SGL DBL TR Bridges W End Trucks Flush 08-11-22
SGL DBL TR Bridges W End Trucks Flush 08-11-22
END TRUCKS
SINGLE GIRDER RATED LOADS:
115 mm (4.5”) thru 305 mm (12.01”)
GENERAL For information regarding attaching, lifting and moving the loads
during installation, refer to ANSI B30.2-latest edition, Chapter
These top running bridge cranes are designed to operate on
2-3 Overhead and Gantry Cranes (Top Running Bridge, Single
parallel crane runway beams with ASCE Rail from 25# to 105# rail
or Multiple Girder, Top Running Trolley Hoist); ANSI B30.17-
or square bar. Specific rail range is wheel diameter dependant.
latest edition, Chapter 17-3 Overhead and Gantry Cranes (Top
Motors are designed for operation on three phase power supplies
Running Bridge, Single Girder, Underhung Hoist) and other
from 190 to 415 V-50 Hz and 200 to 575 V-60 Hz. Bridge motors
applicable codes.
and brakes are designed and intended strictly for variable frequency
control operated by push-button pendant or radio control. Pendant
may be located and suspended from an independent festoon or
attached directly to the hoist and trolley. Standard under running
WARNING
single girder plug & play crane kits described herein are built Before installing the crane on the runway, lock the
to 1 through 15 tonne capacities with spans to 60 feet (18.2 runway conductor disconnect switch in the open (OFF)
meter). Standard top running double girder plug & play crane kits position.
described herein are built to 1 through 20 tonne with spans to
60 feet (18.2 meter). Higher capacities & spans are available and Prior to the start of any crane erection the building should be
reviewed upon individual application. Cranes are designed per measured to confirm span and clearances. These measurements
CMAA Specifications 70 and 74 to meet Class C Moderate Duty should be checked against the corresponding crane
Service classification. measurements to insure correctness of “fit.” After assuring that
the crane fits the building, determine orientation of crane position
with respect to the runway. In addition, verify building and runway
WARNING power supply to ensure it matches the power requirements of
To prevent traverse motors from coming loose, Loctite the crane.
must be applied to mounting bolts and bolts must be
torqued properly. These types of cranes are usually lifted into position on the runway
in one piece. Total weight of this crane should be checked against
Bolt torque should be checked on a regular maintenance lifting equipment selected for erection of this crane.
schedule.
Immediately after the crane is placed on the runway rails check the
Truck Bolt Size Required Torque wheel flange clearances to the rail. Clearance between the side
of rail head and inside flange of wheel should be between a total
115 mm M6 x 1.0 x 20
7.5 to 8 ft-lbs of 3/4” and 1-1/8”, depending on the wheel and rail combination
160 mm M6 x 1.0 x 25 and whether or not the truck is centered on the rail. Total wheel
200 mm M8 x 1.25 x 30 float should not be less than the 3/4" as recommended by CMAA
18 to 20 ft-lbs Specifications #70 and #74.
260 mm M8 x 1.25 x 40
305 mm M12 x 1.75 x 45 62 to 68 ft-lbs Note: It is suggested that the trolley and hoist be
installed on the bridge crane at this time so that all
wiring connections can be completed.
WARNING
Before attempting any electrical connections, the main
power switch feeding the runway conductors must be
LOCKED IN THE OPEN (OFF) POSITION.
NOTICE
A fused disconnect switch or circuit breaker must be
installed and electrically positioned between building
power supply and crane runway conductor system. This
disconnect must be lockable in the open position, in-sight
and in-reach for the crane operator, and clearly labeled.
A second lockable disconnect is required on the bridge
crane, electrically positioned between the runway conductor
system and bridge controls. Refer to Article 610 of NFPA
No. 70 National Electric Code, OSHA Regulation 1910.179,
ANSI/ASME B30.2 and B30.17, local, state and provincial Figure 1. Bridge Gear Motor Quick Connection Plug
standards and regulations for specific requirements.
CAUTION
CAUTION Gearmotors provided with this crane kit are intended for
In accordance with Article 610 of NFPA No. 70 National variable frequency control only. The brake used on the
Electric Code a separate bonding conductor must be run gearmotor is a holding brake with no provision for torque
for ground. Grounding through the wheels to girders and adjustment. Severe load swing will result without the
runway steel is not permitted. controlled deceleration when stopping provided by the
variable frequency control. The use of contactor, across the
line starting, controls is not permitted, will result in damage
RUNWAY CONDUCTORS and premature failure of these units and void any warranty.
Motorized bridge cranes and bridge cranes equipped with a
motorized trolley or hoist require runway conductors. Install
conductors according to manufacturer’s instructions and in NOTICE
accordance with National, State and Local codes.
Prior to placing the crane into service, the crane shall
receive an initial inspection. This inspection should be
RUNWAY COLLECTORS performed by a qualified person in accordance with ANSI/
Install, adjust and align collectors with runway conductors. Connect ASME B30.2 or B30.17, local, state and provincial standards
collectors to appropriate crane wiring as shown in Crane Inter- and regulations.
Connection Diagram Figure 10.
START-UP AND PRE-OPERATIONAL INSPECTION
NOTICE After the crane has been installed on the runway and the crane,
hoist and trolley has been connected to electrical service but prior
A minimum of two collector shoes for each conductor bar to placing into service, as a minimum the following inspections
is required when using variable frequency drives (inverters) should be made by a qualified person.
on bridge and/or hoist controls, per Section 5.14.7 of CMAA
Specifications #70 and #74. Yale•Shaw-Box standard 1. Check the main collector system for proper adjustment
bridge controls utilize variable frequency drive. to maintain proper contact with conductors. Check along
runway for possible interference if power is supplied by a
cable reel or festooned cable.
7. Inspect the alignment of the trolley end stops to the trolley WARNING
and the runway end stops to the bridge end trucks. These bridge cranes are not designed nor intended
8. Turn power on at both disconnects and mainline. Inspect to be used for support or transport of people or for
hoist for reverse phase condition by ensuring push button transporting loads over people.
operation corresponds to intended direction of travel and
correct if necessary per manufacturer’s instructions. Safe operation of an overhead hoist is the operator’s responsibility.
Listed below are some basic rules that can make an operator
9. Operate the crane to verify both motors operate in the same aware of dangerous practices to avoid and precautions to take
direction, in both bridge directions. for his own safety and the safety of others. Observance of these
rules in addition to frequent examinations and periodic inspection
10. With no load, operate hoist/trolley back and forth the full
of the equipment may save injury to personnel and damage to
length of bridge girder and operate the crane the full length
the equipment.
of the runway. During the operation, ensure and verify proper
clearances from obstructions per CMAA, ASME B30.2, ASME
DO NOT load bridge beyond rated capacity.
B30.17 and OSHA requirements.
11. Load testing the crane should be performed in accordance DO NOT subject bridge crane to side loads. Always center
with ANSI/ASME B30.2 or B30.17, local, state and/or provincial trolley over load when hoisting.
codes and regulations. A written report should be prepared
during the performance of this test and placed on file. DO NOT stand and DO NOT cause or allow others to stand or
get under any load the bridge crane is supporting.
OPERATION DO keep clear, and make sure others keep clear, of any load
the bridge crane is supporting.
OPERATOR QUALIFICATIONS
DO NOT attempt to operate bridge crane before completing
Safe and efficient crane operation requires skill, extreme care, tests and adjustments.
good judgment, alertness, concentration and knowledge of and
rigid adherence to proven safety rules and practices. No person DO NOT run bridge crane into end stops, other bridge cranes,
should be permitted to operate a crane or hoist: or any obstruction on beam. Improper and careless operation
can result in a hazardous condition for operator and load.
• Who does not possess the above characteristics
• Who is not qualified or has handicaps that could adversely ALWAYS be sure load is clear of obstruction before travers-
affect such operation ing load.
If bridge crane is mounted on an open-end runway rail, Having inspected and tried the control, the crane operator is
then end stops must be installed to prevent bridge crane now ready to try the crane under power.
from running off the end of the runway rail resulting in
injury to the operator or others, as well as damages to
the load and other property. End stops for the trolley CAUTION
must also be installed. ALWAYS ALLOW THE BRIDGE CRANE TO COME TO
A COMPLETE STOP BEFORE CHANGING DIRECTION.
Refer to hoist and trolley instruction manuals for safety warn- ABRUPT CHANGE OF BRIDGE DIRECTION WHILE
ings on hoists and trolleys. IN MOTION MAY CAUSE ADVERSE OPERATING
CHARACTERISTICS OR DAMAGE TO BRIDGE AND DRIVE
Read and comply with ANSI B30.2 or B30.17-latest edition. COMPONENTS.
Read and comply with all local, state and national safety codes.
STEP 1.
Close the crane runway disconnect switch.
GENERAL
Motor driven cranes are usually operated from a pendant push STEP 2.
button station or radio control, which controls the bridge electrically. Close the crane disconnect switch mounted on the crane. The
The push button may be suspended from the bridge, trolley or crane main disconnect switch is located in the bridge panel and
hoist. Push-button control stations, supported by a strain cable, is operable from the front of the panel without opening the panel.
have a built-in interlock to prevent energizing opposing motions The switch is operated by rotating the handle. The “OFF” and
at the same time. “ON” positions of the switch are marked on the switch assembly.
WARNING To operate the crane, press the button for desired direction,
FWD or REV, to the first step. The crane will start moving and
If any push button binds or sticks in any position - Do
accelerate to its programmed starting speed. Press the same
not turn the power on - Determine the cause of the
button further to the second step and the crane will accelerate
malfunction and correct it before operating the crane.
up to full speed. If the crane reaches a desired speed during this
acceleration, back the button off to the first step to hold that
speed. If the crane is traveling too fast and you wish to slow it
down, release the motion button completely and the crane will
start to decelerate. Once the desired slower speed is obtained,
press button to the first step to hold that speed. To bring the
crane to a stop, release the motion button completely. The crane
will decelerate to a stop and the holding brakes will set.
WARNING
NOTICE
THIS EQUIPMENT IS NOT DESIGNED OR SUITABLE
Since a variety of hoist/trolley combinations may be used AS A POWER SOURCE FOR LIFTING, LOWERING, OR
with this type of bridge crane, refer to the manufacturer’s TRANSPORT OF PERSONS.
instruction manual for this equipment and the specific
details on its operation.
OPERATING THE CRANE
STEP 6. Once the crane has successfully passed its Start-up and Pre-
Once the operator(s) are acquainted and comfortable operating the Operational (Initial) inspection, and all the crane operators have
crane and the hoist/trolley, they shall learn the Pre-Shift inspection been successfully trained and/or licensed, it is now ready to be
procedure. Refer to the INSPECTION section of this manual. placed into service.
WARNING WARNING
If, when depressing the hoist "Up" button, the hook Do not operate a crane, hoist or trolley having unusual
should lower - STOP AT ONCE - Do not attempt to vibrations, sounds, warnings or with anything wrong
operate again. Report this condition to the proper or apparently wrong. Danger may be present that the
supervisor for correction with the instructions furnished crane operator cannot see. Determine and correct the
with your hoist manual by a qualified crane technician. cause of the unusual conditions and make certain that
the crane can be operated SAFELY.
Set lower limit switches of the hoist and insure proper functioning
per the Hoist Manufacturer's Manual. STEP 1.
Turn power on to the crane, disconnects, and mainline. If
When operating the hoist in the up direction CAREFULLY OBSERVE not already done, perform Pre-Shift Inspection. Refer to the
the relationship of the hook block and the bottom of the hoist frame. Inspection Section of this manual.
The hoist upper limit switch, when working properly, should cause
the hoist up motion to stop and/or reverse direction. STEP 2.
Move the crane to the load, making certain the load hook is high
enough to clear any obstruction in its path. Position the hoist and
trolley so that the load hook is centered over the load. Lower the
load hook for load attachment. For larger sized loads, the use of
a rigging or load director may need to be used to direct the lift
and movement of the load. This person should use the proper
hand signals as shown in this manual. The crane operator should
respond only to the signals of the designated person directing
the load, except for emergency stop as shown in Figure 2.
• There are arguments or disagreements with the floor man Reeving Check that the wire rope is properly reeved
and that rope parts are not twisted about each
or hitchers other.
• The operator feels ill or is not alert Limit Switches Check that the upper limit device stops the
lifting motion of the hoist load block before
striking any part of the hoist or crane.
INSPECTION Oil Leakage Check for any sign of oil leakage on the crane
and on the floor beneath the crane.
Overhead cranes are subject to four levels of inspection: Initial, Unusual Sounds Check for any unusual sounds from the crane
Pre-Shift, Frequent, and Periodical in accordance with the latest or hoist mechanism while operating the crane
or hoist.
editions of ANSI/ASME B30.2, B30.17 and CMAA 78. These
inspections are necessary to ensure the equipment is safe for use Warning and Check that warning and other safety labels are
Safety Labels not missing and are legible.
and operating at its required performance level. Inspection criteria
described herein are general requirements. Specific inspection Housekeeping Check area for accumulation of material to
and Lighting prevent tripping or slipping. Also check area for
criteria will be based on the options and accessories provided
poor lighting.
with your crane. Refer to the manufacturer’s maintenance manual
for the hoist/trolley and its specific inspection criteria.
FREQUENT INSPECTION
INITIAL INSPECTION
Frequent inspections are to be performed by a qualified designated
New, re-installed, altered, repaired and modified cranes shall be person. Inspection intervals vary by class of service, for Class C
inspected prior to initial use. Inspection of all altered, repaired or Service cranes they are to be performed monthly at a minimum.
modified cranes may be limited to the provisions affected by the Hooks and wire rope or load chain are to be inspected in monthly
work as determined by a qualified crane technician. Inspections intervals as a minimum and recorded including date, serial/trace
shall include, but not limited to, clearances, operating speeds, numbers and a signature. Frequent inspections also include a
lubrication, control settings, safety devices, etc. Refer to START UP thorough operational inspection. Items to be inspected include
and PRE-OPERATIONAL INSPECTION elsewhere in this manual. traverse motor mounting bolt torque (see page 3 for bolt torque
specifications), limit switches, lubrication levels in all gearcases,
wheels, bearings, etc., brakes, electrical equipment and all safety
PRE-SHIFT INSPECTION devices. Crane is to be operated without a load to check for any
unusual sounds, vibrations, or anything that may be apparently
A pre-shift inspection shall be performed by the crane operator or wrong. The designated person shall determine if conditions found
designated person at the beginning of each shift, or the first time are a hazard and a more detailed inspection is necessary. Refer
the crane is used during each shift. This is a visual and operational to the typical Inspection Schedule and Maintenance Report
inspection to ensure the equipment is in good working order. Items found on page 15 in this manual.
to be checked include limit switches, brakes, electrical equipment
and all safety devices. Crane is to be operated without a load to
check for any unusual sounds, vibrations, or anything that may be
• All connections and mountings for loose bolts, nuts and other
fasteners for tightness.
WARNING
Always lock main switch in the open position (OFF)
before inspection.
NOTICE
Cranes that have been sitting idle for six months or
greater shall receive a complete periodic inspection
prior to its use.
MAINTENANCE
GENERAL
Maintenance services required on top running cranes are, for the
most part, simple periodic inspections and adjustments. Procedures
for lubrication, routine adjustments and replacement of parts, if
required, are described in the following paragraphs.
5. ill gearcase with correct amount of oil per chart above and
F WARNING
replace drain/filler plug.
Make sure that truck is adequately supported so that
6. ount complete gearmotor back on end truck and bolt back
M it cannot drop when wheel is removed. Due to the
into place. Using a torque wrench, tighten all bolts to the weight of the wheels and bearing cages, make sure
specifications listed below: that the proper equipment is in place to safely remove
the wheels and bearing cages from the end truck.
Truck Bolt Size Required Torque Also lock main runway disconnect switch in the open
115 mm M6 x 1.0 x 20 position (OFF) when working on wheels adjacent to
7.5 to 8 ft-lbs runway conductors.
160 mm M6 x 1.0 x 25
200 mm M8 x 1.25 x 30 2. Disconnect power and lock out.
18 to 20 ft-lbs
260 mm M8 x 1.25 x 40
305 mm M12 x 1.75 x 45 62 to 68 ft-lbs NOTICE
7. Re-install motor plug. MAKE SURE ALL JACKING OR LIFTING OF END TRUCK
FOR WHEEL REMOVAL IS DONE NEAR THE BRIDGE
8. urn power back on to crane and test run, checking for any
T
GIRDER(S) OR SIMULTANEOUSLY AT EACH END OF
signs of leaks.
THE TRUCK BETWEEN THE WHEEL AND THE GIRDER(S).
JACKING OR LIFTING ONLY ONE END OF THE TRUCK
MAY PERMANENTLY DAMAGE THE CRANE.
5. ack end truck to height that will allow bearing cage to roll
J
out from end of end truck.
10. P
rior to re-assembling bearings to axle, pack the roller bearings 4. Roll o-ring back into place and re-install brake cover.
with grease. Use NLGI #2 general purpose grease unless 5. Turn power back on to crane and test brakes for proper
the severity of the duty cycle and/or operating environment operation.
warrants otherwise. Press bearings onto wheel axle, ensure
they are fully seated.
Brake Air Gap Inspection for Nord Gearmotors
11. Assemble both bearing caps onto bearings.
The brake air gap is checked by placing a feeler gage between
12. P
lace wheel assembly onto runway rail and roll it into place in metal anchor plate and the brake coil housing. This procedure
the end truck. Orient the grease fitting (if provided) on bearing is identical even for the larger twin rotor brakes.
cap, pointing towards the rail sweep.
Procedure
13. C
arefully lower end truck, ensuring bearing caps and the end 1. oosen the fixing screws that attach the brake to the motor’s
L
truck pilot diameters align properly. Install and tighten bearing end-shield by approximately half a turn.
cap bolts. Using a torque wrench, tighten all bolts to 36 ft. lbs.
torque for 115 mm (4.5"), 160 mm (6.3") and 200 mm (7.9") 2. If required, the brake assembly may be loosened slightly
end trucks, 72 ft. lbs. torque for 260 mm (10.2") and 305 mm from the motor’s end shield by turning the threaded setting
(12.01") end trucks. bolts (hollow screws) that surround the fixing screws, counter
clockwise, into the brake coil housing.
14. Lower end truck onto runway rail.
15. R
e-install rail sweep and gearmotor. Connect motor power Air Gap
Motor End Bell Brake Mounting Bolts
plug. Refer to page 10 for torque specifications.
Shroud
16. T
urn power back on to crane and inspect crane for proper
operation.
3. Carefully roll the o-ring back towards the magnet body exposing
the air gap between the armature plate and magnet. Use feeler Figure 6. Motor Brake
gauge and measure the gap between the armature plate and 3. epending upon whether or not the air gap needs to be
D
magnet. If gap exceeds maximum allowed, replace the brake. decreased or increased, turn the fixing screws accordingly
until the desired nominal air gap is reached, as measured
using the appropriate feeler gauge. Turning the fixing screws
clockwise allows the brake coil housing to be moved towards
the anchor plate and reduces the air gap. Turning the fixing
screws counter-clockwise allows the brake coil housing to be
moved away from the anchor plate and increases the air gap.
5. Tighten the fixing screws to the appropriate torque. 11. Put the fan and screw the two (2) screws of the clamp.
6. Re-check and measure the air gap in multiple locations to 12. Put the fan cover and tighten with four (4) M4 screws.
check for appropriate spacing. Repeat the steps as needed
until the desired air gap spacing is uniform and consistent all
the way around the brake. Fir Gearmotor
Motor Normal Maximum Brake Mounting
Nord Gearmotor horsepower KW Air Gap Air Gap Bolt Torque
Motor Normal Maximum Brake Mounting 0.75 0.55 0.3 0.4 Not Defined
horsepower KW Air Gap Air Gap Bolt Torque 1.0 0.75 0.4 0.5 Not Defined
0.75 - - - - 1.5 1.2 0.4 0.5 Not Defined
1.0 0.75 0.2 0.6 4.4 lb-ft 2.0 1.5 0.4 0.5 Not Defined
1.5 1.2 0.2 0.7 7.4 lb-ft 3.0 2.2 0.4 0.5 Not Defined
2.0 1.5 0.2 0.7 7.4 lb-ft 5.0 3.6 - - -
3.0 - - - -
5.0 - - - - BRAKE RECTIFIER REMOVAL AND REPLACEMENT
Rectifier is located inside the motor conduit box cover. To replace
Brake Air Gap Inspection for FIR Gearmotors
follow these steps:
Procedure
1. Disconnect and lock out power supply.
1. Remove the fan cover
2. Unplug motor leads and open conduit box.
2. Unscrew the (2) screws of the clamp and remove the fan.
3. Remove rectifier and unplug wires.
3. Remove the retaining ring.
4. Plug wires into replacement rectifier.
4. Unscrew the (4) M4 screws.
a. Connect brake leads to DC side of rectifier, terminals
5. emove the brake cover, with rubber bearing holder and the
R marked “+” & “–”.
ball bearing.
b. Connect leads from the plug to the AC side, two
6. heck the air gap (0,4÷0,5 mm) in different positions, using
C terminals marked “~”.
the feeler gauge. 5. Re-assemble in reverse order disassembly.
7. If the air gap is different than the adjustment range: 6. Turn power onto crane and test for proper operation.
a. aintain locked the first nut (and the rotor shaft) with the
M
adjustable spanner.
BRAKE REMOVAL AND REPLACEMENT
b. sing a second adjustable spanner, completely unscrew
U
the second nut. If brake air gap exceeds the maximum allowed, or is not
functioning properly, the brake may need to be replaced. Follow
c. Clean the shaft thread from the old thread-lock. these instructions.
d. sing the first adjustable spanner, adjust the air gap
U 1. Turn power off to crane and lock out.
(maintain locked the rotor shaft):
CW rotation = air gap (DECREASE) 2. nplug motor leads, open motor conduit box and disconnect
U
CCW rotation = air gap (INCREASE) brake leads from rectifier.
e. Check using the feeler gauge in different positions. 3. Remove brake cover.
f. ut a drop of LOCTITE 270 thread-lock on the shaft thread
P 4. Remove retaining ring and fan (if applicable).
and tighten the second nut without touching the first nut.
g. o not move/rotate the first adjustable spanner (first nut)
D 5. emove three (3) mounting bolts holding brake magnet body
R
to the brake disk lining, otherwise the air gap changes. in place. Pull brake leads from motor, remove magnet, brake
Tighten the second nut. coil and rotor.
h. Check the air gap again to confirm the right adjustment. 6. e-assemble in reverse order, and tighten mounting bolts
R
If adjustments are needed, lightly unscrew the second to specified torque.
nut and follow points d – e. Then, finish by following
points g – h. 7. Turn power back on to crane and test brakes for proper
operation.
8. osition the brake cover using a bit of grease and tighten the
P
four (4) M4 screws.
CONDITION
*Recommended
COMPONENT, UNIT OR PART (Check column best indicating condition when part
Inspection CORRECTIVE ACTION NOTES
and location or unit is inspected. Use note column to the right if
Interval
condition is not listed below.)
(Indicate corrective action taken during inspection and note
LUBRICATION REQ.
(Loose Parts or Wires)
REPAIR REQUIRED
REPLACEMENT
(Worn or Damaged)
date. For corrective action to be done after inspection, a
Rust or Corrosion)
CLEANING OR
ADJUSTMENT
LOCATION
REQUIRED
REQUIRED
REQUIRED
MONTHLY
PAINTING
designated person must determine that the existing deficiency
ANNUAL
GOOD
COMPONENT, UNIT does not constitute a safety hazard before allowing unit to
OR PART operate. When corrective action is completed, describe and
note date in this column.)
DATE
Motor
Gears & Bearings
BRIDGE
Wheels
Trucks
Girders & Connections
Footwalk & Handrail
Motor
Motor Brake
Mechanical Load Brake
Overload Clutch
Couplings
Gears, Shafts & Bearings
HOIST
Upper Block
Lower Block
Hook & Throat Opening X Record Hook Throat Opening
Hoist Rope
Rope Drum
Guards
Limit Switch
Bridge Panel
PUSH BUTTON
PANELS AND
CONTROL
Trolley Panel
Hoist Panel
Push Button
Wiring
Motor
Brake (When so Equip.)
Couplings
Gears, Shafts & Bearings
TROLLEY
Frame
Wheels
Bumpers
Guards
Conductors
Collectors
Monorail Joints
RUNWAYS
Monorail
Main Conductors
Main Collectors
General Condition
Load Attach. Chains
MISC.
NOTES
115 mm Truck 160 mm Truck 200 mm Truck 260 mm Truck 305 mm Truck
Ref. Part Quantity Part Quantity Part Quantity Part Quantity Part Quantity
No. Description No. S.G. D.G. No. S.G. D.G. No. S.G. D.G. No. S.G. D.G. No. S.G. D.G.
Driver Wheel (65 mm tread) 23487501 1 1 23487601 1 1 23487701 1 1 23487801 1 1 - - -
1
Driver Wheel (88 mm tread) - - - 23487603 1 1 23487703 1 1 23487803 1 1 45483903 1 1
Trailer Wheel (65 mm tread) 23487502 1 1 23487602 1 1 23487702 1 1 23487802 1 1 - - -
2
Trailer Wheel (88 mm tread) - - - 23487604 1 1 23487704 1 1 23487804 1 1 45483904 1 1
3 Bearing Cage, Open (Driver) 23487901 1 1 23488001 1 1 23488101 1 1 23488201 1 1 45483801 1 1
4 Bearing Cage, Closed (Trailer) 23487902 3 3 23488002 3 3 23488102 3 3 23488202 3 3 45483802 3 3
5 SHCS 11802705 12 12 11802705 12 12 11802728 12 12 11802718 12 12 11802718 12 12
6 Hi-Collar Lock Washer 11803202 12 12 11803202 12 12 11803202 12 12 11803203 12 12 11803203 12 12
7 Bearing 10378011 4 4 10378016 4 4 10380106 4 4 10380106 4 4 10380108 4 4
8 Grease Fitting - - - - - - NO6099 5 5 NO6099 5 5 NO6099 4 4
Rail Sweep (65 mm tread) 23488701 2 2 23488805 2 2 23488901 2 2 23489001 2 2
9
Rail Sweep (88 mm tread) - - - 23488806 2 2 23488902 2 2 23489002 2 2 45492701 2 2
10 M10-1.50 SHCS 11802729 4 4 11802729 4 4 11802729 4 4 11802729 8 8 11802729 8 8
11 M10 Flat Washer 11803101 4 4 11803101 4 4 11803101 4 4 11803101 8 8 11803101 8 8
12 M10 Hi-Collar Lock Washer 11803203 4 4 11803203 4 4 11803203 4 4 11803203 8 8 11803203 8 8
Bumper - R1 11680704 2 2 11680704 2 - - - - - - - - - -
Bumper - R2 11680701 2 2 11680701 2 2 11680701 2 - - - - - - -
13 Bumper - R3 - - - 11680703 2 2 11680703 2 2 11680703 2 2
Bumper - R4 - - - - - - 11680702 2 2 11680702 2 2 11680702 2 2
Bumper - R5 - - - - - - 11680705 - 2 11680705 - 2 11680705 2 2
Flat Washer - R1 11803102 2 2 11803102 2 - - - - - - - - - -
Flat Washer - R2 11803101 2 2 11803101 2 2 11803101 2 - - - - - - -
14 Flat Washer - R3 - - - 11803101 2 2 11803101 2 2 11803101 2 2
Flat Washer - R4 - - - - - - 11803103 2 2 11803103 2 2 11803103 2 2
Flat Washer - R5 - - - - - - 11803103 - 2 11803103 - 2 11803103 2 2
15 H.S. Hex Head Bolt Cl. 8.8 11802609 12 24 11802609 12 24 11802509 12 24 11802509 14 28 11802509 14 28
16 Hex Nut 12 24 10399109 12 24 10399110 12 24 10399110 14 28 10399110 14 28
17 Washer 11803501 12 24 11803501 12 24 11803502 12 24 11803502 14 28 11803502 14 28
18 Slotted Roll Pin 11807001 2 4 11807001 2 4 11807001 2 4 11807001 2 4 11807001 2 4
19 Hand Hole Cap Plug 10849811 4 8 10849811 4 8 10849811 4 8 10849811 4 8 10849811 2 4
Reference Quantity
Number Part Number Required Description
1 1 Fused Disconnect Switch
11692515 15 AMP
11695230 30 AMP
11695260 60 AMP
2 1 Mainline Contactor
33311033 30 AMP
33311036 60 AMP
Reference Quantity
Number Part Number Required Description
3 1 Fuse Base
11695303 30 AMP
11695313 60 AMP
3 Fuses - 600V
11695202 2 AMP
11695203 3 AMP
11695204 4 AMP
11695205 5 AMP
11695206 6 AMP
11695208 8 AMP
11695210 10 AMP
11695212 12 AMP
11695215 15 AMP
11695220 20 AMP
11695225 25 AMP
11695230 30 AMP
11695240 40 AMP
4 1 Variable Frequency Drive
45199723 2 HP, 230V
45199724 3 HP, 230V
45199725 5 HP, 230V
45199726 7.5 HP, 230V
45199727 10 HP, 230V
45199742 2 HP, 460V
45199743 3 HP, 460V
45199744 5 HP, 460V
45199745 7.5 HP, 460V
45199746 10 HP, 460V
45334652 2 HP, 575V
45334653 3 HP, 575V
45334654 5 HP, 575V
45334655 7.5 HP, 575V
45334656 10 HP, 575V
5 33310931 1 Brake Relay (For VFC Control)
33311996 Surge Surpressor
6 1 Fused Transformer
22946771 75VA, 230/460V
22946772 75VA, 208/277V
22946773 75VA, 575V
22946711 100VA, 230/460V
22946712 100VA, 208/277V
22946713 100VA, 575V
3 Fuses - 600V
11696305 .6 AMP
11696307 .8 AMP
11696308 1 AMP
11696310 1.4 AMP
11696312 2 AMP
7 11741010 3 Terminal Boards
8 11785601 1 Ground Lug
Notes
THE WARRANTY STATED BELOW IS GIVEN IN PLACE OF ALL OTHER GOODS THAT SELLER DETERMINES TO HAVE BEEN DEFECTIVE OR, IF SELLER
WARRANTIES, EXPRESS OR IMPLIED, OF MERCHANTABILITY, FITNESS FOR DETERMINES THAT SUCH REPAIR OR REPLACEMENT IS NOT FEASIBLE, TO
A PARTICULAR PURPOSE, OR OTHERWISE, NO PROMISE OR AFFIRMATION A REFUND OF THE PURCHASE PRICE UPON RETURN OF THE GOODS TO
OF FACT MADE BY ANY AGENT OR REPRESENTATIVE OF SELLER SHALL SELLER. NO CLAIM AGAINST SELLER FOR ANY BREACH OF
CONSTITUTE AWARRANTY BY SELLER OR GIVE RISE TO ANY LIABILITY
(i) SUCH WARRANTY WITH RESPECT TO THE ELECTRICAL COMPONENTS OF
OR OBLIGATION.
ANY GOOD SHALL BE VALID OR ENFORCEABLE UNLESS BUYER’S WRITTEN
Seller warrants that on the date of delivery to carrier the goods are free from NOTICE THEREOF IS RECEIVED BY SELLER WITHIN ONE (1) YEAR FROM THE
defects in workmanship and materials. DATE OF SELLER’S DELIVERY TO THE CARRIER AND (ii) SUCH WARRANTY
WITH RESPECT TO THE MECHANICAL COMPONENTS OF ANY GOOD SHALL
SELLER’S SOLE OBLIGATION IN THE EVENT OF BREACH OF WARRANTY
BE VALID OR ENFORCEABLE UNLESS BUYER’S WRITTEN NOTICE THEREOF
OR CONTRACT OR FOR NEGLIGENCE OR OTHERWISE WITH RESPECT TO
IS RECEIVED BY SELLER WITHIN ONE (1) YEAR FROM THE DATE THE DATE
GOODS SOLD SHALL BE EXCLUSIVELY LIMITED TO REPAIR OR REPLACEMENT,
ANY ALLEGED CLAIM ACCRUES. EXCEPT FOR THE WARRANTY SET FORTH
F.O.B. SELLER’S POINT OF SHIPMENT, OF ANY PARTS WHICH SELLER
ABOVE, SELLER MAKES NO OTHER WARRANTIES WITH RESPECT TO THE
DETERMINES TO HAVE BEEN DEFECTIVE or if Seller determines that such
GOODS, WHETHER EXPRESSED OR IMPLIED, INCLUDING ANY WARRANTIES
repair or replacement is not feasible, to a refund of the purchase price upon
OF MERCHANTABILITY, FITNESS FOR A PARTICULAR PURPOSE, QUALITY
return of the goods to Seller.
AND/OR THOSE ARISING BY STATUTE OR OTHERWISE BY LAW OR FROM
Any action against Seller for breach of warranty, negligence or otherwise, must ANY COURSE OF DEALING OR USE OF TRADE, ALL OF WHICH ARE HEREBY
be commenced within one year after such cause of action occurs. EXPRESSLY DISCLAIMED.
NO CLAIM AGAINST SELLER FOR ANY DEFECT IN THE GOODS SHALL BE C. IN NO EVENT SHALL SELLER BE LIABLE TO BUYER OR ANY THIRD PARTY
VALID OR ENFORCEABLE UNLESS BUYER’S WRITTEN NOTICE THEREOF IS WITH RESPECT TO ANY GOOD, WHETHER IN CONTRACT, TORT OR OTHER
RECEIVED BY SELLER WITHIN ONE YEAR FROM THE DATE OF SHIPMENT. THEORY OF LAW, FOR LOSS OF PROFITS OR LOSS OF USE, OR FOR ANY
Seller shall not be liable for any damage, injury or loss arising out of the use of INCIDENTAL, CONSEQUENTIAL, SPECIAL, DIRECT OR INDIRECT DAMAGES,
the goods if, prior to such damage, injury or loss, such goods are (1) damaged HOWSOEVER CAUSED. SELLER’S MAXIMUM LIABILITY TO BUYER WITH
or misused following Seller’s delivery to carrier; (2) not maintained, inspected, RESPECT TO THE GOODS SHALL IN NO EVENT EXCEED THE PRICE PAID BY
or used in compliance with applicable law and Seller’s written instructions and BUYER FOR THE GOODS THAT ARE THE SUBJECT OF THE APPLICABLE CLAIM.
recommendations; or (3) installed, repaired, altered or modified without compliance
D. Seller shall not be liable for any damage, injury or loss arising out of the use of
with such law, instructions or recommendations.
the Goods if, prior to such damage, injury or loss, such Goods are: (1) damaged
UNDER NO CIRCUMSTANCES SHALL SELLER BE LIABLE FOR INCIDENTAL OR or misused following Seller’s delivery to the carrier; (2) not maintained, inspected,
CONSEQUENTIAL DAMAGES AS THOSE TERMS ARE DEFINED IN SECTION or used in compliance with applicable law and Seller’s written instructions and
2-715 OF THE UNIFORM COMMERCIAL CODE. recommendations; or (3) installed, repaired, altered or modified without compliance
INDEMNIFICATION AND SAFE OPERATION with such laws, instructions or recommendations.
Buyer shall comply with and require its employees to comply with directions set E. This warranty is limited and provided only to the original end user. Each Good
forth in instructions and manuals furnished by Seller and shall use and require must be registered within sixty (60) days of receipt of each product to establish
its employees to follow such instructions and manuals and to use reasonable eligibility. Please register at https://www.columbusmckinnon.com/en-us/warranty-
care in the use and maintenance of the goods. Buyer shall not remove or permit registration/ or submit registration card via US mail.
anyone to remove any warning or instruction signs on the goods. In the event F. Any action against Seller for breach of warranty, negligence or otherwise must
of personal injury or damage to property or business arising from the use of the be commenced by Buyer within one (1) year after: (a) the date any alleged claim
goods, Buyer shall within 48 hours thereafter give Seller written notice of such accrues; or (b) the date of delivery of the Goods to Buyer, whichever is earlier.
injury or damage. Buyer shall cooperate with Seller in investigating any such
injury or damage and in the defense of any claims arising therefrom.
If Buyer fails to comply with this section or if any injury or damage is caused,
in whole or in part, by Buyer’s failure to comply with applicable federal or state
safety requirements, Buyer shall indemnify and hold Seller harmless against any
WARNING
claims, loss or expense for injury or damage arising from the use of the goods.
Alterations or modifications of equipment and use of
CMCO Warranty (HOISTS) non-factory repair parts can lead to dangerous operation
A. Columbus McKinnon Corporation (“Seller”) warrants to the original end user and injury.
(“Buyer”) that, for a period of one (1) year from the date of Seller’s delivery of
the goods (collectively, the “Goods”) to the carrier, the Goods will be free from
defects in workmanship and materials. TO AVOID INJURY:
B. IN THE EVENT OF ANY BREACH OF SUCH WARRANTY, SELLER’S SOLE • Do not alter or modify equipment.
OBLIGATION SHALL BE EXCLUSIVELY LIMITED TO, AT THE OPTION OF SELLER, • Do use only factory replacement parts.
REPAIR OR REPLACEMENT, F.O.B. SELLER’S POINT OF SHIPMENT, OF ANY
© 2022 Columbus McKinnon Corporation. All Rights Reserved. P/N: 11532619 REV. AD August 2022