STM Final
STM Final
INTRODUCTION
What is testing?
Testing consumes at least half of the time and work required to produce a functional program.
o MYTH: Good programmers write code without bugs. (It’s wrong!!!)
o History says that even well written programs still have 1-3 bugs per hundredstatements.
Phases in a tester's mental life can be categorized into the following 5 phases:
1. Phase 0: (Until 1956: Debugging Oriented) There is no difference between testing and
debugging. Phase 0 thinking was the norm in early days of software development till testing
emerged as a discipline.
2. Phase 1: (1957-1978: Demonstration Oriented) the purpose of testing here is to show that
software works. Highlighted during the late 1970s. This failed because the probability of
showing that software works 'decreases' as testing increases. I.e. the more you test, the more
likely you will find a bug.
3. Phase 2: (1979-1982: Destruction Oriented) the purpose of testing is to show that
software doesn’t work. This also failed because the software will never get released as you will
find one bug or the other. Also, a bug corrected may also lead to another bug.
4. Phase 3: (1983-1987: Evaluation Oriented) the purpose of testing is not to prove anything
but to reduce the perceived risk of not working to an acceptable value (Statistical Quality
Control). Notion is that testing does improve the product to the extent that testing catches bugs
and to the extent that those bugs are fixed. The product is released when the confidence
on that product is high enough. (Note: This is applied to large software products with millions
of code and years of use.)
5. Phase 4: (1988-2000: Prevention Oriented) Testability is the factor considered here. One
reason is to reduce the labor of testing. Other reason is to check the testable and non-testable
code. Testable code has fewer bugs than the code that's hard to test. Identifying the testing
techniques to test the code is the main key here.
Test Design:
We know that the software code must be designed and tested, but many appear to be unaware
that tests themselves must be designed and tested. Tests should be properly designed and tested
before applying it to the actual code.
There are approaches other than testing to create better software. Methods other than testing
include:
1. Inspection Methods: Methods like walkthroughs, desk checking, formal inspections and
code reading appear to be as effective as testing but the bugs caught don’t completely
overlap.
2. Design Style: While designing the software itself, adopting stylistic objectives such as
testability, openness and clarity can do much to prevent bugs.
3. Static Analysis Methods: Includes formal analysis of source code during compilation. In
earlier days, it is a routine job of the programmer to do that. Now, the compilers have taken
over that job.
4. Languages: The source language can help reduce certain kinds of bugs. Programmers find
new bugs while using new languages.
Testing Debugging
Testing starts with known conditions, Debugging starts from possibly unknown
uses predefined procedures and has initial conditions and the end cannot be
predictable outcomes. predicted except statistically.
Testing can and should be planned, Procedure and duration of debugging cannot
designed and scheduled. be so constrained.
Testing is a demonstration of error or
Debugging is a deductive process.
apparent correctness.
Debugging is the programmer's vindication
Testing proves a programmer's failure.
(Justification).
Testing, as executes, should strive to be
Debugging demands intuitive leaps,
predictable, dull, constrained, rigid and
experimentation and freedom.
inhuman.
Much testing can be done without Debugging is impossible without detailed
design knowledge. design knowledge.
Testing can often be done by an
Debugging must be done by an insider.
outsider.
Much of test execution and design can
Automated debugging is still a dream.
be automated.
o Test designer is the person who designs the tests where as the tester is the one
actually tests the code. During functional testing, the designer and tester are
probably different persons. During unit testing, the tester and the programmer
merge into one person.
o Tests designed and executed by the software designers are by nature biased
Most software is written and used by the same organization. Unfortunately, this situation is
dishonest because it clouds accountability. If there is no separation between builder and
buyer, there can be no accountability.
The different roles / users in a system include:
1. Builder: Who designs the system and is accountable to the buyer.
2. Buyer: Who pays for the system in the hope of profits from providing services?
3. User: Ultimate beneficiary or victim of the system. The user's interests are also
guarded by.
4. Tester: Who is dedicated to the builder's destruction?
5. Operator: Who has to live with the builders' mistakes, the buyers' murky (unclear)
specifications, testers' oversights and the users' complaints?
MODEL FOR TESTING:
o Tests are formal procedures, Inputs must be prepared, Outcomes should predict, tests
should be documented, commands need to be executed, and results are to be
observed. All these errors are subjected to error
o We do three distinct kinds of testing on a typical software system. They are:
1. Unit / Component Testing: A Unit is the smallest testable piece of
software that can be compiled, assembled, linked, loaded etc. A unit is
usually the work of one programmer and consists of several hundred or fewer
lines of code. Unit Testing is the testing we do to show that the unit does not
satisfy its functional specification or that its implementation structure does
not match the intended design structure. A Component is an integrated
aggregate of one or more units. Component Testing is the testing we do to
show that the component does not satisfy its functional
specification or that its implementation structure does not match the
intended design structure.
TAXONOMY OF BUGS:
There is no universally correct way categorize bugs. The taxonomy is not rigid.
A given bug can be put into one or another category depending on its history and the
programmer's state of mind.
The major categories are: (1) Requirements, Features and Functionality Bugs (2)
Structural Bugs (3) Data Bugs (4) Coding Bugs (5) Interface, Integration and System
Bugs (6) Test and Test Design Bugs.
2. Logic Bugs:
Bugs in logic, especially those related to misunderstanding how case statements and logic
operators behave singly and combinations
Also includes evaluation of boolean expressions in deeply nested IF-THEN-ELSE
constructs.
If the bugs are parts of logical (i.e. boolean) processing not related to control flow, they
are characterized as processing bugs.
If the bugs are parts of a logical expression (i.e. control-flow statement) which is used to
direct the control flow, then they are categorized as control-flow bugs.
3. Processing Bugs:
Processing bugs include arithmetic bugs, algebraic, mathematical function evaluation,
algorithm selection and general processing.
Examples of Processing bugs include: Incorrect conversion from one data representation
to other, ignoring overflow, improper use of greater-than-or-equal etc
Although these bugs are frequent (12%), they tend to be caught in good unit testing.
4. Initialization Bugs:
Initialization bugs are common. Initialization bugs can be improper and superfluous.
Superfluous bugs are generally less harmful but can affectperformance.
Typical initialization bugs include: Forgetting to initialize the variables before first use,
assuming that they are initialized elsewhere, initializing to the wrong format, representation
or type etc
Explicit declaration of all variables, as in Pascal, can reduce some initialization problems.
✓ Data bugs:
Data bugs include all bugs that arise from the specification of data objects, their formats,
the number of such objects, and their initial values.
Data Bugs are at least as common as bugs in code, but they are often treated as if they did
not exist at all.
Code migrates data: Software is evolving towards programs in which more and more of
the control and processing functions are stored in tables.
Because of this, there is an increasing awareness that bugs in code are only half the battle
and the data problems should be given equal attention.
Dynamic Data Vs Static data:
Dynamic data are transitory. Whatever their purpose their lifetime is relatively short,
typically the processing time of one transaction. A storage object may be used to hold
dynamic data of different types, with different formats, attributesand residues.
Dynamic data bugs are due to leftover garbage in a shared resource. This can be handled in
one of the three ways: (1) Clean up after the use by the user (2) Common Cleanup by the
resource manager (3) No Clean up
Static Data are fixed in form and content. They appear in the source code or database directly
or indirectly, for example a number, a string of characters, or a bitpattern.
Compile time processing will solve the bugs caused by static data.
✓ Coding bugs:
Coding errors of all kinds can create any of the other kind of bugs.
Syntax errors are generally not important in the scheme of things if the source language
translator has adequate syntax checking.
If a program has many syntax errors, then we should expect many logic and codingbugs.
The documentation bugs are also considered as coding bugs which may mislead the
maintenance programmers.
1. External Interfaces:
The external interfaces are the means used to communicate with theworld.
These include devices, actuators, sensors, input terminals, printers, and communication
lines.
The primary design criterion for an interface with outside world should berobustness.
All external interfaces, human or machine should employ a protocol. The protocol may
be wrong or incorrectly implemented.
Other external interface bugs are: invalid timing or sequence assumptions related to
external signals
Misunderstanding external input or output formats.
Insufficient tolerance to bad input data.
2. Internal Interfaces:
Internal interfaces are in principle not different from external interfaces but they are more
controlled.
A best example for internal interfaces is communicating routines.
The external environment is fixed and the system must adapt to it but the internal
environment, which consists of interfaces with other components, can be negotiated.
Internal interfaces have the same problem as external interfaces.
3. Hardware Architecture:
Bugs related to hardware architecture originate mostly from misunderstanding how the
hardware works.
Examples of hardware architecture bugs: address generation error, i/o device operation /
instruction error, waiting too long for a response, incorrect interrupt handling etc.
The remedy for hardware architecture and interface problems is twofold: (1) Good
Programming and Testing (2) Centralization of hardware interface software in programs
written by hardware interface specialists.
5. Software Architecture:
Software architecture bugs are the kind that called - interactive.
Routines can pass unit and integration testing without revealing suchbugs.
Many of them depend on load, and their symptoms emerge only when the system is stressed.
Sample for such bugs: Assumption that there will be no interrupts, Failure to block or un
block interrupts, Assumption that memory and registers were initialized or not initialized etc
Careful integration of modules and subjecting the final system to a stress test are effective
methods for these bugs.
6. Control and Sequence Bugs (Systems Level):
These bugs include: Ignored timing, Assuming that events occur in a specified sequence,
Working on data before all the data have arrived from disc, Waiting for an impossible
combination of prerequisites, Missing, wrong, redundant or superfluous process steps.
The remedy for these bugs is highly structured sequence control.
Specialize, internal, sequence control mechanisms are helpful.
8. Integration Bugs:
Integration bugs are bugs having to do with the integration of, and with the interfaces
between, working and tested components.
These bugs results from inconsistencies or incompatibilities betweencomponents.
The communication methods include data structures, call sequences, registers, semaphores,
and communication links and protocols results in integration bugs.
The integration bugs do not constitute a big bug category (9%) they are expensive category
because they are usually caught late in the game and because they force changes in several
components and/or data structures.
9. System Bugs:
System bugs covering all kinds of bugs that cannot be ascribed to a component or to their
simple interactions, but result from the totality of interactions between many components
such as programs, data, hardware, and the operating systems.
There can be no meaningful system testing until there has been thorough component and
integration testing.
System bugs are infrequent (1.7%) but very important because they are often found only
after the system has been fielded.
1. Test Debugging: The first remedy for test bugs is testing and debugging the tests. Test
debugging, when compared to program debugging, is easier because tests, when properly designed
are simpler than programs and do not have to make concessions to efficiency.
2. Test Quality Assurance: Programmers have the right to ask how quality in independent testing
is monitored.
3. Test Execution Automation: The history of software bug removal and prevention is
indistinguishable from the history of programming automation aids. Assemblers, loaders, compilers
are developed to reduce the incidence of programming and operation errors. Test execution bugs are
virtually eliminated by various test execution automationtools.
4. Test Design Automation: Just as much of software development has been automated, much test
design can be and has been automated. For a given productivity rate, automation reduces the bug
count - be it for software or be it for tests.
Path Testing:
o Path Testing is the name given to a family of test techniques based onjudiciously
selecting a set of test paths through the program.
o If the set of paths are properly chosen then we have achieved some measure of
test thoroughness. For example, pick enough paths to assure that every source
statement has been executed at least once.
o Path testing techniques are the oldest of all structural test techniques.
o Path testing is most applicable to new software for unit testing. It is a structural
technique.
o It requires complete knowledge of the program's structure.
o It is most often used by programmers to unit test their own code.
o The effectiveness of path testing rapidly deteriorates as the size of thesoftware
aggregate under test increases.
2. Decisions:
▪ A decision is a program point at which the control flow can
diverge.
▪ Machine language conditional branch and conditional skip
instructions are examples of decisions.
▪ Most of the decisions are two-way but some are three way
branches in control flow.
3. Case Statements:
▪ A case statement is a multi-way branch or decisions.
▪ Examples of case statement are a jump table in assembly language,
and the PASCAL case statement.
▪ From the point of view of test design, there are no differences
between Decisions and Case Statements
4. Junctions:
▪ A junction is a point in the program where the control flow can
merge.
▪ Examples of junctions are: the target of a jump or skip instruction
in ALP, a label that is a target of GOTO.
Figure 2.1: Flow graph Elements
Notational Evolution:
The control flow graph is simplified representation of the program's structure.The notation
changes made in creation of control flow graphs:
o The process boxes weren't really needed. There is an implied process on every line
joining junctions and decisions.
o We don't need to know the specifics of the decisions, just the fact that there is a branch.
o The specific target label names aren't important-just the fact that they exist. So we can
replace them by simple numbers.
o To understand this, we will go through an example (Figure 2.2) written in a FORTRAN like
programming language called Programming Design Language (PDL). The program's
corresponding flowchart (Figure 2.3) and flowgraph (Figure 2.4) were also provided below
for better understanding.
o The first step in translating the program to a flowchart is shown in Figure 2.3, where we
have the typical one-for-one classical flowchart. Note that complexity has increased, clarity
has decreased, and that we had to add auxiliary labels (LOOP, XX, and YY), which have
no actual program counterpart. In Figure 2.4 we merged the process steps and replaced them
with the single process box.
o We now have a control flow graph. But this representation is still too busy. We simplify the
notation further to achieve Figure 2.5, where for the first time we can really see what the
control flow looks like.
Flowcharts can be
1. Handwritten by the programmer.
2. Automatically produced by a flowcharting program based on a mechanical analysisof
the source code.
3. Semi automatically produced by a flow charting program based in part on structural
analysis of the source code and in part on directions given by theprogrammer.
There are relatively few control flow graph generators.
There are many paths between the entry and exit of a typical routine.
Every decision doubles the number of potential paths. And every loop multiplies the number of
potential paths by the number of different iteration values possible for the loop.
Defining complete testing:
1. Exercise every path from entry to exit.
2. Exercise every statement or instruction at least once.
3. Exercise every branch and case statement, in each direction at least once.
If prescription 1 is followed then 2 and 3 are automatically followed. But it is impractical for
most routines. It can be done for the routines that have no loops, in which it is equivalent to 2
and 3 prescriptions.
EXAMPLE: Here is the correct version.
For X negative, the output is X + A, while for X greater than or equal to zero, the output is X +
2A. Following prescription 2 and executing every statement, but not every branch, would not
reveal the bug in the following incorrect version:
A negative value produces the correct answer. Every statement can be executed, but if the test cases
do not force each branch to be taken, the bug can remain hidden. The next example uses a test based
on executing each branch but does not force the execution of all statements:
The hidden loop around label 100 is not revealed by tests based on prescription 3 alone because no
test forces the execution of statement 100 and the following GOTO statement. Furthermore, label
100 is not flagged by the compiler as an unreferenced label and the subsequent GOTO does not refer
to an undefined label.
A Static Analysis (that is, an analysis based on examining the source code or structure) cannot
determine whether a piece of code is or is not reachable. There could be subroutine calls with
parameters that are subroutine labels, or in the above example there could be a GOTO that
targeted label 100 but could never achieve a value that would send the program to that label.
Only a Dynamic Analysis (that is, an analysis based on the code's behavior while running -
which is to say, to all intents and purposes, testing) can determine whether code is reachable or not
and therefore distinguish between the ideal structure we think we have and the actual, buggy
structure.
Any testing strategy based on paths must at least both exercise every instruction and take
branches in all directions.
A set of tests that does this is not complete in an absolute sense, but it is complete in the sense
that anything less must leave something untested.
So we have explored three different testing criteria or strategies out of a potentially infinite
family of strategies.
LOOPS:
Cases for a single loop: A Single loop can be covered with two cases: Looping and Not looping.
But, experience shows that many loop-related bugs are not discovered by C1+C2. Bugs hide
themselves in corners and congregate at boundaries - in the cases of loops, at or around the
minimum or maximum number of times the loop can be iterated. The minimum number of
iterations is often zero, but it need not be.
Kinds of Loops: There are only three kinds of loops with respect to path testing:
Nested Loops:
The number of tests to be performed on nested loops will be the exponent of the tests
performed on single loops.As we cannot always afford to test all combinations of nested loops'
iterations values. Here's a tactic used to discard some of these values:
1. Start at the inner most loop. Set all the outer loops to their minimum values.
2. Test the minimum, minimum+1, typical, maximum-1 , and maximum for the innermost
loop, while holding the outer loops at their minimum iteration parameter values. Expand
the tests as required for out of range and excluded values.
3. If you've done the outmost loop, GOTO step 5, else move out one loop and set it up as in
step 2 with all other loops set to typical values.
4. Continue outward in this manner until all loops have been covered.
5. Do all the cases for all loops in the nest simultaneously.
Concatenated Loops:
Concatenated loops fall between single and nested loops with respect to test cases. Two loops
are concatenated if it's possible to reach one after exiting the other while still on a path
from entrance to exit.
If the loops cannot be on the same path, then they are not concatenated and can be treated
as individual loops.
▪ Horrible Loops:
A horrible loop is a combination of nested loops, the use of code that jumps into and out of
loops, intersecting loops, hidden loops, and cross connected loops.
Makes iteration value selection for test cases an awesome and ugly task, which is another
reason such structures should be avoided.
PREDICATE: The logical function evaluated at a decision is called Predicate. The direction
taken at a decision depends on the value of decision variable. Some examples are: A>0,
x+y>=90.......
PATH PREDICATE: A predicate associated with a path is called a Path Predicate. For
example, "x is greater than zero", "x+y>=90", "w is either negative or equal to 10 is true" is a
sequence of predicates whose truth values will cause the routine to take a specificpath.
MULTIWAY BRANCHES:
The path taken through a multiway branch such as a computed GOTO's, case statement, or
jump tables cannot be directly expressed in TRUE/FALSE terms.
Although, it is possible to describe such alternatives by using multi valued logic, an
expedient (practical approach) is to express multiway branches as an equivalent set of
if..then..else statements.
For example a three way case statement can be written as: If case=1 DO A1 ELSE (IF
Case=2 DO A2 ELSE DO A3 ENDIF)ENDIF.
INPUTS:
In testing, the word input is not restricted to direct inputs, such as variables in a subroutine call,
but includes all data objects referenced by the routine whose values are fixed prior to entering
it.
For example, inputs in a calling sequence, objects in a data structure, values left in registers, or
any combination of object types.
The input for a particular test is mapped as a one dimensional array called as an Input
Vector.
PREDICATE INTERPRETATION:
The simplest predicate depends only on input variables.
For example if x1,x2 are inputs, the predicate might be x1+x2>=7, given the values of x1
and x2 the direction taken through the decision is based on the predicate is determined at input
time and does not depend on processing.
Another example, assume a predicate x1+y>=0 that along a path prior to reaching this
predicate we had the assignment statement y=x2+7. although our predicate depends on
processing, we can substitute the symbolic expression for y to obtain an equivalent predicate
x1+x2+7>=0.
The act of symbolic substitution of operations along the path in order to express the
predicate solely in terms of the input vector is called predicate interpretation.
Sometimes the interpretation may depend on the path; forexample,
INPUT X
ON X GOTO A, B, C, ...
A: Z := 7 @ GOTO HEM
B: Z := -7 @ GOTO HEM
C: Z := 0 @ GOTO HEM
.........
HEM: DO SOMETHING
.........
HEN: IF Y + Z > 0 GOTO ELL ELSE GOTO EMM
The predicate interpretation at HEN depends on the path we took through the first multiway
branch. It yields for the three cases respectively, if Y+7>0, Y-7>0, Y>0.
The path predicates are the specific form of the predicates of the decisions along the selected
path after interpretation.
Any set of input values that satisfy all of the conditions of the path predicate expression will
force the routine to the path.
Sometimes a predicate can have an OR in it.
Example:
A: X5 > 0 E: X6 < 0
B: X1 + 3X2 + 17 B: X1 + 3X2 + 17
>= 0 >= 0
C: X3 = 17 C: X3 = 17
D: X4 - X1 >= D: X4 - X1 >=
14X2 14X2
PREDICATE COVERAGE:
Compound Predicate: Predicates of the form A OR B, A AND B and more complicated
Boolean expressions are called as compound predicates.
Sometimes even a simple predicate becomes compound after interpretation. Example: the
predicate if (x=17) whose opposite branch is if x.NE.17 which is equivalent to x>17. Or. X<17.
Predicate coverage is being the achieving of all possible combinations of truth values
corresponding to the selected path have been explored under some test.
As achieving the desired direction at a given decision could still hide bugs in the associated
predicates
TESTING BLINDNESS:
Testing Blindness is a pathological (harmful) situation in which the desired path is achieved
for the wrong reason.
There are three types of Testing Blindness:
Assignment Blindness:
o Assignment blindness occurs when the buggy predicate appears to work correctly
because the specific value chosen for an assignment statement works with both the correct
and incorrect predicate.
o For Example:
Correct Buggy
X = 7 X = 7
........ ........
if Y > 0 if X+Y > 0
then ... then ...
o If the test case sets Y=1 the desired path is taken in either case, but there is still a bug.
Equality Blindness:
o Equality blindness occurs when the path selected by a prior predicate results in a value that
works both for the correct and buggy predicate.
o For Example:
Correct Buggy
if Y = 2 then if Y = 2 then
........ ........
if X+Y > 3 if X > 1
then ... then ...
o The first predicate if y=2 forces the rest of the path, so that for any positive value of x. the
path taken at the second predicate will be the same for the correct and buggyversion.
Self Blindness:
o Self blindness occurs when the buggy predicate is a multiple of the correct predicate and as
a result is indistinguishable along that path.
o For Example:
Correct Buggy
X=A X=A
........ ........
if X-1 > 0 if X+A-2 > 0
then ... then ...
1. The assignment (x=a) makes the predicates multiples of each other, so the direction taken is
the same for the correct and buggy version.
PATH SENSITIZING:
1. This is a workable approach, instead of selecting the paths without considering how to sensitize,
attempt to choose a covering path set that is easy to sensitize and pick hard to sensitize paths
only as you must to achieve coverage.
2. Identify all variables that affect the decision.
3. Classify the predicates as dependent or independent.
4. Start the path selection with un correlated, independent predicates.
5. If coverage has not been achieved using independent uncorrelated predicates, extend the
path set using correlated predicates.
6. If coverage has not been achieved extend the cases to those that involve dependent
predicates.
7. Last, use correlated, dependent predicates.
PATH INSTRUMENTATION:
1. Path instrumentation is what we have to do to confirm that the outcome was achieved by the
intended path.
2. Co-incidental Correctness: The coincidental correctness stands for achieving the desired
outcome for wrong reason.
= 16), yields the same outcome (Y = 2) no matter which case we select. Therefore, the tests
chosen this way will not tell us whether we have achieved coverage. For example, the five
cases could be totally jumbled and still the outcome would be the same. Path
Instrumentation is what we have to do to confirm that the outcome was achieved by the
intended path.
The types of instrumentation methods include:
o Why Single Link Markers aren't enough: Unfortunately, a single link marker may notdo
the trick because links can be chewed by open bugs.
Figure 2.13: Why Single Link Markers aren't enough.
We intended to traverse the ikm path, but because of a rampaging GOTO in the middle of the
m link, we go to process B. If coincidental correctness is against us, the outcomes will be the
same and we won't know about the bug.
Link Counter: A less disruptive (and less informative) instrumentation method is based
on counters. Instead of a unique link name to be pushed into a string when the link is traversed,
we simply increment a link counter. We now confirm that the path length is as expected. The
same problem that led us to double link markers also leads us to double link counters.
UNIT II
TRANSACTION FLOW TESTING AND DATA FLOW TESTING
INTRODUCTION:
USAGE:
o Transaction flows are indispensable for specifying requirements of complicated
systems, especially online systems.
o A big system such as an air traffic control or airline reservation system, has not
hundreds, but thousands of different transaction flows.
o The flows are represented by relatively simple flowgraphs, many of which have a
single straight-through path.
o Loops are infrequent compared to control flowgraphs.
o The most common loop is used to request a retry after user input errors. An ATM
system, for example, allows the user to try, say three times, and will take the card
away the fourth time.
COMPLICATIONS:
o In simple cases, the transactions have a unique identity from the time they're
created to the time they're completed.
o In many systems the transactions can give birth to others, and transactions can
also merge.
o Births: There are three different possible interpretations of the decision symbol,
or nodes with two or more out links. It can be a Decision, Biosis or a Mitosis.
1. Decision: Here the transaction will take one alternative or the other
alternative but not both. (See Figure 3.2 (a))
2. Biosis: Here the incoming transaction gives birth to a new transaction, and
both transaction continue on their separate paths, and the parent retains it
identity. (See Figure 3.2 (b))
3. Mitosis: Here the parent transaction is destroyed and two new transactions
are created.(See Figure 3.2 (c))
Figure 3.2: Nodes with multiple outlinks
Mergers: Transaction flow junction points are potentially as troublesome as transaction flow
splits. There are three types of junctions: (1) Ordinary Junction (2) Absorption (3) Conjugation
1 Ordinary Junction: An ordinary junction which is similar to the junction in a control flow
graph. A transaction can arrive either on one link or the other. (See Figure 3.3 (a))
2 Absorption: In absorption case, the predator transaction absorbs prey transaction. The prey
gone but the predator retains its identity. (See Figure 3.3 (b))
3 Conjugation: In conjugation case, the two parent transactions merge to form a new
daughter. In keeping with the biological flavor this case is called as conjugation.(See Figure
3.3 (c))
PATH SELECTION:
o Select a set of covering paths (c1+c2) using the analogous criteria you used for
structural path testing.
o Select a covering set of paths based on functionally sensible transactions as you
would for control flow graphs.
o Try to find the most tortuous, longest, strangest path from the entry to the exit of
the transaction flow.
PATH SENSITIZATION:
o Most of the normal paths are very easy to sensitize-80% - 95% transaction flow
coverage (c1+c2) is usually easy to achieve.
o The remaining small percentage is often very difficult.
o Sensitization is the act of defining the transaction. If there are sensitization problems
on the easy paths, then bet on either a bug in transaction flows or a design bug.
PATH INSTRUMENTATION:
o Instrumentation plays a bigger role in transaction flow testing than in unit path
testing.
o The information of the path taken for a given transaction must be kept with that
transaction and can be recorded by a central transaction dispatcher or by the
individual processing modules.
o In some systems, such traces are provided by the operating systems or a running log.
BUG ASSUMPTION:
The bug assumption for data-flow testing strategies is that control flow is generally
correct and that something has gone wrong with the software so that data objects are not
available when they should be, or silly things are being done to data objects.
o Also, if there is a control-flow problem, we expect it to have symptoms that can
be detected by data-flow analysis.
o Although we'll be doing data-flow testing, we won't be using data flow graphs as
such. Rather, we'll use an ordinary control flow graph annotated to show what
happens to the data objects of interest at the moment.
1 dd :- probably harmless but suspicious. Why define the object twice without an intervening
usage?
2 dk :- probably a bug. Why define the object without using it?
3 du :- the normal case. The object is defined and then used.
4 kd :- normal situation. An object is killed and then redefined.
5 kk :- harmless but probably buggy. Did you want to be sure it was really killed?
6 ku :- a bug. the object doesnot exist.
7 ud :- usually not a bug because the language permits reassignment at almost anytime.
8 uk :- normal situation.
9 uu :- normal situation.
In addition to the two letter situations, there are six single letter situations.We will use a leading
dash to mean that nothing of interest (d,k,u) occurs prior to the action noted along the entry-exit path
of interest.
A trailing dash to mean that nothing happens after the point of interest to the exit.
They possible anomalies are:
1 -k :- possibly anomalous because from the entrance to this point on the path, the
variable had not been defined. We are killing a variable that does not exist.
2 -d :- okay. This is just the first definition along this path.
3 -u :- possibly anomalous. Not anomalous if the variable is global and has been
previously defined.k- :- not anomalous. The last thing done on this path was to
kill the variable.
4 d- :- possibly anomalous. The variable was defined and not used on this path. But this
could be a global definition.
5 u- :- not anomalous. The variable was used but not killed on this path. Although this
sequence is not anomalous, it signals a frequent kind of bug. If d and k mean dynamic
storage allocation and return respectively, this could be an instance in which a
dynamically allocated object was not returned to the pool after use.
DATA FLOW ANOMALY STATE GRAPH:
Data flow anomaly model prescribes that an object can be in one of four distinct states:
1. K :- undefined, previously killed, doesnot exist
2. D :- defined but not yet used for anything
3. U :- has been used for computation or in predicate
4. A :- anomalous
These capital letters (K, D, U, A) denote the state of the variable and should not be confused
with the program action, denoted by lower case letters.
Unforgiving Data - Flow Anomaly Flow Graph: Unforgiving model, in which once a variable
becomes anomalous it can never return to a state of grace.
Assume that the variable starts in the K state - that is, it has not been defined or does not exist. If an
attempt is made to use it or to kill it (e.g., say that we're talking about opening, closing, and using
files and that 'killing' means closing), the object's state becomes anomalous (state A) and, once it is
anomalous, no action can return the variable to a working state.
If it is defined (d), it goes into the D, or defined but not yet used, state. If it has been defined (D)
and redefined (d) or killed without use (k), it becomes anomalous, while usage (u) brings it to the U
state. If in U, redefinition (d) brings it to D, u keeps it in U, and k kills it.
Forgiving Data - Flow Anomaly Flow Graph: Forgiving model is an alternate model where
redemption (recover) from the anomalous state is possible.
Figure 3.6: Forgiving Data Flow Anomaly State Graph
This graph has three normal and three anomalous states and he considers the kk sequence not to
be anomalous. The difference between this state graph and Figure 3.5 is that redemption is
possible. A proper action from any of the three anomalous states returns the variable to a useful
working state.
The point of showing you this alternative anomaly state graph is to demonstrate that the specifics
of an anomaly depends on such things as language, application, context, or even your frame of
mind. In principle, you must create a new definition of data flow anomaly (e.g., a new state
graph) in each situation. You must at least verify that the anomaly definition behind the theory or
imbedded in a data flow anomaly test tool is appropriate to your situation.
Static analysis is analysis done on source code without actually executing it. For example: source
code syntax error detection is the static analysis result.
Dynamic analysis is done on the fly as the program is being executed and is based on
intermediate values that result from the program's execution. For example: a division by zero
warning is the dynamic result.
If a problem, such as a data flow anomaly, can be detected by static analysis methods, then it
doesn’t belongs in testing - it belongs in the language processor.
There is actually a lot more static analysis for data flow analysis for data flow anomalies going
on in current language processors.
For example, language processors which force variable declarations can detect (-u) and (ku)
anomalies.But still there are many things for which current notions of static analysis are
INADEQUATE.
Why Static Analysis isn't enough? There are many things for which current notions of static
analysis are inadequate. They are:
Dead Variables: Although it is often possible to prove that a variable is dead or alive at a given
point in the program, the general problem is unsolvable.
Arrays: Arrays are problematic in that the array is defined or killed as a single object, but
reference is to specific locations within the array. Array pointers are usually dynamically
calculated, so there's no way to do a static analysis to validate the pointer value. In many
languages, dynamically allocated arrays contain garbage unless explicitly initialized and
therefore, -u anomalies are possible.
Records and Pointers: The array problem and the difficulty with pointers is a special case
of multipart data structures. We have the same problem with records and the pointers to
them. Also, in many applications we create files and their names dynamically and there's no way
to determine, without execution, whether such objects are in the proper state on a given path or,
for that matter, whether they exist at all.
Dynamic Subroutine and Function Names in a Call: subroutine or function name is a dynamic
variable in a call. What is passed, or a combination of subroutine names and data objects, is
constructed on a specific path. There's no way, without executing the path, to determine whether
the call is correct or not.
False Anomalies: Anomalies are specific to paths. Even a "clear bug" such as ku may not be a
bug if the path along which the anomaly exist is unachievable. Such "anomalies" are false
anomalies. Unfortunately, the problem of determining whether a path is or is not achievable
is unsolvable.
How often do we define or create data objects at an interrupt level so that they can be
processed by a lower-priority routine? Interrupts can make the "correct" anomalous and the
"anomalous" correct. True concurrency (as in an MIMD machine) and pseudo concurrency
(as in multiprocessing) systems can do the same to us. Much of integration and system
testing is aimed at detecting data-flow anomalies that cannot be detected in the context of a
single routine.
Although static analysis methods have limits, they are worth using and a continuing trend in
language processor design has been better static analysis methods, especially for data flow
anomaly detection. That's good because it means there's less for us to do as testers and we have
far too much to do as it is.
DATA FLOW MODEL:
The data flow model is based on the program's control flow graph - Don't confuse that with the
program's data flow graph.
Here we annotate each link with symbols (for example, d, k, u, c, and p) or sequences of symbols
(for example, dd, du, ddd) that denote the sequence of data operations on that link with respect to
the variable of interest. Such annotations are called link weights.
The control flow graph structure is same for every variable: it is the weights that change.
Figure 3.9: Control flow graph annotated for X and Y data flows.
INTRODUCTION:
TERMINOLOGY:
1. Definition-Clear Path Segment, with respect to variable X, is a connected sequence
of links such that X is (possibly) defined on the first link and not redefined or killed
on any subsequent link of that path segment. ll paths in Figure
3.9 are definition clear because variables X and Y are defined only on the first
link (1,3) and not thereafter. In Figure 3.10, we have a more complicated
situation. The following path segments are definition-clear: (1,3,4), (1,3,5), (5,6,7,4),
(7,8,9,6,7), (7,8,9,10), (7,8,10), (7,8,10,11). Subpath (1,3,4,5) is not
definition-clear because the variable is defined on (1,3) and again on (4,5). For
practice, try finding all the definition-clear subpaths for this routine (i.e., for all
variables).
2. Loop-Free Path Segment is a path segment for which every node in it is visited
atmost once. For Example, path (4,5,6,7,8,10) in Figure 3.10 is loop free, but path
(10,11,4,5,6,7,8,10,11,12) is not because nodes 10 and 11 are each visited twice.
3. Simple path segment is a path segment in which at most one node is visited twice.
For example, in Figure 3.10, (7,4,5,6,7) is a simple path segment. A simple path
segment is either loop-free or if there is a loop, only one node is involved.
4. A du path from node i to k is a path segment such that if the last link has a
computational use of X, then the path is simple and definition-clear; if the
penultimate (last but one) node is j - that is, the path is (i,p,q,...,r,s,t,j,k) and link (j,k)
has a predicate use - then the path from i to j is both loop-free and definition- clear.
STRATEGIES: The structural test strategies discussed below are based on the program's
control flow graph. They differ in the extent to which predicate uses and/or computational uses
of variables are included in the test set. Various types of data flow testing strategies in decreasing
order of their effectiveness are:
All - du Paths (ADUP): The all-du-paths (ADUP) strategy is the strongest data-flow testing strategy
discussed here. It requires that every du path from every definition of every variable to every some
test.
For variable X and Y:In Figure 3.9, because variables X and Y are used only on link (1,3), any test
that starts at the entry satisfies this criterion (for variables X and Y, but not for all variables as
required by the strategy).
For variable Z: The situation for variable Z (Figure 3.10) is more complicated because the
variable is redefined in many places. For the definition on link (1,3) we must exercise paths that
include subpaths (1,3,4) and (1,3,5). The definition on link (4,5) is covered by any path that
includes (5,6), such as subpath (1,3,4,5,6, ...). The (5,6) definition requires paths that include
subpaths (5,6,7,4) and (5,6,7,8).
For variable V: Variable V (Figure 3.11) is defined only once on link (1,3). Because V has a
predicate use at node 12 and the subsequent path to the end must be forced for both directions at
node 12, the all-du-paths strategy for this variable requires that we exercise all loop-free
entry/exit paths and at least one path that includes the loop caused by (11,4).
Note that we must test paths that include both subpaths (3,4,5) and (3,5) even though neither of
these has V definitions. They must be included because they provide alternate du paths to the V
use on link (5,6). Although (7,4) is not used in the test set for variable V, it will be included in
the test set that covers the predicate uses of array variable V() and U.
The all-du-paths strategy is a strong criterion, but it does not take as many tests as it might seem at
first because any one test simultaneously satisfies the criterion for several definitions and uses of
several different variables.
All Uses Startegy (AU):The all uses strategy is that at least one definition clear path from every
definition of every variable to every use of that definition be exercised under some test.
Just as we reduced our ambitions by stepping down from all paths (P) to branch coverage (C2),
say, we can reduce the number of test cases by asking that the test set should include at least one
path segment from every definition to every use that can be reached by that definition.
For variable V: In Figure 3.11, ADUP requires that we include subpaths (3,4,5) and (3,5) in
some test because subsequent uses of V, such as on link (5,6), can be reached by either
alternative. In AU either (3,4,5) or (3,5) can be used to start paths, but we don't have to use both.
Similarly, we can skip the (8,10) link if we've included the (8,9,10) subpath.
Note the hole. We must include (8,9,10) in some test cases because that's the only way to reach
the c use at link (9,10) - but suppose our bug for variable V is on link (8,10) after all? Find a
covering set of paths under AU for Figure 3.11.
All p-uses/some c-uses strategy (APU+C) : For every variable and every definition of that
variable, include at least one definition free path from the definition to every predicate use; if
there are definitions of the variables that are not covered by the above prescription, then add
computational use test cases as required to cover every definition.
For variable Z:In Figure 3.10, for APU+C we can select paths that all take the upper link (12,13)
and therefore we do not cover the c-use of Z: but that's okay according to the strategy's definition
because every definition is covered.
Links (1,3), (4,5), (5,6), and (7,8) must be included because they contain definitions for variable
Z. Links (3,4), (3,5), (8,9), (8,10), (9,6), and (9,10) must be included because they contain
predicate uses of Z. Find a covering set of test cases under APU+C for all variables in this
example - it only takes two tests.
All c-uses/some p-uses strategy (ACU+P) : The all c-uses/some p-uses strategy (ACU+P) is to
first ensure coverage by computational use cases and if any definition is not covered by the
previously selected paths, add such predicate use cases as are needed to assure that every
definition is included in some test.
For variable Z: In Figure 3.10, ACU+P coverage is achieved for Z by path (1,3,4,5,6,7,8,10,
11,12,13[lower], 2), but the predicate uses of several definitions are not covered. Specifically,
the (1,3) definition is not covered for the (3,5) p-use, the (7,8) definition is not covered for the
(8,9), (9,6) and (9, 10) p-uses.
The above examples imply that APU+C is stronger than branch coverage but ACU+P may be
weaker than, or incomparable to, branch coverage.
All Definitions Strategy (AD) : The all definitions strategy asks only every definition of every
variable be covered by atleast one use of that variable, be that use a computational use or a predicate
use.
For variable Z: Path (1,3,4,5,6,7,8, . . .) satisfies this criterion for variable Z, whereas any entry/exit path
satisfies it for variable V.
From the definition of this strategy we would expect it to be weaker than both ACU+P and
APU+C.
1. All Predicate Uses (APU), All Computational Uses (ACU) Strategies : The all predicate uses
strategy is derived from APU+C strategy by dropping the requirement that we include a c- use for
the variable if there are no p-uses for the variable. The all computational uses strategy is derived
from ACU+P strategy by dropping the requirement that we include a p-use for the variable if there
are no c-uses for the variable.
It is intuitively obvious that ACU should be weaker than ACU+P and that APU should be
weaker than APU+C.
ORDERING THE STRATEGIES:
Figure 3.12compares path-flow and data-flow testing strategies. The arrows denote that the
strategy at the arrow's tail is stronger than the strategy at the arrow's head
o The right-hand side of this graph, along the path from "all paths" to "all statements"
is the more interesting hierarchy for practical applications.
o Note that although ACU+P is stronger than ACU, both are incomparable to the
predicate-biased strategies. Note also that "all definitions" is not comparable to ACU
or APU.
INTRODUCTION:
o Domain: In mathematics, domain is a set of possible values of an independent
variable or the variables of a function.
o Programs as input data classifiers: domain testing attempts to determinewhether
the classification is or is not correct.
o Domain testing can be based on specifications or equivalent implementation
information.
o If domain testing is based on specifications, it is a functional test technique.
o If domain testing is based implementation details, it is a structural test technique.
o For example, you're doing domain testing when you check extreme values of an
input variable.
All inputs to a program can be considered as if they are numbers. For example, a
character string can be treated as a number by concatenating bits and looking at them as if
they were a binary integer. This is the view in domain testing, which is why this strategy has
a mathematical flavor.
o Before doing whatever it does, a routine must classify the input and set itmoving
on the right path.
o An invalid input (e.g., value too big) is just a special processing casecalled
'reject'.
o The input then passes to a hypothetical subroutine rather than on calculations.
o In domain testing, we focus on the classification aspect of the routine rather than
on the calculations.
o Structural knowledge is not needed for this model - only a consistent, complete
specification of input values for each case.
o We can infer that for each case there must be at least one path to process that case.
A DOMAIN IS A SET:
o An input domain is a set.
o If the source language supports set definitions (E.g. PASCAL set types and C
enumerated types) less testing is needed because the compiler does much of it for us.
o Domain testing does not work well with arbitrary discrete sets of data objects.
o Domain for a loop-free program corresponds to a set of numbers defined over the
input vector.
A DOMAIN CLOSURE:
o A domain boundary is closed with respect to a domain if the points on the
boundary belong to the domain.
o If the boundary points belong to some other domain, the boundary is said to be
open.
o Figure 4.2 shows three situations for a one-dimensional domain - i.e., a domain
defined over one input variable; call it x
The importance of domain closure is that incorrect closure bugs are frequent domain bugs. For
example, x >= 0 when x > 0 was intended
Figure 4.2: Open and Closed Domains.
DOMAIN DIMENSIONALITY:
o Every input variable adds one dimension to the domain.
o One variable defines domains on a number line.
o Two variables define planar domains.
o Three variables define solid domains.
o Every new predicate slices through previously defined domains and cuts them in
half.
o Every boundary slices through the input vector space with a dimensionalitywhich
is less than the dimensionality of the space.
o Thus, planes are cut by lines and points, volumes by planes, lines and pointsand
n-spaces by hyperplanes.
BUG ASSUMPTION:
o The bug assumption for the domain testing is that processing is okay but the
domain definition is wrong.
o An incorrectly implemented domain means that boundaries are wrong, which may
in turn mean that control flow predicates are wrong.
o Many different bugs can result in domain errors. Some of them are:
Domain Errors:
▪ Double Zero Representation: In computers or Languages that have a
distinct positive and negative zero, boundary errors for negative zero are
common.
▪ Floating point zero check: A floating point number can equal zero only if
the previous definition of that number set it to zero or if it is subtracted from
itself or multiplied by zero. So the floating point zero check to be done
against an epsilon value.
o Co-incidental Correctness: Domain testing isn't good at finding bugs for which
the outcome is correct for the wrong reasons. If we're plagued by coincidental
correctness we may misjudge an incorrect boundary. Note that this implies
weakness for domain testing when dealing with routines that have binary
outcomes (i.e., TRUE/FALSE)
o Representative Outcome: Domain testing is an example of partition testing.
Partition-testing strategies divide the program's input space into domains such that
all inputs within a domain are equivalent (not equal, but equivalent) in the sense that
any input represents all inputs in that domain.
o If the selected input is shown to be correct by a test, then processing is presumed
correct, and therefore all inputs within that domain are expected (perhaps
unjustifiably) to be correct. Most test techniques, functional or structural, fall
under partition testing and therefore make this representative outcome
assumption. For example, x2 and 2x are equal for x = 2, but the functions are
different. The functional differences between adjacent domains are usually
simple, such as x + 7 versus x + 9, rather than x2 versus 2x.
o Functional Homogeneity of Bugs: Whatever the bug is, it will not change the
functional form of the boundary predicate. For example, if the predicate is ax >=
b, the bug will be in the value of a or b but it will not change the predicate to ax
>= b, say.
o Linear Vector Space: Most papers on domain testing, assume linear boundaries -
not a bad assumption because in practice most boundary predicates are linear.
o Loop Free Software: Loops are problematic for domain testing. The trouble with
loops is that each iteration can result in a different predicate expression (after
interpretation), which means a possible domain boundary change.
NICE DOMAINS:
o Where do these domains come from?
Domains are and will be defined by an imperfect iterative process aimed at
achieving (user, buyer, voter) satisfaction.
o Implemented domains can't be incomplete or inconsistent. Every input will be
processed (rejection is a process), possibly forever. Inconsistent domains will be
made consistent.
o Conversely, specified domains can be incomplete and/or inconsistent. Incomplete in
this context means that there are input vectors for which no path is specified, and
inconsistent means that there are at least two contradictory specifications over the
same segment of the input space.
o Some important properties of nice domains are: Linear, Complete, Systematic,
And Orthogonal, Consistently closed, Convex and simply connected.
o To the extent that domains have these properties domain testing is easy as testing
gets.
o The bug frequency is lesser for nice domain than for uglydomains.
COMPLETE BOUNDARIES:
o Nice domain boundaries are complete in that they span the number space from plus
to minus infinity in all dimensions.
o Figure 4.4 shows some incomplete boundaries. Boundaries A and E have gaps.
o Such boundaries can come about because the path that hypothetically corresponds to
them is unachievable, because inputs are constrained in such a way that such values
can't exist, because of compound predicates that define a single boundary, or
because redundant predicates convert such boundary values into a null set.
o The advantage of complete boundaries is that one set of tests is needed to confirm
the boundary no matter how many domains it bounds.
o If the boundary is chopped up and has holes in it, then every segment of that
boundary must be tested for every domain it bounds.
SYSTEMATIC BOUNDARIES:
o Systematic boundary means that boundary inequalities related by a simple
function such as a constant.
In Figure 4.3 for example, the domain boundaries for u and v differ only by a
constant.
o where fi is an arbitrary linear function, X is the input vector, ki and c are constants,
and g(i,c) is a decent function over i and c that yields a constant, such as k + ic.
o The first example is a set of parallel lines, and the second example is a set of
systematically (e.g., equally) spaced parallel lines (such as the spokes of a wheel,
if equally spaced in angles, systematic).
o If the boundaries are systematic and if you have one tied down and generate tests for
it, the tests for the rest of the boundaries in that set can be automatically generated.
ORTHOGONAL BOUNDARIES:
o Two boundary sets U and V (See Figure 4.3) are said to be orthogonal if every
inequality in V is perpendicular to every inequality in U.
o If two boundary sets are orthogonal, then they can be tested independently
o In Figure 4.3 we have six boundaries in U and four in V. We can confirm the
boundary properties in a number of tests proportional to 6 + 4 = 10 (O(n)). If we tilt
the boundaries to get Figure 4.5,
o we must now test the intersections. We've gone from a linear number of cases to a
quadratic: from O(n) to O(n2).
CLOSURE CONSISTENCY:
o Figure 4.6 shows another desirable domain property: boundary closures are
consistent and systematic.
o The shaded areas on the boundary denote that the boundary belongs to the domain
in which the shading lies - e.g., the boundary lines belong to the domains on the right.
o Consistent closure means that there is a simple pattern to the closures - for
example, using the same relational operator for all boundaries of a set of parallel
boundaries.
CONVEX:
o A geometric figure (in any number of dimensions) is convex if you can take two
arbitrary points on any two different boundaries, join them by a line and all points
on that line lie within the figure.
o Nice domains are convex; dirty domains aren't.
o You can smell a suspected concavity when you see phrases such as: ". . . except if
. . .," "However . . .," ". . . but not " In programming, it's often the buts in the
specification that kill you.
SIMPLY CONNECTED:
o Nice domains are simply connected; that is, they are in one piece rather than
UGLY DOMAINS:
o Some domains are born ugly and some are uglified by badspecifications.
o Every simplification of ugly domains by programmers can be either good orbad.
o Programmers in search of nice solutions will "simplify" essential complexity out
of existence. Testers in search of brilliant insights will be blind to essential
DOMAIN TESTING:
The closure can be wrong (i.e., assigned to the wrong domain) or the boundary (a point in this case)
can be shifted one way or the other, we can be missing a boundary, or we can have an extra boundary.
1. Figure 4.13 shows possible domain bugs for a one-dimensional open domain
boundary.
2. In Figure 4.13a we assumed that the boundary was to be open for A. The bug we're
looking for is a closure error, which converts > to >= or < to <= (Figure 4.13b). One
test (marked x) on the boundary point detects this bug because processing for that
point will go to domain A rather than B.
3. In Figure 4.13c we've suffered a boundary shift to the left. The test point we used for
closure detects this bug because the bug forces the point from the B domain, where
it should be, to A processing. Note that we can't distinguish between a shift and a
closure error, but we do know that we have a bug.
Figure 4.13: One Dimensional Domain Bugs, Open Boundaries.
4. Figure 4.13d shows a shift the other way. The on point doesn't tell us anything
because the boundary shift doesn't change the fact that the test point will be processed
in B. To detect this shift we need a point close to the boundary but within A. The
boundary is open, therefore by definition, the off point is in A (Open Off Inside).
5. The same open off point also suffices to detect a missing boundary because what
should have been processed in A is now processed in B.
6. To detect an extra boundary we have to look at two domain boundaries. In this
context an extra boundary means that A has been split in two. The two off points that
we selected before (one for each boundary) does the job. If point C had been a
closed boundary, the on test point at C would do it.
7. For closed domains look at Figure 4.14. As for the open boundary, a test point on the
boundary detects the closure bug. The rest of the cases are similar to the open
boundary, except now the strategy requires off points just outside the domain.
Figure 4.14: One Dimensional Domain Bugs, Closed Boundaries.
INTRODUCTION:
o Recall that we defined integration testing as testing the correctness of the interface
between two otherwise correct components.
o Components A and B have been demonstrated to satisfy their component tests,
and as part of the act of integrating them we want to investigate possible
inconsistencies across their interface.
o Interface between any two components is considered as a subroutine call.
o We're looking for bugs in that "call" when we do interfacetesting.
o Let's assume that the call sequence is correct and that there are no type
incompatibilities.
o For a single variable, the domain span is the set of numbers between (and
including) the smallest value and the largest value. For every input variable we want
(at least): compatible domain spans and compatible closures (Compatible but
need not be Equal).
CLOSURE COMPATIBILITY:
o Assume that the caller's range and the called domain spans the same numbers - for
example, 0 to 17.
o Figure 4.16 shows the four ways in which the caller's range closure and the
called's domain closure can agree.
o The thick line means closed and the thin line means open. Figure 4.16 shows the
four cases consisting of domains that are closed both on top (17) and bottom (0),
open top and closed bottom, closed top and open bottom, and open top and
bottom.
SPAN COMPATIBILITY:
o Figure 4.18 shows three possibly harmless spanincompatibilities.
o Start with the called routine's domains and generate test points in accordance to
the domain-testing strategy used for that routine in componenttesting.
o Unless you're a mathematical whiz you won't be able to do this without tools for
more than one variable at a time.
PATHS, PATH PRODUCTS AND REGULAR EXPRESSIONS
MOTIVATION:
o Flow graphs are being an abstract representation of programs.
o Any question about a program can be cast into an equivalent question about an
appropriate flowgraph.
o Most software development, testing and debugging tools use flow graphs analysis
techniques.
PATH PRODUCTS:
o Normally flow graphs used to denote only control flowconnectivity.
o The simplest weight we can give to a link is a name.
o Using link names as weights, we then convert the graphical flow graph into an
equivalent algebraic like expressions which denotes the set of all possible paths from
entry to exit for the flow graph.
o Every link of a graph can be given a name.
o The link name will be denoted by lower case italic letters In tracing a path or path
segment through a flow graph, you traverse a succession of link names.
o The name of the path or path segment that corresponds to those links is expressed
naturally by concatenating those link names.
o For example, if you traverse links a,b,c and d along some path, the name for that
path segment is abcd. This pa
o th name is also called a path product. Figure 5.1 shows some examples:
PATH PRODUCTS:
o The name of a path that consists of two successive path segments is conveniently
expressed by the concatenation or Path Product of the segment names.
o For example, if X and Y are defined as X=abcde,Y=fghij,then the path
corresponding to X followed by Y is denoted by
XY=abcdefghij
o Similarly,
YX=fghijabcde
aX=aabcde
Xa=abcdea
XaX=abcdeaabcde
o If X and Y represent sets of paths or path expressions, their product represents the
set of paths that can be obtained by following every element of X by any element of
Y in all possible ways. For example,
o X = abc + def + ghi
o Y = uvw + z
Then,
XY = abcuvw + defuvw + ghiuvw + abcz + defz + ghiz
o If a link or segment name is repeated, that fact is denoted byan exponent. The
exponent's value denotes the number of repetitions:
o a1 = a; a2 = aa; a3 = aaa; an = aaaa . . . n times.
Similarly, if X = abcde then
X1 = abcde
X2 = abcdeabcde = (abcde)2
X3 = abcdeabcdeabcde = (abcde)2abcde
= abcde(abcde)2 = (abcde)3
o The path product is not commutative (that is XY!=YX).
o The path product is Associative.
RULE 1: A(BC)=(AB)C=ABC
where A,B,C are path names, set of path names or path expressions.
o The zeroth power of a link name, path product, or path expression is also needed
for completeness. It is denoted by the numeral "1" and denotes the "path" whose
length is zero - that is, the path that doesn't have any links.
o a0 = 1
o X0 = 1
PATH SUMS:
o The "+" sign was used to denote the fact that path names were part of the same set
of paths.
o The "PATH SUM" denotes paths in parallel between nodes.
o Links a and b in Figure 5.1a are parallel paths and are deno ed by a + b. Similarly,
links c and d are parallel paths between the next two nodes and are denoted by c +
d.
o The set of all paths between nodes 1 and 2 can be thought of as a set of parallel
paths and denoted by eacf+eadf+ebcf+ebdf.
o If X and Y are sets of paths that lie between the same pair of nodes, then X+Y
denotes the UNION of those set of paths. For example, in Figure 5.2:
DISTRIBUTIVE LAWS:
o The product and sum operations are distributive, and the ordinary rules of
multiplication apply; that is
RULE 4: A(B+C)=AB+AC and (B+C)D=BD+CD
o Applying these rules to the below Figure 5.1a yields
o e(a+b)(c+d)f=e(ac+ad+bc+bd)f = eacf+eadf+ebcf+ebdf
ABSORPTION RULE:
o If X and Y denote the same set of paths, then the union of these sets is unchanged;
consequently,
RULE 5: X+X=X (Absorption Rule)
o If a set consists of paths names and a member of that set is added to it, the "new"
name, which is already in that set of names, contributes nothing and can be
ignored.
o For example,
o if X=a+aa+abc+abcd+def then
X+a = X+aa = X+abc = X+abcd = X+def = X
It follows that any arbitrary sum of identical path expressions reduces to the same
path expression.
LOOPS:
Loops can be understood as an infinite set of parallel paths. Say that the loop consists of
a single link b. then the set of all paths through that loop point is
b0+b1+b2+b3+b4+b5+..............
RULES 6 - 16:
o The following rules can be derived from the previous rules:
o RULE 6: Xn + Xm = Xn if n>m
RULE 6: Xn + Xm = Xm if m>n
RULE 7: X nXm = Xn+m
RULE 8: X nX* = X*Xn = X*
RULE 9: X nX+ = X+Xn = X+
RULE 10: X*X + = X+X* = X+
RULE 11: 1 + 1 = 1
RULE 12: 1X = X1 = X
Following or preceding a set of paths by a path of zero length does not change the
set.
RULE 13: 1n = 1n = 1* = 1+ = 1
No matter how often you traverse a path of zero length,It is a path of zero length.
RULE 14: 1++1 = 1*=1
The null set of paths is denoted by the numeral 0. it obeys the following rules:
RULE 15: X+0=0+X=X
RULE 16: 0X=X0=0
If you block the paths of a graph for or aft by a graph that has no paths , there
won’t be any paths.
REDUCTION PROCEDURE:
o In the first way, we remove the self-loop and then multiply all outgoing links by
Z*.
o In the second way, we split the node into two equivalent nodes, call them A and
A' and put in a link between them whose path expression is Z*. Then we remove
node A' using steps 4 and 5 to yield outgoing links whose path expressions are Z*X
and Z*Y.
o Removing the loop and then node 6 result in the following expression:
a(bgjf)*b(c+gkh)d((ilhd)*imf(bjgf)*b(c+gkh)d)*(ilhd)*e
o You can practice by applying the algorithm on the following flowgraphs and
generate their respective path expressions:
o This arithmetic is an ordinary algebra. The weight is the number of paths in each
set.
o EXAMPLE:
▪ The following is a reasonably well-structured program.
13 = 10 + 11 + 12 + 13 = 1 + 1 + 1 + 1 = 4
2. E: Multiply the link weights inside the loop: 1 X 4 = 4
3. F: Evaluate the loop by multiplying the link wieghts: 2 X 4 = 8.
4. G: Simpifying the loop further results in the total maximum number of
paths in the flowgraph:
2 X 84 X 2 = 32,768.
Alternatively, you could have substituted a "1" for each link in the path expression and then
simplified, as follows:
a(b+c)d{e(fi)*fgj(m+l)k}*e(fi)*fgh
= 1(1 + 1)1(1(1 x 1)31 x 1 x 1(1 + 1)1)41(1 x 1)31 x 1 x 1
= 2(131 x (2))413
= 2(4 x 2)4 x 4
= 2 x 84 x 4 = 32,768
This is the same result we got graphically.Actually, the outer loop should be taken exactly four
times. That doesn't mean it will be taken zero or four times. Consequently, there is a superfluous
"4" on the outlink in the last step. Therefore the maximum number of different paths is 8192
rather than 32,768.
STRUCTURED FLOWGRAPH:
Structured code can be defined in several different ways that do not involve ad-hoc rules such as
not using GOTOs.
A structured flowgraph is one that can be reduced to a single link by successive application of
the transformations of Figure 5.7.
Figure 5.7: Structured Flowgraph Transformations.
The node-by-node reduction procedure can also be used as a test for structured code.Flow graphs
that DO NOT contains one or more of the graphs shown below (Figure 5.8) as subgraphs are
structured.
1. Jumping into loops
2. Jumping out of loops
3. Branching into decisions
4. Branching out of decisions
The values of the weights are the number of members in a set of paths.
EXAMPLE:
▪ Applying the arithmetic to the earlier example gives us the identical steps
unitl step 3 (C) as below:
This question can be answered under suitable assumptions primarily that all probabilities
involved are independent, which is to say that all decisions are independent and uncorrelated.
We use the same algorithm as before: node-by-node removal of uninteresting nodes.
Weights, Notations and Arithmetic:
▪ Probabilities can come into the act only at decisions (including decisions
associated with loops).
▪ Annotate each outlink with a weight equal to the probability of going in
that direction.
▪ Evidently, the sum of the outlink probabilities must equal 1
▪ For a simple loop, if the loop will be taken a mean of N times, the looping
probability is N/(N + 1) and the probability of not looping is 1/(N + 1).
▪ A link that is not part of a decision node has a probability of 1.
▪ The arithmetic rules are those of ordinaryarithmetic.
▪ In this table, in case of a loop, PA is the probability of the link leaving the
loop and PL is the probability of looping.
▪ The rules are those of ordinary probabilitytheory.
1. If you can do something either from column A with a probability
of PA or from column B with a probability PB, then the probability
that you do either is PA + PB.
2. For the series case, if you must do both things, and their
probabilities are independent (as assumed), then the probability
that you do both is the product of their probabilities.
▪ For example, a loop node has a looping probability of PL and a probability
of not looping of P A, which is obviously equal to I - PL.
▪ Following the above rule, all we've done is replace the outgoing
probability with 1 - so why the complicated rule? After a few steps in
which you've removed nodes, combined parallel terms, removed loops and
the like, you might find something like this:
▪ Let us do this in three parts, starting with case A. Note that the sum of the
probabilities at each decision node is equal to 1. Start by throwing away
anything that isn't on the way to case A, and then apply the reduction
procedure. To avoid clutter, we usually leave out probabilities equal to 1.
CASE A:
▪ Case B is simpler:
▪ These checks. It's a good idea when doing this sort of thing to calculate all
the probabilities and to verify that the sum of the routine's exit
probabilities does equal 1.
▪ If it doesn't, then you've made calculation error or, more likely, you've left
out some bra How about path probabilities? That's easy. Just trace the path
of interest and multiply the probabilities as you go.
▪ Alternatively, write down the path name and do the indicated arithmetic
operation.
▪ Say that a path consisted of links a, b, c, d, e, and the associated probabilities
were .2, .5, 1., .01, and I respectively. Path abcbcbcdeabddea would have a
probability of 5 x 10-10.
▪ Long paths are usually improbable.
EXAMPLE:
1. Start with the original flow graph annotated with probabilities and processing time.
2. Combine the parallel links of the outer loop. The result is just the mean of the processing
times for the links because there aren't any other links leaving the first node. Also
combine the pair of links at the beginning of the flow graph.
PUSH/POP, GET/RETURN:
This model can be used to answer several different questions that can turn up in debugging.
It can also help decide which test cases to design.
The question is:
Given a pair of complementary operations such as PUSH (the stack) and POP (the stack),
considering the set of all possible paths through the routine, what is the net effect of the
routine? PUSH or POP? How many times? Under what conditions?
Here are some other examples of complementary operations to which this model applies:
GET/RETURN a resource block.
OPEN/CLOSE a file.
START/STOP a device or process.
EXAMPLE 1 (PUSH / POP):
▪ Here is the Push/Pop Arithmetic:
▪ The numeral 1 is used to indicate that nothing of interest (neither PUSH
nor POP) occurs on a given link.
▪ "H" denotes PUSH and "P" denotes POP. The operations are
commutative, associative, and distributive.
▪ G(G + R)G(GR)*GGR*R
= G(G + R)G3R*R
= (G + R)G3R*
= (G4 + G2)R*
▪ This expression specifies the conditions under which the resources will be
balanced on leaving the routine.
▪ If the upper branch is taken at the first decision, the second loop must be
taken four times.
▪ If the lower branch is taken at the first decision, the second loop must be
taken twice.
▪ For any other values, the routine will not balance. Therefore, the first loop
does not have to be instrumented to verify this behavior because its impact
should be nil.
THE PROBLEM:
o The generic flow-anomaly detection problem (note: not just data-flow anomalies,
but any flow anomaly) is that of looking for a specific sequence of options
considering all possible paths through a routine.
o Let the operations be SET and RESET, denoted by s and r respectively, and we
want to know if there is a SET followed immediately a SET or a RESET followed
immediately by a RESET (an ss or an rr sequence).
o Some more application examples:
1. A file can be opened (o), closed (c), read (r), or written (w). If the file is
read or written to after it's been closed, the sequence is nonsensical.
Therefore, cr and cw are anomalous. Similarly, if the file is read before it's
been written, just after opening, we may have a bug. Therefore, or is also
anomalous. Furthermore, oo and cc, though not actual bugs, are a waste of
time and therefore should also be examined.
2. A tape transport can do a rewind (d), fast-forward (f), read (r), write (w),
stop (p), and skip (k). There are rules concerning the use of the transport;
for example, you cannot go from rewind to fast-forward without an
intervening stop or from rewind or fast-forward to read or write without an
intervening stop. The following sequences are anomalous: df, dr, dw, fd,
and fr. Does the flowgraph lead to anomalous sequences on any path? If
so, what sequences and under what circumstances?
3. The data-flow anomalies discussed in Unit 4 requires us to detect the dd,
dk, kk, and ku sequences. Are there paths with anomalous data flows?
THE METHOD:
o Annotate each link in the graph with the appropriate operator or the null operator
1.
o Simplify things to the extent possible, using the fact that a + a = a and 12 = 1.
o You now have a regular expression that denotes all the possible sequences of
operators in that graph. You can now examine that regular expression for the
sequences of interest.
o EXAMPLE: Let A, B, C, be nonempty sets of character sequences whose
smallest string is at least one character long. Let T be a two-character string of
characters. Then if T is a substring of (i.e., if T appears within) AB nC, then T will
appear in AB2C. (HUANG's Theorem)
As an example, let
o A = pp
B = srr
C = rp
T = ss
A = p + pp + ps
B = psr + ps(r + ps)
C = rp
T = P4
Is it obvious that there is a p4 sequence in ABnC? The theorem states that we have
only to look at
LIMITATIONS:
o Huang's theorem can be easily generalized to cover sequences of greater length than
two characters. Beyond three characters, though, things get complex and this method
has probably reached its utilitarian limit for manual application.
o There are some nice theorems for finding sequences that occur at the beginnings and
ends of strings but no nice algorithms for finding strings buried in an expression.
o Static flow analysis methods can't determine whether a path is or is not
achievable. Unless the flow analysis includes symbolic execution or similar
techniques, the impact of unachievable paths will not be included in theanalysis.
The flow-anomaly application, for example, doesn't tell us that there will be a flow anomaly
- it tells us that if the path is achievable, then there will be a flow anomaly. Such analytical
problems go away, of course, if you take the trouble to design routines for which all paths
are achievable.
UNIT-IV
INTRODUCTION:
o The functional requirements of many programs can be specified by decision tables,
which provide a useful basis for program and test design.
o Consistency and completeness can be analyzed by using boolean algebra, which can
also be used as a basis for test design. Boolean algebra is trivialized by using
Karnaugh-Veitch charts.
o "Logic" is one of the most often used words in programmers' vocabularies but one
of their least used techniques.
o Boolean algebra is to logic as arithmetic is to mathematics. Without it, the tester
or programmer is cut off from many test and design techniques and tools that
incorporate those techniques.
o Logic has been, for several decades, the primary tool of hardware logicdesigners.
o Many test methods developed for hardware logic can be adapted to software logic
testing. Because hardware testing automation is 10 to 15 years ahead of software
testing automation, hardware testing methods and its associated theory is a fertile
ground for software testing methods.
o As programming and test techniques have improved, the bugs have shifted closer to
the process front end, to requirements and their specifications. These bugs range
from 8% to 30% of the total and because they're first-in and last-out, they're the
costliest of all.
o The trouble with specifications is that they're hard to express.
o Boolean algebra (also known as the sentential calculus) is the most basic of all logic
systems.
o Higher-order logic systems are needed and used for formal specifications.
o Much of logical analysis can be and is embedded in tools. But these tools incorporate
methods to simplify, transform, and check specifications, and the methods are to a
large extent based on boolean algebra.
Figure 6.1 is a limited - entry decision table. It consists of four areas called the condition
stub, the condition entry, the action stub, and the action entry.
Each column of the table is a rule that specifies the conditions under which the actions
named in the action stub will take place.
The condition stub is a list of names of conditions.
DECISION-TABLE PROCESSORS:
o Decision tables can be automatically translated into code and, as such, are a
higher-order language
o If the rule is satisfied, the corresponding action takes place
o Otherwise, rule 2 is tried. This process continues until either a satisfied rule
results in an action or no rule is satisfied and the default action is taken
o Decision tables have become a useful tool in the programmers kit, in business
data processing.
1. The specification is given as a decision table or can be easily converted into one.
2. The order in which the predicates are evaluated does not affect interpretation of the
rules or the resulting action - i.e., an arbitrary permutation of the predicate order will
not, or should not, affect which action takes place.
3. The order in which the rules are evaluated does not affect the resulting action - i.e.,
an arbitrary permutation of rules will not, or should not, affect which action takes
place.
4. Once a rule is satisfied and an action selected, no other rule need be examined.
5. If several actions can result from satisfying a rule, the order in which the actions
are executed doesn't matter.
DECISION-TABLES AND STRUCTURE:
PATH EXPRESSIONS:
GENERAL:
o Logic-based testing is structural testing when it's applied to structure (e.g., control
flow graph of an implementation); it's functional testing when it's applied to a
specification.
o In logic-based testing we focus on the truth values of control flow predicates.
o A predicate is implemented as a process whose outcome is a truth-functional value.
o For our purpose, logic-based testing is restricted to binary predicates.
o We start by generating path expressions by path tracing as in Unit V, but this
time, our purpose is to convert the path expressions into boolean algebra, using
the predicates' truth values (e.g., A and ) as weights.
BOOLEAN ALGEBRA:
o STEPS:
1. Label each decision with an uppercase letter that represents the truth value
of the predicate. The YES or TRUE branch is labeled with a letter (say A)
and the NO or FALSE branch with the same letter overscored (say ).
2. The truth value of a path is the product of the individual labels.
Concatenation or products mean "AND". For example, the straight- through
path of Figure 6.5, which goes via nodes 3, 6, 7, 8, 10, 11, 12, and 2, has a
truth value of ABC. The path via nodes 3, 6, 7, 9 and 2 has a value of .
3. If two or more paths merge at a node, the fact is expressed by use of a plus
sign (+) which means "OR".
o There are only two numbers in boolean algebra: zero (0) and one (1). One means
"always true" and zero means "always false".
o RULES OF BOOLEAN ALGEBRA:
▪ Boolean algebra has three operators: X (AND), + (OR) and (NOT)
▪ X : meaning AND. Also called multiplication. A st tement such as AB (A
X B) means "A and B are both true". This symbol is usually left out as in
ordinary algebra.
▪ + : meaning OR. "A + B" means "either A is true or B is true or both".
▪ meaning NOT. Also negation or complementation. This is read as either
"not A" or "A bar". The entire expression under the bar is negated.
▪ The following are the laws of boolean algebra:
In all of the above, a letter can represent a single sentence or an entire boolean algebra
expression.
Individual letters in a boolean algebra expression are called Literals (e.g. A,B)
The product of several literals is called a product term (e.g., ABC, DE).
An arbitrary boolean expression that has been multiplied out so that it consists of the sum of
products (e.g., ABC + DEF + GH) is said to be in sum-of-products form.
The result of simplifications (using the rules above) is again in the sum of product form and each
product term in such a simplified version is called a prime implicant. For example, ABC + AB
+ DEF reduce by rule 20 to AB + DEF; that is, AB and DEF are prime implicants.
The path expressions of Figure 6.5 can now be simplified by applying the rules.
The following are the laws of boolean algebra:
Similarly,
The deviation from the specification is now clear. The functions should have been:
Loops complicate things because we may have to solve a boolean equation to determine what
predicate value combinations lead to where.
KV CHARTS:
INTRODUCTION:
o If you had to deal with expressions in four, five, or six variables, you could get
bogged down in the algebra and make as many errors in designing test cases as there
are bugs in the routine you're testing.
o Karnaugh-Veitch chart reduces boolean algebraic manipulations to graphical
trivia.
o Beyond six variables these diagrams get cumbersome and may not be effective.
SINGLE VARIABLE:
o Figure 6.6 shows all the boolean functions of a single variable and their
equivalent representation as a KV chart.
o The charts show all possible truth values that the variable A can have.
o A "1" means the variable’s value is "1" or TRUE. A "0" means that the variable's
value is 0 or FALSE.
o The entry in the box (0 or 1) specifies whether the function that the chart represents
is true or false for that value of the variable.
o We usually do not explicitly put in 0 entries but specify only the conditions under
which the function is true.
Figure 6.6 : KV Charts for Functions of a Single Variable.
TWO VARIABLES:
o Figure 6.7 shows eight of the sixteen possible functions of twovariables.
o Each box corresponds to the combination of values of the variables for the row
and column of that box.
o A pair may be adjacent either horizontally or vertically but notdiagonally.
o Any variable that changes in either the horizontal or vertical direction does not
appear in the expression.
o In the fifth chart, the B variable changes from 0 to 1 going down
the column, and because the A variable's value for the column is 1,
the chart is equivalent to a simple A.
Figure 6.7: KV Charts for Functions of Two Variables.
OR
THREE VARIABLES:
o KV charts for three variables are shown below.
o As before, each box represents an elementary term of three variables with a bar
appearing or not appearing according to whether the row-column heading for that
box is 0 or 1.
o A three-variab e chart can have groupings of 1, 2, 4, and 8 boxes.
o A few examples will illustrate the principles:
Figure 6.8: KV Charts for Functions of Three Variables.
o You'll notice that there are several ways to circle the boxes intomaximum-sized
covering groups.
UNIT V
STATES, STATE GRAPHS, AND TRANSITION TESTING
Introduction
The finite state machine is as fundamental to software engineering as boolean algebra to
logic.
State testing strategies are based on the use of finite state machine models for software
structure, software behavior, or specifications of softwarebehavior.
Finite state machines can also be implemented as table-driven software, in which case
they are a powerful design option.
State Graphs
A state is defined as: “A combination of circumstances or attributes belonging for the
time being to a person or thing.”
For example, a moving automobile whose engine is running can have the following states
with respect to its transmission.
▪ Reverse gear
▪ Neutral gear
▪ First gear
▪ Second gear
▪ Third gear
▪ Fourth gear
State graph - Example
For example, a program that detects the character sequence “ZCZC” can be in the
following states.
Neither ZCZC nor any part of it has been detected.
▪ Z has been detected.
▪ ZC has been detected.
▪ ZCZ has been detected.
▪ ZCZC has been detected.
States are represented by Nodes. State are numbered or may identified by words
or whatever else is convenient.
Inputs and Transitions
Whatever is being modeled is subjected to inputs. As a result of those inputs, the state
changes, or is said to have made a Transition.
Transitions are denoted by links that join the states.
The input that causes the transition are marked on the link; that is, the inputs are link
weights.
There is one out link from every state for every input.
If several inputs in a state cause a transition to the same subsequent state, instead of drawing
a bunch of parallel links we can abbreviate the notation by listing the several inputs as in:
“input1, input2, input3………”.
State Tables
Big state graphs are cluttered and hard to follow.
It’s more convenient to represent the state graph as a table (the state table or state
transition table) that specifies the states, the inputs, the transitions and the
outputs.
The following conventions are used:
Each row of the table corresponds to a state.
Each column corresponds to an input condition.
The box at the intersection of a row and a column speci ies the next state (the
transition) and the output, if any.
State Table-Example
Time Versus Sequence
State graphs don’t represent time-they represent sequence.
A transition might take microseconds or centuries;
A system could be in one state for milliseconds and another for years- the state graph
would be the same because it has no notion of time.
Although the finite state machines model can be elaborated to include notions of time in
addition to sequence, such as time Petri Nets.
o Software implementation
There is rarely a direct correspondence between programs and the behavior of a process
described as a state graph.
The state graph represents, the total behavior consisting of the transport, the software, the
executive, the status returns, interrupts, and so on.
There is no simple correspondence between lines of code and states. The state table forms
the basis.
Important graphs
Equivalent States
Two states are Equivalent if every sequence of inputs starting from one state produces
exactly the same sequence of outputs when started from the other state. This notion can also
be extended to set of states.
TransitionBugs-
unspecified and contradictory Transitions
Every input-state combination must have a specified transition.
If the transition is impossible, then there must be a mechanism that prevents the input
from occurring in that state.
Exactly one transition must be specified for every combination of input and state.
A program can’t have contradictions or ambiguities.
Ambiguities are impossible because the program will do something for every input. Even
the state does not change, by definition this is a transition to the same state.
Unreachable States
An unreachable state is like unreachable code.
A state that no input sequence can reach.
An unreachable state is not impossible, just as unreachable code is not impossible
There may be transitions from unreachable state to other states; there usually because the
state became unreachable as a result of incorrect transition.
There are two possibilities for unreachable states:
o There is a bug; that is some transitions are missing.
o The transitions are there, but you don’t know about it.
Dead States
A dead state is a state that once entered cannot be left.
This is not necessarily a bug but it is suspicious.
Output Errors
The states, transitions, and the inputs could be correct, there could be no dead or
unreachable states, but the output for the transition could be incorrect.
Output actions must be verified independently of states and transitions.
State Testing
Impact of Bugs
If a routine is specified as a state graph that has been verified as correct in all details.
Program code or table or a combination of both must still beimplemented.
A bug can manifest itself as one of the following symptoms:
Wrong number of states.
Wrong transitions for a given state-input combination.
Wrong output for a given transition.
Pairs of states or sets of states that are inadvertently made equivalent.
States or set of states that are split to create in equivalent duplicates.
States or sets of states that have become dead.
States or sets of states that have become unreachable.
Tool Building
If you build test tools or want to know how they work, sooner or later you will be implementing
or investigating analysis routines based on these methods.
It is hard to build algorithms over visual graphs so the properties or graph matrices are
fundamental to tool building.
Cyclomatic Complexity
The cyclomatic complexity obtained by subtracting 1 from the total number of entries in each row
and ignoring rows with no entries, we obtain the equivalent number of decisions for each row. Adding
these values and then adding 1 to the sum yields the graph’s cyclomaticcomplexity.
Relations
A relation is a property that exists between two objects ofinterest.
For example,
“Node a is connected to node b” or aRb where “R” means “is connectedto”.
“a>=b” or aRb where “R” means greater than or equal”.
A graph consists of set of abstract objects called nodes and a relation R between the nodes.
If aRb, which is to say that a has the relation R to b, it is denoted by a link froma to b.
For some relations we can associate properties called as linkweights.
Transitive Relations
A relation is transitive if aRb and bRc implies aRc.
Most relations used in testing are transitive.
Examples of transitive relations include: is connected to, is greater than or equal to, is less than or
equal to, is a relative of, is faster than, is slower than, takes more time than, is a subset of,
includes, shadows, is the boss of.
Examples of intransitive relations include: is acquainted with, is a friend of, is a neighbor of, is
lied to, has a du chain between.
Reflexive Relations
A relation R is reflexive if, for every a, aRa.
A reflexive relation is equivalent to a self loop at everynode.
Examples of reflexive relations include: equals, is acquainted with, is a relativeof.
Examples of irreflexive relations include: not equals, is a friend of, is on top of, isunder.
Symmetric Relations
A relation R is symmetric if for every a and b, aRb implies bRa.
A symmetric relation mean that if there is a link from a to b then there is also a link from b to a.
A graph whose relations are not symmetric are called directed graph.
A graph over a symmetric relation is called an undirected graph.
The matrix of an undirected graph is symmetric (aij=aji) for all i,j)
Antisymmetric Relations
A relation R is antisymmetric if for every a and b, if aRb and bRa, then a=b, or they are the same
elements.
Examples of antisymmetric relations: is greater than or equal to, is a subset of, time.
Examples of nonantisymmetric relations: is connected to, can be reached from, is greater than, is
a relative of, is a friend of
quivalence Relations
An equivalence relation is a relation that satisfies the reflexive, transitive, andsymmetric
properties.
Equality is the most familiar example of an equivalencerelation.
If a set of objects satisfy an equivalence relation, we say that they form an equivalence class over
that relation.
The importance of equivalence classes and relations is that any member of the equivalence class
is, with respect to the relation, equivalent to any other member of thatclass.
The idea behind partition testing strategies such as domain testing and path testing, is that we can
partition the input space into equivalence classes.
Testing any member of the equivalence class is as effective as testing themall.
Partitioning Algorithm
Consider any graph over a transitive relation. The graph may have loops.
We would like to partition the graph by grouping nodes in such a way that every loop is
contained within one group or another.
Such a graph is partially ordered.
There are many used for an algorithm that doesthat:
We might want to embed the loops within a subroutine so as to have a resulting graph
which is loop free at the top level.
Many graphs with loops are easy to analyze if you know where to break the loops.
While you and I can recognize loops, it’s much harder to program a tool to do it unless you
have a solid algorithm on which to base the tool.
UNIT-VI
Automation and Testing Tools: need for automation, categorization of testing tools, selection of
testing tools, Cost incurred, Guidelines for automated testing, overview of some commercial testing
tools.
Testing Object Oriented Software: basics, Object oriented testing
Testing Web based Systems: Challenges in testing for web based software, quality aspects, web
engineering, testing of web based systems, Testing mobile systems.
Testing Activity Tools: These tools are based on the testing activities or tasks in a particular phase
of the SDLC. Testing activities can be categorized as:
--Tools for Review and Inspections
--Tools for Test Planning
--Tools for Test Design and Development
--Test Execution and Evaluation Tools
Tools for Review and Inspections: Since these tools are for static analysis on many items, some tools
are designed to work with specifications but there are far too many tools available that work exclusively
with code. In this category, the following types of tools are required:
Complexity Analysis Tools: It is important for testers that complexity is analysed so that testing
time and resources can be estimated.
Code Comprehension: These tools help in understanding dependencies, tracing, program logic,
viewing graphical representations of the program.
Tools for Test Planning: The types of tools required for test planning are:
-- Templates for test plan documentation.
-- Test schedule and staffing estimates.
-- Complexity analyser.
Coverage Analysis Tools: These tools automate the process of throughly testing the software and
provide a quanttive measure of the coverage of the system being tested.
Memory Testing Tools: These tools verify that an application is properly using its memory
resources.
Test management Tools: Some test management tools such as Rationals TestStudio are integrated
with requirement and configuration management and defect tracking tools, in order to simplify the
entire testing life cycle.
122
Network-testing Tools: These tools monitor, meausre, test and dignose performance across an entire
network.
Performance testing Tools: These tools helps in measuring the response time and load capabilities
of a sytem.
Training is required: Testers require training regarding the tool, otherwise the tools may end up on
the shelf or implemented inefficiently.
Configuration Management: It is necessary to track large number of files and test related artifacts.
Learning Curve for the Tools: Tests scripts generated by the tool during recording must be
modified manually, requiring tool-scripting knowledge in order to make the script robust, reusable
and maintainable.
Testing Tools can be Intrusive: It may be necessary that for automation some tools require that a
special code is inserted in the system to work correctly and to be integrated with the testing tools.
These types of tools are called as intrusive tools.
Multiple Tools are required: It may be possible that your requirement is not satisfied with just one
tool for automation.
Test the tool on an application prototype: While purchasing the tool it is important to verify that
it works properly with the system being developed.
Not all the tests should be automated: Automated testing is an enhancement of manual testing,
but it cannot be expected that all test on a project can be automated.
Select the tools according to Organization needs: Focus on the needs of the Organization and
know the resources (budget, schedule) before choosing the automation tool.
Use proven test-script development techniques: Automation can be effective if proven techniques
are used to produce efficient, maintainable and reusable test-script.
123
Automate the regression tests whenever feasible: Regression testing consumes a lot of time. If
tools are used for this testing, the testing time can be reduced to a greater extent.
Overview of Some Commercial Testing Tools:
Apache’s Jmeter
The Apache Jmeter application is open source software, a 100% pure Java application designed to
load test functional behavior and measure performance. It was originally designed for testing Web
Applications but has since expanded to other test functions.
of test strategy, test planning as well as test design through the creation of TestDirector test cases.
--Test Lab – Helps in managing the execution of tests including the reporting of progress of testing
using Mercury Test Lab.
Dynamic Environment: The dynamic nature of web software creates challenges for the analysis,
testing, and maintenance for these systems.
Very short development time: Clients of web based systems impose very short development time,
compared to other software systems.
Continuous evolution: Demand for more funcitonality and capacity after the system has been
designed and deployed to meet the extended scope and demands i.e Scalability issues.
Compatibility & Interoperability: Web applications often are affected by factors that may cause
incompatability and interoperability issues.
Quality Aspects:
Reliability: Extensive research literature and a collection of commercial tools have been devoted to
testing, ensuring, assuring, and measuring software reliability. Safety-critical software applications
such as telecommunications, aerospace, and medical devices demand highly reliable software, but
although many researchers are reluctant to admit it, most software currently produced does not need
to be highly reliable.
Performance: Performance testing is largely on the basis of load testing, response time, download
time of a web page, or transactions performed per unit time.
Security: We have all heard about Web sites being cracked and private customer information
distributed or held for ransom. This is only one example of the many potential security flaws in Web
software applications. When the Web functioned primarily to distribute online brochures, security
breaches had relatively small consequences. Today, however, the breach of a company’s Web site
can cause significant revenue losses, large repair costs, legal consequences, and loss of credibility
with customers:
Usability: Web application users have grown to expect easy Web transactions—as simple as buying
a product at a store. Although much wisdom exists on how to develop usable software and Web sites,
many Web sites still do not meet most customers’ usability expectations.
Scalability: We must engineer Web software applications to be able to grow quickly in terms of
both how many users they can service and how many services they can offer. The need for
scalability has driven many technology innovations of the past few years. The industry has
developed new software languages, design strategies, and communication and data transfer
125
protocols in large part to allow Web sites to grow as needed.Availability: Availability not only
means that the web software is available at any time, but in todays environemnt it also must be
available when accessed by diverse browsers.
Maintainability: One novel aspect of Web-based software systems is the frequency of new
releases. Traditional software involves marketing, sales, and shipping or even personal installation
at customers’ sites. Because this process is expensive, software manufacturers usually collect
maintenance modifications over time and distribute them to customers simultaneously. For a
software product released today, developers will start collecting a list of necessary changes. For a
simple change, (say, changing a button’s label), the modification might be made immediately. But
the delay in releases means that customers won’t get more complex (and likely important)
modifications for months, perhaps years. Web-based software, however, gives customers immediate
access to maintenance updates - both small changes (such as changing the label on a button) and
critical upgrades can be installed immediately.
Web Engineering:
Conceptual Modeling:
A conceptual model can be defined as a model which is made of concepts and their relationships.
A conceptual model is the first step before drawing a UML diagram. It helps tounderstand
the entities in the real world and how they interact with each other.
As UML describes the real time systems it is very important to make a conceptual model and then
proceed gradually. Conceptual model of UML can be mastered by learning the following three
major elements:
UML building blocks
Rules to connect the building blocks
Common mechanisms of UML
Navigation Modeling : The navigation space model specifies, which objects can be visited through
navigation in the hypermedia application. In the process of building the navigation space model the
developer takes design decisions that are crucial, such as which view of the conceptual model is
needed for the application and what navigation paths are required to ensure the application’s
functionality. The decisions of the designer are based on the conceptual model, use case model and
the navigation requirements that the application must satisfy. The navigational structure model shows
how to navigate through the navigation space by using the access elements
Presentation Modeling: In the next step of our methodology we describe how the information
within the navigation space and the access structures are presented to the user. This is done by
constructing a presentation model which shows an abstract interface design similarly to a user
interface sketch. The presentation model focuses on the structural organization of the presentation
and not on the physical appearance in terms of special formats, colors.
126
Web Scenarios Modeling: The dynamic behaviour of any web scenarios including the navigation
scenarios are modeled here. The navigation structure model is detailed here showing all the sequences.
This modeling is done with the help of sequence, interaction diagram / collaboration digrams and state
chart diagrams.
Task Modeling: The task performed by the user or system are modeled here. Basically, the use-
cases as tasks are refined here. Since use-cases are refined by activity diagrams in UML, these
diagrams are used for task modeling. The modeling elements for task medeling are those for activity
diagrams i.e activities, transitions and branches.
Configuration Modeling: Since web systems are drivers and complex in nature, we need to
consider all the configuration and attributes that may be present on the client as well as on servers.
Deployement diagrams are used for configuration modeling.
Design Activities:
Interface Design: It considers the design of all interfaces recognized in the system including screen
layouts. Interfaces should be designed such that they are flexible, consistent, and readable.
Content Design: Content design is often a type of Web design and development that includes
selecting the right elements and organizing them in a coherent fashion. Content typically includes text,
static and animated graphics, sound and page layout.
Architecture Design: An overall system architecture describes how the network and variuous
servers (Web servers, application servers and database servers) interact.
Presentation Design: This design is related to the look and feel of the application. The design
issues are related to layout of the web pages, graphics to be inserted, color schemes, fonts etc..
Navigation Design: Navigational paths are designed such that usrs are able to navigate from one
place to another in the web application.
--Check if all the interactions between these servers are executed properly.
--Errors are handled properly.
--If database or web server returns any error message for any query by application server, then
application server should catch and display these error messages appropriately to users.
--Check what happens if user interrupts any transaction in-between?
--Check what happens if connection to web server is reset in between?
Usability Testing: Usability Testing concentrates on testing the web application in user point of
view. It includes different scenarios like:
Content checking: Content should be logical and easy to understand. Check for spelling errors.
127
Use of dark colors annoys users and should not be used in site theme. You can follow some
standards that are used for web page and content building. Content should be meaningful. All the
anchor text links should be working properly. Images should be placed properly with proper sizes.
These are some basic standards that should be followed in web development. Your task is to
validate all for UI testing
Content Testing:
Static contents can be checked as part of verification. For instance, Forms are the integral part of
any web site. Forms are used to get information from users and to keep interaction with them. First
check all the validations on each field. Check for the default values of fields and also wrong inputs
to the fields in the forms. Options to create forms if any, form delete, view or modify the forms
must also be checked.
There may be dynamic contents on a web page also. Largely dynamic testing will be suitable in
testing these dynamic contents. These dynamic contents can be in many forms. One possibility is
that constantly changing contents are there, e.g. weather information web pages or online news
paper. Another case may be that web applications are generated dynamically from information
contained in a data base or in a cookie.
Web page content should be correct without any spelling or grammatical errors
All fonts should be same as per the requirements.
All the text should be properly aligned.
All the error messages should be correct without any spelling or grammatical errors and the
error message should match with the field label.
Tool tip text should be there for every field.
All the fields should be properly aligned.
Enough space should be provided between field labels, columns, rows, and error messages.
All the buttons should be in a standard format and size.
Home link should be there on every single page.
Disabled fields should be grayed out.
Check for broken links and images.
Confirmation message should be displayed for any kind of update and delete operation.
Check the site on different resolutions (640 x 480, 600x800 etc.?)
Check the end user can run the system without frustration.
Navigation Testing: Navigation means how the user surfs the web pages, buttons, boxes or how
user using the links on the pages to surf different pages. To ensure the functioning of correct
sequence of navigations, navigation testing is performed on various possible paths. Design the test
cases such that the following navigations are correctly executing: Internal Links, External Links,
128
The following errors can be checked during the navigation testing for the following:
--The links should not be broken due to any reasons.
--The redirected links should be with proper messages displayed to the user.
--Check that all possible navigation paths are active.
--Check that all possible navigation paths are relevant.
--Check the navigations for the Back and Forward buttons, whether these are properly working if
allowed.
Compatibility Testing: Compatibility of your web site is a very important testing aspect. Different
types of features for compatability are:
Browser compatibility
Operating system compatibility
Mobile browsing
Browser Compatibility
Some applications are very dependent on browsers. Different browsers have different configurations
and settings that your web page should be compatible with. Your web site coding should be cross
browser platform compatible. We can perform Testing of web application on different browsers like
Internet Explorer, Firefox, Netscape Navigator, AOL, Safari, Opera browsers with different versions.
OS Compatibility:
Some functionality in your web application may not be compatible with all operating systems. All
new technologies used in web development like graphics designs, interface calls like different APIs
may not be available in all Operating Systems. Test your web application on different operating
systems like Windows, Unix, MAC, Linux, Solaris with different OS flavors.
Mobile Browsing:
This is the new technology age. So in future, Mobile browsing will rock. Test your web pages on
mobile browsers.
Security Testing: Today, the web applications store more vital data and the number of transactions
on the web has increased tremendously, with the increasing number of users. Therefore, in the
internet environemnt, the most challenging issue is to protect the web applications from hackers,
virus launchers.
Security Test Plan: Securing testing can be planned into two categories:
--Testing the security of the infrastructure hosting the Web application and
--Testing for vulnerabilities of the web application.
Firewalls and port scans can be the solution for security of infrastructure. For vulnerabilities, user
authentication, restricted and encrypted use of cookies, data communicated must be planned.
Moreover, users should not be able to browse through the directories in the server. Security Testing
involves the test to identify any flaws and gaps from a security point of view.
answers for security question etc should be submitted via HTTPS (SSL).
2. Verify the important information like password, credit card numbers etc should display in
encrypted format.
3. Verify password rules are implemented on all authentication pages like Registration, forgot
password, change password.
4. Verify if the password is changed the user should not be able to login with the old password.
5. Verify the error messages should not display any important information.
6. Verify if the user is logged out from the system or user session was expired, the user should not
be able to navigate the site.
7. Verify to access the secured and non secured web pages directly without login.
8. Verify the —View Source code¦ option is disabled and should not be visible to the user.
9. Verify the user account gets locked out if the user is entering the wrong password several
times.
10. Verify the cookies should not store passwords.
Performance Testing:
Performance testing is conducted to evaluate the compliance of a system or component with
specified performance requirements.
General Test scenarios:
To determine the performance, stability and scalability of an application under different load
conditions.
To determine if the current architecture can support the application at peak user levels.
To determine which configuration sizing provides the best performance level.
To identify application and infrastructure bottlenecks.
To determine if the new version of the software adversely had an impact on response time.
To evaluate product and/or hardware to determine if it can handle projected load volumes.
Performance Parameters:
--Resource utilization
--Throughput
--Response time
--Database load
--Scalability
--Round trip time
2. Diversity in Mobile Platforms/OSes: There are different mobile operating systems in the
131
market. The major ones are Android, iOS, Symbian, Windows Phone, and BlackBerry(RIM). Each
operating system has its own limitations. Testing a single application across multiple devices
running on the same platform and every platform poses a unique challenge for testers.
3. Device Availability: Access to the right set of devices when there is an ever-growing list of
devices and operating system versions is a constant mobile application testing challenge. Access to
devices can become even more challenging if testers are spread across different locations.
4. Mobile network operators: There are over 400 mobile network operators in the world;out of
which some are CDMA, some GSM.
5. Scripting: The variety of devices makes executing a test script (scripting) a key challenge. As
devices differ in keystrokes, input methods, menu structure and display properties single script does
not function on every device.
6. Choosing how to test: There are two main ways of testing mobile applications: testing on real
devices or testing on emulators. Unfortunately, neither method is flawless.[5] Emulators often miss
issues that can only be caught by testing on real devices, but because of the multitude of different
devices in the market, real devices can be expensive to purchase and time-consuming to use for
testing.
2. Laboratory Testing: Laboratory testing, usually carried out by network carriers, is done by
simulating the complete wireless network. This test is performed to find out any glitches when a
mobile application uses voice and/or data connection to perform some functions.
3. Performance Testing: This testing process is undertaken to check the performance and behavior
of the application under certain conditions such as low battery, bad network coverage, low available
memory, simultaneous access to application’s server by several users and other conditions.
4. Memory Leakage Testing: Memory leakage happens when a computer program or application is
unable to manage the memory it is allocated resulting in poor performance of the application and
the overall slowdown of the system. As mobile devices have significant constraints of available
memory, memory leakage testing is crucial for the proper functioning of an application
5. Interrupt Testing: An application while functioning may face several interruptions like
incoming calls or network coverage outage and recovery. The different types of interruptionsare:
Incoming and Outgoing SMS and MMS
Incoming and Outgoing calls
Incoming Notifications
Battery Removal
Cable Insertion and Removal for data transfer
6. Usability testing: Usability testing is carried out to verify if the application is achieving its goals
and getting a favorable response from users. This is important as the usability of an application is
its key to commercial success (it is nothing but user friendliness).
7. Installation testing: Certain mobile applications come pre-installed on the device whereas others
have to be installed from the store. Installation testing verifies that the installation process goes
132
smoothly without the user having to face any difficulty. This testing process covers installation,
133
Basics:
Terminology:
Object: An entity that has state and behaviour is known as an object e.g. chair, bike, marker, pen,
table, car etc. It can be physical or logical (tengible and intengible).
An object has three characteristics:
state: represents data (value) of an object.
Behavior: represents the behavior (functionality) of an object such as deposit, withdraw etc.
Identity: Object identity is typically implemented via a unique ID. The value of the ID is
not visible to the external user. But,it is used internally by the JVM to identify each object
uniquely.
Class:
A class is a group of objects that has common properties. It is a template or blueprint from which
objects are created.
A class in java can contain:
data member
method
constructor
block
class and interface
Inheritance: When one object acquires all the properties and behaviours of parent object i.e. known
as inheritance. It provides code reusability. It is used to achieve runtime polymorphism.
Polymorphism: When one task is performed by different ways i.e. known as polymorphism. For
example: to convense the customer differently, to draw something e.g. shape or rectangle etc.
Abstraction: Hiding internal details and showing functionality is known as abstraction. For
example: phone call, we don't know the internal processing.
Encapsulation: Binding (or wrapping) code and data together into a single unit is known as
encapsulation. For example: capsule, it is wrapped with different medicines.
Inheritance: Object-oriented programming allows classes to inherit commonly used state and
behavior from other classes. Different kinds of objects often have a certain amount in common with
each other. Mountain bikes, road bikes, and tandem bikes, for example, all share the characteristics
of bicycles (current speed, current pedal cadence, current gear). Yet each also defines additional
features that make them different.
UML is not a programming language but tools can be used to generate code in various languages
using UML diagrams. UML has a direct relation with object oriented analysis and design. After
some standardization UML is become an OMG (Object Management Group) standard.
User View:
The UML user model view encompasses the models which define a solution to a problem as
understood by the client or stakeholders. This view is often also referred to as the Use Case or
scenario view.
Structural View:
The UML structural view encompasses the models which provide the static, structural dimensions
and properties of the modelled system. This view is often also referred to as the static or logical
view. particular point in time.
Behavioural View:
These UML models describe the behavioural and dynamic features and methods of the modelled
system. This view is often also referred to as the dynamic, process, concurrent or collaborative
view. after completion of the elements as flows of processing within a system.
ImplementationView:
The UML Implementation View combines the structural and behavioural dimensions of the solution
realisation or implementation. The view is often also referred to as the component or development
view.
Environment View:
These UML models describe both structural and behavioural dimensions of the domain or
environment in which the solution is implemented. This view is often also referred to as the
deployment or physical view.
Use Case Model: These models depict the functionality required by the system and the interaction
of users and other elements (known as actors) with respect to the specific solution.
Use Case: A Use Case is a scenario that identifies and describe how the system will be used in
given situation.
Actors: Use Cases are typically related to 'actors', which are human or machine entities that use or
interact with the system to
perform a piece of
meaningful work that
helps them to achieve a
goal.
135
Class Diagrams: These models describe the static structure and contents of a system using
elements such as classes, packages and objects to display relationships such as containment,
inheritance and associations.
Object Diagrams: An object diagram represents the static structure of the system at a particular
instance of time.
Sequence Diagram: Describe timing sequence of the objects over a vertical time dimension with
interactions between objects depicted on a horizontal dimension.
Collaboration Diagrams: Describe the interactions and relationships between objects and sequences
of a system organised in time and space. Numbers are used to show the sequence of messages.
State Diagrams: Describe the sequence, status conditions and appropriate responses or actions to
conditions during the life of the objects within the system.
Component Diagrams: These depict the high level organisation and dependencies of source code
components, binary components and executable components and whether these components exist at
compile, link or run time.
Deployment Diagrams: These UML Models depict and describe the environmental elements and
configuration of runtime processing components, libraries and objects that will reside on them.
Unit Testing: In unit testing, the individual classes are tested. It is seen whether the class attributes are
implemented as per design and whether the methods and the interfaces are error-free. Unit testing is the
responsibility of the application engineer who implements the structure.
Subsystem Testing: This involves testing a particular module or a subsystem and is the responsibility
of the subsystem lead. It involves testing the associations within the subsystem as well as the
Interaction of the subsystem with the outside. Subsystem tests can be used as regression tests for each
newly released version of the subsystem.
System Testing: System testing involves testing the system as a whole and is the responsibility of the
quality-assurance team. The team often uses system tests as regression tests when assembling new
releases.
Grey Box Testing: The different types of test cases that can be designed for testing object-oriented
programs are called grey box test cases. Some of the important types of grey box testing are:
State model based testing: This encompasses state coverage, state transition coverage, and state
transition path coverage.
136
Use case based testing: Each scenario in each use case is tested.
Class diagram based testing: Each class, derived class, associations, and aggregations are tested.
Sequence diagram based testing : The methods in the messages in the sequence diagrams are tested.
Techniques for Subsystem Testing: The two main approaches of subsystem testing are:
Thread based testing : All classes that are needed to realize a single use case in a subsystem are
integrated and tested.
Use based testing : The interfaces and services of the modules at each level of hierarchy are tested.
Testing starts from the individual classes to the small modules comprising of classes, gradually to larger
modules, and finally all the major subsystems.
Quality Assurance: Software quality assurance is a methodology that determines the extent to which
a software product is fit for use. The activities that are included for determining software quality are:
Auditing
Development of standards and guidelines
Production of reports
Review of quality system
Quality Factors:
Correctness: Correctness determines whether the software requirements are appropriately met.
Usability: Usability determines whether the software can be used by different categories of users
(beginners, non-technical, and experts).
Portability: Portability determines whether the software can operate in different platforms with
different hardware devices.
Maintainability: Maintainability determines the ease at which errors can be corrected and modules can
be updated.
Reusability: Reusability determines whether the modules and classes can be reused for developing
other software products.Object-Oriented Metrics: Metrics can be broadly classified into three
categories: project metrics, product metrics, and process metrics.
Project Metrics: Project Metrics enable a software project manager to assess the status and
137
performance of an ongoing project. The following metrics are appropriate for object-oriented
software projects:
Number of scenario scripts
Number of key classes
Number of support classes
Number of subsystems
Product Metrics: Product metrics measure the characteristics of the software product that has been
developed. The product metrics suitable for object-oriented systems are:
Methods per Class: It determines the complexity of a class. If all the methods of a class are assumed to
be equally complex, then a class with more methods is more complex and thus more susceptible to
errors.
Inheritance Structure: Systems with several small inheritance lattices are more well–structured than
systems with a single large inheritance lattice. As a thumb rule, an inheritance tree should not have more
than 7 (± 2) number of levels and the tree should be balanced.
Coupling and Cohesion: Modules having low coupling and high cohesion are considered to be
better designed, as they permit greater reusability and maintainability.
Response for a Class: It measures the efficiency of the methods that are called by the instances of the
class.
Process Metrics: Process metrics help in measuring how a process is performing. They are
collected over all projects over long periods of time. They are used as indicators for long-term
software process improvements. Some process metrics are:
Number of KLOC (Kilo Lines of Code)
Defect removal efficiency
Average number of failures detected during testing
Number of latent defects per KLOC