Method Statement
Method Statement
Method Statement
METHOD STATEMENT
CLIENT: CARDINAL NAMDINI MINES LIMITED
WHITE VOLTA RIVER ABSTRACTION
PROJECT:
AND PIPE LINE PHASE I
CONTENTS
Method Statement
PAGE
1 METHOD STATEMENT 3
1.1 Introduction 3
1.1.1 References 3
1.1.2 Scope of Work 3
1.1.3 Location of Works 3
1.1.4 Description and Nature of Works 3
1.1.5 Schedule and Duration of Work 4
1.2 Project Management Organization 5
1.2.1 Project Manager 5
1.2.2 HSE Manager 5
1.2.3 Works Supervisor 5
1.2.4 Engineers / Surveyors 5
1.2.5 Materials Engineer 5
1.2.6 Plant Manager 5
1.2.7 Organisation Chart 5
1.2.8 Plans for Subcontracting 7
1.3 Mobilization, Site Organization & Establishment 8
1.3.1 Mobilization 8
1.3.2 Site Organization 8
1.3.3 Site Establishment 8
1.4 Construction Methodology 10
1.4.1 Sequence/Phasing 10
1.4.2 Resources 10
1.4.3 Execution of the Works 10
1.4.3.1 Site Clearance 10
1.4.3.2 Earthworks 11
1.4.3.3 Catch Pit works 15
1.5 Quality Management, Control & Testing 16
1.6 Mine Site Conditions 17
1.7 Safety / Risks 18
1.7.1 Risks 18
1.7.2 General Safety 19
Method Statement
1 METHOD STATEMENT
1.1 Introduction
This execution plan has been prepared to cover the construction of the Cardinal Namdini
Mines Limited – White Volta Water Abstraction and Pipe Line –Phase I on behalf of Cardinal
Namdini Gold Mines Ltd (CNML). Any amendments required during the work will be
incorporated into this document and issued in accordance with company procedures.
This document will demonstrate our ability to provide a planned approach to the construction
of the project.
1.1.1 References
Documents that relate to the work are as follows:
Document Title Scope of Document Document Ref:
AEL Construction Gantt Chart detailing construction
Schedule activity
Tender Documents CN-22.058
Method Statement
Method Statement
The Plant Manager will be responsible for regular planned maintenance, and day to day repair
of the equipment used on the project. He will report to the PM, and maintain the required
working relationship with the CM. He will lead the team of workshop staff.
Method Statement
Abijah staff will communicate formally in writing and confirm all verbal communication received
and issued, in writing to the Employers Rep.
Abijah staff will attend HSE / E&S / Progress / Technical meetings as required for the project.
Reports for these meetings will be prepared and issued to the relevant CNML / Resident
Engineers staff.
Currently the only such specialist work that is envisaged is the Piezometer scope of work.
Method Statement
Method Statement
A basic on-site workshop and stores will be provided to handle all routine service and
maintenance requirements for the plant and equipment employed on the project. Major re-
builds or overhauls would be carried out off site at our Accra workshop.
Abijah will occupy and / or have access to all Abijah premises established on site for the full
contract period, including and up to completion of the defects liability period.
Abijah Security will be in place as required to cover all of these facilities day and night shift at
all times.
Rubbish and waste will not be allowed to accumulate unnecessarily. Regular removal to
agreed dumps shall be carried out.
Contractor Accommodation Facility
Accommodation for Abijah management will be located close to the Site locality, in local hotel
facility, or in containerised accommodation (both options having been used in the past
projects).
Living accommodation for Abijah senior staff will be located close to the Site locality, in local
housing.
Accommodation for Abijah junior staff is self-provided, as usual practice for the civil
engineering industry.
Resident Engineers Facilities
A converted container unit shall be provided (if required) within the Abijah site establishment
for the use of the Resident engineer / QC staff.
Method Statement
Method Statement
1.4.3.2 Earthworks
PREPARATION OF FORMATION
The embankment formation (for buttresses etc.) will be prepared using grader to remove any
windrows remaining after topsoil stripping. If unsuitable material is discovered in the formation,
resident engineer will be informed and instructions sought. Any unsuitable instructed for
removal by resident engineer will be replaced using fill material. The material removed will be
taken to agreed spoil areas.
Subgrade scarification, proof rolling and compacting shall be performed using CAT 14 working
in conjunction with water tanker and 10T vibrating roller. No material movement is required in
this scope.
BULK EARTHWORKS
Excavation of material in mine stockpiles or borrow areas for use as embankment fill materials
will be carried out by different methods relating to the plant fleet employed.
It is envisaged that the earthworks on this project will be performed by excavator loading direct
to haul trucks for stockpile and borrow pit work, and also via scraper fleet for earth materials
removed from borrow pits.
Haul trucks will deliver material to fill area where spreading, moisture conditioning and
compaction shall take place. This operation shall utilize 14H grader, D6 dozer, water tankers,
10T vibrating roller and 825 compactor.
Articulated Dump Trucks (ADT’s) will deliver rock fill material to fill area (buttresses or
construction platforms) where spreading by D9 dozer shall take place. This material shall be
traffic compacted per specification. Rock fill material going into construction platforms will be
recorded by trip count and multiply by the agreed volume of Articulated Dump Trucks(ADT).
No deleterious material will be allowed to accumulate on haul roads. Grader will be used to
ensure haul roads are kept in a usable condition.
ABIJAHENGINEER LTD Page 10
CNML – Namdini Gold Project
Method Statement
Material disposed of in spoil area will be spread and levelled using CAT D6 dozers.
CAT 330 excavator / CAT D8/9 dozer working in conjunction with CAT 988 pay loader,
loading tipper truck / dump truck
Embankments
In general, the commencement of embankment raises will commence when an adequate
amount of buttress and construction platform work has been completed, which will allow
economic placing of embankment fill.
The cut off trenches (extensions) will be excavated using 360° excavator or scraper. The base
will be compacted using CAT 825 / 563. As the trench progresses it shall be backfilled with
borrowed Zone A material to surrounding ground level. Trench excavation will be managed to
ensure that excavation opens only the volume of trench that can be filled soon after.
Material arising from excavation in cut off trench will be taken to embankment fill areas or
carted to spoil area as the work quantities or material characteristics dictate.
Individual pockets of unsuitable material below formation in the key trench will be excavated
by 360° excavator and removed to spoil area.
As soon as sufficient area of preparation and cut off trench works have been completed, Zone
A fill material for the embankment will be placed. The embankment will be raised in layers
compacted in accordance with the Project Technical Specification (PTS).
Road construction
General Fill materials will be won from borrow by CAT D9 and deposited as necessary.
The material will be spread using D6 and compacted using CAT 825. Material will be watered
by tankers as required to achieve OMC. Compaction will be performed by CAT / Dynapac
vibrating rollers and CAT 825 deadweight roller, all delivering the number of passes as
required by specification and determined in site trials. These materials will be placed in
suitable layer thicknesses compacted in accordance with the PTS.
The road will be raised using the fill material in layers compacted in accordance with the PTS.
As the road is raised, the slopes will be periodically trimmed, and the material trimmed from
the face will be side cast ready for incorporation into the next lift of the embankment.
Final trimming will be carried out by CAT 14H grader and / or CAT D6 dozers as appropriate.
On completion of the road, the batters / overfill on the upstream face will be trimmed using
dozer or excavator as appropriate to the conditions.
Compaction in progress
Method Statement
Method Statement
Method Statement
Method Statement
and/or used whilst undertaking the work will be handled, used, stored and documented
in accordance with assessments and recommendations suitable for the product in
question. Material Safety Data Sheets will be maintained for all products.
• Communications. The project team will be equipped with mobile telephones and
VHF/FM radio communications during operations. The PM will be available to contact by
mobile phone during all operations on a 24-hour basis to provide a point of contact in the
event of an emergency. Contact details for the PM, and other members of the project
team are included in the emergency contact list, which is included in the appendices of
this CMSP.
• Where Fuels, Oils and Lubes are required to be stored, suitable containers will be used
and stored to allow for ventilation and safe dissipation of any accidentally leaked liquid
or gas. No liquid will be discharged into local water systems at any stage of the work on
site. No smoking will be permitted when refuelling is taking place.
• Formwork Operations. Recognising the importance of safety in this critical operation, all
formwork and falsework operations will be managed to ensure safe systems of work are
achieved. This will commence with design of formwork where required (i.e. where
complex constructions are involved). Formwork and falsework will be designed in
accordance with the design codes produced by the system manufacturers, to ensure
overloading cannot take place, and that assembly, erection, striking, etc is carried out in
a safe manner. Industry best practice will be ensured by reference to standards and
regulations such as
1. Health and Safety in Construction (HSENI 2 00 (B)) published by the Health and
Safety Executive UK.
2. Checklist for Assembly, Use and Striking of Formwork published by the Concrete
Society UK
3. Checklist for Erection and Dismantling of Falsework published by the Concrete
Society UK
4. Construction Site Safety, published by the Construction Industry Training Board, UK.
• Electrical Safety. All electrical systems will be manufactured, installed and operated
within the guidelines for the safe use of electricity. The Plant Supervisor will be
responsible for ensuring:
1. All equipment used on site meets the relevant design, installation and operating
requirements of the guidelines for the safe use of electricity.
2. All equipment is inspected and tested routinely before and during operations.
3. All personnel required to operate equipment are competent operators of the
equipment and fully understand the associated operating procedures.
• Noise Hazard. The plant and equipment that will be used during the work may generate
noise, therefore, ear plugs and ear defenders will be available for use by personnel
operating or working near to noisy plant and equipment.
• First Aid Facilities. Medical first aid kits will be available in site offices. The Site Safety
Manager shall ensure that sufficient numbers of personnel are appropriately trained and
hold current first aid certificates.
• In the event of a medical emergency, Ambulance will be called. The injured party will be
transported to on- or off-site medical facilities as appropriate to the situation.
• Site Traffic. The Works Supervisors will be responsible for ensuring that project activities
do not affect the safety of other mine traffic and that a watch is maintained to ensure that
other mine traffic in the vicinity does not compromise the safety of the project
ABIJAHENGINEER LTD Page 15
CNML – Namdini Gold Project
Method Statement
operations.
• Induction, Drills, Toolbox Talks, Training. A formal programme of personnel induction,
drills, training and toolbox talks will be undertaken in accordance with the SPS.
For further details, refer to the Contractor Safety Management Plan for this projec
Method Statement