ID Task Task Name Duration Start Finish Predecessors Resource Names
Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Mode Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 Mobilization 6 days Mon 09/10/23Mon 16/10/23
2 Preparation of Materials 3 days Mon 09/10/23Wed 11/10/23
3 Loading at Honiara 1 day Thu 12/10/23 Thu 12/10/23 2
4 Unloading at Auki 2 days Fri 13/10/23 Mon 16/10/23 3
5 Emergency Maintenance 28 days Tue 17/10/23 Thu 23/11/23
6 Clearing and removal of obstacles from the right of way and along 5 days Tue 17/10/23 Mon 23/10/23 4
the full road section
7 Reinstatement of existing or construction of new unlined drains 5 days Tue 24/10/23 Mon 30/10/23 6
8 Repair of exsiting line drains 5 days Tue 31/10/23 Mon 06/11/23 7
9 Installation of scour checks in drains 5 days Tue 17/10/23 Mon 23/10/23 4
10 Shoulder maintenance - Grading 5 days Tue 17/10/23 Mon 23/10/23 4
11 Removal of landslides on carriageway from cuts and natural slopes 5 days Tue 07/11/23 Mon 13/11/23 8
12 5 days Tue 14/11/23 Mon 20/11/23 11
13 Stone pitching to slopes 10 days Tue 24/10/23 Mon 06/11/23 9
14 Spot gravelling with coronous materials 10 days Tue 17/10/23 Mon 30/10/23 4
15 Emergency grading works for roadway(including shoulders) 10 days Tue 24/10/23 Mon 06/11/23 10
16 Additional material for grading works - Coronous 10 days Tue 31/10/23 Mon 13/11/23 14
17 The replacement of signs along the road 7 days Tue 17/10/23 Wed 25/10/23 4
18 The replacement of sign posts and signs 7 days Thu 26/10/23 Fri 03/11/23 17
19 The resetting of guardrails along the road 7 days Mon 06/11/23Tue 14/11/23 18
20 The realigning of guardrails along the road 7 days Wed 15/11/23Thu 23/11/23 19
21 Routine Maintenance 110 days Tue 07/11/23 Mon 08/04/24
22 Clearing and removal of litter, debris from the right of way and 110 days Tue 07/11/23 Mon 08/04/24 13
along the full road section
23 Maintenance of vegetation within the right of way (1.5m) 110 days Tue 07/11/23 Mon 08/04/24 13
24 Maintenance of all drains in the right of way (both sides) 100 days Tue 21/11/23 Mon 08/04/24 12
25 Construction of Turnouts for existing drains 110 days Tue 07/11/23 Mon 08/04/24 13
26 Detailed Inspections of all culverts, inlets and outlets -31 Culverts 110 days Tue 07/11/23 Mon 08/04/24 13
27 Maintenance of all culverts, inlets and outlets except for the newly 110 days Tue 07/11/23 Mon 08/04/24 13
upgraded ones-23 Culverts
28 Maintenance of culverts - High Pressure Flushing 110 days Tue 07/11/23 Mon 08/04/24 13
29 Installation of Riprap at Outlets D150 - 3m x 2.5m x 0.3m thick layer 110 days Tue 07/11/23 Mon 08/04/24 13
30 Shoulder maintenance - Light grading 110 days Tue 07/11/23 Mon 08/04/24 15
31 Vegetation maintenace work (1.5m) 110 days Tue 07/11/23 Mon 08/04/24 13
32 Additional general fill of 150mm thick for verge works 105 days Tue 14/11/23 Mon 08/04/24 16
33 Installation of turnouts on both sides of verge 110 days Tue 07/11/23 Mon 08/04/24 13
34 Maintenance of slopes 100 days Tue 21/11/23 Mon 08/04/24 12
35 Planting of vegetation (small trees) for Erosion Control (both sides at 110 days Tue 07/11/23 Mon 08/04/24 13
1.5m wide)
36 Maintenance of waterways 100 days Tue 21/11/23 Mon 08/04/24 12
37 Spot Gravelling with coronous materials 105 days Tue 14/11/23 Mon 08/04/24 16
38 Light Grading 110 days Tue 07/11/23 Mon 08/04/24 15
Task Project Summary Manual Task Start-only Deadline
Project: Project Schedule East R Split Inactive Task Duration-only Finish-only Progress
Date: Sun 17/11/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names
Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Mode Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
39 Repair of Small Potholes - 10% ( Removal, Box Out and Compaction ) 110 days Tue 07/11/23 Mon 08/04/24 13
- < 100mm deep
40 Repair of Small Potholes - 2% ( Removal, Box Out and Compaction ) - 110 days Tue 07/11/23 Mon 08/04/24 13
< 100mm deep
41 Cleaning and repair of Signs, km posts and edge marker posts and 110 days Tue 07/11/23 Mon 08/04/24 13
guardrails along the road
42 The replacement of edge marker or culvert marker post along the road110 days Tue 07/11/23 Mon 08/04/24 13
43 Periodic Maintenance 30 days Mon 20/11/23Fri 29/12/23
44 Shoulder Maintenance - Heavy Grading 10 days Mon 20/11/23Fri 01/12/23
45 Gravelling with coronous materials 5% Camber - more than 28% of 30 days Mon Fri 29/12/23
project value 20/11/23
46 Heavy Grading 20 days Mon 04/12/23Fri 29/12/23 44
47 Spot Upgrade 97 days Tue 05/12/23 Wed 17/04/24
48 Boxout, regravel, compact and Construct 200m-300m long x 8m x 90 days Tue 05/12/23 Mon 08/04/24
150mm thick wide reinforcement concrete pavement for select 10%
to 11% slopes at the select locations as per the BOQ (4 Locations)
49 Excavate and construct new trapezoidal earth drain size 300mm 30 days Tue 26/12/23 Mon 05/02/24
base width and 600mm depth on both LHS/RHS of road as directed
by the Engineer
50 Excavate and construct new concrete line drain "Type 1" size 30 days Tue 06/02/24 Mon 18/03/24 49
300mm base width and 500mm Depth on both LHS/RHS of road as
directed by the Engineer
51 Excavate and construct new reinforced concrete V drain "Type A" 90 days Tue 05/12/23 Mon 08/04/24
size 300mm base width and a depth of 150mm on both side of Road
at select locations as per the BOQ (4 Loactions)
52 Construct of turnouts for new drains 15 days Tue 05/12/23 Mon 25/12/23
53 Construct new scour checks for new and existing drains 10 days Tue 26/12/23 Mon 08/01/24 52
54 Removal of existing undersize culverts for replacement with new 10 days Tue 09/01/24 Mon 22/01/24 53
culverts (Item 2.5.1)
55 Remove existing reinforced concrete pipe culvert (removal cost 22 days Tue 23/01/24 Wed 21/02/24 54
included Item 2.5.1) and supply and construct new 1m diameter
reinforced concrete pipe culvert with outfall structures on both
upstream & downstream at locations per BOQ(7 Locations)
56 Construct headwall and wingwall for single 1000mm reinforced 22 days Thu 22/02/24 Fri 22/03/24 55
concrete pipe culvert at select locations as per BOQ (7 Locations)
57 Remoave existing reinforced concrete pipe culvert (removal cost 14 days Tue 05/12/23 Fri 22/12/23
included Item 2.5.1) supply & construct 1500mm dia. Reinforced
concrete pipe culvert with outfall structres on both upstream &
downstream at CH 18.960
58 Construct headwall and wingwall for single 1500mm reinforced 10 days Mon Fri 05/01/24 57
concrete pipe culvert at CH 18.960 25/12/23
59 Construct and treat slope with Gabion retaining wall on one side of 15 days Mon Fri 26/01/24 58
road (2 Loactions) at CH 6.000 08/01/24
60 Construct and treat slope with Gabion retaining wall on RHS of road 12 days Mon Tue 13/02/24 59
at CH 9.900 29/01/24
Task Project Summary Manual Task Start-only Deadline
Project: Project Schedule East R Split Inactive Task Duration-only Finish-only Progress
Date: Sun 17/11/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 2
ID Task Task Name Duration Start Finish Predecessors Resource Names
Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Mode Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
61 Top soil and vegetation Treatment to slopes 20 days Wed 14/02/24Tue 12/03/24 60
62 Final Inspection Work Completion 2 days Tue 09/04/24 Wed 10/04/24 48
63 Demobilization 5 days Thu 11/04/24 Wed 17/04/24 62
Task Project Summary Manual Task Start-only Deadline
Project: Project Schedule East R Split Inactive Task Duration-only Finish-only Progress
Date: Sun 17/11/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 3