0% found this document useful (0 votes)
38 views20 pages

Eurex Top 700

Uploaded by

Tudor Ratiu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views20 pages

Eurex Top 700

Uploaded by

Tudor Ratiu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

999800802 - 02/2022

en-GB

The Formwork Experts.

Doka floor prop Eurex 20 top 700


User Information
Instructions for assembly and use (Method statement)
© by Doka GmbH, A-3300 Amstetten

© by Doka GmbH, A-3300 Amstetten


Tr751-200-01
User Information Doka floor prop Eurex 20 top 700

2 © by Doka GmbH, A-3300 Amstetten 999800802 - 02/2022


User Information Doka floor prop Eurex 20 top 700

Contents
4 Introduction
4 Elementary safety warnings
7 Services

8 Product description

9 Instructions for assembly and use


(Method statement)

14 Possible incorrect usages

15 Technical condition

16 Permitted carrying capacity

18 Transporting, stacking and storing

19 Article list

999800802 - 02/2022 © by Doka GmbH, A-3300 Amstetten 3


Introduction User Information Doka floor prop Eurex 20 top 700

Introduction
Elementary safety warnings
User target groups Remarks on this booklet
▪ This booklet is aimed at all persons who will be work- ▪ This document can be used as general Instructions
ing with the Doka product or system that it describes. for Assembly and Use (Method Statement) or be
It contains information on the standard design for incorporated into site-specific Instructions for
setting up this system, and on correct, compliant uti- Assembly and Use (Method Statement).
lisation of the system. ▪ The graphics, animations and videos in this doc-
▪ All persons working with the product described ument or app sometimes depict partially assem-
herein must be familiar with the contents of this bled assemblies and may require additional
booklet and with all the safety instructions it contains. safety equipment and/or measures to comply
▪ Persons who are incapable of reading and under- with safety regulations.
standing this booklet, or who can do so only with dif- The customer must ensure all applicable regulations
ficulty, must be instructed and trained by the cus- are complied with, even if they are not shown or
tomer. implied in the graphics, animations and videos pro-
▪ The customer is to ensure that the information mate- vided.
rials provided by Doka (e.g. User Information book- ▪ Individual sections contain further safety
lets, Instructions for Assembly and Use, Operating instructions and/or special warnings as applica-
Instruction manuals, plans etc.) are up to date and ble.
available to all users, and that they have been made
aware of them and have easy access to them at the
usage location. Planning
▪ In the relevant technical documentation and form-
work utilisation plans, Doka shows the workplace ▪ Provide safe workplaces for those using the form-
safety precautions that are necessary in order to use work (e.g. for when it is being erected/dismantled,
the Doka products safely in the usage situations modified or repositioned etc). It must be possible to
shown. get to and from these workplaces via safe access
In all cases, users are obliged to ensure compliance routes!
with national laws, standards and regulations ▪ If you are considering any deviation from the
throughout the entire project and to take appropriate details and instructions given in this booklet, or
additional or alternative workplace safety precau- any application which goes beyond those
tions where necessary. described in the booklet, then revised static cal-
culations must be produced for checking, as well
as supplementary assembly instructions.
Hazard assessment
▪ The customer is responsible for drawing up, docu- Regulations; industrial safety
menting, implementing and continually updating a
hazard assessment at every job-site. ▪ All laws, Standards, industrial safety regulations and
This booklet serves as the basis for the site-specific other safety rules applying to the utilisation of our
hazard assessment, and for the instructions given to products in the country and/or region in which you
users on how to prepare and utilise the system. It are operating must be observed at all times.
does not substitute for these, however.
▪ If a person or object falls against, or into, the side-
guard component and/or any of its accessories, the
component affected may only continue in use after it
has been inspected and passed by an expert.

4 © by Doka GmbH, A-3300 Amstetten 999800802 - 02/2022


User Information Doka floor prop Eurex 20 top 700 Introduction

Rules applying during all phases of Assembly


the assignment
▪ The equipment/system must be inspected by the
customer before use, to ensure that it is in an accept-
▪ The customer must ensure that this product is able condition. Steps must be taken to exclude com-
erected and dismantled, reset and generally used for ponents that are damaged, deformed, or weakened
its intended purpose in accordance with the applica- due to wear, corrosion or rot (e.g. fungal decay).
ble laws, standards and rules, under the direction
and supervision of suitably skilled persons.
▪ Using our safety and formwork systems together
with those of other manufacturers can create risks
These persons' mental and physical capacity must
that may lead to injury and damage to property. This
not in any way be impaired by alcohol, medicines or
requires separate verification by the user.
drugs.
▪ Doka products are technical working appliances ▪ The equipment/system must be assembled and
erected in accordance with the applicable laws,
which are intended for industrial / commercial use
standards and rules by trained customer personnel
only, always in accordance with the respective Doka
whilst maintaining any applicable safety inspections
User Information booklets or other technical docu-
that may be required.
mentation authored by Doka.
▪ The stability and load-bearing capacity of all compo- ▪ It is not permitted to modify Doka products; such
modifications constitute a safety risk.
nents and units must be ensured during all phases of
the construction work!
▪ Do not step on or apply strain to cantilevers, clo- Closing the formwork
sures, etc. until suitable measures to ensure their
stability have been correctly implemented (e.g. by
tie-backs). ▪ Doka products and systems must be set up so that
▪ Strict attention to and compliance with the functional all loads acting upon them are safely transferred!
instructions, safety instructions and load specifica-
tions are required. Non-compliance can cause acci-
dents and severe injury (risk of fatality) and consid-
Pouring
erable damage to property.
▪ Sources of fire in the vicinity of the formwork are pro- ▪ Do not exceed the permitted fresh-concrete pres-
hibited. Heaters are permissible only when used cor- sures. Over-high pouring rates overload the form-
rectly and situated a correspondingly safe distance work, cause greater deflection and risk breakage.
from the formwork.
▪ Customer must give due consideration to any and all
Stripping the formwork
effects of the weather on the equipment and regards
both its use and storage (e.g. slippery surfaces, risk
of slipping, effects of the wind, etc.) and implement ▪ Do not strip out the formwork until the concrete has
appropriate precautionary measures to secure the reached sufficient strength and the person in charge
equipment and surrounding areas and to protect has given the order for the formwork to be stripped
workers. out!
▪ All connections must be checked at regular intervals ▪ When stripping out the formwork, never use the
to ensure that they are secure and in full working crane to break concrete cohesion. Use suitable tools
order. such as timber wedges, special pry-bars or system
In particular threaded connections and wedged con- features such as Framax stripping corners.
nections have to be checked and retightened as nec- ▪ When stripping out the formwork, do not endanger
essary in accordance with activity on the jobsite and the stability of any part of the structure, or of any
especially after out-of-the-ordinary occurrences (e.g. scaffolding, platforms or formwork that is still in
after a storm). place!
▪ It is strictly forbidden to weld Doka products – in par-
ticular anchoring/tying components, suspension
components, connector components and castings
etc. – or otherwise subject them to heating.
Welding causes serious change in the microstruc-
ture of the materials from which these components
are made. This leads to a dramatic drop in the failure
load, representing a very great risk to safety.
It is permissible to cut individual tie rods to length
with metal cutting discs (introduction of heat at the
end of the rod only), but it is important to ensure that
flying sparks do not heat and thus damage other tie
rods.
The only articles which are allowed to be welded are
those for which the Doka literature expressly points
out that welding is permitted.

999800802 - 02/2022 © by Doka GmbH, A-3300 Amstetten 5


Introduction User Information Doka floor prop Eurex 20 top 700

Transporting, stacking and storing Symbols used


▪ Observe all country-specific regulations applying to The following symbols are used in this document:
the handling of formwork and scaffolding. For system
formwork the Doka slinging means stated in this DANGER
booklet must be used – this is a mandatory require- This is a notifier drawing attention to an
ment. extremely dangerous situation in which non-
If the type of sling is not specified in this document, compliance with this notifier will lead to death
the customer must use slinging means that are suit- or severe, irreversible injury.
able for the application envisaged and that comply
with the regulations.
▪ When lifting, always make sure that the unit to be WARNING
lifted and its individual parts can absorb the forces This is a notifier drawing attention to a dan-
that occur. gerous situation in which non-compliance
▪ Remove loose parts or secure them so that they can- with this notifier can lead to death or severe,
not slip out of position and drop. irreversible injury.
▪ When lifting formwork or formwork accessories with
a crane, no persons must be carried along, e.g. on
working platforms or in multi-trip packaging. CAUTION
▪ All components must be stored safely, following all This is a notifier drawing attention to a dan-
the special Doka instructions given in the relevant gerous situation in which non-compliance
sections of this document! with this notifier can lead to slight, reversible
injury.
Maintenance
NOTICE
▪ Only original Doka components may be used as This is a notifier drawing attention to a situa-
spare parts. Repairs may only be carried out by the
tion in which non-compliance with this noti-
manufacturer or authorised facilities.
fier can lead to malfunctions or damage to
property.
Miscellaneous
The weights as stated are averages for new material; Instruction
actual weights can differ, depending on material toler- Indicates that actions have to be performed
ances. Dirt accretions, moisture saturation, etc. can by the user.
also affect weight.
We reserve the right to make alterations in the interests
of technical progress. Sight-check
Indicates that you need to do a sight-check
to make sure that necessary actions have
been carried out.

Tip
Points out useful practical tips.

Reference
Cross-references other documents.

6 © by Doka GmbH, A-3300 Amstetten 999800802 - 02/2022


User Information Doka floor prop Eurex 20 top 700 Introduction

Services
Support in every stage of the project High performance, in all stages of the project

▪ Project success assured by products and services


from a single source.
▪ Competent support from planning through to assem-
bly directly on site. Operations Construction Project close-
Tender
scheduling work out
Project assistance from start to finish
Every single project is unique and calls for individual- Engineering
ised solutions. When it comes to the forming opera- ▪ Execution planning
tions, the Doka team can help you with its consulting, ▪ Cycle planning
planning and ancillary services in the field, enabling ▪ Structure modelling/3D-planning
you to carry out your project effectively, safely and reli- ▪ Assembly drawings
ably. Doka assists you with individual consulting ser- ▪ Statics calculation
vices and customised training courses. ▪ Concremote

Efficient planning for a safe project sequence Consulting and training

Efficient formwork solutions can only be developed


▪ Project processing on-site

economically if there is an understanding of project


▪ Formwork instructor

requirements and construction processes. This under-


▪ Training & consulting

standing is the basis of Doka engineering services.


Process optimisation

Optimise construction workflows with Doka


▪ Concremote
▪ myDoka
Doka offers special tools that help you in designing ▪ Planning software
transparent processes. This is the way to speed up ▪ Yard management
pouring processes, optimise inventories and create
more efficient formwork planning processes. Pre-assembly and assembly
▪ Pre-assembly service
Custom formwork and on-site assembly ▪ Pre-assembly on site service
To complement its system formwork range, Doka
offers customised formwork units. And specially Logistics
trained personnel assemble load-bearing towers and ▪ Organisation of transport & freight
formwork on site.
Rental and reconditioning service
Just-in-time availability ▪ Rental service
Formwork availability is a crucial factor in realising ▪ Formwork returns
your project on time and on budget. The worldwide ▪ Reconditioning & service fixed rates
logistics network puts the necessary formwork quanti-
ties on site at the agreed time.
upbeat construction
digital services for higher productivity
Rental and reconditioning service
From planning through to completion - with
The formwork material needed for any particular pro-
upbeat construction we’ll be moving construc-
ject can be rented from Doka’s high-performing rental
tion forward and upping the beat for more pro-
park. Doka Reconditioning cleans and overhauls both
ductive building with all our digital services.
client-owned equipment and Doka rental equipment.
Our digital portfolio covers the entire construc-
tion process and is being extended all the time.
To find out more about our specially developed
solutions go to doka.com/upbeatconstruction.

999800802 - 02/2022 © by Doka GmbH, A-3300 Amstetten 7


Product description User Information Doka floor prop Eurex 20 top 700

Product description

Doka floor prop Eurex 20 top 700 ▪ Quick connection:


Head adapters of various types can be attached in a
crane-handling-safe manner with the spring-locked
The Doka floor prop Eurex 20 top 700 is an adjustable connecting pin
telescopic steel construction prop that conforms to EN
1065. It is intended to be used as a vertical prop for
▪ Drop-out latch:
For safety reasons, Doka props have latches to pre-
temporary works equipment.
vent the inner tube sliding out of the outer tube.
A ▪ special thread geometry, which makes the prop eas-
ier to release even when it is under high load
▪ When the prop is pushed in all the way, it still leaves
B a clear 10 cm gap so that the operator's hands are
not trapped.
C ▪ elbowed fastening clamps, reducing the risk of injury
D and making the props easier to operate
E
F ▪ Galvanised, long-life constructional design

Removable folding tripod 1.20m

CAUTION
Is not substitute for bracing on supporting sys-
tems.
➤ Only use for holding floor props upright!
G The Removable folding tripod 1.20m is mainly intended
to hold Doka floor props Eurex upright while they are
being set up (see table below).
The pivot-mounted legs facilitate positioning close to
walls and in corners, or elsewhere if space is at a pre-
mium.
Props and tripods have to be repositioned separately.
Setup:
➤ Open the clamping lever.

H A

A Head-plate
B Inner tube
C Fastening clamp
D Adjusting nut
E Toggle lever
F Rating label ➤ Open the legs of the tripod and place it in position.
G Outer tube ➤ Slip the floor prop into the tripod.
H Baseplate ➤ Close the clamping lever to secure the assembly.
Closing the clamping lever with the legs folded in
The main features: secures the legs in this position for transport and stor-
▪ DIB (German Institute of Construction Engineering) age.
approval n° Z-8.311-905
▪ EN 1065-compliant floor prop Possible clamping ranges:
▪ high load-bearing capacity Doka floor prop Outer tube Inner tube
- see the section headed 'Permitted carrying Eurex 20 top 400 X —
capacity' Eurex 20 top 550 X X
Eurex 20 top 700 X X
▪ numbered pegging holes, for easier height adjust-
Eurex 30 top 350 X —
ment
Eurex 30 top 400 X —
Eurex 30 top 450 X X
Eurex 30 top 550 X X
Eurex 60 550 — X
98017-200-01

8 © by Doka GmbH, A-3300 Amstetten 999800802 - 02/2022


User Information Doka floor prop Eurex 20 top 700 Instructions for assembly and use (Method statement)

Instructions for assembly and use (Method statement)

Adaptation at edges of Doka floor Doka floor prop Eurex 20 700 as


tables temporary shoring

For details of the permitted load-bearing capacities, For details of the permitted load-bearing capacities,
see the section headed "Permitted carrying capacity". see the section headed "Permitted carrying capacity".

Follow the directions in the "Dokamatic table" Practical example


User Information booklet!

Practical example

98008-201-01

Using on Doka floor tables


98008-200-01

a ... Extended length max. 7.00 m


WARNING
Using with Dokaflex 1-2-4 and Doka ➤ It is not permitted to use Eurex floor props
20 top 700 on Doka tableforms.
Xtra ➤ For these heights, Eurex 20 top 550 floor
props must be used in conjunction with
Use of the 'Eurex 20 top 700 floor prop' with Dokaflex Dokamatic table frames 1.50m.
1-2-4 and Doka Xtra is permitted up to a max. extension
length of 6.00 m.
Using with Floor-prop extension
In applications of this nature, it is advisable to
use a Doka load-bearing tower on account of 0.50m
the low weight of the individual components
and the additional strength.
WARNING
Follow the directions in the “Dokaflex 1-2-4” ➤ It is not allowed to use the 'Eurex 20 top 700
and "Doka Xtra” User Information booklets! floor prop' with the Floor prop extension
0.50m, and the products' safety-first design
in any case makes this impossible.
➤ Alterations or modifications are strictly for-
bidden!

999800802 - 02/2022 © by Doka GmbH, A-3300 Amstetten 9


Instructions for assembly and use (Method statement) User Information Doka floor prop Eurex 20 top 700

Setup and removal ➤ Secure a rope underneath the head-plate and pull on
the rope to extend the floor prop.

NOTICE
For manual transport, grip the floor prop only
by the outer and inner tubes.

9720-006
Setting up with tripod
➤ Set up Removable folding tripod 1.20m.
➤ With one foot against the baseplate to prevent slip-
page, raise the floor prop upright.

98008-204-01

➤ Roughly adjust the height of the floor prop, using the


fastening clamp.
The pegging holes are all numbered, which makes it
98008-202-01
easier to adjust the props to the same height.

CAUTION
➤ Put the floor prop into the Removable folding tripod
1.20m and fix it in place with the clamping lever. ➤ If you do transport the floor props with the
Before stepping onto the formwork, check again to lowering heads still attached, you must
make sure that the props have been correctly fixed secure these with a Spring locked connect-
in the tripods. ing pin 16 mm to prevent them dropping out.
This is particularly important when they are
transported in the horizontal.
➤ Insert a Lowering head H20 into the floor prop.
Leave the correct amount of lowering play (a)!
Clearance a between wedge and head-plate:
6 cm

The lowering heads under edge primary


beams must all be turned to the position in
which the wedges can be knocked open when
98008-203-01 the formwork is stripped.

NOTICE
➤ Observe the safety rules of the working
scaffold!
a

➤ Set up the working scaffold.

98008-205-02

10 © by Doka GmbH, A-3300 Amstetten 999800802 - 02/2022


User Information Doka floor prop Eurex 20 top 700 Instructions for assembly and use (Method statement)

➤ With the prop upright, use the adjusting nut for preci- Bracing
sion adjustment.

Variant 1: Bracing clamp B with planks

NOTICE
Always hammer in the wedge from top to bot-
tom!

Planks can be attached to the floor props as


diagonal braces, using the Bracing clamp B.

98008-205-01

▪ The fastening clamp (A) has to be pushed 9776-201-01


all the way into the floor prop.
▪ Adjusting nut (B) has to be tightened into
contact with the fastening clamp.
Plank fastened to outer Plank fastened to inner
tube tube
A

B C B
C B
98017-202-01

Setting up without tripod

98008-206-01
98008-207-01

A A
➤ To prevent toppling, use Supporting head H20 DF to
secure intermediate props for floor formwork (see
the User Information booklets for Dokaflex 1-2-4 or
Doka-Xtra, as applicable). Recommended dimensions of plank for the Doka
➤ When using props as temporary reshoring, press floor prop Eurex 20 top 700
them sufficiently tightly against the floor structure to Plank dimen-
α α
ensure that they cannot topple. sions
Outer tube Inner tube
[cm]
2.4 x 10 ≥ 14° ≥ 8°
Removal 3 x 10 ≥ 14° ≥ 10°
2.4 x 12 ≥ 24° ≥ 18°
➤ Removal is the reverse of the setup procedure. 3 x 12 ≥ 24° ≥ 20°
Planks of these sizes can also be connected to the Dokamatic table
frame (see Practical example).

999800802 - 02/2022 © by Doka GmbH, A-3300 Amstetten 11


Instructions for assembly and use (Method statement) User Information Doka floor prop Eurex 20 top 700

Practical examples

Planks fastened to Dokamatic table frame 1.50m

D C

A
B

98008-208-02

Planks fastened to tableform superstructure

98008-208-01

A Bracing clamp B
B Bracing plank (site-provided)
C Doka floor prop Eurex 20 top 700
D Dokamatic table frame 1.50m

12 © by Doka GmbH, A-3300 Amstetten 999800802 - 02/2022


User Information Doka floor prop Eurex 20 top 700 Instructions for assembly and use (Method statement)

Variant 2: Screw-on couplers 48mm 135 with Practical examples


scaffolding tubes
4-way head or Lowering head with 2 Doka beams
NOTICE H20
Before fitting the bracing, make sure that the
holes in the floor prop and the 4-way head or
Lowering head are correctly aligned (see
Practical examples)!

Plank fastened to outer Plank fastened to inner


tube tube

B
B C
A

98008-212-01
C D
B
A
C
98008-210-01 98008-209-01 A Screw-on coupler 48mm 135
B Scaffold tube 48.3mm
A Screw-on coupler 48mm 135
C Doka floor prop Eurex 20 top 700
B Scaffold tube 48.3mm
D Transition swivel coupler 48/76mm
C Doka floor prop Eurex 20 top 700

4-way head or Lowering head with 1 Doka beam


NOTICE H20
▪ The 4-way head or Lowering head must be
fixed onto the floor prop before the screw-on
couplers are mounted.
▪ If the screw-on couplers are mounted first,
this makes it impossible to retract the floor
prop all the way.
▪ Carefully screw on the screw-on couplers,
so as not to damage the floor prop.
A
E
B

C
D 98008-211-01

A Screw-on coupler 48mm 135


B Scaffold tube 48.3mm
C Doka floor prop Eurex 20 top 700
D Transition swivel coupler 48/76mm
E Swivel coupler 48mm

Note:
If there is 1 Doka beam H20 resting on the 4-way head
or Lowering head, then an extra scaffolding tube must
be attached so that the floor prop can be braced to the
table frame.

999800802 - 02/2022 © by Doka GmbH, A-3300 Amstetten 13


Possible incorrect usages User Information Doka floor prop Eurex 20 top 700

Possible incorrect usages


Do not use as barrier to close off openings.
WARNING
➤ The uses illustrated below are prohibited, as
are other, similar uses!

Use only perfectly upright and Baseplate must make full-sur-


plumb. face contact with the ground.

9790-209-01

9790-205-01 9790-207-01

Place only on ground of adequate load-bearing strength.


9790-201-01
9790-202-01

Do not attempt to use floor props Do not use anchor rods or


one on top of another. lengths of rebar as substitutes for
the pegs.

9790-212-01
9790-200-01

9790-206-01

Do not use to support formwork Do not use as trenching braces.


panels.
9790-203-01

9790-204-01

14 © by Doka GmbH, A-3300 Amstetten 999800802 - 02/2022


User Information Doka floor prop Eurex 20 top 700 Technical condition

Technical condition
The following quality criteria define the statically permit- Threads
ted degree of damage or weakening.
Use is prohibited if the damage is more extensive. ▪ must be greased over entire length and action must
be smooth.
Outer tube - inner tube
Inner tube

Head plate or baseplate bent out of shape ▪ When the inner tube is rotated inside the outer tube
so that the U-bolt fixing-holes of both tubes are lined
▪ a max. 1 mm outward and up, it must be possible to fully extend and retract the
inner tube.
▪ b max. 3 mm inward is permissible
a
Widening

▪ of the pegging holes in the inner tube is permissible


up to 2 mm.

9790-208-07

9790-208-04
9790-208-01

Cracks in welds

▪ not permissible
9790-208-02

999800802 - 02/2022 © by Doka GmbH, A-3300 Amstetten 15


Permitted carrying capacity User Information Doka floor prop Eurex 20 top 700

Permitted carrying capacity

Used as free (non-system-dependent) Doka floor prop Eurex 20 700 as


construction props temporary shoring

Permitted capacities [kN] as a function of the exten- Permitted load-bearing capacity when used as tempo-
sion length and the position of the outer tube rary reshores (props restrained): 35 kN up to 7.00 m
(as per General Building-Inspectorate Approval prop length (with 2 Doka beams H20 as packers, up to
Z-8.311-905) 6.70 m prop length).
Eurex 20 top 700
Position of
Bottom Top
outer tube*) NOTICE
C70 C70 Prop category The increased load-bearing capacity applies
Prop length [m] D70 D70 to EN 1065 only if the prop is set up with head-plate or, as
7.0 20.6 21.7 applicable, baseplate directly against the
6.9 21.5 22.6 underside of the slab (2 Doka beams H20 or a
6.8 22.4 23.6 strip of formwork sheeting as packer permissi-
6.7 23.3 24.5 ble).
6.6 24.3 25.5
6.5 25.1 26.3 With increased load-bearing capacity
6.4 26.3 27.5
6.3 27.4 28.6
6.2 28.5 29.7 A
C
6.1 29.7 30.9
6.0 30.7 32.0
B B
5.9 32.1 33.9
5.8 33.5 35.7
5.7 35.1
5.6 36.5
5.5
5.4
5.3
5.2
5.1
5.0
4.9
4.8 36.7
4.7 36.7
98008-201-01 98008-201-01
4.6
4.5
4.4 Without increased load-bearing capacity
4.3
4.2
4.1 C
4.0
3.9 B

*) Position of outer tube


Bottom Top

98008-201-01
For details of the permitted capacities of the
A Formwork sheet
Doka floor props when used with the Dokaflex
B Doka beam H20
and Doka Xtra systems, please refer to the rel-
evant User Information booklets. C Lowering head H20 or 4-way head H20

16 © by Doka GmbH, A-3300 Amstetten 999800802 - 02/2022


User Information Doka floor prop Eurex 20 top 700 Permitted carrying capacity

999800802 - 02/2022 © by Doka GmbH, A-3300 Amstetten 17


Transporting, stacking and storing User Information Doka floor prop Eurex 20 top 700

Transporting, stacking and storing

Loading capacity Using Doka stacking pallets as transport


devices
Multi-trip trans- Lifting by crane
Stacking pallet
Doka floor prop port box
1.55x0.85m
1.20x0.80m
Eurex 20 top 150 — 40 NOTICE
Eurex 20 top 250, 300 and 350 40 — ▪ Multi-trip packaging items may only be lifted
Eurex 20 top 400 and 550 30 — one at a time.
Eurex 20 top 700 20 —
▪ Use a suitable crane suspension tackle
Eurex 30 top 250 and 300 40 —
(e.g. Doka 4-part chain 3.20m).
Eurex 30 top 350, 400 and 450 30 —
Do not exceed the permitted load-bearing
Eurex 30 top 550 24 —
capacity.
▪ Load the items centrically.
Doka stacking pallet 1.55x0.85m and ▪ Fasten the load to the stacking pallet so that
it cannot slide or tip out.
1.20x0.80m ▪ Spread angle β max. 30°!
Storage and transport devices for long items.

= =
a
92815-224-01

a
Doka stacking pallet 1.55x0.85m max. 4.5 m
Max. carrying capacity: 1100 kg (2420 lbs) Doka stacking pallet 1.20x0.80m max. 3.0 m
Permitted imposed load: 5900 kg (12980 lbs)
Repositioning by forklift truck or pallet stacking
truck
Using Doka stacking pallets as storage units
NOTICE
Max. n° of units on top of one another ▪ Load the items centrically.
Outdoors (on the site) Indoors ▪ Fasten the load to the stacking pallet so that
Floor gradients up to 3% Floor gradients up to 1% it cannot slide or tip out.
2 6
It is not allowed to stack empty
pallets on top of one another! Bolt-on castor set B
NOTICE
The Bolt-on caster set B turns the stacking pallet into a
▪ Stacked multi-trip boxes or pallets must fast and manoeuvrable transport device.
have the heaviest boxes at the bottom and
the lightest at the top. Suitable for drive-through access openings > 90 cm.
▪ How to use with Bolt-on castor set B:
- Always apply the fixing brake when the
container is 'parked'.
- When Doka stacking pallets are
stacked, the bottom pallet must NOT be
one with a bolt-on castor set mounted to The Bolt-on caster set B can be mounted to the follow-
it. ing multi-trip packaging items:
▪ Doka accessory box
▪ Doka stacking pallets
▪ Protective barrier Z pallet
Follow the directions in the 'Bolt-on castor set
B' Operating Instructions!

18 © by Doka GmbH, A-3300 Amstetten 999800802 - 02/2022


User Information Doka floor prop Eurex 20 top 700 Article list

[kg] Article N° [kg] Article N°


ArticleN°
Article
[kg] list

Doka floor prop Eurex 20 top 700 48.0 586139000 Swivel coupler 48mm 1.5 582560000
Doka-Deckenstütze Eurex 20 top 700 Drehkupplung 48mm
Galvanised Galvanised
Length: 383 - 700 cm Width-across: 22 mm
Follow the directions in the "Fitting
instructions"!

Transition swivel coupler 48/76mm 1.9 582563000


Übergangsdrehkupplung 48/76mm
Galvanised
Width-across: 22 mm
Follow the directions in the "Fitting
instructions"!

Doka stacking pallet 1.55x0.85m 41.0 586151000


Doka-Stapelpalette 1,55x0,85m
Galvanised
Height: 77 cm

Removable folding tripod 1.20m 20.7 586145000 Bolt-on castor set B 33.6 586168000
Stützbein 1,20m Anklemm-Radsatz B
Galvanised Painted blue
Height: 120 cm
Delivery condition: folded closed

Bracing clamp B 1.4 586195000


Verschwertungsklammer B
Painted blue
Length: 36 cm

Screw-on coupler 48mm 135 0.92 582892000


Anschraubkupplung 48mm 135
Galvanised
Width-across: 22 mm
Follow the directions in the "Fitting
instructions"!

Scaffold tube 48.3mm 0.50m 1.7 682026000


Scaffold tube 48.3mm 1.00m 3.6 682014000
Scaffold tube 48.3mm 1.50m 5.4 682015000
Scaffold tube 48.3mm 2.00m 7.2 682016000
Scaffold tube 48.3mm 2.50m 9.0 682017000
Scaffold tube 48.3mm 3.00m 10.8 682018000
Scaffold tube 48.3mm 3.50m 12.6 682019000
Scaffold tube 48.3mm 4.00m 14.4 682021000
Scaffold tube 48.3mm 4.50m 16.2 682022000
Scaffold tube 48.3mm 5.00m 18.0 682023000
Scaffold tube 48.3mm 5.50m 19.8 682024000
Scaffold tube 48.3mm 6.00m 21.6 682025000
Scaffold tube 48.3mm .....m 3.6 682001000
Gerüstrohr 48,3mm
Galvanised

999800802 - 02/2022 © by Doka GmbH, A-3300 Amstetten 19


Near to you, worldwide

Doka is one of the world leaders in developing, manu- technical support are provided swiftly and profession-
facturing and distributing formwork technology for use in ally.
all fields of the construction sector. An enterprise forming part of the Umdasch Group, the
With more than 160 sales and logistics facilities in over Doka Group employs a worldwide workforce of more
70 countries, the Doka Group has a highly efficient dis- than 6000.
tribution network which ensures that equipment and

www.doka.com/floor-props

Doka GmbH | Josef Umdasch Platz 1 | 3300 Amstetten | Austria | T +43 7472 605-0 | F +43 7472 66430 | [email protected] | www.doka.com 999800802 - 02/2022