Lesson 7 Road Construction Methods
Lesson 7 Road Construction Methods
METHODS
Earth Road - It is the “simplest form of road”
Road - is a structure that link barangays and cities in constructed by shaping and smoothing the natural soil
the country. It serves as medium in transporting goods traversed by the road line.
and commodities from one place to another, and as
Gravel Road-Are constructed from natural gravel
communication link which brings economic
together with a sufficient amount of good quality soil
development to a nation.
to serve as binder.
Classifications of Road
It is sometimes termed as an “all weather road” and
Types of Road According to Usage are used to construct Farm to Market Roads which
serves to connect rural and agricultural areas to market
National Road towns
3. City Road - it a street within the urban area of the Types of Road According to Traffic Volume
city.
➢ For heavy traffic load
4. Municipal Road - it is a street within the poblacion ➢ For medium traffic load
area of a municipality. ➢ For light traffic load
Before the start of work on the different items, a joint 5. Clearing shall extend one (1) meter beyond the toe
survey must be undertaken in order to locate the of the fill slopes or beyond rounding of cut slopes for
centerline of the proposed road, to check the existing the entire length of the project.
elevations, cross-sections and other existing structures
as shown on the original plan and prepare/submit an
“As-Staked Plan”, for the approval of the higher Item 101-Removal of Structures and Obstructions
authorities.
Removal of structures and obstructions - consist of the
Item 100-Clearing and Grubbing taking away, wholly or in part, and the satisfactory
disposal off the site of all structures within the
Clearing and Grubbing - is the removal and disposal of
construction site and right-of-way which have not been
all surface objects including vegetation, grass, stumps,
designated to remain. It is important that removal
trees and other protruding obstructions not designated
operations are carefully studied and carried out under
to remain along the roadway prior to commencing of
the careful supervision of the Project Engineer with
any earth-moving activity.
adequate consideration of safety
Types of Clearing and Grubbing
Types of Obstruction
1. Individual Removal of Trees - removal is
1. Existing Pavements
classified depending on the size :
2. Existing Drainage Structures
a. Item 100(3) - Individual Removal of Trees, Small
3. Underground Waterline
b. Item 100(4) - Individual Removal of Trees, Large
4. Electrical Post and Lines
2. Disposal of Debris - The Contractor should 5. Cable and Telephone Lines
coordinate with the Project Engineer regarding the 6. Residential Houses & Buildings
identification of sites for disposal area in compliance
Equipment Requirements
with the provisions stated in the Environmental
Clearance Certificate issued by the Department of - Backhoe
Environment and Natural Resources (DENR). - Dump Truck
- Minor Tools
Equipment Requirements
Construction Procedures
• Bulldozer (155 HP) D65A-8
• Backhoe Simultaneously with the clearing and grubbing works,
• Payloader (1.5 cu.m.) removal of obstructions both overhead and
• Dump Truck (10 cu.m. cap.) underground utilities in particular waterlines and
• Road Grader telephone lines shall be undertaken.
Item 102- Excavation • Dump Truck
• Loader
Excavation - consists of all the excavation for grading
and draining the roadway, and includes loading, Construction Procedures
hauling and placing the excavated materials from 1.Conduct survey works on the existing ground to
roadway cuts to construct embankments or its disposal compare the data as reflected in the approved plans.
to a designated location. 2.Excavate the roadway having unsuitable materials up
to the stable soil condition.
Types of Excavation 3.Dispose/haul the said materials to the
1. Common Excavation designated/approved disposal area.
2. Unsuitable Excavation Item 102(2) - Common Excavation
3. Rock Excavation
4. Unclassified Excavation Common Excavation - refers to the excavation of
5. Surplus Excavation common materials along the road traverse that may be
placed as fill or disposed as surplus.
Equipment Requirements
- Bulldozer - Backhoe Item 102(3) - Rock Excavation
- Dump Truck - Loader
- Drilling Machine Rock Excavation - is the digging on the ground
- Blasting Equipment and Accessories necessary along the road way traverse to remove
encountered rock to its designed elevation either for
Construction Procedures use as an embankment or for hauling to a waste
deposit area.
1. Right-of-way limits must be provided with stakes.
2. Survey works must be conducted on the existing Means of Excavating Rock
ground.
3. Excavate the roadway to the required elevation per 1. Thru Mechanical Ripping - if the rock is soft.
approved plans 2. Thru Controlled Blasting - if the rock is too hard.
4. If unsuitable materials are encountered, excavate the
Item 102(4)-Surplus Excavation
roadway up to the stable soil.
5. If surplus materials are encountered, haul the said Surplus Excavation - are suitable materials excavated
materials to the designated disposal area. along the road traverse which are disposed as excess in
the formation of embankment subgrade.
Item 102(1) - Unsuitable Excavation
Types of Surplus Excavation
Unsuitable Excavation - is the removal and disposal of
saturated mixture of soils and organic matter such as 1. Surplus from Common Excavation
peat and muck which are not suitable as road 2. Surplus from Rock Excavation
foundation materials which can cause instability in 3. Surplus from Unclassified Excavation
embankments
Item 103-Structure Excavation
As a rough guide in recognizing and identifying
unsuitable materials, said materials is composed of Structure Excavation - consists of the necessary
thoroughly decomposed organic material with excavation, removal and satisfactory disposal of all
considerable mineral material, usually black with a materials within the stipulated limits.
few fibrous remains, odorous when dried or burnt,
Types of Structure Excavation
some sand and silt and those materials excavated from
swamps and stagnant water. In order to determine the 1. Culvert Excavation
exact property of the unsuitable materials subject a 2. Dry Excavation
representative sample to laboratory test. 3. Wet Excavation
4. Rock Excavation
Equipment Requirements
5. Bridge Excavation (Unclassified)
• Bulldozer
• Backhoe
Equipment Requirements 2.The material is spread in relatively thin layer of 200
• Dump Truck (10 cu.m.) mm with appropriate crown/cross slope to ensure
• Backhoe (0.80 cu.m.) proper draining of surface water when it rains.
• Minor Tools
3.Compaction should be done by rolling with a
Construction Procedures minimum weight of 10 tons. Rolling/compaction
operation shall progress gradually from the sides to the
1.Prior to structure excavation, all necessary clearing center, parallel to the center of the road and shall
and grubbing shall have been performed. continue until the whole surface has been rolled up to
2.Check and review the plans. the number of passes required based on the trial
section result where a minimum density of 95% is
3.Trenches shall be excavated to the lines and grades attained. During the progress of rolling, a minimum
or elevations shown on the Plans. overlapped width of 300 mm. shall be observed for
each succeeding parallel passes to ensure level
4.The foundation surface shall provide a firm compacted surface.
throughout the length of the culvert.
4.Conduct one group of three in-situ density tests for
Item 104-Embankment each five hundred (500) square meter or fraction
thereof of compacted layer. If it fails to meet the
Embankment - is describe as the work or volume of
minimum 95% density, additional rolling shall be
earthen material necessary in the formation of
undertaken until such time that the required
embankment roadway thru the use of suitable materials
compaction is obtained.
which may be sourced along the road traverse or
borrow from an outside source. These materials are For a saturated material wherein the minimum density
brought and compacted together to a specified degree could not be attained, windrowing should be
to form a stable embankment to bring the road to a undertaken and allow it to dry, and proceed with
desired grade or to elevate it above flood level. rolling up to the desired compaction.
Material Requirements If the material is too dry, watering/sprinkling with
water shall be undertaken uniformly.
Please refer to Section 104.2, Material Requirements
of DPWH Standard Specifications for Highways, What Is an FDT ?
Bridges and Airports, Volume II, 2013 Edition.
FDT is Field Density Test which is conducted on site
Types of Embankment in order to determine if the required compaction
specification has been attained to a specific layer.
1. Embankment from Excavation
2. Embankment from Borrow What Do We Mean by Blue Tops?
Equipment Requirements Blue Tops are painted sticks placed along the side of
the road traverse as guide and reference in the
• Grader, 150 HP
elevation of the different layering requirements of the
• Road Roller, 10 T Vibratory or Tandem
road project
• Water Truck, 500-1000 galloons
Item 105- Subgrade Preparation
For clay material : sheepsfoot roller shall be used to
obtain proper compaction. Subgrade - is that portion of the earth roadbed which
after having been constructed to reasonably close
Construction Procedures
conformance with the lines, grades and cross-sections
A. Construction of embankment on a relatively flat indicated on the plans, receives and supports the sub
terrain: base or base course materials.
1.Check sub grade if already completed in accordance
In a fill section, the sub grade is the top of the
with the plans and specifications for clearing and
embankment or the fill.
grubbing and sub grade preparation prior to filling of
In a cut section, the sub grade is the bottom of the cut.
embankment materials.
Material Requirements Construction Procedures
Please refer to Section 105.2, Material Requirements 1. Check the subgrade, if already completed in
of DPWH Standard Specifications for Highways, accordance with the plans specifications before
Bridges and Airports, Volume II, 2013 Edition. proceeding with the laying of sub base course
materials.
Equipment Requirements
2. Provide blue-top of every 20 meters interval
• Grader, 150 HP (marked staked) for vertical control reference, to be
• Road Roller, 10 T Vibratory or Tandem placed along the side of the roadway.
• Water Truck, 500 – 1,000 galloons
3.Laying and spreading of aggregate sub base
Construction Procedures materials shall be done using road grader on a prepared
subgrade in a quantity which will provide the required
1. Subgrade in Common Excavation :
compacted thickness.
a. Roadbed shall be cleared of unstable materials.
Appropriate crown/cross slope should be maintained
b.Compaction shall be done by rolling using vibratory during laying/spreading operation to ensure proper
road roller or tandem roller. draining when rains occur. No laying/spreading
operation should be done when it is rain; or when base
c.Conduct one group of three in-situ density test for is too saturated.
each 500 square meter or fraction thereof of
compacted layer. 4. Compaction should be done using a vibratory road
roller or tandem roller with a minimum weight of 10
-if it fails to meet the minimum 95 percent density, tons. A maximum compacted thickness for any layer
additional rolling is needed to obtained the required shall not exceed 150 mm. No rolling / compaction
density. operation should be done when it is raining or when
the laid sub base course is fully saturated with rain.
d.The succeeding structural layers should proceed
immediately after preparation of the subgrade. Rolling/compaction shall progress gradually from the
sides to the center, parallel to the center of the road
PART II SUBBASE AND BASE COURSE
and shall continue until the whole surface has been
rolled up to the number of passes required based on the
trial section result where 100% compaction is attained.
Progress rolling should provide 300 mm. overlap of
the width of the wheel for each succeeding parallel
Item 200-Aggregate Sub base Course passes to ensure level compacted surface.
Aggregate Sub base Course - refers to the structural 5. Conduct Field Density Test (FDT) for each
sub-layer material of a roadway placed directly on top compacted layer. If failed to satisfy the Field Density
of the sub-grade. requirements of at least 100% of the maximum dry
density, additional rolling shall be undertaken until
Equipment Requirements such time that the required compaction is attained.
Check the allowable tolerance prior to the start of the
• Road Grader with Scrapper (GD511A-1) succeeding layer. Allowable tolerance is plus or minus
• Vibratory Drum Roller (BW151AC) 20 mm.
• Water Truck (500-1000 gal.)
• Minor Tools Item 201-Aggregate Base Course
Please refer to Section 201.2 Material Requirements of Bituminous material shall either be Rapid Curing
DPWH Standard Specifications for Highways, Bridges (RC) or Medium Curing (MC) Cutback Asphalt,
and Airports, Volume II, 2013 Edition. whichever is called for in the Bill of Quantities (Refer
to the requirements of Item 702 –Bituminous
Construction Procedures Materials).
1. Check the preparation of the existing surface, if it is Range of Temperature: Temperature Range = 32*C
in accordance with the plans and specifications. (min.) to 68*C (max.)
2. Aggregate Base Course shall be placed spread and Equipment Requirements
compact at a uniform mixture on a prepared subgrade
in a quantity which will provide the required • Self-powered pressure bituminous material
compacted thickness, using road grader vibratory road distributor
roller simultaneously. • Power broom or other mechanical sweeping
equipment
3. Conduct Field Density Test for each compacted • Bituminous heating equipment
layer. Allowable tolerance is plus or minus 10mm. • Pressure distributor
• Water sprinkler
Spreading
• Armored Thermometer
➢The subbase/base materials shall be spread to the
Construction Procedures
required thickness for compaction.
1. Prior to the application of the prime coat, check the
➢If the required thickness is 150 mm or less, the
base if it conforms with the required specifications.
material may be spread and compacted in one layer.
2. Apply the prime coat by using pressure distributor at
Compaction a rate of 1 to 2 liters per square meter.
➢Each layer shall be compacted to the full width. 3. Prime coat shall be left undisturbed for a period of
at least 24 hours.
➢Required degree of compaction is 100%
4. Extend the prime coat at least 30 cm. beyond the
edge of the surface on each side.
PART III SURFACE COURSES
5. Observed the time of penetration starting from the
time of its application.
3. The longitudinal joint in one (1) layer shall be offset 19. If the deficiency in the core thickness is more than
that in the layer immediately below approximately 15 5 mm, additional asphalt overlay thickness shall be
cm. permitted to meet the desired thickness but it shall not
be less than 50 mm.
4. The joint in the top layer shall be at the center line
of the pavement if the roadway comprises of 2 lanes. 20. Completed asphalt pavement shall have thickness
tolerance of -5mm.
5. Mechanical spreading shall be used on areas with
irregularities or unavoidable obstacles.
9. Each trip overlapping ½ the roller width, gradually This drawing shows the methodology of constructing a
progressing to the crown of the road. multi layered asphalt concrete pavement includes the
10. For paving in abutting a previously placed lane, the following: application of prime coat, application of
longitudinal joint shall be rolled first followed by the binder course, application of tack coat and the
regular rolling procedure. application of wearing course
a. Joints shall be sealed with asphalt sealant 1. Portland Cement Concrete Pavement (PCCP) –
Rigid Pavement
14. Pavement Protection :
2. Asphalt Concrete Pavement (ACP) – Flexible
a. Against Rain – To protect the newly poured Pavement
concrete pavement.
b. Against Traffic - To protect the newly poured RIGID PAVEMENT
concrete pavement at its early age Rigid Pavement (PCCP) consists of three (3) layers:
“To have a good workmanship, a well trained mason 1. Concrete Slab – Made of reinforced on plain
should be hired to have a smooth pavement surface.”
concrete;
Types Of Pccp Joints 2. Subbase – Portion of the pavement structure
1. Construction Joint : between the subgrade and the slab; and
• Construction Joint is also called “cold joint” 3. Subgrade – Bottom portion of the pavement
structure
I. Quality Control (Pccp) • All joints shall be protected from the intrusion of
injurious foreign material until sealed;
The contactor shall perform all sampling, testing, and
inspection necessary to assure quality control of the • All joints shall be cut within 4 to 24 hours after
component materials of the concrete pouring and sealed with asphalt sealant;
II. Design Mix And Trial Paving (Pccp) • Depth of the weakened plane joint shall not be less
than 50mm whole the width not more than 6mm.
The contractor is required to formulate the design mix,
conduct trial mix and trial paving for approval of the VII.Types And Functions Of PCCP Joints
Project Engineer before commencement of pavement
construction
III.Admixture/Additive (Pccp)
4. Existing tie bars on longitudinal joints are to be Laying of Base Materials by means of Road Grader
retained if these are still in good condition. Where and Paver
necessary, new tie bars shall be installed on drilled
holes and bonded with high viscosity epoxy resin. PART IV DRAINAGE AND SLOPE
PROTECTION STRUCTURES
5. Install forms; side surfaces of the existing PCCP
shall be cleaned.
Please refer to Section 500.2, Material Requirements ➢Backfill are placed and compacted in layers not
of DPWH Standard Specifications for Highways, exceeding 15 cm. on both sides up to an elevation of
Bridges and Airports, Volume II, 2013 Edition. 30 cm above the top of the culvert.
➢Spreading maybe done manually using rakes and
Equipment Requirements
shovels at a thin layer which is most ideal to produce
• Backhoe (0.80 cu.m.) easy compaction of material done using hand tampers
• Plate Compactor (5 HP) to insure a thoroughly tamped backfill.
• Minor Tools ➢After backfilling, pipe culverts are protected by
providing extra fill as cover before any heavy
Construction Procedures equipment is permitted to cross during the construction
of the roadway to protect the job from possible damage
1.The Project Inspector should verify if the inlet and
by excessive loads.
outlet channel are adjusted to ensure a smooth flow of
water and avoid scour.
2.It is important that the base of the excavation is Item 505 Riprap and Grouted Riprap
smooth and conforms to the design culvert grade line.
Riprap and Grouted Riprap - is a type of slope
3.If the excavation is being carried out in wet protection using boulders of specified size and
conditions then, it should be started at the lowest point character which may be done with or without grout
and progressively dug to the higher end. The trench or and which holds in place embankment slopes, cut
streambed must be shaped to fit the bottom of the slopes and other earth surfaces that may either be
culvert. Flat if it is flat bottom and circular if RCPC is eroded or washed away by water.
used.
All work must be constructed on firm ground so that
4.Pipes are installed in the original streambed with there is no chance of settlement or failure by cracking.
their grades and flow line conforming to the natural
channel or canal. Pipe is usually laid with the bell or A. Dry Riprap
female ends upstream.
1. Dry Riprap is more economical without
5.Care must be taken in the jointing process that the considering the grout to bring together the
pushing together of the pipes to complete the joint boulders however; it is only applicable to a
does not disturb the bedding. limited height and slope.
2. .Dry Riprap is stone laid carefully by hand
➢Pipes are installed in the original streambed with following a definite pattern with the voids
their grades and flow line conforming to the natural between the larger stones filled with smaller
channel or canal. stones and the surface kept relatively even. It
➢Laying begins at downstream end of the culvert line requires that the stone be relatively uniform in
to use gravity in properly installing the pipes. size and shape (square or rectangular).
➢Groove ends are placed such that the pipe ends fit at
Advantages associated with the use of Dry Riprap 7. Seat the stones/boulders to the required thickness
include: and that all boulders are placed on firm and compacted
ground.
1. The even interlocking surface produces a neat
appearance. 8. Wet by spraying with water the face of the grouted
2. It is more flexible that it can accommodate riprap structure prior to the application of the grouts
movements due to foundation failures without and fill the voids to the specified depth.
breaking.
9. Check that the faces of stones are relatively free of
Disadvantages associated with Dry Riprap include: grout.
2. Pour concrete mortar on the trench before laying the ➢The riprap is thoroughly rammed into place and the
first layer of stones/boulders for the foundation. finished stone are laid to an even tight surface.
➢Spaces between stones are filed with cement mortar
3. Moisten the surface of the stones before the stone is sufficient enough to fill completely all the voids.
bedded.
Finishing Work
4. Lay the stones/boulders wherein the longer axis of
the stones/boulders is perpendicular to the slopes. ➢Cement grout is placed starting from the bottom to
the top of the surface and then swept with a stiff
5. Alternately lay the stones/boulders and fill all voids broom.
with concrete mortar for the succeeding layers. ➢After grouting, the surface is cured for a period of at
6. Install the weep holes (usually, PVC – 2 inches in least 3 days from the date of installation.
diameter, staggered 1.0 m. on center) provided with
Measurement of Thickness
filter cloth and granular materials.
What is the importance of weep holes in slope 4. Place the larger stones in the foundation to give the
protection/retaining structure? greatest strength and lessen the danger of unequal
settlement.
➢Weep holes are opening provided to permit draining
of water in filter layer or soil layer from behind the 5. Alternately lay the stones/boulders and fill all voids
structure. and interstices of the stones/boulders with concrete
➢If no or insufficient weep holes are installed, this mortar for the succeeding layers.
will cause oversaturation of the embankment and the
6. Lay the stones/boulders upon its broadest face, so
subsequent failure of the road structure.
that the spaces between the stones may be filled most
Item 506-Stone Masonry easily.
Retaining wall - are structures that support soils at 7. Install the weep holes (usually, PVC – 2 inches in
slopes steeper in their angle of repose and because of diameter, staggered 1.0 m. on center) provided with
their resistance to earth pressure derived from their filter cloth and granular materials.
own weight they are also known as “gravity walls”.
8. Seat the stones/boulders to the required thickness
Types of Stone Masonry and that all stones/boulders are placed firmly;
1. Sizes and Shapes : Stones should have a thickness of 9. Flush with mortar all joints between stones/boulders
not less than 150 mm. so that the individual stones laid are parallel to the
faces of the wall in which the stones are set.
2. Dressing : Stones should be dressed to remove any
thin or weak portions 10.Backfill the stone masonry when the mortar has
gained sufficient strength.
3. Finish for expose faces : Face stones should be
pitched to the line along the beds and joints. The Stone Masonry Specifications
maximum projection of rock faces beyond the pitch
➢ Boulders - thickness of not less than 150 mm, and
lines should not be more than 50 mm
widths of not less than one and one-half times their
Equipment Requirements respective thickness, and lengths of not less than one
and one-half times their respective widths.
• One Bagger Mixer
• Water Truck (1000 gal.) ➢ Mortar - composed of one part of Portland Cement
• Backhoe Wheel Type (0.28 cu.m.) and two parts of fine aggregate by volume and
• Minor Tools sufficient water to make the mortar such consistency
that it can be handled easily and spread with a trowel.
Material Requirements
Excavating Stone Masonry Foundation
Please refer to Section 506.2, Material Requirements
of DPWH Standard Specifications for Highways, ➢The foundation bed where the masonry is to be
Bridges and Airports, Volume II, 2013 Edition. placed should be firm and normal to the face of the
wall.
Construction Procedures
➢The bed that will receive the stone should be clean
1. Excavate the trench to the required depth and/or at
and moistened before the mortar is spread.
the stable foundation of the stone masonry structure.
Use of Batterboards Essential to Produce Good
2. Pour concrete mortar on the trench before laying the
Workmanship
first layer of stones/boulders for the foundation.
As in grouted riprap, batter boards are necessary to
3. Moisten the surface of the stones before the stone is
keep the lines and grades of the finished stone masonry
bedded to prevent the stone from absorbing moisture
structure in accordance to the lines and grades of the
from the mortar and thereby causing the mortar to
plans.
shrink and become non-plastic
Laying of Boulders and Grout Equipment Requirements
Types of Curb and Gutter Sidewalk - is typically 100 mm to 150 mm thick slab
on grade and it is an important feature of the urban
1. Rounded Curbs - are used in many residential environment.
areas and are most often used at driveways.
2. Angled Type - is most often used on major Types of Sidewalk
suburban thoroughfares.
Two categories of Sidewalks :
3. Square (90°-edge) Type - is used in towns and
cities as it is a straight step down and less to be 1. Asphalt Sidewalk
tripped-over by pedestrians. 2. Concrete Sidewalk
➢For traffic safety 3. Lane Lines – these are 100 mm wide white stripes
➢To remind particular traffic rules between contiguous lanes of pavement carrying traffic
➢To inform drivers how to use the roadway in the same direction.
Item 606 - Pavement Markings 4. Transverse Lines - are laid across the direction of
travel or markings across the carriageway.
Pavement markings - is essential component of
roadway for the guidance and control of vehicles and Transverse lines should be solid stripes 600 mm (24
pedestrians. They take the form of lines, symbols, inches) wide, of the color specified and placed at an
messages or numerals and may be set into the surface angle to the direction of travel.
applied upon or attached to the pavement.
Transverse lines may be classified into the following
Material Requirements types: Stop Line; Yield (Give Way) Lines; and
Pedestrian Crossing Markings.
Please refer to DPWH Standard Specifications for
Highways, Bridges and Airports, Volume II, series of
2004.
Equipment Requirements
• Cargo Trucks
• Applicator Machine
• Kneading Machine
• Traffic Safety Devices • Minor Tools
Construction Procedures