APP-NOTE-ExportLimitation EN RevC
APP-NOTE-ExportLimitation EN RevC
limitation
Table of contents
04 Requirements
08 Meter configuration
18 Troubleshooting
19 Annex
3
Aurora Vision
FIMER cloud solution for PV plant monitoring and management.
4
Requirements
3. A valid Aurora Vision account must be available. This can 3. Energy meter and inverter firmware release must support
be created directly within the app if an Internet connection is the export limitation according to Annex 1.
available on the mobile device.
4. A compatible energy meter must be properly installed
4. The above smartphone must be connected to the Internet and configured at the Point of Connection according to
to perform the login using the Installer for solar inverters. It is meter manual and the Meter configuration chapter.
possible to log in at an earlier stage.
5. A generator reference system must be used according to
Points 3 and 4 are required for the login process from the Reference system chapter. However, in case of a different
Installer for solar inverters app reference system, it is possible to align it as described in
Step 3: verify the reference system and meter data
acquisition.
NOTE: The Installer for solar inverters mobile app is
not compatible with Huawei smartphones or tablets. NOTE: If an inverter is replaced with an already
used spare, a connectivity factory reset must be
performed before connecting the Ethernet cable
to the inverter.
Many distribution network operators (DNOs) limit the generator A communication channel between the inverters and meter
size or the amount of power allowed to be exported. must be set up. Communication between the inverter and meter
Export limitation is a control function that limits the overall power can be realized in three different ways:
exported into the grid and meets the grid code requirements. • a direct serial RS-485 connection between the inverter and
When a grid code requires an export limit to be set, it is possible energy meter
to satisfy the requirement with FIMER inverters and a meter, • a direct Ethernet connection between inverter and energy
without the need for external controllers or additional devices. meter
An example of an export limitation with no injection is provided in • through or an existing network infrastructure
Figure 1 - Export limitation example, where the inverters follow
the load consumption to guarantee that no power is exported at Connection between inverters is always realized by an Ethernet
the Point of Connection. connection. Refer to the inverter manuals for details on the
Any time the PV power available on the inverters is greater than possible Ethernet connection options.
the load profile (red line), the inverter will reduce its own output
power to satisfy the export limit requirement, while the exceeding
power will be lost.
Any time the PV power available on the inverters is lower than the
load profile (yellow line), the export limit requirement is
Exported
automatically satisfied, and the inverter will provide the full power power
available from the solar source.
Consumed Generated Network
power power infrastructure
Lost energy
Exported energy
Connection diagram
Export limitation curtails the overall power exported from
the PV site into the grid as the net power flowing measured
Serial connection
at the Point of Connection. To achieve this control it is Ethernet connection
Electrical connection
required to install a compatible energy meter according to
Annex 1.
Figure 2 - Export limitation diagram
6
Distributed control
algorithm
The export limitation control adopts a distributed control Consumer reference system
algorithm to manage exported power. Each inverter involved in
the control decides on its own how much power to generate in
order to meet the export limit without the presence of any
defined master of the control.
The distributed algorithm avoids any issue regarding the status
of the controller and allows each inverter to define the best
solution to achieve the target.
Continuous communication between the inverters is always
required to the share meter and inverter details. To establish this
communication, there must be no firewall restrictions on TCP
port 5556 or the multicast IP group 239.192.1.1.
Reference System
Export limitation requires a generator reference system for all
measures and control architecture. A meter must be installed to
Exported power: negative
be compliant with this reference system. If the generator Imported power: positive
reference system is not applied to the meter, faulty behavior of Generated power: negative
Consumed power: positive
the control system will occur.
If an energy meter is installed according to the consumer
reference system, it is not necessary to modify the meter Figure 3.2 - Generator VS consumer reference systems
Export limit
Control set-point
Guard band
Fail-safe operations
The export limitation control design includes a fallback plan to When a fallback plan is active, each inverter will independently
guarantee failsafe operations: when a critical event happens, enter a fallback state providing an output power equal to the
each inverter applies a fallback plan to avoid exceeding the fallback set point.
export limit. The inverter will keep the output power at the fallback set point
The export limitation control activates a fallback plan when one until the triggering conditions are persistently unmet for a time
of the following triggering conditions are satisfied: greater than the operating re-entry time.
• Communication loss with the energy meter used for export The fallback plan can be enabled and configured by using the
limitation. Installer for solar inverters app within the export limitation control
• The export limitation is not reachable and the triggering event setup.
persists for a time greater of fallback activation time.
Fallback set-point
Fault clearance
Time
Figure 5 - Fallback example
Control method
P out
Control method shall be selected to configure which active power
measure is used as reference for the control.
In case single phase method is selected the control will avoid to
exceed the Export Limit for each phase, for example with an Ex-
P1
port Limit of 9kW the control will avoid to exceed 3kW per phase. P2
In case Total power method is selected the control will avoid to ex- P3
ceed the Export Limit for the whole total active power, for example
P tot
with an Export Limit of 9kW the control will avoid to exceed 9kW of
total power across the three phases.
The configuration of the Control method shall be chosen to satisfy
P load P inv
the requirements of the grid standard, just for example Spanish
grid code requires a Power per phase control method whereas
Australia requires to apply Total power method.
Meter configuration
Before activating the export limitation function, at least one PVS-50/60 and B24 connection diagram
meter must be properly configured and acquired by the inverters.
The meter selected must be compliant with the export limit
function according to the compatibility list in Annex 1:
compatibility matrix and must be installed at the Point of
Connection. -T/R
+T/R
RTN
Refer to the meter manual for the meter installation
procedure. 60
50 35 36 37
NOTE: The meter current transformer must be installed
to be complaint with the generator reference system.
J5 3 1
Serial line settings can be left as default but must be noted for
2 8
1 7
J5 J7 J6
J1
PVS-20-30-33 and meter EM133 connection diagram PVS-10-12.5-15 and meter EM133 connection diagram
Figure 9 - PVS-20-30-33 and meter EM133 connection diagram Figure 10 - PVS-10-12.5-15 and meter EM133 connection diagram
Note: Satec meter can be used only in LV systems Note: Export Limitation require to use measures at high
with a PT/VT ratio equal to one. resolution. Resolution can be configured through
EM133 display on user-configurable device options.
through Ethernet
through the internal web server of the meter according to the
M2M-Ethernet manual.
The connection between an Ethernet energy meter and inverter In case of web server configuration, the meter login should apply
can be established directly by using an existing network as the following default settings:
described in the paragraph Connection diagram. The energy • DHCP = Disabled
meter LAN port should be connected to the inverter daisy chain • Default IP = 192.168.1.239
or to a switch or router within the existing network. • Host name = ANALYZER-001
Inverters and meter must be connected and configured for the • Login Account
same LAN. IP settings must be defined by the customer or site IT o Password = admin
manager to avoid conflicts or communication issues. o Username = admin
Switch/Gateway
Figure 13 - Generation mode on M2M-Ethernet meter
Configuration for ABB M4M-Ethernet Configuration for Satec EM133 meter with TCP communica-
tion module
Switch/Gateway
Meter data acquisition Click on Add Monitored Device and proceed with the meter
Monitored Device parameter A43/A44/B23/B24 EM133 EM 133 + TCP module M2M-Ethernet M4M-Ethernet
Connection protocol Modbus RTU Modbus TCP/IP Modbus TCP/IP Modbus TCP/IP Modbus TCP/IP
Slave ID 1 1 Any Any Any
RS-485 Baud Rate 19200 bps 19200 bps - - -
RS-485 Parity Mode Even Parity No Parity - - -
IP Address - - 192.168.0.203 192.168.1.239 192.168.1.12
TCP/IP Port - - 502 502 502
NOTE: the Installer for solar inverters app will perform Meter installation and configuration
the commissioning process on all the inverters in the The meter must be properly configured according to the
device list at the same time. instructions for the meter manual for electrical connection and
The commissioning process through the web user the instructions included in this guide for communication
interface must be repeated for each inverter included physical connection.
on the device list.
Once the meter is properly installed it is necessary to enable the
Firmware upgrade data acquisition of the meter through the Installer for solar
All the inverters enabled for export limitation control need to inverters. In case of a serial RS-485 connection between the
support the control algorithm according to the compatible list meter and inverter, the meter must be assigned to the inverter
included in Annex 1: compatibility matrix. physically connected to the meter, while in the case of an
It is strongly suggested to keep the inverters upgraded to the Ethernet connection, the meter can be assigned to any single
latest firmware and aligned to the same control algorithm inverter.
release. This functionality can be applied only if all the inverters
involved in the control share the latest control algorithm release. NOTE: The meter Ethernet settings must be written on
the inverter. Consequently a fixed private IP address
NOTE: The Installer for solar inverters app can perform must be assigned. It is allowed to enable DHCP on the
the firmware upgrade process on all the inverters on meter only if the DHCP server is configured to assign
the device list at the same time. The firmware upgrade a fixed private IP address associated with the meter’s
process using the web user interface needs to be Mac Address.
repeated for each inverter included on the device list.
NOTE: It is possible to repeat the scanning process Step 2: select the meter
with the re-scan button if one or more inverters are The scanning process automatically finds and lists all meters
missing. previously configured in the monitored device section and that
are compatible with Export Limitation.
Only the meter installed at the Point of Connection should be
selected as a reference meter for the export limitation control.
In case more meters are available, it is possible to expand the
selection to find out additional details of the meters.
16
Step 3: verify the reference system and meter data acquisition Step 4: configure export limitation
If the meter is installed with the consumer reference system, it Since all the devices are already selected, it is possible to proceed
is possible to revert the meter data acquisition to the correct with export limitation settings.
generator reference system without the need to rework the An export limit is expressed as a percentage value of the PV plant
installed meter. nominal power, which is used only as reference number.
The Installer for solar inverters app provides the possibility to The PV plant nominal power shall be intended as the reference
change the reference system used for export limitation directly nominal value used by a specific country to define the limit of
without the need to operate on the installed meter. exported power. Typically this value is represented by the sum of
Through the reverse CT button, it is possible to apply a sign the nominal AC power of the inverters installed.
reversion to any current related measure acquired on the meter. The export limitation control utilizes the export limit parameter as
To check the reference system, select edit meter configuration the threshold value for fail-safe operations. PV plant nominal
under meter details and stop inverter productions using the AC power is not used in the control system.
disconnection or Remote OFF command.
The guard band is the control margin used to achieve the export
limit and is expressed as a percentage of the PV plant nominal
power.
NOTE: The guard band shall not be configured at 0%
in case fallback is enabled.
NOTE: Remember to switch on the right flag to enable Step 7: apply setting
export limitation. Press the save button to apply the new settings and start Export
Limitation control on all selected inverters.
18
Once the export limitation configuration is completed, it is The inverter section of the control status provides details for
possible to immediately check the behavior of the export limita- each inverter participating in the control. For each inverter it is
tion and the real time measures for: possible to check:
• Exported Power: the overall power exported at Point of – Global, alarm and export limitation state: an inverter
Connection, provided by the meter. properly working will have a green flag for each state.
• Generated Power: overall power generated as a sum of – Inverter output power: the output power could be
t h e controlled inverter output power. different on each inverter being the control algorithm
• Consumed Power: calculated power absorbed by the loads. distributed.
– Derating state and set point: the derating state is ON
A colored status bar shows the position of the exported power in when the inverter curtails the output power. The derating set
respect to the control set point (dotted line) and export limit point represents the current power curtailment
(continuous line): applied by the inverter.
If the exported power is less than the control set point, the bar
will be filled in blue (CASE A).
If the exported power is within the guard band, in the band
between the control set point and the export limit, the bar will be
filled in yellow (CASE B).
If the exported power is over the export limit the bar will be filled
in red (CASE C).
The bar will refresh about every 5 seconds, while the export
limitation control operates at a higher frequency, so the bar does
not represent all the power transition within the plant but only a
snapshot of the current situation.
NOTE: The minimum representable value of the status Figure 24 - Export monitoring: inverter status
bar is 35% of the nominal power less than the export
limit. If the power exported at the Point of Connection
is less, the bar will be completely gray. In case the export limitation control is not acting properly; it
is possible to stop the control and change settings to adapt
NOTE: A red colored bar is a triggering condition for a the parameters to increase the efficiency of the system.
fallback plan.
19
Troubleshooting
The PV plant generated power is fixed at 0W and loads are PV plant exported power oscillates continuously
absorbing power.
1. Oscillations in the export limitation can occur if the inverters
1. Check the inverter and meter status. An active fallback for enter continuously on fallback, increasing the fallback activation
missing meter may reduce the generated power. time. If admitted by the grid standard an increase in the guard
band will reduce the number of fallback events and consequently
2. Check the meter position. The meter should be installed at the oscillations.
Point of Connection to include the net power exported into the
grid. In case the meter is not located at the connection point, but 2. Fallback can happen if there is an Ethernet connection failure.
it is installed on the load output or inverter output, the export An unreliable Ethernet connection can trigger a fallback event
limitation may be using an incorrect power value. independently of the fallback settings. If a fallback is caused by
device communication errors, evaluate the integrity of the
3. Check the reference system according to Step 3: verify the Ethernet cables using an Ethernet cable tester.
Reference System and meter data acquisition.
The export limitation cannot properly control the exported power 3. Check the meter settings for current (CT) and voltage (VT)
if the reference system is not aligned to the generator reference transformers. If CT or VT are not properly settled, the meter will
system. not read the effective power flowing through the grid.
4. Check the meter settings for current (CT) and voltage (VT) It is not possible to retrieve all the inverters during the
transformers, if CT or VT are not properly settled, the meter will Export Limitation scan process.
not read the effective power flowing through the grid.
1. If all inverters are not available on the device list, add missing
5. In the case of an M2M meter and if the reverse CT option is inverters with QR code scan (preferred) or Wifi scan.
enabled, check on the energy meter to see if the generation
mode is enabled. 2. If all inverters are available on the device list but are lost
inside Export Limitation inverter selection check the Ethernet
connections and IP settings of inverters. In case of Ethernet ring
PV Plant generated power is fixed at full power and plant topology is used, open the ring disconnecting an Ethernet cable
export power into the grid form a single inverter and try again.
1. Check the meter settings for current (CT) and voltage (VT) 3. In case the network set up VLans, apply the same VLan ID to
transformers. If CT or VT are not properly settled, the meter will all the devices or enable the IGMP protocol on network switches
not read the effective power flowing through the grid. to allow the flow of Multicast packets used by the distributed
control solution.
2. Check the reference system according to Step 3: verify the
Reference System and meter data acquisition. Energy meter measures or PoC measures within Control
Export limitation cannot properly control the exported power if Status page are very low or high.
the reference system is not aligned to the generator reference
system. 1. Verify if the CT and VT ratio are properly set within the energy
meter.
3. Check the flag for export limitation. If export limitation is not
enabled or the configuration is not properly applied, the control Aurora Vision does not notify alarms and events about Export
will not take place. Limitation
4. In case of an M2M meter, check if the generation mode is 1.Make sure the Export Limitation category is included in the
enabled on the energy meter. Event Profile associated with the monitored plant within Aurora
Vision Plant Portfolio Manager.
20
Annex
Connection CT VT
Meter model PN for order Minimum Logger Firmware Release Mounting
mode available available
PVS- PVS- PVS- PVS-
PVS-175
100/120 50/60 10/12.5/15 20/30/33
ABB - 824 212-100 2CMA100180R1000 RS 485 √ x 0.14.9 1.6.9 x 2124B 2117E Din bar
ABB - 824 3 5 2 -100 2CMA100183R1000 RS 485 √ x 0.14.9 1.6.9 x 2124B 2117E Din bar
ABB - A44 212-100 2CMA170534R1000 RS 485 √ √ 0.14.9 1.6.9 √ 2124B 2117E Din bar
ABB - A44 352-100 2CMA170537R1000 RS 485 √ v 0.14.9 1.6.9 √ 2124B 2117E Din bar
ABB - M2M-Ethernet 2CSG299903R4052 Ethernet √ √ 0.14.9 1.6.9 0.4.12 2124B 2117E Front panel
ABB - M4M-20-Ethernet 2CSG204471R4051 Ethernet √ √ 1.0.8 1.8.7 0.4.12 2124B 2117E Front panel
ABB - M4M-30-Ethernet 2CSG274681R4051 Ethernet √ √ 1.0.8 1.8.7 0.4.12 2124B 2117E Front panel
RS 485 or
SATEC· EM 133 - Ethernet √ √ x x x 2124B 2117E Din bar
Minimum lnverter Firmware Minimum Logger Firmware Minimum lnstaller for solar
Inverter model
Release Release Release
Tables list
Table 1 - Serial line connections
Table 2 - Energy meter default settings
Table 3 - Meter compatibility matrix
Table 4 - Inverter compatibility matrix
Table 5 - Guideline track change