TCS P 122 06 R0
TCS P 122 06 R0
TABLE OF CONTENTS
1. SCOPE
2.0 PURPOSE
3.0 APPLICATION
4.1 General
5.1 General
1.0 SCOPE
This standard presents various methods to be adopted in the assembly and erection of
self-supporting latticed and tubular steel structures for the overhead transmission line
system of Saudi Electricity Company (SEC), Saudi Arabia.
2.0 PURPOSE
3.0 APPLICATION
This standard is applicable to the assembly and erection of steel structures. Since
methods will be strongly influenced by the nature of each project, various methods that
have been successfully employed are presented.
The approach used within this standard is to first describe general information, which
is applicable to all phases of steel structure assembly and erection, and then to describe
the methods of erection.
4.1 General
This section covers the various methods and practices employed in assembling
and erecting self-supporting latticed steel structures. Structure foundation and
the dimensions between tower leg attachment points shall be checked prior to
erection.
The field assembly and erection methods chosen will be influenced by such
variables as line and structure design, line route, terrain, climatic and seasonal
weather conditions, the impact of any environmental restrictions, line route
access, and the availability of critical resources in both manpower and
equipment.
Bare wire rope or steel chains shall not be used for handling without
adequate protection of the surface coating. Heavy members shall not
be stacked on top of lighter members. Structural members shall be
stored according to size, lengths and markings. The maximum weight
of steel bundles shall not exceed a specified weight, typically 1600 kg
to 1800 kg, to facilitate handling and unloading. Members with
dissimilar finishes shall not be stored over one another to minimize
discoloration of the lower members.
The material yard shall be kept relatively neat and clean and the
growth of vegetation kept to a minimum. Good housekeeping
minimizes damage and loss of material handling; periodic physical
inventories and complies with environmental considerations.
4.2.3 Assembly
Only torque wrenches, which properly fit the nuts and bolts, shall be
used. The use of wrenches, which in any way deform the nut or cut
or flake the galvanizing is prohibited. Unless otherwise specified in
the project SOW/TS and/or recommended by the manufacturer, the
bolts shall be torqued as per values given in Table 06-1 below:
16 10 to 14
20 17 to 23
Towers shall be erected by any suitable method in the sequence best adapted to
the equipment, workers’ experience and site conditions which will not
overstress structure members.
Tower erection work on any tower foundation shall not take place until the
concrete has achieved strength of at least seventy five percent (75%) of the
specified compressive strength. However, in no case shall tower erection start
until at least ten (10) days after pouring the concrete foundations of a tower has
been completed. Towers can be subjected to stringing loads after the concrete
has achieved its hundred percent (100%) of specified compressive strength.
Adequate tag lines shall be used to ensure that no section of the tower being
lifted will drag on the ground or against any section of the tower already
erected.
At all times at least fifty percent (50%) of the bolts in each connection of the
erected tower members shall be inserted. Until all the bolts in the face of a
section of a tower are inserted, those bolts inserted in that face during erection
shall be finger tightened.
Tower numbering/designation, Danger and Bone & Skull warning signs, shall
be installed on tower for ground and aerial patrolling, as shown in the
Construction Standard TCS-P-122.21. Anti-climbing barrier shall be installed
after the conductor stringing operations are completed on the transmission line.
Cranes with telescoping booms can be more efficient than rigid boom
cranes in rough terrain. Considerable productivity can be lost in the
process of assembly and disassembly of rigid boom cranes. In
addition, continuous handling of boom sections can lead to boom
damage. Preplanning of the crane location at the structure site allows
for any necessary grading work (building of ramps, soil stabilization
etc.) to be accomplished during the foundation construction
operations when suitable equipment is available at the site.
Depending on soil conditions, additional bearing support may be
required under outriggers, tracks, and tires. All soil shall be returned
to a condition acceptable to the SEC Representative after erection.
Any of the following methods shall be used when tower heights and
weights exceed the capability of a crane or where access to the site is
restricted and it shall be noted that experienced knowledgeable
workers are required for a safe and efficient operation:
Using this method to erect towers, the tower shall be paneled meaning
that sections of legs and bracings are bolted loosely together then
moved into position for final tightening.
a. Piecemeal Method
Three techniques are commonly used for this method. The first
method is to install a lifting line from one of the erected legs for
use in lifting other members. The second is to rig a small boom
to one of the erected legs for hoisting purposes, if the design
allows. The third method is to position the base of a single gin
pole in the center of the structure by suspending it from the leg
members at any elevation using bridle slings. The attachment
points for slings and any guys shall be checked for structural
integrity.
b. Section Method
c. Tilt-Up Method
5.1 General
This section covers the recommended procedures for the assembly and erection
of tubular steel structures (poles). These procedures may also apply to single
shaft and H-framed structures. The process will be divided into two main
categories, monopole structures and framed structures i.e. two or more poles
joined by rigid members.
Steel pole erection work on foundation shall not take place until the concrete
has achieved strength of at least seventy five percent (75%) of the specified
compressive strength. However, in no case steel pole erection shall start until
at least ten (10) days after pouring the concrete foundation of a steel pole has
been completed. Steel poles can be subjected to stringing loads after the
concrete has achieved its hundred percent (100%) of specified compressive
strength.
Preplanning of desired crane locations at the structure site allows for any
necessary grading work (building of ramps, soil stabilization, etc.) to be
accomplished during the foundation construction operations, when suitable
equipment is available at the site.
High reach aerial lifts can be effective in providing a safe work position for
workers handling large connection bolts to make aerial connections. The aerial
lift can eliminate the need to install a variety of either temporary or permanent
rigging and climbing devices on each structure. Whenever possible, stringing
travelers and finger lines installed during erection can greatly expedite the wire
stringing operation.
Poles, which consist of one or more sections, shall be assembled either at the
structure site or in a marshalling yard and then transported to the site.
When delivering poles from the storage area to the erection sites, special care
shall be taken during the loading, hauling and unloading to prevent any damage
to the surface of the poles and arms. Slings for handling the poles and arms
shall be made of or covered with nylon or some other non-metallic material to
protect the finish. Poles shall be handled in such a manner that no portion of
the pole is dragged along the ground or against the pole trailer or other objects
that could damage the structure.
Proper initial placement of pole sections can increase the efficiency of the
assembly operation.
Poles and arms shall be placed on suitable cribbing to prevent damage and
provide a level plane that will prevent overstressing of the structure
components.
All finish touch-up shall be done prior to erection. Once the structure
is assembled, it shall be thoroughly inspected. Climbing devices,
Upper and lower pole sections in the area of the slip joint shall
be marked for proper orientation and as a guide for
minimum/maximum slip lengths. Proper orientation and slip
length tolerance for each slip joint shall be as per fabricator’s
drawings. Care shall be taken to match orientation marks
properly while verifying proper alignment of arm connections,
hardware and climbing devices.
As a safety precaution, slip joints below the lift point shall be secured
with a link between the jacking lugs on mating sections during
erection.
Steel poles may be erected by using the lifting lug(s) (if provided) or
by rigging the pole with a padded cable choker. The lift point shall be
supplied by the fabricator or field determined as it varies with the
number of arms and accessories on the pole. Tall, slender structures
may require a two-point lift to prevent overstressing during erection.
During the structure lifting, tag lines shall be used to guide the
structure to its foundation. Once the structure is in place, its vertical
alignment shall be checked, preferably with a transit.
At times, the terrain and environment dictate the need for aerial
assembly. Close inspection of all parts to ensure proper fit is highly
recommended prior to the lift operation.
The bottom pole section is set first, inspected for vertical alignment,
and secured to the foundation. As each subsequent pole section is
stacked, the joint is secured.
After the poles have been assembled, place the poles in proper
relation to each other and level. Install the arms and then the X-
braces (if required) leaving all connections loosely bolted. Special
care shall be taken to maintain the structure geometry when installing
X-braces with adjustable bands. The correct distances between pole
shafts shall be verified before tightening the pole bands. Squareness
of the framed structure shall be checked. It is preferable to erect and
plumb the structure before final tightening of bolted connections.
This procedure shall minimize frame distortion and reduce the
potential for erection-induced stresses. All bolts and nuts shall be
tightened as specified.
5.4.2 Erection
For smaller framed structures, each lower pole section shall be set and
then the entire upper frame shall be preassembled on the ground and
erected as one unit. For larger framed structures, each piece shall be
lifted and attached independently.
Each joint shall be loosely connected until all parts of the structure are
installed. This is necessary to allow adjustments while positioning
and attaching each subsequent part.
The tightening operation shall begin only after all parts are assembled
and all bolts are installed. While tightening the joints, plumbness,
level and orientation shall be continuously checked.
In the case of the anchor bolted concrete type foundation with a base plated
structure, the structure is simply lifted onto the anchor bolts.
The leveling nuts shall be threaded on each bolt sufficiently down on the
threads to allow for the addition of the base plate and top nut. These lower nuts
shall be positioned so that when the base plate is set on the top of them the base
plate will be level and as close as practical to the foundation. After adding the
top nuts, check the structure to ensure if it is oriented and aligned correctly. If
the structure requires raking to allow for load deflections, the nuts above and
below the base shall be readjusted to move the structure out of plumb to the
required position.
When tightening anchor bolt nuts, all nuts on the topside of the base plate shall
be brought to a snug tight condition, and then the nuts on the bottom side of the
base plate shall be brought to a snug tight condition and checked to make sure
that they are bearing completely against the base plate. It is important that the
bottom nuts under the base plate be tightened. Final tightening of the nuts shall
proceed as specified by the manufacturer. If required, anchor bolt nuts may be
secured to the base plate in a manner to prevent unauthorized turning or
removal.
Upon completion of pole erection, the void between the base plate and the
concrete foundation may be filled with non-shrinking, flowable grout.
Special care shall be taken when installing grout so that the pole drains will not
be dislodged or plugged. After the grout has set and the forms removed, each
drain shall be cleared to assure that it is open and free to allow drain water to
flow.
As soon as possible after erection, the contractor shall connect the ground wire
to the grounding attachment on the pole. The wire shall be shaped to fit closely
to the foundation and base of the pole and any excess length shall be trimmed.
Pole numbering shall be installed on pole prior to erection for ground and aerial
patrolling as shown in Construction Standard TCS-P-122.21. Danger & Bone
and Skull warning signs shall be installed on each pole as shown in the
Construction Standard TCS-P-122.21.
The damaged area shall be cleaned using a wire brush and solvent if
necessary to remove rust, grease and other foreign matter. When dry,
the area shall then be coated, using a brush or spray, with a cold
galvanizing compound approved by SEC Representative. As many
coats as necessary shall be applied to obtain a minimum dry film
thickness as specified.
6.5 Bent, deformed or otherwise damaged items (i.e. deformed members may
reflect mislocated footings)
6.11 Plumbness of poles and orientation of erected structures (the final erected
position of a rigid latticed structure will generally be governed by the accuracy
of the installation of the foundations)
Typical Proforma for keeping the record of monitoring, inspection and installation of
structures is attached as an Appendix-1. This Proforma shall be signed by the
Contractor as well as by SEC Representative.
APPENDIX-1
Project:
Contractor:
Temperature: Weather:
• Others (Specify)
General Remarks