MERU UNIVERSITY OF SCIENCE AND TECHNOLOGY
P.O. Box 972-60200 – Meru-Kenya
Tel: 020-2069349, 061-2309217. 064-30320 Cell phone: +254 712524293, +254 789151411
Fax: 064-30321
Website: www.must.ac.ke Email:
[email protected] University Examinations 2016/2017
THIRD YEAR FIRST SEMESTER EXAMINATION
FOR THE DEGREE OF
BACHELOR OF SCIENCE IN INFORMATION TECHNOLOGY
BACHELOR OF SCIENCE IN COMPUTER SCIENCE
BACHELOR OF SCIENCE IN COMPUTER SCIENCE AND FORENSICS
BACHELOR OF SCIENCE IN COMPUTER TECHNOLOGY
&
(FOURTH YEAR FIRST SEMESTER)BACHELOR OF BUSINESS INFORMATION
TECHNOLOGY
CCS 3302: ICT PROJECT MANAGEMENT
DATE: DECEMBER 2016 TIME: 2 HOURS
INSTRUCTIONS: Answer question one and any other two questions.
QUESTION ONE (30 MARKS)
a) Describe the following concepts as used in project management
(i) Project charter (2 marks)
(ii) Monitoring and control (2 marks)
b) Briefly explain two attributes that make IT project different from other types of projects
(2 marks)
c) Describe two roles of a project manager. (2 marks)
d) Describe an overall framework for a project Integration management as it relates to the
other project management knowledge areas and project life cycle. (2 marks)
e) Discuss four (4) tools used in the estimate activity resource process (4 marks)
f) Describe how project management software could assist in project time management and
review. (4 marks)
Meru University of Science & Technology is ISO 9001:2015 Certified
Foundation of Innovations Page 1
g) Briefly explain two basic project cost management principles (4 marks)
h) Explain two elements of communications planning (4 marks)
i) Explain why it is necessary to hold stakeholders meeting during project initiation
(4 marks)
QUESTION TWO (20 MARKS)
a) Identify an IT project of your choice and discuss how you can apply the cycles of project
management to ensure success. (6 marks)
b) Compare and contrast the Project Life Cycle and the System Development Life Cycle
(6 marks)
c) Discuss four reasons for selecting the wrong project (4 marks)
d) Discuss any four project management (PM) process groups (4 marks)
QUESTION THREE (20 MARKS)
a) Describe what is meant by “Project Scope” and its significance in project management.
(4 marks)
b) Explain three suggestions for improving quality for IT projects (6 marks)
c) Explain the term “Project Risk Management” and discuss four major process that could
be applied when managing risk in an IT related project. (6 marks)
d) Explain four levels for project portfolio management (4 marks)
QUESTION FOUR (20 MARKS)
a) Discuss how a Work Breakdown Structure (WBS) can help in cycle of project
management (6 marks)
b) Outline four types of influence that a project manager can have over project team
members (6 marks)
c) Discuss 4 inputs used to estimate project activity resources. (4 marks)
d) Describe the contract closure process (4 marks)
Meru University of Science & Technology is ISO 9001:2015 Certified
Foundation of Innovations Page 2
QUESTION FIVE (20 MARKS)
a) Elaborate on any four aspects of quality in project management (6 marks)
b) Discuss 4 factors to consider when evaluating project impact. (6 marks)
c) What is the purpose of integrated change control in project management? (4 marks)
d) Explain the following terms in IT projects. (4 marks)
(i) Quality planning
(ii) Quality Assurance
(iii) Quality Control
(iv) Cost
Meru University of Science & Technology is ISO 9001:2015 Certified