TỔNG CÔNG TY HÀNG KHÔNG VIỆT NAM
CÔNG TY TNHH MTV KỸ THUẬT MÁY BAY
AMOS TRAINING MODULE ENGINEERING TRAINING MANUAL
HÀ NỘI – 2023
TỔNG CÔNG TY HÀNG KHÔNG VIỆT NAM
CÔNG TY TNHH MTV KỸ THUẬT MÁY BAY
AMOS TRAINING MODULE ENGINEERING TRAINING MANUAL
CODE: AMOS-ENG-MAN
Iss: 01
Rev: 00
Date: 25-Dec-2023
For Training Purposes Only
© 2023 VAECO Training Center
HÀ NỘI - 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 1: GENERAL
GENERAL
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 1-1 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 1: GENERAL 1.1 INTRODUCTION
INTRODUCTION OF TRAINING COURSE/MODULE
Introduction about meaning, purpose of training course/module
AMOS, Aircraft Maintenance and Engineering System, is a complex
integrated software package that manages the maintenance,
engineering and logistic functions of aviation companies.
AMOS is set to replace the AMASIS software, currently in use at VAECO,
which has several limitations in managing aircraft parts and maintenance
logistics. Therefore, training for involved staffs is crucial for daily tasks
using AMOS.
This course aims to provide the Inspector, the staff of unserviceable
part management and Ex-Import staff with the necessary knowledge
and skills to work effectively with AMOS for daily work.
Knowledge
In this course, you will be introduced to the basic features, functions, and
programs in AMOS.
You will be guided through all the AMOS programs used to complete your
work in the Incomming Inspection Section, Unserviceable part
management Section and Ex-Import Section as well.
Skill
After completing this course, you will be able to:
Understand the connections between different modules in AMOS
Understand the basic features of main modules and programs
Be aware of new concepts and terms in AMOS.
Be aware the main workflows in AMOS related to your work.
Proficient in using related AMOS Progams (APN) of Material
Manangement Module: Parts module APNs, Orders module APNs,
Shipment module APNs, Goods Receiving module APNs, Stores
module APNs.
Relationship between training course/module and job
Optimizing Job Management: Training course helps manage job efficiently
with AMOS, from data entry to job control.
Enhancing Safety and Performance: AMOS is crucial for material
management safety and performance. With this training course, the
trainees learn to use it effectively.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 1.1-1 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 1: GENERAL 1.1 INTRODUCTION
Compliance with Regulations and Procedures: Training ensures
compliance with aviation rules while using AMOS.
Streamlining Data Updates: Trainees work with AMOS to maintain
accurate data and follow regulations.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 1.1-2 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 1: GENERAL 1.2 ABBREVIATION
ABBREVIATION
ABBREVIATION MEANING
AMOS Aircraft Maintenance and Engineering System
APN AMOS Progam Number
OEM Original Equipment Manufacturer
EPS Electronic Pending Shelf
CR Consumables Repairables
FA Aircraft type for financial accounting purposes.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 1.2-1 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 1: GENERAL 1.3 TABLE OF CONTENT
TABLE OF CONTENT
1-1
GENERAL ................................................................................................................ 1-1
INTRODUCTION OF TRAINING COURSE/MODULE ......................... 1.1-1
Introduction about meaning, purpose of training course/module......1.1-1
Knowledge .......................................................................................1.1-1
Skill ..................................................................................................1.1-1
Relationship between training course/module and job .....................1.1-1
ABBREVIATION ................................................................................... 1.2-1
TABLE OF CONTENT .......................................................................... 1.3-1
2-1
CONTENT ................................................................................................................ 2-1
GENERAL ............................................................................................ 2.1-1
AMOS Configuration ........................................................................2.1-1
2.1.1.1 Getting Started .............................................................................2.1-1
2.1.1.2 Basic Features .............................................................................2.1-1
2.1.1.3 Basic Configuration ......................................................................2.1-2
Help, Technical Assistance, AMOS mail ..........................................2.1-2
2.1.2.1 Help Topics. Shortcut: Ctrl + F1 ...................................................2.1-2
2.1.2.2 Technical Assistance (Support query) APN: 869..........................2.1-3
2.1.2.3 AMOS mail APN 991 ....................................................................2.1-5
2.1.2.4 AMOS web drive ..........................................................................2.1-5
Essential APNs ................................................................................2.1-6
2.1.3.1 Stock Information APN 221 ..........................................................2.1-6
2.1.3.2 Parts Tracking APN 188 ...............................................................2.1-7
2.1.3.3 Order Tracking APN 1328 ............................................................2.1-8
2.1.3.4 Workorder Information System APN 1 .........................................2.1-9
2.1.3.5 Aircraft Administration APN 308 .................................................2.1-10
2.1.3.6 Part Administration APN 59 ........................................................2.1-10
2.1.3.7 My Personal Data Summary APN 2925 .....................................2.1-11
2.1.3.8 Staff Time Management/Request Tab APN 979 ........................2.1-12
Other APNs ....................................................................................2.1-12
2.1.4.1 Supplement Plannning APNs .....................................................2.1-12
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 1.3-1 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 1: GENERAL 1.3 TABLE OF CONTENT
2.1.4.2 Supplement Engineering APNs ..................................................2.1-13
2.1.4.3 Supplement Logistic APNs .........................................................2.1-13
2.1.4.4 Supplement MCC/Line/Base APNs ............................................2.1-13
BASIC APNS ........................................................................................ 2.2-1
Address Administration (APN 53) ....................................................2.2-1
2.2.1.1 Overview: .....................................................................................2.2-1
2.2.1.2 Path and Interface: .......................................................................2.2-1
2.2.1.3 Exercise: Creation of external address. ........................................2.2-4
Aircraft Administration (APN 308) ....................................................2.2-7
2.2.2.1 Overview ......................................................................................2.2-7
2.2.2.2 Path and interface ........................................................................2.2-7
2.2.2.3 Excercise ....................................................................................2.2-10
PUBLICATION MANAGEMENT ........................................................... 2.3-1
Overview: .........................................................................................2.3-1
AMOS Process ................................................................................2.3-2
Configuration Publication Management (APN 566): ........................2.3-2
2.3.3.1 Overview ......................................................................................2.3-2
2.3.3.2 Main Configuration tab .................................................................2.3-3
2.3.3.3 Distribution Tab ............................................................................2.3-3
2.3.3.4 Documents Tab ............................................................................2.3-3
2.3.3.5 Excercise: .....................................................................................2.3-3
Publication Management (APN 565) ................................................2.3-5
2.3.4.1 Overview: .....................................................................................2.3-5
2.3.4.2 Publication Data tab .....................................................................2.3-7
2.3.4.3 Excercise: .....................................................................................2.3-7
Publication Acknowledgement (APN 685) .....................................2.3-17
2.3.5.1 Overview: ...................................................................................2.3-17
2.3.5.2 Excercise: ...................................................................................2.3-20
Approval Control for Documents and Publications - Overview (APN's
2110, 2111) ..................................................................................................2.3-22
2.3.6.1 Overview ....................................................................................2.3-22
2.3.6.2 Exercise......................................................................................2.3-24
Contact Publication Authors (APN 683) .........................................2.3-25
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 1.3-2 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 1: GENERAL 1.3 TABLE OF CONTENT
2.3.7.1 Overview ....................................................................................2.3-25
2.3.7.2 CMM File Tab .............................................................................2.3-26
Publication Management Reports (APN 565) ................................2.3-27
2.3.8.1 Overview ....................................................................................2.3-27
2.3.8.2 Overview ....................................................................................2.3-28
OEM Documents Library (APN 1525) ............................................2.3-31
MEL Manual Administration (APN 273) .........................................2.3-31
2.3.10.1 Overview .................................................................................2.3-31
MODIFICATION CONTROL ................................................................. 2.4-1
Overview ..........................................................................................2.4-1
AMOS process .................................................................................2.4-3
View/Edit Modifications (APN 63) ....................................................2.4-4
2.4.3.1 Overview ......................................................................................2.4-4
2.4.3.2 Execice how to enter a Modification Document ............................2.4-4
2.4.3.3 Execice Component Document with Revision ............................2.4-14
2.4.3.4 Execice Signoff Tree ..................................................................2.4-21
2.4.3.5 Flow of an Aircraft & Component "On-Wing" Document through
AMOS 2.4-26
2.4.3.6 Execice For Report Back Document .............................................2.4-28
2.4.3.7 Execice Document Revision .......................................................2.4-30
2.4.3.8 Approval Control for Documents and Publications (APN's 2110,
2111) 2.4-33
2.4.3.9 Exercise build the Sign-Off Tree.................................................2.4-35
2.4.3.10 Exercise Component Document with "Replacement of Component
Required" 2.4-46
2.4.3.11 Modification Control Related Reports .....................................2.4-61
2.4.3.12 Weight and Balance - Set Up and Recordingin AMOS ...........2.4-63
ENGINEERING ORDERS .................................................................... 2.5-1
Overview ..........................................................................................2.5-1
How to enter an Engineering Order .................................................2.5-3
2.5.2.1 Exercises ......................................................................................2.5-3
How to set updistribution lists...........................................................2.5-6
2.5.3.1 Exercise:.......................................................................................2.5-6
Approval Informationand EO Details ................................................2.5-9
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 1.3-3 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 1: GENERAL 1.3 TABLE OF CONTENT
2.5.4.1 Exercise:.......................................................................................2.5-9
Approval Control for Documents and Publications - Overview (APN's
2110, 2111) ..................................................................................................2.5-18
EO with Approval Required ............................................................2.5-19
2.5.6.1 Exercise:.....................................................................................2.5-19
ENGINEERING PART 2 ............................................................................. 1
Aircraft Administration (APN 308) Overview .......................................... 1
Aircraft Code Definition (APN 2627) -Overview ..................................... 2
Part Administration (APN 59) - Overview ............................................... 4
Part Requirement Administration (APN 2773)........................................ 7
Rotable Administration (APN 147) ....................................................... 21
Counter Management (APN 2031) Overview ....................................... 25
Maintenance Event Initialiser (APN 1895)Overview............................. 32
Maintenance Event Browser (APN 2151) Overview ............................. 33
Workorder (APN 1418) Overview......................................................... 34
Assemblies with Configuration Definition ............................................. 36
HARDWARE CONFIGURATION & ASSEMBLY HANDLING .................... 1
Hardware Configuration & Assembly Handling process......................... 1
Introduction - Business Processes and modules ................................... 2
Introduction - Exercises overview .......................................................... 4
Exercise 1 - Creation of simple configuration - Fire Extinguisher ........... 5
Exercise 2 - Assembly withsubconfiguration - APU ..........................2-11
Exercise 3 - Create an A/C configurationincluding assemblies .........2-15
Exercise 4 - Configuration Assignment and FP allocation ...............2-16
Exercise 5 - Configuration check and review ....................................2-19
Exercise 6 - Configuration Revision ..................................................2-20
Exercise 7 - Receive an assembly with a configuration ....................2-22
Assembly Configuration Review .......................................................2-28
SOFTWARE MANAGEMENT MODULE .................................................... 1
Software Management Overview ........................................................... 1
Software Management Process ............................................................. 1
Boeing 787 Authorized Configuration Parser (APN 2333) ..................... 2
Software Management: Compare Allowed Configuration vs. As Flying
Configuration ...................................................................................................... 11
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 1.3-4 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 1: GENERAL 1.3 TABLE OF CONTENT
Correct discrepancies between Allowed configuration and As-Flying
configuration ....................................................................................................... 12
Modification of Software ....................................................................... 16
2.8.6.1 Create a new Consumable: ............................................................... 16
2.8.6.2 Create a new Software Part number: ................................................ 17
2.8.6.3 Link Software to USB Stick................................................................ 18
2.8.6.4 Create a new Service Bulletin: .......................................................... 19
2.8.6.5 Link B787-850233-SB2300012-01 to Configuration Change ............ 23
2.8.6.6 Assign SB with status Open .............................................................. 24
2.8.6.7 Check availability and purchase the Consumable Part: .................... 24
2.8.6.8 Receive the Consumable Part .......................................................... 26
2.8.6.9 Perform the Modification ................................................................... 27
2.8.6.10 Reporting Back Modification ......................................................... 29
WORK INSTRUCTION AUTHORING ........................................................ 1
Overview / Introduction .......................................................................... 1
Work Template Manager (APN1848) ..................................................... 2
2.9.2.1 Exercise: Creation of a Work Template in Work TemplateManager
(APN1848) ........................................................................................................ 3
2.9.2.2 Exercise: Creation of a workorder linked to a Work Templatefrom
Work Template Manager (APN1848)................................................................ 6
2.9.2.3 Exercise: Revising a Work Template in Work Template Manager
(APN1848) ........................................................................................................ 8
Work Step Repository (APN1904) ....................................................... 11
2.9.3.1 Exercise: Linking a Repository Work Step to an existingWorkorder . 12
2.9.3.2 Exercise: Revising a linked Work Step ............................................. 14
2.9.3.3 General Notes .................................................................................. 15
2.9.3.4 Combination Work Template Workstep: ........................................... 16
Work Template Manager - JC .............................................................. 17
2.9.4.1 Exercise:........................................................................................... 17
Work Template Manager - Job Cards .................................................. 23
Jobcard with EWI ................................................................................. 28
STRUCTURAL DAMAGE ................................................................... 2.10-1
Overview ........................................................................................2.10-1
Structural Damage process flow ....................................................2.10-2
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 1.3-5 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 1: GENERAL 1.3 TABLE OF CONTENT
Structural Damage Management in Engineering Part 2 .................2.10-3
2.10.3.1 Aircraft Administration (APN 308) Overview ...........................2.10-4
2.10.3.2 Aircraft Code Definition (APN 2627) - Overview .....................2.10-4
2.10.3.3 Part Administration (APN 59) - Overview ................................2.10-6
2.10.3.4 Maintenance Event Initialiser (APN 1895) Overview ............2.10-11
2.10.3.5 Maintenance Event Browser (APN 2151) .............................2.10-16
2.10.3.6 Workorder (APN 1418) Overview .........................................2.10-16
Structural Damage Management in Line/Base Maintenance .......2.10-31
2.10.4.1 Exercise: Structural Damage (APN 786) ...............................2.10-31
2.10.4.2 Exercise: Structural Damage (APN: 786) ..............................2.10-36
Structural Damage Management in Component Workpackage ...2.10-38
2.10.5.1 Overview ...............................................................................2.10-38
2.10.5.2 Exercise: Component W/P Close Loop - Cargo Panel ..........2.10-39
Structural Damage Reporting.......................................................2.10-45
2.10.6.1 Damage Reports ...................................................................2.10-45
2.10.6.2 Illustrations............................................................................2.10-46
2.10.6.3 Other relevant APNs .............................................................2.10-47
3-1
REFERENCE DOCUMENTS ............................................................... 3.1-1
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 1.3-6 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT
CONTENT
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2-1 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
GENERAL
AMOS Configuration
2.1.1.1 Getting Started
There are a few basics that you should know before you can start working
with AMOS:
The log-in screen is the "doorway" to AMOS programs. You have to enter
your personal user ID and password to gain access to the programs.
The UI scaling feature and the new icon set is active per default. If you
want to change your Scaling of AMOS you can do so in the configuration
settings. AMOS > Configuration > UI Scaling.
The User Configured Menu can be customised for each user. This menu
will appear when accessing AMOS and it displays shortcuts to programs
that you most frequently use.
Customize a Main Tool Bar: The Main Toolbar across the top of AMOS
can be configured individually for each user. Each icon in the Main Toolbar
represents a program.
Widgets: With the Widgets feature it's possible to display clock, mini
report, sticky notes, etc. on the starting screen.
Multiple Window Mode: It is possible to open a program multiple times
within AMOS without starting up a new connection and using your
credentials multiple times.
2.1.1.2 Basic Features
Mandatory fields are identified by the small red triangle in the upper left
hand corner. Data must be entered in these fields. Otherwise you will see
a red wavy line in the field.
The unique entry fields are identified by the small green triangle in the
lower right hand corner.
Suggested Fields are very useful, as AMOS will predict and suggest an
entry for you. To confirm the entry click in the field and press the Enter
key.
Cross checked fields normally have a table of data behind them, which
means that the entry must be pre-defined in the table. You can either enter
the details, or you can double click to see the table of data to select your
entry from.
The Instant Information contains detailed information about the data of a
selected field.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-1 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
Certain help function or related programs can be accessed with a right-
click in the active field.
Reports can be generated whenever the small printer symbol or a reports
button is available on the screen.
Part number can be searched either by its number or its description.
2.1.1.3 Basic Configuration
Parameter Setup - APN 1442
In this program the AMOS System Administrator sets the different
parameters and fills together with skilled key users all tables with the
codes used in different AMOS programs. Without these codes the various
AMOS programs cannot be used! The Online description contains for each
program a section in which the related parameters are listed.
Basic Data Administration - APN 18
In this program the AMOS System Administrator together with skilled key
users completes all tables with the codes used in the different AMOS
programs. Without these codes the various AMOS programs cannot be
used.
Workflow Administration - APN 612
Workflow Administration is a great tool for the AMOS Administrator to
create and manage system messages, warnings and other means of
communication. With this program, the AMOS Administrator is able to
setup trigger points in different programs to send messages, warnings etc.
to different user groups or users. With this program you are even able to
stop specified actions if set up by the AMOS Administrator or key user.
Admin Roles - APN 15
This module is used to assign programs and licences (and users) to roles.
A role is a group with defined access rights for specific programs and
licences. Users can be assigned to one or more roles, depending on the
department they work for.
Help, Technical Assistance, AMOS mail
2.1.2.1 Help Topics. Shortcut: Ctrl + F1
AMOS Online Documentation provides:
Detailed descriptions about the various AMOS programs
Information on how to use certain programs
Frequently asked questions
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-2 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
Process descriptions
Opens the AMOS online help. Path: Help/Help Topics
Or in a program, refer three dots at the right up corner of the display
window, and
2.1.2.2 Technical Assistance (Support query) APN: 869
Support query (Shortcut: Ctrl + F2) works only if you are in a program.
You will be prompted with message windows before the "Create Query"
dialogue window opens where you must fill in the mandatory fields and
can make your query.
Or Path: Applications/Quality Assurance/Technical Assistance
Technical Assistance is used to report a problem which has occurred
directly to the person or department responsible. It can be used by any
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-3 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
AMOS user and from every AMOS program. The purpose of the
program is to collect and track different issues within AMOS, for example:
Aircraft queries: handle the different problems of the mechanics
Workorder queries: handle questions regarding workorders
Order complaints: handle issues or questions with an order
Shipment complaints: handle issues with internal and external
shipments
Parts compliants: handle issues with a rotable part.
Invoice complaints: handle issues with an invoice.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-4 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
2.1.2.3 AMOS mail APN 991
Path: Applications/Misc/Messaging/AMOS Mail
AMOS Mail mainly serves two purposes.
As a mail program which includes a text editor for composing
messages and allowing you to send these messages through AMOS.
Sent messages are stored in electronic mailboxes until the recipient
retrieves them. To see if you have any mail, you must check your
electronic mailbox periodically, although AMOS alerts you when mail is
received with the icon at the bottom right and message that pops
up briefly and disappears. After reading your mail, you can store it in a
text file, forward it to other users or delete it.
It serves as a Task scheduler, for example if you want to force a reader
to perform an action such as acknowledging a publication from
Publication Management (APN 565)
2.1.2.4 AMOS web drive
The AMOS web drive is a web space located directly on the AMOS server.
It's possible to store or view documents saved on the web drive.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-5 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
stores files needed to be functional, e.g. pictures appearing on a report.
AMOS users will have access to these files directly out of AMOS or via
webbrowser.
Essential APNs
2.1.3.1 Stock Information APN 221
The following information is available:
Stock availability at the main base and stations
Interchangeability and alternate availability
Parts in transfer to stations
Part kit and assembly information
Store location and location restrictions
Information about parts in quarantine and hangar
Parts on open orders
Event forecasting
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-6 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
2.1.3.2 Parts Tracking APN 188
Parts Tracking is a very comprehensive information program in AMOS. It
contains extensive information regarding the history and movements of
parts and their alternates. The information comes from various AMOS
programs.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-7 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
2.1.3.3 Order Tracking APN 1328
The main purpose of Order Tracking is to search orders and associated
data. It collects all relevant pieces of information regarding the different
orders, such as purchase or repair orders, ever created in AMOS.
Order Tracking also enables you to create and track order reminders.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-8 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
2.1.3.4 Workorder Information System APN 1
Path: Applications/Production/Workorder Information System
The Workorder Information System (WIS) is a very important
roubleshooting tool in AMOS, since all workorders that have been entered
in AMOS can be retrieved here.
The program, with its various filter settings, is therefore ideal for perform
effective troubleshooting for individual aircraft registrations, aircraft types
or components.
In Workorder Information System you can generate different types of
reports about workorders. A selection of possible reports:
WO-Summary report
WO-Summary report with hours
Department Hour Report
Workorder - Text Overview
Workorder Material Report
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-9 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
2.1.3.5 Aircraft Administration APN 308
Path: Applications/Engineering/Aircraft/Aircraft Administration
Aircraft Administration is used to enter, view or modify data about all
aircraft of the company. Before working with AMOS, all aircraft data must
be known to AMOS.
Aircraft Administration serves as a tool to enter data and is also a good
source of information for everything in connection with the aircraft.
2.1.3.6 Part Administration APN 59
Path: Applications/Material Management/Parts/Part Administration.
All part numbers are assigned in Part Administration and are unique in
AMOS. A prerequisite for using part numbers in AMOS is that they are
known to AMOS, except when using Workorder, where unknown part
numbers can be entered.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-10 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
2.1.3.7 My Personal Data Summary APN 2925
Path: Applications/Human Resources/My Personal Data Summary
My Personal Data Summary provides each user with the master data
relevant to their personal login, the information is displayed under the
three main tabs, User, Master Data and Reference Data. You can review
personal data and request rectifications as required.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-11 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
2.1.3.8 Staff Time Management/Request Tab APN 979
Path: Applications/Human Resources/Shift Planning/Staff Time
Management
The Request tab serves two purposes. Absences or overtime of
employees can be entered here, however the staff can also directly
request their favoured days off in the system.
Other APNs
These APNs are might be useful for End-Users to study other
departments/modules functions.
2.1.4.1 Supplement Plannning APNs
Maintenance Forecast APN 1844
View/Edit WorkPackage APN 58
WorkPackage Browser APN 30
Aircraft Browser APN 158
Production Planning APN 1110
Production Control APN 1016
Address Administration APN 53
Hangar Planning APN 2677
Part Requirements Administration APN 2773
Work Template Manager APN 1848
Workorder APN 1418
Maintenance Programs Administration APN 249
Operator Maintenance Program APN 1934
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-12 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
2.1.4.2 Supplement Engineering APNs
Structural Damage APN 786
Weight & Balance APN 292
Aircraft Utilization APN 206
Flight Logbook APN 1589
Aircraft Status Report APN 476
Publication Management APN 565
Modification Status APN 231
Component Modification Status APN 639
Powerplant Administration APN 743
Oil Consumption Statistics APN 839
Software Tracking APN 1832
Systems Reliability APN 399
Part Reliability APN 401
Work Template Manager APN 1848
Work Step Repository APN 1904
Publication Management APN 565
2.1.4.3 Supplement Logistic APNs
Stock Information APN 221
Pickslip Request APN 225
Picking List Management APN 2612
Part Requirement Administration APN 2773
Rotable Administration APN 147
Part Tracking APN 188
Repair Administration APN 1431
EPS APN 326
Suspicious Parts APN 464
2.1.4.4 Supplement MCC/Line/Base APNs
Fleet Tracker Dashboard APN 3126
Repetitive Item Tracking APN 649
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-13 DATE: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.1 GENERAL
Event Tracking APN 432
Electronic pending shelf APN 326
Maintenance coordination module APN 617
Unscheduled ground time APN 1188
Delay & cancellations APN 547
Technical delay & cancellations APN 713
Experience Sheet APN 217
Technical Case Manager APN490
Swap Rotables APN 2130
Missing Parts List APN 1134
Parts Transfer APN 293
Flight Log APN 1573
Aircraft Utilization APN 206
Component Tree Label booking APN184
Rotables Label Booking APN 150
Swap Rotables APN 2130
Repairable Consumables Label Booking APN 1206
Fleet Tracker Dashboard APN 3126
Tool Handover APN 1507
Line Maintenance Manage APN 2950
Work Time Tracking APN 1131
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.1-14 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
BASIC APNS
Address Administration (APN 53)
2.2.1.1 Overview:
All addresses must be defined in Address Administration before they
can be used in any other AMOS program.
Properties can be defined to use the addresses in other AMOS
programs, for example the address code must be defined as a Station
& a Store if the address is to then be further defined in the program
Store Management APN 2409.
The standard practice for external addresses is to use the Cage Code
as the AMOS Address Code.
Financial Data has to be defined to use financial programs in AMOS.
For example, account numbers for Billing and Invoice Checking.
Especially Creditor & Debitor Account No.
Vendor Approval has to be defined to be able to use specific vendors
in AMOS depending on the relevant parameter setting. A workflow is
available to control the creation of a new Addres/Vendor code in AMOS
or when transferred from your ERP system -- Workflow ID 161 - New
Address Stored.
Warranties can be defined to find relevant information regarding repair
and warranty orders in AMOS.
The tabsheet Certificates records the Approval Nb. of the Address
(Supplier/Vendor/Maintenance Provider). The Certificate = IA-Internal
Approval, which contains the Expiry Date, can be used as a control to
only enable to issue Orders to Vendors with this Certificate (Parameter
1157). Also, there is a report 'Address Certificate Expiry Report'.
Workflows regarding the approval procedures have an effect on the
Certificates tab and they can be set in Workflow Administration APN
612. For a new address a quality approval is required and usually a
supplier audit / evaluation process is considered essential.
Turn Around Time can be set for the specific parts supplied by this
address.
Supplier Rating helps the user to indicate how reliable a supplier is.
2.2.1.2 Path and Interface:
Path: Applications/Financial Management/Address Administration
Interface:
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-1 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
Buttons
The following buttons are in Address Administration.
Button Description
Search Use to search for information.
New Item Licence required. Use to enter new addresses.
New Sub Item Licence required. Use to enter new sub addresses.
Report Use to generate reports.
Delete Licence required. Use to delete the selected item.
Each time a new station is entered into Address
Administration, use to load the station
and make it visible in Store & Location Management
- RETIRED, Flight Log and Event Tracking.
Note: When a station is linked to addresses with
Sync Stations
different statuses for example active
or inactive, you have to update these addresses before
synchronising the stations.
The Stations used within several addresses dialogue
opens.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-2 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
Save Use to save information.
Cancel Use to cancel information.
Exit Use to exit the program.
Search tab (in Search Filters section): You can search for addresses
using the Search Filters section in the Search tab.
Result tab: All information matching the search of your address will
appear in the Result tab. The address tree shows all relations of the
address.
Extended tab (in Extended Search Filters section): You can search for
addresses in more detail using the Extended Search Filters section in the
Extended tab.
Whole Tree tab: All existing addresses are displayed in the Whole Tree
tab.
Details section: In this section, the details of the selected address are
shown. You can also use this section to create a new address.
Address tab: All information related to an address is created and
displayed in this tab.
Properties tab: All information related to the properties of an address is
created and displayed in this tab. This tab contains the System Properties
tab and the User Defined Properties tab. Each address can have one or
more properties. The properties define the way they are used in other
programs. For Eeample: If an address is an outstation it must be defined
as SA. - STATION.
System Properties tab: System Properties are defined to assign
additional information to an address and are used in some AMOS
modules.
User Defined Properties tab: In the User Defined Properties tab, you can
define customised properties with a high level of flexibility because names
and values can be entered without any restrictions. Specific for interfaces.
Com. data tab: All communication data is created and displayed in this
tab.
Certificates tab: All certificates are managed in this tab.
Conditions tab: Conditions are set up so that you can charge customers
for any services you provide and receive.
Warranties tab: The Warranties tab stores and maintains warranties
which the addressee, for example a vendor, grants your company.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-3 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
Currencies tab: Various currencies for different vendor Account Numbers
and Types are defined here for use in Billingand Invoice Checking. You
can also define a specific Bill Type which should be used as the default
when generating a bill in Billing.
Order Surcharges tab: Order Surcharges can be set up in this tab to be
used in Order Management. Define the surcharge type, the amount of the
surcharge and link the surcharge to specific order types. Surcharges are
also printed on the order report.
Remarks tab: Any remarks concerning the address can be stored here.
Special tab: Any speciality concerning the address can be entered in this
tab.
Black List tab: You can put an address or vendor on the Black-List for not
paying invoices, breaching a contract or other reasons. The Black List tab
is red when activated and the black listed address has a black background
in the address list.
Used by tab: In this tab you can assign the Owner of the address.
Shipping Account tab: The information in this tab is used, for example if
you would like to return a part to a customer under their Shipper Account
number so that shipping costs are invoiced to the customer.
Parts tab: In the Parts tab you can enter all the part numbers which can
be purchased from or repaired at this vendor. All active part numbers, the
vendor will be displayed in Part Administration > Miscellaneous tab >
Vendor tab and then in Repair Administration > Details tab > Part
Vendor tab. Any connection between an address and a part number
established in this tab will automatically appear in Part Administration,
Miscellaneous > Vendor tab.
Supplier Rating tab: You can rate the quality of your vendor or customer
in this tab. The rating set up is defined in Active Supplier Ratin.
2.2.1.3 Exercise: Creation of external address.
In this exercise we will create an external address and complete some
important tabs.
Open Address Administration Module (APN 53)
Select: New Item
Code: AM04
Type: MA = Main Address
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-4 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
Name: AMOS VENDOR04
Address Tab
Address: Your choice
Homebase: ZRH
Currency: CHF
Select: Save
Note: select Define New button if a pop up message appears.
Properties Tab
Select: New
Type: AO (double click in the field)
Value: AOG DESK
Remarks: Close to Airport
Select: Save
Certificates Tab
Select: New
Type: IA (Internal Approval)
Number: SWSQA004
Issue Date: Today
Select tickbox Approved and Save
Note: The Allowed Order types section can be used in conjunction with
the UIA option in Logistics
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-5 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
Administration (APN 1014) to allow certain order types depending on the
IA certificate.
Parameter 1728 provides additional settings based on the material type.
Com. Data Tab
Select: New
Address Administration (APN 53)
Type: P (phone)
Remarks: AOG DESK
Number: +41-752-6565665
Select: Save & New
Type: F (TELEFAX)
Remarks: Reception
Number: +41-752-6565000
Select: Save
You received the information that one of your aircraft is grounded in ZRH
and you need to get the part.
You search for an AOG desk in Zurich:
Clear the Code on the left hand search field
Open Extended Tab
Property: AO
Homebase: ZRH
Select: Search
Open Result tab
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-6 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
You can now view all addresses with homebase Zurich that have an AOG
Desk
Similar can be done with property "Supplier"
Aircraft Administration (APN 308)
2.2.2.1 Overview
The program Aircraft Administration is used to enter, view or modify data
about all aircraft operated or maintained by a company.
Aircraft Administration is also a good source of information of each
individual aircraft registered in AMOS.
The main information that a planner will want to verify or view in this
program can be found in the Daily Average Tab.
The daily average value is important for the calculation of future
maintenance events (forecasting) and is usually changed according the
schedule (e.g., winter or summer).
2.2.2.2 Path and interface
Path: Applications/Engineering/Aircraft/Aircraft Administration
Interface:
ButtonsThe following buttons are in Aircraft Administration.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-7 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
Button Description
Search Use to search for information.
Clear Use to clear all fields.
Licence required. Use to create a new aircraft
New
entry.
Save Use to save information.
Licence required. Use to start the aircraft
Archive/Deactivat
deactivation process. See the Aircraft deactivation
e
section for more information.
Licence required. Use to suspend or resume the
selected aircraft from a specific date. Opens the
Suspend / Resume Aircraft dialogue to enter the
date from which the aircraft is suspended and any
remarks.
When an aircraft is resumed, all maintenance events
Suspend/Resume affected will automatically have extension transfers
created. Former due values and new due values are
available in Maintenance Event Browser. Additional
information is also available in History Viewer.
Note: Maintenance events linked to this suspension
will have their ToGo values automatically extended
when the forecast is calculated.
Barcode Use to print a barcode for the aircraft.
Print Use to print an overview of all aircraft for which an
Airworthiness airworthiness certificate is defined.
Use to print a report in order to compare the status
Plate & Mod of the aircraft, what is actually installed and what
Report should be installed in accordance with the aircraft
configuration.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-8 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
AMOS makes this report based on the information
collected from Rotables Administration > Mod. Info
tab.
Exit Use to exit the program.
Aircraft filter panel
Use the Aircraft Filter Panel to search for aircraft using different filters. By
default the two criteria, General and A/C Type are displayed.
The Search panel is split into two sections:
▪ Filter - the exclusion filter.
▪ Select Data - a table showing the filtered results where you select an
entry to be displayed on the right side of the screen in the Data Section.
Aircraft Details tab
In this tab are a variety of tabs with different functions. For an explanation
of each tab, refer to the respective chapters. A tab highlighted in green
always contains information.
Main tab
In the Main tab, the basic data of the aircraft is entered/displayed.
Counter tab
The Counters tab is disabled when non managed rotables are loaded in
Rotables Administration.
The Counter tab gives you an overview of active aircraft and component
counters. It performs manual read-outs and counter resetting
Daily Average tab
The daily average value is important for the calculation of future
maintenance events and is usually changed according to the winter or
summer schedule.
Utilization tab
The Utilization tab shows the current data stored in Aircraft Utilization.
Rating tab/section
The rating information is displayed as a tab or a section, depending on the
program you are working in.
Weight and Balance tab
The Weight & Balance tab displays a version of the main screen of Weight
& Balance. For a detailed description of the different functions of this
program refer to Weight & Balance.
Communication tab
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-9 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
The Communications tab displays an overview of all communication data
concerning the aircraft. As each aircraft may have different methods of
contact, all necessary numbers and information are stored here.
Warranty tab
You can enter the warranty limits of the aircraft and initially installed
components into the Warranty tab. These entries are processed into
workorders for the aircraft or components only for customers whose
workorder supports this function.
Event Forecast tab
The Event Forecast tab offers a read-only version of the main screen of
Maintenance Forecast and cannot be modified. For more information
regarding this tab, refer to Maintenance Forecast.
History tab
The History tab lists all previous owners, previous registrations and other
details about the history of the aircraft. The History tab also includes data
from History Viewer. All the data displayed here has to be entered
manually. For example, just changing the owner in Aircraft Administration
or the registration in Code Transfer will not create an entry in the History
tab.
Limit./Spec. tab
This tab contains special values concerning the aircraft.
Plate and Mod Status tab
In this tab, you can enter the software status of specific components on
delivery of aircraft and then check the correctness of parts installed on the
aircraft.
Delivered Rotables tab
In this tab , you can enter the original components which were delivered
with the aircraft.
Remarks tab
Any remarks concerning the aircraft can be entered in this tab.
OEM Documents tab
When you import the AMM for this aircraft type from OEM Documents
Management > OEM Document Import tab, they will be displayed here.
2.2.2.3 Excercise
A new (used) aircraft has arrived in your company. Please enter the
following information about the new aircraft as follows.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-10 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
Main tab
Click on: New
A/C
JMB
Registration:
Description: AIRBUS 321-111 JMB
A/C-Prefix: HB
A/C- Type: 32S
A/C-Model: 321
A/C-Subtype: -111
Serial
5202
Number:
A/C- Owner: SWS
A/C-
SWS
Operator:
Object-Type: A (Aircraft)
MFG-Date: 01.Apr.2006
First Flight
26.04.2006
Date
Del- Date: Yesterday
Daily Hours: 10.5
Daily Cycles: 5.0
Select: Include A/C to ModControl
Click on: Save
You have defined the main information about the aircraft. You now wish to
define the limits and specifications of the aircraft.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-11 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
The aircraft has some limitations. Its landing category is 3B; it is not
approved for ETOPS flights but does have RVSM equipment installed.
Define this information as follows:
Limit./Spec. tab
Select from Available Limitations CAT 3B and move it to Aircraft
Limitations. Do the same for ETOPS N and RVSM Y
Click on: Save
Define the previous owner of the aircraft
History tab
Prev. A/C
F-ABCD
Reg.:
Operator &
Air Regional
Owner:
From Date: 27.07.2008
Until Date: -2d
Start-TAH: 8536
End TAH: 12356
Start-TAC: 2458
End-TAC: 5879
Click on: Save
Define the current total hours and cycles of the aircraft as follows
Utilization tab
Click on: Set Counter Values
Date/Time yesterday / 05:00
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-12 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. BASIC APNS
C (Flight
5879
Cycles):
H (Flight
12356:00
Hours):
AH (APU
2751:00
Hours):
Click on: OK
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.2-13 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
PUBLICATION MANAGEMENT
Overview:
Publication Management is used for the following:
- Announcing the arrival of new publications.
- Registering new publications.
- Editing existing documents.
- Archiving documents.
- Managing Media types, Revision types and Physical locations.
- Distribution and processing of documents such as service bulletins and
airworthy documents.
- Sending documents to other AMOS programs for further processing.
The main screen of Publication Management is split into two parts:
- Selection of Publications section: Allows you to search for documents
using various search filters.
- Data Section: Contains all details of a selected document.
AMOS also offers two other programs to help manage publications:
- Publication Acknowledgement is used to to confirm the receipt of a
document.
- Contact Publication Authors offers the possibility to contact an author
via e-mail.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-1 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
AMOS Process
Publication & OEM Library
Manage incomming documents / manuals and distribute them to the responsible department.
Ma nufacture / Autho rity
C omp any Manuals
Procedures AMM, EMM,
AD’s / SB’s Quality Memo’s Repair Approvals CMM IPC Task Card SB’s
Manuals MMEL, NDT, TSM
SGML or
S1000D
Each document has to be
activated after upload
OEM Documens Applies only for SGML Or
Mng. (APN 1524) S1000D doc’s
Contact
Conf. Publication Publication Mng.
Publication Author
Mng. (APN 566) (APN 565)
(APN 683)
Library
All Doc’s which Publication
are not SGML Revision Report
shall be stored in (APN 807)
the web-drive
Publication
OEM Documens
Location Report
Library
(APN 681)
(APN 1525)
Maintenance
08.01 08.02
Publication Scheduled Unscheduled
Acknowlegement Line Line
(APN 685) Maintenance Maintenance
„INLINING“ Link
Engineering
Worktemplates are linked between AMM &
03.04 Set the controlling OEM AMM
to AMM, IPC, SB, and Publication MP Aircraft
Modification and Taskcard for each AC in
can be printed attached Acknowlegement (APN 249) Link The Active Administration
Control <OEM Documents>
to the WO (APN 685) AMM to Taskcard (APN 308)
Worktemplate
Configuration Publication Management (APN 566):
2.3.3.1 Overview
Configure Publication Management is a simple set up program used in order
to define specific values according to various requirements.
Those entries serve as a basis for following programs:
• Publication Management
• Engineering Orders
• View/Edit Modifications
In Main Configuration tab we can define basic data concerning the different
publications, media and revision types as well as the physical locations.
Any kind of distribution lists and members thereof can be defined in the
Distribution tab.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-2 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Possible consequences and impact for document to be released to APN 63
can be outlined in the Documents tab
2.3.3.2 Main Configuration tab
2.3.3.3 Distribution Tab
The three tabs (Distribution List, Distribution Members and Distribution Filter)
offer you the possibility to create and maintain any kind of distribution lists and
members, as well as defining distribution filters which can be used in the tab
Distribution in Publication Management program.
2.3.3.4 Documents Tab
This tab is only for MOD. CONTROL related documents for reporting
purposes.
It allows you to enter any impact the document might have through
“Document
Assessment”.
2.3.3.5 Excercise:
Definition of company specific basic data for use in Publication Management
Before you can start to use the program Publication Management, you need
to enter some basic information as follows:
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-3 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Open "Configure Publication Management (APN 566)
Tab Main Configuration > Tab Publication Types
Select: NEW
Type: AFM_01
Description: AIRPLANE FLIGHT MANUAL
Requires Version Control: Yes (tick the box)
Select: SAVE
Tab Main Configuration >Tab Physical Locations
Select NEW
Physical Location: TED
Description: Technical Library ZRH
Select: SAVE
Definition of Publication Distribution Lists
Tab Distribution > Tab Distribution List
Select: NEW
Name: DL_TE AFM_01
Description: Distribution List for Tech Engineering
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-4 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
AFM_01
Select: SAVE
Tab Distribution > Tab Distribution Members
Right-click on the "Name" column header, then select "Show Column" and
then "User-Sign". This will show an additional column with the User Signs.
Double click in the field in the DL_TE AFM_01
yellow header and select
Select: NEW
Data Section: Please add the TE_01
(Technical Engineering_01)
Department
Select: SAVE
In List: Please tick the box next to TE_01 and
your user sign to your distribution list
Select: SAVE
Publication Management (APN 565)
2.3.4.1 Overview:
Publication Management is used for the following:
• Announcing the arrival of new publications
• Registering new publications
• Editing existing documents
• Archiving documents, e.g. all operator letters
• Managing Media-types, Revision-types and Physical locations for one or
multiple copies
• Distributing and processing of documents for example service bulletins,
airworthiness
documents
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-5 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
• Sending documents for example service bulletins to other AMOS programs
for further
processing.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-6 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
2.3.4.2 Publication Data tab
The Data Section on the right-hand side of the screen contains all the basic
information necessary
for the different publication types for example SB, AMM.
Here it is possible to view either the details of an existing publication or, enter
a new publication with New button.
2.3.4.3 Excercise:
Entering a Document into Publication Management Excercise
Publication Management is used to register and announce the arrival of new
publications which have been received by your Company.
Modification publications such as AD's and SB's, can then be forwarded on
through AMOS to the programs Engineering Orders (APN 852) and View /
Edit Modifications (APN 63).
Open Publication Management (APN 565)
Please enter an Airplane Flight Manual into AMOS as follows:
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-7 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Tab Publication Data
Select: NEW
Document No.: S6T320-01-00
Publi. Type: AFM_01
Subject: AIRPLANE FLIGHT MANUAL
Issued By: AIRBUS
Issue No.: 00
Issue Date: -5m
Revision No.: 00
Revision Type: Complete
Media Type: HC
Received By: TLC
Phys.Location: TED
Compliance MAN
Select: SAVE
sub tab Remarks
Remark: For SWS 32S only.
Select: SAVE
sub tab Aff AC-Types
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-8 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
AC-Type: 32S
AC-Model: 320
Select: SAVE
sub tab Publi. State
Current State: ACTIVE
Select: SAVE
Please write down your
Publication Number:
Location Tracking Excercise
Once you have entered a new Publication, you can then specify how many
copies of the Publication you have received, and where they will be physically
located.
This tab also allows the Technical Librarian to register any movement of a
document = if a document is lent to a person, if it is returned to the librarian or
if it transferred between departments/people within the company.
Location Tracking Tab
Select: NEW
Copy No: 01
Phys. Location: TED
Media Type: HC
Select: OK
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-9 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Publication Distribution Excercise
This Tab also allows the Technical Librarian to announce the arrival of a new
Publication to selected staff in your company.
Tab Distribution
Choose a copy to 01 I TED I HC I
distribute:
Select: ADD TO LIST
"Choose Distribution Members window" appears
Tab Distribution Lists
Select: Distribution list for Tech Engineering AFM_01
Select: OK
Select the line Select the Edit-Button and remove the tick
Acknowledgment Required
Select: DISTRIBUTE
You will receive a pop-up to tell you that the distribution was successful.
Select: OK
Revision of Publications Excercise
If you have received a new Revision of a Publication which you have already
registered in AMOS, you can revise it as follows:
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-10 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
**Before proceeding, please make sure that you have your Publication on
screen**
Tab Publication Data
Select: COPY
Change the S6T320-01-00A
Document No.:
Change the Revision 00 to 01
No. from:
Change the Revision -2w
date to
Select the tick boxes: Copy State
Copy
Locations
Copy References
Select: OK
Your new Document will appear on screen.
Tab Publication Data
Change the Revision TEMP REVISION
Type to:
sub tab Parent Publi.
Parent Publication Enter the number of your original Publication
Number
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-11 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
sub tab Publi. State
Current State: Active
Select: SAVE
Change the Current State of your original document S6T320-01-00 to
Superseded.
Tab Revisions has changed colors to green. What data has been added?
All the entries and changes done to the selected document can be seen here.
To view the details go to Tab Revision Info and select the Load Change
History.
Then select an entry - to view all details.
Connection to View / Edit Modifications (APN 63) and Engineering Orders
(APN 852)
For a basic assessment the sub tabs of the tab Document Assessment
together with Approval Control can be used. A more in depth assessment is
available in the program Engineering Orders (APN 852).
Modification publications such as AD's and SB's, can then be forwarded on
through AMOS, to the programs Engineering Orders (APN 852), for extended
assessment, and/or View/Edit Modifications (APN 63), for actively managing
and tracking all the modifications and related OEM documents.
This action can only be performed in the Document Assessment Tab with the
buttons "Release to Mod. Con." and "Assess in Eng. Orders" and only if the
following 2 preconditions have been met;
The same Document Type must exist in Basic Data Administration (APN
18) for use in the program View/Edit Modifications.
Publication type has been defined as "Requires Document Assessment" in
Configure Publication Management.
The chart here below shows how a document in APN 565 can be then
managed through different flows in order to finally have it available in APN 63
(NOTE: a document can also be created directly in APN 63)
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-12 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
As soon as a new document is entered into Publication Management, using
document codes defined in Basic Data Administration > Document
Management > Document Types table, AMOS can automatically create a new
document, based on the existing data, in View/Edit Modifications.
This is achieved if parameter 1420 is set to Y or if parameter 1420 is set to N
but the “document assessment” tab for that document has been activated in
APN 565.
However, the "Document not yet released from Publ. Management"
watermark, indicates, that the document is still being used in Publication
Management and cannot be changed yet in View/Edit Modifications.
The search criteria must be adjusted to include them and make them visible in
View/Edit Modifications.
Publication Management - advanced usage
In the following exercise we will return to Configure Publication Management
(APN 566) to learn how to set-up a distribution list with specific filter settings.
We will then enter a Modification related document and apply the advanced
filter before distributing the Document.
After we acknowledged the receipt of the Document, we release it to
Modification Control.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-13 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Configure Publication Management (APN 566)
Please create a new Distribution List and assign members as follows:
Tab Distribution > sub tab Distribution List
Name: 01_SB ATA CHAPTER
Description: 01_SB ATA CHAPTER
Tab Distribution > Tab Distribution Members
Please add some users and your user sign to your distribution list.
We will now add a filter to the distribution list to specify exactly which
Documents are applicable to the members of the list.
Tab Distribution > sub tab Distribution Filter
Select: NEW
Title: 01_SB 32S ATA 57
Type: SB
Description: SB's for ATA 57
Distrib. List: 01_SB ATA CHAPTER
Responsible: Double-click & select your login
Select: SAVE
Select distribution filter that you just created
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-14 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Filter Settings
ATA: 57
AC Type: 32S
Select: Add and Save
To demonstrate the application of the filter settings we have just created, we
will now enter an SB for a specified ATA Chapter and apply the Distribution
List.
Publication Management (APN 565)
Define a New Publication, Type SB
Tab Publication Data
Publi. Type: SB
Document No.: A320-57-20
Subject: WINGS - CENTER WING - INSPECTION OF
CENTER WING BOX LOWER PANEL BORE
HOLES
ATA-Chapter: 57
Issued By: AIRBUS
Issue Date: -5m
Issue No.: 00
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-15 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Revision No.: 00
Media Type: HC
Received by: DBAG
Phys.Location: TED
Compliance: REC
Select: SAVE
sub tab Aff AC-Types
AC-Type: 32S
AC-Model: 320
Select: SAVE
Please write down
your Publication
Number:
Now apply the Distribution Filter:
Tab Distribution
Select: Auto fill
AMOS will check all Distribution Lists that have one or more Filter Settings.
If a Filter setting corresponds to the information entered about the Document,
AMOS will automatically add the appropriate members.
Select: Distribute
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-16 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
You will receive a pop-up to tell you that the distribution was successful.
Select: OK
Publication Acknowledgement (APN 685)
2.3.5.1 Overview:
This program will list those publications that require you to acknowledge the
receipt of, either physically or electronically, after their distribution.
You may choose to use this program directly or the message that you receive
will also contain a link that will open the program preloaded for you to
process.
The types of document that may be controlled using this program could be:
- Service Bulletins
- Airworthiness Directives
- Modifications
- Company Process Guides
- Design Drawings
- AMM's
- IPC's
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-17 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Acknowledge a publication:
Open Publication Acknowledgement (APN 685)
Publication Acknowledgement Report:
This report includes information about the Selected document and the
members of the distribution list can be printed so that a physically signed
acknowledgement can be obtained. Workflow ID 40 - an email is sent if a
publication was either acknowledged or declined.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-18 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
There are various reports that can be extracted from Publication
Management:
Publication Report
This report contains the main details about the publication.
Publication Acknowledgement Report
This report contains the main details about the publication along with a
signature block.
Publication Summary Report
This report contains more detailed information about the publication.
Latest Revisions
This report shows list of the latest revisions available of each document.
Distribution State Report
This report will give an overview of all distribution members who have not
acknowledged the receipt of any documents distributed to them yet.
Multi Acknowledgement Report
A given user can acknowledge multiple publications within a single formSome
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-19 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Reports have single, dedicated APN’s:
Publication Location Report (APN 681)
Enter a physical location and view a report of the Publications which are
registered to
that Location. A Report of this information can then be printed.
Publication Revision Report (APN 807)
Generate a report which shows the revision status of the selected documents.
Filter by A/C type, location, etc.
2.3.5.2 Excercise:
Trainer will show how to search for a publication to be acknowledged and to
perform this action in APN 685.
Continue with the exercise:
Perform the acknowledgement of the SB you entered before (you can use the recorded
publicationnumber to quickly search it).
With the assistance of the trainer, check the result of the acknowledgment in the Distribution
tab ofyour publication in APN 565.
If you have the licenses (acknowledge of publication to
Workgroup/Department), the buttons Accept Publication and Decline
Publication will be available, when a publication, that was distributed to a
member that are part to the same Work Group or Department than me.If you
don’t have the licenses, the buttons will be disabled.
Your company wants to implement this SB on one or more aircraft. Therefore,
this SB must be available in APN 63 for further actions.
In order to perform the "Release to Mod. Control" action, the applicable
department needs first to perform an assessment.
In APN 565, ensure you display your publication A320-57-20.
Select the Tab Document Assessment
Select New
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-20 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Review All the tickboxes and the first four tabs.
You can enter and select, for information, all
the details that you think will be useful to make
your assessment complete and precise.
Shop/Line Doc A
NOTE: With the "Type of modification" tickboxes, you can define if the
document is applicable to the aircraft (this is the default selection) or a
specific component. This is very important and this information is
transferred to APN 63 after the release.
Select Save
Optionally, you can already define here the effectivity that can be anyway
edited or revised later in APN 63. To define the effectivity, you can use the
Effectivity sub-tab.
You are now ready to release the document to View/Edit Modifications (APN
63).
Select Release to Mod. Con.
Select YES & OK
Select (Open Modification Yes
Control)
Review the information transferred to APN 63.
NOTE: Approval Control is available for publications released to
Modification Control and for publications released to Engineering Orders
(APN 852).
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-21 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Approval Control for Documents and Publications - Overview (APN's
2110, 2111)
2.3.6.1 Overview
Approval Control allows to set condition(s) to allow an approval request on
documents. The involved APN's are:
Approval Control Configuration (APN 2111) - configure the conditions under
which an approval request will be needed and the relevant responsible to
approve.
Approval Control Board (APN 2110) - view/monitor/act on each specific
approval request
NOTE: Preconditions to use approval control for publications and documents
are:
Activate the related parameter(s):
-Parameter 1666 for View/Edit Modifications (APN 63)
-Parameter 1667 for Publication Management (APN 565)
-Parameter 1668 for Engineering Orders (APN 852)
Setting the related parameter to Y, will enable a tab (at the top of the screen)
and a button (at the bottom of the screen) both called "Approval" in the
corresponding APN.
Configure APN 2111 with the necessary rules, conditions and responsible to
approve
Ensure the person to approve has the proper licenses to respond to approval
requests
NOTE: When releasing a document to Modification Control from either APN
565 or APN 852, AMOS will check if a rule exists in APN 2111 and will not
allow to proceed with the release of the document to APN 63 unless the full
process (approval request + approval confirmation) is accomplished.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-22 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-23 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
2.3.6.2 Exercise
The trainer will show how to set Approval Control Configuration (APN 2111) in
order to allow an approval request for specific documents.
Ensure parameter 1667 is set to Y in APN 1442.
In Approval Control Configuration (APN 2111), build a rule to allow approval
request for documents having:
SHOP & LINE (i.e. “A”) or LINE document (i.e. “L”) in APN 63 main tab -->
Shop/Line doc field
AND
MANDATORY (i.e. "MAN") as compliance type in APN 63 main tab The result
should be the following:
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-24 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
In the tab "Who should approve?" define "Another User" as responsible. This
will give the chance to the user to define manually who should approve.
The trainees will need to close and re-open APN 63, if not already done, to
see the effect of setting parameter 1667 to Y.
In the following exercise the trainees will request an approval and the trainer
will then show how this is approved from APN 2110.
Contact Publication Authors (APN 683)
2.3.7.1 Overview
The program Contact Publication Authors allows the Technical Librarian to
contact Publication Authors via e-mail. The main purpose would be to check
with the author if there are any newer revisions available of the publication
that we currently have.
A history of any correspondence can also be retrieved.
There are 2 preconditions to use this program (additional requirements for the
CMM tab are explained later):
The author of the publication, e.g. Boeing or Airbus, must have the property
PA, Publication Author, assigned to the address code in the program Address
Administration (APN 53).
The publication type must be marked as Requires Version Control when
defined in Configure Publication Management (APN 566).
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-25 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
NOTE: To see the publication of your selected author, you need to set a
revision date in Publication Management (APN 565)- tab Publication Data.
2.3.7.2 CMM File Tab
Preconditions:
Address used in APN 565 as "Issued by" author, must be existing in APN 53
with the same code used in CSV-file.
Address must have a property PA . Additionally the field "Value" in this
property must contain the address code.
Address must contain at least one email address in "Com. Data" Tab.
"Document No.", "Publi. Type" and "Issued By" in APN 565 must be filled and
the same as in the csv file.
The CSV-file must follow the pre-defined structure.
Your trainer will show the behavior of the tab. NO EXERCISE
Create a publication type "CMM" in APN 566 that "Requires Version
Control".
In APN 53, ensure that address "81205" has property PA with value
"81205".
In APN 53, add an email address for 81205 in Com. Data Tab, "Mail:"
field.
In APN 565, create a CMM publication "21-12-34" with Rev.17, issued by
81205, compliance MAN
Save on the desktop the csv file stored in webdrive, "Publications" folder
Go to APN 683, Tab CMM File, load the file and process.
NOTE: the "Author" field is optional as it is for filtering the results of the file
processing.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-26 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
In "Contact Form" tab, the user can prepare an email. Clicking on "Send"
in the "CMM file" pane, would send emails to the publication authors for
which the "Select" tickbox has been selected in the CMM tab
Publication Management Reports (APN 565)
2.3.8.1 Overview
There are various reports that can be extracted from Publication
Management:
Publication Report
This report contains the main details about the publication
Publication Acknowledgement Report
Although publications can be acknowledged electronically within AMOS, a
report which includes information about the selected document and the
members of the distribution list can be printed so that a physical
acknowledged signature can be obtained.
This report is available from the programs Publication Management and
Publication Acknowledgement.
Latest Revisions
Generate a report which shows the latest revision available of all documents
(in accordance with the chosen criteria).
Distribution State Report
This report will give an overview of all distribution members who have not
acknowledged the receipt of any documents distributed to them yet.
Multi Acknowledgement Report
A given user can acknowledge multiple reports within a single form.
Publication Location Report (APN 681)
Enter a physical location and view a report of the Publications which are
registered to that Location. A Report of this information can then be printed.
Publication Revision Report (APN 807)
Similar to the Latest Revision Report but with additional search criteria and
filters. Tab Further Processing
Further Processing Report (+ Plain)
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-27 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Shows Responsible, Verfication Sign, Approval Sign, Department, Due Date,
Closed Date and Remarks from the tab.
OEM Documents Management (APN 1524)
2.3.8.2 Overview
This program is used to upload the OEM documents into AMOS and de-
/activate different revisions for either the fleet or a single aircraft.
There are 2 different ways to upload them into AMOS:
Load one file after another - short but very high impact on the server
Queue the files in the program and import them as one - heavy impact on the
server but can be scheduled by the AMOS Administrator.
NOTE: For some OEM documents, a classification and an effectivity type can
be defined.
The classification, is for information only and will not restrict the possibility to
map an OEM document to the relevant A/C tail sign.
The effectivity type, is used to define how the imported document was defined
by the OEM and will be used by AMOS whenever it has to choose the
applicable document to be printed when they are linked to a TC or WO.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-28 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Use the file: Sample_NDT_FlyingShark.zip copy from Publication Foder in
amos webdrive
Open OEM Documents Management (APN 1524)
Tab OEM Document Import
OEM Doc Type NDT
A/C Type 32S
Sned and import on Server - Open
click on
This action will analyze the file and save it on the server.
NOTE: To send the file to the server will save a lot of time during the
upload.
OEM AIRBUS
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-29 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
Effectivity Type Manufacturer Serialnumber (MSNBR)
Select Import
This will take some minutes (> 5 Min)
There could be a message "Query runs longer ) - ignore it.
Confirm the message that will tell you if the upload was successful.
Switch to the tab Overview.
The NDT should be shown here - if not select Reload.
Select the line of the NDT and Activate
Select Immediate Activation
Click on OK
If necessary it can also be deleted.
Switch to the tab Aircraft Mapping and select NDT from the drop down menu.
A/C Type 32S and Searc
Multiselect Aircraft A323-A352
Select button Map OEM Document
Select The uploaded document
Select OK & OK
With this you assigned the NDT to the selected Serial Numbers of the 32S
fleet.
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-30 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
In Aircraft Admin (308) is a tabsheet for each tailsign OEM Documents, which
enables the Mapping of different OEM Documents for the selected Aircraft.
OEM Documents Library (APN 1525)
With OEM Documents Library, you will be able to display all imported OEM
documents that will be available for linking to Work Templates and Work
Steps.
You can handle the multiple revisions and compare the content. It will show
the content of the loaded OEM Document in Detail.
ONLY FOR TRAINER
In APN 1524 the tab Overview is still opened from the former
exercise. Select the uploaded NDT
Select OPEN
AMOS automatically opens OEM Documents Library (APN 1525) and displays the
selected OEM document.
To display the content of a chapter, sub chapter or single entry, navigate to the item and
double-click on the entry. On the right side the content is displayed.
To print the selected item use the button Report Generator.
MEL Manual Administration (APN 273)
2.3.10.1 Overview
A Minimum Equipment List (MEL) manual is based on the Master Minimum
Equipment List (MMEL) which is approved by the responsible Aviation
Authority.
The MMEL is defined per aircraft model and is a list of systems, instruments
and equipment that may be inoperative for further flight.
The MEL is prepared by the operator with reference to the MMEL and used
by aircraft dispatcher to verify under what conditions the airplane can be
released and under which operational restrictions.
MEL can be made available in AMOS through different processes:
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-31 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: CONTENT 2. 3 PUBLICATION MANAGEMENT
complete manual creation in MEL Manual Administration (APN 273)
Import through Airbus MMEL Import (APN 1070) if you have a MEL in SGML
format.
Import through OEM Documents Management (APN 1524) if you have a MEL
in supported format.
Import through Data-Transfer (APN 261) if you have space text delimited
format
CODE OF TRAINING PAGE SPH: 01 SSĐ: 00
COURSE AMOS-SP-EP-MAN 2.3-32 DATE: 30-Nov-2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
MODIFICATION CONTROL
Overview
This program is used to manage and control the SB/AD modification status. Define
the compliance requirements.
View/Edit Modifications (APN 63) is used for the following:
- Entering new modification documents and assigning them to an aircraft or
component.
- Viewing documents for informational purposes.
- Modifying documents.
- Deleting a document.
Engineering Orders (APN 852) is mainly used for third party maintenance, where
labour and material costs can be set up and managed. You can use it to create
hierarchical structures where you can collect different engineering orders in an
Engineering Order Cover. This is useful when you have several Service Bulletins
(SBs) affecting different areas of the aircraft airframe or component modifications.
Modification Status (APN 231) is used to Printable Version Modification Status
Component Modification Status (APN 639) is used to Printable Version Component
Modification Status
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-1 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-2 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
AMOS process
03.04 – Modification Control
Manage and control the SB/AD modification status. Define the compliance requirements.
Authority
Manuf. /
Inte rnal Vendor
Start
SB AD
Campaign Documents
Re-Approve
03.08 Engineerin g 01.08
End
Pub lica tion s & Perform Yes Ord er Yes Engineerin g O rders
Approval App roved No
OEM Libra ry necessary? Control
(APN852)
End
No 1. Release appr ove d
EO to A PN63 (- - -
Yes dotted line)
Modification Activity KPI Analyzer
End
No View/Edit OR
Engineering
(APN640) (APN1120)
Modificatio ns
(APN63) 2. Release DOC in
APN fo r Pl anning
(solid line)
Modificatio n S tatus 04.06
Aircraft
(APN231) Reporting-Back
03.09 Work 03.15
Instructions Softwa re
Aircraft or Authoring Manag ement
On Wing
Componen t
Componen t 03.05
On/Off Configuration
Modificatio n S tatus Comp
Wing Manag ement
(APN639)
Planning
04.01
Plan ning
Forecast
Off Wing
Maint.
08.01/08.03
Schedu led
Maintenan ce
Material
06.02 05.03
Goo ds Repair &
Receiving Exchange
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-3 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
View/Edit Modifications (APN 63)
2.4.3.1 Overview
The AMOS Program View/Edit Modifications is used for the following purposes:
- To enter, edit and revise modification documents.
- To assign modification documents to the applicable aircraft registrations or
components.
- Specify the qualifications, man hours, parts and any other information required
to perform the document.
- Extended search filter to view information about specific modification
documents.
To be able to perform any function within the program, specific access rights are
required.
There are several ways a document can be entered in APN 63:
- releasing a publication from APN 565, Publication Management
- releasing an EO document/tree from APN 852, Engineering Orders
- creating a document directly in APN 63, View/Edit Modifications
2.4.3.2 Execice how to enter a Modification Document
The purpose of this exercise is to help you to become familiar with the layout of the
program and its basic behavior. Please proceed as follows:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-4 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Go to View/Edit Modification (APN 63)
Main Tab
Select New
Document No: A320-23-1277-01
Doc-Type: SB
COMMUNICATIONS - ANTI HIJACK CAMERA
Subject: MONITORING. INSTALL UNIT FOR A COCKPIT
SURVEILLANCE SYSTEM.
Issued by: AIRBUS
Issue Date: -3m
Revision Date/Rev: No Rev Date / 00
Receiving Date: -3m
Effective Date: -2m
ATA-Chapter: 23-72
Shop/Line Doc.: A
Type of Change: Z (Design/Major Change)
Compliance Type: REC (Recommended)
Method of Compl. MO (Modification)
Type of modification: Aircraft/Airframe modification
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-5 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Document with Yes (select the tick box)
hardtime limit:
Select Save
Signoff-Tree Tab
Select the tickbox: "Document Included in Signoff-Tree (= document
write-off logic)"
Select Save
Effectivity Tab
Select New Effectivity
A/C Type: 32S
Select Next
Serial Number Type: Serial Number
Serial Number Ranges
Number From: 003005
Number To: 004669 (include)
Select Finish
Select the line of effectivity that you have just entered.
Revisions Tab in the lower section
Select De-/Activate
Select Yes
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-6 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Ensure the line of effectivity you previously defined is selected.
Effectivity tab - sub tab Time Requirement - sub tab Editor
Select New (in the sub tab editor )
The "Time Requirement Wizard" dialogue box will appear.
1. Mode Selection
Select: Basic Definition
Select Next
2. Thresholds
Select: Before
Dimension: D (Calendar Days)
Due at: +1y
Select Finish
The time requirement is still in edit mode and needs to be activated to be
productively used. To activate your time requirement, proceed as follows:
Select Activate
NOTE: You can create a general time requirement that will be valid for all the
effectivity rows you defined, or, for each effectivity, use its specific Time
Requirement sub-tab to create individualized time requirement. icon
appears on effectivity line level in case of individualized time requirement.
Effectivity Tab - sub tab Properties (alternatively, you can add the remarks in
the "Report Back" column in the effectivity tree panel).
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-7 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Next to "Reporting Remarks
Back Rem...",
select:
Please enter the Ensure that all parts have been correctly recorded
following text: through label booking on the parent workorder.
Select OK
Select Save
WORK TEMPLATE NOTE: you can create a general work template that
will be valid for all the effectivity rows you defined, or, you can create an
individual Work Template for each effectivity by using its specific Work
Template sub tab.
In case an individualized Work Template is created and activated,
icon appears on relevant effectivity line and this will override the general
Work Template (if existing).
Select the tab Effectivity
Select the Title Line in your Effectivity Definition:
select the tab Work Template
Select New (in the sub tab Work Template )
1. Header Information
ATA Chapter 23-72
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-8 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Prio 2
Select Next
2. Task Classifications
Select Next
3. Add Work Step
Select Individual
Headline: @STANDARD_HEADLINE@
Description Text: @STANDARD_TEXT@
Select Next
4. Meta Data
Select Next
5. Work Step Ref./Class.
Select Next
6. Part Request Tmp./ Phase
Select Add
23-1277-15
Part Number: (the Part Number is "unknown", this is
common for a Modification Document and
allowed by AMOS)
Qty: 1
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-9 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Required (%): 100
Select OK
Select Next
7. Resource Request
Select (from drop Facility
down list):
Select New
Resource Type: HANGAR
Property Type: (leave it empty)
Duration: 22:00
Select OK
Select (from drop Staff
down list):
Select New
Select: Scope
Planning Qualification: B1
Total Hours: 20:00
Select OK
Select: Staff
Select New
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-10 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select: Scope
Planning Qualification: B2
Total Hours: 01:00
Quantity: 1
Select OK
Select (from drop Aircraft
down list):
Duration 22:00
Select Ok and Finish
All of the information you have just entered in the wizard will appear in the
Work Template Tab.
Select Activate
More Info tab
Est. Manhours 22.00 (Decimal entry requested)
Occasion H (HMV - Heavy Maintenance)
Requesting TE_01
Department
Est.labour Costs: 250 (this field can be used as calculator, i.e. for 5
hours at 50 CHF you can type 50*5)
Est.Material Costs: 2000
Select Save
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-11 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Markings Tab - Document Affects Section
Select Add
Select AOM
Select OK
Select Save
Tab Modification Plan
Select Campaign
Start Date +2w
End Date +1y
Select Save
Main tab
Section Document assessment (bottom page)
Change status to R (Released)
Select Save
Status Tab - Assign View Tab
AMOS will present a coloured block for each Aircraft that falls within the
Document Effectivity
Select:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-12 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select:(from drop down Open
list)
Select
(assign to all aircraft within effectivity)
All Aircraft will be pre-assigned with the Status of Open.
Select
The "Initialise Documents" screen will appear for you to cross check the
assignment information. You can also enter an assignment reason if you
wish.
Select OK
Print a report that can be used for review and printed for approval.
Select Reports
Report Modification Control
Select OK
Review the report and how all the different details have been used for the
report that can be printed or saved (e.g. in pdf).
Press Cancel to exit.
With the assistance of your Trainer, find the Aircraft Registration AAA in the program
Maintenance Forecast (APN 1844). Can you find the Document you have entered?
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-13 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Please open up Modification Control (APN 63) again and select the document you
just created. Select the tab Effectivity.
The worktemplate in APN 63 is now in a read only mode. Why? How can you revise
it if needed?
2.4.3.3 Execice Component Document with Revision
Your Company has received 1 Service Bulletin from the Aircraft Manufacturer and 1
Service Bulletin from the Component Manufacturer. It is your task to enter these
Documents into the View/Edit Modification program.
The performance of the Honeywell document will fulfill the requirements of the Airbus
document and therefore, we can link them together in a so called "Signoff-Tree".
In the following exercise, you will enter these 2 Documents and learn how to create
the Signoff-Tree.
Enter the Honeywell Component (on-wing) Service Bulletin IGV-3886188-01 into
View/Edit Modification (APN 63)
Main Tab
Select New
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-14 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Document No: IGV-3886188-01
Doc-Type: SB
APU IGV ACTUATOR - INSPECTION OF
Subject: ELECTRICAL CONNECTORS
Issued by: 99193
Issue Date: -8m
Revision Date / Rev: No Rev Date / 00
Receiving Date: -8m
Effective Date: -8m
ATA-Chapter 49-20
Shop/Line Doc.: A
Type of Change: Z (Design / Major Change)
Compliance Type: MAN (Mandatory)
Method of Compl. IN (Inspection)
Type of Modification: Component modification
Document with Yes (select the tick box)
hardtime limit:
Replacement of No (de-select the tick box - if needed)
component required:
Select Save
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-15 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Effectivity Tab
Select New Effectivity
Partnumber 3886188-2
Select Next
Tick All Serial Numbers
Select Finish
Select the line of effectivity that you have just entered.
Tab Revisions
Select De-/Activate
Select Yes
Ensure the effectivity line you have just defined is selected
Time Requirement Tab - Editor Tab
Select New (in the Editor tab)
The "Time Requirement Wizard" dialogue box will appear.
1. Mode Selection
Select: Basic Definition
Select Next
2. Thresholds
Select: Before
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-16 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Dimension: H (Flight Hours)
Due at: 30000
Select Finish
Select Activate
Add Reporting Back Remarks to warn the user upon Report Back with this
message:
"Ensure that the WO clearly states if findings were found or not. Do not
report back in case of missing information and inform the relevant
department".
Do not forget to save your entries.
Main tab
Section Document assessment (bottom page)
Change status to R (Released)
Select Save
Enter a NEW document for the AIRBUS Aircraft Service Bulletin A320-49-095-01
Main Tab
Document No: A320-49-095-01
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-17 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Doc-Type: SB
APU IGV ACTUATOR -INSPECTION OF
Subject: ELECTRICAL CONNECTORS
Issued by: AIRBUS
Issue Date: -8m
Revision Date / Rev: No Rev Date / 00
Receiving Date: -8m
Effective Date: -8m
ATA-Chapter 49-20
Shop/Line Doc.: A
Type of Change: N
Compliance Type: MAN (Mandatory)
Method of Comp.: IN (Inspection)
Type of Modification: Aircraft/Airframe Modification
Document with hard Yes (select the tick box)
time limit:
Select Save
Effectivity Tab
Select New Effectivity (this will open a wizard)
A/C Type 32S
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-18 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select Next
Serial Number Type: Serial Number
Select tickbox All Serial Numbers
Select Next
A/C Manufactured -10y
after:
Select Next
Select: Add New Rule then OK
Your trainer will
explain how to build
the following rule to
refine the
applicability
IMPORTANT NOTE: Do not change the original
depending on the
position of the blue "true/false" blocks as their
APU P/N installed
position in the Part Installation Dependency yellow
(NOTE: to have a block is relevant.
bigger area to
(PN = 3800708-1)
work with, you can
select Undock
View. Remember
to press Dock
View to go back to
the original
window)
Select Validate Rule then OK (correct the rule in case of
errors)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-19 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select Save Rule Set
Select Next
Step 5 of the Wizard. The Applicability should now
show only 15 affected airplanes without the grey
highlighting, i.e. the only ones manufactured in the
Review: last 10 years and with the applicable APU P/N
installed.
Select Finish
Select the line of effectivity that you have just entered.
Tab Revisions
Select De-/Activate
Select Yes
Ensure the line of effectivity you previously defined is selected.
Effectivity Tab - Time Requirement Tab - Editor Tab
Select New
The "Time Requirement Wizard" dialogue box will appear.
1. Mode Selection
Select: Basic Definition
Select Next
2. Thresholds
Select: Before
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-20 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Dimension: H (Flight Hours)
Due at: 30000
Select Finish
Select Activate
NOTES ON EFFECTIVITY FRAMEWORK:
As we have seen above, with the effectivity framework, you can define rules and
restrictions on the effectivity, to finally have the needed applicability.
You can also define Child Effectivities (New Child Effectivity button), meaning that
after you create a main (or "parent") effectivity, you can add as many child effectivity
rows below the parent, to fine-tune the definitions of your effectivities as needed.
In case you use Child Effectivities, please consider the following:
A Child Effectivity will always inherit Restrictions and A/C model from the parent
Rules and Serial Numbers definition must be entered on the child level. If you have
rules or Serial Numbers defined on the "parent" level, they won't be considered
anymore as soon as a child effectivity is existing for that row.
RULES:
In addition to the rule that we used in this exercise (Part Installation Dependency)
other functions are available:
"Part Units Installation Dependency": same as "Part installation dependency" if
applicability depends on a quantity of (not)installed units >1
"Rotable Installation Dependency": if applicability is depending on a specific
installed/not-installed rotable SN
"Pre / Post Modification": if applicability depends on modification status of another
document
2.4.3.4 Execice Signoff Tree
Now that both Documents have been entered, you can define the Signoff Tree as
follows:
Document A320-49-095-01
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-21 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Signoff-Tree Tab
In the Signoff-Tree table put the IGV document.
Document No: Double-click to open the search dialogue
Enter IGV-3886188-01
Select Search
Select your document
Select OK & Save
The search dialogue helps to refer to the correct Revision of the selected
document.
The IGV document is now shown in the tree of the Airbus document.
Document IGV-3886188-01
Signoff-Tree Tab
"Document included in Signoff-Tree ( =
Select tickbox: document write-off logic)"
Select Save
In this way we have included the IGV SB in its own signoff tree, since this is the
document that will be eventually performed without relying on any other documents.
NOTE: A document in APN 63, must have a defined signoff-tree in order to be assigned to an
A/C or to a component.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-22 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
This is done by either ticking the mentioned box (for documents that will be performed)
or by listing all the required documents in the Signoff-tree table or both, as applicable,
depending on the tree structure.
As the IGV SB is the Document that will be physically carried out, we will now define
the Work Template information of this Document, and assign it to the relevant
Component.
Make sure the IGV-3886188-01 SB is loaded
Effectivity tab
Select: The Effectivity row you created
Work Template Tab (for the selected effectivity)
Select New
ATA Chapter: 49-20
Prio: M
Select NEXT until you reach step 3 - Add Work Step
Work Step Creation Individual
Options:
Headline: @STANDARD_HEADLINE@
INSPECTION OF ELECTRICAL CONNECTORS
Description Text: IMPORTANT NOTE: CLEARLY STATE ON THE
WO ACTION IF THE INSPECTION REVEALED ANY
FINDINGS OR NOT.
Select Next until you reach Step 7: Resource Request.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-23 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select New (Staff)
Select: Scope
Planning Qualification: B1
Total Hours: 01:00
Time Offset: 01:00
With the time offset, we can shift the starting time of the selected resource
by the entered time offset value (e.g. you must let the engine cool down in
order to then be able to use the borescope tool without causing damage to
the equipment).
Select New (Aircraft)
Duration 3:00
Select OK
Select Finish
Set your Work Template to Active.
Main tab
Section Document assessment (bottom page)
Change status to R (Released)
Select Save
Status Tab - Assign View Tab
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-24 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select
Select: Open
Select: 3886188-2 / 01-2422
Select
Initialise Documents: Cross check the "Expected" date.
Select OK
Review the Airbus SB status, to see how the signoff tree definition is affecting the
involved documents.
Later in this exercise we will create a Revision of the Document issued by Honeywell
(IGV-3886188- 01).
Before we revise the Document, we will "perform" it on the applicable Component.
This will allow you to see the full revision process, as well as the flow of an Aircraft or
Component "On-Wing" Document through AMOS.
Please note that this is the shortened process flow, and not the full "planning" flow
which would normally be performed.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-25 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
2.4.3.5 Flow of an Aircraft & Component "On-Wing" Document through AMOS
Please select your Honeywell Document IGV-3886188-01 we will issue the carry out
Workorder directly from View/Edit Modifications.
Status Tab - Assign View Tab (Make sure that "Info" is selected)
Please find P/N: 3886188-2 with S/N: P-4722 (A323)
Left mouse click on the yellow assignment box for this P/N & S/N.
In the overview of all document pendings within Signoff-Tree section select
the line containing your "event"
Select Issue W/O
Select Yes
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-26 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
You will now see the Workorder number in the corresponding column.
Write down your WO
number:
Select OK to close the dialogue box.
View the Workorder in the program Workorder (APN 1418). You will see that
AMOS has automatically referenced both Documents from the Signoff Tree
on the Workorder.
You have physically performed the SB so you need to "Close" the Workorder as
follows: APN 1418 (Workorder)
Select
1. Action
Performed Date: Today
Time: Now
Headline: SB IGV-3886188-01 PERFORMED
Action: SB PERFORMED. NO FINDINGS.
Performed Sign: Your user sign
Select Next until you reach step 3 - Close W/O
3. Close W/O
Closing Station: ZRH
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-27 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Closing Date: Today
Closing Time: Now
AMOS will enter the corresponding flight leg information.
Approval No. Confirm suggestion
Closing Sign: Your user sign
Select Finish
2.4.3.6 Execice For Report Back Document
The last step in the Document flow is to "Report Back" to AMOS that the Document
has been performed. We will report back the document as follows:
Please open the program Reporting Back Maintenance Event (APN 280):
Click on the little arrow next to: Exclude Documents, the section will open,
and will be renamed to
Include Documents
Document No: IGV-3886188-01
Select: Search
Your Document will appear in the middle of the screen. Please select it.
Select Report Back
1. Information Text
Any text entered into the Remarks Tab (Black text) or Reporting Back
Message (Red text) of the Document will appear here.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-28 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select the tick box to confirm that you read the message.
Select Next
2. Performed Data
C (Flight Cycles): Please check the value.
H (Flight Hours): Please check the value.
D (Calendar Days) Today
Write any text that you would like to record in the
History of this document accomplishment, for
example:
Report Back
Remarks:
"Dirty finger prints are complete and stating NO
FINDINGS"
Select Next
3. Next Due Events
You should see the event status Closed. Why?
Select Finish
Select OK
You will receive a pop-up telling you that the document has been
successfully reported back
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-29 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select OK
Now view the Status Tab of your Document in the program View/Edit
Modifications.
Check the status of the Airbus SB. How has it been affected by the reporting back of
the Honeywell SB?
With the assistance of your trainer find your document in Maintenance Event
Browser (APN 2151). Can you find the remarks you entered during the Report Back
of your component SB?
2.4.3.7 Execice Document Revision
The Document you have just performed on one Component is Revision 00.
We have now received Revision 01 and therefore we need to update the Document
Revision level in AMOS.
Start by finding your Honeywell SB IGV-3886188-01 in View/Edit Modifications.
Main Tab
Select Copy
The Copy Document screen will appear
Revision: 01
Rev. Date -1w
R.State R (Released)
AMOS has automatically selected some check boxes on the "Copy
Document" screen. Cross check this information and add the following
check boxes:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-30 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Signoff-Tree
Copy to Higher Documents
Reporting Back Message
Effectivity Options - Time Requirement
Select Copy
Select Exit - Show New Doc
To continue with the revision process, we must now update the Status Tab of Revision
01 as follows: Make sure that Revision 1 is loaded
Status Tab - Assign View Tab
Revision 00 of the Document was performed and Closed on P/N: 3886188-
2 with S/N: 01-2422.
AMOS does not automatically copy the Status from one document
Revision to another because it could be that you have to perform the new
Revision on all Components. The assigning of a Status is therefore left to
the AMOS user.
We can however force AMOS to pull through a performance history if we
need to do so as follows:
Select Advanced
Select Copy Document Assignments
Copy Assignments
from Document No: IGV-3886188-01
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-31 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Double click on the field and be sure that Revision 00 is selected.
Select: Closed -> See prev. Docstatus
Select Copy
The Component that was performed under Revision 00 now has the status
of "See prev. Docstatus"
Finally we will complete the Replacement information as follows
Signoff-Tree Tab - Replacement Information Table
Repl.-Code: S (Supersedes)
Document No: IGV-3886188-01
Once you have entered the Document number, you need to be careful that
Revision 00 is selected.
Double click in the Document No field and select Rev 00.
Select Save
AMOS will ask if you would like the Repl.-Code SB entered into the
Superseded Document revision 00.
Select Yes
Select your Revision 00. You will now see that a red watermark appears on
screen notifying you that the Document is Superseded.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-32 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
2.4.3.8 Approval Control for Documents and Publications (APN's 2110, 2111)
Approval Control allows to set condition(s) to allow an approval request on
documents. The involved APN's are:
Approval Control Configuration (APN 2111) - configure the conditions under which an
approval request will be needed and the relevant responsible to approve.
Approval Control Board (APN 2110) - view/monitor/act on each specific approval
request
NOTE: Preconditions to use approval control for publications and documents are:
Activate the related parameter(s) (APN 1442):
-Parameter 1666 for View/Edit Modifications (APN 63)
-Parameter 1667 for Publication Management (APN 565)
-Parameter 1668 for Engineering Orders (APN 852)
Setting the related parameter to Y, will enable a tab (at the top of the screen) and a
button (at the bottom of the screen) both called "Approval" in the corresponding APN.
Configure APN 2111 with the necessary rules, conditions and responsible to approve
Ensure the person to approve has the proper licenses to respond to approval requests
NOTE: When releasing a document to Modification Control from either APN 565 or
APN 852, AMOS will check if a rule exists in APN 2111 and will not allow to proceed
with the release of the document to APN 63 unless the full process (approval request
+ approval confirmation) is accomplished.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-33 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
The following setup will be performed by the trainer only!
- Ensure parameter 1666 is set to Y in APN 1442.
- In Approval Control Configuration (APN 2111), build a rule to allow approval
request for documents having:
- SHOP & LINE (i.e. “A”) or LINE document (i.e. “L”) in APN 63 main tab -->
Shop/Line doc field
AND
- MANDATORY (i.e. "MAN") as compliance type in APN 63 main tab The result
should be the following:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-34 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
- In the tab "Who should approve?" define "Another User" as responsible. This
will give the chance to the user to define manually who should approve.
- The trainees will need to close and re-open APN 63, if not already done, to see
the effect of setting parameter 1666 to Y.
- In the following exercise the trainees will request an approval and the trainer
will then show how this is approved from APN 2110.
2.4.3.9 Exercise build the Sign-Off Tree
Your Company has received 1 Service Bulletin and 2 Airworthiness Directives. It is
your responsibility to enter these Documents into View/Edit Modifications (APN 63)
and to build the Sign-Off Tree.
The purpose of this exercise is for you to further understand the definition of Sign-off
Trees.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-35 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
CLOSE and REOPEN APN 63 to make sure approval control is enabled. Please enter
the 3 documents and build the Sign-off Tree correctly.
Document 1 - SB issued by Airbus
Document No: A320-57-1133-01
Doc-Type: SB
WINGS - INBD FLAP INSPECT THE
Subject: TRUNNION AND SLIDING PANEL
Issued by: AIRBUS
Issue Date: -5m
Revision Date/Rev: No Rev Date / 00
Receiving Date: -5m
Effective Date: -5m
ATA-Chapter: 57-51
Shop/Line Doc.: L LINE MAINTENANCE DOCUMENT
Type of Change: N
Compliance Type: MAN (Mandatory)
Method of Compl. IN (Inspection)
Type of Modification: Aircraft/Airframe modification
Document with Yes (tick the box)
hardtime limit:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-36 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select Save
Effectivity Tab
Select New Effectivity
A/C Type: 32S
Select Next
Serial Number Type: Serial Number
Serial Number Ranges
Number From: 003005
Number To: 004669 (Include)
Select Finish
Select the line of effectivity that you have just entered.
Tab Revisions
Select De-/Activate
Select Yes
Define the time requirement: this document has to be performed before
50000 Total A/C Hours.
Do not forget to activate your Time Requirement.
Main tab
Section Document assessment (bottom page)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-37 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Change status to R (Released)
Select Save
Document 2 - AD issued by DGAC
Document No: F-2011-139-01
Doc-Type: AD
Subject: WEAR DAMAGE TO INBOARD FLAP TRUNNIONS
Issued by: DGAC
Issue Date: -5m
Do not forget to
activate your Time No Rev Date / 00
Requirement.Revisi
on Date/Rev:
Receiving Date: -5m
Effective Date: -5m
ATA-Chapter: 57-51
Shop/Line Doc: L
Type of Change: N
Compliance Type: MAN (Mandatory)
Method of Compl. IN (Inspection)
Type of modification: Aircraft / Airframe Modification
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-38 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Document with Yes (tick the box)
hardtime limit:
Select Save
Effectivity Tab
Select New Effectivity
A/C Type: 32S
Select Next
Serial Number Type: Serial Number
Serial Number Ranges
Number From: 003005
Number To: 004669 (Include)
Select Finish
Select the line of effectivity that you have just entered.
Tab Revisions
Select De-/Activate
Select Yes
Define the time requirement: this document has to be performed before
50000 Hours.
Main tab
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-39 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Section Document assessment (bottom page)
Change status to R (Released)
Select Save
Document 3 - AD issued by FAA.
Document No: 2011-04-06-01
Doc-Type: AD
A320 FAMILY INBD FLAP INSPECTION OF
Subject: TRUNNION AND SLIDING PANEL
Issued by: FAA
Issue Date: -5m
Revision Date/Rev: No Rev Date / 00
Receiving Date: -5m
Effective Date: -5m
ATA-Chapter: 57-51
Shop/Line Doc.: L
Type of Change: N
Compliance Type: MAN (Mandatory)
Method of Compl. IN
Type of modification: Aircraft / Airframe Modification
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-40 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Document with Yes (tick the box)
hardtime limit:
Select Save
Effectivity Tab
Select New Effectivity
A/C Type: 32S
Select Next
Serial Number Type: Serial Number
Serial Number Ranges
Number From: 003005
Number To: 004669 (Include)
Select Finish
Select the line of effectivity that you have just entered.
Tab Revisions
Select De-/Activate
Select Yes
Define the time requirement: this document has to be performed before
50000 Hours.
Do not forget to activate your Time Requirement.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-41 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Main tab
Section Document assessment (bottom page)
Change status to R (Released)
Select Save
Now build your Sign-off Tree accordingly:
REMEMBER: The SB issued by AIRBUS is the one that will be physically performed.
Because we are going to perform the SB issued by AIRBUS, we want to add the Work
Template information to that Document, and assign the status of "Open" to the
corresponding Aircraft Registrations as follows:
Ensure that you have loaded the A320-57-1133-01 SB.
Tab Effectivity - select the Title entry for your effectivity
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-42 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Work Template Tab
Select: New
Header Information
ATA Chapter: 57-51
Prio: M
This is an Individual Work Step:
Headline: @STANDARD_HEADLINE@
Description: @STANDARD_TEXT@
Resource Request
Select: Staff
Select: New
Select: Scope
Planning qualification: B1
Total Hours: 24:00
Quantity: 2
Select: OK
Select: Aircraft
Select: New
Duration: 14:00
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-43 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select: OK
Select: Finish
Set your Work Template to Active.
We will now proceed with our exercise in order to request an approval for the SB
Ensure you select and display the main tab of your SB A320-57-1133-01
Click on Approval
A pop-up will show the matching approval control rule defined by the trainer
A peer user has to be Your trainer login
specified:
For the trainer only!! send the approval request to one of the trainees.
You will then ask her/him to approve your SB approval request.
Click on Request Approval
Check the Approval tab to see that the document is now waiting for
approval.
For Trainer only:
The trainer will now approve all the requests from the trainees.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-44 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Reload the SB and check how the Approval tab contents has changed & you
received an AMOS Mailwith the notice of the approval.
Status Tab - Assign View Tab
Select:
Select: Open
assign all aircraft within effectivity)
Select
Select
Initialise Documents: OK
QUESTIONS:
Which of the three documents is displayed in Maintenance Forecast (APN 1844)?
Why? What is the status of the two AD's? Why is it automatically set?
What if the AD issued by DGAC contained additional requirements, i.e. the SB is not
enough to comply with it?
When dealing with components documents, it is very important that parameter 1442
is set properly according to the company needs.
Example: An AD has only a component SB in the signoff tree. Should the AD status
be changed if a post-SB component is removed and pre-SB component installed?
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-45 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
The parameter also ensures, if set to Y, that rotable driven dependencies work on a
component- subcomponent signoff tree (example ENGINE SB linked to a VBV
ACTUATOR SB) as they work for an A/C - Component signoff tree.
2.4.3.10 Exercise Component Document with "Replacement of Component Required"
Flow of a Component "Replacement Required" Document through AMOS
View/Edit Modifications (APN 63)
Define the Modification Document and initialise it to the relevant Components.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-46 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Main Tab
Select New
Document No: 201-32-43-01
Doc-Type: SB
REMOVE AND REPAIR SHOCK ABSORBER
Subject: ASSY DUE TO CRACKING OF SLIDING TUBE
Issued by: K0654
Issue Date: -1m
Revision Date / Rev: No Rev Date / 00
Receiving Date: -1w
Effective Date: -1m
ATA-Chapter 32-11
Shop/Line Doc: A
Type of Change: N
Compliance Type: MAN (Mandatory)
Method of Comp. MO (Modification)
Type of Modification: Component modification
Document with hard Yes (select the tick box)
time limit:
Replacement of Yes (select the tick box)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-47 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
component required:
Select Save
Signoff-Tree Tab
"Document included in Signoff-Tree ( =
Select the tickbox: document write-off logic)"
Select Save
Effectivity Tab
Select New Effectivity
Partnumber 201371268-01
Select Next
Select All Serial Numbers
Select Finish
Select the line of effectivity that you have just entered.
Tab Revisions
Select De-/Activate
Select Yes
Ensure you select the effectivity row you have created.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-48 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
This Document has to be performed within 10'000 Flight Hours based on
the Issue Date of the document.
DO NOT FORGET TO ACTIVATE THE TIME REQUIREMENT!
NOTE: for components, the option "Perform at Next Shop visit" in the
Time Requirement tab makes the document available for selection also
after future removals
Properties tab
OPEN (Special Rule Apply!)
(Note: Auto Assign to OPEN cannot be used
Auto Assign Status: until a Time Requirement has been entered for
the Effectivity)
NOTE: if you use the Auto Assign function, AMOS will set the status
automatically for that specific effectivity row. This is available for the majority
of the available status.
It is highly recommended you check the STATUS tab anyway for
correctness and to ensure no A/C or component have been left
unassigned.
If you use the auto assignment to OPEN, like in this example, a time
requirement must exist, otherwise AMOS cannot initialise the document
on the relevant aircraft/component.
Select Save
Reporting Back Remarks, enter the following text.
Ensure that the documentation received with the returned component
clearly states the modification status of the component.
Select Save
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-49 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Tab More Info
Select: Material under Warranty
Select: Save
WARRANTY NOTE: later in the training, we will see where and how we can
search accomplished documents covered by warranty.
For on-wing documents, the tickbox "Warranty" can be also selected at step
5 of the worktemplate wizard. This would in the end mark as "warranty"
covered the final WO and make it available for APN 83 Warranty Claims.
Main tab
Section Document assessment (bottom page)
Change status to R (Released)
Select Save
Check the status of your document. It is now assigned and initialised to all applicable
components.
Please note the Aircraft registration on which the Component is installed. You will
need thisinformation in the next part of the exercise.
Aircraft Registration: _ _ and PN/SN:
Maintenance Forecast (APN 1844)
Issue the Replacement Event Workorder
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-50 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
We will now find the Rotable Replacement Event, and issue the Workorder required to
remove the affected Component.
Please note that this is the shortened process flow, and not the full "planning" flow
which would normally be performed.
With the assistance of your Trainer, find your Aircraft in the program
Maintenance Forecast (APN 1844). Please select it with a double click.
Show Until: all
Select Event Type XOR (this setting allows you to view one event type
filter setting only)
Select (acitvate) the
(Show Replacement Events)
following Event Type
filter:
You will see that AMOS has automatically created a "Replacement Event"
whose origin is your Modification Document.
For more details about the origin, right click on the Event and select
"Action", and then "Replacement Overview".
The same information can be seen in the main forecast view applying
different filter settings to see both replacement events and documents. This
is done as follows:
Select Event Type
filter setting
Make sure the "Show Replacement Events" &
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-51 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Filters "Documents" is selected
We will now issue the Workorder that is required to "replace" the
component. For the purposes of our exercise, we will simply perform the
removal.
Select: Your Replacement Event (PN 201371268-01)
Select Issue Workorder
The Workorder number will now appear in the W/O-Flags column of your
Replacement Event.
Workorder (APN 1418)
Remove the affected Component and Close the Workorder
We will book the removal of the applicable Component and Close the replacement
Workorder. Please load & review the Workorder in the program Workorder (APN
1418)
IMPORTANT INFORMATION
You have issued the Workorder for the Replacement Event for part number:
201371268-01. AMOS has automatically added the same part number as a Part
Request in the Planning View of the Workorder. AMOS has assumed that this is the
scenario:
Remove part number A, replace with part number A However, you may have other
scenario's:
Scenario 1:
Remove part number A, replace with part number A, but there are additional parts
required in order to perform the work (tools etc)
You must enter some additional information against part number A in Part
Administration (APN 59). BEFORE you assign the Document to the Part Number.
In the Replacement Tab, define a new Work Template, and enter the additional parts
that are required (part request). When the document is then assigned to the part
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-52 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
number, AMOS will use this Work Template. It will also automatically add part number
A to the part request.
Scenario 2:
Remove part number A, replace with part number B
Once again, you must enter some additional information against part number A in
Part Administration (APN 59). BEFORE you assign the Document to the Part Number.
Part number B must be defined as a one-way alternate of part number A
In the Replacement Tab, define a new Work Template, and enter part number B as
the required part (part request). When the document is then assigned to the part
number, AMOS will use this Work Template. You can of course, also add any
additional parts that are required (tools).
We will now complete the Workorder information, and perform the removal
of the component as follows:
While in the Maintenance Forecase double-click on the WO Number
of Replacement Event This will open up the WO in the program
Workorder (APN 1418)
(Production View) Add Entry
Select
Select: Action
Performed Date: Today
Time: Now
Action Text: ROTABLE REMOVED
Performed Sign: Enter your User sign
Select Next
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-53 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
(component change)
Select
For the purposes of this exercise, we will only perform the Removal.
OFF Section (these fields should have been completed automatically, but
please cross check)
Part No.: 201371268-01
Serial No.: 637-01
Select OK
Select Finish
The Labelbooking screen will appear. Cross check the information that
AMOS has entered.
Select Counters
Select OK
Removal Store/US Confirm the suggestions
Location:
Select Book Label
The label was successfully booked.
Select OK
Select Exit
The Component Change will now display as "BOOKED".
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-54 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Now Close the Workorder as follows:
Select Close
Closing Station: ZRH
Closing Date. Today
Closing Time: Now
AMOS will enter the corresponding flight leg information.
Approval No: Confirm suggestion
Closing Sign: Your user sign
Select Finish
Repair Administration (APN 1431)
The Component is now in Repair Administration waiting for a Repair Order,
requesting the performance of the Modification, to be generated.
Please open the program Repair Administration (APN 1431)
Find P/N:201371268-01 S/N: 637-01
Check all yellow Tabs and make sure that the SB 201-32-43-01 is
assigned to the Repair Order in the Modifications Tab. If it is not, please
tick the box in the "Items to Save" column, next to the Document and
Select Save Mod
Complete the information on the Details Tab as follows:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-55 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
K0654
Repair Station: (Check Part Vendor Tab to see the vendors
defined for this part in APN 59)
Reason for Removal: SD
Required Condition: SB
Priority: EXP
You have to review / open all yellow tabs - to review their content.
Select Generate Order
The order will automatically open in the program Order Management
(APN 2015)
Click on the ">" next to Order Details and then on ">" close to Pos.1
Click on the level; Modifications for 201......
Check the Modification Tab, you should see that the Modification
Document is selected.
Main Tab (Order Number Tab)
Issued By Address TPU
Cross check the Order Information. A number of fields are automatically
completed by AMOS.
Select Save
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-56 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select Issue
Write down your Order
Number:
Select Print (0)
Check the details of your Order print. The Order print should contain a
line: "Modifications to perform"
Select Book
The status of the order should now be displayed as "Booked/Open"
Goods Receiving (APN 2121) / Reporting Back Maintenance Event (APN 280)
Component is received back in serviceable and modified condition. Modification Document is
reported back as performed against this component.
Open the program Goods Receiving (APN 2121)
Order Number: Enter your Repair Order number.
Click on Search
Click on New Receiving
A new receiving number is now generated. Please enter the following
information:
Receiving Date: Today
AWB No: 02050901
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-57 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Click on Save Receiving
Select your component in the Order Details section and click on the Process
Receiving button. Please enter the following information:
Certificate Date: Today
Certifying Company: K0654
NOTE: if preliminary certificate details have been defined for the vendor in
APN 53,when entering the vendor code, AMOS will already fill the table with
some details. In this case select the applicable row and click on Edit
Certificate Data to enter the details below.
If no certificate type has been pre-determined for a vendor then after
entering the Cert Date & Company click on the Add button to enter the
certificate type and number.
Certificate Type: E1
Form Tracking K0654637-01
Number:
Certifying Company: K0654
Click on OK
Click on Receive Physically
The program Component Inspection and Records (APN 2293) will now open.
Inspection Time Confirm suggestion
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-58 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Cross check the information that AMOS has automatically entered.
Select on the LH side: Component Modifications
On the right side there will be 2 windows. The upper one shows Open &
not assigned Modifications (if the tickbox it ticked). As soon as you select
one of the entries in the lower part of the screen you will be able to
perform the Reporting Back of the selected Modification.
Select the Mod listed
In some cases you have to initialize the document first. You will find the
document then in the tab Initialisation. Select it and click on Initialise.
In the new Initialisation window select the document in the upper section.
Select the status OPEN from the drop-down menu
With the assignment of the status OPEN the document is transferred
into the lower section of the screen.
Select the document and click on Next.
In the next window cross-check the data and the due-date and close the
window by clicking on the
Finish button.
The Reporting Back Modification window will now
become active. Select the document.
Click on Report Back
1. Information Text - any remarks (black text) or reporting back message
(red text) entered in the document will show here. Additionally the user will
have to select a tick box to confirm that they have rea the reporting back
message.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-59 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Select: Tick box confirming the Reporting Back Message.
Click on Next
2. Performed Data:
Cycles: Check the cycles that AMOS has entered.
Hours: Check the hours that AMOS has entered.
Date: Today
Make sure that there is a link on the Reference Documents section. It
refers to the Repair Order.
Click on Next
3. Next Due Events
You should see the "Event Status" of the document as "Closed". Why?
Click on Finish
The Mod Info dialogue box will appear. This will allow the user to update the
"Component", "Hardware","Software" and "Database" Mod Status as
required.
Click on Component Tab
Component Mod A
Status
Press: Enter or the Tab key
Modification Date: Today
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-60 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Click on Modified
Click on Order
Order field: Right click / select History and your previous repair
order.
Click on Save
Click on OK
You will receive a message to tell you that the Event has been successfully
reported back.
Click on OK (twice)
Select Finish Component Inspection
If you have reported the modification in the previous steps then there should
be no open documents for this component. Otherwise it could be reported
back at this step
Your Repair Order now has the status "RECEIVED".
Now return to View/Edit Modifications, APN 63, and view the status of your
Document.
To view more details about the current status of the component open
Rotable Administration (APN 147) and select the Mod Info Tab sheet.
2.4.3.11 Modification Control Related Reports
Modification Status (APN 231)
Modification Status allows you to retrieve and print a detailed modification status
report per:
Aircraft
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-61 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Component
Document number
Assembly
The program also allows to have multiple aircraft selected, in order to get partial or
complete fleet status report.
An example is the following AD report on 5 airplanes, where you can also see the
available reporting options:
Component Modification Status (APN 639)
Component Modification Status gives a complete overview of all open/not
performed/repetitive component documents from different perspectives.
The program not only lists component documents but also indicates any kind of
problems in connection with the documents, for example problems with sign off trees
or effectivity, therefore, it serves as an important tool to help keep your AMOS data
clean.
The user can choose between the following perspectives in order to see the
component document status:
Aircraft: the component document status for components currently
installed on a chosen aircraft or fleet
Store: the component document status for all components
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-62 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
effected by a document that are currently in a chosen station/store;
only those stations/stores are listed for which data are available
Ex-House: the component document status for all components effected
by a document that are currently on a chosen repair station vendor; only
those vendor codes are displayed for which data are available
Part No.: the component document status per part number effected by a
document
In-House: the component document status for all components currently
unserviceable, either in an internal shop, the Electronic Pending Shelf or
in Repair Administration
Unknown: the component status for components that fall in one of the following
conditions:
not installed on an aircraft, on location U/S, with no order
not installed on an aircraft, on location U/S, no internal repair exists, and the related
Repair order is closed.
Modification Activity (APN 640)
This program allows the user to produce a report about modification documents that
have been performed, closed, ex factory, repetitive etc for selected aircraft
registrations or aircraft types within a selected period of time.
Example:
Find documents performed on COMPONENTS in the last month
covered by warranty.You should be able to find the off-wing
2.4.3.12 Weight and Balance - Set Up and Recordingin AMOS
The following information and exercises will show how AMOS can be configured to
allow the recording of Aircraft Weight and Balance information.
You will also learn how to enter a weight change manually, and how the Reporting
Back of a Modification Document can update the weight information of an Aircraft.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-63 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Weight & Balance Set-Up (APN 285)
For the purposes of Weight & Balance, the following information can be defined in this
program:
Weight & Balance Fleet Code.
Definition of the Aircraft Basic Weight information and weighing
positions. This information is contained within a "Fleet Code", this
Fleet Code can then be assigned to the applicable Aircraft
registrations.
This has an impact on the W&B calculations.
Weight & Balance Cabin Versions.
Within a particular Aircraft Type that your company operates, there may be
different configurations of the Cabin. Define the different Cabin Versions
which can then be assigned to the applicable Aircraft registrations.
This tab is not used in the W&B calculations but could be used to
manage the different fleet configurations.
IMPORTANT: new aircraft created in APN 308, do not appear
automatically in APN 285. You need to create a new entry in the main tab
for each aircraft registration that you need to link to a WB and/or Cabin
code.
Hint for the trainer
The following setup will be performed by the trainer only!
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-64 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
The tickbox "Include operational items" in APN 292 (Fleet view tab -->
Envelope), allows to center the Weight-CG chart in the Fleet Op.
Basic Weight and Fleet Op. CG thus showing the limits with reference to
operational data.
To show the behavior of the tickbox you have to enter some information in
APN 285 for the fleet code A320-01.
The following example values can be used for this purpose.
WB-Fleet tab
Fleet Op. Basic Weight:
423
50.00 KG Fleet Op. CG:
188
00.00 MM
WB-Fleet tab --> Operational items table
Add 2 pilots, for a total of 140 kg, with an Op. Item arm of 2000.00 MM
When you are asked if a new entry should be written in the W&B records,
say YES.
WORKFLOW SETUP
For trainer only: activate the rule "Exceeding Limits Template Rule" on
workflow 20 (APN 612) in order to show how people can be informed
when limits are exceeded.
Ensure that the trainer user sign is in the recipients list and that an AMOS
mail is sent.
Lateral CG Note:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-65 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Some helicopters (depending on the type and the operations), might require a
calculation of the lateral CoG.
When creating a new fleet Fleet Code in the WB-Fleet tab, after saving you can select
the tickbox "Lateral CG Relevant".
This option will enable additional fields that relate to the lateral CG calculation.
MAC relevant tickbox
Deselecting the "MAC relevant" tickbox will change the amount and type of available
fields to allow a different definition of the needed values whenever the MAC is not
relevant (e.g. Helicopters).
Weight & Balance (APN 292)
How to enter Weighing Data manually
Aircraft AAA has been weighed as part of a regular check. It is your task to enter the
weighing information that has been recorded on the Workorder.
Please open the program Weight & Balance (APN 292)
Select Aircraft: AAA
Aircraft View Tab - Main tab
Click on New Weighing
Date and time of -2m / 12:55
Weighing:
Issued By: BGGO
Workorder: 2’200’191
Description: Scheduled Weighing
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-66 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
View the Workorder and write down the weights as
recorded in the Action text: NLG:
LH (MLG):
RH (MLG):
Now return to the program Weight & Balance (APN 292).
Double click in the Weight
field:
Enter the weights you wrote down in the appropriate "Reading 1" fields.
Select OK
Select Save Weighing
Click on: Yes (to confirm the change)
Based on your entries and the Fleet Code Weight information assigned to
your Aircraft, AMOS has recalculated the Operating Basic Weight (as well
as other weight information) of your Aircraft.
NOTE: weight and balance entries can be edited or deleted with the
available buttons Save Weighing and Delete only if a user is licensed to
do so.
When entering an older weighing AMOS will use the date & time of the
weighing and re-sequence the entries - and if necessary re-calculate the
values automatically.
INFO: Parameter 1239's integer value is used to define the number of digits
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-67 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
displayed after the point for all the Weight & Balance values. The number of
digits displayed after the point into Weight and Balance could be equal to
"2", "3" or "4"
How to view graphics with optimized position and history of weighing.
Fleet View Tab - Envelope Tab
Select Aircraft: AAA (in the right hand side pane)
Select the tickbox: Show only selected Aircraft
Select Show History
How to enter a weight change to be automatically applied.
Your company has decided to modify the cabin layout for part of the Airbus fleet. The
impact on weight and balance has been estimated. Enter the weight changes to the
corresponding Service Bulletin according to values given below.
Please open the program View/Edit Modifications (APN 63)
Search for SB: A320-25-1591-01
Effectivity Tab
Select the effecitivity entry
Go to Weight & Balance sub tab
Select: New
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-68 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Enter the following Weight information:
Item Weight Change: 150.00
Dim. of Weight: KG
Item Arm: 7000.00
Item Moment calculated automatically
Dim. of Arm: MM
Select Save
We will now "Report Back" the performance of the SB, this process will update the
weight information of the applicable Aircraft.
Please open the program Maintenance Forecast (APN 1844)
Select your Aircraft: AAA
Find your SB: A320-25-1591-01
Right click on your SB
Select: Action
Select: Report Back
Select Next (until you reach step 3)
NOTE: If the event is overdue, you will have to choose an "Interval Usage
Reason Code" (e.g. HNG, if the hangar was not available) in order to be
allowed to press "Next" at step.2.
Select Finish
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-69 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 4 MODIFICATION CONTROL
Event successfully reported back.
Select OK
Now view the result of this action in the program Weight & Balance (APN 292)
Select Aircraft: AAA
Aircraft View Tab
You will now see an entry of the Type "Automatic". This is the performance
of the SB.
Tab Fleet View - sub tab List
Review the "Note" column text
Fleet View Tab - EnvelopeTab
Select Aircraft: AAA (in the right hand side pane)
Select the tickbox: Show only selected Aircraft
Select Show History
Is your Aircraft still within weight limits?
NOTE: If the weight is out of limits, in addition to the text added to the "Note"
column under the "List" tab, AMOS will highlight the relevant weight value in
red, adding an exclamation mark after it, both in the "List" and "Envelope"
tabs.
This does not happen if the CG is out of limits.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.4-70 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
ENGINEERING ORDERS
Overview
Engineering Ordersis mainly used for third party maintenance, where labour and
material costs can be set up and managed. You can use it to create hierarchical
structures where you can collect different
engineering orders in an Engineering Order Cover. This is useful when you have
several Service
Bulletins(SBs) affecting different areas of the aircraft airframe or component
modifications.
Note:The program is only used for administrative purposes and all other tasks are
managed in the
Modification Control programs.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-1 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
AMOS PROCESS
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-2 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Modification Control – Engineering Oder
Manage and control the SB/AD modification status. Define the compliance requirements.
Authority
Manuf. /
Inte rnal Ven dor
Start
SB AD
Campaign Documents
Re-Approve
03.08 Eng ineerin g 01.08
End
Pub lica tions & Per form Yes Order Yes Eng ineerin g O rders
App roval App roved No
OEM Libra ry necessary? Control
(APN852)
End
No 1. Release approve d
EO to APN63 (- - -
Yes dotted line)
Modificatio n Activity KPI Analyzer
End
No View/Edit OR
Engineering
(APN640) (APN112 0)
Modificatio ns
(APN63) 2. Release DOC in
APN fo r Pl anning
(solid line)
Modificatio n Status 04.06
Aircraft
(APN231) Reporting-Back
03.09 Work 03.15
Instructions Softwa re
Aircraft or Authori ng Manag ement
On Wing
Componen t
Componen t 03.05
On/Off Configuration
Modificatio n Status Comp
Wing Manag ement
(APN639)
Planning
04.01
Plan ning
Forecast
Off Wing
Maint.
08.01/08.03
Schedu led
Maintenan ce
Material
06.02 05.03
Goo ds Repair &
Receiving Exchange
How to enter an Engineering Order
Engineering Order can be used to assess a Service Bulletin or any other document
type and estimate the cost of the implementation. There are several tab sheets which
can be filled with various data to describe the impact, consequences and costs.
In the Engineering Order you have the possibility to create either an
EOC = Engineering Order Cover
or
EOD = Engineering Order Details
2.5.2.1 Exercises
Your company has received a SB. Although the SB is mandatory, your company
would like to evaluate the SB with an Engineering Order Cover.
Please open the program Engineering Orders (APN 852)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-3 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Tab Main Data
Click on: New
EO number: EOC-32S-57-0001-R-00-02
WINGS - INBOARD FLAP INSPECT THE
Subject: TRUNNION AND SLIDING PANEL
ATA-Chapter: 57-51
Issued by: SWS
Work Category: Minor
Work Class: Inspection
Classification Appr. Data/Std. Practice
Type of Mod: Aircraft/Airframe Modification
Compliance: MAN (Mandatory)
Approval required: Immediately
Prepared by / Date: Your user sign / today
Click on: Save
Tab Engineering >Tab General > Tab Safety
Click on: New
Severity: High
Prob. of Recurrence: Medium
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-4 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Click on: Save
Tab Engineering > Tab General > Tab Background
Some operators have reported inboard flap
Trunnion wear damage. This is due to the
movement of the sliding panel hook, which can
move out of the Trunnion protected area during
Text: flap operation.
(Available as Autotext) The inboard flap Trunnion wear associated with a
drive failure at track 2 or associated with a hard
jam at track 1 could lead to loss of flap surface
control. A free moveable flap could detach from the
wing. Subsequent damage of the tail plane is
envisaged.
Click on: Save
Tab Engineering > Tab General > Tab Motivation
Select: Airworthiness and Reliability
Click on: Save
Tab Engineering > Tab General > Tab Rejection Consequences
Select: Operation and Repetitive Maintenance
Click on: Save
Tab Cost Info > Tab Project Costs
Click on: New
Project Currency CHF
Click on: Save
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-5 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Tab Cost Info > Tab Business Case
Click on: New
Total Number of A/C: 15
Engineering: Time[min] - 240 / 100.00
Cost/h:
Maintenance: Time[min] 480 / 135.00
- Cost/h:
Planning/Admin: 60 / 80.00
Time[min] - Cost/h:
Additional Equip./Tools: 130.00
Click on: Save
Click on Printer Icon to print the EO Business Case report
How to set updistribution lists
In order to be able to use the Distribution Tab in the Engineering Order program, we
have to define some information in the program Configure Publication Management
(APN 566).
2.5.3.1 Exercise:
You will create a distribution list for EOC with a specific ATA chapter and a specific
affected A/C type. Please open Configure Publication Management (APN 566)
Tab Main Configuration > Tab Publication Types
Please check that the Publication Types of EOC and EOD are already
entered into this Tab.
Tab Distribution >Tab Distribution List
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-6 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Click on: New
Name LIST-EOC-32S-57-02
Description List for EOC with ATA57 and 32S airplanes
Click on: Save
These actions simply assign the Department and User Sign to the just created list in
the middle of the screen.
Tab Distribution > Tab Distribution Members
Click on: New
Department: TE_02
Click on: Save
Right-click on the "Name" column header, then select "Show Column" and
then "User-Sign".
Check in the User-sign column: if your User sign (i.e. TU02) is not in the
list, add it as explained in the next steps.
Click on: New
User-Sign: choose your user sign.
Click on: Save
You now want to add the users to your Distribution List.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-7 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Double click in the LIST-EOC-32S-57-02
field distribution list
and select:
Tick the box "In List" next to your Department and User Sign.
Click on: Save
Tab Distribution > Tab Distribution Filter
Click on: New
Title: EOC-32S-57-02
Type: EOC
Description: EOC 32S ATA57
Distrib. List: LIST-EOC-32S-57-02
Responsible: Double click and choose your user sign
Click on: Save
Select: Your Distribution Filter
Ensure you select the Distribution filter settings that you have just created.
Then, add the following filter criteria in the related Filter Settings table
ATA Chapter: 57
A/C Type: 32S
Click on: Add
Click on: Save
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-8 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Now that the list is configured we return to our Engineering Order and perform the
Distribution as follows:
Open Engineering Orders (APN 852)
Ensure you are working on the EOC that you previously created & reload it, then use
the distribution list as follows:
Tab Distribution
Click on: Auto fill
Click on: Distribute
If your Distribution List configuration is correct, you should receive the
"Distribution Successful" pop- up.
NOTE: As all users have used ATA chapter 57, A/C type 32S and
publication Type EOC, the "Autofill" action will add all the users defined for
each distribution list that matches with your EOC criteria.
Click on: OK
Your trainer will now demonstrate how the distribution can be acknowledged in the
program Publication Acknowledgment (APN 685).
Approval Informationand EO Details
2.5.4.1 Exercise:
The Engineering Order Cover has been approved. Please enter the approval
information: Open Engineering Order (APN 852) and search for your entered EOC:
Tab Main Data
Approved By: APXE
Date: Today
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-9 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Approval: Tick the "Approved" radio button (this is for
information only)
Select: Save
Select The printer icon and check all available reports
NOTE: the approval information defined above are entered manually and they are
"information only" thus not triggering any action in any other APN.
On the other hand, there is the option, completely independent from the one described
above, to use the Approval Control module in order to manage requests and approval
processes within AMOS. This will be explained later by the trainer.
Now that the SB has been evaluated on an EOC, your Company wishes to create 2
separate EOD to split the EOC.
One EOD will be for the LH side, the other for the RH side.
Create your 2 Engineering Order Details and create the Sign-off Tree. Engineering
Order (APN 852)
EOD #1
Tab Main Data
Select: New
Number-Generator: EOD-32S-57-0001-R-00-021
WINGS - INBOARD FLAP - INSPECT THE LH
Subject: TRUNNION AND SLIDING PANEL
ATA-Chapter: 57-51
Issued By: SWS
Work Category: Minor
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-10 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Work Class: Inspection
Classification Appr.Data/Std. Practice
Type of Mod.: Aircraft/ Airframe Modification
Compliance: MAN (Mandatory)
Approval required: Immediately
Prepared by/date: Your user sign/today
Select: Save
Write down your _
AMOS assigned EO
number (top right)
Tab Engineering > Tab Effectivity
Select New Effectivity
A/C-Type: 32S
Select Next
Serial Number Ranges
SN From: 1501
SN To: 1515
Select: Finish
Ensure the line of effectivity you previously defined is selected.
tab Revisions
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-11 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Click on: De-/Activate
Select: Yes
Ensure the line of effectivity you previously defined is selected.
Tab Time Requirement > Tab Editor
Select: New
1. Mode Selection
Select: Advanced Definition
Select: Next
2. Header
Select: Single Event
Select: Next
3. Threshold Group
Select: Next
4. Thresholds
Select: Before
Dimension: H
Due At: 40000
Select: Finish
Activate your Time requirement clicking on Activate
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-12 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Tab Engineering > Tab Effectivity > Tab Work Template (next to Tab
Applicability )
Select: New
1. Header Information
ATA-Chapter: 57-51
Select: Next
2. Task Classifications
Select: Next
3. Add Work Step
Work Step Creation Individual
Option
Headline: Perform inspection of the Trunnion and Sliding
Panel on the LH side
During sliding panel inspection, pay special attention
to the sliding panel hook attachment for loose screws
and correct installation. Report on the Workorder if
Description blend had to be performed. NOTE: This reporting is
mandatory. If reporting is not performed, the
inspection will have to be performed again.
Select: Next until you reach the Step 7. Resource Request
7. Resource Request
Select: New (Staff)
Select: Scope
Planning Qualification: B1
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-13 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Total Hours 02:00
Quantity 1
Select: OK
Select: Finish
Select: Activate
EOD #2
To create the second EOD, you will use a faster option taking some information from
EOD#1.
Ensure you are on the Tab Main Data of EOD-32S-57-0001-R00-021
Click on: Save as New
In the "To->" Section, write the following details
Document No.: EOD-32S-57-0001-R00-022
WINGS - INBOARD FLAP - INSPECT THE RH
Subject: TRUNNION AND SLIDING PANEL
Select: OK
The screen will now show the newly created EOD.
Write down your _
AMOS assigned EO
number
Instead of setting up the same Effectivity entry, Work Template and Time
Requirement we will use the Copy function of the Effectivity
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-14 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Select the EOD just created for the LH (the one that contains the effectivity)
Tab Engineering > Tab Effectivity Select your created Effectivity entry
tab Revisions
Select COPY EFFECTIVITY
Switch back to your copied document EOD-32S-57-0001-R00-022
Tab Engineering > Tab Effectivity
Select Paste Effectivity as New
Using this copy function not only copies the Effectivity entry but also the Time
Requirement defined for the effectivity and the Work Template.
Select the entry of the Effectivity
tab Revisions
Select De-/Activate
Confirm Popup
Tab Work Template
Right-click on the Workstep text > Description
Change Headline to adapt the instructions to the RH side.
Headline: Perform inspection of the Trunnion and Sliding Panel
on the
RH side
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-15 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Click on: Save
You now must build a sign-off Tree (a relationship structure between the documents)
as follows: To do this, ensure you display your EOD for the LH side:
Tab Signoff-Tree
Select Document included in Signoff-Tree (= document
write-off logic)
If needed: Clear the field containing "-> PLEASE DEFINE! <-"
Select Save
Repeat the same for the EOD for the RH side.
Ensure you now display your EOC, and proceed as follows:
Tab Signoff-Tree > Signoff-Tree table
NOTE: to enter documents in this table, it is safer to double click in the
relevant row, search for the needed document and add it. In this way you
ensure that the correct revision is selected.
If you enter "EOD" into the search field it will make it easier.
Please also note that you might need to include documents not yet released
from P.M. (APN 565) and E.O (APN 852) in the search dialog in order to see
the documents.
In the first empty row, enter EOD-32S-57-0001-R00-021.
In the following empty row, enter EOD-32S-57-0001-R00-022.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-16 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Select Save
This tree-structure (or Signoff-Tree) just created, means that the EOC is fulfilled by
the accomplishment of BOTH the EOD for the LH side and the EOD for the RH side
The end result, that can be also reviewed in the Signoff Tree tab in the left part of the
screen (as soon as one affected document involved document is selected), is as
follows
To build this relationship, please keep in mind these general rules:
every document that will be performed (in this case the two EOD's), will be marked
as "Included in Signoff tree" by ticking the related box in the Signoff-Tree tab (this will
also put an asterisk (*) beside the name of the document in the Signoff Tree view).
for each document fulfilled (or partially fulfilled) by other documents (in this case the
EOC), you will need to fill the table "Signoff-Tree" in the Signoff-Tree tab with all the
relevant documents (in this case the two EOD's).
Release the complete Engineering Order Tree to Modification Control
Load your EOC in APN 852
NOTE: we release the EOC as this would also release the relevant tree
structure under the higher document, i.e. the two EOD's.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-17 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Tab Main Data
Click On Release to Mod. Con.
Click On Yes (twice)
You can now view the complete tree in the program View/Edit Modifications
(APN 63).
Approval Control for Documents and Publications - Overview (APN's 2110,
2111)
Approval Control allows to set condition(s) to allow an approval request on
documents. The involved APN's are:
Approval Control Configuration (APN 2111) - configure the conditions under which an
approval request will be needed and the relevant responsible to approve.
Approval Control Board (APN 2110) - view/monitor/act on each specific approval
request
NOTE: Preconditions to use approval control for publications and documents are:
1) Activate the related parameter(s):
-Parameter 1666 for View/Edit Modifications (APN 63)
-Parameter 1667 for Publication Management (APN 565)
-Parameter 1668 for Engineering Orders (APN 852)
Setting the related parameter to Y, will enable a tab (at the top of the screen)
and a button (at the bottom of the screen) both called "Approval" in the
corresponding APN.
2) Configure APN 2111 with the necessary rules, conditions and responsible to
approve
3) Ensure the person to approve has the proper licenses to respond to approval
requests
NOTE: When releasing a document to Modification Control from either APN 565
or APN 852, AMOS will check if a rule exists in APN 2111 and will not allow to
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-18 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
proceed with the release of the document to APN 63 unless the full process
(approval request + approval confirmation) is accomplished.
EO with Approval Required
With the following exercise, we will see how the approval control can be set for an
EO depending on certain conditions.
For this purpose, we will create only one EOD with the related financial
information.
Less step-by-step instructions will be provided to give you the chance to get
familiar with the APN on your own with a scenario.
The following part is for the trainer only!
Change the parameter 1668 to Y to activate the Approval Control for EO.
In APN 2111, build a rule for EOD's that are not mandatory and where the total
implementation cost is higher than 10'000.
In the tab "Who Should approve?" add "Another User" as option. This will leave the
choice to the user releasing the EOD.
2.5.6.1 Exercise:
Close APN 852 and reopen it to make sure the approval control is activated.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-19 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Create an EOD according to the following scenario.
BACKGROUND
During landing, the APU fuel drain mast installed on the lower fuselage
of the 32S family, could be damaged by debris kicked up by the main
wheel tyres.
The aircraft manufacturer, released an optional modification to replace the
APU drain mast with an improved material. This document affects all 32S
manufactured more than 4 years ago.
Engineering decided to introduce this modification and prepared an EOD for
the fleet operated by SWS, with the relevant cost information.
For your reference, this is the sequence of steps that should be followed:
> Create EOD-32S-28-0002-R00
(NOTE: If you are already familiar with APN 565, you can start entering
the OEM document (e.g. SB A320-28-0002) In Publication Management
and create the EOD directly from the publication "Document Assessment"
tab pressing the Assess in Eng. Orders button.)
> Subject: "Exchange of APU drain mast"; ATA 49-17
> Ensure the compliance is not Mandatory
> Add an effectivity and activate it (if not added, this must be done in APN
63 after the release)
> Add a time requirement (within 1 year), and activate it (if not added,
this must be done in APN 63 after the release)
> Adda worktemplate, and activate it (if not added, this must be done in
APN 63 after the release)
> Add Cost Info (currency and costs). Feel free to enter the values that are
more realistic for you, but ensure the total cost in the Business Case tab
is higher than 10'000.
> Definethe Sign-off tree for the document (in this example, the
EOD is the only productive document)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-20 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
You are now ready to release the document to APN 63.
Main Data tab
Click on Release to Mod. Con.
At this point, AMOS will check if the document
requires an approval. If so, you will get a dialog
to request the approval.
Due to the setup done on the rule, a user has to be specified in the
field "A peer user has to be specified".
Enter: Your trainer login
For the Any trainee user sign (you will then ask her/him to approve
trainer with your assistance, if required)
ONLY!!
Enter:
Click on: Request Approval
AMOS will show a dialog message warning you that the document has
not been approved yet, and therefore it was not released to APN 63
Click on: OK
For the trainer ONLY!!
Go to APN 2110 and approve all the approval requests from the trainees
Review the email you receive after the document approval and the
"Approval tab"
Select Search (to refresh the screen)
Click on: Release to Mod. Con.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-21 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 5 ENGINEERING ORDER
Click on: Yes (twice)
At this point, the release to APN 63 should be successful. Review your
document in APN 63.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.5-2 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
ENGINEERING PART 2
Aircraft Administration (APN 308) Overview
Aircraft Administration is the source of important information for many different
programs within AMOS such as Maintenance Programs Administration, View /
Edit Modifications and Workorder to name just a few.
Crucial Aircraft data such as:
- Limitations like the Autoland category
- Link the aircraft to an existing Maintenance Program or an existing
Aircraft Configuration
- Aircraft Rating
- Assigned Counters to an Aircraft
- Utilization (Airline) or Ground Time of of an Aircraft
- Linked OEM documents can be found here.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-1 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Aircraft Code Definition (APN 2627) -Overview
This program is used for managing Panels, Areas, Zones, System configuration
and Mission configuration per aircraft type / fleet.
Aircraft Code Definition (APN 2627)
Define a new Area and a new Opening and Closing Workorder for a Panel for
A/C Type 32S:
Aircraft Type
Select: 32S
Areas tab
Click on: New
Code: 19001
Description: BELLY FAIRING AC AND HYD COMP
Click on: OK
Panels tab - Add a NEW panel
Code: 197GB01
Description: BELLY FAIRING ACCESS PANELS ON LH
Click on: OK
Opening Workstep
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-2 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Click on: Add Entry
Choose: Description
OPEN PANEL 197GB01, BELLY FAIRING ACCESS
Description Text:
PANELS ON LH
Click on: Save
Click on: Add Entry
Choose: Zones/Areas/Panels/Special
Area Codes: 19001
Click on: Save
Click on: Add Entry
Choose: Resource Requirement / Staff
Scope/ Planning
B1
Qualification:
Total Hours: 00:54
Quantity: 1
Click on: Save
Repeat the steps described above for the
Closing Workstep. Adapt the Workstep
Description accordingly.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-3 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Part Administration (APN 59) - Overview
All part numbers must be defined in the program Part Administration before they
can be used in any other AMOS program. Exceptions are Part Requests on a
Workorder, on a Taskcard, on a Document and on a Generic Event where
unknown Part Numbers can be entered.
Each Part Number can have important characteristics and details assigned to
it which will determine how it is used in other AMOS programs. New Part
Numbers are usually entered into AMOS by the Spares Department, although
certain details such as information regarding Alternates and Aircraft Positions
are generally entered by the Engineering Department.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-4 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Part Administration (APN 59) Engine part withrequirement
Enter a new Part Number
Parts Tab
Click on: Create Part
Part Number: PW1130GA-JM
Description: ENGINE ASSY
Material Class: Rotable
Material Type: P
Measure Unit: EA (Each)
FA Type: 32S
ATA-Chapter: 72-00
Click on: Publish
You can enter a reason for the creation of a new part. This is not mandatory.
Click on: OK
Weight: 7100
Specification: PW1000 108-INCH
Country of Origin: USA
Default Supplier: PW416
Default Repair: 00198
Click on: Save
Main Tab - Alternates Tab
Click on: New
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-5 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Type: A
Alternate: PW1130G-JM
Select: Two ways interchangeability
Approved by: VAE03203
Approved Date: -3w
Click on: Save
AMOS will present the Set Alternative Two Ways dialogue box.
Click on: Yes
Main Tab - Location Tab
Click on: New
Station: HAN
Store: Main
Location: 12D6
Click on: Save
Remarks Tab - Int. Remarks Tab
Text: HIGH VALUE ITEM
Click on: Save
Aircraft tab - Aircraft Type:
Click on: New
Aircraft Type: 32S
Number Type: S (Serial Number)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-6 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Number From: 1000
Number to: 8000
Qty per A/C: 2
IPC Reference: 72-00-00-05-300B
Click on: Save
Miscellaneous Tab - Special Tab
Click on: New
Special: ENGINE
Click on: Save
Click on: New
Special: MAJEQU
Click on: Save
Click on: New
Special: MTBUR
Amount: 6500
Click on: Save
Part Requirement Administration (APN 2773)
Open Part Requirement Administration (APN 2773):
Requirement 1: Special Inspection (IN) must be performed every 24000 FH
or 8000 FC
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-7 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Click on: New
Requirement: ENGINE 01 INSPECTION
Type: IN (Inspection)
Description: SPECIAL ENGINE INSPECTION
Select: Component Replacement
Compliance Type: HT (Hard Time Limit)
Click on: Save
Effectivity section
Click on: New Effectivity
Partnumber: PW1130GA-JM
Click on: Next
Tick: All Serial Numbers
Click on: Finish
Select your Effectivity
Select Revision tab
Click on: De-/Activate
Click on: Yes
Select the Effectivity title
Time Requirement / Editor tab
Click on: New
Select: Basic Definition
Click on: Next (Until you reach the Intervals)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-8 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Dimension: H
Amount: 24000
Click on: +Interval
Dimension: C
Amount: 8000
Click on: Finish
Click on: Activate
If any tools or special instructions are required to remove the part, the
Replacement Tab in Part Administration (APN 59) should be used to create
a Worktemplate for Replacement.
Requirement 2: A Boroscope Inspection (BO) which must be performed
with a threshold of 25000 FH or 15000 FC and an interval every 6000 FH or
1500 FC
Click on: New
Requirement: ENGINE 01 BOROSCOPE
Type: BO
Description: INSPECTION OF TURBINE
Select: On Wing/Closed Loop/On Shelf
Compliance Type: HT (Hard Time Limit)
Click on: Save
Effectivity section
Click on: New Effectivity
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-9 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Partnumber: PW1130GA-JM
Click on: Next
Tick_ All Serial Numbers
Click on: Finish
Select your Effectivity
Select Revision tab
Click on: De-/Activate
Click on: Yes
Select the Effectivity title
Time Requirement / Editor tab
Click on: New
Select: Basic Definition
Click on: Next
Threshold (Within,
H
MFG Date)
Amount: 25000
Click on: + Threshold
Threshold (Within,
C
MFG Date)
Amount: 15000
Click on: Next
Dimension: H
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-10 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Amount: 6000
Dimension: C
Amount: 1500
Click on: Finish
Click on: Activate
A Boroscope tool is required to perform this task. You can enter this
information in the Work Template Tab next to Time Requirement.
Worktemplate tab
Click on: New
Header Information
ATA-Chapter: 72-00
Click on: Next until you reach step 3: Add Work Step
Select: Individual
Click on: Next until you reach step 6: Part Requests
Part Requests
Click on: Add
Part Number: 01-08000-25
Qty: 1
Click on: OK
Click on: Finish
Now Activate your Work Template
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-11 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Requirement 3: A Special Cleaning of the Engine has to performed on
demand
Click on: New
Requirement: SPECIAL ENGINE 01 CLEANING
Type: EC
Description: SPECIAL ENGINE CLEANING
Select: On Wing/Closed Loop/On Shelf
Compliance Type: HT (Hard Time Limit)
Click on: Save
Effectivity section
Click on: New Effectivity
Partnumber: PW1130GA-JM
Click on: Next
Tick: All Serial Numbers
Click on: Finish
Select your Effectivity
Select Revision tab
Click on: De-/Activate
Click on: Yes
Select the Effectivity title
Time Requirement / Editor tab
Click on: New Unlimited Time Req.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-12 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Select: Repetitive Event
Click on: OK
Click on: Activate
Worktemplate tab
Click on: New
Header Information
ATA-Chapter: 72-00
Click on: Next
Line / Heavy: L (Line Maintenance)
Click on: Next
Headline: @STANDARD_HEADLINE@
PREPARE AND PERFORM ENGINE
Description Text: CLEANING IAW JC 720000-100-901
Click on: 2 x Next until Ref / Classification step
Enter Free Text: JC 720000-100-901
Click on: Add
Click on: 2 x Next until Resource Request
Click on: New (Staff)
Scope / Planning
LB
Qualification:
Total Hours: 03:00
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-13 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Quantity: 1
Click on: OK
Click on: Finish
Now Activate your Work Template
Life Limit Requirement with Pro-rata Calculation
In AMOS it is possible to assign Ratings to an Aircraft or to individual
Rotables/Assemblies. Ratings can be used in conjunction with the Pro-Rata Life
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-14 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Limit Requirements to calculate the utilization, ToGo and Next Due values of
the Life Limit.
Precondition: In Basic Data Administration (APN 18) the Rating Category and
the Rating must be defined
With the next exercise you will learn how to create a Life Limit Requirement with
Pro-Rata calculation.
Scenario:
In this exercise we will use the PW Engine (PN: PW1130GA-JM) as it already
has an inherited Rating "A" from the Aircraft it is installed on.
We will define the Life Limit on the level of the engine and not the sub-parts with
the following intervals:
30'000 FC on Rating A (20K)
25'000 FC on Rating B (25K)
20'000 FC on Rating C (28K)
In addition to the three Rating intervals a Fallback interval as a safety net
is required. Usually the shortest interval is used for the safety net scenario.
Open Part Requirement Administration (APN 2773):
Click on: New
Requirement: ENGINE 01 LL
Type: LL (Life Limit)
Description: PW ENGINE THR Dependant Life Limit
Select: Component Replacement
Compliance Type: HT (Hard Time Limit)
Pro-rata Calculation and read the appearing dialog
Tick:
careful.
Click on: OK
Rating Category: Double-click and choose THR (Thrust Rating)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-15 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Click on: Save
All engines with Rating C (28K)
Click on: New Effectivity
Part Number: V2533-A5
Click on: Next
Click on: Include existing Serial Number
Select: V11700
Click on: OK
Click on: Next
Rating: C
Click on: Finish
Select your Effectivity
Time Requirement / Editor tab
Click on: New
Click on: Next
Group Name: Rating C (28K)
Dimension: C
Due at: 20000
Click on: Finish
All engines with Rating B (25K)
Click on: New Effectivity
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-16 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Part Number: V2500-A5
Click on: Next
Click on: Include existing Serial Number
Select: V11700
Click on: OK
Click on: Next
Rating: B
Click on: Finish
Select your Effectivity
Time Requirement / Editor tab
Click on: New
Click on: Next
Group Name: Rating B (25K)
Dimension: C
Due at: 25000
Click on: Finish
All engines with Rating A (20K)
Click on: New Effectivity
Part Number: V2533-A5
Click on: Next
Click on: Include existing Serial Number
Select: V11700
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-17 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Click on: OK
Click on: Next
Rating: A
Click on: Finish
Select your Effectivity
Time Requirement / Editor tab
Click on: New
Click on: Next
Group Name: Rating A (20K)
Dimension: C
Due at: 30000
Click on: Finish
Fallback as safety net, no Ratings
Click on: New Effectivity
Part Number: V2533-A5
Click on: Next
Click on: Include existing Serial Number
Select: V11700
Click on: OK
Click on: Finish
Select your Effectivity
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-18 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Time Requirement / Editor tab
Click on: New
Click on: Next
Group Name: FALLBACK
Dimension: C
Due at: 20000
Click on: Finish
Right-Click on: ENGINE 01 LL (left side)
Choose: Part Requirement / Action.../Activate WT/TREC/EFF
Click on: Activate all and OK
Part Req Initialiser / Intialisation tab
Select your Rotable
Click on: Initialise
Click on: Next and check the Expected Due Date of the Life
Limit
Click on: Finish
Check the current status of the engine and the currently assigned interval
depending on the allocated rating:
Open Aircraft Adminsitration (APN 308):
Double-click: A335
Rating tab
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-19 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Dimension: Choose Flight Cycles
Select V2500-A5 / V11700 and review the values
To demonstrate the calculation of the Engine Pro-Rata Life Limit, we need to
change the rating of the aircraft:
Dimension: Choose Flight Cycles
Click on: Change Rating
Date of Change: - 37 days / 10:00
Select: C [THR]
Click on: (Add)
Select: A [THR]
Click on: (Remove)
Click on: OK
Click on: Yes
Double-click on A335 to refresh the screen
Rating tab
Dimension: Choose Flight Cycles
Select V2500-A5 / V11700 and review the values
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-20 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Open Rotables Administration (APN 147):
Partnumber: V2500-A5
Serialnumber: V11700
Click on: Search
Requirements tab
Select the Life Limit requirement and check the following values:
Due at, Interval, Expected (due date), Since req., Utilisation and To Go
Rating tab
Dimension: Choose Flight Cycles
Review the table in the History section
Rotable Administration (APN 147)
Overview
In Rotables Administration, all important data concerning rotables are
stored. These data keep track of the hours and cycles of the rotables in your
company.
Sometimes, it is necessary to enter or update rotables data, as in the following
situations:
New AMOS customers who have to make their company's rotables,
including the ones installed on the aircraft, known to AMOS, if this is
not done in Data Transfer.
A new aircraft arrives in your company and the rotables installed on
this aircraft have to be made known to AMOS, if this is not done in
Data Transfer.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-21 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Manual correction of data after data transfer.
Individualize Time Requirements on the level of a component / serial
number.
Only the AMOS System Administrator and key people in the spares
department and engineering department should be able to enter new data
or perform changes in this program since this should be used only in very
rare cases.
As soon as there are movements (receivings, transfers, performance of
requirements, installation-removal from aircraft ...) you should not change
any data in this program since it will not write any history in the database
and therefore cause discrepancies in the parts history.
In this program, you will find all relevant information about a serial number
requirement, interval and next due at.
It is also used to have time since new or time since installation (TSN-TSI)
and cycles since new or cycles since installation (CSN-CSI) info of a rotable
at a particular date.
Rotable Administration - Correct wrong Countervalues
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-22 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Scenario:
You are informed via Technical Assistant that there was a mistake during
receiving of P/N 9024-15704-2 S/N 26A45-01. The inspection of the linked
certificate shows that the TSN value of the component was entered incorrect.
You have to adjust the value from 35'200 Flight Hours to 38'200 Flight Hours.
The component is installed in an Aircraft.
Open Rotable Administration (APN 147):
Partnumber 9024-15704-2
Serialnumber: 26A45-01
Click on: Search
Select Requirements tab and check the Expected Date and To Go
value of the H (Flight Hours) Counter:
Expected:
To Go: _
Counter tab / Actual Values tab and select the H (Flight Hour) counter of
the component.
Counter Values tab
Since: All
Select entry (Inspection Detail):
Readout Date/Time: _ _
Click on: Edit
Life Value: 38200:00
Click on: Save
Maybe you have to update the screen by clicking on Search
Select Requirements tab and check the adjusted Due Date and To Go
value of the H (Flight Hours) Counter.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-23 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Note: This only changes the current actual counters of this rotable. The History
may need to be adjusted as well.
Rotable Administration (APN 147) - Create New S/N
Your instructor will explain the following process, the steps below are for
reference only.
The reasons for having to create a new S/N for a rotable are few but essential,
one or 2 examples might be:
The delivered rotables list with a phased in A/C is not complete
A long term A/C in the fleet and the rotable in question was never recorded or
removed The following steps would be used to create the S/N in question.
Open the program Rotables Administration, APN 147
Part number field: 1018278-1
Click: Search
At this time there are no results as currently no S/N exists.
Click: New
Serialnumber field: 465135
Condition: N (NEW)
TSN, CSN &
Unknown
Manufacture Date
Delivery Date: -140d
Aircraft: A323
Installation Date -140d
Position: 14HH
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-24 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Owner: HVN
Click: Save
Confirm the hours & Cycles based on the installation date
Click: Ok
A pop-up will appear
asking for a booking
S/N not recorded as delivered with the A/C.
text, enter the reason
for the new S/N.
Click: OK
The booking text that has been entered can then be viewed in the program
Parts Tracking after having selected the history entry for the "Installation" and
then the tab sheet Details of selected booking, sub tab, Booking text.
In addition a workflow might be used that can be triggered by the creation of a
new rotable. This might be used to inform other related departments that a new
rotable has been created outside of the normal process.
Counter Management (APN 2031) Overview
The impact of flying operations against equipment and components installed on
an aircraft needs to be tracked and recorded.
This program contains all dimensions / counters that can be defined for each
aircraft type and rotable part.
You can add any pre-defined counter template to your aircraft types and rotable
parts but you can also individualise your counters to a specific aircraft or rotable.
Counter Management (APN 2031) Rule for APU Hours
For the purposes of this exercise, we have pre-defined all data that is labeled
as a Step. In your productive environment, you will also have to define these
data. This is the reason for the detailed description below.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-25 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
The data that you will have to enter during this training will be labeled as
Exercise.
The "Counter" and "Counter Template" for the purposes of recording and
tracking of APU Hours has already been defined in our AMOS Training
Database.
The following steps that have been performed to define the AH (APU Hours)
Counter are listed below for your information only:
Step 1 - Definition of the Counter
Counter Definition Groups Tab
Click on: New
Code: AH
Name: APU Hours
Display Format: Time Amount
Click on: Save
Click on: New
Code: AC
Name: APU Cycles
Display Format: Time Amount
Click on: Save
Because this counter will be "Readable" (values will be entered manually) it
does not require a Rule.
If however, your APU Hours are not entered manually but calculated from a
ratio of the Aircraft Flight Hours, then a Rule will be required.
Step 2 - Definition of the APU Hours as a Master Counter Template Group
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-26 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Counter Template Tab
Group Name DEF_AH-AC_Master
Description: Default Counters plus APU Hours- Cycles Master
Reference: Part
Click on: Save
Click on: Add
Counter Definition: AH
Description: Master Counter AH
Counter Type: Master
Counter Value
Manual readout
Creation:
Click on: Save
Click on: Add
Counter Definition: AC
Description: Master Counter AC
Counter Type: Master
Counter Value
Manual readout
Creation:
Click on: Save
Click on: Reassign Reference
Choose Reference
Part / 3800708-1
(s):
Choose a new DEF_AH-AC_Master
Counter Template
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-27 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Group
Create XX
Counters Yes (ticked)
which are new...
Counter Remarks: New Counter Group created
Repeat the steps above for a new Counter Template Group for AH which
will be used as Child Counters assigned to the subcomponents and then
assign the affected part(s) to the group.
Exercise - cross check an actual Rotable
We will now cross check the information we have about the APU.
The APU will be "Readable" (values will be entered manually) from Techlog or
Work Order.
Create a Work Order to readout APU Hour/Cycle from A/C
APN 1418
Click on: New system W/O
Choose Maintenance
Click on: Next
Fill A/C A327, ATA 49-00,
Confirm Date, time ….
Click on: Next
Headline and Description: READ OUT APU
Fill
HOUR/CYCLE,
Click on: Finish
The WO number will
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-28 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
pop out
Click on: Action
Confirm Date, time, headline….
Fill action PERFORMED TO READ OUT APU HOUR/CYCLE,
Tick Work on step completed -> Close work step
Confirm Performed sign
Click on: Finish
Click on: More
Click on: Counter Update
Choose APU (what is installed on A/C A327)
Confirm Date, time….
Display value
Fill APU Cycles: 20000
APU Hours: 21000
Click on: Finish
Then Close WO
Confirm Date, time, choose Flight leg ……
Click on: Finish
Select the result
APN 308 or 3021
Choose A/C A327, tab Counter
The entry that appears is the historical APU Hour/Cycle information or
Read out information (date, time, WO….)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-29 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Counters with Rule - Penalty Factor on Non-StandardRunways
We need to create a new Counter which adds a penalty factor to the Main
Landing Gear (MLG) if we have a arrival / departure on an airport with a non-
standard runway. In this exercise we are using BSL.
Two parts are affected in this example: P/N 201581001-01 MLG and P/N
201540302-01 Torque Link with a Life Limit requirement.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-30 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Create the following rule:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-31 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Maintenance Event Initialiser (APN 1895)Overview
This program is used to initialise all Maintenance Events (Checks, Documents,
Rotables, Requirements and Taskcards) created in AMOS and synchronise
Time Requirement and MP Revision
The program offers the following functions:
Multiple search criteria available based on the maintenance event.
Display of the work template for not yet initialised maintenance events
Display of workorder/planning information for pending events
Multi-Selection for both, not yet and already initialised events
Synchronization of Time Requirements
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-32 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Maintenance Event Browser (APN 2151) Overview
The program offers the following functions:
Multiple search criteria available based on the maintenance events.
Display historic, current, and future maintenance events.
Display the details, work templates, and in the history tab, the related
Workorders issued.
View a summary and any transfer information of a selected maintenance
event.
Allow direct modification using advance administrative tasks (appropriate
buttons)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-33 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Workorder (APN 1418) Overview
Event Tracking / Transfer WO / Damage / AD-HOC JIC and Structural Damage
Event Tracking (APN 432)
Event Tracking gives the Maintenance Controller the tools to record all events
which impact on the operation of the A/C or a Station. Events can be classified,
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-34 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
given ‘advise’ times and a log of the actions taken to resolve the event can be
kept within the program.
Scenario:
During the last flight to ZRH, the pilot reported possible hail damage.
MCC created an unscheduled W/O and sent a line maintenance technician to
the aircraft to check for structural damage. The technician found a dent and
contacted us in the Enginnering.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-35 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Assemblies with Configuration Definition
Configuration Definition manages and controls aircraft, assembly and E-
enabled configurations. It is designed to meet the extensive software
requirement, especially on new generation aircraft.
For a given aircraft configuration, it is possible to define the list of Functional
Positions which identifies a functional area on the aircraft. This code must be
unique for a given configuration. On each functional position, you will have the
possibility to define rules and conditions in order to specify which parts or
software can be installed.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-36 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Assemblies - Receiving of an Assembly (APN 2121)
Search for Part
3800708-1
Number:
Click on: Search
Select the Order containing Part Number 3800708-1 only
Click on: New Receiving
Receiving Date: Today
Click on: Save Receiving
Click on: Process Receiving
Part No.: 3800708-1
Serial number: 12701
Condition: N(ew)
Owner: HVN
Received Location: HAN
Certificate Date: -4w
Certificate Company: EPCOR
Click on: Add
Certificate Type: Choose E1 = EASA 145
Form Tracking
EPCOR-12703
Number:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-37 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Certified by: EPCOR
Click on: Add
Click on: Receive Physically
Inspection Date &
Confirm Proposals
Time:
C (Flight Cycles) 0
H (Flight Hours) 00:00
Manufacture Date: -4w
Click on: Save
Because you are receiving an assembly, you have to enter information
about the sub-components of the assembly.
Click on: Tree Receiving
Click on: Show Configurations Tree
In displayed dialog AMOS will present to you all possible Assembly
configurations for the highest part number. Here: The only possible
configuration is pre-selected
Click on: Import & Close
Type the Serial number of all delivered sub-components (all other sub
components are missing):
Part Number Serial Number
3800708-1 12701
2704506-5 12701
3886188-2 12701
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-38 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
3805057-1 12701
3822400-5 12701
3840161-1 12701
3840165-4 12701
3822391-6 12701
3822504-3 12701
3291432-1 12701
3291238-2 12701
3876287-1 12701
3888058-7 12701
70722365-2 12701
70210-160494-1 12701
4131020-4 12701
3616140-7 12701
Click on: Save (to save the entered Serial Numbers)
Click in the Description field and multiselect in the same field by holding
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-39 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
down the CTRL key and click on all other P/N with a SN to be received.
Click on: Apply to
Tick Condition N (New)
Select New TSN: 00:00
Select New CSN 0
Select MFG-Date: -4w
Click on: OK
After you entered the information you have to check the requirements in
column Additional Data of the received parts and adjust the data according
the shipped papers.
Double click on:
In the upcoming window search for the section "LL Life Limit". This will
be different for each rotable depending on the assigned requirement.
Click on: OK
IMPORTANT:
This needs to be done for each single part, within the tree, which is
received.
When the data has been correctly entered the icon will change:
Click on: Save
Click on: Finish Component Inspection
AMOS will indicate if any of the received part numbers are within the
effectivity range of a document, previously entered into AMOS, and the
user will be presented with a number of options to select from.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-40 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
The paperwork delivered with the affected component shows that the
modification is performed.
Select: the listed Modification
Initialisation tab
Select: the listed Modification
Click on: Initialise
Select: the listed Modification
Choose Status... Select Ex-Factory
Click on: Next
Review the given forecast
Click on: Finish
Un-Tick: Open & not assigned Mods only
Review result
Click on: Exit
Open Configuration Control (APN 3128):
Aircraft or Component section
Click on: Component
Partnumber: D23589521
Serialnumber: 12701
Click on: Search and select the result
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-41 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Click on: (Check Config)
Review the result / current status of your assembly
Click on: (History)
Review the result / current status of your assembly
Click on: Report
Report: Choose and click on OK
Preview the Life Limit Part Status Report
Assemblies - Component Tree Label Booking (APN184)
This exercise will show you how to install one of the missing sub-components
when an assembly is still in the store. Assembly P/N 3800708-1 is incomplete,
but we have one of the missing sub-components (P/N 3291432-1) available in
our training store.
Before the item can be installed onto the assembly, you first need to order this
item from Stores, i.e. you need to issue a Pickslip (= material request). Then
Stores will confirm the Pickinglist with the allocated serial number. The sub-
component can now be installed onto the assembly.
Need to create the Reference-Tree (APN 246) for APU P/N 3800708-1 (include
P/N 3291432-1)
Create the new Order (APN 2015) for P/N 3291432-1, then go to Good
Receiving (APN 2121) to put P/N 3291432-1 into store.
Pickslip Request (APN: 225)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-42 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Click on: New
Mech. Sign: Your training login sign
Receiver: HONEYWELL
Part needed: 1x 3291432-1
Click on: Send to Store
Write down your Pickslip Number: _ _
Picking List Management (APN: 2612)
Pickslip No: Enter your Pickslip Number from above
Click on: Search
Picking List / Requests
section
Select your requested Part Number
Write down the allocated Serial Number: _
Booking Sign & Date (Mid down) and Allocate
Confirm:
Material
Click on: Book
Component Tree Label Booking (APN: 184)
Partnumber: 3800708-1
Serialnumber: 12701
Click on: Search
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-43 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Configuration tab
All missing parts of the assembly are indicated with
Select line with 3291432-1
Partnumber
Click on: Install
Station: HAN
Confirm: Date & Time
Performed By: Your login
Click on: Next
Select P/N 3291432-1& your Serial number reported above
Tick: Special Booking & Installation only
Click on: Finish
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-44 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Assemblies - Replacement of an Assembly with partstransfer
To install the assembly which we have completed in the former exercise, we
need to complete the corresponding Workorder.
But first we have to find the Workorder.
Open Workorder Information System (APN 1):
Select A/C: A323
ATA: 49
Description Text /
REPLACE APU
Headline:
State: O (open)
Click on: Search
Double click in the WO field to open the workorder
Workorder (APN 1418):
Click on: (Part Request)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-45 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Click on: Add
Part Number: 3800708-1
Qty: 1
Click on: OK
Click on: Save
Because you have added a Part Request to your Workorder, the "Create
Pickslip" pop-up will open automatically. (It can be disabled in Form
Configuration by your AMOS Administrator, APN 1444).
Click on: Issue Pickslip
Pickslip Request (APN: 225)
AMOS will complete all of the relevant information for you. Please review
the details before the next step.
Click on: Send
You will receive a pop-up informing you that the pickslip has been issued.
This pop-up also includes the pickslip number.
Write down your pickslip number
Click on: OK
Now confirm your pickslip as follows:
Open Picking List Management (APN: 2612)
Enter your pickslip number and click on Search
Picking List / Picking List Details / Selection Panel
Select the line with: P/N: 3800708-1 and S/N 12701
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-46 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Click on: Take
Confirm: Booking Sign & Date (mid down)
Click on: Book
Please close the program Picking List Management and return to your
Workorder. By loading theWorkorder, you will see that the part request is
confirmed.
Continue Workorder (APN 1418)
Click on: (Action)
Confirm Date, Time & Headline
REPLACED APU
Action Text: WO COMPLETED
Performed Sign: Your Login
Click on: Next
Click on: (Add Time)
Add for AASP, FKSM and your Login 04:00 hours each
Click on: (Component Change)
ON-Part
Part No: 3800708-1
Serial No: 12701
Cerficate No. Confirm Suggestion
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-47 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
OFF Part
Part No: 3800708-1
Serial No: Double click and select entry
Position: Confirm
Click on: OK
Click on: Finish
The Labelbooking dialog will open automatically. (It can be disabled in
Form Configuration by your AMOS Administrator, APN 1444).
Click on: Counters
Click on: OK
Removal Store: Confirm the suggested store by AMOS
Removal U/S
Confirm the suggested location by AMOS
Location:
Click on: Book Label
You are installing an Assembly with missing sub-components (LRU). The
Assembly you are removing is complete. You can transfer the serviceable sub-
component(s) from the Assembly you are removing, on to the Assembly you
are installing. AMOS will present the "Define Transfer LRU’s" Dialog Box
Items to Install section
Select the first entry marked with (Missing part)
Matching LRUs tab
Tick check box in Transfer
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-48 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
column
The transfered P/N & S/N is shown beside
Repeat this for all missing LRUs. Double check if you have all missing LRUs
transfered.
Click on: Continue Label Booking
Click on: Exit
The Assembly is now installed, and complete. You can check this in the
program Rotables Administration (APN: 147)
The workorder can be closed now and the A/C can be released:
Click on: Close
Closing Station: HAN
Closing Date: Today
Closing Tim: Now
Approval No. Confirm sugesstion
Closing Sign: Your login
Tick: CRS
Released to service under Approval certificate
Select:
number....
Release Sign: Your login
Open Configuration Control (APN 3128):
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-49 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2.6 Engineering Part 2
Aircraft or Component section
Click on: Component
Partnumber: 3800708-1
Serialnumber: 12701
Click on: Search and select the result
Click on: Check
Review the result / current status of your assembly
Click on: History
Review the result / current status of your assembly
Click on: LLP Status and OK
Preview the Life Limit Part Status Report
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.6-50 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2.7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
HARDWARE CONFIGURATION & ASSEMBLY HANDLING
Hardware Configuration & Assembly Handling process
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-1 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2.7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Introduction - Business Processes and modules
Business Processes:
Engineering
03.05 - Configuration Management
03.04 - Modification Control
03.02 - Part Definition
Maintenance
08.05 - Component Removal/Installation
Technical Records
08.05 - Component Removal/Installation
Store
06.02 - Goods Receiving
AMOS Modules:
Configuration Definition (APN 2818)
Configuration Control (APN 3128)
Part Administration (APN 59)
Aircraft Administration (APN 308)
Rotables Administration (APN 147)
View/Edit Modifications (APN 63)
Order Management (APN 2015)
Goods Receiving (APN 2121)
Component Inspection and Records (APN 2293)
Basic Tables
Many AMOS tables are defined in Basic-Data Administration, APN 18.
For this training, the following tables shared with many other programs, will be important:
- Aircraft Type
- ATA Chapter
- Position
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2.7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Another table used in this module is defined in APN 2627 and it is called
- Aircraft Systems
Parameter and Workflows
1675 - Use "CONTROLLED FUNCTIONAL POSITIONS" / "NEW CONFIGURATION
MANAGEMENT" in "COMPONENT TREE LABEL BOOKING"
1723 - Activate Tree Receiving with Config Management
1732 - Use configurations in Parts Consumption Forecast
Whenever needed, you can check directly what parameters and workflows
(and their present condition) accessing the "About" section of each APN:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-3 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2.7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Introduction - Exercises overview
Configuration Definition, APN 2818, handles hardware and software
configuration and provides you with the following benefits:
control of hardware (both for the full aircraft and its sub-assemblies) and
software configurations in one single program
compliance with the ATA 2400 data exchange standard
extensive configuration check and comparison tools
SB/modification related configuration changes
set priority on the allowed Parts (e.g. preferred or mandatory PN to be
procured)
integration with the effectivity framework already used in all amos
maintenance events (part requirements, checks, modifications and
maintenance programs taskcards)
enhance the receiving process providing import-from-file and auto-populate
features
Configurations can be small and easy (e.g. slide assembly with cylinder) or very
complex (e.g. engine and, ultimately, the aircraft itself).
Each assembly/aircraft configuration might contain sub-components that are
assemblies as well (e.g. APU has a fire extinguisher containing two cartridges).
In the following exercise you will learn to build a configuration from the smallest
assembly up to the aircraft configuration.
We will use a simplified structures for training purposes.
The chart that follows, introduces the first part of the exercise with the exercise
flow, a graphical representation of it and the AMOS result.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-4 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2.7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Exercise 1 - Creation of simple configuration - Fire Extinguisher
In this exercise, you will learn how to create a simple assembly configuration.
Imagine a fire bottle, that has two cartridges on it to be tracked. First we need
to create the PN in APN 59.
Open Part Administration (APN 59):
Click on Create Part
Partnumber 474152-01
Description Fire Extinguisher
Material Class Rotable
Material Type P
FA Type 32S
ATA Chapter 26-00
Click on: Save Working Copy -> Publish
You can enter a booking text that will be visible in APN 188 for tracking
purposes.
Click on OK
Open Configuration Definition (APN 2818)
Click on New (LH side)
In the first wizard New Configuration, then Next
step, choose
Choose Type Assembly Configuration
Name 01 - Fire Extinguisher
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-5 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2.7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Description Configuration done by ... (your name)
Click on Import current alternates in effectivity list
Or Effectivity for main P/N only
Partnumber 474152-01, then Next
Click on Create
The Effectivity of this 01 - Fire Extinguisher configuration was created with
All S/N.
To change S/N, click to:
To add the other Effectivity P/N, follow the below step.
Click on + EFF (Add effectivity P/N)
Title Fire Bottle 474152-02
Partnumber 474152-02
Click on Next
Select Tickbox All Serial Numbers
Click on Finish
Click on: De-/Activate, to activate your effectivity, then Yes
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-6 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2.7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
We will now proceed creating the two positions where the cartridges are
located.
These positions are called "functional positions" in AMOS, and they are typically
named after
OEM-provided codes (e.g. FIN codes for Airbus). For this training we will use a
terminology that helps understanding.
Tab Allowed Configuration
Select your configuration (should be 01 - Fire Extinguisher)
Click on: + FP (Add new Functional Position)
FP Type: Hardware
Code: CARTR_TOP
Click on: Next
ATA Chapter: 26-00
Click on: Finish
A functional position can be applicable to all or some of the PN's the
configuration applies to, so we need to define the effectivity here as well. In this
case we will assume both cartridges are always to be tracked when dealing with
this configuration.
Select the newly created Func. Position
Click on: + EFF (Add effectivity)
Click on: Finish
Select Effectivity underneath the Functional Position name
P/N List section
Click on New
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-7 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2.7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Part Number 30903898
NOTE:
With the "Status" list, you can set if this P/N is
Allowed, Preferred or Mandatory.
This will have an effect on:
the material allocation for unscheduled events
label bookings (depending on setup of workflow
183)
APN 2818 checker tab comparison results
Validity dates will also give chance to restrict an
allowed P/N for a certain period only.
Click on Add then Save
We will now add the second FP, for the second cartridge.
Repeat the above steps, to create a second
FP called CARTR_BOTTOM, where
only PN
30903899 is allowed.
Hint: you can try the Clone button to create one
FP starting from an existing one, but careful: it
also copies the P/N list!
Part Change P/N 30903898 to 30903899
We now have one configuration, applicable to one Fire Extinguisher PN, with
two FP's, one for each cartridge.
We will now learn how can we use a certain configuration for more parts.
Another fire extinguisher P/N 472088-1 uses exactly the same configuration:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-8 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
The configuration is also applicable to PN 472088-1, so we will include it in the
configuration effectivity.
Select Uppermost configuration level
Click on + EFF (Add effectivity)
Title Fire Bottle 472088-1
Partnumber 472088-1
Serial Numbers All Serial Numbers
Click on Finish
NOTE: If the affected P/N's have a similar root or structure, another option would be
to revise the existing effectivity row, using "wildcards" to include both P/N's in one row.
For the second fire bottle, we can reuse the same functional positions. As we left the
FP effectivity very general, we do not need to add P/N 472088-1 to them. If a FP
applies only to specific main assemblies, then its effectivity would have to be defined
accordingly to precisely set the higher assy part numbers the FP is applicable to.
We have now a configuration that applies to two main PN's.
Every effectivity and P/N list definition needs an activation. This is a lot of manual
work that can be left at the end of the configuration, as activating the configuration will
automatically activate everything underneath:
Click on: De-/Activate (left side)
Click on: Yes (to confirm)
Review the resulting tree, expanding all the configuration levels (hint: use the +/-
button at the bottom-right corner of the panel).
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-10 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Exercise 2 - Assembly withsubconfiguration - APU
We will now create another configuration, this time for an APU, and we will later
inlcude the fire extinguisher in it.
Copy an existing P/N to get a new one to work with.
Open Part Administration (APN 59):
Partnumber: 3800708-1
Click on: Load
Click on: Copy Part
From: 3800708-1
To: 3800708-101
Click on: Copy, then OK, and then Exit
Instruction for the trainer only!!!
Set as two ways 4950597-1 and 4950597-2
alternates
We will now define a configuration for this APU. Open Configuration Definition (APN
2818):
Click on: New (LH side)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-11 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Choose: New Configuration, then Next
Type: Assembly Configuration
Name: APU 3800708-101
Description: APU configuration for 3800708-101
Settings
Click on: Import current alternates in effectivity list
Or Effectivity for main P/N only
Partnumber: 3800708-101
Click on: Next
Click on: Creat
The Effectivity of this APU 3800708-101 configuration was created with All
S/N.
To change S/N, click to:
To add the other Effectivity P/N, follow the below step.
Load the new + EFF (Add Effectivity)
configuration, & click
on:
Partnumber: 3800708-201
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-12 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Click on: Next
Select: All Serial Numbers
Click on: Next
Rotable Owner: HVN
Click on: Finish
We will now define the functional positions, and again for the goal of the exercise, we
will use terminology that helps understanding, rather than OEM codes.
Select: uppermost level of the configuration
Click on: + FP (Add new Functional Position)
FP Type: Hardware
Code: TURBINEDISK
Click on: Next
Line Replaceable unit: NO (leave unticked)
Click on: Finish
We do not need to define a part number for the effectivity if the FP is always applicable
in the configuration.
Click on + EFF (Add Effectivity) then Finish
Select Effectivity underneath the Functional Position name
P/N List section: Add allowed P/N 3840165-4
Repeat the steps to create the functional position, to add the following ones, with the
relevant allowed P/N
Functional Position Allowed Part Number(s)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-13 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
COMPRESSOR DISK 3822391-6
THERMOCOUPLE LH 4950597-1
(this is a Line including alternates
Replaceable Unit FP!)
HINT: Use the Clone button to copy from the LH
THERMOCOUPLE RH thermocouple FP
(this is a Line 4950597-1
Replaceable Unit FP!)
including alternates
FIRE EXT 474152-01
(this is a Line
Replaceable Unit FP!)
This last P/N, is exactly the one we built a configuration for, in the first exercise. As a
final step for this exercise, we will activate and review the APU configuration.
Click on: De-/Activate (left side)
Click on: Yes
Review the configuration / sub-components select uppermost level of the
configuration
Click on:
(Show P/N Tree)
Another view can be found clicking on GRAPH (Show Config Graph)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-14 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
To see this and other available filters/grouping settings, click on the "funnel" icon on
the top right of the Configuration section.
Exercise 3 - Create an A/C configurationincluding assemblies
We will now create a small A/C configuration with 2 engines and one APU.
NOTE: for this exercise each configuration will be applicable to one S/N only, to
avoid any overlapping between exercises.
Before you proceed, the trainer will show you how you can create an allowed
configuration from an existing reference tree.
Open Configuration Definition (APN 2818):
Click on: New (LH side), then Normal
Type: Aircraft Configuration
Name: Configuration for A324
Click on: Finish
Click on: + EFF (Add Effectivity)
A/C Type: 32S
Click on: Next
Click on: Include existing Serial number
Search and select: A324
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-15 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Click on: OK then Finish
Select the uppermost configuration level, and create three HARDWARE FP's, using
the same process used for the assembly, with the following details.
Hardware Allowed Part Number
Functional Position
ENGINE LH V2533-A5
ENGINE RH V2533-A5
APU 3800708-101
Activate the A324
configuration for
Exercise 4 - Configuration Assignment and FP allocation
Once a configuration is ready to be used, it can be assigned to the relevant A/C.
Load Configuration for A321
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-16 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Click on: Assign (LH, Assign Configuration)
Click on: Search
See Overview
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-17 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
AMOS will show you what will happen if you proceed with the assignment:
Rotables already on the aircraft on uncontrolled positions will be moved to a
controlled position (namely functional position) if:
the functional position is available (not yet allocated) AND the FP
name is the same as the old position OR the PN accepted on that FP
is matching.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-18 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Exercise 5 - Configuration check and review
Go back to Configuration Definition (APN 2818):
Reload Configuration for A324
Tab Checker
Assignments: Choose A324
Section As Booked
Click on: Check
Review the result in sub-tab As Booked:
Some rotables do not have FP
Some rotable do not have installation information (P/N and S/N)
Some rotable have different about allowed P/N
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-19 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Exercise 6 - Configuration Revision
Your trainer will now setup a document that will be needed later on.
For the trainer ONLY
If not existing, create SB A320-49-1185 in APN 63 with these
details
Subject: NEW TURBINE DISK WITH BUILT-IN BLADES (BLISK)
Issued by: 06848
Type: Component
Applicable to: 3800708-101 (wildcard to include all trainees' APUs).
Time Requirement: unlimited, single event
Auto Assign to open
Run the task EffectivityApplicabilityService once.
(You can also right click on the header level of the effectivity in APN 63 and
then select Document > Action > Update Applicability)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-20 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
In this exercise we will learn how a configuration can be revised depending on aviation
industry and company needs.
Example: A SB introduces a new turbine disk for the APU. Once the APU is post SB,
only the new P/N can be installed.
Open Configuration Definition (APN 2818):
Load configuration: APU 3800708-101
Click on: Manage P/N (left side)
Type: Hardware
Document: A320-49-1185
Current Partnumber: 3840165-4
Activate option: PRE document only
New Partnumber: 3842107-11
Activate option: POST document only
Click on: Next
De-select all configurations except APU 38000708-101 and EXCLUDE
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-21 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
them. Double-check if all other configurations are shown in RED
Click on: Finish
Review the Effectivities and the Rules created for Functional Position TURBINEDISK.
Exercise 7 - Receive an assembly with a configuration
We will now simulate the receiving of an assembly for which a configuration exists.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-22 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Your trainer will first guide you through the creation of a purchase order that will then
be received. Open Order Management (APN 2015):
Click on : New Order
Select: P (Purchase) and OK
Order Date: today
Vendor: HWELL
Issued by address: HVN
Click on:: Save
Order detail 1
Click on: Add Detail
Part number: 3800708-101
Required condition: OH
Unit Price: 500'000 USD
Click on: Save & Issue
Purchase Order
Number:
The APU has arrived at your store. Search for your order and book the receipt. Open
Goods Receiving (APN 2121):
Click on: Search
Click on: Process Receiving
Qty / Backorder: 1
Partnumber: 3800708-101
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-23 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Serial No.: 0101
Condition: OH
Owner: HVN
Location: HAN
Certificate Date: -1w (1 week ago)
Certifying Company: HWELL
Click on: Add
From the Drop-Down E1
Menu, choose:
Certificate Number: CRT1201
Click on: Add
Click on: Receive Physically
The Component Inspection & Records (APN 2293) dialog appears
automatically
C (Flight Cycles): 10000
H (Flight Hours): 13000:00
Manufacture Date: -5y
Click on: Save
It's at this stage that we will see the effect of the configuration we created.
Click on: Tree Receiving (middle)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-24 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Click on: Show Configurations Tree
Click on: Import then Close
You will see two sections on the right side (Hint: you might have to move
the dotted line at the far right to see the second section).
You now have two options: import and manual entry.
Manual entry of serial numbers
We will now load our configuration
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-25 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
In the resulting configuration, fill in the relevant PN and SN information
Functional Position Part Number
Serial Number
TURBINE DISK 3840165-4
01123
COMPRESSOR 3822391-6
DISK 01789
THERMOCOUPLE 4950597-1
LH TH3401
THERMOCOUPLE 4950597-1
RH TH7801
FIRE 474152-01
EXTINGUISHER
01938
CARTR_TOP 30903898
01A12
CARTR_BOTTOM 30903899
01A56
Click on Save any time you want to ensure your changes get stored in the system.
In this exercise, we will assume the subparts are all overhauled with the same APU
utilisation, except the cartridges which are new
Left section: click on: the description field of the first subcomponent.
Keep the Ctrl key pressed on your keyboard and
select all subcomponents except the cartridges
Click on: Apply To
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-26 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Condition: OH
New TSN: 13000:00
New CSN: 10000
Mfg. Date: -5y
Click on: OK
Do the same to for the cartridges, to set these details:
Condition: N
TSN: 00:00
CSN: 0
Mfg. Date: -1m
Click on Save any time you want to ensure your changes get stored in the system.
Requirements of main assembly and subcomponents
While requirements for the main assembly, if any, are listed in the "Requirements"
tab, for each subcomponents affected by part requirement an icon with a "spanner"
will appear in the Additional Data column.
Double click on the spanner icon for the turbine rotor
Review the information and the "To Go" information, and confirm this
dialog.
Reviewing the part requirement, turned the icon into a green tick
confirmation symbol
Repeat the above for any components having requirements to be checked.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-27 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Component Modifications handling at receiving
When documents are applicable for the main assembly or any
subcomponents, the Component Modifications tab will show list them for
appropriate actions.
In our environment, we have set up workflow 320, that triggers a popup
after the component inspection to review and act as needed.
This workflow is not needed if component modifications have to be handled by a
different department at a later stage.
Click on: Finish Component Inspection
Review the dialog with the modification(s)
Select: A320-49-1185
Review the tab-sheets
Here, if not already assigned or closed, a document could be initialised
to then make it available to the planning department. In this exercise we
will skip this step.
Click on: Exit
Review P/N 3800708-201 / S/N 0101 in Rotables Administration (APN 147),
especially the tab called "Assembly".
Assembly Configuration Review
Open Configuration Definition (APN 2818):
Load configuration 3800708-101
Tab Checker
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-28 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Assignments P/N 3800708-101 / S/N 0101...
dropdown list: select:
Section As Booked
Click on: Check
Review the result in the As-Booked tab
We will now simulate (with a shortened process, for demonstration
purposes only) the accomplishment of the SB used previously in the
effectivity rule creation.
Open View/Edit Modifications (APN 63):
Document No: A320-49-1185
Click on: Search
Tab Status
Select: Assign
Choose in drop-down Closed
list:
Click on Pane: 3800708-101 / 0101
Click on: Assign
Go through the wizard click on Next, reviewing each step until you
get the Finish button. Press OK to confirm the upcoming pop-up
windows.
Notice the colour change on your rotable.
Open Configuration Definition (APN 2818):
Load configuration 3800708-101
Tab Checker
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-29 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Assignments P/N 3800708-101 / S/N 0101...
dropdown list: select
Section As Booked
Click on: Check
Review the result in the tab As-Booked
Configuration Control (APN 3128)
Configuration Control is the central place to visualise and manage as-
booked configurations. Intended for for maintenance control centre or
configuration engineers.
The available actions in this program can be divided into 4 groups.
Booking
Replace Opens the Replace wizard allowing you to:
Swap rotables on the same aircraft.
Swap rotables between aircraft.
Correction
Assign position Assign a functional position to a hardware component.
It opens the Assign functional position window
allowing you to select the functional position to which
you want to assign the component.
Assign configuration Assign a configuration to an aircraft. The same
function is available in Configuration Definition, by
clicking Assign button under Allowed Configurations
section or Allowed Configuration tab.
Verification
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-30 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Check Triggers an immediate check of the current
configuration with respect to the last booking actions.
History Opens the Check History window listing all the
verifications you have performed by clicking Check
button.
Reports
Equipment List Displays the Report Generator window from
where you can print:
For aircraft: the Aircraft Equipment List Report
For components: the Component Equipment List
Report
Soft-Limit Displays the Report Generator window from
where you can print the Component Soft-Limit
Report. This report is only available for
components
LLP Status Displays the Report Generator window from where
you can print the LLP Status Report. This report is
only available for components.
Click on: Component
Part Number: 3800708-101
Serial Number: 0101
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-31 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
Click on: Search
Select the component and review the results.
Reports LLP Status
Try to load your A/C configuration and run the Check from here, then
create and review the following reports: Equipment List, Aircraft
Summary, Installation & Removal
Aircraft Administration (APN 308)
Check the assignment of an aircraft configuration
Configuration Control (APN 3128)
Explain the importance of the module
Show the manually assignment / correction of missing / wrong positions
Execute a Verification Check and show the history
Create and explain important Reports like EQUIPMENT LIST and LLP
STATUS
Goods Receiving (APN 2121)
Show how to star with the 1st step of an assembly receiving (Role:Store)
Component Inspection & Records (APN 2293)
Explain the two different methods of receiving of sub components (Import
an Serial number file or creating is manually)
Show and explain how to receive and assembly
o Define TSN, CSN, MFG Date of highest / higher part number
o Update existing requirements if given
o Select the corresponding Configuration
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-32 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
2. 7 HARDWARE CONFIGURATION & ASSEMBLY
PART 2: AMOS ENGINEERING
HANDLING
o Check for each sub component TSN, CSN, MFG Date and Condition
o If given: Don't forget to check Requirements, Update Warranties etc
Decide if the assembly is in an acceptable version for your company
Explain again the differences of missing LRUs and not LRUs. What are
the consequences in AMOS?
Rotables Administration (APN 147)
Check the actual status of an assembly
Show all important tab sheets and explain the content
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.7-2-33 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
SOFTWARE MANAGEMENT MODULE
Software Management Overview
Software Management is a program to manage software. This includes:
Defining the software number (part number for software).
Defining software locations.
Assigning Software Copy IDs to a location.
Note: Software Media Types and Software Types must first be defined in Basic-
Data Administration > Engineering tables > Software Management tables.
Software Management Process
03.15a – S/W Config. Management (Software Management)
Define and administer aircraft software. “Authorized & System Configuration”
Input
03.05 03.12a 03.03 03.04 New partnumber is 08.04
Start
Configuration Aircraft Maintenance Modification required (Modifications, Workorder
Management Phase in Program Control CMM, IPC, SIL ..) Process
Boeing 787?
Yes
03.15b
S/W Config.
Management
Boeing 787
Authorized
Configuration
Report
Tracking of current
Software installations
Software Tracking and historical installation
No (APN 1832)
Engineering
Boeing Pharser
(APN2333) End
Aicraft reference configuration,
- Define: Systems, new FP, installations
rules.
E-enabled 03.05 - Define PF-Ref.Tree for each Aircraft.
Data - Transfer Software Configuration - Create and monitor Rule Packages
(APN261) Configuration per Management applicable for several FP
A/C tail - Compare “As-Flying vs Authorized vs
System”, “System vs Authorized” and
Files to Upload: “System vs System”
XACSYSTEM
XCONFCONFIG
XCONFFP
XCONFFPHEADER
XCONFPPROP
XEFF
XEFFSER Flying Configuration
acc. Aircraft (XML)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-1 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
03.15b - S/W Config. Management (Software Definition)
Define/Update Software Partnumber and decide the Purchase process if existing
Start
Input
Software change with
New partnumber
03.15a unknown new
is required
S/W Config. Workorder software partnumber
(Modifications,
Management (APN 1418) installed on
CMM, IPC, SIL ..)
Workorders
ValidatIon
according to
provided
documents
Locations Tab
SW to be 03.02
Software Software - S/W Location
purchased in Yes Downloaded No Part
Management Management - S/W Location Description
AMOS Definition
(APN 2618) (APN 2618) - S/W Storage Type
Definitions Tab
- S/W Part No.
Engineering
- S/W Description
- S/W Revision
- S/W Type If Downloaded:
- S/W Media type S – order for P/N: LSAP,
- S/W Aircraft Type (Service Partnumber)
- S/W Vendor Yes Specification: SW P/N
- ATA Chapter
- Issue Date
05.02
- Effective Date
Purchasing
- Expiry Date
No
03.15a
S/W Config.
Management
Boeing 787 Authorized Configuration Parser (APN 2333)
Effectivity type must be Scenario:
You have phased-in a Boeing 787 with the provided data at the point of ToT
(Transfer of Title) from Boeing. Your tail number is GAA. All Part Numbers, Software
Numbers, Software Locations, Software Copies and Rotables are uploaded to
AMOS.
Together with the ToT Boeing provides you with an "As Delivered Authorized
Configuration" containing all Functional Positions and the links between Hardware
and Software. This configuration we have to upload for your Aircraft
With the Boeing 787 Authorized Configuration Parser (APN 2333) we have to create
Text-Files (XFiles) which can be uploaded to AMOS. Contact your AMOS
Administrator in order to upload the files in your Productive Environment.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-2 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Note: The following steps will be performed only by the trainer.
Open Boeing 787 Authorized Configuration Parser (APN 2333):
Click beside the field Authorized Configuration file:
Browse to the Authorized Configuration File (As-delivered Converted Auth
Config prefix_GAA.XML) provided by Boeing.
Select the file and Open
click on:
Click beside the field Output Folder:
Browse to the folder where AMOS should store the Text-Files (XFiles) e.g.
Desktop. The instructor will assist you if needed.
Mayor Type: 787
Effectivity Type: Choose A/C Type
A/C Registration or 787
A/C Type:
Aircraft Configuration GAA_2015-02-25Z
Name:
Click on: Create XFILES
AMOS creates the following Text Files (XFiles) wich needs to be uploaded in the
system:
XACSYSTEM.txt A/C System
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-3 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
XEFF.txt Name and A/C (Type) Effectivity
XEFFSER.txt Effectivity Ranges and Serialnumbers
XCONFCONFIG.txt Name and Description of the configuration
XCONFFP.txt Configuration Functional Position
XCONFFPHEADER.t Configuration Position Header
xt
XCONFFPPROP.txt Configuration Functional Position Properties
Before you upload the Text-Files (XFiles) you have to create two missing settings
manually. Open Aircraft Code Definition (APN 2627):
Select A/C Type: 787
System tab
Click on: New
Code: N/A
Description: NOT APPLICABLE
Click on: Next
Click on: Finish
Open Data Transfer (APN 261) to upload the Text-Files (XFiles) to the system.
NOTE: importing these xfiles on the client side might be a lengthy process.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-4 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
To make sure the process is faster, execute them on the server side by selecting the
tickbox "Execute Transfer on Server" before you start, and monitor the progress in
the "Server Transfer Status" tab
For trainer : The next step is already done. Needs to be done only once for the
whole fleet.
Don't forget to tick "Execute Transfer on Server"
Click on the > in front of "Aircraft Setup" in the tree structure on the left side:
1. Upload XACSYSTEM.txt
Click on: XACSYSTEM
Click on: Browse and browse to the file XACSYSTEM.txt
Click on: Open
Click on: Preview XACSYSTEM
Click on: Primary Check XACSYSTEM
Click on: DB Check XACSYSTEM
Click on: Yes
If there are no errors close the appearing window
Click on: Transfer XACSYSTEM
For trainer : The next steps needs to be performed.
Click on the > in front of "Effectivity" in the tree structure on the left side:
2. Upload XEFF.txt
Click on: XEFF
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-5 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Click on: Browse and browse to the file XEFF.txt
Click on: Open
Click on: Preview XEFF
Click on: Primary Check XEFF
Click on: DB Check XEFF
Click on: Yes
If there are no errors close the appearing window
Click on: Transfer XEFF
3. Upload XEFFSER.txt
Click on: XEFFSER
Click on: Browse and browse to the file XEFFSER.txt
Click on: Open
Click on: Preview XEFFSER
Click on: Primary Check XEFFSER
Click on: DB Check XEFFSER
Click on: Yes
If there are no errors close the appearing window
Click on: Transfer XEFFSER
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-6 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Click on the > in front of "Aircraft Configuration" in the tree structure on the left side:
4. Upload XCONFCONFIG.txt
Click on: XCONFCONFIG
Click on: Browse and browse to the file XCONFCONFIG.txt
Click on: Open
Click on: Preview XCONFCONFIG
Click on: Primary Check XCONFCONFIG
Click on: DB Check XCONFCONFIG
Click on: Yes
If there are no errors close the appearing window
Click on: Transfer XCONFCONFIG
5. Upload XCONFFPSIMPLE.txt
Click on: XCONFFPSIMPLE
Click on: Browse and browse to the file
XCONFFPHEADER.txt
Click on: Open
Click on: Preview XCONFFPSIMPLE
Click on: Primary Check XCONFFPSIMPLE
Click on: DB Check XCONFFPSIMPLE
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-7 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Click on: Yes
If there are no errors close the appearing window
Click on: Transfer XCONFFPSIMPLE (this may take a while)
Open Configuration Definition (APN 2818):
Click on Search and filter GAA_2015-02-25Z
Double click: GAA_2015-02-25Z
Select: GAA_2015-02-25Z (middle)
Click on: + FP (Add new FP). (right side top)
FP type: Hardware
Code: N/A
Description: NOT APPLICABLE
Insert after FP clear this field
Click on: Next
Click on: Finish
Now you can continue to upload the remaining Text-Files (XFile) in Data Transfer
(APN261).
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-8 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
7. Upload XCONFFPPROP.txt
Click on: XCONFFPPROP
Click on: Browse and browse to the file XCONFFPPROP.txt
Click on: Open
Click on: Preview XCONFFPPROP
Click on: Primary Check XCONFFPPROP
Click on: DB Check XCONFFPPROP
Click on: Yes
If there are no errors close the appearing window
Click on: Transfer XCONFFPPROP
To check the Upload and to activate the configuration, open Configuration Definition
(APN 2818):
Double click: GAA_2015-02-25Z
Select minimum one Hardware Functional Position and one Software
Functional Position and check the tab sheets "Effectivity" and "P/N List".
Now we have to activate the configuration (may take a minute or two)
Click on: De-/Activate (left side).
Click on: Yes (This may take a minute or two)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-9 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
The activation will set all settings to read only, To adapt changes, you have to revise
the entry in question in order to have a complete traceability.
Link the activated Authorized Configuration to your aircraft:
Click on: Assign (left Side)
Click on: Yes
Check the allocation of the components on the functional positions
Click on: YES
Open Aircraft Administration (APN 308) and select A/C GAA
Limit / Spec- tab-sheet
Aircraft Configuration: should be GAA_2015-02-25Z
For trainer : The whole fleet can be linked to one configuration. Here we will assign
it to GAO only, for training purposes.
In order to perform the additional exercises an upload of Software Bookings is
needed. Precondition for the upload is an activated Aircraft Configuration which was
done the steps before.
Switch back to Data Transfer (APN 261).
Click on the > in front of "Software Management" in the tree structure on the left side:
4. Upload XSWBOOKING_GAO.txt
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-10 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Click on: XSWBOOKING
Click on: Browse and browse to the file
XSWBOOKING_GAO_V12.20.txt.
Click on: Preview XSWBOOKING
Click on: Primary Check XSWBOOKING
Click on: DB Check XSWBOOKING
Click on: Yes
If there are no errors close the appearing window
Click on: Transfer XSWBOOKING
Note: The file will need a couple of minutes to be uploaded
Software Management: Compare Allowed Configuration vs. As Flying
Configuration
During the Aircraft Phase-In process we download the "As-Flying" configuration from
the aircraft to compare it to the "Allowed" configuration (based on the ToT
Configuration) and the "As-Booked" configuration (status in AMOS).
We have to correct the "Allowed" and/or the "As-Booked" configuration if necessary.
Open Configuration Definition (APN 2818):
Click on: Search
Filter your aircraft GAA
Double Click on: GAA_2015-02-25Z
Allowed Configuration
Select: GAA_2015-02-25Z
As Flying tab
Choose: Import from File
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-11 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Click on: OK
Browse to the As Flying Configuration File: AirplaneConfig_SWS_GAA_2015-
03-12_16.55.28Z.XML).
Click on: Open
Checker tab
Assignments: Choose GAA
As-Flying section
Un-Tick: Partial Check
Click on: Check (in the As-Flying section)
Checker > As-Flying > Allowed tab
Filter Functional LS1025067
Position
Click on the + in front of the Functional Position
In the column Relation you can find the following icons:
(green) Both configuration matches
(red) Setting exists in As Flying but not in the selected
Allowed or As-Booked (blue) Setting exists in Allowed or
As-Booked but not in AS Flying
Repeat the filtering for the As-Booked tab beside and check the result - no
discrepancy found.
Correct discrepancies between Allowed configuration and As-Flying
configuration
Checker > As-Flying tab > Allowed tab
Filter Functional LS1025067
Position
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-12 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Find discrepancy with the blue arrow (exists in Allowed, but not in As-Flying):
should be LS1025067.06
Find the missing Software in Allowed Configuration (Red arrow): Should be
SWS25-HCM2-0009
To correct the discrepancies we check in addition As Booked:
Checker > As Flying tab > As-Booked tab
Filter Functional LS1025067
Position
SWS25-HCM2-0009 should be booked at position LS1025067.07
COL4C-0019-0015 should be booked at position LS1025067.06
Allowed Configuration tab (on Top)
Filter Functional LS1025067
Position
Select: Software P/N COL4C-0019-0015 underneath
LS1025067.07
P/N List section (below)
Click on: Revise
Revision Number: 2
Revision Reason: DEFINE MISSING SOFTWARE AND DELETE OLD
SOFTWARE IN ALLOWED CONFIG.
Click on: Save
Click on: Parts
Software Number: SWS25-HCM2-0009
Click on: Add
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-13 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Select given Software Number (COL4C-0019-0015)
Click on: Remove
Click on: Save
P/N List section
Select: Revision 2
State tab (right)
Select SWS25-HCM2-0009 LS1025067.07 / GAA pane
Click on: Manage (above)
Select your Revison
Change Status Choose Allowed
(down):
Click on: OK
COL4C-0019-0015 is As-Booked and As Flying at position LS1025067.06
BCG24-U000-0124 is Allowed at position LS1025067.06
but not in As-Fyling We will now correct this discrapancy
Select: Software P/N BCG24-U000-0124 underneath
LS1025067.06
P/N List section (below)
Click on: Revise
Revision Number: 2
Revision Reason: DEFINE CORRE CT SOFTWARE AT POSITION AND
DELETE THE WRONG ONE
Click on: Save
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-14 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Click on: Parts
Software Number: COL4C-0019-0015
Click on: Add
Select given Software Number (BCG24-U000-0124)
Click on: Remove
Click on: Save
P/N section tab
Select: Revision 2
State tab (right)
Select COL4C-0019-0015 LS1025067.06 / GAA pane
Click on: Manage (above)
Select your Revison
Change Status Choose Allowed
(down):
Click on: OK
Select your Configuration (GAA_2015-02-25Z) to check again for
discrepancies
Checker tab
Assignments: Choose GAA
As-Flying section
Un-Tick: Partial Check (if necessary)
Click on: Check
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-15 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Filter Functional LS1025067 in Allowed and As-Booked tab
Position
Click on the + in front of the Functional Position in both tabs: No discrepancies
Modification of Software
Trainer:
Ensure that parameter 1681 Modifications PRE / POST Status is adjusted
correctly as precondition for the exercise:
String: PRE: -,O,B,G,J,A / POST: C,F,T,V,H
Integer: 1
Scenario:
You received a new software for Service Bulletin (SB) B787-850233-SB2300012-01
delivered on an USB Stick. The accomplishment of the SB is the improvement of a
new software. This SB replaces the Software Part number BCG24-U000-0124 with
the new Software Part number BCG24-CC90-0001.
Engineering Department decided to implement the SB on our 787 fleet in next 3
months with you as the responsible Software Engineer.
2.8.6.1 Create a new Consumable:
In order to have a Part Request on the Workorder performing the SB, a new
Consumable needs to be created. With this Consumable we can state the
availability of the new software.
Open Part Administration (APN 59):
Click on: Create Part
Part Number: SB2300012-01
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-16 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Description: USB-Stick with SOFTWARE KIT
Material Class: Consumable
Material Type: N (Non Aircraft Material)
Measure Unit: EA
FA Type: 787
ATA Chapter: 23
Click on: Publish
Click on: OK
Country of Origin: US
Default Supplier: BOEING
Click on: Save
2.8.6.2 Create a new Software Part number:
Create the new Software Part number stated in the SB. Open Software
Management (APN 2618):
Definition tab
Click on: New
Software Part BCG24-CC90-0001
Number:
Description: 23 CFM AMI UADF DB
Software Type: DB
Media Type: USB
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-17 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Vendor: BOEING
ATA Chapter: 23
Click on: Save
Click on: Release
Release Date: Today
Released By: Your login
Release Remarks: New Software from BOEING
Click on: Save
2.8.6.3 Link Software to USB Stick
Locations tab
Click on: New
Software Location: USB SB2300012-01
Description: SB2300012-01
Storage Type Consumable
Consumable: SB2300012-01
Click on: Save
Click on: Manage Media Set
Available Software Filter BCG24-CC90-0001
Numbers:
Click on:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-18 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Tick: Master
Click on: Save
Click on: Release
Release Date: Today
Released By: Your Login
Released Remarks: Software delivered on USB
Quantity: 1
Click on: Save
2.8.6.4 Create a new Service Bulletin:
Open View/Edit Modifications (APN 63):
Click on: New
Document No: B787-SB2300012-01
Doc-Type: SB
Subject: Aeronautical Telecommunications Network Function
Data Link and Avionics Software Change
Issued by: BOEING
Issue Date: -3m
Rev: 00
Receiving Date: -3m
ATA-Chapter: 23
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-19 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Shop/Line Doc A
Type of Change: N
Compliance Type: REC (Recommended)
Type of modification: Aircraft/Airframe Modification
Document with Y (tick)
hardtime limit:
Click on: Save
Signoff-Tree tab
Select
Click on: Save
Select Effectivity tab
Click on: New Effectivity
Title: B787-SN 236701
A/C Type: 787
Click on: Next
Click on: Include existing Serialnumber
Choose Serial 236701
number:
Click on: OK
Click on: Finish
Select your Effectivity line & Choose Revisions tab
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-20 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Activate the Effectivity Revision click on: De-/Activate & Yes
Time Requirement / Editor tab
Click on: New
Select: Basic Definition
Click on: Next
Baseline: Before
Dimension: D(ays)
Due at: +3m
Click on: Finish
Click on: Activate
Work Template tab
Click on: New
ATA-Chapter: 23
Click on: 2 x Next
Headline: @STANDARD_HEADLINE@
CHANGE SOFTWARE AS LISTED
IAW SB B787-850233-SB2300012-
01:
Description Text:
OFF: SOFTWARE PART NUMBER BCG24-
U000-0124 ON: SOFTWARE PART NUMBER
BCG24-CC90-0001
Click on: 3 x Next (until you reach Part Request)
Click on: Add
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-21 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Part Number: SB2300012-01
Qty: 1
Click on: OK
Click on: Next
Click on: New (Staff)
Scope / Planning B1
Qualification:
Total Hours: 01:30
Quantity: 1
Click on: OK
Click on: Next
Current Software No: BCG24-U000-0124
Click on: Search
All affected Functional Positions are listed in the appearing dialog.
New Software No.: BCG24-CC90-0001
Click on: Add
Click on: Finish
Don't forget to set the Work Template to Active
Click on the current Software No. listed in the Work Template in order to
update the Aircraft Configuration.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-22 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Choose: Action... / Manage Func. Pos
Please select a Double Click and choose GAA_2015-02-25Z
Configuration:
Click on: OK
P/N List tab / New Rule Header
Code: B787-850233-SB2300012-01
Description: UPGRADED SOFTWARE CONTROLLED VIA SB
Tick: Event Controlled
Revision Number: 00
Software Number: BCG24-CC90-0001
Click on: Save (don't close the dialog)
2.8.6.5 Link B787-850233-SB2300012-01 to Configuration Change
Requirement Link tab - to link the SB to the Software Change
Click on: Add Entry... and choose Requirement Links
On top choose Document
In the field next to the B787-850233-SB2300012-01
previous one, enter
the following:
Click on: Add
Click on: Save
Check if all Functional Positions are selected.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-23 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Click on: OK
2.8.6.6 Assign SB with status Open
Open View/Edit Modifications (APN 63):
Search for B787-850233-SB2300012-01
Status tab
Select:
Select your Aircraft GAA
Click on: Assign
Check the Expected Due Date and confirm the appearing Initialize Document
dialog
The SB is now initialised for your aircraft GAA
To check the Due Date of the SB in Maintenance Forecast 2 (APN 1844), just open
the program and double-click your aircraft GAA.
The instructor will assist you if needed.
Depending on Modification Status of SB B787-850233-SB2300012-01: PRE MOD:
Software Part Number BCG24-U000-0124 can be booked.
POST MOD: Software Part Number BCG24-CC90-0001 can be booked.
A full traceability of Sofware Changes / Software Booking are given in Software
Tracking (APN 1832) in tab History.
2.8.6.7 Check availability and purchase the Consumable Part:
Open Parts Consumption Forecast (APN 204):
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-24 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Select your Aircraft GAA
Due In: ALL
Planned In: ALL
Click on: Search
Select the line with Part No. SB2300012-01
Part View tab
Select the line with the event (left side)
Click on: Generate Oder (bottom)
Choose: B (SB Order)
Tick: Link part request to order detail
Click on: OK
Complete Purchase Order:
Vendor: BOEING
Issued by Address: TPU
Click on: Save
Click on: Issue
Write down your order Number:
To check the availability of the service part, open Parts Consumption Forecast (APN
204):
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-25 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Select your Aircraft GAA
Due In: ALL
Planned In: ALL
Click on: Search
What do you see in the status ("?") column?
2.8.6.8 Receive the Consumable Part
After downloading / receiving of the new Software state the Consumable Part as
available. Open Goods Receiving (APN 2121):
Order: Your Order Number
Click on: Load
Click on: New Receiving
Click on: Save Receiving
Click on: Process Receiving
Batch No. Automatic Numbering (tick)
Expiry Date: Unlimited (tick)
Condition: N (new)
Owner: SWS
Number of Batches: 1
Click on: Receive Physically
An Invoice can be booked based on this receiving.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-26 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
2.8.6.9 Perform the Modification
Open View/Edit Modifications (APN 63):
Search for: B787-850233-SB2300012-01
Select Status tab
Select:
Select GAA
Select: B787-850233-SB2300012-01
Click on: Issue W/O
Click on: Yes
Write down the Workorder Number:
Open Workorder (APN 1418):
Workorder Number: Your Workorder Number
Click on: Load
Click on:
(to enter an action)
Confirm: Date & Time
Headline: Confirm proposal
Action Text: SOFTWARE CHANGE PERFORMED IAW SB
B787-850233-SB2300012-01 AND COMPANY
PROCEDURES
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-27 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
Performed Sign: Your Login
Click on: Next
Click on: Add Entry and choose Time
User Sign: Your Login
Duration: 01:20 (type: 120)
Click on: OK
Click on: Finish
Click on: Software Booking (left side)
Ensure that the software will be installed at each Functional Position
Install Date: Today
Installed by: Your Login
Installed at: ZRH
Click on: Book - OK
Close W/O
Closing Station: ZRH
Closing Date & Confirm proposal
Closing Time:
Approval No: Confirm proposal
Closing Sign: Your Login
Click on: Finish
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-28 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 8 SOFWARE MANAGEMENT
2.8.6.10 Reporting Back Modification
Open View/Edit Modifications (APN 63):
Search for: B787-850233-SB2300012-01
Select Status tab
Select GAA
Select: B787-850233-SB2300012-01
Click on: Report Back
Click on: Next
Click on: Next
Click on: Next
Click on the in front of B787-850233-SB2300012-01 and check if all
Functional Positions are selected.
With Reporting Back the SB the new revision of the Aircraft Configuration will
be activated.
Click on: Finish
Click on: OK
Click on: OK
The SB is now closed.
Check your active configuration for Software Number BCG24-CC90-0001 in
Configuration Definition (APN 2818).
The software booking can be reviewed in Software Tracking (APN 1832).
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.8-29 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
WORK INSTRUCTION AUTHORING
Overview / Introduction
Business Processes:
Engineering
03.09 - Work Instruction Authoring
03.04 - Modification Control
03.02 - Part Definition
Maintenance
08.03 - Base Maintenance, Heavy Checks
AMOS Modules:
Work Step Repository (APN 1904)
Work Template Manager (APN 1848)
View/Edit Modification (APN 63)
Part Administration (APN 59)
Part Requirements Administration (APN 2773)
Maintenance Programs Administration (APN 249)
Form Configuration (APN 1444)
Maintenance Forecast (APN 1844)
Workorder (APN 1418)
View / Edit Workpackage (APN 58)
PDF Overlay (APN 3170)
Basic Tables
Many AMOS tables are defined in Basic-Data Administration, APN 18. For this
training, the following table is specific to Work Templates:
Meta Data Key
Other tables which are shared with many other programs, will also be important:
Aircraft Type
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-1 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
ATA Chapter
Position
Parameter
1663 - Taskcard Worktemplate editing in Maintenance Program Administration
Workflows
ID230: Worktemplate Modification
ID 390: Work Template Update Revision Workflow
Work Template Authoring
Work Templates are the origin of many executable documents within AMOS. Once
available within the Work Template Manager the Work Template can be controlled
centrally without the need to have access to the individual programs defining and
managing the events themselves.
On an individual level the Work Steps are considered to be the smallest plannable and
executable element within AMOS regardless of the event type. A Work Step contains
not only performance instructions but also links, classifications, manhours, parts as
well as many other elements.
1 or more Work Steps can be used to create a Work Template that is either available
as an unlinked Work Template to use in the Workorder when created in the Work
Template Manager or if created in Engineering programs such as View/Edit
Modification and be viewed and managed centrally.
Work Steps and Work Templates can be copied and pasted between maintenance
events and controlled by revision if required.
Work Template Manager (APN1848)
The Work Template Manager program allows you to create predefined Templates
used in Workorders, Job Cards and Customer Requirements.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
In this training we will focus on Workorder and JC (Job Card) Templates. Customer
Requirement Templates are covered in the Quotation Manager training.
2.9.2.1 Exercise: Creation of a Work Template in Work TemplateManager (APN1848)
In this exercise we will create a very basic Work Template with 2 Work Steps.
This Work Template will be used in a workorder later during this training. We will then
revise one of the Work Steps in the Work Template and explain how it affects the
workorder.
Open program Work Template Manager (APN1848).
Click on: New
Click on: New Standalone Work Template
The Work Template Wizard for Stand Work Template will open and guide
through the creation of a Standalone Work Template.
Number: WT02
Title: Test Work Template 02
Revision Number 00
Revision Date: Confirm the date suggested by AMOS
ATA Chapter: 05
Click on: Next
Click on: AOG Risk - Next
Headline: WORK STEP 1
Description: PERFORM WORK STEP 1
Click on: Next (3x)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-3 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Step 6.Part Request Rmp./Codes
Click on: Add
Part Number: W54204
Qty: 1
Click on: OK
Click on: Next
Step 7. Resource Request
Make sure Staff is selected. (Next to the New button).
Click on: New
Planning Qualification: A
Total Hours: 2:00
Quantity: 2
Sign Off Performed
Configuration:
Click on: OK
Click on: Finish
We will now add another Work Step to the Work Template:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-4 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: + Add Entry
Select: Create Work Step
Headline: WORK STEP 2
Description: PERFORM WORK STEP 2
Click on: Finish
Right-click on the
grey header of Resource Requirement
Work Step 2 and
click on:
Click on: Staff
Complete the stuff Planning Qualification: A, Total Hours: 00:30,
request using the Quantity:1, Sign Off Configuration: Performed
following details:
Click on: Save
To be able to use the Template it must be activated.
Click on: Activate
Meta Data Tab: This tab allows you to add more search options.
Click on Meta Key ATA Reference
and choose:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-5 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Meta Key: Click into the empty field & select ATA Reference
Click on: Choose (right top of the screen)
Click on: 05 - Periodic Inspections
Click on: OK
Click on Meta Key Aircraft Type
and choose:
Click on: Choose (right top of the screen)
Click on: 32S
Click on: OK
2.9.2.2 Exercise: Creation of a workorder linked to a Work Template from Work
Template Manager (APN1848).
Open Workorder (APN:1418):
Click on: New Template Workorder
To be able to find our Work Template make sure that within the Search Section the
Type TW (Standalone Work Template) is set:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-6 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: Search
Select: WT02
The "Wizard - Create WO" opens - and the WO Type Scheduled is pre-
selected.
Click on: Next
Enter A/C Reg.: AAB
Click on: Next
Due Date: +2d
Enter and Click: Finish
When using a Workorder Template the WO you are creating with will behave as any
other Workorder. This means that the setup for WO, the rules of Form Configuration
(APN 1444) and of course all the Workflows will be triggered, which are setup for
Workorders. The Workflow 32 "Zero-Stock for Part Number entered in Workorder" is
triggered every time there is a Part Request added to a Workorder & there is no
stock of the requested part.
Due to our setup the part request added to the Work Template earlier triggers the
Workorder Module to create a Pickslip.
AMOS will automatically show a popup to create a Pickslilp for the part request of
the WO we just created.
Create Pickslip for W/O - Dialogue box will open to send a pickslip to the
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-7 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
store:
Click on: Cancel
Now that the Workorder is created, you will see an next to the Workorder
number in the header, which is indicating that it is linked to an Active Template from
the Work Template Manager.
There is also a line in the header that shows which Work Template was used to
create this Workorder
Currently it is still possible to edit the Work Steps.
Within the Workorder in the production view right-click on the Work Step. In the menu
you can see you are still able to edit the entry.
2.9.2.3 Exercise: Revising a Work Template in Work Template Manager(APN1848)
Our next step is to make changes in the original Work Template WT02. Go back to
Work Template Manager (APN1848).
In the filter section of the Work Template Manager there is too many filter settings to
display all of them.
You will notify that some of the sections have a small arrow pointing to the right in
front.
To get a result in the search you have to - at least - open one of those collapse filter
settings. If you closed the Work Template Manager:
Search Section: Requirement Reference
Select TW (Standalone Work Template)
Click on: Search
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-8 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Select: WT02
tab Work Template - Revisions Section
Click on: New Revision
Right-click on: 1 Work Step (the header line)
Select Description
Add to the original IF THERE ARE FINDINGS PLEASE OPEN A
text: FINDING WORKORDER.
Click on: Save
Click on: Activate
In the pop up select your entry to review in the lower part the different
versions of the Work Template.
Click on: Sync Revision WT
Go back to the Workorder Module (APN1418)
Click on: Load
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-9 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Verify the changes in Work Step 1
Go back to Work Template Manager
Revisions Section
Click on: New Revision
Make sure the OK
Version 2 of the
Template is
selected:
Right-click on the Description
header of Work
Step 1 and select
Add to the original text: MAKE SURE TO FOLLOW THE
INSTRUCTIONS OF THE MOE
Click on: Save - OK
Click on: Activate
Review the pop up and select the line with the word "plannable" to compare
the 2 versions.
Click on: Exit (Do not synchronize the Revisions!)
Go back to the Workorder Program (APN1418).
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-10 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: Load
Review the R
Icon in front of
the Workorder
number:
This indicates there is a new Work Template Revision available for your
Workorder which is not yet synchronized.
Click on: Sync Revision WT - OK
Review the A
Icon in front of
the Workorder
number:
General Note:
When a revised Work Template in Work Template Manager is synchronized with a
workorder and thereafter the Work Template revision is deleted then the link
between the Work Template and the workorder is also deleted.
In other words, the workorder is now a standard workorder without an "A" in front of
the workorder number.
Work Step Repository (APN1904)
The Work Step Repository program allows you to store individual Work Steps that
are often used. There are two ways to create a Work Step in AMOS.
The most common way is via the Work Template wizard for any maintenance event
(Workorder, Taskcards ). At the Work Step level you have the option to save the
Work Step in the Repository.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-11 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Once saved it is possible to link or import the Work Step to any maintenance event
Work Template. You can edit an imported Work Step however a linked Work Step
needs to be revised in the Work Step Repository program.
The second option is to create a Work Step in the program Work Step Repository
itself.
The creation of the Work Step is exactly the same as explained in the exercise of
the Work Template Manager program.
Open Work Step Repository (APN1904)
In the search section on the left hand of the screen enter following search
criteria:
Work Step Number 5302
Click on: Search
Verify the Revision N
Status:
Click on: Activate
Only active Work Steps can be used in other programs.
2.9.3.1 Exercise: Linking a Repository Work Step to an existingWorkorder
Go back to APN1418 and find your Workorder. (Use the right-click and history) We
will add another Work Step. This time from the Work Step Repository.
In the Planning View of the Workorder :
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-12 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: + Add Entry
Click on: Link Repository Work Step
The wizard will take you into APN:1904 Work Step Repository where you can
search for stored Work Steps.
In the search section on the left hand of the screen enter following search
criteria:
Work Step Number 5302
Click on: Search
Select the Work Step. On the right side you can verify its content.
Click on: Save
The Work Step is added to the workorder. The Work Step also has the indicating
that it is linked to an active Work Step within the Work Step Repository (APN1904)
While the Work Step is linked, no Editing is possible on the Work Step.
The advantage here is that if the Work Step is revised in the repository, as long as
no Action has been performed on the Workorder Work Step, it can be updated
during the revision process.
Double Click on: Work Step No: 5302
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-13 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Review the pop up OK
2.9.3.2 Exercise: Revising a linked Work Step
Within the WO you are able to open the Work Step Repository to revise the Work
Step:
Click on the words: "WORK STEP"
Click on: Open With - Work Step Repository
Work Step Repository (APN1904)
Click on: New Revision
"Create Work Step Revision" Wizard will show up.
Add following text: I.A.W. AMM 78-20-13-040
Click on: Finish - Activate
In the popup dialogue you are able to compare the archived and active revision of
the Work Step.
Select Exit
Workorder (APN1418)
Click on: Load
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-14 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
3rd Work Step: In the header of the 3rd Workstep an "R"
indicates that theWork Step was revised and this
version is archived.
Right click on the word Select Update Revsion"
"Work Step"
In the following popup window you are able to compare both versions of the
Work Step. You will be able to see the changes easily.
Click on: OK
Verify the Work Step text and the icon (A) in the header of the 3. Work Step.
Revising a linked Work Step via the workorder:
The only way to revise a linked Work Step via a workorder is by unlinking the Work
Step from the repository.
Right Click on the Work Step 3.
Click on: Unlink Revision
This only allowed if the user has the license for this function.
Now the Work Step is unlinked, and editing is possible.
2.9.3.3 General Notes
2.9.3.3.1. Work Template:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-15 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
A workorder linked to a Work Template from the Work Template Manager
(APN1848) contains an "A" in front of the Workorder number.
If a new revision is available in the Work Template Manager, all Maintenance Events
linked to that Work Template will be requested to be synchronized to the latest
revision.
If you choose not to synchronize the linked Work Template then the "A" in front of the
workorder number becomes an "R" after reloading.
The newest revision of that Template can then be updated by selecting the "Sync
Revision WT" button on the left hand section of the Workorder Program (APN1418).
2.9.3.3.2. Workstep:
A workorder Work Step linked to a Work Step from the Work Step Repository
(APN1904) contains an "A" in front of the Work Step number and is by default not
editable.
If a new revision is available in the Work Step Repository, workorders linked to that
Work Step but not to any Work Template will be requested to be synchronized to the
latest revision.
If you choose not to synchronize the linked Work Step, then the "A" in front of the
Work Step number becomes an "R" after reloading the workorder.
The newest revision of that Work Step can then be updated in the Workorder
Program (APN1418) by selecting the grey bar of that Work Step," left click - select
"Action - Synch Revision WT" .
2.9.3.4 Combination Work Template Workstep:
A workorder linked to a Work Template from the Work Template Manager
(APN1848) contains an "A" in front of the Workorder number and in addition a Work
Step is linked to a Work Step from the Work Step Repository (APN1904) then the
Work Step contains an "A" in front of the Work Step number.
If a new revision is available in the Work Template Manager, synchronization will
update the Work Template of the workorder to the latest revision and will remove
the added repository Work Step from the workorder (since this is not a part of the
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-16 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Work Template). The same applies if a workorder is linked to a Work Template from
any maintenance requirement like Modification, Taskcard, Check, Part
Requirement.
If a new revision is available in the Work Step Repository, the workorder linked to
that Work Step will not be requested to be synchronized to the latest revision.The
newest revision of that Work Step can then be updated in the Workorder Program
(APN1418) by selecting the grey bar of that Work Step," left click - select "Action -
Update Revision" .
Work Template Manager - JC
In this exercise we will create a JC (Job Card) that can be utilised to provide a step
by step maintenance inspection JC. We will create a JC to instruct the maintenance
personnel on the steps required to perform a cabin inspection.
Open the program Work Template Manager (APN 1848)
2.9.4.1 Exercise:
Click on: New
Click on: New Jobcard Template
Number: SWS-CI-02
Title: INTERIOR CABIN INSPECTION
Rev. No.: 00
Rev. Date: today
ATA Chapter: 25-00
Click on: Next until step 3
Headline: FWD VESTIBULE
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-17 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Description Text: PERFORM VISUAL INSPECTION OF
THE FWD VESTIBULE FOR SIGNS OF
DAMAGE AND POOR CONDITION
Click on: Next until step 7 (Resource Request)
Click on: New (with Staff selected in the drop
down)
Constraint: Scope
Planning Qualification: MECH
Total Hours: 00:15
Quantity: 1
Click on: OK
Click on: Finish
The Work Template is now displayed on the right hand side under the Work
Template tab, sub tab Work Template Revision.
Currently we have a single Work Step and the status of the Work Template is
"New". We will add now a 2nd Work Step to our Job Card:
Within the Work Template Add Entry...
Revision Tab, click:
Click on: Create Work Step
Headline: FWD LAVATORY
Description Text: PERFORM VISUAL INSPECTION OF
THE FWD LAVATORY FOR SIGNS OF
DAMAGE AND POOR CONDITION
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-18 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: Next until Resource Request
Click on: New (with Staff selected in the drop
down)
Constraint: Scope
Planning Qualification: MECH
Total Hours: 00:10
Quantity: 1
Click on: OK
Click on: Finish
Before we set the Work Template "Active" we will add some additional Work Steps.
Within the Work Template Add Entry...
Revision Tab, click:
Click on: Create Work Step
Headline: PASSENGER CABIN
Description Text: PERFORM VISUAL INSPECTION OF
THE PASSENGER CABIN FOR SIGNS
OF DAMAGE AND POOR CONDITION
INCLUDING CABIN CLASS CURTAINS
AND DIVIDERS
Click on: Next until Resource Request
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-19 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: New (with Staff selected in the
dropdown)
Constraint: Scope
Planning Qualification: MECH
Total Hours: 02:00
Quantity: 2
Click on: OK
Click on: Finish
Now that we have the JC prepared we will activate the revision. Click on Activate.
To allow for enhanced filtering we will use Meta Data.
Tab sheet Meta Data
Click on Meta Key and choose: Aircraft Type
Click on: Choose (right top of the screen)
Click on: 32S
Click on: OK
We will now combine the Template Workorder and the JC.
This method allows the JC to be collected into the workpackage once the workorder
has been added to the workpackage.
After the Job Card is collected the request for parts & resources will be added to the
Work Package Data.
Create a Work Template for the cabin inspection and link the JC to the Template:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-20 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: New
Click on: New Standalone Work Template
Number: SWS-WO-CI-02
Title: CABIN INSPECTION
Rev. No.: 00
Rev. Date: today
ATA Chapter: 25-00
Click: Next until Add Work Step
Headline: PERFORM CABIN INSPECTION
Description text: PERFORM CABIN
INSPECTION IAW ATTACHED
JC
Click on: Next until Resource Request
Click on: New (with Staff selected in the
dropdown)
Constraint: Skill
Planning Qualification: B1
Quantity: 1
Click on: OK
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-21 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: Finish
tab Work Template - section Revisions
Click on: Activate
Now that we have an active Work Template we will link the JC.
Within the Work Template tab select the Linked Jobcards tab.
tab Work Template - tab Linked Jobcards
Click on: Add Jobcard
The window "Select a Work Template" will open up:
Click on: Search
Select SWS-CI-02
Click on: OK
Now we will create a Workorder using the Template we just created, add the
Workorder to a workpackage and collect the Job Card.
Open Workorder (APN:1418):
Click on: New Template Workorder
To be able to find our Work Template make sure that within the Search Section the
Type TW (Standalone Work Template) is set:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-22 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: Search
Select: SWS-WO-CI-02
Click on: Next
The "Wizard - Create WO" opens - and the WO Type Scheduled is pre-
selected.
Click on: Next
Enter A/C Reg.: AAB
Click on: Next
Due Date: +2d
Enter and Click: Finish
The trainer will guide you through to assign the Workorder to a Workpackage and
collect the Job Card.
Work Template Manager - Job Cards
Only for demonstration
We would like to change a link to the AMM into a Jobcard to follow up all single
steps of the AMM to be performed.
We want to add the AMM reference to the complete Work Template - not to a single
Work Step. Therefore we have to select the icon at the bottom of the screen -
not the one inside of eachWork Step.
Open View/ Edit Modifications (APN 63)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-23 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Document No A320-78-0011
Effectivity tab > Select the Effectivity Line > Work Template tab
Click on: New Revision
Click on: Add Entry
Select: Task References / Links
Reference Type AMM
Double-click & Select AMM Reference
Click on:
In the screen Click on the tab Search
Double click: Document
Click on: active AMM
Click on: OK
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-24 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
AMM Reference 78-32-00-010-010
Click on: Search
Select the first entry (1000EM1) OK
Your are back now at the New Task Reference/Links dialogue
Click on: Save
And do not forgot to activate your Revision!!
The link to the AMM should now appear at the bottom of the Work Template.
Click on: Revision Number of the header of
the Work Template
Select: Open with ... Work Template Manager
Work Template Manager (APN 1848)
If not shown - select the Work Template in the Search Section on the left
side.
Click on: New (Revision of the Work Template)
Select the tab - AMM Documents
In the header the active AMM should be shown - if missing double-
click into the empty field and select the one in there.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-25 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
AMM Select the active AMM
Click on: Document & AMM Reference (set the
tick before both entries)
Click on: Create Jobcard
The dialogue to create a Jobcard will open:
Rev. No.: 00
Rev. Date: today
For the rest of the Steps we don't want to add any additional data.
In this example we will create a Jobcard that will be available to collect into the
workpackage as an event in its own right.
Click on NEXT until the last step:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-26 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: Finish
Pop-up Window: YES
The newly created Job Card is loaded now as a Work Template.
Click on: Activate
If this is not activated you will not be able to collect it into the workpackage. Select the
Document Work Template (SB/A320-78-0011) from the left side:
Select: The New revision
Click on: Activate
Due to the fact that pending entries existed for several A/C you have to synchronize
the existing events with the new revision of the Work Template for the Document and
the Jobcard.
In the upcoming dialogue you are able to update all pending events.
AMOS will present a list of events, which are affected of the changes of the Work
Template and the change on the Jobcard.
In the lower part of the screen you are able to view the changes of the Work Template
if you select one entry.
To update all entries make sure they are all ticked.
Click on: Synch Revision WT
The trainer will now demonstrate how this document can be found in the Maintenance
Forecast, added into a workpackage and then be collected within the workpackage.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-27 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Jobcard with EWI
Provide paperless maintenance execution for line and base maintenance.
As the first phase, the idea is to generate Electronic Work Instructions (EWI) for all
events (except WO) as paper behind glass:
The focus was on integrating AMM references linked to Event, JC or CR to the PDF
Overlay and generate automatically some Signature boxes.
Demonstration only:
In this exercise the trainer will demonstrate how to create a Job Card and add an AMM
task to the Job Card.
In the second step the attached AMM Task will be used in the Workpackage as the
EWI (Electronic Work Instructions).
Note: Check the settings of Parameter 1824 = String = Y
Open Work Template Manager (APN 1848)
Click on: New
Click on: New Jobcard Template
Number TOWING - NOSE GEAR FROM FRONT
Title TOWING WITH THE NOSE GEAR
FROM THE FRONT
Revision Number 00
Revision Date today
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-28 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
ATA Chapter 09-10
Click on: Next
Line/Heavy L
Click on: Next
Work Step Ceation Options Individual
Phase PR_IN (Pre Inspection)
Headline TOWING OF A/C WITH NOSE
GEAR FROM THE FRONT
Description Text WHEN TOWING AN A/C WITH
NOSE GEAR FROM THE FRONT
MAKE SURE YOU FOLLOW THE
ATTACHED AMM TASK
09-10-00-584-002
Click on: Next
Select Meta Key Aircraft Type
Click on: Choose - in the list select 32s
Click on: Next
Double-Click & Select Reference AMM
Type
Select link type AMM Refernce
Click on: Choose
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-29 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Navigate to the Chapter 09 and 09-10-00-584-002
select
Click on: OK
Click on: Next (Until Resource Request)
Select Aircraft
Click on: New
Duration 00:30
Click on: OK
Select Staff
Click on New
Planning Qualification B1
Total Hours 00:30
Click on: OK
Click on: Finish
To be able to use the Template it must be activated.
Click on: Activate
We will create now a Workorder Template
Click on: New
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-30 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Select Standalone Work Template
Number TOWING
Title TOWING OF A/C
Revision Number 00
Revision Date today
ATA Chapter 09-10
Click on: Next (until Step 3 Add Work Step)
Headline TOWING
Description Text MAKE SURE WHEN TOWING AN A/C
TO FOLLOW THE INSTRUCTIONS
ATTACHED AS JC
Click on: Next (until Step 7 Resource Request)
Make sure Staff is selected
Click on: New
Planning Qualification B1
Total Hours 00:30
Quantity 1
Click on: OK
Click on: Finish
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-31 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: Activate
Tab - Linked Jobcards
Click on: Add Jobcard
Click on: Search
Select TOWING - NOSE GEAR FROM FRONT
Click on: OK
Open the module Workorder (APN 1418)
Click on: New Template W/O
Click on: Search (Type must be set to TW)
Select Towing / Towing of AC
Check, if the JC is attached
Click on: Next
Make sure Scheduled is selected
Click on: Next
A/C Reg AAO
Click on: Next
Due Date Today
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-32 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: Finish
We will add this Workorder to a Workpackage scheduled for today. Open
Maintenance Forecast (APN 1844)
Search for the just created Workorder
Add the Workorder to a Workpackage scheduled for today- if necessary create a
new Workpackage. Open the Workpackage and make sure you collect the Jobcard.
Within View/Edit Workpackage (APN 58)
Select tab - Production / Pending
Select Jobcard Towing
Click on: Create EWI (might be hidden - use more
button)
Confirm the popup message - YES
Select in Planing View- Add Electronic Work Instructions
Entry
The module PDF Overlay (APN 3170) will open up and display the AMM Task as an
Electronic Work Instructions.
Note: The PDF Overlay opens in Draft Mode!! To perform the actual Stamping you
have to leave the Draft Mode!
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-33 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Use the different Stamp Boxes to confirm the requested steps be performed.
When pointing with the mouse pointer over one signature box and left click your
login will be set into the signature box.
PFMD, INSP, DI - Used to stamp your login into a Performed,
Stamp Inspedcted, Double Insp. field Double Click
and select Qualification
Markup - add a date Used to add a field containing the date selected on
the right side of the buttons
NA Used to add the N/A sign into the signature field
instead of the signature
Picture Used to add a picture into the Jobcard
Rectangle Frame Used to add a rectangle frame by holding the left
mouse key and drag it right and down
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-34 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Table Used to add a table to the JC - this table can be filled
Text Used to point into one of the fields of the
table to add individual text
Arrow Adds an arrow that can be arranged with 2 dots on
each side to point to something specific
Total Signed Shows the number of total sign-fields and the
number of them not signed
Open Signatures Shows the number of Signatures, Inspections
and Double Inspection fields
Signature Action Next Signature Box - this button focus on the next
signature field to the end of the document
Stamp your login into the signature fields and close the workorder.
Click on: Next Sign Request box
Click on: Stamp or N/A
Move your mouse pointer over the signature field and left - click
Continue until all signature fields are stamped
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-35 DATE: 01 DEC 2023
AMOS ENGINEERING MODULE
PART 2: AMOS ENGINEERING 2. 9 WORK INTRUCTION
Click on: Export PDF (PDF icon in File section)
You would now be able to save the Jobcard & the data you added as a pdf. With a
workflow you could save the pdf on a specified folder to archive the data.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
STRUCTURAL DAMAGE
Overview
Structural Damage is used to display data about damages on an aircraft or
rotable parts. To have a better overview, Structural Damage gives you the
opportunity to pinpoint the location of the damages on pre-scanned
images. The pictures are used to create a Dent & Buckle Chart, where
every damage can be viewed in detail. A table displays an overview of all
damages of the aircraft or rotable.
Structural Damage has a Search Filter panel on the left with several
selections to refine your search and filter for specific damage settings.
Several tabs can be generated with specific search sets. Once you have
entered your search and filter criteria, click Search to show information in
the rest of the program window.
Note: Images must already be entered in Aircraft Administration or Part
Administration in order to load them in this program.The following image
types are supported: PNG, JPG, GIF, CGM and SVG.
Features
All features apply to both aircraft and rotable part damages.
One workorder can have several damages but one damage can only
have one main workorder.
As soon as a damage with a repetitive inspection is created, an Ad-hoc
JIC can only be created directly from Structural Damage if the
Workorder No. field is filled with a linked workorder.
Rotable part damages can be displayed on both an aircraft and a
rotable chart and the damage follows the part when it is installed on a
different aircraft.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-1 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Structural Damage process flow
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-2 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Structural Damage Part Damage – Flow
Structural Damage Management in Engineering Part 2
Overview:
Aircraft Administration (APN 308)
Aircraft Code Definition (APN 2627)
Part Administration (APN 59)
Maintenance Event Initialiser (APN 1895)
Technical Assistance (APN 869)
Maintenance Event Browser (APN 2151)
SD Workorder for Loan Replacement & Work Steps - Workorder (APN
1418)
Event Tracking / Transfer WO / Damage / AD-HOC JIC and Structural
Damage - Event Tracking (APN 432) / Structural Damage (APN 786)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-3 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
2.10.3.1 Aircraft Administration (APN 308) Overview
Aircraft Administration is the source of important information for many
different programs within AMOS such as Maintenance Programs
Administration, View / Edit Modifications and Workorder to name just a
few.
Crucial Aircraft data such as:
Limitations like the Autoland category
Link the aircraft to an existing Maintenance Program or an existing
Aircraft Configuration
Aircraft Rating
Assigned Counters to an Aircraft
Utilization (Airline) or Ground Time of of an Aircraft
Linked OEM documents can be found here.
2.10.3.2 Aircraft Code Definition (APN 2627) - Overview
This program is used for managing Panels, Areas, Zones, System
configuration and Mission configuration per aircraft type / fleet.
2.10.3.2.1. Exercise: Define a new Area and a new Opening and Closing
Workorder for a Panel for A/C Type 32S:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-4 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Aircraft Type
Select: 32S
Areas tab
Click on: New
Code: 19001
Description: BELLY FAIRING AC AND HYD COMP
Click on: OK
Panels tab - Add a NEW panel
Code: 197GB01
Description: BELLY FAIRING ACCESS PANELS ON LH
Click on: OK
Opening Workstep
Click on: Add Entry
Choose: Description
Description Text: OPEN PANEL 197GB01, BELLY FAIRING ACCESS
PANELS ON LH
Click on: Save
Click on: Add Entry
Choose: Zones/Areas/Panels/Special
Area Codes: 19001
Click on: Save
Click on: Add Entry
Choose: Resource Requirement / Staff
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-5 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Scope/ Planning B1
Qualification:
Total Hours: 00:54
Quantity: 1
Click on: Save
Repeat the steps described above for
the Closing Workstep. Adapt the
Workstep Description accordingly.
2.10.3.3 Part Administration (APN 59) - Overview
All part numbers must be defined in the program Part Administration
before they can be used in any other AMOS program. Exceptions are Part
Requests on a Workorder, on a Taskcard, on a Document and on a
Generic Event where unknown Part Numbers can be entered.
Each Part Number can have important characteristics and details assigned
to it which will determine how it is used in other AMOS programs. New
Part Numbers are usually entered into AMOS by the Spares Department,
although certain details such as information regarding Alternates and
Aircraft Positions are generally entered by the Engineering Department.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-6 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-7 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
2.10.3.3.1. Exercise: Enter a new Part Number
Parts Tab
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-8 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: Create Part
Part Number: PW4168A01
Description: ENGINE ASSY
Material Class: Rotable
Material Type: P
Measure Unit: EA (Each)
FA Type: 330
ATA-Chapter: 72-00
Click on: Publish
You can enter a reason for the creation of a new part. This is not
mandatory.
Click on: OK
Weight: 7100
Specification: PW4000 100-INCH
Country of Origin: CA
Default Supplier: 16359
Default Repair: SRT-ENG
Click on: Save
Main Tab - Alternates Tab
Click on: New
Type: A
Alternate: PW4168A
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-9 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Select: Two ways interchangeability
Approved by: NXBM
Approved Date: -3w
Click on: Save
AMOS will present the Set Alternative Two Ways dialogue box.
Click on: Yes
Main Tab - Location Tab
Click on: New
Station: ZRH
Store: Main
Location: 12D6
Click on: Save
Remarks Tab - Int. Remarks Tab
Text: HIGH VALUE ITEM
Click on: Save
Aircraft tab - Aircraft Type:
Click on: New
Aircraft Type: 330
Number Type: S (Serial Number)
Number From: 1000
Number to: 8000
Qty per A/C: 2
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-10 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
IPC Reference: 72-00-00-05-300B
Click on: Save
Miscellaneous Tab - Special Tab
Click on: New
Special: ENGINE
Click on: Save
Click on: New
Special: MAJEQU
Click on: Save
Click on: New
Special: MTBUR
Amount: 6500
Click on: Save
2.10.3.4 Maintenance Event Initialiser (APN 1895) Overview
This program is used to initialise all Maintenance Events (Checks,
Documents, Rotables, Requirements and Taskcards) created in AMOS
and synchronise Time Requirement and MP Revision.
The program offers the following functions:
Multiple search criteria available based on the maintenance event.
Display of the work template for not yet initialised maintenance events
Display of workorder/planning information for pending events
Multi-Selection for both, not yet and already initialised events
Synchronization of Time Requirements
Scenario:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-11 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Engineering has received a Technical Query via Technical Assistance
that a new Check was created yesterday. This check needs to be
initialised for aircraft AAA and DAA.
2.10.3.4.1. Technical Assistance (APN 869):
Overview
Technical Assistanceis used to collect and track several problems within
AMOS.
Every new entry or a change to an entry, response or note triggers a
workflow which must be activated in Workflow Administrationby your
AMOS System Administrator. Four different workflows are available for
which rules can be defined.
Note: When you first open the program, there is no information displayed
until you use the Search filters.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-12 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
2.10.3.4.2. Exercise: Open Technical Assistance (APN 869) and search for the
query fulfilling the following conditions:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-13 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Station: ZRH
Assigned Group: Engineering
Double click in the field Header contains
Operator: Phrase
Type in: Check
Click on: Add new condition
Change operator OR to AND if required
Operator: Exact Word
Type in: AAA
Click on: OK
Click on: Search
Read the query carefully.
Open Maintenance Event Initializer (APN 1895) to initialise the Weekly
Check:
A/C registration: AAA;DAA
Click on: Exclude Checks (should be Include Checks
afterwards)
Check Type: Weekly
Click on: Search
Initialisation tab
Why do the listed aircrafts have different due dates?
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-14 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
How was the due date calculated by the system?
Select the line with aircraft AAA
Click on: Initialise
Choose: Enter Last Performed
D (Calendar Days): -4d
Click on: Next
Check the new Due Date
Click on: Finish
Select the line with aircraft DAA
Click on: Initialise
Choose: Enter Next Due
D (Calendar Days): +7d / 23:59
Click on: Next
Check the new Due Date
Click on: Finish
Click on: Search
Maintenance Events tab
Check the result of the initialised Weekly Checks
Go back to Technical Assistance:
Click on: Add Entry
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-15 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Choose: Close
Add the following Note:
Dear Declan,
the Weekly Check is now initialised for aircrafts
AAA and DAA Regards
(Your Name)
Click on: OK
2.10.3.5 Maintenance Event Browser (APN 2151)
The program offers the following functions:
Multiple search criteria available based on the maintenance events.
Display historic, current, and future maintenance events.
Display the details, work templates, and in the history tab, the related
Workorders issued.
View a summary and any transfer information of a selected
maintenance event.
Allow direct modification using advance administrative tasks
(appropriate buttons)
2.10.3.6 Workorder (APN 1418) Overview
2.10.3.6.1. SD Workorder for Loan Replacement & Work Steps
Please create a new Aircraft Workorder with the following data.
W/O Type: Scheduled
A/C Registration: BAA
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-16 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
ATA-Chapter 78-31
Date: -1d
Time: 14:00
Sign Your login
Station To: ZRH
Click on: Next
Add Work Step (Note: In Workorder main screen, this will be displayed as
Work Step 1)
Date & Time: -1d, 14:15h
Headline: PREPARE FOR REPLACEMENT OF LOAN UNIT
Description: PREPAR AIRCRAF FO REPLACEME OF THRUS
E T R NT T
REVERS
ER
Description Sign: Your login
Click on: Finish
Complete the entered WO with the following information:
Click on: Administr. Transfer
Due Date: Today
Sign: Your login
Reason: PLN
Click on: Save
In the Work Step 1 section, on the Planning View section
Select: Resource Request
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-17 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: New (Staff)
Scope / Planning MECH
Quali.
Total Hours 3:00
Quantity 2
Click on: Save
We will now import a predefined workstep from the Workstep Repository:
Workstep 2
Planning View
Click on: Import Repository Work Step
Description Text: THRUST REVERSER
Click on: Search
Select Workstep No: 6296
Click on: Save
The second workstep for replacement of Thrust Reverser is now added to the
workorder
We will now enter the 3rd Workstep manually:
Workstep 3
Click on: (Create Work Step)
Headline: TESTING OF THRUST REVERSER
Description: CARRY OUT TESTING OF T/R IN COMPLIANCE
WITH MOE
Work Step Idle-/Test-Run
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-18 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Class./Ref.
Skill/Manhours B1 technician for 3
Mhrs Two MECH for
6 Mhrs
Click on: Finish
To perform the second work step, you have to issue a pickslip:
Under Related Actions, click on Issue Pickslip
Create Pickslips window opens
Click on: Issue Pickslip
Check the appearing Pickslip Request and click on Send
Take a note of your pickslip number _ _
Picking List Management (APN: 2612)
Enter your pickslip number and click on Search
Picking List / Request section
Select the line with your requested Part number
Write down the allocated Serial Number: _
Confirm:: Booking Sign & Date
Click on: Book
You will receive a pop-up informing you that your pickslip is completely
booked.
Click on: OK
Please close the program Picking List Management and return to your
Workorder.
This work has been performed and the Rotable Replacement has to be
booked before the Workorder is closed. Proceed as follows:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-19 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: in the gray header of the Work Step 1, on the
Production View section.
Performed Date: Today
Performed Time: Now
Headline: PREPARE FOR REPLACEMENT OF LOAN UNIT.
Action: LIFTING EQUIPMENT INSTALLED SATIS.
Select: Work on step completed -> Close work step
Performed Sign: Your login sign
Click on: Next
Click on: Add/Edit Time
User Sign: Your login
Duration: 1:30
Repeat the time for user AASP, Duration: 1:30
Add time and click Finish
on:
Click on: in the gray header of the Work Step 2, on the
Production View section.
Performed Date: Today
Performed Time: Now
Headline: REPLACEMENT OF LOAN UNIT
Action: REPLACEMENT OF THRUST REVERSER
PERFORMED IAW AMM 78-31-01-0004-001
PARAGRAPH 2.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-20 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Performed Sign: Your login sign
Click on: Next
Click on: Time
User Sign: Your login
Duration: 3:50
Repeat the time for user AASP, Duration: 3:30
Click on: Uplifts
Oil Uplift: ENG1: 3.5
ENG2: 3.0
Oil sign Your login
Click on: Ok
Now book the Rotable replacement as follows:
Click on: Component Change
ON Section:
Part No: 70M000-513
Serial No: Type in the reported Serial Number from above
Certificate No. Confirm the suggestion
OFF Section
Part No: Confirm the Part Number suggested by AMOS.
Serial No: Double click in the field, and select the S/N currently
installed.
Position: Confirm the position suggested by AMOS
Click on: OK
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-21 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: Finish
Based on our Workorder Setup, AMOS will automatically open the
program Labelbooking. Double check the information on the label.
Click on: Counters
Hours: Check the hours suggested by AMOS.
Landings/Cycles: Check the cycles suggested by AMOS
Click on: OK
Removal Store: Confirm the suggested store by AMOS
Removal U/S Confirm the suggested location by AMOS
Location:
With parameter 1'641 the store / location can be prefilled with the Default
User Settings
Click on: Book Label
AMOS will present a message stating that the label was successfully booked.
Click on: OK
Click on: Exit in the label booking window
Right click: in the gray header of the Work Step 2, on the
Production View section.
Choose: Close to close the second workstep
Close the Workorder as follows:
Click on: Close
AMOS will present the Close W/O Wizard. Workstep 3 must have an Action
Text entered against it to allow the closure of the Workorder.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-22 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Performed Date: Today
Performed Time: Now
Headline: Confirm Suggestion
Action text: OPERATIONAL TEST PERFORMED IAW
AMM78-31-00-710-040-A
Time: Please book 3 hrs for the following logins: Your login,
AASP and FKSM
Click on: Next
Closing Station: ZRH
Closing Date/Time: Today/Confirm the time suggested by AMOS.
Select: The last actual Flight TAH/TAC
Approval No. Confirm Suggestion
Closing Sign: Your login sign.
Click on: Finish
Your Workorder is now Closed.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-23 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
2.10.3.6.2. Event Tracking / Transfer WO / Damage / AD-HOC JICand
Structural Damage
Event Tracking (APN 432)
Event Tracking gives the Maintenance Controller the tools to record all
events which impact on the operation of the A/C or a Station. Events can
be classified, given ‘advise’ times and a log of the actions taken to resolve
the event can be kept within the program.
Scenario:
During the last flight to ZRH, the pilot reported possible hail damage.
MCC created an unscheduled W/O and sent a line maintenance technician
to the aircraft to check for structural damage. The technician found a dent
and contacted us in the Enginnering.
Our task is now to complete the W/O.
Event Tracking (APN: 432)
Open the program Event Tracking (APN: 432)
Search tab
At Date: today
A/C: AAA
ATA Chapter: 53-11
Click on:
Select the event in the Result tab and read the content carefully.
In the yellow header click on Ref. W/O and choose: Open with.../
Workorder
2.10.3.6.3. Workorder (APN: 1418)
You now have to transfer the workorder to the expected final repair, and
create an Ad Hoc JIC which will be used to perform the repetitive
inspection of the dent, until the dent has been finally repaired.
Open the program Workorder (APN:1418)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-24 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Enter your workorder number from the previous exercise and press Load
Click on: (Description)
Complete the Work DENT EXTERNAL FUSELAGE SKIN FR 9,
Step Description with STRG 7 DENT DIAMETER: 55.0 MM,
DEPTH:1.5 MM
Click on: Save
Click on: (Action)
Perform Date / Time: Confirm the date and time suggested by AMOS
Headline: DENT IS IN ALLOWABLE LIMIT ACC. SRM 53-
11-17
PERFORM REPETITIVE INSPECTION EVERY
3000 FC. WORKORDER TRANSFERRED TO
FINAL REPAIR, REPAIR SHOULD BE
PERFORMED BEFORE 60000 CYCLES
Action: FOR DETAILS REFER TO DAMAGE CHART IN
STRUCTURAL DAMAGE
AD-HOC JIC CREATED, PLEASE DEASSIGN ON
FINAL REPAIR.
Perform Sign: Confirm the sign suggested by AMOS
Click on: Next
Click on: Time
User Sign: HXYO
Duration: 1:00
Click on: OK
Click on: Finish
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-25 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
You now have to transfer the workorder to the final repair
Click on:
Select: DD
Station: ZRH
Transfer Date / Time: Confirm suggested date and time
Input Type: Due
Due at: 60000 Cycles
Reason: FREP
Approval No. Confirm suggested approval number
Transfer Sign: Enter your log-in sign
Click on: Finish
You can now continue, and enter information about the Man Hours and
Qualifications required to perform the final repair
On the right hand side (Planning View) click on the resource request icon in
the work step header
Click on: Staff
Scope / Planning B1
Qualification:
Total Hours 36:00
Quantity 2
Click on: Save
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-26 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
2.10.3.6.4. Structural Damage
You can now add the information about the Structural defect found
Click on: Damages
Click on: New
Damage Description: HAIL DAMAGE
Type of Damage: DT (Dent)
Nature of Damage: OTH (Other)
Damage Classification: MINOR
Frame/Station: FR9
Stringer/Longeron: STRG7
Side: RH
Dimension:
Unit: MM
Depth: 1.5
Diameter: 55
Inspection:
Within Limit Tick
Further Action Required: Tick
Repetitive Inspection:
Select by document reference
Now define the Ad Hoc JIC to perform the repetitive inspection of the dent.
Click on: Ad Hoc JIC
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-27 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: New
Title: REPETITIVE INSPECTION_01
Click on: Save
Click on: New (Worktemplate)
ATA Chapter: 53-11
Click on: Next until Add workstep is displayed.
Headline: REPETITIVE INSPECTION
Description: PERFORM REPETITIVE INSPECTION IAW SRM
53-11-17
Click on: Next until the step to add a Resource Request is
displayed
Click on: New (Staff)
Scope / Planning NDT
Qualification:
Total Hours: 0:30
Click on: OK
Click on: Finish
Set the worktemplate to Active
Select tab-sheet: Time Requirement/Init Aircraft
Sub Tab: Editor
Click on: New
Mode Selection: Basic Definition
Click on: Next (x 2)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-28 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Dimension: C
Amount 3000
Click on: Finish
Click on: Activate
A/C to Assign: Confirm your Aircraft
Click on: Initialise
Set Taskcard Number: 3000 Cycle Inspection 01
Select: OK
Select: Enter Next Due
C(Flight Cycles) 24400
Click on: Next
Click on: Finish and OK
Choose: Taskcard (the name of the AD Hoc JIC should
appear)
Status: NEW
Entry Date/Sign: Today / Your login
Reference Type: SRM
Insert free text 53-11-17
Click on: Add
Select tab-sheet: Add. Data
Defect Part: SKIN
Inspection Method Used DETAILED VISUAL
Select: Save
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-29 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: OK
The workorder remains open because it has been transferred to the final
repair limit.
Please open the program ‘Maintenance Forecast’ and find your workorder,
and Ad Hoc JIC
The damage has been reported and inspected but still has to be recorded
on the Structural Damage (Dent & Buckle) Chart.
2.10.3.6.5. Structural Damage (APN: 786)
Click on: Choose A/C
Double click: AAA
Damage settings / Header
Tick: ATA incl. 53-11
Damage settings / Description
Tick: Nature of Damage incl. & choose OTH (Other)
Damage settings / Inspection
Tick: Further Action Required (incl.)
Tick: Within Limit, incl.
Click on: Search
Select on the upper right side the chart AAA - A320 RH UPPER VIEW
Select your Structural Damage in the table below
Position your mouse/cursor above the #3 RH Windshield in the AAA - A320
RH UPPER VIEW picture and click.
Your Structural Damage is now positioned on the RH VIEW Chart.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-30 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Next step is to link some photographs of the damage. The perfect place
to store those files is the AMOS Webdrive. The link to the damage can be
performed as follows:
Click on the entry Reference/Links column of the reported Damage:
Select: Manage References/Links
Select the Link Type Webdrive
Click on: Choose
Browse to folder: Structural Damage/A320 Family
Select: Pic_HailDamage(Dent).jpg
Click on: OK & Save
Report
Click on: Preview the Structural Damage Report and the
Single Damage Report
Structural Damage Management in Line/Base Maintenance
2.10.4.1 Exercise: Structural Damage (APN 786)
You are going to create a Workorder (APN 1418) which is recording a new
damage found on the aircraft by the Pilot.
If this is being created for a non managed A/C you have the possibility to
produce a Single Damage Report to send to the operator for their records
along with the tech log entry and workorder.
You will then add the damage entry to the relevant Structural Damage
chart.
Click on: New System WO
Select W/O Type
Select: Aircraft Workorder
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-31 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Select Pirep
Click on: Next
Header Information
A/C Registration: AAJ
ATA-Chapter 53
Station To: ZRH
Date: Yesterday
Time: 10:00
Sign: Confirm the sign suggested by AMOS
Click on: Next
Add Work Step (Description text)
Date: Yesterday
Time 10:00
Headline: BIRDSTRIKE TO A/C NOSE.
BIRDS ENCOUNTERED ON DESCENT INTO BSL.
Description: FEATHERS AND BLOOD EVIDENT ON RADOME.
Description Sign: Confirm the sign suggested by AMOS
Click on: Next
Workstep Class. / Ref.
Ref type AMM
Insert as free text 53-10-61
Click on: Add
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-32 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: Finish
Add an action, select Action
Performed Date: Yesterday
Time: 10:30
Headline: BIRDSTRIKE TO A/C NOSE.
FEATHERS AND RESIDUE CLEANED OFF.
INSPECTION PERFORMED (TAP TEST) IAW NTM
51-77-10.
SMALL AREA OF DELAMINATION FOUND ON
RADOME DEAD CENTER.
Action: APPROX. 10MM DIA.IN LIMIT IAW AMM 53-10-61.NO
PAINT DAMAGE EVIDENT. CLEAR TAPE APPLIED
OVER DAMAGE AREA TO PREVENT POSSIBLE
WATER INGRESSION.
FOR DETAILS REFER TO DAMAGE CHART IN
STRUCTURAL DAMAGE.
Performed Sign: Confirm the User suggested by AMOS.
Click on: Next
Now enter your working time as follows:
Click on: Time
User sign: Confirm the sign suggested by AMOS
Duration: 01:00
Change to Start/Dur: -1D / 10:30
Click on: OK
Click on: Finish
Add the information about the structural defect found
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-33 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: Damages
Click on: New
Damage Description: BIRDSTRIKE TO RADOME NOSE
Type of Damage: DEBONDING
Nature of Damage: BIRDSTRIKE
Damage MINOR
Classification:
Location/Other Radome dead center
Location
Dimension: MM
Diameter: 10
Inspection: Within Limit
Status: NEW
Entry Date/Sign: Today / Your login
Reference Type: AMM
Insert free text 53-10-61
Click on: Add
Select: Add. Data tab
Defective Part: COMPOSIT PARTS
Inspection Method DETAILED VISUAL & OTHER
Used
Tick Temp. Protection Applied
Select: Save
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-34 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: OK
Now you can Transfer the workorder with the following information:
Click on:
Select Radio Button: DD
Station: ZRH
Transfer Baseline: Yesterday
Time: 10:00
Input Type: Due
Check Type: C
Reason: PLN
Transfer Sign: Confirm the sign suggested by AMOS
Click on: Finish
Your workorder is now Transferred.
Write down your WO number:
The damage has been reported and inspected but still has to be recorded
on the Structural Damage (Dent & Buckle) Chart.
In the event of this being recorded for a non managed A/C this step would
be dependent on your processes. If Structural Damage is used then as
well as a Single Damage Report, a Dent & Buckle Chart can be produced
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-35 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
which includes the damage charts for the A/C type and the A/C's individual
damage entries.
2.10.4.2 Exercise: Structural Damage (APN: 786)
Click on: Choose A/C
Double click: AAJ
Damage settings / Header
Tick: ATA incl. 53
Damage settings / Description
Tick: Nature of Damage incl. & choose BIRDSTRIKE
Damage settings / Inspection
Tick: Within Limit, incl.
Click on: Search
Select on the upper right side the chart AAJ - FRONT VIEW
Select your Structural Damage in the table below
Postion your mouse/cursor dead center of the A/C nose in the AAJ -
FRONT VIEW picture and click. Your Structural Damage is now positioned
on the FRONT VIEW Chart.
Left click on the damage information bubble and drag and drop to a
position not covering the picture
In Structural Damage we can also record Damages to A/C Components (if
Picture Images have been added in APN:59 Part Administration).
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-36 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
In the next step we will link the damage to the Component. Double click on
the Damage item 1(either on the Damage List or on the Picture View).This
will re-open the Damage Report.
As the Damage has been Located on a picture view, you now have the
Component fields available.
Add Part Number: D5311047700007
Add Serial Number: Double click in the Serial Number field and select
your installed Serial number.
Click on: OK and Save.
The Damage is now recorded as a Rotable Damage, with the P/N visible on
the item. Now we will copy the Damage to the Rotable Picture.
In the Search filter click on Rotable Selection, Choose Rotable. Click
Search, highlight your Rotable and OK.
At the bottom left, Click Search again and your Rotable image will appear on
the Chart Info List.
Hold the Ctrl button, and with your mouse select the Front View and the
Rotable Image. You now have both images visible.Adjust, with the slidebar,
to see the Item info on the Front View.
Right click in the Item bubble and select Copy Entry.
On the Radome picture Right click and Paste Entry.
Now you have two entries for the same Damage.One on the A/C and one on
the Rotable.
Report
Click on: Preview the Structural Damage Report and the
Single Damage Report
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-37 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Q&A: Explain the overview of the process that is used within AMOS to
record the occurrence of damage to the A/C, and which different roles
would be involved.
How can a user make a link to a digital photograph of the damage?
Structural Damage Management in Component Workpackage
2.10.5.1 Overview
Component W/P Close Loop - Cargo Panel
Component Workpackagecontains all the required functions to manage
extensive maintenance, repair and overhaul activities in a shop
environment. It enables you to plan, control and execute the production of
single components and complex assemblies not only in-house but also for
third party maintenance.
Component Workpackageis based on the aircraft maintenance concept
and benefits from all the features available in the corresponding programs,
such as the forecast of maintenance events, the production plans or the
capacity planning.
Component Workpackageallows you to:
▪ Create component workpackages for rotables, consumable repairables
or unknown part numbers.
▪ Set the target start and end dates, the planned start and end dates, and
the turnaround time.
▪ Visualise the component tree and modify it: create tags, add children to
the component tree, disassemble a sub assembly, scrap components.
▪ Assign executable (shopcards) and non-executable (customer
requirements) events, edit the planned dates of the work steps.
▪ Pause / resume work on the component, confirm the shop arrival, route
component to a next shop.
▪ Create work steps, import a work step from the repository, duplicate the
work step and edit the work step sequence.
▪ Add shopcards defined in Work Template Manager, create ad hoc
shopcards.
▪ Create shopcard findings.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-38 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
▪ Add, import and delete component certificates and release components.
▪ You can export Metadata from this program to Storage Engine Manager,
to send all documentation related to the CM WP for archiving to an
external document management system. After CM WP release, workflow
525 - Main Component Released (Post-Save), is used to trigger the
storage engine.
In Repair Administrationit is also possible to:
▪ Create a component workpackage from an existing repair order.
▪ Or link a repair order to an existing component workpackage.
Note: In the context of a component workpackage, the only type of
executable event is the shopcard, i.e., there is no taskcard, workorder,
block taskcard or check such as for the aircraft workpackage.
2.10.5.2 Exercise: Component W/P Close Loop - Cargo Panel
In the exercise we will demonstrate the Close Loop process. The purpose
of the Close Loop is to perform a Maintenance operation in the shop under
the release of the Aircraft. This is especially related to hangar support
shop operation (eg Cleaning, Interior, Structure, Paint…)
Open the program Workorder (APN 1418)
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-39 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: New System W/O
Select W/O Type
Select: Aircraft Workorder
Select: Maintenance
Click on: Next
Header Information
A/C Registration: AAA
ATA-Chapter 53-30
Station To: ZRH
Date: Today
Time: Now
Sign: Your login
Click on: Next
DAMAGED FASTENERS TO BE
Description: REPLACED DAMAGED PROTECTIVE
FINISH TO BE RENEWED
Description Sign: Your login
Click on: Finish
Click on: Create CM W/P
Part No. D5237295200000
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-40 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Serial No. 1001
Req. condition R
Shop STRUCTURES
Target Date / Time TOM / 1400
Reason for removal Hint, right click & history to retrieve the original
complain
Click on: Finish & OK
In this case the panel is serialised however not recorded in AC
configuration. We can still record it and proceed the Component
Workpackage. This is possible as there is no Label Booking involved in
this process thus the part is removed physically but not AMOS wise.
Open the program Component Workpackage (APN 3075)
Search Section
Return Type: Closed Loop (CL)
Click on: Search
Find your Component Workpackage and highlight it
Workpackage Tab / Main Tab / General information
W/P Status Open
Click on: Save
Planning Tab / Input Tab
Click on: Confirm Shop Arrival
Confirm the displayed information
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-41 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: Finish & OK
Production Tab / Pending Tab / Issue Actions
Click on: Create Shopcard
Click on: Next
Number SH1001
Title CARGO PANEL REFURBISHMENT
Click on: Next
Phase SH-SREP
DO FASTENER REMOVAL IAW SRM 51-42-
00. RENEW THE PROTECTIVE FINISH IAW
SRM 51-75-12. DO FASTENER
Description Text INSTALLATION IAW SRM 51-43-00.
PUT ALL THE RETAINED HARDWARE IN
IDENTIFIED PLASTIC BAG ATTACHED TO
THE RELATED UNIT.
Confirm Description Sign
Click on: Next until step 5. Part Requests
Production Tab / Pending Tab / Planning View
Click on: Add
Part Number: TTP1757
Qty: 2
Click on: Add & New
Part Number: 32593-1
Qty: 4
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-42 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: OK & Finish
Production Tab / Pending Tab / Related Actions
Highlight your Shopcard
Click on: Start Live Booking
Click on: Issue Pickslip & OK
Click on: Issue Pickslip
Receiver: 6600
Click on: Send
Note the pickslip number here:
Click on: OK
Open the program Picking List Management (APN 2612)
Pickslip No: Your pickslip number
Click on: Search
Highlight both the requests
Booking Sign / Date STOR / today
Click on: Book
Go back to the program Component Workpackage (APN 3075)
Production Tab / Pending Tab / Production View / #1 Work Step
Click on: Update Component Condition
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-43 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Condition: R
Confirm Performed Date & Time
Action Text: ALL WORK PERFORMED IAW SRM REFERENCES
Confirm Performed Sign
Click on: Save
Click on: Close Work Step
Confirm all mandatory fields
Click on: Finish
Production Tab / Pending Tab / Related Actions
Click on: Stop Live Booking
Production Tab / Pending Tab / Actions
Click on: Close
Click on: OK
Confirm Closing Station, Closing Date & Closing Time
Approval No. CH145.000
Confirm Closing Sign
Click on: Finish
The panel is ready to be returned to the Aircraft and you will now generate
the related paperwork.
Planning Tab / Input Tab
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-44 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Click on: Print Component Tag & OK
You have now an updated tag to attach to the unit, close the print preview
pane.
Planning Tab / Input Tab / Result Pane
Right click on: Your Shopcard
Shopcard / Report / Print Shopcard Report
Click on: Cancel
In case of Close Loop no certificate is generated, the work performed in
the shop is encompassed under the release of the Maintenance
Workorder. The printed Shopcard will be attached to the the Aircraft dirty
finger print (DFP) for reference.
You can now close your Workpackage
Structural Damage Reporting
2.10.6.1 Damage Reports
There are 3 available reports in the Structural Damage module:
1. Single damage report
2. D&B chart – Structural Damage Report
3. Table report (to print the damage table content)
The D&B chart will contain all the damages that result from the search.
Besides the options in the report dialog, the report also respects the
settings made in the search filter of the program. The damages contained
in the report are defined by the search filters themselves, as it contains the
damages listed in the table as a result of the current search.
Additionally, the “Chart options” in the search filter are regarded in the
Structural Damage Report, if charts are to be printed. The “Red Circle”,
“Fill Colour”, “Full Entry” and “Status Code” options will define how the
charts are displayed in the report, and the “display mode” (“All” / “Only
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-45 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
Containing Damages”) defines whether charts without damages are
included.
2.10.6.2 Illustrations
OVERVIEW:
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-46 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
2.10.6.3 Other relevant APNs
APN 612:
Using Workflows you are able to inform other user / departments about
specific
work which was accomplished.
For Structural Damage there are some Workflows available:
1. Remove component from A/C chart
2. Delete Item
3. Item marked as “Closed”
4. Enter new Item
5. Print original List
For each of the above listed events you are able to select different actions,
like send an AMOS Mail Message, send an E-Mail, show a popup etc.
Please contact your AMOS Admin to setup the Workflow.
APN 18:
Basic Data Administration is one of the programs that serves the data into
the different programs.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-47 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
This is the place you are able to define what entries you want to choose
within the program.
Please contact your AMOS Admin for adding new entries into the specific
lists.
APN 16:
Within APN 16 (Admin Programs) you will find different licences – to limit
the rights of the different user groups.
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-48 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 2: CONTENT 2.7 STORE MODULE
AMOS-CP-MAN PAGE ISS: 01 REV: 00
2.9-2.10-49 DATE: 01 DEC 2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 3:
CODE OF TRAINING Page Iss.: 01 Rev.: 00
COURSE AMOS-SP-EP-MAN 3-1 Date: 30-Nov-2023
AMOS TRAINING MODULE
SUPPLY - EXIMPORT
PART 3: 3.1 REFERENCE DOCUMENTS
REFERENCE DOCUMENTS
CODE OF TRAINING Page Iss.: 01 Rev.: 00
COURSE AMOS-SP-EP-MAN 3.1-1 Date: 30-Nov-2023