Next Week Plan
Next Week Plan
1 Transformer -01
Next w
Total
Sr.No. Work Description Unit
Quantity
94 10 10 0
80 30 30 10
9 15 9 14
8 16 4 4 5 5 5
10 14 3 3 5 4 2
0 2 1 0 1
0 8 4 4 4
0 8 4 0
0 16
0 8
0 8 8 8
0 8 8 0
0 8 8 0
0 8 4
0 8
0 16
0 8
60 80 30 10 10 0 20
0 60 30
0 60
0 60
60 24 10 10 14 14
50 34 10 10 10
0 26 6 0 6 0 8
0 84 15 15
4 3 3 2
2 5 3 4
2 5 2
to 11-02-2024)
2/8/2024 2/9/2024 2/10/2024 2/11/2024
Till date
A P A P A P A complete
10
14
2 9
4 7
0 0
A P A P A P A
4 8
4 0 0
8 0 8 0 0
4 0 4 0
0
0
0 4 0
0
8 0
0
8 0 8 0
0
8
0 10 0 10 0 10
30
60
30 30
24
10 14 14 34
0
0 6 0
30 24
2
2 4
2 2 2 1 4
Over all
% of % of completion over
completion Reason For Delay
completion all
till date
Material received at
0% 94 90% site on (10-02-24)
febrication wip
56% 17 71%
Under progress
50% 17 71%
under progress
material ordering
0% 0 0%
under progress
100% 8 100%
Completed
0% 0 0% Material available
filling under progress
0% 0 0% Depend upon point no
B
0% 0 0% Depend upon point no
B
0% 0 0% Depend upon point no
B
0% 0 0% Depend upon point no
B
0% 0 0% Depend upon point no
B
13% 70 33%
1 Transformer -01
Total
Sr.No. Work Description Unit Quantity
94 10 4 0 6 0
90 20 20 0
23 1 1 1
17 7 3 3 4 2
17 7 3 2 4 0
0 2 1 0 1
0 8 8 0
0 16 8 0 8
0 8
0 8 8 8
0 8 8 8
0 8 4 0 4
0 8
0 16
0 8
0 70 10 0 30 0 30 0
0 70 70 0
0 70 20
0
70
7 81 15 15 15 0 15
0 57 7 0 10 0 15
0 26 6 0 8
0 84 15 0 15
0
6 1 1 0
6 1 1 0
6 1 1
OLBAGH-RSS(12-02-2024 to 18-02-2024)
2/15/2024 2/16/2024 2/17/2024 2/18/2024
A P A P A P A
2 1
10 10
02-24 to 18-02-2024)
2/15/2024 2/16/2024 2/17/2024 2/18/2024
A P A P A P A
0
8 0
0
8 0
8 0 8 0
8 0
0 20 0 20 0 10 0
40 0 30 0
0 15 0 21 0
0 15 0 10 0
0 6 0 6 0
0 15 0
0
Over all
completion till % of completion over all Reason For Delay
date
0 0%
0 0%
0 0% Materials recive from date 18/02/24
100%
8
8 100%
0 0%
0 0%
Materials available 18/02/24
0 0%
0 0%
0 0%
0 0%
0 0% Due to Drg. Pending
0%
0
25%
22
0 0% Due less manpower
0 0%
0 0%
0 0%
0 0%
0 0% still Weight bridge not shiffted
Sr.No. Work Description Unit Total
Quantity
1 Transformer -01
A Jali Painting & Fixing for Trafo-01 Catchpit Nos 104
Total
Sr.No. Work Description Unit
Quantity
Gaurd Room
Excvation Meter 27
PCC Meter 18
Raft Reinforcement Lot 1
Raft Shuttering work Meter 18
Raft Casting work Lot 1
Water Proofing GIS Roof Slab
Deep Cleaning Sqm 238
Gola of Parapit Sqm 64.8
Primer (01 coat) Sqm 238
Water Proofing (1st Coat) Sqm 238
Water Proofing -(02 Coat) Sqm 238
C Meter 8
Concreting of 02nd stage
Completed Planned
This Week P A P A P A
97 7 4 3 3 2 1
100 10 10 0
24 0
22 2 2 0
19 5 3 2
0 2 1 1
Completed Planned
This Week P A P A P A
20 7 7 7
18 18
0 1 0.5 0.5
0 18
0 1
0 238
0 238
0 8 8 0
0 16 8 0 8 0
0 8
0 4 4 4
0 8 4
8 0
0 8
0 16
0 8
10 0 30 0
0 70
0 70
0 70
0 70
0 15 0 21 0
37 51 15
20 20 0
0 88 20
6 0
0 26
15 0 14 0
0 84
1 0
6 1
1 0
6 1
6 1
N OF CIVIL,PHOOLBAGH-RSS(12-02-2024 to 18-02-2024)
2/22/2024 2/23/2024 2/24/2024 2/25/2024
P A P A P A P A
1 2
P A P A P A P A
18
10 10 8 8
1 1
140 238 98
238 238
8 0
8 0 8 4
8 0
30 0
30 0 40 0
20 20 0 20 0 10 0
40 0 30 0
15 0 15 0 18 0
8 0 6 0 6 0
15 0 20 0 10 0 10 0
1 0
)
Till date
% of completion Over all completion till date % of completion over all
complete
0 0% 100 91%
0 24 100%
0%
3 60% 22 92%
0% 0%
0 0
7 100% 27 100%
18 100% 18 100%
1 100% 1 100%
18 100% 18 100%
1 100% 1 100%
0 0% 0 0%
0 0% 0 0%
0 0% 0 0%
8 100% 8 100%
0 0% 0 0%
4 25% 4 25%
0 0% 0 0%
0
0
0 0% 0 0%
0 0% 0 0%
0 0% 0 0%
0 0% 0 0%
0
0
0 0% 37 42%
20 23% 20 23%
0 0% 0 0%
0 0% 0 0%
0 0
0
0 0% 6 86%
0 0% 6 86%
0 0% 6 86%
Reason For Delay
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
1 Transformer -01
B Gravell filling Sqm 110 100 10 10
1 Gaurd Room
Backfilling of Soil.
Meter 27 0 27 27
Plinth PCC
Meter 20.2 0 20.2 20.2
PCC Meter 16 0 16 16
Casting Meter 16 0 16 16