Divisional Office,
Traction Distribution,
Tiruchchirappalli
Sub:-Parting of contact wire near Raised Register Arm Clamp in MAQ-JOKT section –
reg.
****
3. Depots are advised to check all RRA clamp locations used in new electrification
works also to ensure adoption of latest RRA clamp as per RDSO drawing No.
ETI/OHE/P/1370-1 Rev.H issued during June 2019 (copy enclosed). Further it is
advised to conduct special check in contractor’s depot of RE/CN/RVNL and also in
the OHE already erected in the on-going electrification works to ensure RRA clamps
without sharp edges and without sharp angle of deviation.
4. The method of calculating the angle of deviation of contact wire at RRA clamp
location is given below for ready reference.
AMAL
DN: c=IN, o=SOUTHERN RAILWAY,
ou=ELECTRICAL/TRD,
2.5.4.20=77600d0d865b889b90bfac93dd3bdd
04a52e52e2311a764383b5ffccac37c551,
SEBASTIAN
postalCode=620001, st=TAMIL NADU,
serialNumber=805727f6e4beb4d0ef9c4b1068
a3f4c7cc7a1050646f3312c7e65d0e14826944,
cn=AMAL SEBASTIAN
Date: 2022.03.03 15:05:41 +05'30'
DEE/TRD/TPJ
ADEE/TRD/TVR
प्रधानकार्ाालर्
बिजलीशाखा, चेन्नई-3
Headquarters office
Electrical Branch
दक्षिणरे लवे Chennai-600 003
SOUTHERN RAILWAY
No.E.252/V/26/3/1 21.02.2022
Sub:-Parting of contact wire near Raised Register Arm Clamp in MAQ-JOKT section – reg.
Ref:- RB Letter No. 2021/EEM/161/8/Punct/Pt-Part(2) (3371819) dated 14.02.2022
^^^^^^^^^^^
1. PREAMBLE:
Contact Wire parting in CR has taken place near RRA clamp on 01.11.21 due to sharp angle of
termination. It was advised to divisions earlier also to identify such locations and monitor them
frequently on quarterly basis to detect if there is any chance of contact wire parting. However only
Chennai division has identified one location and no location has been identified by any other division.
There was a case of contact wire parting from RRA clamp on 11.02.2022 in MAQ-JOKT section in PGT
division, where contact wire snapped at RRA clamp location No.6/38, which was erected by RE/MS
during February 2017. The detail of failed location is appended before for reference:-
Span length – 29.5m
Track Centre – 5.95m
Degree of curvature in OOR span = 11.5° inside curve.
Subsequently the entire MAQ-JOKT section has been checked and it is observed that further 8 locations
has been identified with sharp curve of more than 8° curve; out of which 5 locations were executed by
‘RE/MS’ and 3 locations were executed by ‘CN/MS’.
2. In order to avoid similar failure at RRA camp location in future, all executing agencies viz.,’RE/MS’,
‘CN/MS’ and ‘RVNL/MTMY’ along with division/(s) shall ensure that the angle of deviation of contact
wire at OOR location should be as minimum as possible and also the angle of deviation be restricted
preferably in the range of 2.5° to 6.2° for anchor spans of 72.0m to 27.0m respectively with 3.0m
implantation of anchor mast. However the angle of termination should not be > 8°.
3. In order to avoid contact wire parting at RRA location, divisions are advised to follow Special
Maintenance Instruction No.TI/MI/0058 (copy enclosed). In addition, whenever the RRA clamp is
opened for shifting, the clamp bolts are to be loosened properly and then only the shifting should be
done. Under no circumstances, should the clamp be hit/ hammered as the contact wire is liable to be
damaged.
4. In view of the above, it is felt necessary to check all RRA clamp locations used in new electrification
works also to ensure adoption of latest RRA clamp as per RDSO drawing No. ETI/OHE/P/1370-1 Rev.H
issued during June 2019 (copy enclosed). Divisions are advised to conduct special check in contractor’s
depot of RE/CN/RVNL and also in the OHE already erected in the on-going electrification works to
ensure RRA clamps without sharp edges and should not have sharp angle of deviation
5. Action taken for Para 4.0 above may be submitted to HQ on PRIORITY please.
In all new RE/RVNL/Construction works this point must be made as a check point and a summary
statement indicating angle of deviation of all contact wire terminations should be submitted jointly
signed by executing agency and divisional officials along with EIG documents.
Further CPD/RE/MS and CEE/CN/MS may please take necessary action for correcting the locations
identified by PGT division in MAJN Yard and submit PDC for the same.
Encl: as above.