Faq On The Assam Public Procurement Act and Rules Final
Faq On The Assam Public Procurement Act and Rules Final
Questions (FAQs)
ON
THE ASSAM PUBLIC PROCUREMENT ACT (APPA 2017)
AND
THE ASSAM PUBLIC PROCUREMENT RULES (APPR 2020)
Disclaimer
If there is any conflict between the FAQ and the provisions in the APPA
2017 and APPR 2020, the provisions in the APPA-2017 and APPR-2020
shall prevail
Updated on: 30th July, 2022
Sl. Query Response
1. What is Please refer to the Assam Financial Rules (AFR), 1939 and
Administrative the Delegation of Financial Powers (DFP) Rules, 2022.
Approval? “Administrative approval” – This term denotes the formal
acceptance, by the administrative department concerned of the
proposals based on preliminary plans for incurring any
expenditure in the Public Works or any other department of
Government on a work initiated by, or connected with, the
requirements of such administrative department. It is, in effect,
an order to the Public Works or such other Department of
Government to execute certain specified works at a stated sum
to meet the administrative needs of the department
requisitioning / requiring the work.
2.b What is Please refer to the AFR, 1939 and the DFP Rules, 2022
“Technical “Technical Sanction” (TS) has the same meaning as in the
Sanction” Assam Financial Rules, 1939.
For every works (except petty works and repairs, and repairs
for which a lump sum provision has been sanctioned), a
detailed estimate must be prepared for the ‘sanction’ of
competent authority and this ‘sanction’ is known as the
"technical sanctions" to the estimate (AFR 240).
Page 1 of 48
Sl. Query Response
3. What is a “Bid”? Please refer to the Section 2(a) of the APPA, 2017 and Rule
2(1)(d) of the APPR, 2020
4. What is “Notice Please refer to the Section 2(d) of the APPA, 2017 and Rule
Inviting 21(5)(v) of the APPR, 2020
Bids”(NIB)? Notice Inviting Bids (NIB) [or Notice Inviting Tender (NIT) or
Invitation for Bids (IFB) or Invitation to Bid (ITB) or Notice
Inviting Tender (NIT)] is a document published by a procuring
entity inviting bids for procurement of specific goods, works, or
services relating to a subject matter of procurement
5.a What is Bid Please refer to the Section 2(e) of the APPA, 2017.
Security? "Bid Security" means a security provided to the procuring entity
by a bidder for securing the fulfilment of any obligation in terms
of the provisions of the bidding documents.
5.b What should be Please refer to the Rule 29(9)(i) of the APPR, 2020.
the amount of The amount of bid security is generally, between 2% to 5% of
Bid Security? the estimated value of procurement, and the amount so
calculated and rounded off to nearest thousand rupees, should
be specified in the bidding documents
5.c In case of two Please refer to the Section 14(iv) of the APPA, 2017.
envelop bids, bid In case of two envelop bids, bid security shall be submitted in
security shall be or along with the first envelope containing the technical bid
submitted with
Technical or
Financial Bid?
5.d When shall be Please refer to the Rule 29(2) of the APPR, 2020.
the Bid Security The Bid Security deposited by a bidder shall be forfeited:
deposited by a a) if bidder withdraws or modifies its bid after opening of bids;
bidder forfeited or
to Govt.?
Page 2 of 48
Sl. Query Response
b) if bidder, after being selected for award of contract, does not
sign the Contract or does not deposit the required
performance security within the specified period; or
c) if bidder breaches any provision of code of integrity
prescribed for bidders specified in the Assam Public
Procurement Act and the Rules; or
d) in two-stage bidding, if bidder withdrawing from the bid fails
to declare its intention to withdraw, citing the reasons
thereof, at least the day before the date fixed for submission
of final bid
5.e If a bidder refuse Please refer to the Rule 23(4)(ii) of the APPR, 2020.
to extend Validity Prior to the expiry of the period of validity of bids, the procuring
of his bid beyond entity, in exceptional circumstances, may request the bidders
the original to extend the bid validity period for a specified additional
stipulated period of time. A bidder, by option, may refuse the request and
validity, should such refusal shall be treated as withdrawal of bid but in such
the amount of Bid cases the bid security shall not be forfeited.
Security be
forfeited to Govt.?
6. Who is a Please refer to the Section 2(f) of the APPA, 2017 and Rule
Competent 2(1)(f) of the APPR, 2020
Authority? A person, body of persons, organs or an agency competent to
take administrative actions.
7.a What is a Please refer to the Rule 2(g) of the APPR, 2020
“Construction Construction Committee means a quasi-governmental
Committee”? committee, comprising inter-alia at least two Government
officials of Grade III level or above, constituted by an
authorized district officer for implementation of various
schemes that are predominantly of local nature and which
require local monitoring, provided they are recognized under
the relevant scheme guidelines.
7.b What kind of Please refer to the Rule 24(N) of the APPR, 2020.
works can be
Page 3 of 48
Sl. Query Response
executed under Construction Committee may take up execution of works under
“Construction the following schemes viz. MP-LADS / MLA-ADS / Schemes
Committee”? under Untied Funds, etc.
8.a What is Please refer to the Section 3(4)(b) of the APPA, 2017 and
“Emergency Rule 2(1)(i) and 24(C)(vii) of the APPR, 2020.
Procurement”? Section 3(4)(b): “Emergency procurement” are those
procurements that are necessary for the management of any
‘disaster’, as defined in section 2(d) of the Disaster
Management Act, 2005 (i.e. “disaster” means a catastrophe,
mishap, calamity or grave occurrence in any area, arising
from natural or man-made causes, or by accident or
negligence which results in substantial loss of life or human
suffering or damage to, and destruction of, property, or
damage to, or degradation of, environment, and is of such a
nature or magnitude as to be beyond the coping capacity of
community of the affected area).
8.b What shall be Please refer to the Rule 24(C)(vii) of the APPR, 2020.
the composition The composition of the District Emergency Procurement
of the District Committee shall be as follows: -
Emergency a) Deputy Commissioner – Chairperson
Procurement b) District Officer of the Concerned Department– Member
Committee? Secretary
c) Sub-divisional Officers of Civil Sub-division – Members
Page 4 of 48
Sl. Query Response
d) Finance and Accounts Officer – Member
e) Concerned Technical Officer – Member
9. What is ‘e- Please refer to the Rule 2(g) of the APPA, 2017.
procurement’? "e-procurement" means the electronic (process of
procurement) where in the physical tendering activity is carried
out online using the Internet and associated technologies.
10. Who is a Please refer to the Rule 2(k) of the APPR, 2020.
“Financial Senior most officer responsible for financial and / or accounts
Advisor”? management in a procuring entity, or an Administrative
Department
11. What is Please refer to the Rule (1)(m) of the APPR, 2020.
“International It is a bidding process in which qualified bidders from all over
Competitive the world, except those having nationality of a country declared
bidding” (ICB)? ineligible by the Central Government, are allowed to
participate.
12. What is Please refer to the Rule 2(1)(n) of the APPR, 2020.
“National It is a bidding process in which qualified bidders within India
Competitive only are allowed to participate
Bidding” (NCB)?
13. What is Please refer to the Rule 2(1)(o) of the APPR, 2020
“Sanction”? “Sanction” means financial sanction and has the same meaning
as in the Assam Financial Rules, 1939, as amended time to time
14. What are Please refer to the Rule 2(1)(s) of the APPR, 2020
“urgent works”? “Urgent works” as distinct from ‘emergency works’, means
works which require immediate commencement for
completion within a very short, compressed time schedule or
which need to be taken up on priority basis in the public interest
to ensure the safety and security of life or prevention of loss of
public assets.
15. What is a “Start- Please refer to the Rule 2(1)(t) of the APPR, 2020
up”?
Page 5 of 48
Sl. Query Response
“Start-up” means any entity recognized as a start-up by the
Government of Assam or the Government of India.
17. What are Please refer to the Section 8(2) of the APPA, 2017 and Rule
“Vendor and 9 of the APPR, 2020
Contractor These are registers or databases related to procurement which
Register”; are required to be maintained by every procurement entity
“Procurement following electronic or physical format as official records and
Register”; ensure their safe custody as per provision of sub-section (2), of
“Purchase Order section 8 of the Act
Guard Register”;
“Stock Register”
; “Asset
Register” and
“Liability
Register”?
23. What is “Code of Please refer to the Section-11 of the APPA, 2017and Rule 20
Integrity”? of APPR, 2020
Page 6 of 48
Sl. Query Response
Rule-12 of inter alia mentions that an unimpeachable standard
of integrity shall be maintained as prescribed under Section 11
of the APPA, Central Civil Services (Conduct) Rules-1964, All
India Services (Conduct) Rules-1968 or the Assam Civil Service
(Conduct) Rules-1965
24. What is ‘Single Please refer to the Rule 14 of the APPR, 2020.
Envelope Bid’? ‘Single Envelope Bid’ is a way of receiving of bids in which the
technical, quality and performance aspects, commercial terms
and conditions and the financial aspects including the price are
contained in a single envelope.
25. What is “Two Please refer to the Rule 14 of the APPR, 2020.
Envelope Bid”? ‘Two Envelope Bid’ is a way of receiving of bids in which the
techno commercial aspects of the bid, that include, the
documents/information relating to the technical, quality, bid
security and commercial terms & conditions are placed in one
envelope (called ‘Technical Bid”) and the financial terms
including price and relevant discounts are placed in another
separate (envelope called “Financial Bid”).
26. What is the Please refer to the Section 14 of the APPA, 2017 and Rule 15
“Criteria of Bid of the APPR, 2020.
Evaluation”? The criteria for bid evaluation shall be detailed by the procuring
entities in the bidding documents based on the provisions in
the aforementioned Section and Rule.
27. When “Price Please refer to the Section 15 of the APPA, 2017 and Rule 16
Negotiations” of the APPR, 2020
are permitted? According to Section-15 of the APPA, 2017, no price negotiation
shall be held by a procuring entity with a bidder with respect to
a bid presented by him except as otherwise provided in Section
31 (2)(b) or Section 35 of the Act or in such circumstances and
subject to such conditions as may be prescribed.
28. What is “Pre- Please refer to the Section 2(s), Section 2(t) and Section-18
Qualification” of the APPA, 2017 and Rule 18 of the APPR, 2020.
and "Pre- Section 2(s) - "pre-qualification" means the procedure set out
Qualification to identify, prior to inviting bids, the bidders that are qualified
Documents"? (to participate in a bidding process); and
29.a What is “Public Please refer to the Section 2(u) of the APPA, 2017.
Procurement”?
Page 8 of 48
Sl. Query Response
Section 2(u) of the Assam Public Procurement Act, 2017 defines
"procurement" or "public procurement" as the acquisition by
purchase, lease, license or otherwise of works, goods or
services, including award of Public Private Partnership
projects, by a procuring entity whether directly or through an
agency with which a contract for procurement services is
entered into, but does not include any acquisition without
consideration, and "procure" or "procured" shall be construed
accordingly.
29.b What is Please refer to the Section 3(2) of the APPA, 2017.
“Procuring “procuring entity” means any - department of the State Govt. or
Entity” its subordinate office; PSU owned/controlled by the State
Govt.; entity whose expenditure is met from the Consolidated
Fund of the State; entity or board or corporation or authority or
society or trust or autonomous entity established or
constituted by an Act of the State Legislature or an entity owned
or controlled by the State Govt.; entity which the State Govt.
may notify to be a procuring entity for the purpose of this Act,
procurement support agency/ agent/consultant involved in
procurement.
30. Who is a Please refer to the Section 2(b) of the APPA, 2017.
‘Bidder’? “Bidder" as any person, company, firm, agency, institution, etc.
participating in a procurement process of a procuring entity for
procurement of Goods, Works or Services.
31. Who is a Please refer to the Section 2(za) and Section 19 of the APPA,
“Registered 2017 and Rule 19 of the APPR, 2020.
Bidder”? Section 2(za): "registered bidder" is a bidder who is on a list of
registered bidders of the procuring entity maintained under
Section 19 of the Act.
Rule 19: Inter alia mentions that The procuring entity may
prepare a registered panel of eligible bidders of good conduct
and the bidders so empanelled shall be listed with the procuring
entity as registered bidders.
Page 9 of 48
Sl. Query Response
32. What are the Please refer to the Section 19(4) of the APPA, 2017 and Rule
“Conditions for 20 of the APPR, 2020.
removal of Section 19(4) inter alia mentions that the State Govt. may
registered prescribe the procedure and conditions in the rules and
bidders from guidelines for removal of registered bidders from list of
list”? registered bidders.
33. What is a ‘Late Please refer to the Rule 23(7) of the APPR, 2020.
Bid’? “Late bids” are those bids which arrive by post or delivered by
hand after the deadline for submission of bids.
34. What is Please refer to the Rule 23(13) (ii)(a) of the APPR, 2020.
“Deviation” in “Deviation” in terms of bidding documents means a departure
terms of bidding (in the bid submitted) from the requirements specified in the
documents? bidding documents
35. What is Please refer to the Rule 23(13) (ii)(b) of the APPR, 2020.
“Reservation” in “Reservation” in terms of bids means putting conditions or
bids? withholding (by the bidder) from complete acceptance of the
terms & conditions and other requirements specified in the
bidding documents.
36. What is Please refer to the Rule 23(13) (ii)(c) of the APPR, 2020.
“Omission” in “omission” is the failure (on the part of the bidder) to submit
terms of bidding part or all of the information or documentation required in the
documents? bidding documents
37. What is “Open Please refer to the Section 29 of the APPA, 2017 and the Rule
Competitive 21(5)(v) and Rule 24(A) of the APPR,2020.
Bidding”? ‘Open Competitive Bidding’ emanate from ‘Transparency’
which is one of the fundamental principles of public
procurement as per Section 4 of the APPA.
Page 10 of 48
Sl. Query Response
Section 29 of the APPA mentions that every procuring entity
shall prefer the open competitive bidding as the most preferred
method of procurement to be followed.
38. What is Please refer to the Section 30(1) and Section 6 of the APPA,
“Limited 2017 and the Rule 21(5)(v) and Rule 24(B) of the APPR,2020.
Bidding”? Limited Bidding is a procedure for obtaining bids only from a
limited number of Bidders.
39. What is “Single Please refer to the Section 31 of the APPA, 2017 and the Rule
Source 24(C) of the APPR, 2020.
Procurement”? Single Source Procurement is a procedure for obtaining bid
only from a single Bidder under conditions specified in Section
31 of the APPA and Rule 24(C) of the APPR, and after recording
the specific reasons and circumstances thereof.
40. What is “Two- Please refer to the Section 32 of the APPA, 2017 and the Rule
Stage Bidding”? 24(D) of the APPR, 2020.
Page 11 of 48
Sl. Query Response
In some instances, as mentioned in the Act and the Rules
procurement entity may opt for two-stage bidding.
In the 2nd stage, only the selected bidders of the first stage are
invited to submit their detailed technical and financial
proposals and after evaluation against a given set of criteria the
most responsive bid is selected.
41. What is an Please refer to the Section 2(h) and 33 of the APPA, 2017 and
“Electronic the Rule 24(E) of the APPR, 2020.
Reverse “Electronic Reverse Auction” is an online real- time purchasing
Auction”? technique to select the successful submission, which involves
presentation by bidders of successively lowered bids during a
scheduled period of time and the automatic evaluation of bids.
42. What is Please refer to the Section 34 of the APPA, 2017 and the Rule
“Request for 24(F) of the APPR, 2020.
Quotations”? “Request for Quotations” is a method of procurement wherein
quotations in sealed envelopes are requested simultaneously
from as many potential bidders as practicable, subject to a
minimum of three, for submission within a given date and time,
provided the potential bidders are genuine, having clear
individual established identity and not a sister concern of one
another. The successful quotation shall be the lowest priced
quotation meeting the needs as set out in the request for
quotations.
Page 12 of 48
Sl. Query Response
for procurement, only if the estimated cost or the value of the
subject matter of procurement is less than Rs.1.0 lakh (Rupees
One lakh) on one occasion, but it shall not exceed Rs.5.0 lakh
(Rupees Five Lakh) in a financial year [Rule 24(F)(i)]
43. What is “Spot Please refer to the Section 34(3) of the APPA, 2017 and the
Purchase”? Rule 24(G) of the APPR, 2020.
44. What are Please refer to the Section 35(A) of the APPA, 2017 and the
“Competitive Rule 24(H) of the APPR, 2020.
Negotiations”? This procurement method may be used when ‘Open
Competitive Bidding’ is not practicable owing to urgency
brought about by unforeseen events or where procurement
involves goods/ materials such as oilseeds, cotton, livestock,
etc. whose prices fluctuate frequently.
Page 13 of 48
Sl. Query Response
The committee then decide the best and final offers received.
Final bids received are not negotiated any further, and are
evaluated to determine lowest or most advantageous bid
conforming to the agreed terms.
45. What is “Rate- Please refer to the Section 2(z) and Section 36(1) of the
Contract”? APPA, 2017 and the Rule 24(I) of the APPR, 2020.
46. What are Please refer to the Rule 24(I)(vi) of the APPR, 2020.
“Parallel Rate Rule 24(I)(vi): If the quantity of the subject matter of
Contracts” ? procurement required is beyond the capacity of the lowest
bidder or the subject matter of procurement is of a critical or
vital nature, rate contracts may be entered with more than one
bidder in the order of their standing in the final evaluation of
bids but at the successful lowest bid rate as parallel rate
contracts.
47. What is Please refer to the Section 28(i) and Section 36(1) of the
Government e- APPA, 2017 and the Rule 24(I)(2) of the APPR, 2020.
Market (GeM)?
Page 14 of 48
Sl. Query Response
Government e-Market Place (GeM) is an electronic and online
procurement process through a portal of the Government of
India.
48. What is Please refer to the Section 2(i) and Section 2(j) and Section
“Framework 36(1) of the APPA, 2017 and the Rule 24(J) of the APPR, 2020.
Agreement Section 2(i)- Framework Agreement Procedure: means a
Procedure” and procedure conducted in two stages: a first stage to select
“Framework supplier(s) / contractor(s) to be a party(ies) to a framework
Agreement”? agreement with a procuring entity, and a 2nd stage to award
contract (call-off contracts) under the framework agreement to
supplier(s) or contractor(s). There is no guarantee of award of
any call-off contracts under the framework agreements.
49. What is the Please refer to the Section 2(zf) and Section 35(B) of the
“Swiss APPA, 2017 and the Rule 24(M) of the APPR, 2020.
Challenge Section 2(zf)- "Swiss Challenge Method (SCM)" means a
Method”? method of Procurement in which an unsolicited proposal for a
government project is received and third party(ies) are allowed
to challenge the original proposal through open bidding, and
then the original proponent is given a chance to counter-match
the most advantageous / most competitive offer.
Rule 24(M)(ii) - Eligible sectors: This method of procurement
may not be adopted below the specified threshold value or for
sectors or sub-sectors that are not notified to be eligible under
SCM Method.
50. What is “Earnest Please refer to the Rule 24(M)(vii) of the APPR, 2020.
Security”? Under the Swiss Challenge Method of Procurement, the project
proponent, shall furnish interest-free Earnest Security
amounting to a percentage of the total estimated cost of the
project, as notified by the Finance Department from time to
time, through bank guarantee from a scheduled bank or any
other acceptable instrument with a validity period of not less
than 180 days commencing from the date of receipt of the
comprehensive proposal by the Administrative Department
including claim period of 60 days. The validity period may be
extended as mutually agreed, from time to time. The bid shall
be summarily rejected if the detailed and comprehensive
proposal is not accompanied with the Earnest Security.
Page 16 of 48
Sl. Query Response
51. Who is a Please refer to the Rule 24(M)(xiii) of the APPR, 2020.
“Transaction The Transaction Advisor is hired for a project under Swiss
Advisor”? Challenge Method for providing technical, financial and legal
advice and assisting the Administrative Department concerned
in the entire process of finalization of the successful bidder and
award of contract. Alternatively, an officer of the Department
may be entrusted with the responsibilities of the Transactional
Advisor.
52. What are Please refer to the Section 2(zb) of APPA, 2017and Rule 25
“Services” or of the APPR, 2020.
“Consulting Section 2(zb)- Services means any subject matter of
Services” and procurement other than goods or works and includes physical,
what is the maintenance, professional, intellectual, consultancy and
procedure for ? advisory services or any service classified or declared as such by
a procuring entity and does not include appointment of any
person made by any procuring entity.
53. What are “Non- Please refer to the Rule 25 of the APPR, 2020.
Consulting Rule 25(1)(b) (Eplaination-1I): Similarly, “Non-Consulting
Services”? Services," means any subject matter of procurement, other than
goods or works except those consequential or incidental to that
service or subject matter, that involve physical, measurable
deliverables or well defined outcomes, where performance
criteria or standards can be clearly identified and consistently
applied.
Page 17 of 48
Sl. Query Response
These services include maintenance, transportation, hiring of
vehicle, outsourcing management of building facilities,
management, security, catering, reprography, photocopier
service, janitor, office errand services, drilling, aerial
photography, video recording, satellite imagery, survey,
mapping, Information Technology related services like website
design, maintenance, etc.
54. What is Please refer to the Section 27(4) of the APPA, 2017 and Rule
“Performance 30 of the APPR, 2020.
Security”? Performance security is a percentage of the contract value that
is deposited with the procuring entity by the successful bidder
as a guarantee to perform and execute the contract as agreed.
The manner of collecting the performance security is decided
by the procuring entity and is specified in the bidding
documents. The performance security is returned to the
contractor/ vendor at the end of the satisfactory completion of
the contract including all contractual obligations related to
warranty, guarantee, defect liability period, operations,
maintenance etc.
55. What are Please refer to the Rule 33 of the APPR, 2020.
“Repeat If an original supply order for a subject matter of procurement
Orders”? was given to a supplier of goods or services after Open
Competitive Bidding, and if so provided for, in the bidding
documents, repeat orders for supply of additional quantities of
that subject matter of procurement may be placed with the
original supplier at the same rates and on the same terms and
conditions as in the original order subject to the following
conditions: -
Page 18 of 48
Sl. Query Response
a) that the procuring entity is satisfied that initiating a new
procurement shall not lead to better competitive prices and
such satisfaction is recorded in writing;
b) the value of the repeat orders shall be limited to such
percentage of the original contract value as may be notified
by the Finance Department from time to time;
c) the repeat orders shall be placed within 6 months of the
expiry of the original contract
56. What is “Quality Please refer to the Rule 25 (1) to 25(6) and Rule 25(7)(a) of
and Cost Based the APPR, 2020.
Selection” QCBS (Quality and Cost Based Selection) is competitive
(QCBS) Method? method procurement for hiring consultancy service, where
both quality and cost of the proposal is taken into consideration
during evaluation of bids and award of contract.
57. What is “Least Please refer to the Rule 25(7)(b) of the APPR, 2020.
Cost System” LCS is a competitive process for selection of consulting services
(LCS)? under which the selection of the successful firm also takes into
account the quality of the Proposal and the cost of the services.
There is no weightage for technical score in the final evaluation
and the responsive technically qualified proposal received with
the lowest price or cost is selected for award.
Page 19 of 48
Sl. Query Response
58. What is “Quality Please refer to the Rule 25(7)(c) of the APPR, 2020.
Based Selection” QBS (Quality Based Selection) is also a competitive process for
(QBS) Method? selection of consulting services under which the Proposal
quality is evaluated without using cost as an evaluation
criterion. The financial proposal of only the highest technically
qualified firm is evaluated and negotiated, and is considered for
award.
59. What is “Fixed Please refer to the Rule 25(7)(d) of the APPR, 2020.
Budget System” Fixed Budget System (FBS) is a competitive process under
(FBS)? which the selection of the successful firm takes into account the
quality of the Proposal and the cost of the services. FBS is
appropriate only when the assignment is simple and
unambiguous, where the TOR can be precisely defined, and
where the budget or fund available for the purpose is fixed and
shall not be exceeded. The RFP specifies the available budget
and the minimum score for the technical Proposals. The
proposal with the highest technical score that meets the fixed
budget requirements is considered for award.
60. What is Please refer to the Rule 25(7)(e) of the APPR, 2020.
Consultants’
Page 20 of 48
Sl. Query Response
Qualifications Consultants’ Qualifications Selection (CQS) is appropriate only
Selection (CQS)? for small assignments when highly specialized expertise is
required or consulting firms with depth of expertise in specific
areas or when recruitment time is critical and the small
assignment is short-term, and when preparing and evaluating
competitive proposals is unjustified.
61. What is Single Please refer to the Section 31 of APPA, 2017 and Rule 24(C)
Source Selection and Rule 25(7)(f) of the APPR, 2020.
(SSS)? Under Single Source Selection (SSS) a bid is solicited from a
single prospective bidder and contract is awarded following
negotiation as needed adhering to the Rule 16.
Page 21 of 48
Sl. Query Response
of procurement, such that no reasonable alternative or
substitute source exists, and the use of any other
procurement method would therefore not be possible; or
b) there is an extremely urgent need for the subject matter of
procurement, and engaging in any other method of
procurement would be impractical; or
c) the procuring entity, having procured goods, equipment,
technology or services from a supplier, determines that
additional supplies or services must be procured from that
supplier for reasons of standardization or because of the
need for compatibility with existing goods, equipment,
technology or services; or
d) there is an existing contract for the subject matter of
procurement which can be extended for additional goods,
works or services and that the procuring entity is satisfied
that no advantage would be obtained by further
competition, the prices are reasonable and provisions for
such extension exist in the original contract; or
e) the procuring entity determines that the use of any other
method of procurement is not appropriate for the protection
of national security interests; or
f) procurement from a particular prospective bidder is
necessary in terms of sub-section (2) of section 6 of the Act
(relating to Procurement Preference Policy, Assam,); or
g) subject matter is of artistic nature; or
h) subject matter of procurement is of such nature as requires
the procuring entity to maintain confidentiality, like
printing of examination papers;
62. What is “Bid Please refer to the Rule 21(c) of the APPR, 2020 and the
Data Sheet”? Standard Bidding Documents (SBD) issued by the Finance
Department under Rule 21(5).
Page 22 of 48
Sl. Query Response
provides specific data and modifications that complement,
supplement, or amend the corresponding clauses in the ITB in
the standard bidding documents keeping it relevant to the
specific procurement. Whenever there is a conflict, provisions
in the BDS prevail over those in ITB.
63. What are Please refer to the Rule 21(e) of the APPR, 2020 and the
“Bidding Standard Bidding Documents (SBD) issued by the Finance
Forms”? Department under Rule 21(5).
64. What is a “Rate- Please refer to the Section 28(l) and Rule 24(L) of the APPR,
Bank”? 2020
65. What is Please refer to the Rule 3(3) of the APPR, 2020
“Detailed
Page 23 of 48
Sl. Query Response
Project Report” Detailed Project Reports (DPRs) are the outputs of planning
(DPR)? and design phase of a project. DPR is a very detailed and
elaborate plan for a project indicating overall programme,
different roles and responsibilities, activities, possible risks and
recommended measures to mitigate them and resources
required for the project and also its operation/maintenance of
the project after completion.
66. What is Terms Please refer to the Rule 25(3)(d) of the APPR, 2020
of Reference The “Terms of Reference (TOR)”, defines the assignment,
(ToR)? objectives, scope, outputs, and outcomes of the consultancy
services and provides necessary background information. TOR
shall be carefully framed in precise terms by the procuring
entity and it should allow prospective consultants to propose
their own methodology and work schedule. The TOR shall,
inter alia, include - (i) objectives of the assignment; (ii)
background of the project and relevant information; (iii) Scope
of the services to be provided; (iv) Tasks to be carried out and
completion schedule; (v) output to be delivered and/or
outcome; (vi) support and inputs to be made available by the
procurement entity; (vii) Time-frame for completion of the
assignment; and (viii) Requirements of Key Experts.
66.a What is Request Please refer to the Rule 25(3)(e) of the APPR, 2020
for Proposals The Request for Proposals (RFP) for a specific consulting
(RFP) services assignment provides all the information necessary for
document? the short-listed consultants to prepare their proposals. It
identifies the evaluation criteria, selection method, and
procedures that will be used to evaluate them. The RFP also
contains the Terms of Reference (TOR) and the draft contract
for the assignment
67. What is the need Please refer to the Preamble of the APPA, 2017, which
to establish the mentions that it is expedient to establish legal foundations for
legal procedures for procurement by public entities so as to ensure –
foundations of
Page 24 of 48
Sl. Query Response
public i. timely delivery of its intended outcomes with efficiency,
procurement? economy, professionalism and public accountability
from its officers and staff;
ii. the highest standards of transparency, fairness, equality
towards Its bidders;
iii. support to policies of the State on soda/, economic and
environmental issues; and
iv. assurance to public and other stakeholders regarding
probity and integrity of the process.
68. What is e- Please refer to the Section 2(g) and Section 28(2) of APPA,
procurement? 2017 and related provisions in the APPR, 2020
69. What is the Please refer to the Section 2(x) and Section 3(2) of the APPA,
meaning of 2017
“Procuring According to Section 3(2) of the APPA, "procuring entity,
Entity”? means
Page 25 of 48
Sl. Query Response
70. What is Please refer to the Section 2(o) of the APPA, 2017
“Goods”? "Goods" includes all articles, material, commodities, electricity,
livestock, furniture, fixtures, raw material, spares, instruments,
software, machinery, equipment, industrial plant, vehicles,
aircraft, ships, railway rolling stock and any other category of
goods, whether in solid, liquid or gaseous form, purchased or
otherwise acquired for the use of a procuring entity as well as
services or works incidental to the supply of the goods if the
value of services or works or both does not exceed that of the
goods themselves
71. What is Please refer to the Section 2(zd) of the APPA, 2017
“Works”? “Works” means all works associated with the construction,
reconstruction, site preparation, demolition, repair,
maintenance, or renovation or railways roads, highways or a
building, an infrastructure or structure or an installation or any
construction work relating to excavation, drilling, installation
of equipment, and materials, as well as services or goods
incidental or consequential to the works if the value of those
services or goods does not exceed that of the works themselves.
72. What is the Please refer to the Section 2(zc) of the APPA, 2017
“Subject Matter "Subject Matter of Procurement" means any item of
of procurement whether in the form of goods, services or works
Procurement”?
73. Who is a Please refer to the Section 2(b) of the APPA, 2017
“Bidder”? "Bidder" means any person, company, firm, agency, institution,
etc. participating in a procurement process of a procuring entity
for procurement of Goods, Works or Services
74. What is Please refer to the Section 5(4) of the APPA, 2017 and Rule
“Procurement 4 of the APPR, 2020
Plan”? A “Procurement Plan” is a document prepared by procurement
entities and to be submitted along with their annual budget
plan. The procurement plan shall detail information regarding
their procurement requirements for the financial year and shall
Page 26 of 48
Sl. Query Response
contain at the least a brief description of the goods, works or
services for which procurement action is to take place;
proposed methods of procurement; any provision of price or
purchase preference as per the APPA; time schedule for key
procurement activities and any other relevant information
pertaining to the procuring entity’s plan for procurement in the
respective financial year.
75. What is a “Joint Please refer to the Rule 5(3) of the APPR, 2020
Venture”? A Joint Venture (JV) is a business arrangement in which two or
more parties agree to pool their resources, and having formal
intent and legal competency to enter into an agreement or
contract, can either be incorporated or unincorporated.
Page 27 of 48
Sl. Query Response
legally authorized signatories of all the partners or,
otherwise, all the parties in JV shall sign the Agreement.
76. What is a A consortium is not a merger and each participant carries on its
consortium? normal business operation without any interference and
How is it remains independent. A joint venture is an association of two or
different from a more parties and can be incorporated or unincorporated. Unless
Joint-Venture? otherwise stated in the bidding documents, all partners of the
consortium, similar to the case of joint venture, shall be jointly
and severally liable for the bid and for the execution of the
Contract in accordance with the terms of the contract.
77. What is a “Lead Please refer to the Rule 5(3)(d) of the APPR, 2020
Partner” in a In case of Bid from a Joint Venture (JV), the JV shall nominate
Joint Venture? a “Lead Partner”, who shall have the authority to conduct all
business for and on behalf of any or all the parties of the JV
during the bidding process and during execution of the
contract. This authorization shall be evidenced by submitting a
power of attorney signed by the legally authorized signatories
of all the partners or, otherwise, all the parties in JV shall sign
the Agreement
78. What is the Please refer to the Section 6(5) and Section 7 of the APPA,
“Qualification of 2017 and Rule 7 of the APPR, 2020
Bidders”? Section 6(5) inter alia mentions that - procuring entity may lay
down reasonable Eligibility Conditions for participation in the
procurement process, as distinct from and in addition to any
technical or financial qualification criteria.
Page 28 of 48
Sl. Query Response
prequalification documents or bidder registration documents;
(b) fulfil any other qualifications as may be prescribed
79 What are the Please refer to the Section 10 of the APPA, 2017 and Rule 11
documentary of the APPR, 2020
records of All procuring entities shall maintain and preserve in safe
procurement to custody, the documentary record of procurement proceedings
be and of communications as per provision of the Section 10 of the
maintained/kept Act and Rule 11 of the APPR
ready by
procuring entity
as per Assam
Record Rules?
80. How Please refer to the Section 19 of the APPA, 2020 and Rule -
Registration of 19 of APPR, 2020.
bidders is done
as per APPA and
the APPR?
81. What are the Please refer to the Section 20 of the APPA, 2020 and Rule -
Minimum 21 of APPR, 2020.
Required
Documents to be
included in the
bidding
document?
82. What is SBD Please refer to the Section 20(4) of the APPA, 2020 and Rule
(“Standard -21(5) of APPR, 2020.
Bidding SBDs as model bidding documents have been notified by the
Documents”)? Government for procurement of works, goods and services.
Page 29 of 48
Sl. Query Response
83. What is Pre-bid Please refer to the Section 22(4) of the APPA, 2020 and Rule
conference/ -22 of APPR, 2020.
Meeting? Why Section 22(4) of the APPA mentions that procuring entity may
do we need it? hold a pre-bid conference to clarify doubts of potential bidders
in respect of a particular procurement and the records of such
conference shall be intimated to all bidders and where
applicable, shall be published on the State Public Procurement
Portal.
84. What may be the Please refer to the Rule -23(1) of APPR, 2020.
“various As per the Rule, every procuring entity shall constitute and
committees” notify one or more Committees for the following purposes,
notified by a namely: -
Procuring
a) Preparation of bidding documents;
entity?
b) Opening of bids;
c) Evaluation of technical and financial bids;
d) Monitoring of contract;
e) Spot Purchase;
f) Purchase Committee for Competitive negotiations;
g) Any other purpose relating to procurement like preparation
or evaluation of Detailed Project Report, etc. as may be
decided by the procuring entity:
Page 30 of 48
Sl. Query Response
85. What are the Please refer to the Rule -23(7) of APPR, 2020.
steps to be dealt Any bid that is submitted personally by hand after the time and
with “late bids”? date fixed for submission of bids under any circumstances. Any
bid which arrives by post after the deadline for submission of
bids shall be declared and marked as “Late” and returned
unopened to the bidder if the bidder so requests. In case of e-
procurement, the system shall not allow any bids to be
uploaded after the deadline for submission of bids
86. What is the Please refer to the Rule -23(9) of APPR, 2020.
“Procedure for Bids shall be opened as per the procedure mentioned in the
Opening of Rule by the Bid Opening Committee constituted by the
bids”? procuring entity at the time, date and place specified in the
bidding documents in the presence of the bidders or their
authorised representatives who choose to be present, enabling
them to watch the proceedings.
87. What will a Please refer to the Rule -23(20) of APPR, 2020.
procuring entity Rule 23(20(i) – If after evaluation of bids, the Bid Evaluation
do if after Committee ends up with only one responsive bid, the
evaluation of Committee shall check as to whether while floating the Notice
bids only one Inviting Bids all necessary requirements to encourage
responsive bid is competition, like, standard bidding terms and conditions,
received? industry-friendly specifications, wide publicity, sufficient time
for formulation of bids, etc. are fulfilled. If not, the Committee
shall recommend cancellation of the bid process and issue of
fresh Invitation for Bids after rectifying the deficiencies and the
procurement entity shall act accordingly.
Page 31 of 48
Sl. Query Response
by the concerned procuring entity, detailing the process
undertaken, the bid process shall be considered valid even if
there is one responsive bid, provided that: -
88. What a The procuring entity shall explore the likely reasons for lack of
procuring entity suitable bids, may go for a market survey, hold dialogue with
will do if after potential suppliers and based on the feedback, as relevant,
three revisit the specified eligibility and techno-commercial
consecutive provisions, specifications, delivery schedules, guarantee/
invitations for warranty etc. given in the bidding document to ensure that such
quotations, no requirements are not unduly restrictive, and are in line with
suitable bid is market availability. The bidding documents may be
received? appropriately revised before requesting fresh Bids.
Page 32 of 48
Sl. Query Response
Department responsible for the sector of such proprietary shall
lay down the schedule of powers for signing such certificate.
90. What is the Please refer to the Rule 24(c)(vii) of APPR, 2020.
“Role of District Rule 24(C)(vii)- In emergent situations arising in a district of
Emergency the State out of floods and other calamities, natural or
Procurement otherwise, or urgency for upholding human rights, the relevant
Committee”? subject matter may be procured from a single source at or below
the ceiling rates to be fixed by a District Emergency
Procurement Committee (DEPC), comprising the following
officials:
The Role of the DEPC is to decide the ceiling rates for the
subject matter of procurement on the basis of analysis of the
wholesale market or authorised dealer rates of that subject
matter prevailing during the previous six months.
91. Upto what Please refer to the Rule 24(F)(i) of APPR, 2020.
value/ amount Request for Procurement method may be adopted by a
RFQ can be Procurement Entity if the estimated cost or the value of the
sought? subject matter of procurement is less Rupees One lakh (Rs.1
lakh) on one occasion, but it shall not exceed Rupees Five Lakh
(Rs. 5 lakh) in a financial year. However, the Finance
Department may, by notification, raise or lower the monetary
ceiling values prescribed.
92. What is Please refer to the Section 28(k) of the APPA, 2017 and Rule
procurement 24(K) of APPR, 2020.
from “e- Section 28(k)- a procuring entity may procure a subject matter
commerce”? of procurement inter alia by means of any of the e-commerce
method.
Page 33 of 48
Sl. Query Response
Rule 24(K)- Procuring entities may choose to procure its
essential common use needs through e-commerce websites in
case the subject matter of procurement is not available on GeM,
subject to the provisions as given in the Rules.
93. What is the Please refer to the Rule 24(G)(ii) of APPR, 2020.
“Role of Spot The Role of Spot Purchase Committee is to survey the market
Purchase diligently to ascertain the specifications, quality and
Committee”? reasonableness of rate with reference to the wholesale market
price, identify the appropriate supplier of the subject matter
thereof and record the certificate prescribed in the Rule and
signed by all the members. Departmental Stores, Shopping
Malls, Authorised Dealers may be included in the market
survey and reputed internet shopping portals may also be
explored.
94. What is Please refer to the Section 28(l) of the APPA, 2017 and Rule
Community 24(L) of APPR, 2020.
Procurement? The community procurement method shall be adopted for
community driven schemes for procurement of inputs like,
equipment, machinery etc., in community driven schemes
where each beneficiary of such scheme, whether individual or
group or community, is required to bear a part of the cost of
such input by way of bank loan or otherwise as “beneficiary
share.”
95. What is State Please refer to the Rule 24(M)(i) and 24(M)(iv) of APPR,
level 2020.
Empowered State Level Empowered Committee or SLEC is a body, chaired
Committee? by the Chief Secretary, that shall be constituted by the State
Page 34 of 48
Sl. Query Response
Government under the APPR as a Competent Authority for the
purpose of Swiss Challenge Method of Procurement.
98. What is Please refer to the Rule 23(11) and Rule 23(16) [for goods,
“Technical works and NCS] and 25(5) [for consultancy] of APPR, 2020.
Evaluation”? a) For goods, works and non-consulting services (NCS):
Technical evaluation is to assess the responsiveness,
technical capability including experience, personnel,
compliance with specifications, deviations, qualification
criteria etc. to meet the technical requirements and to
execute the contract, if awarded.
Page 35 of 48
Sl. Query Response
experience of the firm, transfer of knowledge). The
Committee shall record in detail the reasons for acceptance
or rejection of the technical proposals analysed and
evaluated by it and prepare a list of the bids that have been
qualified and accepted technically.
99. What is financial Please refer to the Rule 23(12) and Rule 23(17) [for goods,
evaluation? works and NCS] and 25(6) [for consultancy] of APPR, 2020.
100. What is the Please refer to the Section 2(d) of the APPA, 2017.
meaning of “Bidding Documents” means documents for procurement of
bidding Goods, Works or Services issued by the procuring entity,
documents? including any amendments thereto, that set out the terms and
conditions of the given procurement and includes the invitation
to bid; The term "bidding document" also includes the "Request
for Proposal" and "Request for Quotation" documents used for
hiring consultancy and non-consultancy services.
101. What is the Please refer to the Section 13(1)(i) of the APPA, 2017.
meaning of The term 'techno-commercial bid' denotes the bid containing
techno- the technical, quality and performance aspects, commercial
commercial bid? terms and conditions and all other details and documents in the
bid, except the price and relevant financial details.
102. What is EPC Please refer to the Section 18(1)(c) of the APPA, 2017.
contracts?
Page 36 of 48
Sl. Query Response
Engineering, procurement, and construction (EPC) contracts
are a form of contract where the Contractor carries out detailed
engineering design, procures all equipment and materials, and
under takes the construction. The procuring entity provides
basic engineering to the contractor and the latter performs
detailed design based on the received basic design.
103. What is turnkey Please refer to the Section 18(1)(c) of the APPA, 2017.
contracts? The term EPC is used as synonymous with “turnkey” mode.
104. What is the Please refer to the Section 11(3)(f) and Section 46 of the
meaning of APPA, 2017 and Rule 20(d).
debarment, and A bidder shall be debarred by the State Government if he has
what are the been convicted of an offence -
conditions for
a) under the Prevention of Corruption Act, 1988; or
debarment?
b) under the Indian Penal Code, 1860 or any other law for the
time being in force, for causing any loss of life or property
or causing a threat to public health as part of execution of a
public procurement contract
105. What are Please refer to the Section 11(3)(f) and Section 46(4) of the
timelines for APPA, 2017.
such If a procuring entity finds that a bidder has breached the code
debarment? of integrity prescribed in terms of section 11, it may debar the
bidder for a period not exceeding three (3) years
Page 37 of 48
Sl. Query Response
106. What is Please refer to the Rule 21(b) of the APPR, 2020.
Instructions to a) Instructions to Bidders (ITB) is a Section of bidding
Bidders? documents issued by the procurement entity for
procurement of goods, works and non-consulting
services. This Section provides relevant information as
well as instructions to assist prospective bidders in
preparation and submission of bids. It also includes the
mode and procedure to be adopted by the Employer for
receipt and opening as well as scrutiny and evaluation of
bids and subsequent award of contract.
107. What are Please refer to the Rule 21(f) of the APPR, 2020.
General General Conditions of Contracts (GCC) are set of defined terms
Conditions of and conditions of the contract in the bidding documents/RFP
Contract and issued for subject matter of procurement. These conditions
Special shall not be altered while customizing the standard bidding
Conditions of document issued by the Finance Department. However, the
Contract? respective clauses of GCC should be supplemented and or
amended in the Special Conditions of Contract (SCC). In such
case, clauses contained in GCC and related SCC shall be read
together. Whenever there is a conflict between information
contained in GCC and SCC, the clauses contained in SCC shall
prevail.
108. What does the Please refer to the Section 50 of the APPA, 2017 and the Rule
State 32 of the APPR, 2020.
Procurement The functions of the State Procurement Facilitation Cell may be
Facilitation Cell seen in the Section 50 of the APPA, 2017 and the Rule 32 of the
do? APPR, 2020
Page 38 of 48
Sl. Query Response
The main functions of the SPFC is given below:
Page 39 of 48
Sl. Query Response
109. What is the State Please refer to the Section 17 of the APPA, 2017 and the Rule
Public 17 of the APPR, 2020.
Procurement State Public Procurement Portal is an online platform to be set
Portal (SPPP)? up and maintain by the State Government accessible to the
public for posting matters relating to public procurement
110. Why do we need Please refer to the Section 17 of the APPA, 2017 and the Rule
the SPPP, when 17 of the APPR, 2020.
we have the e- The State Public Procurement Portal shall contain the specified
procurement information relating to the APPA, APPR, SBDs and other
portal? Notifications issued by the State Government for both manual
and e-procurement also the State Public Procurement
Statistics. A link is also provided for the e-procurement portal
from the SPPP, for carrying out the online process of electronic
Page 40 of 48
Sl. Query Response
tendering using the internet and associated technologies, and
contains very detailed information but related to e-mode only.
111. What is the Please refer to the Section 24 of the APPA, 2017 and the Rule
difference 23(1), Rule 23(9) and Rule 23(10 to 20) of the APPR, 2020.
between the Bid Bid Opening Committee (may have a minimum of two
Opening members) is responsible for opening of bids received prior to
Committee and the bid submission deadline, in presence of the bidders or their
the Bid authorised representatives, and preparing record of the
Evaluation proceedings of bid opening, signed by all members of the
Committee? committee, and also sign each bid that has been opened.
112. What is Digital Please refer to the Rule 23(2)(vii) of the APPR, 2020.
Signature Digital Signature Certificates (DSC) is a tool used for
Certificate electronically sign documents and is equivalent of physical
(DSC)? signature and fully legally valid. It can be presented
electronically to prove signatory’s identity. DSC is also used for
e-procurement portal for submission of bids.
113. What is Please refer to the Section 32(2)(f), Section 42(2) of the
withdrawal of APPA, 2017 and the Rule 20(1)(e), Rule 23(4)(ii), Rule 23(8),
bids? and Rule 23(9)(v) of the APPR, 2020.
Page 41 of 48
Sl. Query Response
A bidder may withdraw its bid by sending a written notice, duly
signed by the bidder or his authorised representative in writing,
before the deadline for bid submission. Bids requested to be
withdrawn are returned unopened to the bidders. No bid shall
be withdrawn after the time and date fixed for receipt of bids.
In cases of e-procurement, bidders may withdraw their bid
online as per the norms applicable for the e-procurement
portal.
114. What is Please refer to the Rule 23(8), of the APPR, 2020.
substitution of A bidder may substitute its bid by sending a written notice, duly
bids? signed by the bidder or his authorised representative in writing,
before the deadline for bid submission. No bid shall be
substituted after the time and date fixed for receipt of bids. In
cases of e-procurement bidders may substitute their bid online
as per the norms applicable for the e-procurement portal.
115. What is Please refer to the Rule 23(8), of the APPR, 2020.
modification of A bidder may modify its bid by sending a written notice, duly
bids? signed by the bidder or his authorised representative in writing,
before the deadline for bid submission. No bid shall be
modified after the time and date fixed for receipt of bids. In
cases of e-procurement bidders may modify their bid online as
per the norms applicable for the e-procurement portal
116. What is Bill of The Bill of Quantities (BoQ) is part of the Bidding Document,
Quantities which is prepared based on the detailed estimated cost. BoQ
(BoQ)? provide information on the quantities of Works to be
performed and it enable bidders to prepare and quote rates for
each item of the BoQ and to calculate the quote total Bid Price.
During contract execution, BoQ is inter alia used for accessing
the progress of works against individual items and record
measurements in MBs, and payment to contractors based the
rates quoted for BoQ items.
117. What is the Please refer to the Rule 23(13), of the APPR, 2020.
difference
Page 42 of 48
Sl. Query Response
between A bid shall be deemed to be responsive if it meets the
responsive bid requirements of the bidding documents without any material
and deviation, reservation, or omission where: -
unresponsive or a) “deviation” is a departure from the requirements specified
non-responsive in the bidding documents;
bid?
b) “reservation” is the setting of limiting conditions or
withholding from complete acceptance of the requirements
specified in the bidding documents; and
118. What is Please refer to the Rule 23(15) of the APPR, 2020.
immaterial non- Immaterial non-conformities in bids are non-
conformities in conformities that do not constitute a material deviation,
bids? reservation or omission and deem the bid to be responsive. The
Bid Evaluation Committee may request the bidder to submit
necessary information or documents which are historical in
nature, and may rectify immaterial non-conformities or
omissions on the basis of the information or documentation
received from the bidder.
Page 43 of 48
Sl. Query Response
119. What is PAG? PAG stands for Permanent Advisory Group. Please refer to
the OM (FEB.366/2016/Pt/53 dated.12th November, 2021)
120. What is the a) Company: According to the Indian Companies Act 2013,
difference a company is defined as an association that can be formed
between a by natural persons, legal entities, or a mixture between the
company, a
Page 44 of 48
Sl. Query Response
firm, a two, and the main purpose of the company is to develop
partnership firm commercial activities.
and an agency? b) Firm: A firm is a commercial enterprise, a company that
buys and sells products and/or services to consumers with
the aim of making a profit. A business entity such as a
corporation, limited liability company, public limited
company, sole proprietorship, or partnership that has
products or services for sale is a firm.
c) Partnership firm: A partnership is a relationship between
individuals who have agreed to share the profits of a
business carried on by all or any one of them acting for all
as stated in the Indian Partnership Act. Therefore, a
partnership consists of three essential elements.
i. A partnership must be a result of an agreement
between two or more individuals.
ii. The agreement must be built to share the profits
obtained from the business.
iii. The business must be run by all or any of them
representing the rest
121. What is the Please refer to the Rule 3(2) and Rule 25(3)(a) of the APPR,
Scope of Work? 2020.
122. What is the Please refer to the Section 6(5) and Section 7 of the APPA,
Eligibility 2017 Rule 5 and Rule 7 of the APPR, 2020.
Criteria and Eligibility criteria is the set of Eligibility Conditions laid
down for participation in the procurement process, as distinct
Page 45 of 48
Sl. Query Response
Qualification from and in addition to any technical or financial qualification
Criteria? criteria to ensure compliance with Transparency and Code of
Integrity. Section 6(5)(a)- Eligibility Conditions for
participation in the procurement process, as distinct from and
in addition to any technical or financial qualification criteria,
is to ensure compliance with the Transparency and Code of
Integrity. The Rule 5 of APPR mentions about general
Eligibility Conditions, such as e.g. bidder shall not have been
debarred or have a conflict of interest, etc.
123. What is Contract Please refer to the Section 2(v) of the APPA, 2017.
Management? "Procurement Contract" means a contract entered into between
the procuring entity and a successful bidder concerning the
subject matter of procurement.
124. What is appeal Please refer to the Section 38 to Section 40 of the APPA,
in procurement? 2017 and Rule 26, Rule 27 and Rule 28 of APPR, 2020.
Who can file an If any bidder or prospective bidder is aggrieved that any
appeal? decision, action or omission of the procuring entity is
contravention to the provision of the Assam Public
Page 46 of 48
Sl. Query Response
Procurement Act and Rules or any guidelines issued there
under, he may file an appeal to such officer of the procuring
entity as may be designated by it for the purpose within the
specified period, giving the specific ground(s) on which he feels
aggrieved.
125. What is the Please refer to the Rule 23(16) and Rule 25(5) of the APPR,
meaning of 2020,
‘technically Technically qualified bidders are the bidders who meet the
qualified eligibility criteria and are substantially responsive to the
bidders’? technical and commercial qualifying criteria specified in the
bidding documents.
126. Can we extend Please refer to the Section 23(2) and Rule 23(5) of the APPR,
the bid 2020,
submission Yes, the bid submission deadline may be extended by the
deadline if so procurement entity in exceptional circumstances like-
requested by a
i. sufficient number of bids have not been received and the
bidder?
procuring entity is of the opinion that further bids are
likely to be submitted if time is extended; or
ii. the bidding documents are required to be substantially
modified, and the time remaining for preparation of bids
appears to be insufficient
127. Minimum Please refer to the Section 23(1)(ii) of APPA, 2017 and Rule
number of bid 23(5) of the APPR, 2020
evaluation The bid evaluation committee shall have minimum three (3)
committee members.
member?
Page 47 of 48
Sl. Query Response
128. What is No limits. The decision should be need based.
minimum and
maximum time
limit for
extension of Bid
submission
date?
Page 48 of 48