DETAILED CUM ABSTRACT ESTIMATE
Construction of CC Road from Bairi Srinu (H) to Ramu (H) in Adharsh Nagar in Manuguru Municipality
in Manuguru Mandal of Bhadradri Kothagudem Dist.,
Road Length 183.00 meters
Quant
S No Description No. Length Breadth Depth Rate Per Amount
ity
1 2 3 4 5 6 7 8 9 10
Wetmix Macadam
1 Providing, Laying, Spreading and compacting graded HBG crushed stone
aggregate as per table 400.11 and 400.12 of MORD to Wet Mix macadem
specification including cost,seignorage of all materials and including
premixing the material with water at OMC in Mechanical mix plant (pug mill)
carriag of mixed material by tipper to site , laying in uniform layers with
motor grader on base course on well prepared surface and compacting with
Vibratory roller to acheive the desired density etc., as directed by the
Engineer-in-Charge and as per MoRT&H specification.406 (4th revision)
and 406 MORD complete for finished item of work. (Payment based on
levels for finished item of work)
1 x 1 183.00 3.00 0.075 41.18
41.18 2918.50 cum 120184.00
Cement Concrete Pavement M 30
2 Construction of un-reinforced, dowel jointed at expansion and construction
joint only, plain cement concrete pavement, thickness as per design, over a
prepared sub base, with 43 grade cement or as per Clause 1501.2.2 M30
(Grade), coarse and fine aggregates conforming to IS : 383, maximum in a
concrete mixer of not less than 0.2 cum capacity and appropeiate weigh
batcher using approved mix design, laid in approved fixed side formwork
(steel channel, laying and fixing of 125 mictron thick polythene film,
wedges, steel plates including levelling the formwork as per drawing),
spreading the concrete with sholvels, rakes, compacted using needle,
scareed and plate vibrators and finished in continuous operation including
provision of contraction and expansion, construction joints, applying
debonding strips, primer, sealant, dowel bars, near approaches to bridge /
culvert and construction joints, admixtures as approved, curing of concrete
slabs for 14- days, with water finishing to lines and grade as per drawing
and Technical Specification Clause 1501 MORD.
1 x 1 183.00 3.00 0.175 96.08
96.08 7028.80 cum 675327.00
Selected Earth Shoulders
3 Construction of improved subgrade/ Shoulders by providing selected earth
having minimum CBR of 10%, MDD not less than 1.85 g/cc with LL & PI not
more than 40% and 20 respectively"&" and spreading in uniform layers with
tractor grader on prepared surface, and compacted at OMC with vibratory
roller 80-100 kN to meet requirement of Table 300.2 with as per
Technical"&" Specification Clause 303 MORD / 305 MORTH, by using
machinery including contractors profit & Over head charges
1 x 2 183.00 0.30 0.25 27.45
27.45 466.75 cum 12812.00
Total :: 808323.00
Assistant Engineer Deputy Executive Engineer Executive Engineer
TWS/Manuguru TWSD/Paloncha TWDivn/Bhadrachalam