PROJECT LESSONS LEARNED PROCEDURE - KECL PRC 1106 - Rev 02
PROJECT LESSONS LEARNED PROCEDURE - KECL PRC 1106 - Rev 02
Ref. No: KECL/ENG/PRC/1110 Issue Date: 21st Apr, 2022 Rev. No.: 01 Page 1 of 11
Ref. No: KECL/ENG/PRC/1110 Issue Date: 21st Apr, 2022 Rev. No.: 02 Page 2 of 11
The change(s)/amendment(s) noted below have been made, reviewed and approved by the
involved parties for issue
Entire Nicholas
Updating Document Sadiq Musa Eduard
1 13/01/2020 document Umoh
Kida Koumako
All rights reserved. None of the information contained in this document shall be disclosed outside own company, and no part of this
document may be reproduced or transmitted without the written permission of KOHASA ENGINEERING COMPANY LIMITED
KOHASA ENGINEERING COMPANY LIMITED
Documented Information Title: PROJECT LESSONS-LEARNED
PROCEDURE
Ref. No: KECL/ENG/PRC/1110 Issue Date: 21st Apr, 2022 Rev. No.: 02 Page 3 of 11
Table of Contents
1. INTRODUCTION ...................................................................................... 4
2. PURPOSE OF DOCUMENT ........................................................................... 4
3. OBJECTIVE ........................................................................................... 4
4. REFERENCES ......................................................................................... 5
5. TERMS AND DEFINITIONS ........................................................................... 5
6. ABBREVIATIONS AND MEANING .................................................................... 6
7. RESPONSIBILITIES AND AUTHORITY............................................................... 7
7.1 Project Manager ............................................................................. 7
7.2 Project Engineer ............................................................................. 7
7.3 Project Control Engineer ................................................................... 7
7.4 Document Control Officer .................................................................. 7
7.5 Responsible Persons ......................................................................... 7
8. PROCEDURE.......................................................................................... 7
8.1 Lessons Learned ............................................................................. 7
8.2 Lessons Learned applied from previous Projects ....................................... 8
8.3 Process Improvement Recommendations ................................................ 8
8.4 Time to Start the Processes................................................................ 8
8.5 Project Progress Meeting ................................................................... 9
8.6 Project Closeout Meeting / Discussion .................................................. 10
9. RECORDS ............................................................................................ 10
All rights reserved. None of the information contained in this document shall be disclosed outside own company, and no part of this
document may be reproduced or transmitted without the written permission of KOHASA ENGINEERING COMPANY LIMITED
KOHASA ENGINEERING COMPANY LIMITED
Documented Information Title: PROJECT LESSONS-LEARNED
PROCEDURE
Ref. No: KECL/ENG/PRC/1110 Issue Date: 21st Apr, 2022 Rev. No.: 02 Page 4 of 11
1. INTRODUCTION
Capturing lessons learned is an integral part of every project and serves several purposes.
While the finalization of a formal lessons learned document is completed during the project
closeout process, capturing lessons learned should occur throughout the project lifecycle to
ensure all information is documented in a timely and accurate manner. The lessons learned
document serves as a valuable tool for use by other project managers within KOHASA as an
organization who are assigned similar projects. This document should not only describe what
went wrong during a project and suggestions to avoid similar occurrences in the future, but it
should also describe what went well and how similar projects may benefit from this
information. This document shall be communicated to the entire Project Team for every
project.
2. PURPOSE OF DOCUMENT
The purpose of this document is to help the project team share knowledge gained from the
project so that the entire organization may benefit. A successful Lessons-Learned program
will help project teams:
3. OBJECTIVE
Each project captures all its Lessons Learned before the end of the project
All Lessons Learned are properly documented
All Lessons Learned are reviewed, categorized and grouped as appropriate by the Project
Team
All Lessons Learned are available for general viewing throughout the organization
All rights reserved. None of the information contained in this document shall be disclosed outside own company, and no part of this
document may be reproduced or transmitted without the written permission of KOHASA ENGINEERING COMPANY LIMITED
KOHASA ENGINEERING COMPANY LIMITED
Documented Information Title: PROJECT LESSONS-LEARNED
PROCEDURE
Ref. No: KECL/ENG/PRC/1110 Issue Date: 21st Apr, 2022 Rev. No.: 02 Page 5 of 11
4. REFERENCES
All rights reserved. None of the information contained in this document shall be disclosed outside own company, and no part of this
document may be reproduced or transmitted without the written permission of KOHASA ENGINEERING COMPANY LIMITED
KOHASA ENGINEERING COMPANY LIMITED
Documented Information Title: PROJECT LESSONS-LEARNED
PROCEDURE
Ref. No: KECL/ENG/PRC/1110 Issue Date: 21st Apr, 2022 Rev. No.: 02 Page 6 of 11
EM Engineering Manager
PM Project Manager
PE Project Engineer
PCON Project Control
DB Database
LL Lessons Learned
LLL Lessons Learned Log
DCC Document Control Centre
DC Document Control
TD Technical Director
OPD Operations Director
All rights reserved. None of the information contained in this document shall be disclosed outside own company, and no part of this
document may be reproduced or transmitted without the written permission of KOHASA ENGINEERING COMPANY LIMITED
KOHASA ENGINEERING COMPANY LIMITED
Documented Information Title: PROJECT LESSONS-LEARNED
PROCEDURE
Ref. No: KECL/ENG/PRC/1110 Issue Date: 21st Apr, 2022 Rev. No.: 02 Page 7 of 11
8. PROCEDURE
state what the impact was and provide a recommendation for project managers to consider on
future projects. It is important to note that not only failures or shortcomings are included but
successes as well.
All rights reserved. None of the information contained in this document shall be disclosed outside own company, and no part of this
document may be reproduced or transmitted without the written permission of KOHASA ENGINEERING COMPANY LIMITED
KOHASA ENGINEERING COMPANY LIMITED
Documented Information Title: PROJECT LESSONS-LEARNED
PROCEDURE
Ref. No: KECL/ENG/PRC/1110 Issue Date: 21st Apr, 2022 Rev. No.: 02 Page 8 of 11
The lessons learned document for the previous project are sighted during a new project
internal / progress meetings, to serve as a guide. This information not only shows the value of
the documentation of such lessons, but it also shows which lessons are consistently applied
by other similar projects. It is important to reference not only what the lesson was but from
It is important that once lessons learned are collected and documented, The project manager,
shall approve and implement any process improvements identified. Organizations need to
strive for continuous improvement and this portion of the lessons learned process is an
integral step.
The Project Manager will introduce all that is needed to drive this process from the internal
Project kicks off meeting and the Project team should begin to use this document at its first
project progress meeting. Continually recording Lessons-Learned throughout the project is the
best way to ensure that they are accurately recorded. Topics can be selected from the
following;
All rights reserved. None of the information contained in this document shall be disclosed outside own company, and no part of this
document may be reproduced or transmitted without the written permission of KOHASA ENGINEERING COMPANY LIMITED
KOHASA ENGINEERING COMPANY LIMITED
Documented Information Title: PROJECT LESSONS-LEARNED
PROCEDURE
Ref. No: KECL/ENG/PRC/1110 Issue Date: 21st Apr, 2022 Rev. No.: 02 Page 9 of 11
Sponsor
Customer
Management
support
Objectives
Objectives
Every last week of the month during the internal project progress meeting, the Project team is
to discuss what strategies contributed to success as well as areas of potential improvement
and enter conclusions in the Lessons Learned Log.
All rights reserved. None of the information contained in this document shall be disclosed outside own company, and no part of this
document may be reproduced or transmitted without the written permission of KOHASA ENGINEERING COMPANY LIMITED
KOHASA ENGINEERING COMPANY LIMITED
Documented Information Title: PROJECT LESSONS-LEARNED
PROCEDURE
Ref. No: KECL/ENG/PRC/1110 Issue Date: 21st Apr, 2022 Rev. No.: 02 Page 10 of
11
The Project management team will gather all Lessons-Learned and conduct meetings for
project closeout at the end of the project, and this should happen not later than 4 weeks and
not earlier than 3 weeks after the project closeout report is submitted.
During the team discussions: the following shall be followed
Be positive
Do not place blame!
Focus on successes as well as failures
Indicate which strategies contributed to the success
Indicate which improvement strategies would have the greatest impact
9. RECORDS
All rights reserved. None of the information contained in this document shall be disclosed outside own company, and no part of this
document may be reproduced or transmitted without the written permission of KOHASA ENGINEERING COMPANY LIMITED
KOHASA ENGINEERING COMPANY LIMITED
Documented Information Title: PROJECT LESSONS-LEARNED
PROCEDURE
Ref. No: KECL/ENG/PRC/1110 Issue Date: 21st Apr, 2022 Rev. No.: 02 Page 11 of
11
Project Lessons
Learned LOG.xlsx
All rights reserved. None of the information contained in this document shall be disclosed outside own company, and no part of this
document may be reproduced or transmitted without the written permission of KOHASA ENGINEERING COMPANY LIMITED