Bid Form Fgu Builders
Bid Form Fgu Builders
Note : Please find attached detailed cost breakdown as per scopes of work.
Contractor Date:______________________
45-47 Rosas St., Jem Subd., Parang, Marikina City
Telefax : 89416831, Telephone : 89420435
Cellphone : +639228899704
E-mail : [email protected]
b. 2" CONCRETE TOPPING (Refer to Architectural Works) 2,054.09 sq.m. 337.50 470.40 693,253.69 966,241.58 1,659,495.27
c. STRUCTURAL STEEL
1.00 Steel columns 96,467.80 kg. 68.85 31.99 6,641,808.03 3,085,734.81 9,727,542.84
2.00 Steel beams 130,236.70 kg. 68.85 31.99 8,966,796.80 4,165,907.37 13,132,704.17
3.00 Roof framing works - kg. - - - - -
3.01 Steel trusses 8,424.90 kg. 68.85 79.97 580,054.37 673,722.40 1,253,776.77
3.02 Roof purlins 1.00 lot 179,831.42 115,071.51 179,831.42 115,071.51 294,902.93
3.03 Welding rods and consumables 1.00 lot 1,104,873.12 - 1,104,873.12 - 1,104,873.12
3.04 Anchor bolts 1.00 lot 317,151.45 133,951.10 317,151.45 133,951.10 451,102.55
3.05 Plate connections 1.00 lot 188,479.02 79,605.42 188,479.02 79,605.42 268,084.44
b. ROOFING WORKS
1.00 Flat Clay roof tiles lot - - - - BY OTHERS
1.01 Contractor's Admin/Supervision fee only lot - - - - -
1.02 Site preparation and installation lot - - - - -
2.00 Supply and installation of GA. 24 Prepainted longspan metal roof undersheeting with 50mm thk
rockwool roof insulation blanket, foil-faced on both sides with chicken wire mesh; to include all
necessary pre-painted bended materials (Ridge roll, flashing, etc) with complete accessories. lot - - - - BY OTHERS
Supply and installation of Ga. 22 prepainted GI roof eaves end trim on 3mm x 38mm steel flat bar
3.00 lot - - - - BY OTHERS
brackets spaced at 300mm (see detail)
Supply and installation of 12mm thk. Hardie Senepa Fascia Board, to include all necessary fixing
4.00 lm - - - - BY OTHERS
accessories.
SUB-TOTAL IV.b. -
4.01 Underground cistern 47.52 lnm 697.50 324.05 33,145.20 15,399.01 48,544.21
5.00 Supply and installation of 6 mils polyethylene sheet vapor barrier (300mm overlap) on 150mm thk
gravel bedding with 2' thk lean concrete topping
5.01 Slab on grade - sq.m. - - - - INCLUDED
6.00 Supply and installation of integral waterproofing ( Final brand for Architect's approval)
6.01 swimming pool & jacuzzi 15.79 cu.m 1,755.00 815.36 27,702.68 12,870.46 40,573.13
d. FLOOR FINISHES
1.00 Installation of Owner Supplied Floor Tile
1.01 Natural stone tiles (FF-01) 20.79 sq.m OSM 2,352.00 OSM 48,898.08 48,898.08
1.02 600mm x 1200mm Homogenous floor tiles (FF-02) 432.56 sq.m OSM 1,332.80 OSM 576,521.30 576,521.30
1.03 600mm x 60mm Homogenous floor tiles (FF-03) 300.40 sq.m OSM 1,332.80 OSM 400,371.79 400,371.79
1.04 450mm x900mm Homogenous floor tiles (FF-04) 181.21 sq.m OSM 1,332.80 OSM 241,522.02 241,522.02
1.05 Engineered wood flooring, to include complete underlays as recommended by supplier (FF- sq.m OSM - OSM - BY OTHERS
05)Using 12mm Marine Plywood as substrate sq.m - - - - BY OTHERS
WPC Floor Decking by Biowood, to include all necessary surface preparation and fixing
1.06 lot - - - - BY OTHERS
accessories (FF-06)
1.07 17.5 x 17.5 non-skid paver tiles (FF-07) 363.77 sq.m OSM 1,332.80 OSM 484,832.66 484,832.66
1.08 300mm x 600mm Non Skid Floor Tiles (FF-08) - sq.m OSM - OSM - N/A
1.09 Epoxy Floor Finish (FF-09) 28.86 sq.m 1,620.00 752.64 46,759.68 21,724.20 68,483.88
1.10 Solid Narra Plank (FF-10) - sq.m - - - - N/A
1.11 600mm x 600mm Homogenous Tile Non Skid (FF-11) 76.07 sq.m OSM 1,332.80 OSM 101,379.43 101,379.43
e. WALL FINISHES
1.00 600mm x 600mm Homogenous wall tiles 332.41 sq.m OSM 1,332.80 OSM 443,037.21 443,037.21
1.01 All toilets
2.00 Board formed concrete finish - sq.m 5,265.00 2,430.40 - - -
3.00 Plain plaster painted finish - sq.m - - - - INCLUDED IN PAINTING
4.00 Stone / Tile Wall Cladding 112.75 sq.m OSM 3,684.80 OSM 415,461.20 415,461.20
f. CEILING FINISHES
1.00 Supply and installation of 12mm thk. Boral (tapered-edge) gypsum board ceiling on standard metal
867.09 sq.m 1,296.00 627.20 1,123,743.46 543,836.34 1,667,579.80
ceiling frame, paint finish (CF-03)
2.00 Supply and installation of 12mm thk. moisture-resistant Boral (tapered-edge) gypsum board ceiling on
136.08 sq.m 1,539.00 627.20 209,428.66 85,350.00 294,778.66
standard metal ceiling frame, paint finish (CF-02)
3.00 Supply and installation of exposed slab soffit, smooth plaster painted finish (CF-00) 176.75 sq.m 405.00 470.40 71,582.94 83,142.26 154,725.20
4.00 Supply and installation of from 1"x6" Biowood roof ceiling eaves on metal ceiling furrings spaced at
1.00 lot - - - - BY OTHERS
300mm OC, to include complete mounting accessories
5.00 Supply and Installation of 6mm thk Fiber Cement Board on LGS framing off White Paint Finish
68.62 sq.m 1,620.00 627.20 111,161.16 43,037.21 154,198.37
(USING 6MM FIBERCEMENT) (CF-04)
2.00 WINDOWS
REFER TO FINAL WINDOW SCHEDULE. BY OTHERS
Supply and installaiton of 2"x14"x4' KD Narra wooden stair treads, to include complete mounting lm
1.00 31.35 21,439.72 1,960.63 672,135.30 61,465.60 733,600.90
accessories, as shown on detials.
Supply and installation of from 1"x6"x4' KD Narra wooden stair riser cladding, to include complete lm
2.00 - - - - - N/A
mounting accessories, as shown on details.
3.00 Supply and installation of 1"x2" creosoted wood sleeper for stair treads - lm - - - - N/A
Supply and installation of from 2"x3" Narra Handrail, varnish finish; to include complete mounting
4.00 66.20 lm 1,418.20 274.76 93,881.70 18,188.80 112,070.50
accessories, as shown on details.
i. SPECIALTIES
SUB-TOTAL IV.i. -
j. PAINTING WORKS
1.00 Wall Painting (Interior) 2,056.77 sq.m 405.00 470.40 832,993.15 967,506.12 1,800,499.27
2.00 Wall Painting (Exterior) 453.97 sq.m 472.50 548.80 214,501.01 249,138.95 463,639.95
3.00 Ceiling (Latex Painting) 1,071.79 sq.m 405.00 470.40 434,072.93 504,167.66 938,240.59
4.00 Doors - sq.m - - - - -
a. Duco - sq.m - - - - N/A
b. Varnish 177.83 sq.m 607.50 705.60 108,029.30 125,474.03 233,503.32
c. QDE - sq.m - - - - N/A
d. Epoxy ( for Steel Doors Only) 20.68 sq.m 607.50 705.60 12,563.10 14,591.81 27,154.91
5.00 Stair tread, handrails, wood planks, eaves
a. Varnish finish 95.04 sq.m 607.50 705.60 57,736.80 67,060.22 124,797.02
6.00 Canopy steel frame, exterior steel railing, steel roof trusses, purlins (Using Epoxy Primer) 1,898.60 sq.m 202.50 235.20 384,466.50 446,550.72 831,017.22
7.00 Others to complete the work (please identify) - sq.m - - - - -
Sanding works for Stair Threads Narra 64.42 sq.m - 3,292.80 - 212,109.00 212,109.00
2.00 50mmx 150mm C-Channel ledge end trim, to include complete mounting accessories, epoxy paint finish kgs - - - - INCLUDED
3.00 Supply and installation of 10mm thk clear tempered glass canopy on stainless steel mounting pins, to lot
- - - - BY OTHERS
include all necessary mounting accessories
4.00 Supply and installation of 50mm x 12mm thk steel flatbar stair hand rail on 2x 50mm x 12mm thk steel lot
flatbar vertical balusters and 16mm square steel bar horizontal balustrade, epoxy paint finish; to include 1.00 81,069.12 34,240.10 81,069.12 34,240.10 115,309.22
complete mounting accessories.
5.00 Supply and installation of steel canopy frame, as shown on details, to include all necessary mounting lot
- - - - INCLUDED
accessories, epoxy paint finish
6.00 Supply and installation of CHB perimeter fence @ 2.00m high, to include 300mm x 300mm RC fence lot
columns, plaster and painted finish, complete with all necessary accessories, as shown on the plans 1.00 - - - - NO DETAIL
7.00 lot
Supply and installation of steel gate, 50mm x 100mm x t=1.5mm steel frame, to include heavy-duty
1.00 96,503.40 41,043.97 96,503.40 41,043.97 137,547.37
pillow block and complete mounting accessories (verify approved design), epoxy paint finish
sub-total
sub-total
sub-total
sub-total
VI. PLUMBING WORKS (Refer to attached Plumbing Works Bidform) 1.00 lot
VII. MECHANICAL WORKS ( Refer to attached Mechanical Works Bidform) 1.00 lot
T O T A L P R O J E C T C O S T
NOTE:
THIS SCOPE OF WORK SHALL SERVE AS A GUIDE FOR EVALUATION OF THE WORK AND PROGRESS
PAYMENTS BUT SHALL NOT BE CONSTRUED AS THE EXCLUSION FROM THE SCOPE OF WORK. ALL ITEMS
CALLING FOR LABOR AND MATERIAL NOT LISTED ABOVE BUT CALLED FOR IN THE PLANS, DETAILS,
AND SPECIFICATIONS SHALL BE DEEMED AS PART OF THE SCOPE OF WORK AND SHALL BE
ACCOMPLISHED BY THE CONTRACTOR AS IF MENTIONED ABOVE.
Submitted by:
PROJECT : PROPOSED 2-STOREY RESIDENCE
LOCATION : Avocado Street, Ayala Alabang, Muntinlupa City
OWNER : MR. & MRS. MANUEL PALAGANAS
SUBJECT : BID FORM
DATE : NOVEMBER 24, 2023
I. POWER SYSTEM
A. Distribution, Power and Lighting Panel "Gentec", "LJ" or
"Systems PowerMark" with Molded Case Circuit Breaker
"ABB", "Eaton", "GE", "Schneider" or "Siemens".
Complete in place.
SUB-TOTAL (I.A) -
SUB-TOTAL (I.B) -
SUB-TOTAL (I.C) -
SUB-TOTAL (I.D-2) -
SUB-TOTAL (I.E) -
SUB-TOTAL (I.F) -
SUB-TOTAL (I.G) -
SUB-TOTAL (I.H) -
SUB-TOTAL (II.A) -
SUB-TOTAL (II.B) -
SUB-TOTAL (II.C-1) -
SUB-TOTAL (II.C-2) -
SUB-TOTAL (II.D) -
SUB-TOTAL (II.E) -
SUB-TOTAL (II.F) -
SUB-TOTAL (II.G) -
SUB-TOTAL (III.A-1) -
SUB-TOTAL (III.A-2) -
SUB-TOTAL (IV.A) -
SUB-TOTAL (IV.B) -
SUB-TOTAL (IV.C-1) -
SUB-TOTAL (IV.C-2) -
SUB-TOTAL (IV.D) -
SUB-TOTAL (IV.E) -
SUB-TOTAL (CCTV SYSTEM) -
T O T A L P R O J E C T C O S T -
Amount in Words
Notes:
1. All unit costs shall include the direct cost of materials, labor and mark-up including VAT.
2. lm - linear meter
PROJECT : PROPOSED 2-STOREY RESIDENCE
LOCATION : Avocado Street, Ayala Alabang, Muntinlupa City
OWNER : MR. & MRS. MANUEL PALAGANAS
SUBJECT : BID FORM
DATE : NOVEMBER 24, 2023
a. Water closets
a.1 Flush tank 14 sets
b. Lavatory
b.1 Counter top 16 sets
c. Shower and in-bath fittings 10 sets
d. Toilet accessories (please identify):
d.1 Toilet paper holder sets
d.2 hook sets
e. Bath tub 1 sets
f. Kitchen sink and kitchen faucets, to include complete
mounting accessories 2 sets
d. Grease Trap Cap. = 7GPM 2 sets
b. Gate Valves
- 20 mm. dia.. 0 pcs
- 25 mm. dia.. 25 pcs
- 32 mm. dia.. 0 pcs
- 40 mm. dia.. 9 pcs
c. Check Valves
- 40 mm. dia.. 3 pcs
d. Y-strainer
- 40 mm. dia.. 3 pcs
e. Water Meter
- 25 mm. dia. 1 pcs
f. Hose Bibb
- 20 mm. dia.. 0 pcs
g. Float Valve
- 25 mm. dia.. 1 pcs
b. Floor Drains
- 50 mm. dia.. 30 pcs
f. Perforated Pipes
- 50 mm. dia.. 36 lm
i. Balcony Draiins
- 50 mm. dia.. 7 pcs
Diaphragm Tank
Cap. 1 sets
Instantaneous Type
Multi Point EWH 4 sets
SUB-TOTAL OTHERS
T O T A L P R O J E C T C O S T
UNIT COST SUBTOTAL COST
TOTAL AMOUNT
MATERIAL LABOR MATERIAL LABOR
OSM - OSM - -
OSM - OSM - -
OSM 4,146.59 OSM 4,146.59 4,146.59
113,616.60
- - - - -
425.25 318.81 125,874.00 94,368.32 220,242.32
- - - - -
1,080.00 808.94 120,960.00 90,601.71 211,561.71
- - - - -
978.75 734.14 24,468.75 18,353.55 42,822.30
- - - - -
2,038.50 1,528.46 18,346.50 13,756.12 32,102.62
- - - - -
580,693.28
656,208.98
- - - - -
- - - - -
3,358.80 2,494.52 221,680.80 164,638.22 386,319.02
5,522.85 4,104.38 149,116.95 110,818.39 259,935.34
15,187.50 11,283.30 15,187.50 11,283.30 26,470.80
- - - - -
- - - - -
1,533,147.15
43,124.55
957,847.27
3,884,637.83 #REF!
PROJECT : PROPOSED 2-STOREY RESIDENCE
LOCATION : Avocado Street, Ayala Alabang, Muntinlupa City
OWNER : MR. & MRS. MANUEL PALAGANAS
SUBJECT : BID FORM
DATE : NOVEMBER 24, 2023
E. Wall Caps
1.0 100mm diameter
2.0 150mm diameter
3.0 200mm diameter
G. Duct tape
H. Duct clips
H. Adhesives
I. Duct Sealants
J. Canvass cloth
B. Pipe Insulation
1.0
2.0
3.0
4.0
5.0
C. Filters
1.0
2.0
3.0
D. Sight glass
1.0
2.0
3.0
F. Consumables
G. Refrigerant charge
C. Ventilating Fans
1.0 EF-1 CEILING CASSETTE TYPE @ 50 CFM
2.0 EF-2 CEILING CASSETTE TYPE @ 70 CFM
3.0 EF-3 CEILING CASSETTE TYPE @ 100 CFM
4.0 EF-4 CEILING CASSETTE TYPE @ 150 CFM
5.0 EF-5 CEILING CASSETTE TYPE @ 200 CFM
6.0 EF-6 INLINE TYPE KFAN @ 1800 CFM
7.0 KEF-1 RANGE HOOD TYPE @ 800 CFM
8.0 OF-1 OSCILLATING FAN @ 1,500 CFM
BID SUMMARY
I. DUCT WORKS
II. REFRIGERANT PIPING & ACCESSORIES
III. MECHANICAL EQUIPMENTS
IV. GENERAL EXPENSES
lot - - - - INCLUDED
pcs. - - - - INCLUDED
pcs. - - - - INCLUDED
gal - - - - INCLUDED
gal. - - - - INCLUDED
roll - - - - INCLUDED
pcs. - - - - -
pcs. - - - - -
pcs. - - - - -
pcs. - - - - -
412,202.41
pc. - - - - -
pc. - - - - -
pc. - - - - -
pc. - - - - -
pc. - - - - -
pc. - - - - -
lot - - - - -
kg. - - - - -
1,413,929.21
1 pcs. 113,562.54 3,669.12 113,562.54 3,669.12 117,231.66
1 pcs. 115,080.62 2,751.84 115,080.62 2,751.84 117,832.46
1 pcs. 121,328.42 2,751.84 121,328.42 2,751.84 124,080.25
9 pcs. 146,424.92 2,751.84 1,317,824.24 24,766.56 1,342,590.80
5 pcs. 163,897.70 2,751.84 819,488.48 13,759.20 833,247.68
7 pcs. 251,331.80 2,751.84 1,759,322.57 19,262.88 1,778,585.45
pcs.
- - - - INCLUDED
pcs.
- - - - INCLUDED
pcs.
- - - - INCLUDED
pcs.
- - - - INCLUDED
pcs.
- - - - INCLUDED
pcs.
- - - - INCLUDED
pcs.
1 210,573.68 2,751.84 210,573.68 2,751.84 213,325.52
6,529,276.85