DOW 1995 Check List
DOW 1995 Check List
EDITION1-JUNE 2005
CONTENTS
1.INTRODUCTION 5
2.PURPOSE AND SCOPE 5
2.1 GENERAL
2.2 REFERENCES 5
2.3 RESPONSIBILITIES
3.QUALITY AUDIT PLAN 7
INTRODUCTION
Quality Control Checklist has been produced as a general guide for the Quality
Control of Road and Bridge Construction Contracts.The Checklists included in this
Manual are based on the Department of Works Specification for Road and Bridge
Works August 1995.
The contract documents take precedence over this Manual and in the event of any
perceived conflict reference is to be made to theProject Manager for clarification.
PURPOSE AND SCOPE
The initial suite of Checklist has been developed from the Department of Works
Specification for Road and Bridge Works August 1995.These checklists are seen as
the first stage of development of the Quality Control Manual and further Checklists
are envisaged to be added to the manual as Specifications are reviewed and
incorporated in the system.
REFERENCES
As noted above the checklists form an integral part of Quality Control and the
completed checklists willform the majorityof the Quality Documentation for the
project.Other documentation that will need to be referred to will included:
·Department of Works Specification for Road and Bridge Works August 1995
·Special Conditions ofContract
·Construction Drawings
QUALITYAUDIT PLAN
As noted in the Contact Administration Guide Procedure CA15-Quality Audits,the
Project Manager is responsible for producing a Quality Audit Plan for individual
projects.The purpose of this plan is to identify what sections of the work need to be
audited,who will audit the work and when the audits will take place.
It should be noted that the Auditing scheduled in the Audit Plan is additional to
everyday surveillance activities,and is an opportunity for an independent individual
to review the work practices and quality of the project.
#1 GENERAL-CHECKLIST
Project:... … … . .… .. ..
“Lot”checked:.. … ..
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works.
1.8 TRAFFIC CONTROL
1.8.2 Temporary traffic diversion works have been approved by the Engineer.
1.8.2 The Contractor maintains diversion roads to a standard that will ensure proper passage for
traffic in all reasonable weather conditions.
1.8.2 Temporary bridges have been designed for T44 loading in accordance with NAASRA
Design Specification 1976
1.8.3
Any road closure has been authorised by the Engineer.
1.8.4 Temporary traffic control techniques and signage are operating effectively.
1.8.5 Road furniture removed as a result of temporary works has been reinstated,if required,at
project completion.
1.9 The Contractor has maintained all set out pegs in their correct position.
1.11 Construction traffic abides by any enforced load limits on roads and structures
1.12 The Engineer has been advised of any conflict with Public or Private Utilities.
1.13 Has the Contractor contacted all Public Authorities and co-ordinated any protection work or
relocation work.
Comments:
Signed:.... … … …
Date:.... .
2 ESTABLISHMENT
#2 ESTABLISHMENT -CHECKLIST
Project:... …….
“Lot”checked:.. … …
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works
2.1 CONTRACTOR'S
2.1.1 All accommodation,sheds and storage areas meet with relevant Health and Sa
Regulations.
2.1.1 Appropriate waste collection facilities are in place
2.1.4 Disposal of any debris on site has been approved by the Engineer
(iii)
2.1.4 On demobilisation,the site is in a neat and tidy condition.
(v)
2.2 ENGINEER'S ESTABLISHMENT
2.2.2 Within one month of Tender acceptance,the Contractor has erected a temporary office for the
Engineer.
2.2.2 The location of the office has been determined by the Engineer.
2.2.6 The Contractor maintains the office in a clean and tidy condition,with appropriate disposal of
waste.
Comments:
Signed: ……
Date: …………………………………
2 ESTABLISHMENT -CHECKLIST
#3 CLEARING AND GRUBBING -CHECKLIST
Project:.. … .
“Lot”checked:.. ..
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works.
3.1 CLEARING AND GRUBBING
3.1 Trees to be removed have been identified
3.1 Trees and shrubs have been cleared by cutting or breaking off≤250mm above ground level
3.1 The area to be cleared and grubbed has been adequately identified.
3.1 The area has been adequately grubbed by removing fallen trees,stumps,logs,upturned roots,
rotten wood and allother vegetable growth.
3.1 Holes,such as those left from stumps,in areas of embankments have been backfilled and
compacted.
3.2 The Contractor has adequate measures in place to prevent the spreading of fires
3.2 Un-burnable material if buried on site is done outside the structural backfill area.
3.3 Top soil is removed to a depth of 150mm and stockpiled or disposed of as directed by the
Engineer.
3.3 After grubbing and stripping,the topsoil surface has been graded to facilitate accurate survey
3.6 Piles are extracted or cut off one metre below river bed level,or as directed by the Engineer
Comments
Signed:..
Date:.... …
3 CLEARING AND GRUBBING-CHECKLIST FORM SU03
#4 EARTHWORKS-CHECKLIST
Project:.. … .....
“Lot”checked: … . …
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works
4.2 EXTENT OF WORKS
4.2.1 Dimensions of excavations and embankments are in accordance with D
4.2.4 Joints between new and existing pavement are stepped 150mm(vertica
(horizontal)if the sub-base layer is≥200mm.
4.7 Excavated rock suitable for stone pitching,gabions etc has been reserved if req
4.13
4 EARTHWORKS -CHECKLIST
SU04
4.13 When blasting near buildings ground vibrations are less than those specified in
Ground vibrationshave been measured with a Vibragraph supplied by the Contr
4.13 The Contractor has given 10 days notice of intention to blast,together with loca
methods to be adopted.
4.13 Explosives are stored in a secure place,clearly identified with warning signs.
4.13 If the work is accessible=by the general public,before any shots are fired,know
the apparent danger must be conveyed to all persons in the area.
4.14.2 Compaction has been continued until movement of the surface under t
negligible.
4.14.3 The 300mm layer below the sub-base,or other thickness,as directed by
been formed with material<75mm nominal size,and has a minimum 4
of 8%.This material has been compacted in 200mm layers loose,to 100
(Characteristic Value).
4.14.4 The Contractor has provided 7 days prior notice of “Upper Layer”plac
submitted material samples for approval prior to placement.
4.15.2 Materials which cannot be suitably compacted are not located within 6
underside of the sub-base
4.15.3 The 300mm layer below the sub-base,or other thickness,as directed by
been formed with material<75mm nominal size and has a minimum 4
of 8%.This material has been compacted in 200mm layers loose,to 100
(Characteristic Value)
4.15.4 The Contractor has provided 7 days prior notice of “Upper Layer”plac
submitted material samples for approval prior to placement.
4.15.6 Topsoil has been spread in the areas and to the depths required.Stone
material with least dimension greater than the depth of spread have b
4 EARTHWORKS-CHECKLIST
SU04
4.18 BORROW
4.18 The Contractor has planned his earthworks operations to maxim
excavated material and to minimise the use of Borrow ma
4.18 Borrow pits have been excavated to provide natural drain
4.18 Borrow pits have been cross-sectioned by the Contractor
representative of the Engineer,before material is removed
4.19 FILL TO STRUCTURALFOUNDATIONS
4.19.1 Fill to structural foundations has not commenced without approval of
Contractor's construction procedure hasalso been approved bythe Eng
4.19.2 Fill below structural foundations above natural surface has been in 20
compacted to 95%MDD (Standard Compaction)
4.19.5a Abutment backfilling has not commenced until approved by the Engine
4.19.5b A drainage layer 300mm wide has been placed behind wall type abutm
subsoil drain.Material used has 100%passing a 75mm sieve &25%pass
sieve.
Comments:
Signed:.... … … ………
Date:..... ....
4 EARTHWORKS -CHECKLIST
SU04
“Lot”checked:. … .
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works.
5.2 MATERIALS
5.2.1 The Contractor has provided a material source assessment at least 10 working
material deliveries commence,to stockpile or pavement.
5.2.2 Base and sub-base materials meet all requirements of Section 5.2.2 of the Spec
such as grading,PI,LL and CBR.
5.2.2 Imported material has not been added to the source material without the Engi
approval.
5.2.3.1 Coronous material for use in base and sub-base layers has been approved by th
5.2.3.2 The method of selecting and processing Coronous material"has been approved
Engineer.
5.2.3.2 Coronous base and sub-base material conforms to the requirements of Section
the Specification.
5.3.3 Lot sizes,number and frequency of material tests has been determined by the E
5.4 CONSTRUCTION
5.4.1 The Contractor is responsible for maintaining the surface in a condition that co
with the specification-until the end of the maintenance period
5.4.2 Individual compacted layer thickness shall be between 75-250mm compacted th
5.4.3 Prior to overlaying existing formation,the surface has been scarified and shaped
necessary.The total depth of scarified and added material does not exceed the p
layer thickness.
5.4.5 The final unbound pavement layer has a uniform surface free from loose,segreg
contaminated areas and with course particles slightly exposed.
5.4.6 The bituminous prime coat was applied to the base course after level;compactio
surface finish had been approved by the Engineer
5.4.7 Pavements with Type 1 materials shall be constructed with self propelled sprea
machines,unless approved otherwise by the Engineer
5.5 PRODUCT STANDARDS
5.5.1 The horizontal location of any point on the pavement is within a
except as follows:
-for unconstrained pavement edges -50mm,+250mm
5 BASE AND SUB-BASE PAVEMENT COURSES-CHECKLIST FORM SU05
Pavement
Course
Base Course
Sub-base
5.5.5 The finished surface shall be free of segregation and tightly hel
5.6 CONSTRUCTION COMPLIANCE TESTING
5.6.1 Lot sizes,numbers and frequency of testing will be as directed by the E
5.6.2 Geometric tolerances,except for surface evenness,has been checked b
random stratified sampling.
5.6.3 The compaction standard for each lot has been represented by the Cha
the Relative Dry Density.
5.6.3 The location of in-situ dry density testing has been chosen by a method
stratified sampling.
5.6.4 Lots have been sampled to ensure there is no segregation.
dt'spler
5.6.5 The surface of the pavement in every layer displays no visible vertical
compaction equipment.
Comments:
Signed. .….Date:.. … … .…
5 BASE AND SUB-BASE PAVEMENT COURSES -CHECKLIST
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works.
6.1 BITUMINOUSPRIME COAT
6.1.2 Cutback bitumen conforms to the requirements of Section 6.1.2 of the Specification
6.1.2 The Contractor has tested the cutback bitumen for conformance with AS 2157
6.1.4 The Contractor has measured and recorded the road temperature at regular interval
6.1.5 Before spraying,the surface of the base course has been swept free of loose stones,dirt and
foreign material.
6.1.5 Spraying does not commence until the prepared surface has been approved by the En
6.1.6 The spray bar operator has all nozzles in full view.
6.1.7 The spray bar and all measuring equipment on the distributor have been recently calibrated
and a record supplied to the Engineer.
6.1.8 Performance testing of the distributor has been made,if requested by the Engineer
6.1.9 The use of hand spraying has been approved by the Engineer.
6.1.10 The spray length has been measured and marked on the ground.
6.1.12 The width of primed surface is 150mm wider on each side than that specified
6.1.14 Prime coat is applied during dry conditions with road temperature≥18℃
6.1.15 Adjacent structures and trees are protected from splattering prior to spraying.
6.1.16 Traffic has not been permitted on the prime coat until fully penetrated and dried in.
6.1.16 If unable to reroute traffic,and if approved by the Engineer,blotter material has been
spread to avoid picking up by traffic.
6.2.3 The Contractor has submitted details of adhesion agent for the Engineer's approval.
6.2.4 Aggregates are clean,hard,dry crushed stone or gravel which conforms to Section 6.2.4 of
the Specification
6.2.5 Single seal application uses 19mm then 13.2mm nominal size unless directed by the
Engineer.
6.2.6 The bottom 50mm of stockpiled aggregate or any contaminated aggregate has not been used
in the work.
6.2.7 All aggregate has been precoated.Precoating material is distillate with 10%bitumen and
!%megamine BA applied within the range of 6-12litres/m³.
6.2.8 The Contractor has supplied details of the plant and equipment as required by the Engineer
6.2.8 Plant and equipment conform to the requirements of Section 6.2.8 of the Specification
6.2.9 Before application of binder,the surface has been swept free of loose stones,dirt and
foreign material.Sweeping extends 200mm beyond the edge ofthe area to be sprayed.
6.2.10 The application rate of bituminous binder material and cover aggregate has been
determined by the Engineer.The application rate falls within the ranges tabulated:
Aggregate Size
19mm
13.2mm
9.5mm
6.2.10 The application of bituminous binder material is made by means of a mechanical distributor
or handheld spray equipment approved by the Engineer.
6.2.11 Bituminous material spray temperature is between the range 165-185℃ and has not been
held at this temperature longer than 10 hours
6.2.12 The area to be sprayedis limited to that which can be covered in 15 minutes of spraying
6.2.13 Spraying is not performed in wet conditions,during high winds or when the ambient
temperature<18℃
6.2.13 After application,the quantity of material sprayed is checked against the area covered and
any necessary adjustments are made to subsequent runs.
6.2.15 The aggregate is rolled by either pneumatic tyred or steel wheeled rollers (if approved by
the Engineer),until aggregate is firmly embedded.
6.2.16 Traffic is not permitted on the new work until sufficient rolling has taken place.
6.2.16 “Wet Tar”and 20kph signs have been erected at 300m intervals
6.2.17 The treated surface is checked during the maintenance period for softening and bleeding.
Comments
Signed:. ..
Date:.... … …
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works.
7.2 MATERIALS
7.2.1 RC pipes are of the correct class and are free of defects and damage to ends
7.2.2 Jointing mortar is one part Portland Cement to two parts fine sand with enough water for a
satisfactory consistency.All mortar is used within 30 minutes of adding water.
7.2.4 Culverts have been tested in the presence of the Engineer's representative prior to leaving the
place of manufacture.
7.2.4 All culvert sections are free from defects or damage to edges.
7.2.4 Lifting hooks or holes are provided in the decks of culverts
72.4 The Contractor has submitted a base slab design for the Engineer's approval,if no su
detail is shown on the drawings.
7.3 Where select material is not specified below the bedding layer,the top 150mm of formation
is compacted to the relative density of the adjacent embankment material.
7.3 The width of trenches is just enough to permit satisfactory jointing of pipes and compaction
of backfill materials
7.3 Rock above invert level is excavated to 150mm below invert level and backfilled with
selected material.
7.3 Soft and spongy foundation material has been removed to a depth as directed by the Engineer
for a width 1.5 times the diameter or span of culvert from the centreline of the barrel and
backfilled according to Section 7.5 of the Specification.
7.3 Culverts are bedded on sand 75mm thick.Pipe bedding is shaped to fit the underside of the
culvert and graded to provide uniform bearing.
7.4 PLACING
7.4.1 RC pipes are laid from the outlet end with socket ends upstream and spigots downstream
7.4.5 For multi-cell culverts,a 15mm gap is provided between adjacent cells and
cement mortar or approved bitumen filler.
7.4.5 Mortared joints are protected form the sun and cured for 48 hours.
7.5 BACKFILLING
7.5 Backfill material is not placed until the culvert has been inspected and approved for backfill
7.5 The backfill material is free from lumps and vegetable matter and stone>75mm and has at
least 50%retained on 2.46mm sieve.PI≤12%
7.5 Material under the haunches of pipes and near the sides of culverts is compacted with hand
held equipment
7.5 Backfill on both sides of culverts is performed concurrently with a maximum level difference
of 150mm between them.
7.5 Backfill around culverts extends 300mm above their top and for one diameter either side of
their centreline for pipe culverts or half the wall height for box culverts,measured from the
wall face
7.5 Culverts laid in a trench are backfilled to the full height,length an width of trench
7.5 Drainage structures once installed are not damaged by heavy construction equipment
7.7 TAKING UP AND STACKING CULVERTS
7.7 Culverts taken up are stacked neatly in lines clear of earthworks,watercourses,dra
fences.
7.7 Culverts not re-laid are taken to the Engineer's compound and stacked as directed
7.10.2 Filter material is placed above the slotted pipe 300mm thick and compacted by vib
plates or tampers.Additional lifts of filter material do not exceed 200mm loose.Filt
material is compacted to 90%MDD
7DRAINAGE-CHECKLIST
7.11.3 No earth or rock falls into the mix as the concrete is poured.
7.11.4 Precast concrete drainage units use concrete Grade 30.All formwork and casting i
submitted for the Engineer's approval.Precast unit dimensions are within a toleran
±3mm.
7.13.3 For cast in-situ work,where an extrusion process is used,the concrete is Grade 30 (for
testing only needs to meet Grade 25 requirements)
7.13.3 The extruded concrete surface is free of voids,honeycombing and has a steel trowelled
finish.
7.13.3 Where the Contractor uses an extrusion mould,a test section is provided for approval by the
Engineer.
7.13.4 Precast concrete sections are constructed using Grade 30 concrete and have an individual
tolerance of±3mm to the specified dimension.
7.13.4 Cast in-situ work has expansion joints at 20m intervals &construction joints at 5m intervals
7.13.4 Expansion joints are 6mm bitumen impregnated fibre board in the full cross-section.
7.13.4 Construction joints are grooves 40mm deep and 6mm wide.
7.13.4 Cast in-situ concrete work is cured in an approved manner for at least 7 days.
7.13.7 Horizontal and vertical alignments of the product do not vary from those specified by more
than ±10mm.Overall dimensions of the product are not less than those specified on
Drawings
7.13.8 Where the product is not placed on a pavement layer,the sub-grade is compacted and a
bedding layer of sub-base material placed to a compacted thickness of 75mm at 95%MDD.
Signed:.... … … … …
Date:.... …… .
7 DRAINAGE -CHECKLIST
Project:. . … .......
“Lot”checked:.. …
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works
8.1 ROAD SIGNS
8.1.2
8.2.3 Steel beam guardrail,posts and terminal sections are Armco Flex-Beam Guardrail or similar
approved by the Engineer.No punching,cutting,or welding is done in the field.Holes for
special details have the Engineer's approval.
8.2.3 Bolts for guardrail extend 6mm beyond nuts,except where required for adjustment,extend no
more than 12mm.
8.2.4 Posts are set to a line,level and spacing conforming to the line and grade of roadway.
8.2.4 Posts are backfilled with approved material and thoroughly tamped.
8.4.7 Approaches to single lane bridges are marked with a yellow coloured bar marking system as
8ROADSIDE FURNITURE AND MARKINGS-CHECK
SU08
“Lot”checked:... …
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works.
9.1 STONE PITCHING Yes/No
9.1.1 Stone is roughly dressed with general minimum dimensions of 150mm
dimension of 450mm.
9.1.2 Mortar used consists of one part Portland Cement to two parts of clea
sand with sufficient water to be workable
9.1.3 Stones are bedded in mortar to a depth of 60%of the stones thickness.
9.1.4 Mortared joints are well rodded to a depth of 75mm minimum and kep
hours.
9.2 ROCKWALLING
9.2.1 Stones are durable and greater that 0.016m³in volume with minimum
and minimum plan dimensions of 300mm.
9.2.1 The base of the wall is embedded at least 300mm unless founded on ro
be securely keyed.
9.2.4 Grouted and Masonry Rockwalling is capped with a 25mm mortar laye
Comments
Signed:..
Date:...
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works.
GENERAL
10.1 Pile materials(steel,concrete or timber)conform to specified requirements.
10.1 Tubular steel piles with closed ends are driven with a driving shoe.
10.2 Installed to within l in 100 of specified batter and head to±75mm of specified p
INSTALLATION
10.3.2 RC piles are lifted and stacked at two points,1/5 of their length from each end.
10.3.2 RC piles are pitched by lifting at a point 3/10ths the length fromthe head.
10.3.2
RC piles are not driven until 28 days old
10.3.3 The necessary cushioning is provided between driving helmet and pile.
10.3.3 Piles are spliced in accordance with specified requirements Section 10.3.3
10.3.4.2 The appropriate hammer has been provided in accordance with Section 10.3.4.
10.3.4.3.
10.3.4.7 Piling with followers is performed only with written permission of the Engineer
10.3.4.8 Water jet equipment can deliver at least 700MPa at two 20mm nozles
DRIVEN PILES-CHECKLIST
10.3.6 Prior to driving,piles are identified with a unique number and marked
500mm from the pile toe.
10.3.6 All pile driving is supervised and installation data recorded on the Em
form.Duplicate copies of the standard form to be submitted to the Eng
10.3.6 As built location plan of the piles installed is provided and includes the
specified inSection 10.3.6(a)to (e).
Comments
Signed:.
Date:...
DRIVEN PILES-CHECKLIST
#10 PILING FOR STRUCTURES
BORED PILES-CHECKLIST
Project:. . .
“Lot”checked:.. … … …
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works
GENERAL
10.1 Pile materials (steel,concrete or timber)conform to specified requirements.
10.2 Installed to within 1 in 100 of specified batter and head to±75mm of specified position
INSTALLATION
10.4.1
Engineer or representative is present during boring.
10.4.1
The boring equipment has been accepted by the Enginee
10.4.2 Boring equipment is fitted with suitable controls to ensure alignment can be monitored
prior to and during boring.
10.4.3 Boring logs are submitted to the Engineer within 3 working days of completion.
10.4.4 Boreholes are covered at all times when work is not in progress.
10.7.2 Concreting is commenced only after the Engineers approval of the excavation.
10.7.2
Concreting is preformed in one continuous operation.
10.7.2 The final level of concrete is suitably above the required finished level to ensure pile head
concrete quality.
10.7.5 Sand has been approved by the Engineer prior to filling of the piles.
LOAD TESTING
10.6 Load testing equipment and procedures match those specified in Section 10.6.
10.6 Load test results and driving records are submitted to the Engineer within 7 days of the test
10.6 The Contractor has been advised of the Engineers interpretation of the load test results
within 7 days of their receipt.
Signed:... ...Date:... … … .
10 PILING FOR STRUCTURES
#11 FALSEWORK-CHECKLIST
Project: …
“Lot”checked: … … ………………
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works.
11.1 GENERAL
11.1 The Contractor has provided the Engineer with detailed Drawings and calculations for
proposed Temporary Works at least four weeks before work commences.
11.1 Temporary Works are not used without written consent of the Engineer.
11.1 Falsework is released at the time and in the order consented by the Engineer.
11.1 Falsework not founded on a satisfactory footing is supported on piles approved by the
Engineer.
11.1 Falsework is not supported on constructed portions of the substructure without the Engineers
approval.
11.1 All timber is well seasoned and free from knotholes,loose knots and other defects
11.1 Equipment for removing falsework is not operated upon or attached to any portion of the new
structure without the Engineers approval.
Comments:
Signed:. … …
Date:..... …… ………
11 FALSEWORK-CHECKLIST
SU011
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works.
12.1 GENERAL
12.1 There are no gaps in the formwork that will permit loss of materia
12.1 Check width and length of formwork,diagonal for square and plum
12.2 CONSTRUCTION
12.2.1(a) Formwork is not warped or buckled and concrete contact surface
the correct class.
12.2.2(a) Check that formwork used for exposed surfaces has the correct su
12.2.1(b) The design of mild steel formwork has been reviewed by the Engin
commences.
12.2.1(b) Check for Mild Steel forms that all bolt and rivet heads are counte
been ground back
12.2.2 Forms are designed and constructed such that removal can be ma
concrete or forms.
12.2.2 There are no wires or bolts extendingto the surface of the concret
1,222 Internal tie bolts can be extracted without damage to the concrete
12.2.2 Holes left behind from internal ties are filled with mortar to the E
12.2.3 Different release agents are not used on visible sections of the sam
12 FORMWORK
SU012
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works
13.2 MATERIALS
13.2 The Contractor has produced a Manufacturer's certificate as evidence that all steel complies
with the relevant specification.If such a certificate can not be produced the steel shall be
tested in accordance with Section 13.2 of the specification.The certificates and/or samples
have been supplied at least 3 weeks before fixing steel on site.
13.3 PROTECTION
13.3 Steel is stacked in racks above ground and is clear of mud.
13.5 Cover is maintained by precast concrete blocks or other devices acceptable to the Engineer
The block strength should be equivalent to that of the surrounding concrete.Bar chairs are
adequately spaced to prevent bars from sagging.
13.5 Welding of reinforcement is not undertaken without written approval of the Engineer.
13.6 SPLICING
13.6
Comments:
13 STEEL REINFORCEMENT-CHECKLIST
SU013
Signed:. … ....Date:.... .
13 STEELREINFORCEMENT-CHECKLIST
SU013
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works.
MATERIALS &MIX DESIGN
14.5.1 The Contractor has submitted details of the concrete mix proposed for each par
& Grade of concrete,for approval by the Engineer.The information to be forwarde
14.6.3 consistent with Clause 14.6.3 of the specification.
14.6.5 Preliminary mixes have been made and tested,or approved on the basis of past
by the Engineer before placement
14.5 Materials used in the production of concrete satisfy the requirements of Section
Specification.
14.6.2 The Contractor has provided details of any proposed grout mix for the Engineer
together with6 test specimens.
PLACEMENT
14.9.2 Forms are clean and any foreign matter removed.
14.15 Verticality of forms,location of blockouts and cross-sectional dim
elements cast,satisfy required tolerances.
14.8.3 Check that ready mixed concrete is placed at temperatures less than or equal t
tabulated below.
ConcreteGrad Temperature(C)
e
15-30 33
40 30
14.8.2 Check delivery dockets for mix details.Take slump test to make
with the mix design and specification.
14.9.7 Check that the face of construction joints are prepared as follows:
● Surface roughened
·Foreign matter removed
14 CONCRETE
SU014
14.9.2 Concrete is not dropped from a height of more than 2 m which may ca
tremie or approved pump is to be used to place from height.
14.9.5 High frequency internal vibrators are being used to place the concrete
concrete which shall be placed without tamping,rodding or vibrating)
14.9.2 Concrete is placed in a continuous manner.
14.9.2 Concrete chutes are metallic and free of hardened concrete coatings.
14.9.2 Approval for use of concrete pumps has been granted by the Engineer
14.9.3 Concrete is not placed under water unless approved by the Engineer a
of cement is increased by 25%
14.9.5(c) One vibrator is provided for each 5m³of concrete placed/hour with a m
vibrators.
14.95(g) Vibrators are not applied direct to steel reinforcement in hardened con
14.8.2 Check that the concrete is placed within the time limits in the specific
14.11.4 Exposed concrete surfaces other than slabs,are cured for at least 7 da
cured for at least 14 days.
Comments:
Signed. …… … …
Date:....
14 CONCRETE WORK-CHECKLIST
SU014
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works
15.1 GENERAL
15.1.1 The Contractor has submitted 3 copies of Wor
one monthprior to commencement of fabricati
15.2 MATERIALS
15.2.2(1) Test certificates have been supplied to the Engineer
appropriate standards
15.3 FABRICATION
15.3.2 The appropriate method of cutting steel has been us
and corners rounded to a radius of 2mm.
15.3.4(3)(a) The correct electrodes are being used and are stored
STRUCTURAL STEELWORK-CHECKLIST
SU015
15.3.6(1) All holes have been drilled with burrs and other defe
STRUCTURALSTEELWORK-CHECKLIST
SU015
15.8.6 High tensile bolts are not tensioned until the joint is
15.8.7(1) The Contractor has supplied test certificates for eac
month before their use.
Comments:
Signed:...
Date:....... ......…
STRUCTURAL STEELWORK-CHECKLIST
SU015
“Lot”checked: … …
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works
16.1.1 All surfaces to be protected are thoroughly dry and free from oil,greas
deleterious substances
16.1.1 Steelwork has been abrasive blast cleaned to the appropriate class of
16.1.2 Prime coat has been applied(if required),within three hours of blast cl
16.6 Damaged areas have been cleaned back to base metal and edges beve
Up painting per Section 16.3.3.Touch Up painting overlaps existing by
16.8 Completed joints have been painted as specified within 10 days of the
16.9.3(b) Buried seismic restraint components not cast in concrete have been ad
Comments:
Signed..... … …
Date:.... …
16 PROTECTION OF STEELWORK-CHECKLIST
“Lot”checked:... ……
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works
17.2 BEARINGS
17.2.1 Bearings are in the correct position.
17.2.1 Sliding bearings are set to the correct offset,dependant on ambient temperatur
17.2.2 The hardness of elastomeric bearing pads is 50±5 on the Durometer scale,or as
indicated.
17.2.2 The Contractor has submitted physical &mechanical property test certificates o
bearingto the Engineer.
17.2.2
All bearings are marked with a unique identifying
17.2.2(c) Mortar under bearings extend beyond the bearing by the thickness of the morta
battered off at 1 to 1.
17.3.4 Waterstops are fixed to the reinforcement to maintain position during concretin
17.3.4 Waterstops are cut and spliced in accordance with Manufacturer's recommend
17.3.5 Test certificates detailing the joint filler stress/strain relationship have been sub
17.3.6 Joint sealants to trafficked surfaces are hot poured coal tar based,acceptable to
Engineer.Sealant is applied in accordance with Manufacturer's recommendatio
17.4 SCUPPERS
17.4 Drainage scuppers are uPVC pipes arranged so as not to stain exposed surfaces
discharged
17.5 Sand for epoxy mortar is hard,sharp,siliceous and free of organic mate
the grading of Section 17.5 of the Specification.
17.5 Binder and sand are mixed in the ratio of 5 to 2
17.6 Surfaces to be treated are roughened or etched and cleaned with acet
Comments:
Signed:...
Date:
18.1.4 Wire is PVC coated if required.PVC coating is 0.55mm thickness (average)and con
to the properties of Section 18.1.4(a)to (i)of the Specification.
18.1.6 All gabion edges have been selvedged with 3.4mm diameter wire where required.
18.1.9 Filling material is hard durable stone minimum dimension 100mm and maximum
dimension 250mm.
18.1.10 Gabion and reno mattress materials conform to the following tolerances:
Wire diameter ±2.5%
Length ±3%
Width ±25mm
Other dimensions ±3%
18.1.11 Gabions and mattresses are laced together along all adjoining corners and sides
18.1.12 At least two rows of empty gabions are wired together at the face of uncompleted
prior to filling gabions closest to the completed work.
18.1.13 Gabions≥1m high are cross tensioned in each compartment at 3rd points in heigh
18.6.2 The Contractor handles the fabric with care to prevent it being pierced.
Signed.. … …… .
Date:... … .
#19 DAYWORKS-CHECKLIST
Project:.. .
"Lot"checked:... ……
Numbers shown refer to the relevant section of the Department of Works Specification,for Road and Bridge
Works.
19.1.1 Labour rates for Dayworks are as listed in the Bill of Quantities.Ra
rate plus a rate for skill as specified by theRegistered Award,as se
Relations Act of PNG.This rate has been further increased to allow
and overhead.
19.1.1 Written approval has been given by the Engineer for any overtime
19.3.4 The Contractor has kept the plant in good repair to ensure proper
19.3.9(iv) PIant hire hours include delay for minor normal repairs,provided
in any one day<1/10 of the work time for that day.
19.3.9(vi) Payment has not been made for work affected by adverse weather
19.3.9(vii) Time spent by plant travelling within the site has been approved b
Comments:
Signed:.
Date:.... … ......
19 DAYWORKS-CHECKLIST
SU019
19 DAYWORKS-CHECKLIST
SU019
Project:....
Date Sample
sampled
number
DENSITY TESTING-SUMMARY OFTEST RESULTS
ASPHALTIC CONCRET
ASPHALTIC CONCRETE -SUMMARY OF TEST RESULTS
(TESTING OF FIELD DENSITY)
Project:.... … … … …
Results Required
ASPHALTIC CONCRETE-SUMMARY OF TEST RESULTS
Date sampled
Sample
number
Results Required
Project:. .
Location or Lot Number:.
PLANT/LABOUR ITEM
4
5
MATERIALS
SIGNED..
(for Contractor)
DATE......./....../......
DAYWORKS AGREEMENT SHEET
5
5
uality
this
ge
ny
n.
trol
out in
e
na
s
n as
ists
nd
ality
rol
ield
the
lists
ll be
ce
eports
ce
the
l
o be
rried
ng
uent
dual
d and Bridge
neer.
the Engineer.
ectively.
instated,if required,at
ect position.
d structures
e Utilities.
-CHECKLIST
ESTABLISHMENT
t with relevant Health and Safety
by the Engineer
ondition.
erected a temporary office for the
eer.
SU02
d and Bridge
mps,logs,upturned roots,
herwise directed.
ading of fires
l backfill area.
operations
d of as directed by the
…
..
M SU03
d and Bridge
AL FOUNDATIONS
y damage to adjacent buildings,roads and footpaths etc
ctivities
ffected by water inflow and are suitable for pouring
brations are less than those specified in AS2187
with a Vibragraph supplied by the Contractor
hot is fired.
100%MDD(Characteristic Value)
s to sub-base requirements.
by at least 2m
ges -50mm,+250mm
SU05
Primary
Tolerance
(mm)
±15
±25
compaction requirements:
aracteristic Value)
MDD(Characteristic Value)
properties:
rs
tor have been recently calibrated
ngineer.
he ground.
trip of paper.
amp.潮湿
ce of±75mm
SU06
≥18℃
to spraying.
ineer's approval.
of the Specification
f a mechanical distributor
M SU06
minutes of spraying
when the ambient
etion of spraying.
taken place.
FORM SU07
e to ends
damage to edges.
cks of culverts
he Engineer's approval,if no such
awings.
nd backfilled with
sheet ahead
placed
M SU07
t tight
thick,compacted to 95%MDD,
the sub-base is compacted to 100%
vent distortion.
ete is poured.
wide.
ROADSIDE FURNITUR
Sign faces are reflectorised using heavy duty reflectorised paint confo
h Group 3
n of not less than
for adjustment,extend no
grade of roadway.
g.
r Markings which are yellow.
s instructions.
gineer.
FORM SU09
d and Bridge
..
a driving shoe.
ified requirements.
l H-piles.
d by the Engineer.
as specified in Section10.3.5.
re redriven.
,for Road and Bridge
ecified requirements.
n progress.
n to ensure stability.
ontinuous operation.
ed finished level to ensure pile head
ng of the piles.
anner.
.
,for Road and Bridge
he Engineer.
d by the Engineer.
ORM SU012
that all bolt and rivet heads are countersunk and welds have
FOR CONCRETE-CHECKLIST
FORM SU013
n diameter.
of concrete.
Bars are spliced and lapped as shown on the Drawing or as approved by the
EMENT-CHECKLIST
han 17.5MPa.
&FINISHING
oreign matter removed.
lockouts and cross-sectional dimensions of concrete
red tolerances.
ed at temperatures less than or equal to the values
Temperature(C)
33
30
ss than 35°℃.
WORK-CHECKLIST
erve.
equired
s applied.
FORM SU015
d and Bridge
ctor has submitted 3 copies of Workshop drawings for review by the Engineer,
rior to commencement of fabrication.
has not commenced until the Engineer has consented to the use of the Shop
rocedures and the program of work.
tes have been supplied to the Engineer,to prove the steels compliance with
tandards
ION
ate method of cutting steel has been used,surfaces are of the required Class
ounded to a radius of 2mm.
lectrodes are being used and are stored in warm dry conditions.
ot commenced until the Engineer has approved the Welding Procedure and
or has submitted test assembles duplicating actual conditions.
STEELWORK-CHECKLIST
ponents have been inspected and tested as necessary and approved by the
or to being despatched from the workshop
uds not showing 360°weld fillet,or have been repaired by welding,or who's
e than 1.5mm greater than specified,have been struck with a hammer and
of a completed hole is 2mm larger that the bolt except for HSFG bolts
le diameter is not more than 3mm larger than the bolt.
nts have been match marked prior to despatch to facilitate reassembly in the
arkplans have been furnished to the Engineer.
n has been executed to the shapes and dimensions shown on the plans and to
s specified in Section 15.5 of the specification.
are protected from damage during delivery ie bottom flanges of plate girders
d chains used for lifting components are padded to prevent damage to steelwork
otective coating.
bolts are assembled with one hardened washer under the nut or bolt head.
ssembled with convexity outwards.
bolts are not tensioned until the joint is inspected by the Engineer.
or has supplied test certificates for each batch of HSFG bolts at least one
their use.
FORM SU016
re not painted.
Manufacturers instructions
ess
MISCELLANEOUS BRID
FORM SU017
d and Bridge
position.
ffset,dependant on ambient temperature
ng tolerances:
ontinuous length.
e manufactured from PVC with fixing strip along
MISCELLANEOUS BRI
ADHESIVE
dite AV138 with hardener HV998 mixed in the ratio
F
RIVER TRAINING AND BANK PROTE
FORM SU018
…… ...
………
,for Road and Bridge
e void ratio.
r tops.
quate compaction
mum of voids
…
.
PROJECT CHECKLIST
Chainage
Location
ASPHALTIC CONCRETE-SUMMARY OF TEST RESULTS
Chainage
ASPHALTIC CONCRETE-SUMMARY OF TEST RESULTS
RY OF TEST RESULTS
ITY ETC)
.... .....
… .. ..
Location
“PROJECT NAME
DAYWORKS AGREEMEN
……
R ITEM HOURS
ESTABLISHMENT
PROJECT CHECKLIST
ESTABLISHMENT
PROJECT CHECKLIST
ESTABLISHMENT
FORMSU02
PROJECT CHECKLIST
CLEARING AND GRUBBING
PROJECT CHECKLIST
EARTHWORKS
Carehas been taken toprotect any permanent or temp
PROJECT CHECKLIST
EARTHWORKS
PROJECT CHECKLIST
EARTHWORKS
PROJECT CHECKLIST
BASE PAVEMENT COURSES
-BASE PAVEMENT COURSES
3m Straight X-fall
Edge
Deviation
(mm)
5 +0.5%
8 +0.5%
BITUMINOUS SURFACING
BITUMINOUS SURFACING
ication Rate Cover Aggregate(m²/m³)
65-80
80-105
100-135
BITUMINOUS SURFACING
ROADSIDE FURNITURE AND MARKINGS
STEEL REINFORCEMENT
n on the Drawing or as approved by the Engineer.
PROJECT CHECKLIST
STEEL REINFORCEMENT
STRUCTURAL STEELWORK
STRUCTURAL STEELWORK
STRUCTURAL STEELWORK
PROTECTION OF STEELWORK
MISCELLANEOUS BRIDGEWORK ITEMS
MISCELLANEOUS BRIDGEWORK ITEMS
NG AND BANK PROTECTION
Marshall
Voids Voids Bitumen
Stability
% Filled %
kN
“PROJECT NAME”
SIGNED...
(PMR)
DATE............./.
PROJECT CHECKLIST
TABLISHMENT
FORM SU⁰1
Yes/No
FORM SU⁰2
Page 1 of 2
CT CHECKLIST
TABLISHMENT
FORM SU02
Yes/No
Page 2 of 2
JECT CHECKLIST
TABLISHMENT
ORMSU02
Page 3 of 2
ECT CHECKLIST
FORM SU03
Yes/No
Page 1 of 2
ECT CHECKLIST
ARTHWORKS
FORM SU04
Yes/No
n toprotect any permanent or temporary structures nearby.
Page 1 of
ECT CHECKLIST
ARTHWORKS
FORM
Page 2 of
JECT CHECKLIST
EARTHWORKS
FORM
Page 3 of
JECT CHECKLIST
Yes/No
Page 1 of 2
PROJECT CHECKLIST
Surface Evenness
(RR counts/km
60
FORM SU05
Page 2 of 2
PROJECT CHECKLIST
URFACING
FORM SU06
Yes/No
.
Page 1 of3
PROJECT CHECKLIST
URFACING
regate(m²/m³)
Page 2 of 3
PROJECT CHECKLIST
SURFACING
Page 3 of 3
PROJECT CHECKLIST
DRAINAGE
Yes/No
Page 1 of 3
PROJECT CHECKLIST
DRAINAGE
FORM SU07
PROJECT CHECKLIST
DRAINAGE
FORM SU07
Page 3 of 3
PROJECT CHECKLIST
FORM
Yes/No
FORM
Page 1 of 1
PROJECT CHECKLIST
FORM
Page 2 of 1
PROJECT CHECKLIST
CTURES
FORM
Page 1 of 1
PROJECT CHECKLIST
DRIVEN PILES
FORMSU10.1
Yes/No
FORM SU10.1
Page 1 of 2
PROJECT CHECKLIST
DRIVEN PILES
FORM SU10.1
Page 2 of 2
PROJECT CHECKLIST
BORED PILES
FORM SU10.2
Yes/No
FORM SU10.2
Page 1 of 1
PROJECT CHECKLIST
FALSEWORK
FORM SU011
Yes/No
FORM
Page 1 of 1
PROJECT CHECKLIST
Yes/No
FORM
Page 1 of 1
PROJECT CHECKLIST
FORM
Page 2 of 1
PROJECT CHECKLIST
ORCEMENT
Yes/No
FORM
Page 1 of 1
LIST
FORM
Page 2 of 1
PROJECT CHECKLIST
CONCRETE WORK
FORM SU014
Yes/No
FORM
Page 1 of 2
PROJECT CHECKLIST
CONCRETE WORK
FORM
Page 2 of 2
PROJECT CHECKLIST
TEELWORK
Yes/No
FORM
Page 1 of 3
PROJECT CHECKLIST
STEELWORK
FORM
Page 2 of3
PROJECT CHECKLIST
ORK
FORM
Page 3 of 3
PROJECT CHECKLIST
K
Yes/No
FORM SU016
Page 1 of 1
PROJECT CHECKLIST
Yes/No
FORM
Page 1 of 2
PROJECT CHECKLIST
FORM
Page 2 of 2
PROJECT CHECKLIST
Yes/No
FORM
Page 1 of 2
PROJECT CHECKLIST
FORM
Page 2 of 2
PROJECT CHECKLIST
DAYWORKS
FORM SU019
Yes/No
FORM
Page 1 of 1
PROJECT CHECKLIST
FORM TR-01
Moisture
Moisture Density
Range ** Required
FORM TR-01
Page 1 of 1
PROJECT CHECKLIST
FORM TR-02
Marshall Bitumen
Flow
Stability Content Total
mm
kN Mix
FORM TR-03
PROJECT CHECKLIST
Strength Required Conform
MPa strength (Y/N)
FORM
Page 1 of 1
PROJECT CHECKLIST
FORM DW01
FORM DW-01
Page 1 of 1
人
Yes/No
/koelo,bret/
alibyote
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
FORM TR-01
Conforms
(Y/N)
Page 1 of 1
Pass(Y/N)
FORM TR-03
Particle Size
Distribution
(Y/N)
Page 1 of 1
Comments
INDEX OF CHECKLISTS
SU01 General
SU02 Establishment
SU03 Clearing and Grubbing
SU04 Earthworks
SU05 Base and Sub-base Pavement courses
SU06 Bituminous Surfacing
SU07 Drainage
SU08 Roadside Furniture and Markings
SU09 Masonry Structures
SU10.1 Piling for Structures-Driven Piles
SU10.2 Piling for Structures-Bored Piles
SU11 Falsework
SU12 Formwork for Concrete
SU13 Steel Reinforcement
SU14 Concrete Work
SU15 Structural Steelwork
SU16 Protection of Steelwork
SU17 Miscellaneous Bridge Items
SU18 River Training and Bank Protection
SU19 Daywork
Pages Issue
Edition Revision Description Approved By
Affected Date
INTRODUCTION
Quality Control Checklist has been produced as a general guide for the Quality
Control of Road and Bridge Construction Contracts.The Checklists included in this
Manual are based on the Department of Works Specification for Road and Bridge
Works August 1995.
The contract documents take precedence over this Manual and in the event of any
perceived conflict reference is to be made to theProject Manager for clarification.
PURPOSE AND SCOPE
The initial suite of Checklist has been developed from the Department of Works
Specification for Road and Bridge Works August 1995.These checklists are seen as
the first stage of development of the Quality Control Manual and further Checklists
are envisaged to be added to the manual as Specifications are reviewed and
incorporated in the system.
REFERENCES
As noted above the checklists form an integral part of Quality Control and the
completed checklists willform the majorityof the Quality Documentation for the
project.Other documentation that will need to be referred to will included:
·Department of Works Specification for Road and Bridge Works August 1995
·Special Conditions ofContract
·Construction Drawings