Piling Work Order Terms and Condition
Piling Work Order Terms and Condition
Scope of work:-
1. The work should be executed as per specification mentioned in Tender
document.
2. The Work includes-
a. Drilling/boring through any type of soil/Soft rock/ hard rock up to depth as
directed for 500/600/700/800/1000 mm outer dia bored cast in-in-situ
vertical piles duly stabilizing the sides by drilling fluids (Reverse or DMC
method) or by driving 6mm thick casing pipe upto loose strata or refusal
level or by any other approved method and disposal of drilled/bored
material to a distance exc. 50m and not exc. 100m all as specified and
shown on drawings.
b. RCC M-35 design mix for cast-in-situ piles using tremie method including
chipping of piles from cut off level to a minimum height of 50 cm
including disposal of chipped off concrete to a distance exc. 50m. and
n.exc. 100m complete all as specified and shown on drawings.
c. High strength deformed steel TMT steel bars 10mm dia and over, cut to
length, bent to shape required, including cracking bending spirally for
hooping for columns, hooking ends and binding with and including mild
steel wire (annealed) not less than 0.9mm dia complete all as specified and
directed.
Particular Specifications
CAST-IN-SITU BORED PILING WORK
1. The contractor shall visit the site to ascertain water table
2. The piles are required to be provided as shown on drawings.
3. The steel reinforcement as shown on drawings shall be provided throughout
the length of the pile.
4. Tack welding of reinforcement shall be done in accordance with the relevant
IS to facilitate lowering of the reinforcement cage in the drilled hole of the pile
and no extra payment shall be allowed to the contractor on this account.
5. The contractor shall execute the work in accordance with the sound
engineering practice. He shall make good the damages due to the bad
materials/workmanship at his own expenses.
CAST-IN-SITU BORED PILES CONSTRUCTION
1. Boring may be done by rotary or percussion equipment, grabbing equipment
and by reverse or direct mud circulation method or by any other approved
method. Boring of cast-in-situ piles shall be carried out in accordance with
clause 3.30.1 to 3.30.7 of SSR Part I 2009 and as per provisions of IS-2911,
1985.
2. Stabilization of the sides of the bore holes shall be done by the use of drilling
fluids or casing. The suction or the flow of material from the ground adjacent
to the hole being bored shall be restricted to barest minimum while
progressing the boring.
Payment Terms:
The bill will be submitted by the subcontractor to the Project Manager. He will certify
the same as per actual measurement. Following deductions shall be effected in the
running bills as, when and if applicable –
1. 10% of cost of work done shall be retained as Retention Amount from each
running bill
2. 5% retention will release after completion of work and submission of all
documents as per clause no 8 of Special condition of Contract.
3. Remaining 5% retention will be paid one year after completion of defects
liability period.
4. For unsatisfactory workmanship, 50% of cost of that work shall be retained till
the work is rectified to the satisfaction of Project Manager.
5. Payment for the amount due as per certified running bill will be made within
15 days of certification of the bill.
6. Agreed rate shall remain valid till the completion of the job in all respects and
shall be free from variation due to increase or decrease in labour charges, fuel
costs or any other reasons whatsoever, other than statutory variation.
7. Any damage or loss of any type to the property, other materials and works
due to poor and faulty workmanship will be debited to you.
8. Claims for interest on delayed payments will not be entertained by the VIPL.
9. In case of termination of contract or appointment of another subcontractor for
same scope of work, the billing will be done on pro-rata basis.
Schedule of Execution:
Termination of Contract:
1. We reserve our rights to terminate any specific labour of subcontractor
working on site at any time without intimation to him or subcontractor.
2. We reserve our rights to terminate the contract at any time any stage without
any intimation to the subcontractor.