Next Week Plan

Uploaded by

Sumanta Das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views33 pages

Next Week Plan

Uploaded by

Sumanta Das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 33

BACKLOG DELAY WORK P

Sr.No. Work Description Unit Total


Quantity

1 Transformer -01

A Jali Painting & Fixing for Trafo-01 Catchpit Nos 104

B Gravell filling Sqm 110

Front side BW towards Temple (15)m length


2 below FGL
A Panel Erection Nos 24

C Column shuttering above FGL beam between Nos 24


panel

D Column casting above FGL beam between panle Nos 24

5 Readyness of Gents Toilet


A Toilet Sheet & Wash Basin Fittings of Gents Toilet Nos 2

Next w
Total
Sr.No. Work Description Unit
Quantity

1 Construction of Rail cum Road infront of Trafo-


02
A Steel binding including Lugs fixing Meter 8
B Meter 8
Side shuttering & 01st stage concreting
C Rail fixing including alignment Meter 16
D Meter 8
Concreting of 02nd stage

2 Construction of Rail cum Road infront of Trafo-


01
A Base prepration & PCC
Meter 8

B Soling in 300 mm thick


Meter 8
C
PCC Over soling Meter 8
D
Steel binding including Lugs fixing Meter 8
E
Side shuttering & 01st stage concreting Meter 8
F
Rail fixing including alignment Meter 16
G
Concreting of 02nd stage Meter 8

3 Internal Drainage towards Colony side BW


A PCC of Drain Meter 210
B Brickwork / RCC Meter 210
C Bottom finishing / RCC Meter 210
D Internal Plaster / RCC Meter 210

4 Coping over Colony side BW


A Beam steel binding Meter 84
B Side & Bottom shuttering of beam Meter 84
C
Fixing of Y Angle Nos 26
D
Casting of Coping beam Meter 84

5 Weight Bridge side BW


A Column shuttering Nos 7
B Column casting Nos 7
C De shuttering Nos 7
DELAY WORK PLAN OF CIVIL,PHOOLBAGH-RSS(05-02-2024 to 11-02-2024)
2/5/2024 2/6/2024 2/7/2024 2/8/2024
Planned
Complete This
d P A P A P A P
Week

94 10 10 0

80 30 30 10

9 15 9 14

8 16 4 4 5 5 5

10 14 3 3 5 4 2

0 2 1 0 1

Next week plan of (05-02-24 to 11-02-2024)


2/5/2024 2/6/2024 2/7/2024 2/8/2024
Planned
Complete This
d Week P A P A P A P

0 8 4 4 4
0 8 4 0

0 16
0 8

0 8 8 8

0 8 8 0

0 8 8 0

0 8 4

0 8

0 16

0 8

60 80 30 10 10 0 20
0 60 30
0 60
0 60

60 24 10 10 14 14
50 34 10 10 10

0 26 6 0 6 0 8

0 84 15 15

4 3 3 2
2 5 3 4
2 5 2
to 11-02-2024)
2/8/2024 2/9/2024 2/10/2024 2/11/2024
Till date
A P A P A P A complete

10

14

2 9

4 7

0 0

2/8/2024 2/9/2024 2/10/2024 2/11/2024

A P A P A P A

4 8

4 0 0

8 0 8 0 0
4 0 4 0
0

0
0 4 0
0
8 0
0
8 0 8 0
0
8

0 10 0 10 0 10
30
60

30 30

24
10 14 14 34

0
0 6 0

30 24

2
2 4
2 2 2 1 4
Over all
% of % of completion over
completion Reason For Delay
completion all
till date

Material received at
0% 94 90% site on (10-02-24)
febrication wip

33% 90 82% Material available but


can not complete
without completion of
Point no A

balance (01) hold due


93% 23 96%
to excess issue

56% 17 71%
Under progress

50% 17 71%
under progress

material ordering
0% 0 0%
under progress

100% 8 100% Completed


0% 0 0% Delay due to
manpower issue
0% 0 0% Depend upon point no
B&C
0% 0 0% Depend upon point no
B

100% 8 100%
Completed

0% 0 0% Material available
filling under progress
0% 0 0% Depend upon point no
B
0% 0 0% Depend upon point no
B
0% 0 0% Depend upon point no
B
0% 0 0% Depend upon point no
B
0% 0 0% Depend upon point no
B

13% 70 33%

Delay due to changes


in drawing

100% 84 100% completed


100% 84 100% completed
0% 0 0% Febrication under
progress
depend upon point no
D

67% 6 86% under progress


80% 6 86% under progress
80% 6 86% under progress
Sr.No. Work Description Unit Total
Quantity

1 Transformer -01

A Jali Painting & Fixing for Trafo-01 Catchpit Nos 104

B Gravell filling Sqm 110

Front side BW towards Temple (15)m length


2 below FGL
A Panel Erection Nos 24
Column shuttering above FGL beam between
B Nos 24
panel

C Column casting above FGL beam between panle Nos 24

3 Readyness of Gents Toilet


A Toilet Sheet & Wash Basin Fittings of Gents Toilet Nos 2

Total
Sr.No. Work Description Unit Quantity

1 Construction of Rail cum Road infront of Trafo-


02
A Side shuttering & 01st stage concreting Meter 8
B Rail fixing including alignment Meter 16
C Concreting of 02nd stage Meter 8

2 Construction of Rail cum Road infront of Trafo-


01
A Soling in 300 mm thick
Meter 8
B PCC Over soling Meter 8
C Steel binding including Lugs fixing Meter 8
D Side shuttering & 01st stage concreting Meter 8
E Rail fixing including alignment Meter 16
F Concreting of 02nd stage Meter 8

3 Internal Drainage towards Colony side BW


A Steel binding + shuttering (Raft + Wall) Meter 210
B Raft casting Meter 210
C Wall shuttering both side Meter 210
D Wall casting Meter 210

4 Coping over Front side BW

A Coping steel binding Meter 88


B side shuttering & casting Meter 88
C Fixing of Y Angle Nos 26
D Casting of Coping beam Meter 84

5 Weight Bridge side BW


A Column shuttering Nos 7
B Column casting Nos 7
C De shuttering Nos 7
BACKLOG DELAY WORK PLAN OF CIVIL,PHOOLBAGH-RSS(1
2/12/2024 2/13/2024 2/14/2024 2/15/2024
Planned
Complete This
d P A P A P A P
Week

94 10 4 0 6 0

90 20 20 0

23 1 1 1

17 7 3 3 4 2

17 7 3 2 4 0

0 2 1 0 1

Next week plan of (12-02-24 to 18-02-2


2/12/2024 2/13/2024 2/14/2024 2/15/2024
Planned
Complete
d This
P A P A P A P
Week

0 8 8 0
0 16 8 0 8
0 8
0 8 8 8
0 8 8 8
0 8 4 0 4
0 8
0 16
0 8

0 70 10 0 30 0 30 0
0 70 70 0
0 70 20
0
70

7 81 15 15 15 0 15
0 57 7 0 10 0 15
0 26 6 0 8
0 84 15 0 15
0

6 1 1 0
6 1 1 0
6 1 1
OLBAGH-RSS(12-02-2024 to 18-02-2024)
2/15/2024 2/16/2024 2/17/2024 2/18/2024

A P A P A P A

2 1

10 10

02-24 to 18-02-2024)
2/15/2024 2/16/2024 2/17/2024 2/18/2024

A P A P A P A

0
8 0
0
8 0
8 0 8 0
8 0

0 20 0 20 0 10 0

40 0 30 0

0 15 0 21 0
0 15 0 10 0
0 6 0 6 0
0 15 0

0
Over all
completion till % of completion over all Reason For Delay
date

Due non availablity of materials till


97 93.3
17/02/24

Due non availablity of materials till


100 90.9
17/02/24 balance work in progress

24 100% 100% completed

22 92% due to less manpower

19 79% due to less manpower

0% Due non availablity of materials


0

0 0%
0 0%
0 0% Materials recive from date 18/02/24
100%
8
8 100%
0 0%
0 0%
Materials available 18/02/24
0 0%
0 0%

0 0%
0 0%
0 0% Due to Drg. Pending

0%
0

25%
22
0 0% Due less manpower
0 0%
0 0%

0 0%
0 0%
0 0% still Weight bridge not shiffted
Sr.No. Work Description Unit Total
Quantity

1 Transformer -01
A Jali Painting & Fixing for Trafo-01 Catchpit Nos 104

B Gravell filling Sqm 110

Front side BW towards Temple (15)m length


2 below FGL
A Panel Erection Nos 24
Column shuttering above FGL beam between
B panel Nos 24

C Column casting above FGL beam between panle Nos 24

3 Readyness of Gents Toilet

A Toilet Sheet & Wash Basin Fittings of Gents Toilet Nos 2

Total
Sr.No. Work Description Unit
Quantity

Gaurd Room

Excvation Meter 27
PCC Meter 18
Raft Reinforcement Lot 1
Raft Shuttering work Meter 18
Raft Casting work Lot 1
Water Proofing GIS Roof Slab
Deep Cleaning Sqm 238
Gola of Parapit Sqm 64.8
Primer (01 coat) Sqm 238
Water Proofing (1st Coat) Sqm 238
Water Proofing -(02 Coat) Sqm 238

1 Construction of Rail cum Road infront of Trafo-


02
A Meter 8
Side shuttering & 01st stage concreting
B Rail fixing including alignment Meter 16

C Meter 8
Concreting of 02nd stage

2 Construction of Rail cum Road infront of Trafo-


01
C
Steel binding including Lugs fixing Meter 8
D
Side shuttering & 01st stage concreting Meter 8
E
Rail fixing including alignment Meter 16
F
Concreting of 02nd stage Meter 8

3 Internal Drainage towards Colony side BW

A Steel binding + shuttering (Raft + Wall) Meter 210

B Raft casting Meter 210

C Wall shuttering both side Meter 210


D Wall casting Meter 210

4 Coping over Front side BW

A Coping steel binding Meter 88

side shuttering & casting Meter 88


C
Fixing of Y Angle Nos 26
D
Casting of Coping beam Meter 84

5 Weight Bridge side BW


A
Column shuttering Nos 7
B
Column casting Nos 7
C
De shuttering Nos 7
BACKLOG DELAY WORK PLAN OF CIVIL,PH
2/19/2024 2/20/2024 2/21/2024

Completed Planned
This Week P A P A P A

97 7 4 3 3 2 1

100 10 10 0

24 0

22 2 2 0

19 5 3 2

0 2 1 1

Next week plan of (12


2/19/2024 2/20/2024 2/21/2024

Completed Planned
This Week P A P A P A

20 7 7 7

18 18

0 1 0.5 0.5

0 18
0 1

100 138 138 138


0 64.8 50 50 14.8 14.8

0 238 238 238

0 238
0 238

0 8 8 0

0 16 8 0 8 0

0 8

0 4 4 4
0 8 4
8 0
0 8

0 16

0 8

10 0 30 0
0 70

0 70

0 70
0 70

0 15 0 21 0
37 51 15
20 20 0
0 88 20
6 0
0 26
15 0 14 0
0 84
1 0
6 1
1 0
6 1

6 1
N OF CIVIL,PHOOLBAGH-RSS(12-02-2024 to 18-02-2024)
2/22/2024 2/23/2024 2/24/2024 2/25/2024

P A P A P A P A

1 2

ek plan of (12-02-24 to 18-02-2024)


2/22/2024 2/23/2024 2/24/2024 2/25/2024

P A P A P A P A

18

10 10 8 8

1 1
140 238 98

238 238

8 0

8 0 8 4

8 0

30 0

30 0 40 0

20 20 0 20 0 10 0

40 0 30 0

15 0 15 0 18 0

8 0 6 0 6 0

15 0 20 0 10 0 10 0
1 0
)
Till date
% of completion Over all completion till date % of completion over all
complete

7 100% 104 100%

0 0% 100 91%

0 24 100%

0%

3 60% 22 92%

0% 0%
0 0

7 100% 27 100%

18 100% 18 100%

1 100% 1 100%

18 100% 18 100%

1 100% 1 100%

138 100% 238 100%


64.8 100% 64.8 100%

238 100% 238 100%

238 100% 238 100%

238 100% 238 100%

0 0% 0 0%

0 0% 0 0%

0 0% 0 0%

8 100% 8 100%

0 0% 0 0%

4 25% 4 25%

0 0% 0 0%

0
0

0 0% 0 0%

0 0% 0 0%

0 0% 0 0%

0 0% 0 0%
0
0

0 0% 37 42%

20 23% 20 23%

0 0% 0 0%

0 0% 0 0%

0 0
0
0 0% 6 86%

0 0% 6 86%

0 0% 6 86%
Reason For Delay

Completed

Due to non availablity of


manpower

Completed

Due to non avability of


manpower

20% materials available


(accessories not available

Completed

Completed

Completed

Completed

Completed

Completed
Completed

Completed

Completed

Completed

Due to non avability of


manpower
Due to non avability of
manpower
Due to non avability of
manpower

Due to non avability of


manpower
Due to non avability of
manpower
Due to non avability of
manpower
Due to non avability of
manpower

Due to non avability of


manpower
Due to non avability of
manpower
Due to non avability of
manpower
Due to non avability of
manpower

Due to non avability of


manpower
Due to non avability of
manpower
Due to non avability of
manpower
Due to non avability of
manpower
Due to non avability of
manpower
Due to non avability of
manpower
Due to non avability of
manpower
BACKLOG DELAY WORK PLAN OF CIVIL,PHOOLBAGH-RSS(26-02-2024 to 03-03-2024)
2/26/2024 2/27/2024 2/28/2024 2/29/2024 3/1/2024 3/2/2024 3/3/2024
Total Planned
Sr.No. Work Description Unit Completed
Quantity This Week P A P A P A P A P A P A P A

1 Transformer -01
B Gravell filling Sqm 110 100 10 10

Front side BW towards Temple (15)m length


2 below FGL
Column shuttering above FGL beam between
B Nos 24 22 2 2
panel

C Column casting above FGL beam between panle Nos 24 22 2 2

3 Readyness of Gents Toilet 0

A Toilet Sheet & Wash Basin Fittings of Gents Toilet Nos 2 0 2 1 1

1 Construction of Rail cum Road infront of Trafo-


02
A Side shuttering & 01st stage concreting Meter 8 0 8 8
B Rail fixing including alignment Meter 16 0 16 8 8
C Concreting of 02nd stage Meter 8 0 8 8
2 Construction of Rail cum Road infront of Trafo-01
C Steel binding including Lugs fixing Meter 8 4 4 4
D Side shuttering & 01st stage concreting Meter 8 0 8 8
E Rail fixing including alignment Meter 16 4 12 8 4
F Concreting of 02nd stage Meter 8 0 8 8 8

3 Internal Drainage towards Colony side BW


A Steel binding + shuttering (Raft + Wall) Meter 210 0 70 10 30 30
30 40
B Raft casting Meter 210 0 70
20 20 20 10
C Wall shuttering both side Meter 210 0 70
D Wall casting Meter 210 0 70 40 30

4 Coping over Front side BW


A Coping steel binding Meter 88 37 51 15 15 21

side shuttering & casting Meter 88 20 68 20 20 14 14

C Fixing of Y Angle Nos 26 0 26 6 8 6 6

D Casting of Coping beam Meter 84 0 84 15 14 15 20 10 10

5 Weight Bridge side BW


A Column shuttering Nos 7 6 1 1

B Column casting Nos 7 6 1 1


C De shuttering Nos 7 6 1 1

Next week plan of (26-02-24 to 03-03-2024)


Total Planned 2/26/2024 2/27/2024 2/28/2024 2/29/2024 3/1/2024 3/2/2024 3/3/2024
Sr.No. Work Description Unit
Quantity
Completed
This Week P A P A P A P A P A P A P A

1 Gaurd Room
Backfilling of Soil.
Meter 27 0 27 27

Plinth PCC
Meter 20.2 0 20.2 20.2

Plinth beam Reinforcement


nos 5 0 5 2 3

Plinth beam side shuttering.


Meter 20.26 0 20.2 8.6 11.66
Plinth Beam casting
Lot 5 0 5 2 3

Column Plinth Level to lintel level Reinforcement


nos 4 4 2 2

Column Plinth Level to lintel level Casting


nos 4 4 2 2

2 Water Proofing CRB roof Slab


Deep Cleaning
Sqm 351 351 100 100 151

Gola of Parapit Sqm 80 0 80 35 35 10

Primer (01 coat)


Sqm 351 0 351 150 201

Water Proofing (1st Coat)


Sqm 351 0 351 351

Water Proofing -(02 Coat)


Sqm 351 0 351
3 Painting-02 coat in GIS building
Stagging
LOT 1 0 1 1

Painting -02 coat Wall


Sqm 751.68 0 751.68 150 150 150 150 151.68

4 Aluminium Door First floor Meter 20 0 20 5 10 15

5 Stair case window Meter 18.9 0 18.9 5 5 8.9

Road Work (B/W GIS Building & Tranfo-


01)
6) Road compction Meter 16 0 16 10 6

GSB Filling & compaction Meter 16 0 16 16

PCC Meter 16 0 16 16

Reinforcement cutting & binding Meter 16 0 16 10 6

Shuttering fixing Meter 32 0 32 32

Casting Meter 16 0 16 16