Variance

Uploaded by

AnishKaria
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Material Variance

1. Material Price Variance (MPV)


(Standard Price – Actual Price) X Actual Quantity

2. Material Usage Variance (MUV)


(Standard Quantity – Actual Quantity) X Standard Price

3. Material Cost Variance


(Standard Cost – Actual Cost)
(Standard Quantity X Standard Price) – (Actual Quantity X Actual Price)

4. Material Yield Variance


(Actual Yield – Standard Yield) X Standard Material Cost Per Unit

Standard Material Cost Per Unit = Standard Cost of Standard Mix / Net Standard Output

5. Material Mix Variance


(Revised Standard Quantity – Actual Quantity) X Standard Price.
Sums on Material Variance

Question No. 1
ABC ltd. provides following information
Standard Price: Rs. 10/- Standard Quantity: 20 kgs
Actual Price: Rs. 9/- Actual Quantity: 22 kgs
You are required to calculate
Material Price Variance, Material Usage Variance and Material Cost Variance

Question No. 2
PQR ltd. provides manufactures 100 units of Product “X”
Standard Price: Rs. 10/- Standard Quantity: 20 kgs per unit
Actual Price: Rs. 9/- Actual Quantity: 22 kgs per unit
You are required to calculate
Material Price Variance, Material Usage Variance and Material Cost Variance

Question No. 3
Calculate Material Variances for an output of 80 units from the following information given
Standard Quantity: 3 kgs per unit of output Actual Quantity Consumed: 2 kgs per unit
Standard Price: Rs. 4/- per kg Actual Price: Rs. 6/- per kg

Question No. 4
Calculate Material Variances for an output of 80 units from the following information given
Standard Quantity: 3 kgs per unit of output Actual Quantity Consumed: 160 kgs
Standard Price: Rs. 4/- per kg Actual Price: Rs. 6/- per kg

Question No. 5
Calculate Material Variances from the following information

Standard Actual
Material
Qty. (kg) Price (Rs.) Qty. (kg) Price (Rs.)
X 60 15 55 18
Y 40 12 45 10
Question No. 6
The standard cost shows the following data related to materials need to produce 1 kg of
Product “Y”
Quantity of Material Required : 3 kg
Price of Material : Rs. 2.5/- per kg
Actual Production : 100 kg of Product “Y”
Actual Quantity of Material Used : 3,500 kg
Price of Material : Rs. 3/- per kg
Calculate: Material Price Variance, Material Usage Variance and Material Cost Variance

Question No. 7
The following information is provided by the company

Standard Actual
Material
Qty. (kg) Price (Rs.) Value (Rs.) Qty. (kg) Price (Rs.) Value (Rs.)
X 60 10 600 55 12 660
Y 40 12 480 45 10 540
Output 90 kg 1080 80 kg 1200

Calculate: Material Price Variance, Material Usage Variance, Material Cost Variance and
Material Yield Variance.

Question No. 8
The following information is provided by the company

Standard Actual
Material
Qty. (kg) Price (Rs.) Value (Rs.) Qty. (kg) Price (Rs.) Value (Rs.)
X 60 10 600 55 12 660
Y 40 12 480 45 10 540
Gross
100 kg 100 kg
Output
Loss 10 kg 20 kg
Net
90 kg 1080 80 kg 1200
Output

Calculate: Material Price Variance, Material Usage Variance, Material Cost Variance and
Material Yield Variance.