Technical Report
Technical Report
Objectives:
2. Methodology
Electrical Engineering:
Chemical Engineering:
Environmental Engineering:
Recommendations:
2. Key Components
Penstocks:
o Design Parameters:
Turbines:
Pumps:
o Contents:
Turbines
Generators
Control systems
Transmission Lines:
Energy Generation Cycle: Show how water flows from the upper
reservoir, through the penstocks and turbines, and into the lower
reservoir during electricity generation.
4. Environmental Considerations
5. Safety Systems
6. Design Standards
Where:
HHH is the effective head (height difference between the upper and
lower reservoirs) in meters.
Let’s assume an efficiency of 85% and a target head of 500 meters (based
on similar projects like the Coire Glas PSH project, which also has a head
of approximately 500 m).
This means the flow rate through the turbines must be approximately
239.25 cubic meters per second to generate 1 GW of power with a 500
m head.
Where:
Substituting values:
This means the surface area of the upper reservoir would be around
258,500 square meters, or approximately 0.26 square kilometers.
2. Penstock Design
The penstock diameter DDD can be estimated using the flow rate QQQ
and the flow velocity vvv. The flow rate is related to the cross-sectional
area AAA and the velocity by:
For a facility with a head of 500 meters, the penstock length will depend
on the vertical and horizontal distance between the reservoirs. Let’s
assume a length of 1 km. The head loss due to friction can be estimated
using the Darcy-Weisbach equation:
Where:
fff is the friction factor (assume 0.02 for smooth steel penstocks),
Thus, the head loss due to friction is approximately 3.24 meters, which is
small relative to the 500 m head and can be considered negligible in the
design.
3. Turbine Selection
Number of Turbines
4. Pumps
The pumps must be sized to handle the same flow rate of 239.25 m³/s to
pump water back into the upper reservoir during periods of low demand.
Reversible pump-turbines are often used, which means the same
equipment will be used for both pumping and generation.
Flow Rate: The penstock and turbine flow rates should be designed
with a 10-15% tolerance to accommodate seasonal variations in
water availability and grid demand fluctuations.
Conclusion
These dimensions and tolerances should provide a solid basis for detailed
engineering design and allow the facility to operate efficiently and safely.
1. Reservoirs:
Upper Reservoir:
Lower Reservoir:
o The lower reservoir is positioned 500 meters below the upper
reservoir. It should have the same capacity as the upper
reservoir (approximately 5.17 million cubic meters) to
ensure full system operation.
2. Penstock:
3. Turbines:
Type: The facility will use Francis turbines, which are suitable for
medium head projects like this one (with a 500-meter head).
4. Pumping System:
Flow Rate: The pumps must be designed to handle the same flow
rate as the turbines: 239.25 cubic meters per second.
5. Powerhouse:
6. Transmission Lines: