University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
2.5- Variable Load on Power Station
• The function of a power station is to deliver power to a large number of
consumers.
• However, the power demands of different consumers vary in accordance
with their activities.
• The result of this variation in demand is that load on a power station is
never constant, rather it varies from time to time.
• The load on a power station varies from time to time due to uncertain
demands of the consumers is known as variable load on the station.
2.5.1- Load Curve:
• The curve showing the variation of load on the power station with
respect to time is known as a load curve.
• Daily load curve: It shows the variations of load with respect to time
during the day (i.e., 24 hours) as shown in figure 2.3.
Fig. 2.3: daily load curve of a power station.
1|Page Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
• The area under the daily load curve gives the number of units generated
in the day.
Units generated/day = Area (in kWh) under daily load curve
• The highest point on the daily load curve represents the maximum
demand on the station on that day (It is clear that from fig. 2.3, being
maximum at 6 P.M. in this case).
• The area under the daily load curve divided by the total number of hours
gives the average load on the station in the day.
• Monthly load curve: It can be obtained from the daily load curves of
that month (average values of power over a month at different times of
the day are calculated and then plotted on the graph).
• Yearly load curve: It can be obtained by considering the monthly load
curves of that particular year.
• The yearly load curve is generally used to determine the annual load
factor.
2|Page Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
2.5.2- Load Duration Curve:
• When the load elements of a load curve are arranged in the order of
descending magnitudes, the curve thus obtained is called a load duration
curve as shown in figure 2.4.
Fig. 2.4: load duration curve
• The load duration curve is obtained from the same data as the load curve
but the ordinates are arranged in the order of descending magnitudes.
• In other words, the maximum load is represented to the left and
decreasing loads are represented to the right in the descending order.
• Hence the area under the load duration curve and the area under the
load curve are equal. For example, 20 MW for 8 hours; 15 MW for 4
hours and 5 MW for 12 hours.
3|Page Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
2.5.3- Base Load and Peak Load:
• The changing load on the power station makes its load curve of variable
nature.
• However, the load curve on a power station can be considered in two
parts, namely;
• Base load: The unvarying load which occurs almost the whole day on the
station is known as base load as shown in figure 2.5.
Fig. 2.5 beak and base loads
• It is clear that 20 MW of load has to be supplied by the station at all
times of day and night i.e. throughout 24 hours.
• Peak load: The various peak demands of load over and above the base
load of the station is known as peak load.
• It is clear that there are two peak demands of load in figure 10 excluding
base load.
4|Page Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
• These peak demands of the station generally form a small part of the
total load.
2.5.4- Types of Loads:
• The load may be resistive (e.g., electric lamp), inductive (e.g., induction
motor), capacitive or some combination of them.
• The various types of loads on the power system are:
1- Residential Load:
• Consists of lights, fans, refrigerators, heaters, television, small
motors for pumping water etc.
• Most of the residential load occurs only for some hours during
the day (i.e., 24 hours) e.g., lighting load occurs during night time
and load occurs for few hours.
• For this reason, the load factor is low (10% to 12%).
2- Commercial load:
• It consists of lighting for shops, fans and electric equipment’s
used in restaurants etc.
• This class of load occurs for more hours during the day as
compared to the residential load.
• The commercial load has seasonal variations due to the
extensive use of air-conditioners and space heaters.
5|Page Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
3- Industrial load:
• The magnitude of industrial load depends upon the type of
industry.
• Thus, small scale industry requires load up to 25 kW, medium
scale industry between 25kW and 100 kW and large-scale
industry requires load above 500 kW.
2.5.5-Important Terms and Factors:
1- Connected load:
It is the sum of continuous ratings of all the equipments connected to
supply system.
• A power station supplies load to thousands of consumers.
• Each consumer has certain equipment installed in his building.
• The sum of the continuous ratings of all the equipments in the
consumer’s building is the “connected load” of the consumer.
• For instance, if a consumer has connections of five 100-watt lamps
and a power point of 500 watts, then connected load of the
consumer is 5 × 100 + 500 = 1000 watts.
• The sum of the connected loads of all the consumers is the
connected load to the power station.
6|Page Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
2- Maximum demand:
It is the greatest demand of load on the power station during a given
period.
• The load on the power station varies from time to time.
• The maximum of all the demands that have occurred during a given
period (say a day) is the maximum demand.
• Referring back to the load curve of Fig. 2.3, the maximum demand
on the power station during the day is 6 MW and it occurs at 6 P.M.
• Maximum demand is generally less than the connected load because
all the consumers do not switch on their connected load to the
system at a time.
• The knowledge of maximum demand is very important as it helps in
determining the installed capacity of the station.
• The station must be capable of meeting the maximum demand.
7|Page Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
3- Demand factor:
It is the ratio of maximum demand on the power station to its connected
load i.e.,
• The value of demand factor is usually less than 1.
• It is expected because maximum demand on the power station is
less than the connected load.
• If the maximum demand on the power station is 80 MW and the
connected load is 100 MW, then demand factor = 80/100 = 0·8.
• The knowledge of demand factor is vital in determining the
capacity of the plant equipment
4- Average load (Average demand):
The average of loads occurring on the power station in a given period (day
or month or year).
8|Page Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
5- Load factor:
The ratio of average load to the maximum demand during a given period
i.e.,
• The load factor may be daily load factor, monthly load factor or
annual load factor if the time period considered is a day or month
or year.
• Load factor is always less than 1 because average load is smaller
than the maximum demand.
• The load factor plays key role in determining the overall cost
• per unit generated.
• Higher the load factor of the power station, lesser will be the cost
per unit generated.
9|Page Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
Example 2.1:
A generating station has a connected load of 43MW and a maximum demand
of 20 MW; the units generated being 61·5 × 106 per annum. Calculate (i) the
demand factor and (ii) load factor.
6- Diversity factor:
The ratio of the sum of individual maximum demands to the maximum
demand on power station, i.e.,
• A power station supplies load to various types of consumers whose
maximum demands generally do not occur at the same time.
• Therefore, the maximum demand on the power station is always
less than the sum of individual maximum demands of the consumers.
• Obviously, diversity† factor will always be greater than 1.
10 | P a g e Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
• The greater the diversity factor, the lesser is the cost of
generation of power.
7- Plant capacity factor:
It is the ratio of actual energy produced to the maximum possible energy
that could have been produced during a given period i.e.,
• Thus, if the considered period is one year,
• The plant capacity factor is an indication of the reserve capacity
of the plant.
• A power station is so designed that it has some reserve capacity
for meeting the increased load demand in future.
• Therefore, the installed capacity of the plant is always somewhat
greater than the maximum demand on the plant.
11 | P a g e Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
8- Plant use factor:
It is ratio of kWh generated to the product of plant capacity and the
number of hours for which the plant was in operation i.e.
• Suppose a plant having installed capacity of 20 MW produces annual
output of 7·35 × 106 kWh and remains in operation for 2190 hours
in a year. Then,
Example 2.2:
A generating station has a maximum demand of 25MW, a load factor of
60%, a plant capacity factor of 50% and a plant use factor of 72%. Find
(i) the reserve capacity of the plant (ii) the daily energy produced and (iii)
maximum energy that could be produced daily if the plant while running as
per schedule, were fully loaded.
12 | P a g e Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
Example 2.3:
13 | P a g e Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
14 | P a g e Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
15 | P a g e Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
Example 2.4:
16 | P a g e Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
17 | P a g e Dr. Mushtaq Najeeb
University of Anbar Electric Power I/1st Sem.
College of Engineering Third Class
Dept. of Electrical Engineering 2022-2023
18 | P a g e Dr. Mushtaq Najeeb