/RMLF/HQ/342/2021-2022
1. Road Works
Earthworks
Construction of 300mm Improved Subgrade 0.6km
150mm Base quality subbase-0.6km
150mm hand packed stones-0.6km
50mm Ac surface
Pothole patching and repair works
AC regulation and Overlay
Provision and installation of road furniture.
Road marking
2. Drainage Works
2 Prioritization of Verify the There are records on stakeholder Conduct and Noted KURA-HQ
works undertaking of engagement Supplement
RICS and its place There are no evidence to show that ARICS with road
in selection ARICS conducted for the road maps that depict
and prioritization of road condition and
works. Stakeholder their extents
participation.
Confirm proper Key intervention measures captured HQ to provide Noted KURA-HQ
scoping of works were: geotagged photos
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
and appropriate - Earthworks showing road
intervention - Construction of 300mm Improved conditions before
measures Subgrade 0.6km interventions
- 150mm Base quality subbase-0.6km Provide map
- 150mm hand packed stones-0.6km showing road
- 50mm Ac surface maintenance
- Pothole patching and repair works action required
depending on
- AC regulation and Overlay
existing condition
- Provision and installation of road
furniture.
- Road marking
- Drainage works
- Maintenance of traffic around and
through works
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
- Relocation of services
There is no documentation of road
conditions before intervention
3 Planning of Development of the An annual workplan prepared and Seeking approval None Not
Works annual work plan submitted to KRB of work plans Applicable
commendable
Verify the PPRA’s Standard Documents for Small Use of standard None Not
availability and use Works applied documents Applicable
of Manuals for cost estimating (2019) commendable
guidelines/manuals available at KURA HQ Office. Apply updated
for planning Cost estimating manuals require cost estimation
updating manual once
released
In the meantime,
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
apply consumer
indices to reflect
price changes
4 APRP Confirm eligibility The projects under HQ were not listed Commendable None Not
of the project for in the APRP. Only the amount allocated Applicable
funding using the to the region was stated
Road Maintenance The project was funded under savings
Levy Fund
Check for works There were no works outside the APRP Commendable None Not
outside APRP Applicable
Explain the budget No budget overruns. Commendable None Not
Overruns/Savings A budget Savings of Kshs. 826,627.60 Applicable
was realized.
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
Check for multiple No multiple funding on the road Commendable None Not
funding or Applicable
duplication of
works
Check for omitted No omitted works from the APRP. Commendable. None Not
road works in the Applicable
APRP/County Gvt
work plans
Comment on the No carry over of the works Commendable. None Not
status of carry over No overlaps with 2020/2021 projects Applicable
works and any
overlaps with FY
2020/2021 works
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
5 Project Design Adherence to Detailed sketch with scoping report Commendable None Not
project preparation availed Applicable
process and design Invert levels established
steps Standard drawings applied for culverts,
kerbs and IBD drains
Use of raised road kerbs appropriate in
case of errant vehicles
Appropriateness of Open drains suitable for the area Commendable None Not
designs with regard Laying of kerbs with drainage slots Applicable
to economy and appropriate
efficiency Side slabs for drains appropriate
The designs were efficient and
economic
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
6 Tendering and Advertisement of A complete contract document was Commendable. None Not
Procurement tenders, Check for signed. Applicable
an efficient Contract documents has main sections
tendering process for small works- conditions of contract,
and the specifications, special specifications,
completeness of and bill of quantities
contract documents, Tender was for Youth category, which
Publicity boards. is appropriate to enhance competition.
1 No Publicity boards provided in the
contract and Engineers instructions
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
Adequacy of the Bill descriptions are adequate as Commendable None Not
BoQ descriptions compared to standard specifications Applicable
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
Comparison of unit Item BoQ Range Marke Unit rates applied None Not
rates adopted in the Rate t in this Contract Applicable
BoQ with the AC 23000 20000- 30000 were within the
market rates 39000 prevailing market
Kerbs 1000 400- 1000 rates except for
1500 AC which has a
Marking 1400 150- 1500 large variation
2500 from the market
Concrete 13000 1200- 13000 modal rate
25000
7 Project Verify works Engineers staff included RE, ARE, Supervision of the None Not
Management/ supervision and Roads Inspector and Supervisor. project was well Applicable
Construction availability of Project provided a vehicle. facilitated.
Stage adequate Bill item 01.80-030 allows for
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
supervision allowances for RE’s staff @ 600,000.00
resources (staff, Bill Item 01.80-010 allows for material
vehicles, funding testing @ Kshs. 300,000.
etc)
Handling of No variation orders encountered Commendable None Not
advances, Approval for expending supervision PC Applicable
guarantees, sums sought by RE and granted by PE
insurances, site No claims issued on project
instructions, claims, Advance payments not applicable
variation orders and
cost
Comment on the One IPC document of Kshs. Commendable None Not
payment timelines 13,807,721.28 is filed and fully Applicable
to supported
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
contractors/supplier
s
Comment on the The works is at 30% with 83% of time Commendable. None Not
delivery of works lapse. The project is slowly progressing Applicable
within the planned
time and cost
Confirm Completed works certified by RE, ARE Due to low quality Noted KURA-HQ
certification of the and Site Agent precast units
works done; work Following tests were conducted at onset (kerbs, IBDs,
approval forms, of the project: channels) in the
approved material - Concrete classes market, kerbs (see
tests, RE approvals - Asphaltic Concrete Mix Analysis. photo),
for use of materials - Base layers e.g., Field Density Tests manufacturer’s
on site, Details for following tests missing certificates to
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
measurement sheets - Manufacturer certificates for Kerbs, accompany all
IBDs, deliveries on site
- Confirmatory tests for concrete during If kerbs are made
casting of concrete in culverts on site, concrete
confirmatory tests
to be carried out
Equip RE office
with Rebound
Hammer to test
quality of concrete
before leaving
manufacturer/
contractor’s yard
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
Verify proper field Daily worksheets available. Keeping records Noted KURA-HQ
inspection by road Records filed to september Commendable
overseers and Equipment for confirmatory tests not Equip RE office
methodology availed to RE staff with equipment for
works inspection.
Expand survey
equipment in
specifications,
Clause 132 to
include Rebound
Hammer
Measurement of Appraisal done Commendable. None Not
individual bill items Measurement sheets duly filled Applicable
and valuation
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
Inspection and Daily inspection done as evident in the Taking over None Not
acceptance of works daily worksheets certificate to be Applicable
There are no substantial or acceptance issued to the
yet since the project is at 30% contractor.
Comment on proper Quite commendable filing and record Filing None Not
filling of records keeping. Commendable Applicable
and ease of retrieval
of documents
8 Quality of Check on the Project is ongoing. Expand test results Noted KURA-HQ
Ongoing/Compl performance, All materials were subjected to testing to cover pre-casted
eted works standards, prior to use in the field and the test units
adherence to results approved by the engineer
tolerance and There was sufficient supervision of
durability of the work execution by the inspection team
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
works as evident in the daily worksheets
Review construction Method of construction and other Commendable None Not
methods used, procedures given by contractor Applicable
supplies and work approved by the engineer.
procedures
Carry out Rebound hammer test on concrete Commendable None Not
confirmatory tests structures is satisfactory (Photo 5-72) Applicable
for completed and
ongoing works
Perform visual The works are ongoing Commendable None Not
inspection of Instalation of Kerbs on going (Photo 5- Applicable
completed works 70)
and rate the works
as either good, fair
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
or poor
9 Quality Control Review of quality Existing approach for quality control Confirmatory tests Noted KURA-HQ
control systems in focusses on initial selection of materials. for Precast units to
place Need to expand material testing be carried at the
program to confirmatory tests on site- source by
earthworks and concrete. Engineer.
For precast units, carry out the tests at Concrete works to
the source, before delivery. be subjected to
fresh and hardened
concrete tests.
Compare the quality Inspection and acceptance report Commendable None Not
control records i.e., adequate with respect to the Applicable
inspection and specifications provided in the scope of
acceptance reports work.
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
with specifications
Comment on Most material tests are conducted at the Expand test Noted KURA-HQ
sampling and start of the contract works. results.
testing of materials, Material Test results carried out at the
and use of test start of the contract may not fully
results to ensure address quality of works throughout the
works quality project period.
10 Environmental Review the There was no provision for Carry out Noted KURA-HQ
and Social Audit environmental environmental impact and mitigation feasibility study
issues impact mitigation measures. and ESIA and
measures applied However, no negative effects of this detail in the EMP
project on the environment were noted Detailed EMP to
during the field visits and audit. be captured in the
monthly reports
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
Assess on-site No provisions for trainings on There is need to Noted KURA-HQ
health and safety occupational health and safety. provide for
measure training SUM in
Bill 25 under
Cross Cutting
Issues.
Provide for
training SUM in
Bill 25 under
Cross Cutting
Issues.
Gender Monthly labour returns showing the Commendable and None Not
considerations in number of males, females and PWD should be upheld. Applicable
employment who were involved in the project were
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
available.
Documentation of There was no documentation of on Environmental Noted KURA-HQ
major major environmental and social issues Management Plan
environmental and expected. to capture key
social issues Noise and dust expected due to environmental and
expected and proximity of houses to the road social issues
appropriate should be provided
remedial measures for by the
Contractor to show
how he/she would
deal with arising
environmental and
social issues.
11 Road Safety Adherence to the Project scope and activities did not alter Commendable None Not
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
designs given in road geometry Applicable
terms of road
geometries
Comment on clarity Road reserves clear Commendable None Not
of road reserves and Applicable
clearance of site
Verify the Furniture provided for in Bill 20. Commendable None Not
construction of Applicable
necessary road
furniture
12 Roads 2000 Training on R2000 Specifications allow for Training of site Create awareness Under KURA-HQ
Strategy Strategy for both staff R2000 strategy by implementatio
field and senior facilitating training n
personnel of personnel on the
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
same.
Add training and
awareness creation
as a cross-cutting
issue- Bill 25
Integration of cross Labour sourced from project area Commendable None Not
cutting issues Materials sourced from project area. Applicable
Employment levels 30% gender rule is not met as depicted Adhere to the 30% Noted KURA-HQ
and adherence to in the Contractor’s monthly and daily employment to
30% employment to labour returns. women
women
Extent of use of Extensive use of local labor and Commendable None Not
local labour and materials observed. Applicable
materials
Ta Reporting Area Audit Observations Recommendation Management's Action By
ble Comments
2-
3.
H
Q2
3-
34
2
sp
eci
fic
fin
di
ng
s
S/
No
13 Post- Issuance of take There are no post construction - None Not
Construction over certificate, management practices in place yet as the Applicable
Management defects liability roject is ongoing at 30%
period and control
of road services and
utilities
14 Prior Audit . The project was not audited previously - None Not
recommendation Applicable
s
15 Performance Aspects of good Filing system and documentation good Commendable None Not
work Applicable
practice/weaknesses
both on the agency
and contractor.
1.1.4 Periodic Maintenance of Pepo Lane & Windy Lane
KURA/RMLF/HQ/346/2021-2022
Location Of Contract
1. Road Works
Facilitation of the supervision staff
Pothole patching and overlay on the 2km carriageway
Construction of 1.5km long, 2m wide walkway on both side of the carriageway using concrete paving
blocks
Lining of drain using IBDs on both sides of the 1.5km long carriageway Issued by the Kenya Urban
Roads Authority
Pothole
Stage construction to subbase layer of the gravel section of the road
Road marking
Installation and repair of raised kerbs and channel
Installation of road signs
2. Drainage Works
5. Maintenance of works during Contract Period – Defect Liability Period shall be 1 month.
1.1.5.3 Specific Technical Audit Findings
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
1 Need Identification of The roads qualified for Rehabilitation Commendable None Not
Assessment the need for It serves the residents of Karen Applicable
implementation of Characterized by medium traffic volume
the works
2 Prioritization of Verify the There are no records on stakeholder Conduct and Supplement Noted KURA HQ
works undertaking of engagement ARICS with road maps
RICS and its place ARICS conducted for the road that depict road condition
in selection and their extents
and prioritization
of works.
Stakeholder
participation.
Confirm proper Scoping of works conducted HQ to provide geotagged Noted KURA HQ
scoping of works Key intervention measures captured were: photos showing road
and appropriate Base repairs using hand packed conditions before
intervention stones. interventions
measures Pot-hole repairs Provide map showing
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
Site clearing road maintenance action
Removal of top soil required depending on
AC 50mm surfacing of carriage existing condition
way
Installation of Kerbs and excavation
of drains
Road furniture, marking and road
signs
Installation of culverts and lining of
IBDs
Protection works
Drainage works
Maintenance of traffic through
traffic
Relocation of services
There is no documentation of road
conditions before intervention
3 Planning of Development of An annual workplan prepared and Seeking approval of work None Not
Works the annual work submitted to KRB plans commendable Applicable
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
plan
Verify the PPRA’s Standard Documents for Small Use of standard None Not
availability and use Works applied documents commendable Applicable
of Manuals for cost estimating (2019) Apply updated cost
guidelines/manuals available at KURA HQ Offices. estimation manual once
for planning Cost estimating manuals require updating released
In the meantime, apply
consumer indices to
reflect price changes
4 APRP Confirm eligibility None of the projects under HQ region was None Not
of the project for listed in the APRP. Only the allocated Applicable
funding using the amount to the region was stated
Road Maintenance The funding of this project was from the
Levy Fund special allocation
Check for works - - None Not
outside APRP Applicable
Explain the budget No budget overruns. Commendable None Not
Overruns/Savings The contract sum was Kshs. Applicable
281,818,967.40 and engineer’s estimate
was Ksh. 89,845,325
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
Check for multiple No multiple funding on the road Commendable None Not
funding or Applicable
duplication of
works
Check for omitted No omitted works from the APRP. Commendable. None Not
road works in the Applicable
APRP/County Gvt
work plans
Comment on the No carry over of the works Commendable. None Not
status of carry over No overlaps with 2020/2021 projects Applicable
works and any
overlaps with FY
2020/2021 works
5 Project Design Adherence to Detailed sketch with scoping report Preparation of detailed None Not
project preparation availed sketches commendable. Applicable
process and design Establishing invert levels for drainage
steps works (Bill 5 activities) done
Standard drawings applied for culverts,
kerbs and IBD drains
Use of raised road kerbs appropriate in
case of errant vehicles
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
Appropriateness of Open drains suitable for the area Commendable None Not
designs with Laying of kerbs with drainage slots Applicable
regard to economy appropriate
and efficiency Side slabs and IBDs for drains appropriate
The designs were suitable economically
and were efficient
6 Tendering and Advertisement of A complete contract document was signed. Commendable. None Not
Procurement tenders, Check for Performance bond wa provided Applicable
an efficient Contract documents has main sections for
tendering process small works- conditions of contract,
and the specifications, special specifications, and
completeness of bill of quantities
contract 1 No Publicity boards provided in the
documents, contract and Engineers instructions
Publicity boards.
Adequacy of the Bill descriptions are adequate as Commendable None Not
BoQ descriptions compared to standard specifications Applicable
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
Comparison of unit Item BoQ Range Market Unit rates applied in this None KURA-HQ
rates adopted in Rate Contract were slightly
the BoQ with the AC 10584 20000- 30000 lowerthan the
market rates 39000 prevailing market rates
Kerbs 400 400- 1000 for AC and kerbswhich
1500 has a large variation
Marking 1500 150- 1500 from the market modal
2500 rate
Concrete 18000 1200- 13000
25000
7 Project Verify works Engineers staff included RE, ARE, Roads Supervision of the project None Not
Management/ supervision and Inspector and Supervisor. was well facilitated. Applicable
Construction availability of Bill item 01.10 allows for allowances for
Stage adequate RE’s staff @ 2,000,000.00
supervision Bill item 01.03 allows for allowances for
resources (staff, RE’s miscellaneous account @
vehicles, funding 1,500,000.00
etc) Bill Item 01.05 allows for provision of
vehicle 2 no. saloon car not less tha 2700
cc and maintained with fuel and provided
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
driver
Handling of No variation orders encountered None Not
advances, Approval for expending supervision PC Commendable Applicable
guarantees, sums sought by RE and granted by PE
insurances, site No claims issued on project
instructions, Advance payments not applicable
claims, variation
orders and cost
Comment on the There are no payments made yet as the - None Not
payment timelines project is at 5% and is relatively new Applicable
to
contractors/supplie
rs
Comment on the The works are oongoing Contractor to be issued a Noted REs
delivery of works The project is at 5% and 83% of time has slow progress letter
within the planned elapsed hence the project is progressing at
time and cost a slow rate
Confirm Completed works certified by RE, ARE Due to low quality precast Noted KURA HQ
certification of the and Site Agent units (kerbs, IBDs,
works done; work Following tests were conducted at onset of channels) in the market,
approval forms, the project: kerbs (see photo),
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
approved material - Concrete classes manufacturer’s
tests, RE approvals - Asphaltic Concrete Mix Analysis. certificates to accompany
for use of materials - Base layers e.g., Field Density Tests all deliveries on site
on site, Details for following tests missing If kerbs are made on site,
measurement - Manufacturer certificates for Kerbs, concrete confirmatory
sheets IBDs, tests to be carried out
- Confirmatory tests for concrete during Equip RE office with
casting of concrete in culverts Rebound Hammer to test
quality of concrete before
leaving manufacturer/
contractor’s yard
Verify proper field Daily worksheets available. Keeping records Noted KURA HQ
inspection by road Records filed for all the months Commendable
overseers and Equipment for confirmatory tests not Equip RE office with
methodology availed to RE staff equipment for works
inspection.
Expand survey equipment
in specifications, Clause
132 to include Rebound
Hammer
Measurement of Measurement sheet availed for individual Commendable. None Not
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
individual bill bill items Applicable
items and Appraisal done
valuation
Inspection and Daily inspection by the supervision team Commendable None Not
acceptance of as evident in the daily report Applicable
works No acceptance report as the project is at
5%
Comment on Quite commendable filing and record Filing Commendable None Not
proper filling of keeping. Applicable
records and ease of
retrieval of
documents
8 Quality of Check on the All materials used were subjected to Expand test results to Noted KURA HQ
Ongoing/Compl performance, testing in the lab prior to use in the field cover pre-casted units
eted works standards, Sufficient supervision of work execution prior to use
adherence to as evident in the daily worksheet signed by RE to issue instructions to
tolerance and the inspection team cover the pre-casted units
durability of the Survey conducted adequately test results
works
Review Method of construction and other Commendable None Not
construction procedures given by contractor approved Applicable
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
methods used, by the engineer.
supplies and work
procedures
Carry out Tests done on concrete structures and The quality of road kerbs Noted KURA HQ
confirmatory tests elements available on site using a rebound and concrete paving
for completed and hammer blocks available on site is
ongoing works Rebound hammer results for Kerbs is at poor
18N/mm2 compared to the required The RE to ensure the
strength of 25N/mm2 quality of PCC units at the
Rebound hammer results for Concrete manufacturer’s yard
paving blocks is at 22N/mm2 compared to before procurement
the required strength of 49N/mm2
Construction is ongoing
Perform visual Commendable None Not
inspection of Installation of IBDs and side slabs is Applicable
completed works ongoing (Figure 4-99)
and rate the works Channel installation and road kerbs
as either good, fair ongoing (Figure 4-98)
or poor Base preparation of carriage way and
footpath is ongoing (Figure 4-97)
9 Quality Control Review of quality Existing approach for quality control Confirmatory tests for Noted KURA HQ
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
control systems in focusses on initial selection of materials. Precast units to be carried
place Need to expand material testing program at the source by Engineer.
to confirmatory tests on site- concrete. Concrete works to be
For precast units, carry out the tests at the subjected to fresh and
source, before delivery. hardened concrete tests.
Compare the Inspection and acceptance report adequate Commendable None Not
quality control with respect to the specifications provided Applicable
records i.e., in the scope of work.
inspection and
acceptance reports
with specifications
Comment on Most material tests are conducted at the Expand test results. Noted KURA HQ
sampling and start of the contract works. RE to expand issuance of
testing of Material Test results carried out at the start instructions to include
materials, and use of the contract may not fully address tests for precast units
of test results to quality of works throughout the project
ensure works period.
quality
10 Environmental Review the There was provision for environmental Conduct feasibility Under KURA HQ
and Social Audit environmental impact and mitigation measures, e.g., for studies and ESIA and implementati
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
issues impact mitigation dust, temporary water pumps were used in details to be captured in on
measures applied watering (Figure 4-100) EMP
However, these were not capture in the
EMP
Assess on-site Temporary road signs were used as The on-site health and Noted KURA HQ
health and safety warning signs safety measures should be
measure Issuance of reflectors to the workers applied
Provide for training SUM
in Bill 25 under Cross
Cutting Issues.
Gender Monthly labour returns showing the Commendable and should None Not
considerations in number of males, females and PWD who be upheld. Applicable
employment were involved in the project were
available.
Documentation of There was no documentation of on major The use of temporary Noted KURA HQ
major environmental and social issues expected. water pumps and water
environmental and Noise and dust expected due to proximity tanks to mitigate dust is
social issues of houses to the road commendable
expected and Detailed EMP to be
appropriate captured in MPR
remedial measures
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
11 Road Safety Adherence to the Project scope and activities did not alter Commendable None Not
designs given in road geometry Applicable
terms of road
geometries
Comment on Road reserves clear Commendable None Not
clarity of road Applicable
reserves and
clearance of site
Verify the Furniture provided for in Bill 20. Commendable None Not
construction of Applicable
necessary road
furniture
12 Roads 2000 Training on R2000 Specifications allow for Training of site Create awareness R2000 Under KURA HQ
Strategy Strategy for both staff, but there was no evidence of such strategy by facilitating implementati
field and senior activities being conducted training of personnel on on
personnel the same.
Add training and
awareness creation as a
cross-cutting issue- Bill
25
Integration of cross Labour sourced from project area Commendable None Not
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
cutting issues Materials sourced from project area. Applicable
Employment levels 30% gender rule not met as depicted in the Adhere to the 30% Noted KURA HQ
and adherence to Contractor’s monthly and daily labour employment to women
30% employment returns.
to women
Extent of use of Extensive use of local labor and materials Commendable None Not
local labour and observed. Applicable
materials
13 Post- Issuance of take The project is on-going - None Not
Construction over certificate, Applicable
Management defects liability
period and control
of road services
and utilities
14 Prior Audit . The project was not audited previously Not Applicable None Not
recommendation Applicable
s
15 Performance Aspects of good Kerb- kerb gaps that allow road surface Commendable None Not
work drainage. Applicable
practice/weaknesse Filing system and documentation good
s both on the
Tabl Reporting Area Audit Observations Recommendation Management' Action by
e s Comments
2-5.
HQ
27-
356
spec
ific
findi
ngs
S/No
agency and
contractor.
1.1.6 Improvement of Quickmart-Fedha school of aviation
KURA/RMLF/HQ/359/2021-2022
Total 1.0 km
The total length of the road is approximately 1.0 Km.
1. Road Works
2. Drainage Works
4. Relocation of services.
5. Maintenance of works during Contract Period – Defect Liability Period shall be 3 months.
1.1.6.3 Specific Technical Audit Findings
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
1 Need Identification of the The roads qualified for Commendable None Not
Assessment need for improvement Applicable
implementation of It serves the Embakasi residents
the works Characterized by high traffic
volume
2 Prioritization of Verify the There are records on stakeholder Conduct and Noted KURA HQ
works undertaking of RICS engagement Supplement ARICS
and its place in There are no records to show that with road maps that
selection ARICS conducted for the road depict road condition
and prioritization of and their extents
works. Stakeholder
participation.
Confirm proper Scoping of works conducted HQ to provide Noted KURA HQ
scoping of works and Key intervention measures geotagged photos
appropriate captured were: showing road conditions
intervention - Facilitation of the supervision before interventions
measures staff Provide map showing
- Site clearance road maintenance action
- Earthworks to formation levels required depending on
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
including reprocessing existing existing condition
road and topping up to achieve
formation level using natural
gravel or suitable fill
- Construction of the pavement
structure along the existing
alignment
- Laying 50mm AC Type I as
wearing Course on Base
- 35mm AC wearing course on
1.5m walkway on both sides of
the road.
- Provision and installation of
road furniture including road
marking.
- Installation of Road signs
There is no documentation of road
conditions before intervention
3 Planning of Development of the An annual workplan prepared and Seeking approval of None Not
Works annual work plan submitted to KRB work plans Applicable
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
commendable
Verify the PPRA’s Standard Documents for Use of standard None Not
availability and use Small Works applied documents Applicable
of Manuals for cost estimating (2019) commendable
guidelines/manuals available at KURA HQ Offices. Apply updated cost
for planning Cost estimating manuals require estimation manual once
updating released
In the meantime, apply
consumer indices to
reflect price changes
4 APRP Confirm eligibility of The project was funded by CS Commendable None Not
the project for allocation Applicable
funding using the The projects under HQ were not
Road Maintenance listed in the APRP, only the
Levy Fund amount allocated to the region was
stated
Check for works No works outside APRP Commendable. None Not
outside APRP Applicable
Explain the budget No budget overruns. Commendable None Not
Overruns/Savings The budget for this project was Applicable
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
Kshs. 80,000,000
Check for multiple No multiple funding on the road Commendable None Not
funding or Applicable
duplication of works
Check for omitted No omitted works from the APRP. Commendable. None Not
road works in the Applicable
APRP/County Gvt
work plans
Comment on the No carry over of the works Commendable. None Not
status of carry over No overlaps with 2020/2021 Applicable
works and any projects
overlaps with FY
2020/2021 works
5 Project Design Adherence to project Detailed sketch with scoping report Preparation of detailed None Not
preparation process availed sketches commendable. Applicabl
and design steps Establishing invert levels for e
drainage works (Bill 5 activities)
done
Standard drawings applied for
culverts, kerbs and IBD drains
Use of raised road kerbs
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
appropriate in case of errant
vehicles
Appropriateness of Open drains suitable for the area Commendable None Not
designs with regard Laying of kerbs with drainage slots Applicable
to economy and appropriate
efficiency Side slabs for drains appropriate
The designs were suitable
economically and were efficient
6 Tendering and Advertisement of A complete contract document was Commendable. None Not
Procurement tenders, Check for an signed. Applicable
efficient tendering Performance bond was provided
process and the Contract documents has main
completeness of sections for small works-
contract documents, conditions of contract,
Publicity boards. specifications, special
specifications, and bill of quantities
Tender was for All category, which
is appropriate to enhance
competition.
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
1 No Publicity boards provided in
the contract and Engineers
instructions
Adequacy of the Bill descriptions are adequate as Commendable None Not
BoQ descriptions compared to standard Applicable
specifications
Comparison of unit Item BoQ Range Market Commendable. Unit None Not
rates adopted in the Rate rates applied in this Applicable
BoQ with the market AC 35000 2000- 30000 Contract were within
rates 39000 the prevailing market
Kerbs 1000 400- 1000 rates
1500
Marking 1300 150- 1500
2500
Concrete 15000 1200- 13000
25000
7 Project Verify works Engineers staff included RE, ARE, Supervision of the None Not
Management/Co supervision and Roads Inspector and Supervisor. project was well Applicable
nstrutcion Stage availability of Project provided a double cab facilitated.
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
adequate supervision 4WD not less than 2500cc and
resources (staff, with driver and fuel maintenance
vehicles, funding etc) under bill 01.11
Bill item 01.16 allows for
allowances for RE’s staff
Bill Item 01.07 allows for material
testing @ KShs. 200,000.
Handling of No variation orders encountered Commendable None Not
advances, Approval for expending Applicable
guarantees, supervision PC sums sought by RE
insurances, site and granted by PE
instructions, claims, No claims issued on project
variation orders and Advance payments not applicable
cost
Comment on the No payments made yet as the Commendable None Not
payment timelines to project is at 5% Applicable
contractors/suppliers
Comment on the The project is ongoing Commendable. None Not
delivery of works It is at 5% and is expected to be Applicable
within the planned completed by Feb, 2023
time and cost
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
Confirm certification Completed works certified by RE, Manufacturer’s Noted KURA HQ
of the works done; ARE and Site Agent certificates to
work approval forms, Following tests were conducted at accompany all deliveries
approved material onset of the project: on site to ensure quality
tests, RE approvals - Concrete classes If kerbs are made on
for use of materials - Asphaltic Concrete Mix site, concrete
on site, measurement Analysis. confirmatory tests to be
sheets - Base layers e.g., Field Density carried out
Tests Equip RE office with
Details for following tests missing Rebound Hammer to
- Manufacturer certificates for test quality of concrete
Kerbs, IBDs, before leaving
- Confirmatory tests for concrete manufacturer/
during casting of concrete in contractor’s yard
culvert
Verify proper field Daily worksheets available. Keeping records Noted KURA HQ
inspection by road Equipment for confirmatory tests Commendable
overseers and not availed to RE staff Equip RE office with
methodology equipment for works
inspection.
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
Measurement of Measurement sheet availed for Commendable. None Not
individual bill items individual bill items Applicable
and valuation Appraisal done
Inspection and Daily inspection by the inspection - None Not
acceptance of works staff as evident in the daily Applicable
worksheets
No substantial or acceptance work
yet as the project is relatively new
Comment on proper Quite commendable filing and Filing Commendable None Not
filling of records and record keeping. Applicable
ease of retrieval of
documents
8 Quality of Check on the All materials were subjected to Expand results to cover Noted KURA HQ
Ongoing/Compl performance, testing prior to use in the filed pre-casted units
eted works standards, adherence Sufficient work supervision by the RE to issue instructions
to tolerance and inspection team to cover pre-casted units
durability of the
works
Review construction Method of construction and other Commendable None Not
methods used, procedures given by contractor Applicable
supplies and work approved by the engineer.
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
procedures
Carry out Tests done on concrete structures Quality control None Not
confirmatory tests for and elements. commendable. Applicable
completed and Rebound tests results on concrete
ongoing works elements and structures such as
kerbs and culvert wing walls were
satisfactory.
Perform visual Work is on-going Commendable None Not
inspection of Excavations and handpacking of Applicable
completed works and stones is ongoing (Figure 4-140)
rate the works as Installation of Culverts is ongoing-
either good, fair or Access and cross culverts (Figure
poor 4-143)
9 Quality Control Review of quality Existing approach for quality Confirmatory tests for Noted KURA HQ
control systems in control focusses on initial selection Precast units to be
place of materials. carried at the source by
Need to expand material testing Engineer.
program to confirmatory tests on Concrete works to be
site- earthworks and concrete. subjected to fresh and
For precast units, carry out the tests hardened concrete tests.
Engineer to issue Site
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
at the source, before delivery. Instructions and ensure
compliance with: testing
of precast units at the
manufacturers yard
Compare the quality Inspection and acceptance report Commendable None Not
control records i.e., adequate with respect to the Applicable
inspection and specifications provided in the
acceptance reports scope of work.
with specifications
Comment on Most material tests are conducted Expand test results to Noted KURA HQ
sampling and testing at the start of the contract works. cover PCC units
of materials, and use Material Test results carried out at
of test results to the start of the contract may not
ensure works quality fully address quality of works
throughout the project period.
10 Environmental Review the There was no provision for Conduct feasibility Noted and is KURA HQ
and Social Audit environmental environmental impact and studies and ESIA and under
issues impact mitigation mitigation measures. details to be captured in implementatio
measures applied However, no negative effects of EMP n
this project on the environment Detailed EMP to be
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
were noted during the field visits captured in MPR
and audit.
Assess on-site health No provisions for trainings on The on-site health and Noted KURA HQ
and safety measure occupational health and safety. safety measures should
be applied
Provide for training
SUM in Bill 25 under
Cross Cutting Issues.
Gender Monthly labour returns showing Commendable and None Not
considerations in the number of males and females should be upheld. Applicable
employment who were involved in the project
were available.
Documentation of There was no documentation of on Environmental Noted and is KURA HQ
major environmental major environmental and social Management Plan to under
and social issues issues expected. capture key implementatio
expected and Noise and dust expected due to environmental and n
appropriate remedial proximity of houses to the road social issues should be
measures provided for by the
Contractor to show how
he/she would deal with
arising environmental
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
and social issues.
11 Road Safety Adherence to the Project scope and activities did not Commendable None Not
designs given in alter road geometry Applicable
terms of road
geometries
Comment on clarity Road reserves clear Commendable None Not
of road reserves and Applicable
clearance of site
Verify the Furniture provided for in Bill 20. Commendable None Not
construction of Applicable
necessary road
furniture
12 Roads 2000 Training on R2000 Specifications allow for Training Create awareness R2000 Has been
Strategy Strategy for both of site staff strategy by facilitating taken up
field and senior training of personnel on
personnel the same.
Add training and
awareness creation as a
cross-cutting issue- Bill
25
Integration of cross Labour sourced from project area Commendable None Not
Tabl Reporting Area Audit Observations Recommendation Management's Action By
e Comments
2-6.
HQ
30-
359
spec
ific
findi
ngs
S/No
cutting issues Materials sourced from project Applicable
area.
Employment levels 30% gender rule not met as Adhere to the 30% Noted KURA HQ
and adherence to depicted in the Contractor’s employment to women
30% employment to monthly and daily labour returns.
women
Extent of use of local Extensive use of local labor and Commendable None Not
labour and materials materials observed. Applicable
13 Post- Issuance of take over The project is new and is at 5% - None Not
Construction certificate, defects Applicable
Management liability period and
control of road
services and utilities
14 Prior Audit . The project was not audited - None Not
recommendation previously Applicable
s
15 Performance Aspects of good Filing system and documentation Commendable None Not
work good Applicable
practice/weaknesses
both on the agency
and contractor.
1.1.7 Upgrading To Bitumen Standard of Un Avenue-Kiambu Road Exit Link
KURA/RMLF/HQ/343/2021-2022
Verify the availability The Contract document was Guidelines and manuals None Not
Table Reporting Area Audit Observations Recommendation Management Action By
2-7. Comments
HQ24
-343
specifi
c
findin
gs
S/No
and use of prepared to FIDIC standard. adequately used Applicable
guidelines/manuals for
planning e.g.;
Supervision and
Contract Evaluation
manual, AASHTO
1999, FIDIC Red
Book etc
4 APRP Confirm eligibility of The project was funded under Only projects in the None Not
the project for funding CS allocation APRP should benefit Applicable
using the Road from RMLF
Maintenance Levy
Fund
Check for works Project funding was through Only projects in the None Not
outside APRP or CS Allocation which doesn’t APRP should benefit Applicable
County Government affect APRP planned works from RMLF
work plans
Explain the budget Savings of Kshs 1,472,803.18 A good practice to be None Not
Overruns/Savings were made since the award upheld Applicable
contract sum was Kshs
58,527,196.80 and the budget
allocation Kshs 60,000,000
Check for multiple Funding was only done through Commendable None Not
Table Reporting Area Audit Observations Recommendation Management Action By
2-7. Comments
HQ24
-343
specifi
c
findin
gs
S/No
funding or duplication CS allocation. Hence, no Applicable
of works multiple funding of the project
Check for omitted road Project funding was through Only projects in the None Not
works in the CS Allocation which doesn’t APRP should benefit Applicable
APRP/County Gvt affect APRP planned works from RMLF
work plans
Comment on the status There was no carry over works Commendable None Not
of carry over works from FY 2020/2021. Order to Applicable
and any overlaps with commence was issued on 4th
FY 2020/2021 works May 2022
5 Project Adherence to project The design steps were adhered Commendable. None Not
Design preparation process to. Working drawings are a Applicable
and design steps The designs provided were key deliverable in project
Appropriateness of adequate and appropriate for preparation and should be
designs with regard to feasible execution of the works. availed before project
economy and Drawing of proposed road commencement
efficiency realignment on LR No.
12825/203. Appropriate Work
programme prepared as well
6 Tenderin Advertisement of The tender was advertised Commendable None Not
g and tenders, Check for an under women category and the Applicable
Procurem efficient tendering contract awarded to the lowest
ent process and the bidder (Unami Construction Co.
Table Reporting Area Audit Observations Recommendation Management Action By
2-7. Comments
HQ24
-343
specifi
c
findin
gs
S/No
completeness of Ltd) on 8th April 2022.
contract documents, The unit rates adopted and are
Publicity boards. as indicated above and within
market rates
Item 1.09 in the BOQ provides
for the placing of publicity
stickers.
Adequacy of the BoQ Bill descriptions are adequate Commendable None Not
descriptions as compared to standard Applicable
specifications
7 Project Verify works R.E and A.R.E appointed for Adequate facilitation of - -
Table Reporting Area Audit Observations Recommendation Management Action By
2-7. Comments
HQ24
-343
specifi
c
findin
gs
S/No
Manage supervision and the project and funds for their the RE and his staff in
ment / availability of remuneration provided for terms of vehicles and
Construct adequate supervision under Bill 1 in the Bill of remuneration.
ion Stage resources (staff, Quantities. Contractor provided Key staff such as
vehicles, funding etc.) qualified project manager, site surveyor provided by the
agent and equipment (grader, contractor should be
lorry etc.) qualified
Handling of advances, Performance bond provided by Commendable None Not
guarantees, insurances, Century Micro Finance Bank, Applicable
site instructions, site instructions by the R.E filed
claims, variation in the project file
orders and cost
Comment on the No amount had been certified Payment should be made None Not
payment timelines to by the contractor at the time of to the contractor after Applicable
contractors/suppliers the audit inspection and approval
of works
Comment on the Time elapsed is 40% and the Slow progress report None Not
delivery of works work carried out is only issued to the contractor Applicable
within the planned earthworks with gravelling
time and cost Slow progress report to be
issued by the RE
Confirm certification Works approval for site Commendable None Not
of the works done; clearance and earthworks for Applicable
Table Reporting Area Audit Observations Recommendation Management Action By
2-7. Comments
HQ24
-343
specifi
c
findin
gs
S/No
work approval forms, cut and fill availed
approved material Approval done by ARE and RE
tests, RE approvals for
use of materials on
site, measurement
sheets
Verify proper field Site instruction by RE on Commendable None Not
inspection by road 10/6/2022 on setting out data Applicable
overseers and and traverse stations, clear site
methodology on road reserve, remove
cracked pipe culverts and earth
works
Measurement of Measurement sheets filed, and Commendable None Not
individual bill items duly filled Applicable
and valuation
Inspection and Daily inspection by the Commendable None Not
acceptance of works supervision team as evident in Applicable
the monthly report
No record of substantial
inspection and acceptance
reports as the project is on
going
Comment on proper Neat project file with Ensure the filling of all Noted KURA-HQ
Table Reporting Area Audit Observations Recommendation Management Action By
2-7. Comments
HQ24
-343
specifi
c
findin
gs
S/No
filling of records and documents sequentially filed project related documents.
ease of retrieval of and organized. However, the Update the project file
documents file missed minutes of site with all the documents
meetings required
8 Quality Check on the All the materials used was Expand test results to Noted KURA-HQ
of performance, subjected to testing in the lab cover pre-casted units.
Ongoing/ standards, adherence prior to use in the field and Engineer to issue
Complete to tolerance and results approval done by the instructions to cover for
d works durability of the works engineer pre-casted units
Sufficient supervision of work
execution
Review construction Method of construction and Commendable None Not
methods used, supplies other procedures given by Applicable
and work procedures contractor and approved by the
RE
Carry out confirmatory - - None Not
tests for completed and Applicable
ongoing works
Perform visual Cut and fill work carried out Commendable None Not
inspection of perfectly (Photo 4-77) Applicable
completed works and Carriage way graded well.
rate the works as either (Photo 4-75)
good, fair or poor
Table Reporting Area Audit Observations Recommendation Management Action By
2-7. Comments
HQ24
-343
specifi
c
findin
gs
S/No
The project is ongoing
9 Quality Review of quality Provision for material testing Quality control which None Not
Control control systems in and other material testing ensures quality works and Applicable
place services provided for in Bill 1 use of appropriate
of the BoQ construction methods
RE provided with a 4WD sufficiently provided for.
station vehicle of fuel capacity
2500cc fueled and maintained
and an item of Kshs 1.5Million
to allow for attendance of the
RE to the staff
Compare the quality Daily inspection carried out by Commendable None Not
control records i.e., the supervision team Applicable
inspection and
acceptance reports
with specifications
Comment on sampling Gravel samples were obtained Commendable None Not
and testing of from the supplier and were Applicable
materials, and use of tested for dry sieving
test results to ensure
works quality
10 Environ Review the Copies of EIA and NEMA EIA and NEMA reports None Not
mental environmental impact report and recommendations should be included in the Applicable
Table Reporting Area Audit Observations Recommendation Management Action By
2-7. Comments
HQ24
-343
specifi
c
findin
gs
S/No
and mitigation measures were not present in the file file.
Social applied Provision of Kshs 200,000 is
Audit made for operation of the
issues contractor’s Environmental
Management Plan and payment
of required fees to NEMA.
Assess on-site health Bill 25 allows for HIV/ AIDS Measure of on-site health Noted KURA-HQ
and safety measures awareness campaigns. There to be put in place
are no records of such activities Provide for on-site health
being conducted measures in the BoQ
No records to show safety gears
availed
Gender considerations The monthly labour returns Commendable None Not
in employment shows that both male and Applicable
females were employed in the
work force
Documentation of A letter written on 14th July Provide remedial Noted and KURA-HQ
major environmental 2022 to Chief Officer Water, measures for under
and social issues Environment, Energy and environmental issues implementati
expected and Natural resources (Kiambu experienced on
appropriate remedial County) to harvest trees lacks a Detailed EMP to be
measures remedial measure e.g., planting captured in MPR
of trees to compensate for the
Table Reporting Area Audit Observations Recommendation Management Action By
2-7. Comments
HQ24
-343
specifi
c
findin
gs
S/No
cut trees
11 Road Adherence to the Designs adopted did not alter Commendable None Not
Safety designs given in terms the road geometries Applicable
of road geometries
Comment on clarity of Road reserves were clear Commendable None Not
road reserves and Applicable
clearance of site
Verify the construction Bill 20 in the BOQ provides Relevant road furniture None Not
of necessary road for the installation of reflectors, provided for in the BOQ Applicable
furniture thermoplastic material for road and is commendable
marking, 250*125 class 25/20
precast concrete, 100*125 flush
kerbs,16 steel pipe bollards of
Dia. 150mm; 1.05m above the
ground and permanent road
signs
12 Roads Training on R2000 Specs allow for Training of site Create awareness R2000 Noted KURA-HQ
2000 Strategy for both field staff. There is no record of such strategy by facilitating
Strategy and senior personnel training activities being training of personnel on
conducted the same. Add training
and awareness creation as
a cross-cutting issue- Bill
25
Table Reporting Area Audit Observations Recommendation Management Action By
2-7. Comments
HQ24
-343
specifi
c
findin
gs
S/No
Integration of cross Labour and Materials sourced File the records of Noted KURA-HQ
cutting issues from project area. HIV/AIDS activities
The HIV/AIDS activities were being carried out
provided for in the BQ but there
is no record of such activities
being conducted
Employment levels Labour returns show that both Implement the 30% Noted KURA-HQ
and adherence to 30% males and females were employment to women
employment to women employed but the 30%
employment to women was not
met
Extent of use of local Extensive use of local labor and Commendable None Not
labour and materials materials observed. Applicable
13 Post- Issuance of take over The project is at 40% progress - None Not
Construct certificate, defects Applicable
ion liability period and
Manage control of road
ment services and utilities
14 Prior The project was not audited - None Not
Audit previously Applicable
recomme
ndations
15 Performa Aspects of good work Following documents checklist Commendable None Not
Table Reporting Area Audit Observations Recommendation Management Action By
2-7. Comments
HQ24
-343
specifi
c
findin
gs
S/No
nce practice/weaknesses Good filing and record keeping Applicable
both on the agency and
contractor.
1.1.8 Upgrading To Bitumen Standard of Kerarapon Drive (Part)
KURA/RMLF/HQ/335/2021-2022
Filling with gravel or approved materials for sub-grade and sub-base layers; and shoulders
Excavation of drains
Road furniture:
Road marking.
9 Environme Review the The contractor used a water sprayer The exercise mitigated the None Not
ntal and environmental impact truck to subdue dust pollution negative environmental Applicable
Social mitigation measures emanating from the ongoing earth impact resulting from dust.
Audit applied works. The Contractor had
issues There was an Environmental and Social included the Environmental
Impact Assessment (ESIA) that was management plan in the Bill
carried out from 24th May,2022 to 27th of Quantities.
May, 2022. There was a memo written This is commendable
to the Resident Engineer requesting for
approval of expenditure of
KSH.194,200 for the ESIA.
Assess on-site health The excavations on site were Safety measures onsite were Noted KURA-HQ
and safety measures barricaded with safety tapes and found adequate and
warning signs to ensure safety working.
precautions. HIV/AIDS awareness
Dust pollution was mitigated by use of should be a mandatory
temporary bumps and water spraying exercise.
the earthworks.
Table Reporting Area Audit Observations Recommendation Managemen Action by
2-8. t Comments
HQ1
6-
335
speci
fic
findi
ngs
S/No
There was no HIV/AIDs awareness for
the audited project period.
Gender There were 22 staffs allocated to this The ⅔ gender rule should Noted KURA-HQ
considerations in project out of which 21 were male and 1 be observed given that the
employment female. This represented 95% male and project was under women
5% female category.
2/3 gender rule was not attained.
Documentation of Dust pollution is a major environmental Quite commendable None Not
major environmental pollutant which was adequately Applicable
and social issues mitigated.
expected and The social issues anticipated were
appropriate remedial handled through stakeholder
measures participation meetings and ESIA
reports.
10 Road Adherence to the The road design specified a carriageway Commendable None Not
Safety designs given in of 9m which was adhered to from Applicable
terms of road earthworks.
geometries
Comment on clarity The road reserves were clear Commendable None Not
of road reserves and Applicable
clearance of site
Verify the Furniture provided for under bill 20 Commendable None Not
Table Reporting Area Audit Observations Recommendation Managemen Action by
2-8. t Comments
HQ1
6-
335
speci
fic
findi
ngs
S/No
construction of The installation of road kerbs is ongoing Applicable
necessary road
furniture
11 Roads 2000 Training on R2000 Training on R2000 strategy was not Field staff to be trained on Noted KURA-HQ
Strategy Strategy for both evident in the field staff. R2000 strategy.
field and senior Provide for R2000 training
personnel in the BoQ Bill 25
Integration of cross Cross cutting issues such as All cross-cutting issues Noted KURA-HQ
cutting issues environmental protection was followed should be followed up and
up and implemented in the field. implemented in the field as
Some cross-cutting issues such as provided for in the BoQ
HIV/AIDS awareness, Covid 19
guidelines and gender equality were not
implemented in the field.
Employment levels The staff composition was 95% men The 30% women Noted KURA-HQ
and adherence to and 5% women. composition should be
30% employment to The 30% women employment was not reinforced both in the office
women observed. staff and field staff.
Extent of use of local There was use of local labour and This should be upheld None Not
labour and materials materials throughout the project Applicable
period
Table Reporting Area Audit Observations Recommendation Managemen Action by
2-8. t Comments
HQ1
6-
335
speci
fic
findi
ngs
S/No
12 Prior Audit The project was not previously audited Not Applicable None Not
recommend Applicable
ations
13 Exemplary Aspects of good work The files were well organized into Quite commendable None Not
Performanc practice e.g., sections hosting different project Applicable
e documentation of documents.
works done and
organization of files
BOQs
1.1.1
Upgrading to bitumen standards of UN Avenue Kiambu road exit link
BILL 1: GENERAL
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
SHS
1.01 Allow a provisional Sum for material PC 1 200,000.00 200,000
testing services and other Laboratory SUM
Services.
1.02 Include percentage of P.C Sum in item 1.05 % 10 200,000.00 20,000
for Contractor's overhead and profit
5.03 Provide, place and compact approved fill m3 4,212 850 3,580,200
material on cut areas.
Total of Bill Carried Forward to Summary 6,295,200
BILL 8: CULVERTS AND DRAINAGE WORKS
DESCRIPTION UNIT QTY RATE AMOUNT
No separate payment shall be made for gravel for 1
blinding and hauling to spoil unsuitable excavation
materials and the cost of such shall be included in the
rates and /or prices.
8.01 Excavate in soft materials for side drains,drop inlets, 3
m 3,900 400 1,560,000
outfall and mitre drains including cart to spoil.
8.02 Clean culverts of all sizes to free flow conditions m 100 400 40,000
8.03 Excavate in soft materials for pipe culverts headwalls, m3 100 400 40,000
wingwalls, apron, toewalls and drop inlets.
8.04 Provide, lay and joint 450 mm inner diameter (ID) m 100 600 60,000
precast concrete pipes.
8.05 As in item 8.06 but 600 mm ID. m 150 8,000 1,200,000
8.06 As in item 8.06 but 900 mm ID. m 50 10,000 500,000
8.07 Provide place and compact class 15/20 concrete to beds, m3 200 11,000 2,200,000
sorrounds, haunches and
for margin between the shoulder and open drain.
8.08 Provide place and compact class 25/20concrete to 3
m 120 12,000 1,440,000
headwalls, wingwalls, aprons and toe walls to
pipeculverts; and slabs on drains, including form work
8.90 Provide and place A142 fabric mesh reinforcement for m 2 20 550 11,000
item 8.11.
8.10 Provide and lay 150mm thick grouted stone pitching with m 2 500 1,800 900,000
ratio 1:4 cement to mortar as directed
8.11 Excavate in any material, provide, lay and joint 600mm x m 2,600 1,200 3,120,000
360mm Invert Block Drain (IBD) complete with 2 side
slabs of 600x225x75mm as lining for storm water drain
including bedding and backfilling with selected material
as per the specifications or as instructed by the Engineer.
8.12 Excavate in any material, provide, lay and joint 300mm m 200 1,000 200,000
Invert Block Drain (IBD)with single side slabs of
600x225x75mm as lining for storm water drain including
bedding and backfilling with selected material as per the
specifications or as instructed by the Engineer.
8.13 Extra over Item 8.11 for precast sideslab of 600x225 m 2 100 1,200 120,000
75mm
Total of Bill Carried Forward to Summary 11,391,000
BILL9: PASSAGE OF TRAFFIC
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
KSHS SHS
9.01 Allow for the passage of traffic km 1.0 200,000 200,000
through the works.
Total of Bill Carried Forward to 200,000
Summary
KSHS SHS
15.01 Prepare surface of carriageway and repair Ltr 15,552 140 2,177,280
areas, provide and spray MC-30 cutback
bitumen at a rate of 0.8-1.2 lt/m2 as prime
coat.
15.02 Prepare surface of carriageway, repair areas, Ltr 12,960 160 1,814,400
provide and spray K1-60bitumen emulsion as
tackcoat or seal to repair areas at a spray rate
of 0.8 - 1.0 L/m2 as directed.
Total of Bill Carried Forward to Summary 3,991,680
BILL 16: BITUMINOUS MIXES
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
KSHS
SHS
16.01 Provide, place and compact 50mm thick asphalt m 3 558
concrete Type 1 with 5 - 6 % nominal bitumen
content by weight to total mix as wearing course
on carriageway as directed.
1.13 Allow a Provisional Sum of KShs 500,000 for the Prime 1 500,000
Engineer's miscellaneous account to be spent in whole or Cost
part as instructed by the Engineer and to be reimbursed
against receipts.
1.14 Extra over item on item 1.13 for contractors’ overheads % 500,000 10%
and profits.
1.15 Provide erect and maintain publicity signs as instructed by No. 2 155,000
the Engineer.
1.16 Allow for attendance upon the Engineer by the following PC
staff in accordance with Clause 137 of Special Sum
Specification
4.06 Extra Over on Item 4.05 for the Contractors % 500,000 10% 50,000.00
Overheads and Profit.
(i) For lane marking (broken lines) with yellow M2 132 1,300 171,600.00
paint, 100 mm wide
(ii) For edge lines (continuous line) with white M2 264 1,300 343,200.00
paint, 150 mm wide
20.02 Provide and lay cement concrete kerb/divider
for road edge and traffic islands in concrete
Class 25/20 as per the drawings and as
instructed by the Engineer
complete with all leads and lifts. Pre-cast/cast-
in-situ kerb / divider
(i) Raised kerbs m 1,000 850 850,000.00
(ii) Flush kerbs m 2,500 850 2,125,000.00
20.03 Provide and place approved road
signs (Area <1m2) as directed by the Engineer;
Summary Project:
Item No. Description Amount (KShs)
1 Preliminary & General Items 4,729,000.00
4 Site clearance and topsoil stripping 938,000.00
5 Earthworks 10,870,600.00
7 Excavation and filling for structures
8 Culvert and drainage Works 22,296,500.00
9 Passage of traffic 75,000.00
12 Natural material subbase and base 5,688,000.00
15 Bituminous surface treatment & surface dressing 3,207,600.00
16 Bituminous Mixes 17,010,000.00
20 Road Furniture 3,654,800.00
25 Cross Cutting issues 495,000.00
Sub Total 68,964,500.00
Add VAT @ 16% 11,034,320.00
Grand Total Carried Forward to Form of Bid 79,998,820.00
BILL 1: GENERAL
ITE DESCRIPTION UNIT QTY RATE AMOUNT
M
1.01 Allow a provisional Sum for material testing PC 1 300000 300,000
services and other Laboratory Services. SUM
1.02 Include percentage of P.C Sum in item 1.05 for % 10 30,000
Contractor's overhead and profit
1.03 Allow a provisional sum of Kshs 500,000 for the PC 1 500000 500,000
Resident Engineer's Miscellaneous account to be spent SUM
in whole or part as directed by the Resident Engineer
against receipts.
1.04 Include percentage of P.C Sum in item 1.07 for % 10 50,000
Contractor's overhead and profit
1.05 Allow Kshs 2,000,000 for attendance of the PC 2,000,000
Engineer to the staff in accordance with clause 137 of SUM
special specifications.
1.06 Include percentage of P.C Sum in item 1.09 for % 10 200,000
Contractor's overhead and profit
1.07 Provide, fuel and maintain with driver, 1No. 4WD Station V.mth 8 200,000 1,600,000
Wagon vehicle (Odometer 0 - 60,000km)of engine
capacity minimum 2500cc for exclusive use of the
Engineer inclusive of the first 4000 Km per vehicle month
in accordance with clause 138of the standard
specifications.
1.08 EO Item 1.11 for kilometers travelled in any month in km 2,00 30 60,000
excess of 4,000km for all running costs 0
1.09 Provide, place and maintain publicity stickers in No. 3 40000 120,000
accordance to KURA's standard drawing on the provided
steel frames (inclusive of transport of the steel frames
from KURA offices and returning the same upon
completion)
1.10 Provision and operation of the Contractor's PC sum 1 200000 200,000
Environmental Management Plan and
performance of all measures required by Clause142
including payment of all fees to NEMA
1.11 Include percentage of P.C Sum in item 1.14 for % 0.1 20,000
Contractor's overhead and profit
Total of Bill Carried Forward to Summary 5,080,000.00
4.03 Excavate, remove and dispose cracked pipe m 100 600 60,000
culverts of any size.
Total of Bill Carried Forward to Summary 3,065,000.00
5.03 Provide, place and compact approved fill material on m3 5,040 1,500 7,560,000
cut areas.
Total of Bill Carried Forward to Summary 24,560,000.00
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
No separate payment shall be made for gravel for blinding and
hauling to spoil unsuitable excavation materials and the cost of
such shall be included in the rates and /or prices.
8.01 Excavate in soft materials for side drains, drop inlets, outfall and 3
m 9,000 300 2,700,000
mitre drains including cart to spoil.
8.02 Clean culverts of all sizes to free flow conditions m 100 200 20,000
8.03 Excavate in soft materials for pipe culverts headwalls, m3 100 400 40,000
wingwalls, apron, toewalls and drop inlets.
8.04 Provide, lay and joint 450 mm inner diameter (ID) precast m 150 4,500 675,000
concrete pipes.
8.05 As in item 8.06 but 600 mm ID. m 300 6,500 1,950,000
8.06 As in item 8.06 but 900 mm ID. m 60 9,000 540,000
8.07 Provide place and compact class 15/20 concrete to beds, m3 613 15,.000 9,195,000
sorrounds, haunches and for margin between the shoulder and
open drain.
8.08 Provide place and compact class 25/20 concrete to headwalls, 3
m 131 20,000 2,620,000
wingwalls, aprons and toe walls to pipe culverts; and slabs on
drains, including form work.
8.90 Provide and place A142 fabric mesh reinforcement for item 2
m 20 600 12,000
8.11.
8.10 Provide and lay 150mm thick grouted stone pitching with ratio 2
m 500 1,500 750,000
1:4 cement to mortar as directed
8.11 Excavate in any material, provide, lay and joint 600mm x m 4,200 1,500 6,300,000
360mm Invert Block Drain (IBD)complete with 2 side slabs of
600x225x75mm as lining for storm water drain including
bedding and backfilling with selected material as per the
specifications or as instructed by the Engineer
8.12 Excavate in any material, provide, lay and joint 300mm Invert m 500 1,500 750,000
Block Drain (IBD) with single side slabs of 600x225x75mm as
lining for storm water drain including bedding and backfilling
with selected material as per the specifications or as instructed
by the Engineer.
Extra over Item 8.11 for precast sideslab of 600x225 75mm 2
m 100 1,500 150,000
11.02 Provide, place and compact natural gravel of CBR m3 300 2,000 600,000
greater than 30% to shoulders/walkways, accesses and
busbays as directed.
Total of Bill Carried Forward to Summary 640,000.00
15.02 Prepare surface of carriageway, repair areas, provide Ltr 25,200 150 3,780,000
and spray K1-60bitumen emulsion as tackcoat or seal
to repair areas at a spray rate of
0.8 - 1.0 L/m2 as directed.
Total of Bill Carried Forward to Summary 7,560,000.00
5.03 Provide, place and compact approved fill material m3 3,600 300 1,080,000
on cut areas.
8.12 Excavate in any material, provide, lay and joint m 200 2,000 400,000
300mm Invert Block Drain (IBD) with single side
slabs of 600x225x75mm as lining for storm water
drain including bedding and backfilling with selected
material as per the specifications or as instructed by
the Engineer.
Extra over Item 8.11 for precast sideslab of 600x225 m 2 100 300 30,000
75mm
12.01 Provide, place and spread natural gravel of CBR m3 1,080 2,000 2,160,000
greater than 30% as sub-base material on selected
sections as directed.
12.02 Provide, place and spread natural gravel of CBR m3 1,080 2,000 2,160,000
greater than 60% as base material on walkways as
directed by the Engineer.
12.03 Provide, lay, and compact hand packed stone material m3 252 3,000 756,000
for base layer and base repair sections including
filling of voids with stone dust and watering as
directed by the Engineer.
15.02 Prepare surface of carriageway, repair areas, provide Ltr 12,960 200 2,592,000
and spray K1-60bitumen emulsion as tackcoat or seal
to repair areas at a spray rate of
0.8 - 1.0 L/m2 as directed.
Total of Bill Carried Forward to Summary 2,995,200
20.05 Place and provide gauge 16 steel pipe Bollards of Dia No 10 3,500 35,000
150mm and 1.05m above the ground and as directed.
20.06 Extra over item 20.05 for reflective material including m 10 400 4,000
sticking/fixing to the bollards as directed by the
Engineer
BILL 1: GENERAL
ITE DESCRIPTION UNIT QTY RATE AMOUNT
M
1.01 Allow a provisional Sum for material testing PC 1 200,000.00 200,000
services and other Laboratory Services. SUM
1.02 Include percentage of P.C Sum in item 1.05 % 1 10% 20,000
for Contractor's overhead and profit
1.03 Allow a provisional sum of Kshs 150,000 for PC 1 500,000.00 500,000
the Resident Engineer's Miscellaneous account to SUM
be spent in whole or part as directed by the
Resident Engineer against receipts
1.04 Include percentage of P.C Sum in item 1.07 % 1 10% 50,000
for Contractor's overhead and profit
4.03 Excavate, remove and dispose cracked pipe culverts m 200 700 140,000
of any size.
Total of Bill Carried Forward to Summary 2,319,600
5.03 Provide, place and compact approved fill material on m 3 7,776 1,600 12,441,600
cut areas.
5.04 Provide rock fill to formation level or as directed by m 3 240 2,500 600,000
the Engineer
Total of Bill Carried Forward to Summary 17,152,100
BILL 8: CULVERTS AND DRAINAGE WORKS
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
No separate payment shall be made for gravel for
blinding and hauling to spoil unsuitable excavation
materials and the cost of such shall be included in the
rates and /or prices.
8.01 Excavate in soft materials for side drains, drop inlets, 3
m 5,400 500 2,700,000
outfall and mitre drains including cart to spoil.
8.02 Clean culverts of all sizes to free flow conditions m 200 150 30,000
8.03 Excavate in soft materials for pipe culverts headwalls, 3
m 1000 500 500,000
wingwalls, apron, toewalls and drop inlets.
8.04 Provide, lay and joint 450 mm inner diameter (ID) m 200 1,500 300,000
precast concrete pipes.
15.02 Prepare surface of carriageway, repair areas, provide Ltr 20,640 120 2,476,800
and spray K1-60bitumen emulsion as tackcoat or seal
to repair areas at a spray rate of
0.8 - 1.0 L/m2 as directed.
5 EARTHWORKS 17,152,100
8 CULVERTS AND DRAINAGE WORKS 42,549,000
9 PASSAGE OF TRAFFIC 360,000
Sub-total 1 141,006,600
Add 16% of Sub-total 1 for Value Added Tax to be reimbursed in certificates 22,561,056
against official receipts
Grand Total Carried Forward to Form of Bid 163,567,656
1.1.1 Periodic maintenance of Pepo Lane Windy Lane
Sub-total 1 77,452,867
Add 16% of Sub-total 1 for Value Added Tax to be reimbursed in certificates 12,392,458.72
against official receipts
Grand Total Carried Forward to Form of Bid 89,845,325.72
1.1.1 Improvement of Baraka Lane off Eastern Bypass
COST ESTIMATES FOR BARAKA LANE
BILL 1: GENERAL
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
1.01 Allow a provisional Sum for material testing PC 1 200,000.00 200,000
services and other Laboratory Services. SUM
Include percentage of P.C Sum in item % 10 20,000
1.02 1.05 for Contractor's overhead and profit
1.03 Allow a provisional sum of Kshs PC 1 200,000.0 200,000
200,000 for the Resident Engineer's SUM 0
Miscellaneous account to be spent in whole or
part as directed by the Resident Engineer against
receipts.
1.04 Include percentage of P.C Sum in item 1.07 % 10 20,000
for Contractor's overhead and profit
1.05 Allow Kshs 1,000,000 for attendance of PC 1 1,000,000. 1,000,000
the Engineer to the staff in accordance with SUM 00
clause 137 of special specifications.
1.06 Include percentage of P.C Sum in item 1.09 % 10 100,000
for Contractor's overhead and profit
1.07 Provide, fuel and maintain with driver,1No. V.mth 9 150,000.00 1,350,000
4WD Station Wagon vehicle (Odometer 0
- 60,000km) of engine capacity minimum
2500cc for exclusive use of the Engineer
inclusive of the first4000 Km per vehicle
month in accordance with clause 138 of
the standard specifications.
1.08 EO Item 1.11 for kilometers travelled in any km 2,000 20 40,000
month in excess of 4,000km for all running costs
1.09 Provide, place and maintain publicity stickers in No. 2 50,000 100,000
accordance to KURA's standard drawing on the
provided steel frames (inclusive of transport of
the steel frames from KURA offices and returning
the same upon completion)
1.10 Provision and operation of the PC 1 200,000.00 200,000
Contractor's Environmental SUM
Management Plan and performance of all
measures required by Clause 142 including
payment of all fees to NEMA
1.11 Include percentage of P.C Sum in item 1.14 % 10 20,000
for Contractor's overhead and profit
Total of Bill Carried Forward to 3,250,000
Summary
BILL 4: SITE CLEARANCE AND TOPSOIL STRIPPING
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
4.01 Clear site on road reserve including removal of m2 400 10 4,000
trees, hedges, bushes, vegetation,
enchroachments (includingstructures) and other
deleterious materials grub up roots and compact
backfill to 100% MDD(AASHTO T99) with
approved material in accordance with the
specifications, and as directed.
4.02 Light bush clearing PC 500 6 3,000
SUM
4.03 Excavate, remove and dispose cracked pipe % 100 1000 100,000
culverts of any size.
Total of Bill Carried Forward to 107000
Summary
BILL 5: EARTH WORKS
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
KSHS
PC 200,000
SUM
No separate payments shall be made for the
overhaul of material and the cost of such
haulage shall be included in the rates and or
prices
5.01 Cut to spoil in soft material 3
m 8,910 300 2,673,000
15.01 Prepare surface of carriageway and repair areas, PC 9,072 100 907,200
provide and spray MC-30 cutback bitumen at a rate SUM
of 0.8-1.2 lt/m2 as prime coat.
15.02 Prepare surface of carriageway, repair areas, provide % 7,560 100 756,000
and spray K1-60bitumen emulsion as tackcoat or seal
to repair areas at a spray rate of 0.8 - 1.0 L/m2 as
directed.
Total of Bill Carried Forward to Summary 1,663,200