100% found this document useful (2 votes)
605 views118 pages

RR&R 21cv736 Notes

Uploaded by

shahxubairyousuf
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
605 views118 pages

RR&R 21cv736 Notes

Uploaded by

shahxubairyousuf
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 118

SHRIDEVI INSTITUTE

OF ENGINEERING
& TECHNOLOGY
TUMKUR-572106

DEPARTMENT OF CIVIL ENGINEERING

SEVENGTH SEMESTER

Rehabilitation and Retrofitting


CODE –21CV736

Dept. of Civil Engg, SIET


Course Title: R e p a i r , R e t r o f i t t i n g & Rehabilitation
of Structures
As per Choice Based Credit System (CBCS) scheme]
SEMESTER:VII
Subject Code 18CV824 IA Marks 50
Number of Lecture Hours/Week 03 Exam Marks 50
Total Number of Lecture Hours 54 Exam Hours 03
CREDITS –03 Total Marks- 100
Course Objectives: This course will enable students to;
1. Investigate the cause of deterioration of concrete structures.
2. Strategise different repair and rehabilitation of structures.
3. Evaluate the performance of the materials for repair
Revised
Modules Teaching Bloom’s
Hours Taxonomy
(RBT) Level
Module -1
General: Introduction and Definition for Repair, Retrofitting, Strengthening and
rehabilitation. Physical and Chemical Causes of deterioration of concrete
structures, Evaluation of structural damages to the concrete structural elements 11 hours L1,L2
due to earthquake.
Module -2
Damage Assessment: Purpose of assessment, Rapid assessment, Investigation of
damage, Evaluation of surface and structural cracks, Damage assessment 11 Hours L1,L2
procedure, destructive, non-destructive and semi destructive testing systems

Module -3
Influence on Serviceability and Durability: Effects due to climate, temperature,
chemicals, wear and erosion, Design and construction errors, corrosion
mechanism, Effects of cover thickness and cracking, methods of corrosion 11 Hours L1,L2,L3
protection, corrosion inhibitors, corrosion resistant steels, coatings, and cathodic
protection.
Module -4
Maintenance and Retrofitting Techniques: Definitions: Maintenance, Facts of
Maintenance and importance of Maintenance Need for retrofitting, retrofitting of
structural members i.e., column and beams by Jacketing technique, Externally
11 Hours L1,L2,L3
bonding(ERB) technique, near surface mounted (NSM) technique, External post-
tensioning, Section enlargement and guidelines for seismic rehabilitation of
existing building
Module -5
Materials for Repair and Retrofitting: Artificial fibre reinforced polymer like
CFRP, GFRP, AFRP and natural fiber like Sisal and Jute. Adhesive like, Epoxy
Resin, Special concretes and mortars, concrete chemicals, special elements for
accelerated strength gain, Techniques for Repair: Rust eliminators and polymers 10 Hours L1,L2,L3
coating for rebar during repair foamed concrete, mortar and dry pack, vacuum
concrete, Gunite and Shot Crete Epoxy injection, Mortar repair for cracks,
shoring and underpinning
Course outcomes: After studying this course, students will be able to:
1. Understand the cause of deterioration of concrete structures.
2. Able to assess the damage for different type of structures
3. Summarize the principles of repair and rehabilitation of structures
4. Recognize ideal material for different repair and retrofitting technique
Program Objectives:
Engineering knowledge
Problem analysis
Interpretation of data
Question paper pattern:
The question paper will have 5 modules comprising of ten questions. Each full question carrying 16 marks
There will be two full questions (with a maximum of three subdivisions, if necessary) from each module.
Each full question shall cover the topics as a module
The students shall answer five full questions, selecting one full question from each module. If more than one
question is answered in modules, best answer will be considered for the award of marks limiting one full
question answer in each module.
SIET, Department of Civil Engineering

MODULE-1
Introduction
1.1 General
Concrete is the most extensively used construction material in the construction of various structures
such as bridges, buildings and precast products pipes, poles, sleepers etc.From the past and even at
the present times, too much emphasis is on concrete compressive strength rather than environmental
factors, which is known as durability. This is one of the main reasons for serious deterioration of
concrete structures that is prevalent today. Maintenance, repair and strengthening of constructed
facilities/infrastructures is presently the most significant challenge facing the concrete industry

Repair, Retrofitting and Rehabilitation of Structures (21CV736) Module-1 Introduction 1


SIET, Department of Civil Engineering

Fig 1.1: Deterioration of Concrete Structures

Repair, Retrofitting and Rehabilitation of Structures (21CV736) Module-1 Introduction 2


SIET, Department of Civil Engineering

1.2 Durability of concrete


A concrete is said to be durable if it withstands the conditions for which it has been designed, without
deterioration, over a period of years. Durability of concrete is used to characterize in broad terms the
resistance of concrete to physical or chemical attacks due to the external causes or by the internal
causes.
External causes – weathering, temperature, abrasion, electrolytic action and attack by natural or
industrial liquids and gases.
Internal causes – Alkali aggregate reaction, volume change due to thermal properties of aggregate,
cement paste and permeability of concrete

Fig 1.2: Durability of concrete


The following factors influence the durability of the concrete

1. W/C ratio
2. Curing period
3. Cement content and its properties.
4. Aggregates
5. Mix design
6. Workability
7. Admixtures
8. Thermal incompatibility of concrete constituents.
9. Transition zone
10. Environmental Interaction

Repair, Retrofitting and Rehabilitation of Structures (21CV736) Module-1 Introduction 3


SIET, Department of Civil Engineering

1.3 Definitions

1 Defects: These are the flaws that are introduced through poor design, poor workmanship
before a structure begins its design life or through inadequate operation and maintenance during
its service life

2 Repair: Process of reconstruction and renewal of the existing buildings, either in whole or in
part

OR

To bring back the position of the structure to its previous condition so it gives performance same as
previously. It doesn’t cover the strength aspect of the structures.

Some examples of repair…….

 Decoration of structure, Painting, White Washing.

 Checking the wiring of building.

 Replastering of any wall if required

 Repairing of damaged flooring

 Repair of door and window

 Checking or repairing of pipe line connections, gas line connections and plumbing serveries.

 Relaying disturbed roof tiles.

3 Renovation: Process of substantial repair or alteration that extends a building’s useful life.

4 Remodeling: Essentially same as renovation – applied to residential structures.

5 Rehabilitation: An upgrade required to meet the present needs – being sensitive to building
features and a sympathetic matching of the original construction or the process of repairing or
modifying a structure to a desired useful condition.

OR

Rehabilitation of a building means returning a building or a structure to a useful state by means


of repair, modification, or alteration. It is related to the strength aspect of structures. To Bring
back the position and condition of the structure by considering the strength aspect.

Some of the examples of Rehabilitation…..

Repair, Retrofitting and Rehabilitation of Structures (21CV736) Module-1 Introduction 4


SIET, Department of Civil Engineering
 To fill the wide cracks using some suitable material

 Injecting epoxy like material in to cracks in walls,columns,beams, etc.

 Removal of damaged portion of masonry and reconstructing it using rich mortar mix.

 Addition of reinforcing mesh on both sides of the wall.

6 Restoration: The process of re-establishing the materials, form and appearance of a


structure.

7 Strengthening: The process of increasing the load-resistance capacity of a structure or


portion.

8 Retrofitting: The process of strengthening of structure along with the structural system, if
required so as to comply all relevant codal provisions in force during that period.

9 Demolition: The process of pulling down of the structure not deemed to be fit for service.

Need for Repair and Rehabilitation of Structures:

The extent of deterioration to concrete structures globally is occurring at an alarming rate. It is


now being confirmed that even if the structural design abides by all the specific building code
requirements like the concrete quality, cover etc., there is still an acceptable high risk of
deterioration of concrete and corrosion of reinforcement. Steel corrosion is found to be most
severe cause of deterioration of reinforced concrete that can create cracks, spalls the concrete
cover, reduce the effective c/s area of the reinforcement and lead to collapse.

Repair, Retrofitting and Rehabilitation of Structures (21CV736) Module-1 Introduction 5


SIET, Department of Civil Engineering

Causes for deterioration of concrete structures

Repair, Retrofitting and Rehabilitation of Structures (21CV736) Module-1 Introduction 6


SIET, Department of Civil Engineering

PHYSICAL CAUSES
1. SHRINKAGE
2. FREEZING AND THAWING
3. WEATHERING
4. ABRASION, EROSION AND CAVITATION
5. TEMPERATURE
6. FIRE
7. THERMAL MOVEMENT
8. CONSTRUCTION ERRORS
9. DESIGN ERRORS

CHEMICAL CAUSES
1. Acid Attack
2. Aggressive water Attack
Alkali carbonate rock reaction
3. Alkali silica reaction
4. Alkali Aggregate reaction
5. Sulphate Attack
MECHANICAL CAUSES
1. SETTLEMENT AND MOVEMENT
2. ACCIDENTAL LOADINGS

Repair, Retrofitting and Rehabilitation of Structures (21CV736)Module 1- Introduction 7


SIET, Department of Civil Engineering

PHYSICAL CAUSES

1. SHRINKAGE

Shrinkage is defined as the volume changes in concrete due to loss of moisture from concrete due to
evaporation or by hydration of cement.
In practice, the shrinkage is measured as linear strain in terms of mm/mm, expressed in 10-6.
Shrinkage can be classified in to following categories
1. Plastic shrinkage
2. Drying shrinkage
3. Autogenous shrinkage
4. Carbonation shrinkage
1. Plastic shrinkage

The concrete will exhibit bleeding to some degree between placing and setting time is called plastic
shrinkage. Bleeding is the appearance of moisture on the surface of concrete; caused by the settling of
the heavier components of the mixture. Usually, the bleed water evaporates from the concrete
surface.

Fig 1.3: Plastic Shrinkage cracks

Repair, Retrofitting and Rehabilitation of Structures (21CV736)Module 1- Introduction 8


SIET, Department of Civil Engineering

A typical plastic shrinkage cracks occurred due to

 Rapid evaporation of water from the surface of concrete.


 Occurs within few hours after placing concrete while still it is in plastic and before it has attained
sufficient strength.

 These cracks occur almost entirely on horizontal surfaces exposed to atmosphere. These cracks
are parallel to one another are spaced 0.3m to 0.1m apart and width varying from 0.1mm to
3mm.

 The magnitude depends upon ambient temperature, relative humidity and wind velocity.
 It also depends up on the rate of evaporation of water from the surface of concrete (1kg/m2/hr)
Elimination of plastic shrinkage cracks

Plastic shrinkage cracks can be eliminated by following measures

 Reduce the time between placing and finishing. If there is delay cover the concrete with polythene
sheets.

 Minimize evaporation by covering concrete with fog spray and curing compounds.
 Erect temporary roof to protect concrete from hot sun.
Plastic settlement shrinkage crack

These cracks can occur concrete starts setting. This happens when
1. The concrete cover over the reinforcement is too small.
2. The mix contains too many fines.
3. The mix is too slow in releasing its bleed water.
4. This form of cracking is the easiest to identify as it reflects the location of reinforcement

Fig 1.4: Plastic settlement cracks

Repair, Retrofitting and Rehabilitation of Structures (21CV736)Module 1- Introduction 9


SEIT, Department of Civil Engineering

Fig 1.5: Method of prevention of plastic shrinkage cracks

2. Drying shrinkage
The loss of moisture after setting is called drying shrinkage. It is the long term change in volume of
concrete.
If this shrinkage could take place without any restraint, there would be no damage to the concrete.
The combination of shrinkage and restraints causes tensile stresses that can ultimately lead to
cracking.
A drying shrinkage cracks occurred due to

 These cracks is caused by physical loss (evaporation) and chemical loss(hydration) of water
during the hardening process and exposure to unsaturated air.

 Reduction in volume of concrete can cause cracks if it is restrained and its tensile strength
exceeded.

 These cracks appears at about 7-10 days after concreting and about 80% of drying shrinkage
take place in about a year.

 It is influenced by cement content, water content, aggregates, curing, humidity and temperature

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 10


SEIT, Department of Civil Engineering
 It is confined to non-structural members, floor toppings and parapet walls
Controlling drying shrinkage cracks

 Use of minimum water content.


 Use of highest possible aggregate content.
 Providing adequate and early curing.
 Providing sufficient close spaced reinforcement.
 It is confined to non-structural members, floor toppings and parapet walls

Fig 1.6: Drying shrinkage cracks

3. Autogenous shrinkage

Autogeneous shrinkage cracks occurred due to

 If no movement of water to or from set paste of concrete is allowed, then the shrinkage developed
is known as autogeneous shrinkage.

 This shrinkage is caused by the loss of water consumed or used in the hydration of cement.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 11


SEIT, Department of Civil Engineering
 The magnitude of this shrinkage is very small and is not much of significance.

Controlling Autogenous shrinkage cracks

 Consider a higher content of supplementary cementitious material like Fly ash and Ground
granulated blast furnace Slag (GGBS) in the concrete mix.

 Keep the surface of the concrete continuously wet; conventional curing by sealing the surface to
prevent evaporation is not enough and water curing is essential.

 Consider addition of shrinkage-reducing admixtures more commonly used to control drying


shrinkage,

 Consider addition of saturated lightweight fine aggregates

4. Carbonation shrinkage

Carbonation is the reaction of CO2, which is present in the atmosphere with hydrated cement. The
CO2 in presence of moisture forms carbonic acid that reacts with calcium hydroxide - Ca(OH)2, a
product of hydration to form Calcium Carbonate (CaCO3).

 Carbonation shrinkage is probably caused by the dissolution of crystals of calcium hydroxide and
deposition of calcium carbonate in its place.

 The carbonation proceeds from the surface of concrete inwards, but does so extremely slowly.

 The actual rate of carbonation depends on the permeability of the concrete, its moisture content
and on the CO2 content and relative humidity of the ambient medium.

 Concrete made with high water-cement ratio and inadequately cured will be more prone to
carbonation i.e. there will be a greater depth of carbonation.

Fig 1.7: Carbonation shrinkage

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 12


SEIT, Department of Civil Engineering

Fig 1.8 : Graphical representation of formation of various shrinkage

2. FREEZING AND THAWING

Freeze-thaw disintegration or deterioration takes place when the following conditions are present.
(a) Freezing and thawing temperature cycles within the concrete.

(b) Porous concrete that absorbs water (water-filled pores and capillaries)

Mechanism

 As the temp. of a critically saturated concrete is lowered during cold weather, the freezable water
held in the capillary pores of the cement paste and aggregates expands upon freezing. If
subsequent thawing is followed by refreezing the concrete is further expanded, so that repeated
cycles of freezing and thawing have a cumulative effect.

 Concrete hydraulic structures are vulnerable to freezing and thawing. Exposure in such areas as
the top walls, piers, parapets and slabs enhances the vulnerability of concrete to the harmful
effects of repeated cycles of freezing and thawing.

 The use of de-icing chemicals on concrete surfaces may also accelerate damage caused by
freezing and thawing and may lead to pitting and scaling.

 It involves the development of osmotic and hydraulic pressure during freezing, principally in the
paste, similar to ordinary frost action.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 13


 Freeze and thaw deterioration generally occurs on horizontal surfaces that are exposed to
water, or on vertical surfaces that are at the water line in submerged structures.

 Freezing water contained in the pore structure expands as it is converted into ice.
Preventive Measures

1. Use of lowest practical water-cement ratio and water content.


2. Use of air entrainment.
3. Use of durable aggregate.
4. Adequate curing of concrete prior to exposure to freezing conditions.
5. Designing the structure to minimize the exposure to moisture.
3. WEATHERING

 It is defined as change in colour, texture, strength, chemical composition, or other properties


of a natural or artificial material due to the action of weather.

1. The damage from freezing and thawing is the most common weather related physical
deterioration.

2. Alternate wetting and drying, and heating and cooling may cause cracking in concrete due to
weathering.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module- 1 Introduction 14


SIET, Department of Civil Engineering
3. If the volume changes due to these processes are excessive, cracks may develop.

4. The damage due to these factors may appear in the form of general flaking and spalling of
concrete from the surface of concrete.

5. Concrete generally loses strength with increase in temperature about 300 C, damage being
greater with aggregate having higher coefficient of thermal expansions.

Fig 1.9: Weathering

4. CRAZING

 Crazing is the development of fine random cracks on the surface of the concrete caused by
shrinkage of the surface layer.

 These cracks do not affect the structural integrity of concrete but may lead to subsequent
deterioration of the concrete.

 The cracks are shaped like irregular hexagon and are typically not more than 50 to 100 mm
across. They are rarely more than few millimeters deep and are more noticeable on steel troweled
surfaces.

 They generally occur in the over floated or over troweled surface layers of concrete slabs and in
the formed surfaces of concrete.

 craze cracks develop at an early age and are apparent the day after placement. The crazing is
more prominently seen when the surface is wet.

The generally observed reasons for appearance of Crazing cracks are

• Poor or inadequate curing.

• Too wet a mix, excessive floating, the use of a jitterbug or any other procedure which depresses the
coarse aggregate and produces an excessive concentration of cement paste and fines at the surface.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 15


SIET, Department of Civil Engineering
• Sprinkling cement on the surface to dry up bleed water. This concentrates fines on the surface.

• Occasionally carbonation of the surface can cause crazing.

• Finishing while there is bleed water present on the surface or the use of steel trowel at a time when
the smooth surface brings up too much water and cement fines. The use of a darby or bull float while
bleed water is present will produce a high water-cement ratio at the surface, which makes the slab
more susceptible to crazing.

Preventive Measures

 Damping the sub grade before placing concrete.


 Avoiding over-finishing of the surface.
 Delaying trowelling until the surface moisture has disappeared.
 Avoiding sprinkling of dry cement or water on the surface during finishing operation.
 Curing as soon as possible.
 Avoiding high temperature differentials between the concrete and curing water.

Fig 1.10: Crazing Cracks

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 16


SIET, Department of Civil Engineering
5. HONEYCOMBING ON CONCRETE

 Honeycomb consists of exposed pockets of coarse aggregates not covered by a surface layer of
mortar.

 It may also be defined as the hollow spaces and cavities left in the concrete mass on surface or
inside the concrete which is caused by mortar not filling the space between coarse aggregates

 This may be caused by inadequate compaction.

 Presence of excess water in concrete or by leaky forms, which allow the water to escape.

Fig 1.11: Honeycombing


Types of Honeycomb

 Small size honeycomb – Depth is less than 25mm


 Moderate size honeycomb- Deeper than 25mm but steel bars have not exposed.
 Larger size honeycomb- Deeper than 25mm and bars have come out
Causes of Honeycomb

1. Poor workability
2. Poor grading of aggregate
3. Grout leak.
4. Movement of formwork.
5. Improper compaction.
6. Improper cover and placement of rebar

Preventive measures

 To follow good construction practice.


 To use workable concrete.
 To provide good forms.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 17


SIET, Department of Civil Engineering
 To give proper vibration.
 To be planned sequence of placing

Repair of honeycombs

 Hack and remove the loose particles in order to appear sound surface.
 Surface is cleaned by water jet to obtain dust free surface
 Construction grout is applied.
 Texture and colour should be matched for aesthetic finish
 Curing is done.

6. POPOUTS ON CONCRETE

 A popout is a small, cone shaped cavity or hole in a horizontal concrete surface left after a near
surface aggregate particle has expanded and fractured.

 The cavity may range from 6mm to few mm diameter

Causes

 They are caused by freezing of water in the aggregate particles that have internal pore structure
which causes to expand.

 pop outs do not appear during construction but they start to appear during the first winter and may
continue to form for several years

Fig 1.12: Popouts

FOLLOW THESE RULES FOR POPOUTS:

1. Use durable aggregate from a proven source. A limit of 1% deleterious material by mass of dry
aggregate has been found to minimize difficulties with popouts.

2. Use concrete with the lowest water content and slump possible for the application.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 18


SIET, Department of Civil Engineering
3. Use air entrained concrete.

4. Do not finish concrete when bleed water is on the surface.

5. Avoid over finishing or hardsteel troweling where not needed, such as most exterior and garage
slabs.

6. Reduce concrete temperature to 10C to 21C.

7. Impervious floor coverings or membranes should be avoided for slabs on grade as they can
aggravate popouts.

8. Provide proper drainage. Slope the slab surface to provide good drainage. Basements slabs
should be provided with a free draining granular base in areas with high groundwater
conditions.

REPAIR OF POPOUTS

 Surfaces with pop outs can be repaired.

 A small patch can be made by drilling out the spalled particle and filling the void with a damp
pack mortar, or other appropriate patching material.

 If pop outs are too numerous to patch individually, a thin bonded overlay or surfaces grinding
may be used to restore serviceability.

7. CREEP ON CONCRETE

Concrete undergoes instantaneous elastic deformation when subjected to sustained loads with
respect to time known as creep

Factors affecting

1. W/C ratio.
2. Type of aggregate.
3. Admixture
4. Age of concrete
5. Type of cement and cement content
6. Mix proportions.
7. Mixing Time.
8. Humidity.
9. Temperature.
10. Size of the specimen.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 19


SIET, Department of Civil Engineering
Creep Coefficient

The ratio of the ultimate creep strain to the elastic strain at the age of loading is termed as creep
coefficient.

The assumed data of creep coefficient are given below

Age of Loading Creep coefficient

7 Days 2.2

28 Days 1.6

1 year 1.1

Fig 1.13: Deformation of hardened concrete

8. THERMAL MOVEMENT IN CONCRETE

 Thermal movement is defined as concrete expands or contracts when change in temperature.


Causes

 Thermal movement due to considerable amount of heat due to heat of hydration, atmospheric
temperature and external fire.

 Due to thermal movement, changes in shape and volume of concrete causes cracks on the
concrete structure.

 The extent of temperature rise depends on the properties of cement used and the shape and size
of the component.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 20


SIET, Department of Civil Engineering
 The heat of hydration may not be significant but in mass concrete works it is an important factor
to be considered.

 In load bearing structures, horizontal cracks may appear in the cross walls as shown in figure.

Fig 1.14: Thermal movement in load bearing structures


 In frame structures, roof slab along with beams and columns moves jointly causes diagonal cracks
in walls which are located parallel to movement and horizontal cracks below beams in walls
which are right angles to movement as shown in fig.

Fig 1.15: Thermal movement in framed structures

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 21


SIET, Department of Civil Engineering
 Horizontal cracks may also appear at the support of a brick parapet wall or brick-cum-iron
railing over RCC cantilever slabs as shown in fig. due to differential thermal movement.

Fig 1.16: Thermal movement in parapet wall

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 22


SIET, Department of Civil Engineering

PREVENTIVE MEASURES

 Use of pozzolana.
 Use of low heat cement.
 Pre-cooling of aggregates and mixing water.
 Post cooling of concrete by refrigerated water through pipes embedded in the body of concrete.
 Providing joints to relieve the restraints in the structure.
 Providing adequate reinforcement to distribute the stresses.
 Providing suitable cover.
9. FIRE ON CONCRETE

 Concrete is considered fireproof on account of its incombustibility and low thermal diffusivity.

 Concrete can also experience explosive spalling and deterioration during heating which need to
be understood and designed against either at the materials level and/or at the structural level.

 The extent of fire depends upon the intensity and duration of fire.

 The principal types of damages are

 Reduction in strength of concrete

 Cracking and spalling of concrete

 Deflection and deformation of members

 Discolouration

 other miscellaneous functional failures.

 Fire resistance of concrete is determined by 3 factors

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 23


SIET, Department of Civil Engineering
 The capacity of concrete itself to withstand heat.

 The conductivity of the concrete to heat.

 The coefficient thermal expansion of concrete.

 The effect of increase in temp. on the strength of concrete is not much up to a temp. of about
250o C but above 350o C, definite loss of strength takes place.

 In mortar or concrete, the aggregates undergo a progressive expansion on heating while the
hydrated products of the set cement, beyond the point of maximum expansion shrinks. These two
opposing actions progressively weaken and crack the concrete.

 The test results indicated that even the best fire resistant concrete found to fail if concrete is
exposed for a considerable period to a temp. exceeding 900 C, while reduction in strength occurs
at a temp of about 600C.

Fig 1.17: Fire damage on concrete structure

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 24


SIET, Department of Civil Engineering
CHEMICAL CAUSES

Acid Attack

 Concretes made of Portland cement (OPC) are highly alkaline with pH values normally above
12.5 and are not easily attacked by acidic solutions.

 As the pH of the solution decreases the equilibrium in the cement matrix is being disturbed, and
the hydrated cement compounds are essentially altered by hydrolytic decomposition which leads
to the severe degradation of the technical properties of the material.

 At pH values lower than 12.5 portlandite is the first constituent starting dissolution.

 If pH decreases to values lower than stability limits of cement hydrates, then the corresponding
hydrate loses calcium and decomposes to amorphous hydrogel.

 The final reaction products of acid attack are the corresponding calcium salts of the acid as well
as hydrogels of silicium, aluminum, and ferric oxides.

 The solubility of Al2O3 and Fe2O3 depends on the pH value of the acting solution, while SiO2
is insoluble in acidic solutions except in HF

1. SULPHURIC ACID ATTACK

 Sulphuric acid attack causes extensive formation of gypsum in the regions close to the surfaces,
and tends to cause disintegrating mechanical stresses which ultimately lead to spalling and
exposure of the fresh surface.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 25


SIET, Department of Civil Engineering
 Owing to the poor penetration of sulphuric acid, the chemical changes of the cement matrix are
restricted to the regions close to the surfaces

 The chemical reactions involved in sulphuric acid attack on cement based materials can be given
as follows:

Ca(OH)2 + H2SO4 CaSO4 .2H2O

3CaO.2SiO2 .3H2O + H2SO4 CaSO4 .2H2O + Si(OH)4

 Source water has high sulphur content, both as sulphate or sulphide, and form hydrogen
sulphide, H2S.

 The hydrogen sulphide gas comes out of the solution and forms sulphuric acid in the air space.

 Sulphuric acid is highly reactive and reacts with calcium compounds to form gypsum which
causes the concrete to soften, ultimately leading to roof collapse.

Organic matter + SO4 2- S2- + H2O + CO2


S2- + 2H+ H2S

H2S + 2O2 H2SO4

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 26


SIET, Department of Civil Engineering
2. HYDROCHLORIC ACID ATTACK

 The chemicals formed as the products of reaction between hydrochloric acid and hydrated
cement phases are some soluble salts and some insoluble salts.

 Soluble salts, mostly with calcium, are subsequently leached out, whereas insoluble salts along
with amorphous hydrogels, remain in the corroded layer.

 Besides dissolution, the interaction between hydro gels may also result in the formation of some
Fe-Si, Al-Si, Ca-Al-Si complexes which appear to be stable in pH range above 3.5.

Ca (OH)2 + 2HCl CaCl2 + 2H2O

 The reaction essentially causes leaching of Ca (OH)2 from the set cement.

 After leaching out of Ca (OH)2 , C-S-H and ettringite start to decompose, with release of Ca2+
to counteract the loss in Ca(OH)2 and the set cement starts to disintegrate accelerating the
dissolution.

Ca6Al2 (SO4)3 (OH)12. 26H2O 3Ca2+ +2[Al (OH) 4] - +4OH- +26H2O


3Ca + +2[Al(OH) ] - +4OH- +12HCL 3CaCl + 2ALCL + 12H O
2 4 2 3 2

 There are few indications through experiments about the formation of Friedel’s salt, C3A.CaCl2
.10H2O, by the action of CaCl2 , formed due to reaction of HCL with CH and C3A

 Hydrochloric acid attack is a typical acidic corrosion which can be characterized by the
formation of layer structure.

 Chandra divided the cross section of damaged prisms into three main zones; undamaged zone,
hydroxide mixture zone or brown ring, and attacked zone. By hydroxide mixture zone, he referred
to a layer formed by undissolved salts seen as a dark brown ring.

Preventive Measures

 By increasing cement content and reducing W/C ratio.


 By improving quality of cover concrete.
 By treating the surface with sodium silicate known as water glass.
 By surface treatment with coal, tar, bituminous paints, epoxy resins etc
3. AGGRESSIVE WATER ATTACK

 Water has been reported to have extremely low concentrations of dissolved minerals.
 This soft or aggressive water will leach calcium from cement paste or aggregates and this attack
take places very slowly.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 27


SIET, Department of Civil Engineering
 Aggressive water attack to have a serious effect on hydraulic structures, the attack must occur in
flowing water. This keeps a constant supply of aggressive water in contact with the concrete and
washes away aggregates particles that become loosened as a result of leaching of the paste

 Visual examination will show concrete surfaces that are very rough in areas where the paste has
been leached.

 If the aggregate is susceptible to leaching, holes where the coarse aggregate has been dissolved
will be evident.

 Water samples from structures where aggressive water attack is suspected may be analyzed to
calculate the langlier index, which is a measure of the aggressiveness of the water.

Preventive Measures

 Assessing the nature of water at the site before construction.


 Water quality evaluation in structures to monitor the aggressiveness of water at the structure
Coating with an non Portland-cement based coating

4. ALKALI REACTION ON CONCRETE

 The reaction of silica and carbonates in aggregates with the alkalis(Sodium or potassium
hydroxide) in cement produces a gel, which causes expansion and cracks is called alkali reaction

 Sodium hydroxide penetrates concrete and becomes concentrated at an evaporating face, physical
damage would result from crystallisation of sodium carbonate.

(A) Alkali-aggregate reaction (AAR)

 This is also called alkali carbonate reaction. Carbonate rock aggregates have been reactive in
concrete.

 This reaction is apparently limited to reactions with impure dolomitic aggregates and are a result
of either dedolomitization or rim-silicification reactions.

Causes

 Visual examination of those reactions that are serious enough to disrupt the concrete in a structure
will generally show map or pattern cracking and a general appearance, which indicates that the
concrete is swelling.

 A distinguishing feature which differentiates alkali-carbonate rock reaction from alkali-silica


reaction is the lack of silica gel exudations at cracks.

 Petrographic examination in accordance with ASTM C295 may be used to confirm the presence
of alkali-carbonate reaction.
Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 28
SIET, Department of Civil Engineering
Influencing Factors

 Size of aggregate.
 Porosity of aggregate.
 Alkali content in cement.
 Fineness of cement particles.
 Availability of non evaporable water in the paste.

Fig 1.18: Alkali aggregate reaction on concrete


(B) Alkali-Silica reaction(ASR)

 The sodium and pottasium alkalis released during the hydration of OPC and siliceous constituent
in aggregate.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 29


SIET, Department of Civil Engineering
 The alkali-silica gel formed, imbibes pore fluid causing expansion. Expansion of gel induces
stresses and these stresses may be ocassionaly base enough to cause cracking and expansion of
concrete

Causes

 Visual examination of those reactions that are serious enough to disrupt the concrete in a structure
will generally show map or pattern cracking and a general appearance, which indicates that the
concrete is swelling.

 Petrographic examination may be used to confirm the presence of alkali-silica reaction.

 Apart from cracking, the major effect of ASR is a reduction in comp. strength, tensile strength
and modulus of elasticity.

 The resulting damage due to ASR depends upon the amount of moisture of available for the ASR
gel to expand.

 Unconfined concrete undergoing AAR exhibits tell-tale signs of surface map cracking on
exposed surfaces.

 The new method called Uranyl (Uranium) acetate fluorescence technique and is rapid and
economical.

Fig 1.19: Alkali silica reaction mechanism

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 30


SIET, Department of Civil Engineering

Fig 1.19: Alkali silica reaction on concrete

Preventive Measures

 Use of low alkali content.


 use of slag cement
 Use of non-reactive aggregates
 Use of silica in concrete mix

5. SULPHATE ATTACK

 Sulphates found in most of the soils as calcium, potassium, sodium and magenisum.
 Solid salts do not attack concrete, but when present is solution they can react with hardened
cement paste.
 Sulphate attack occurs when pore system in concrete is penetrated by solution of sulphates.
 Sulphate reaction depends upon
 Concentration of sulphate ions.
 Cations present in the suplhate solution
 C3A content in cement

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 31


SIET, Department of Civil Engineering
 Density, Permeability of concrete.

 The second hydration product, tricalcium aluminate hydrate reacts with sulphate solution form
sulpho aluminate hydrate(ettringite), which has greater volume than that of the original
compound.

 Due to this, the resultant internal expansive stress may be great enough to cause deformation,
cracking and eventually loss of cohesion.

 When concrete cracks, its permeability increases and the aggressive water penetrates more easily
in to the interior, thus accelerating the process of deterioration

Physical Mechanism

 In addition to two chemical reactions, there may also be a purely physical phenomenon in which
the growth of crystals of sulphate salts disrupts the concrete.

 The damage starts at the egdes and corners and is followed by progressive cracking and spalling
which reduces the concrete to a friable or even soft state.

 The rate of sulphate attack increases with increase in strength of the solution.

 The rate of sulphate attack can be reduced by the use of cement low in tricalcium acuminate and
by the addition of pozzolanic materials

Fig 1.20: Sulphate attack mechanism

Preventive Measures

 Using dense concrete with a low water cement ratio.


 Using sulphate resisting cement/super sulphated cement.
 Minimum cement content and max W/C ratio.
 Provision for expansion through joints.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 32


SIET, Department of Civil Engineering

Fig 1.21: Sulphate attack on concrete

6. CHLORIDE ATTACK

 Chloride can be introduced in to the concrete by coming into contact with environment
containing chlorides, such as sea water or deicing salts.

 Penetration of the chlorides starts at the surface and then moves inward.
 Chlorides may enter in to concrete from following sources
Cement of the concrete

Water mixed in concrete

Aggregates

Admixtures added

Chloride difussion from atmosphere

Mechanism

 The concentration of chlorides in contact with the reinforcing steel will cause corrosion when
moisture and oxygen are present.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 33


SIET, Department of Civil Engineering
 As the rust layer builds, tensile forces generated by the expansion of the oxide cause the concrete
to crack and delaminate.

 the concentration of chlorides necessary to promote corrosion, among other factors, is greatly
affected by the concrete’s pH.

 It was known that a threshold level of 8000ppm of chloride ions was required to initiate
corrosion when the pH was 13.2.

Max.
chloride
Use of Concrete
content in
kg/m3

Concrete containing metal and steam cured at high temp. and prestressed
0.4
concrete

R.C.C or plain concrete containing steel 0.6

Concrete not containing embedded metal or any materialrequiring


3.0
protection from chlorides

 As the pH was lowered in to 11.6, corrosion was initiated with only 71ppm of chloride ions.

 The IS 456-2000 has specified the chloride content as chlorine, in concrete at the time of placing
as shown in table

7. SEA WATER ATTACK

 The marine environment is characterized by wave action, which imposes shock loads and causes
the erosion of concrete structures by abrasion.

 In addition, the concrete is exposed to the aggressive constituents of sea water and subjected to
repeated freeze-thaw and wet-dry cycles.

 The deterioration of concrete structures in such an environment is both chemical and physical in
nature and the type of the attack may be demarcated into 3 zones depending on the tidal lines as
shown in fig.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 34


SIET, Department of Civil Engineering

Fig 1.22: Sea water attack on concrete

 The upper part above the high tide line is not directly exposed to sea water. However, it is
opposed to atmospheric air, frost action, and windblown sea salts. Consequently, cracking due to
reinforcement corrosion and/or freeze-thaw cycles is the main deterioration phenomena in this
zone.

 In the tidal zone, the structure is subjected to alternate wet and dry cycles, freeze and thaw
cycles, impact of waves, and floating ice, abrasion by sand and gravel, and reinforcement
corrosion.

 The lower zone, submerged in water, is a relatively stable environment, where freeze-thaw action
and reinforcement corrosion does not occur.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 35


SIET Department of Civil Engineering
Preventive Measures

 Concrete density, cement type and cement content play a vital role in the resistance of concrete
to sea water.

 Concrete made with calcium aluminates, super sulfate cements and other supplementary
cementitious materials.

 Sufficient cover to reinforcement.

 Low W/C and high cement content.

 Well compacted concrete and good workmanship.

9.2 EVALUATION OF STRUCTURAL DAMAGES TO THE CONCRETE


STRUCTURAL ELEMENT DUE TO EARTHQUAKE

The proposed evaluation methodology is divided in to 3 components.

1. Condition Assessment.
2. Visual Inspection.
3. Non-Destructive Evaluation(NDE)
Failure of Reinforced Concrete Column

1. Formation of plastic hinge at the base of ground level column

2. Diagonal shear crack in midspan of columns

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 33


SIET, Department of Civil Engineering

3. Shear and splice failure of longitudinal reinforcement

Failure of Reinforced Concrete Beam

1. Shear-Flexure Failure

7 Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 34


SIET, Department of Civil Engineering
2. Shear Failure in beam - column joint

7 Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 35


SIET, Department of Civil Engineering
3. Failure of Reinforced Concrete Slab

1. Punching Shear Failure

7 Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 36


SIET, Department of Civil Engineering
1. Condition Assessment
The aim of condition assessment of the structure is the collection of information about the structure
and its past performance characteristics to similar type of structure during past earthquakes and the
qualitative evaluation of structure for decision making.

1. Data collection/information gathering

The information required for the evaluated building can be divided as

Building Data

• Architectural, structural and construction drawings.


• Vulnerability parameters : number of stories, year of construction
• Specifications, soil reports and design calculations
Construction Data

• Identifications of gravity load resisting system.


• Identification of lateral load resisting system
• Field survey of the structures existing condition.
Structural Data

• Materials
• Structural Concept: Vertical and horizontal irregularities.
• Ductile detailing
• Foundations
• Non-structural Elements
2. Past Performance Data

Past performance of similar type of structure during the earthquake provides considerable amount of
information for the building, which is under evaluation process.

Materials Concerns

• Low grade of concrete.


• Deterioration in concrete
• High cement-sand ratio
• Corrosion in reinforcement
• Spalling of concrete

7 Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 37


SIET, Department of Civil Engineering
Structural Concerns

• The relativity low stiffness of the frames.


• Pounding-column distress, possibly local collapse
• Unsymmetrical Buildings in plan
• Unsymmetrical Buildings in elevation
Detailing Concerns

• Large tie spacing in columns lack of confinement of concrete-shear failure


• Insufficient columns lengths-concrete to spall
• Insufficient column strength for full moment hinge capacity-brittle failure
• Inadequate reinforcing of beam column joints or location
3. Seismic Evaluation Data

Seismic evaluation of data will provide a general idea about the building performance during an
earthquake.

Materials Evaluation

• Building height > 3 stories, min grade of concrete, M 30 to M 40 particularly in columns of lower
stories.

• Maximum grade of steel should be Fe415 due to inadequate ductility

• No siginficant deterioration in reinforcement

• No evidence of corrosion or spalling of concrete

Structural Components

• Evaluation of column shear strength and drift


• Evaluation of plan irregularities
• Evaluation of Vertical irregularities
• Evaluation of beam-column joints.
• Evaluation of pounding
• Evaluation of interaction between frame and infill
Structural Detailing should comply with IS: 13920-1993

• Flexural members
• Columns
• Foundation
• Non-structural components
Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 38
SIET, Department of Civil Engineering
2. Visual Inspection/Field Evaluation

Visual Inspection is an integral part of evaluation, and in fact, is the most widely used.

Procedures for Visual Inspection are

1. Description
• Perform a walk through visual inspection to become familiar
• Gather information on the design, construction, maintenance and operation of the structure.
• Plan the complete investigation
• Perform a detailed visual inspection and observe type of damages
• Observe damage documented on sketches
2 Equipments

• Optical magnification- detailed view of local distress


• Stereo microscope- 3 dimensional view of surface.
• Fiberscope and bore scopes- inspection of regions inaccessible to naked eye.
• Tape
• Flashlight- To aid in lighting the area to be inspected
• Crack comparator- To measure width of cracks
• Pencil- To draw sketches of cracks
• Camera-For photographs or video tape
3 Execution

• To identify the location of vertical structural elements


• To sketch the elevation with sufficient details.
• To take photo graphs of cracks
• Observation of the non-structural elements.
4 Limitations

• Applicable to surface damage


• No identification of inner damage

3. Non-destructive Evaluation

Non- destructive evaluation is discussed in MODULE-2 same thing can be incorporated here.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 1- Introduction 39


SIET, Department of Civil Engineering

MODULE-2
DAMAGE ASSESSMENT
2.1 Purpose of Assessment
 Reinforced concrete is comprised of two basic materials, steel and concrete. The two materials
work in a synergetic fashion when constructed properly to provide composite components which
have very strong structural characteristics.
 Concrete is strong in compression but weak in tension but steel is strong in tension and little in
compression. Therefore, in order to construct structural elements which are long lasting,
economical, and have both compressive and tensile capacity, steel is combined with concrete to
harness the compressive strength of concrete and tensile strength of steel.
 Beams are horizontal structural components that support floors, ceilings, roofs or decks and
carries load perpendicular to the longitudinal axis of the beam and load tends to cause the bending
of the beam. This bending creates compressive forces in upper depth of the beam carried by
concrete and tensile force in the lower depth of the beam carried by the steel.
 Columns are vertical structural components that support beams and other structural elements.
The compressive loads carried by columns are primarily parallel to the vertical or longitudinal
axis of the column. Uniform concentric load is applied, comp. load occurs within the columns
cross section and are distributed between the concrete and steel reinforcement
 Eccentric load is applied to a column, bending will occur in column, with outer section of column
in tension and inner section being in compression. The tension load within the column carried by
steel and compression load carried by concrete.
 Cast-in-place buildings are erected using temporary forms that concrete is placed into and then
forms removed and failure will occur throughout the concrete member and/or its connections.
 Precast buildings elements generally formed off-site and then shipped to be assembled on-site
using some type of anchoring device and failure will typically occurs at the joints and/or
connections
2.2 Rapid Assessment
The rapid structural safety assessment should performed in the following ways
1. Review the entire outside of the structure.
2. Enter the building only if necessary to determine the extent of damage.
3. Determine what extent of damage found in the structural and non-structural elements.
4. Secure all areas that need to be isolated and post UNSAFE signage.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 1


SIET, Department of Civil Engineering

 The objectives of rapid structural safety assessment is to quickly inspect and evaluate the concrete
structure and determine if the damage structure is unsafe for personnel within the building and
rescue personnel accessing the building.
 Two primary concerns need to be considered when performing this assessment of the structure
that has sustained structural damage.
 Assessment includes quick evaluation of the building structural components (eg. Beams,
columns, slabs etc.) and non-structural components (Eg. Structural debris, partition walls,
ceilings, glass, pipe anchoring etc)
 If there are any visual signs of structural and/or non-structural damage, then the specific building
area needs to be isolated, secured, and marked as UNSAFE.
 The rapid structural damage assessment would note the major failures within the structure
including major structural elements of beams, columns, and roof and floor decks. The on-scene
commander should be notified immediately of the risk, and the area secured and marked
UNSAFE.
 The rapid non-structural damage assessment would note the major failure within the building
structure such as structural debris, partitions, ceilings, glass and piping.
 Concrete is a brittle material and, therefore, has a tendency to fragment into small. Dense, hard
pieces with rough edges. Settlement or shifting of damaged structure may cause fragments to fall
resulting in serious harm to personnel and/or additional damage to remaining structure
 Depending on the structural and non structural elements within the building matrix and their
relation to rescue/recovery activities, there may be varying importance on the ability of these
elements to provide adequate support. For ex. Failure of a column at ground level may cause
failure of the remaining structure above that columns, or failure of beam above an area where
rescure/ recovery workers are operating may cause collapse of floor
 The ability to perform a rapid structural safety assessment is likely to require a good flashlight(or
headlamp), because adequate lightening is not available in or around the remaining structure. In
addition, a note book, pen or pencil, spray paint and camera will be needed for the assessment.
 Personnel performing the rapid structural safety assessment in and around the remaining
structure should wear appropriate personal protective equipment (PPE). At a minimum PPE
should include a hardhat, steel-toed boots, gloves and respiratory protection from dust.
2.3 Investigation of Damage
The investigation of reasons for damage to structures is largely a matter of gathering information by
observation, studying records and asking questions, supplemented if necessary by a certain amount of
testing, and then interpreting the information thus obtained.
The general procedure for an investigation can be briefly summarized as given below
1. Documentation of damage.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 2


SIET, Department of Civil Engineering

2. Visual observation.
3. Measurements on geometrical parameters such as deflections and deformations
4. Experimentation for evaluating the material properties and behaviour
5. Interpretation and analysis of test results
6. Analysis of the building its damaged state taking in to account the test results obtained during
investigation.
7. Formulation of repair measures.
8. Post-repair evaluation.
1. Observation
Texture of concrete surface may suggest possibility of chemical attack, leaching of the matrix or
in the case of sulphate attack, whitening of the concrete. Rust stains often indicate corrosion of
reinforcement but they may caused by contamination of aggregates. Relatively straight cracks usually
indicate excessive but fairly uniform tensile strain. Cracks caused by unidirectional bending will be
widest in the zone of max. tensile stress and will taper along the length, while cracks caused by direct
tension will be of roughly uniform width.
2. Questioning
Record of mix proportions, sources of materials, cube test results, weather conditions etc may be
available, particularly for recent built structures. It is always useful to ask questions of as many as
possible of the people who were concerned with the design or construction
2.4 Damage Assessment Procedure
The first key step of investigation is to make a diagnosis of the defect or the failure of the building.
The important steps are
1. Visual Inspection.
2. Study of available documentation
3. Estimation of actual loads and environmental effects
4. Diagnosis.
1. Visual Inspection
Any damaged structure, as a first step, requires an extensive visual inspection followed by
documentation of the details. A perusal of the documentation, supported by photographs.
2. Study of available documentation
Study of available documentation will give some idea on the history of construction. Original
quality, analysis and design methods with assumption made, and the type of materials used. A
comparison of adjacent buildings also helps in proper diagnosis.
3. Estimation of actual loads and environmental effects
• It is generally found that there is, in majority of the cases, the load acting on the structure will
be much different from the load assumed in design calculations.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 3


SIET, Department of Civil Engineering

• cracking or any other damage may, sometimes attributed to the fact that these loads or certain
load combinations were not considered in the analysis and design.
• Effect of temperature changes a hostile atmosphere would impose serviceability and durability
problems and also result in undesirable effects in foundations.
4. Diagnosis
• In any investigation, diagnosis of the cause or causes of damage is of prime of importance and
difficult too.
• A proper and reliable diagnosis can be made only by the conducting a systematic investigation
using proven test methods and experienced personnel.

Fig 2.1: Flow chart for damage assessment

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 4


SIET, Department of Civil Engineering

2.5 Evaluation of surface and structural cracks


 The cracks in a structure are broadly classified in to two categories:
 Superficial cracks.
 Structural cracks.
 The structural cracks may be active and dormant.
 A crack where a movement is observed to continue is termed active, whereas the crack where no
movement occurs is termed dormant or static.
 The following information may help in diagnosing the cracks
1. Whether the crack is new or old.
2. Type of crack, i.e., whether it is active or dormant.
3. Whether it appears on the opposite face of the member also, pattern of the cracks.
4. Soil condition, type of foundation used, sign of movement of ground, if any,
5. Observations on the similar structures in the same locality,
6. Study of specifications, method of construction used and test results at the site, if any,
7. Views of designer, builder, occupants of the building, if any
8. Weather during which the structure has been constructed
 The evaluation of cracks is necessary for the following purposes
1. To identify the cause of cracking.
2. To assess the structure for its safety and serviceability.
3. To establish the extent of cracking
4. To establish the likely extent of further deterioration
5. To study the suitability of various remedial measures,
6. To make a final assessment for serviceability after repairs.
 Apart from visual inspection, tapping the surface and listening to the sound for hollow areas may
be one of the simplest methods of identifying the weak spots.
 The suspected areas are then opened up by chipping the weak concrete for further assessment.
 The comparative strength of concrete in the structure may be assessed to a reasonable accuracy
by non-destructive testing and by tests on the cores extracted from the concrete.
2.6 Testing systems of hardened concrete
There are number of testing systems available and they could be used on structures to assess the
quality of concrete and steel.
Testing system of hardened concrete can be divided in to three categories
1. Non-Destructive Testing System(NDTS)
2. Semi Destructive Testing Systems(SDTS)
3. Destructive Testing Systems(DTS)

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 5


SIET, Department of Civil Engineering

1. Non-Destructive Testing System (NDTS): To assess the quality of concrete in its damaged state
without any disturbance of surrounding concrete.
2. Semi Destructive Testing Systems (SDTS): To assess the quality of concrete in its damaged
state with partial disturbance of surrounding concrete.
3. Destructive Testing Systems (DTS): To assess the quality of concrete with complete
disturbance of surrounding concrete (loaded up to failure).
2.6.1 Destructive Testing System (DTS)
 The most common destructive test is load test and is used to assess the strength of concrete. Load
testing is sometimes used as an alternative method of assessing structural capacity.
 Load tests are usually carried out for one of the following reasons
• There are still doubts about the satisfactory performance of the structure under load after a
survey and local testing.
• It is difficult or impossible to determine inadequate information about the structure and its
materials.
• Verification of structural analysis in cases where the complexity of structural forms does not
lend itself to analysis
 The following aspects were set for during the testing programme
• To conduct the load test on the beam up to 1.25 times the designed live load.
• To monitor the deflections and recovery of the beams during incremental loading and
unloading.
• To compare the actual deflections with that of theoretical deflections
(a) Assessment of existing concrete structures
 It has been learnt that concrete structures requires a closer inspection, not only after construction
but also periodically at regularly interval.
 The quality control measures during construction are
Workability test on concrete
Compressive strength of concrete samples.
 It is well known fact the results of the above tests do not reflect on true quality of concrete,
existing in concrete structures because the quality of concrete depends on many factors such as
mixing, transporting, placing, compacting and curing of concrete
 Assessment of quality of concrete is necessary to ensure that the quality of execution is
satisfactory and to identify any deficiency so that they can be rectified. This can be achieved by
conducting some in-situ tests like non-destructive and partially destructive on the structures
besides visual inspection.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 6


SIET, Department of Civil Engineering

(b) Load test on structures


 This is a method of assessing the strength of the in-situ of concrete member. In most cases, this
test is performed for the proof of structure capacity, not for suspect or critical location.
 The principle aim of this test is to demonstrate satisfactory performance under an over load,
above the design working value. This is usually judged by measurement of deflections under this
load which may be sustained for a specified period.
Procedure
 A live load of 1t/sqm was taken for imposed load calculation plus dead load as Floor finishing
load and partition wall load were also considered. Thus imposed load was taken as 1.25times live
load as per IS:456-2000 clause 17.6 page no.30
 The load was imposed on the beam as UDL spreads over an area of 55.5 sqm. Thus a total load
of 84t was arrived at and imposed in 12 stages of 7t each at an interval of 15 minutes.
 The load of 7t was imposed with the help of 200 sand bags weighing 35kg as first step and
increased in steps up to 84t.
 Dial gauges and electric strain gauges were fixed at different locations.
 Separate platform was provided to read and record the deflections from dial gauges, strain from
strain indicator during loading and unloading.
 Total time for maximum load was 26hrs and the maximum load was kept for more than 43hrs
during which creep effect was monitored and the time taken for unloading was 32 hrs during
which deflection recovery was monitored.
 The recorded and theoretical deflections were compared.
 As per IS:456-2000, the deflections due to imposed load only shall be recorded. If within 24hrs
of removal of imposed load, the structure doesnot recover at least 75% of the deflection under
superimposed load, the test may be repeated after a lapse of 72hrs.
 If recovery is less than 80%, the structure shall be unacceptable.
 As per clause 17.6.3.1, the maximum deflection in mm shown during 24hrs under load is less
than 40l2/D
Where l – effective span
D – Over all depth

Fig 2.2: Load test on structures

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 7


SIET, Department of Civil Engineering

2.6.2 Non-Destructive Testing System (NDTS)


The non-destructive testing tests carried out on hardened concrete are
1. Surface Hardness Method.
2. Ultrasonic pulse velocity method.
3. Resonant Frequency Method.
4. Dynamic or vibration method.
5. Pulse Attenuation Method.
6. Pulse echo Method.
7. Radioactive Methods.
8. Nuclear Methods
9. Magnetic Methods

1. Surface Hardness Method(Rebound Hammer Test)


Fundamental Principle
The Schmidt rebound hammer is principally a surface hardness tester. It works on the principle that
the rebound of an elastic mass depends on the hardness of the surface against which the mass
impinges. There is little apparent theoretical relationship between the strength of concrete and the
rebound number of the hammer. However, within limits, empirical correlations have been established
between strength properties and the rebound number.
Equipment Details
The Schmidt rebound hammer is shown in Fig. 4.1. The hammer weighs about 1.8 kg and is suitable
for use both in a laboratory and in the field. A schematic cutaway view of the rebound hammer is
shown in Fig. . The main components include the outer body, the plunger, the hammer mass, and the
main spring. Other features include a latching mechanism that locks the hammer mass to the plunger
rod and a sliding rider to measure the rebound of the hammer mass. The rebound distance is
measured on an arbitrary scale marked from 10 to 100. The rebound distance is recorded as a
“rebound number” corresponding to the position of the rider on the scale.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 8


SIET, Department of Civil Engineering

Fig 2.3: Schematic representation of rebound hammer


Procedure
 The method of using the hammer is explained using Fig.
 With the hammer pushed hard against the concrete, the body is allowed to move away from the
concrete until the latch connects the hammer mass to the plunger, Fig.a.
 The plunger is then held perpendicular to the concrete surface and the body pushed towards the
concrete, Fig.b. This movement extends the spring holding the mass to the body.
 When the maximum extension of the spring is reached, the latch releases and the mass is pulled
towards the surface by the spring, Fig.c.
 The mass hits the shoulder of the plunger rod and rebounds because the rod is pushed hard
against the concrete, Fig.d.
 During rebound the slide indicator travels with the hammer mass and stops at the maximum
distance the mass reaches after rebounding. A button on the side of the body is pushed to lock the
plunger into the retracted position and the rebound number is read from a scale on the body.

Fig 2.4: Working principle of rebound hammer

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 9


SIET, Department of Civil Engineering

Interpretation of results
Average Rebound Number Quality of concrete
>40 Very good hard layer
30 to 40 Good layer
20 to 30 Fair
< 20 Poor concrete
0 Delaminated

2. Ultrasonic pulse velocity(UPV) test


Fundamental Principle
 A pulse of longitudinal vibrations is produced by an electro-acoustical transducer, which is held
in contact with one surface of the concrete under test.
 When the pulse generated is transmitted into the concrete from the transducer using a liquid
coupling material such as grease or cellulose paste, it undergoes multiple reflections at the
boundaries of the different material phases within the concrete.
 A complex system of stress waves develops, which include both longitudinal and shear waves,
and propagates through the concrete. The first waves to reach the receiving transducer are the
longitudinal waves, which are converted into an electrical signal by a second transducer.
 Electronic timing circuits enable the transit time T of the pulse to be measured.
 Longitudinal pulse velocity (in km/s or m/s) is given by:
V= L/T
where v is the longitudinal pulse velocity, L is the path length, T is the time taken by the pulse to
traverse that length.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 10


SIET, Department of Civil Engineering

Equipment for pulse velocity test


The equipment consists essentially of an electrical pulse generator; a pair of transducers used should
be in the range of 20 to 150 kHz, an amplifier and an electronic timing device for measuring the time
interval between the initiation of a pulse generated at the transmitting transducer and its arrival at the
receiving transducer. Two forms of electronic timing apparatus and display are available, one of
which uses a cathode ray tube on which the received pulse is displayed in relation to a suitable time
scale, the other uses an interval timer with a direct reading digital display

Fig 2.5: Component of Ultrasonic pulse velocity

Determination of pulse velocity


Transducer arrangement
The receiving transducer detects the arrival of that component of the pulse, which arrives earliest.
This is generally the leading edge of the longitudinal vibration. Although the direction in which the
maximum energy is propagated is at right angles to the face of the transmitting transducer, it is
possible to detect pulses, which have travelled through the concrete in some other direction. It is
possible, therefore, to make measurements of pulse velocity by placing the two transducers on either:

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 11


SIET, Department of Civil Engineering

 Opposite faces (direct transmission)


 Adjacent faces (semi-direct transmission): or
 Same face (indirect or surface transmission).

Fig 2.6: Measurement of Ultrasonic pulse velocity


Determination of pulse velocity by direct transmission
Where possible the direct transmission arrangement should be used since the transfer of energy
between transducers is at its maximum and the accuracy of velocity determination is therefore
governed principally by the accuracy of the path length measurement. The couplant used should be
spread as thinly as possible to avoid any end effects resulting from the different velocities in couplant
and concrete.
Determination of pulse velocity by semi-direct transmission
The semi-direct transmission arrangement has a sensitivity intermediate between those of the other
two arrangements and, although there may be some reduction in the accuracy of measurement of the
path length, it is generally found to be sufficiently accurate to take this as the distance measured from
centre to centre of the transducer faces. This arrangement is otherwise similar to direct transmission.
Determination of pulse velocity by indirect or surface transmission
Indirect transmission should be used when only one face of the concrete is accessible, when the
depth of a surface crack is to be determined or when the quality of the surface concrete relative to the
overall quality is of interest. It is the least sensitive of the arrangements and, for a given path length,
produces at the receiving transducer a signal which has an amplitude of only about 2% or 3% of that
produced by direct transmission.
Interpretation of results
Longitudinal Pulse Velocity(km/sec) Quality of concrete
>4.5 Excellent
3.5 – 4.5 Good
3.0 – 3.5 Doubtful

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 12


SIET, Department of Civil Engineering

2.0 -3.0 Poor


< 2.0 Very poor

3. Resonant Frequency method


 This method is based up on the determination of the fundamental resonant frequency of vibration
of a specimen.
 The equipment used usually known as SONOMETER.
 This method can be used in laboratory.
 The size of specimen in these tests is limited to 150mmX300mm cylinder or 75mmx 75mm x
300mm prisms
 Resonant frequency test is used for following purpose
 For studying deterioration effects of concrete
 To study the effects due to acid and alkali reactions.
 For determining the damage due to fire
 To calculate the dynamic modulus of elasticity of concrete

Fig 2.7: Resonant frequency equipments


4. Dynamic or vibration method
 These methods are important non-destructive methods used for testing concrete strength and other
properties.
 The fundamental principle of this method is in the propagation of sound velocity through a solid
material
 A mathematical relationship could be established between the velocity of sound through the
specimen and its resonant frequency. From this relationship, the modulus of elasticity of the
material is determined. For deriving this relationship, the solid medium are considered to be
homogeneous, isotropic and perfectly elastic.
 The velocity of sound V in a solid material is a function of the square root of the ratio of its
modulus of elasticity E and its density ρ

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 13


SIET, Department of Civil Engineering

V = f [g E / ρ ] ½
where g is acceleration due to gravity
5. Pulse Attenuation method
 This is a wave propagation method in which the electromagnetic waves, typically in the
frequency ranged 500 MHz to 1000MHz are allowed to propagate through solids.
 The methodology is used for subsurface investigation in civil engineering structures and in
particular concrete structures.
 The basic principle is that the attenuation properties of the electromagnetic waves are influenced
by the electrical properties of the solid material tested.
 The dominant properties are the electrical permittivity, which determines the signal velocity, and
the electrical conductivity, which determines the signal attenuation.
 Reflection and refraction of the radar waves will occur at interfaces between different materials
and the signal returning to the surface antenna can be interpreted to provide an evaluation of
properties and geometry of subsurface features.
6. Pulse echo method
 Pulse echo technique was developed for pile integrity testing and now it is popular for concrete
structures and structural elements.
 An instrument commercially known as DOCTER marked in Denmark is available with a field
computer, related softwares and transducers.
 The system found to be useful for
 Testing for thickness and flaws in concrete.
 Testing for wave speed on the surface.
 Testing for depth of surface opening cracks.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 14


SIET, Department of Civil Engineering

Fig 2.8: Component of Ultrasonic pulse echo equipment


7. Radioactive method
 The use of X-rays and gamma rays as non-destructive method for testing properties of concrete.
 The degree of attenuation depends on the kind of matter traversed, its thickness, and the
wavelength of the radiation.
 The intensity of the incident gamma rays and the emerging gamma rays after passing through the
specimen are measured. These two values are made use for calculating the density of structural
concrete members.
 Gamma radiation source of known intensity is made to pass and penetrate through the concrete.
The intensity of other face is measured and thickness of concrete is calculated
2.6.3 Semi-Destructive Testing System (NDTS)
The semi-destructive tests are
1. Penetration Techniques.
2. Pull-out and Pull-off Tests.
3. Core sampling and testing.
4. Break off test
5. Half-cell potential survey
6. Carbonation and pH value test
7. Chloride content test

1. Windsor probe or Penetration resistance test


In 1964 and 1966, a technique known as Windsor Probes was advanced for testing concrete in lab
and in situ.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 15


SIET, Department of Civil Engineering

Fundamental principle
The Windsor probe, like the rebound hammer, is a hardness tester, and its inventors’ claim that the
penetration of the probe reflects the precise compressive strength in a localized area is not strictly
true. However, the probe penetration does relate to some property of the concrete below the surface,
and, within limits, it has been possible to develop empirical correlations between strength properties
and the penetration of the probe.
Equipment
The Windsor probe consists of a powder-actuated gun or driver, hardened alloy steel probes,
loaded cartridges, a depth gauge for measuring the penetration of probes, and other related
equipment.
As the device looks like a firearm it may be necessary to obtain official approval for its use in some
countries. The probes have a tip diameter of 6.3 mm, a length of 79.5 mm, and a conical point. Probes
of 7.9 mm diameter are also available for the testing of concrete made with lightweight aggregates.
The rear of the probe is threaded and screws into a probe driving head, which is 12.7 mm in diameter
and fits snugly into the bore of the driver. The probe is driven into the concrete by the firing of a
precision powder charge that develops energy of 79.5 m kg. For the testing of relatively low strength
concrete, the power level can be reduced by pushing the driver head further into the barrel.

Fig 2.9: Component of Windsor probe equipment


Procedure (AS PER ASTM C 803)
 The area to be tested must have a brush finish or a smooth surface.
 To test structures with coarse finishes, the surface first must be ground smooth in the area of the
test. Briefly, the powder-actuated driver is used to drive a probe into the concrete.
 If flat surfaces are to be tested a suitable locating template to provide 178 mm equilateral
triangular pattern is used, and three probes are driven into the concrete, one at each corner.
 A depth gauge measures the exposed lengths of the individual probes.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 16


SIET, Department of Civil Engineering

 The manufacturer also supplies a mechanical averaging device for measuring the average
exposed length of the three probes fired in a triangular pattern. The mechanical averaging device
consists of two triangular plates. The reference plate with three legs slips over the three probes
and rests on the surface of the concrete.
 The other triangular plate rests against the tops of the three probes.
 The distance between the two plates, giving the mechanical average of exposed lengths of the
three probes, is measured by a depth gauge inserted through a hole in the centre of the top plate.
 For testing structures with curved surfaces, three probes are driven individually using the single
probe locating template. In either case, the measured average value of exposed probe length may
then be used to estimate the compressive strength of concrete by means of appropriate correlation
data.
2. Pull out and pull off test
 A pullout test measures the force required to pullout from concrete a specially shaped rod which
enlarged end has been cast into that concrete.
 The stronger the concrete more is the force required to pullout.
 The ideal way to use pullout test in the field would be to incorporate assemblies in the structure.
The standard specimens could then be pulled out at any point of time.
 The force required denotes the strength of concrete.
 Internal Fracture Test
The Capo Test
Limpet Test
 Internal Fracture Test
 It is the pullout test, which has been most widely used in the field. It was first developed for
testing high alumina cement concrete components but further work has been carried out to
produce correlation curves for concrete.
 To carry out the test 6mm hole is drilled to a depth of 30-35 mm and the hole is blown out and
each holes should be at least 100mm apart and drilled away from reinforcement
 It is usually to carry out six tests on a member and the average of six max readings is used to
read off the mean comp. strength from calibration curve

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 17


SIET, Department of Civil Engineering

Fig 2.10: Component of pull out test equipment


3. Carbonation test
 Carbonation test is carried out using simple Phenolpthalein test.
 Phenolphthalein spray is an indicator of pH value and as carbonation has its effect on pH of
concrete, the change in colour indicates the extent of carbonation.
 The test is conducted by drilling hole on the concrete surface to different depths up to cover
concrete, spraying with phenolphthalein, and observing the colour change.
 Uncarbonated surface exhibits pink colour while carbonated concrete exhibits no change in
colour.
 The depth of carbonation is estimated based on the change in colour profile.

Fig 2.11: carbonation tested sample


4. Core test
 Concrete cores are used for testing of actual properties of concrete in existing structures such as
strength, permeability, chemical analysis, carbonation etc.
Core Sampling and Testing of Concrete
 Concrete cores are usually cut by means of a rotary cutting tool with diamond bits. In this
manner, a cylindrical specimen is obtained usually with its ends being uneven, parallel and square
and sometimes with embedded pieces of reinforcement.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 18


SIET, Department of Civil Engineering

 The cores are visually described and photographed, giving specific attention to compaction,
distribution of aggregates, presence of steel etc.

Fig 2.12: Core test equipment and sample extrusion of core


 Capping of concrete core
 The ends of the specimen shall be capped before testing. The material used for the capping
shall be such that its compressive strength is greater than that of the concrete in the core. Caps
shall be made as thin as practicable and shall not flow or fracture before the concrete fails
when the specimen is tested. The capped surfaces shall be at right angles to the axis of the
specimen and shall not depart from a plane by more than 0·05 mm.
 After checking for irregularities) the core shall be placed in water at a temperature of 24° to
3O°C for 48 hours before testing. The overall height of the specimens, with capping shall be
measured to the nearest millimetre.

Fig 2.13: Capping of concrete Core


As per IS: 516-1959
 Neat Cement - Test cylinders may be capped with a thin layer of stiff, neat Portland cement
paste' after the concrete has ceased settling in the moulds, generally for two to four hours or

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 19


SIET, Department of Civil Engineering

more after moulding. The cap shall be formed by means of glass plate not less than '6·5 mm in
thickness or a machined metal plate not less than 13 mm in thickness and having a minimum
surface dimension at least 25 mm larger than the diameter of the mould. It shall he worked on
the cement paste until its lower surface rests on the top of the mould, The cement for capping
shall be mixed to a stiff paste for about two to four hours before it is to be used in order to
avoid the tendency of the cap to shrink. Adhesion of paste to the capping plate may be avoided
by coating the plate with a thin coat of oil or grease.
 Curing - The test specimen- shall be stored in a place, free from vibration, in moist air of at
least 90 percent relative humidity and at a temperature of 27° ± 2°e for 24 hours ± l hour from
the time of addition of water to the dry ingredients, After this period, the specimens shall be
marked and removed from the moulds and, unless required for test within 24 hours,
immediately submerged in clean, fresh water or saturated lime solution and kept there until
taken out just prior to test. The water or solution in which the specimens are submerged shall
be renewed every seven days and shall be maintained at a temperature of 27° ± 2°C. The
specimens shall not be allowed to become dry at any time until they have been tested.
 Testing of concrete core
 Test the specimen within 7 days after coring.
 Calculation of Compressive Strength of Concrete Core
 Calculate the compressive test of the specimen using the computed cross sectional area based
on average diameter of the specimen. If the L /D ratio is 1.75 or less, correct the results
obtained by multiplying with correction factors as given below.
 The value obtained after multiplying with correction factor is called corrected compressive
strength, this being equivalent strength of a cylinder having L/D ratio of 2. The equivalent
cube strength can be calculated by multiplying the corrected cylinder strength by 5/4.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 20


SIET, Department of Civil Engineering

 Calculation of Concrete Core compressive strength template

Compressive Strength
Correction Factor for
Core Comp. Strength

Corrected Cylinder
Failure Load (KN)

Equivalent cube
strength(MPa)
Core Diameter

Compressive
Core Height

H/D Ratio

H/D ratio
Sample

H (cm)

D (cm)

(MPa)
(MPa)
Sl. No

No.

As per IS:516-1959 & IS:456-2000 Cl.17.4.3 concrete in the member represented by a core
test shall be considered acceptable if the average equivalent cube strength of the cores is
equal to 85% of the cube strength of the grade of concrete specified for the corresponding
age and no individual core has a strength less than 75%.
 Factors Affecting Strength of Concrete Cores
Size of stone aggregate
If the ratio of diameter of core to maximum size of stone aggregate is less than 3, a reduction in
strength is reported. For concrete with 20mm size aggregate, 50mm dia core has been tested to give
10% lower results than with 10mm dia cores.
Presence of transverse reinforcement steel
It is reported that the presence of transverse steel causes a 5 to 15% reduction in compressive strength
of core. The effect of embedded steel is higher on stronger concrete and as its location moves away
from ends, i.e. towards the middle. However presence of steel parallel to the axis of the core is not
desirable.
H/D ratio
This has been already discussed above. However its value should be minimum 0.95 and maximum 2.
Higher ratio would cause a reduction in strength
Age of concrete
No age allowance is recommended by the Concrete Society as some evidence is reported to suggest
that in-situ concrete gains little strength after 28 days. Whereas others suggest that under average
conditions, the increase over 28 days’ strength is 10% after 3 months, 15% after 6 months. Hence it is
not easy to deal the effect of age on core strength.
Strength of concrete
The effect in reducing the core strength appears to be higher in stronger concretes and reduction has
been reported as 15% for 40 MPa concrete. However a reduction of 5 50 7% is considered
reasonable.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 2- Damage Assessment 21


SIET, Department of Civil Engineering

MODULE-3
Influence on serviceability and durability
3.1 Effect due to temperature
 Change in temperature cause a corresponding change in volume of concrete.
 Two types of temp. change
• Temperature change internally by the heat of hydration of cement.
• Temperature change generated by variation in climatic conditions.
(a) Internally generated temperature differences
Mechanism
 Hydration of Portland cement is an exothermic reaction.
 In large volume placements, significant amount of heat may be generated and the temp. of
concrete may be raised above 38oC over the concrete temp. at placement.
 Temp. rise is not uniform throughout the mass of concrete, and steep temp. Gradients may
develop. This temp. gradients give rise to a situation known as internal restraint-the outer portion
of concrete may be losing heat while the inner portion are gaining heat.
 If the differential is great, cracking may occur. Simultaneously with the development of this
internal restraint condition, as the concrete mass begins to cool, a reduction in volume take place.
 If the reduction in volume is prevented by external conditions such as by chemical bonding,
mechanical interlock or by piles, the concrete is externally restrained
Symptoms
 Cracking resulting from internal restraint will be relatively shallow and isolated.
 Cracking resulting from external restraint will usually extend through the full section.
Prevention
 Low heat content or combination of cement and pozzolana
 Placing the concrete at minimum practical temp.
 Aggregates with low modulus of elasticity and low coefficient of thermal expansion.
 Cooling internally appropriate to minimizing temp. difference
(b) Externally generated temperature differences

Mechanism

 The basic failure mechanism in this case is same as that for internally generated temp.
Differences-the tensile strength of concrete is exceeded.

 The temp. Change in this case leading to the concrete volume change is caused by external
factors, usually change in climatic conditions.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 1


Serviceability and Durability
SIET, Department of Civil Engineering

Symptoms
 Visual examination will show regularly spaced cracking in the case of restrained contraction.
 Spalling at expansion joints will be seen in the case of restrained expansion
Prevention
 Provision for the use of expansion and contraction joint
 Providing reinforcing steel (temp. steel) will help to distribute cracks and minimize the size of
those occur.
3.2 Effect due to Wear and Erosion
 Wear refers to wearing away of the surface by friction.
 Erosion refers to wearing away of the surface by fluids.
 Concrete used in roads, floors, the pavements and the concrete used in the hydraulic structures
should exhibit resistance against wear and erosion.
Mechanism
 Abrasion-erosion damage is caused by the action of debris rolling and grinding against a concrete
surface.
 In hydraulic structures, the area’s most likely to damage are spillway, aprons, stilling basin slabs,
and culverts.
 The sources of debris include construction trash left in a structure, riprap brought back into a
basin by eddy currents because of poor hydraulic design or asymmetrical discharge, and riprap or
debris thrown into a basin by public.
 As the outer paste of concrete wears, the fine and coarse aggregate are exposed and abrasion and
impact will cause additional degradation that is related to aggregate-to-paste bond strength and
hardness of the aggregate.
Symptoms
 Concrete surfaces abraded by waterborne debris are generally smooth and may contain localised
depressions; debris remaining in the structure will be spherical and smooth.
 Mechanical abrasion is usually characterized by long shallow grooves in the concrete surface and
spelling along monolith joints.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 2


Serviceability and Durability
SIET, Department of Civil Engineering

Prevention
 Design
 Operation.
 Use of steel fibres in concrete matrix improves abrasion resistance of concrete.
 Polymer based systems
 Aggregate in concrete should be wear resistant.
 The shape and texture of aggregate plays an important role in abrasion resistance of the
concrete.
 More the compressive strength of concrete higher is the resistance to wear and erosion.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 3


Serviceability and Durability
SIET, Department of Civil Engineering

3.3 Effect due to Chemicals


This is same as effect due to chemical attack which has been discussed in Module -1
3.4 Effect due to Climate
This is same as effect due to freezing and thawing which has been discussed in Module -1
3.5 Design and construction error
Design Errors
Design errors may be divided into two general types:
1. Inadequate structural design
2. Lack of attention to relatively minor design details.
1. Inadequate structural design
Mechanism
The failure mechanism is simple – the concrete is exposed to greater stress than it is capable of
carrying or it sustains greater strain than its strain capacity.
Symptoms
Visual examinations of failures resulting from inadequate structural design will usually show one of
two symptoms.
First, errors in design resulting in excessively high compressive stresses will result in spalling.
Similarly, high torsion or shear stresses may also result in spalling or cracking.
Second, high tensile stresses will result in cracking.
Prevention
Inadequate design in prevented by thorough and careful review of all design calculations. Any
rehabilitation method that makes use of existing concrete structural members must be carefully
reviewed.
2. Poor design details
 A structure may be adequately designed to meet loadings and other overall requirements, poor
detailing may result in localized concentrations of high stresses in otherwise satisfactory concrete.
These high stresses may result in cracking that allows water or chemicals access to the concrete.
 Poor design detailing may simply allow water to pond on a structure, resulting in saturated
concrete.
 poor detailing does not lead directly to concrete failure; rather, it contributes to the action of one
of the other causes of concrete deterioration
(a) Abrupt changes in section
Abrupt changes in section may cause stress concentrations that may result in cracking. Typical
examples would include the use of relatively thin sections such as bridge decks rigidly tied into
massive abutments or patches and replacement concrete that are not uniform in plan dimensions.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 4


Serviceability and Durability
SIET, Department of Civil Engineering

(b) Insufficient reinforcement at reentrant corners and openings.


Reentrant corners and openings also tend to cause stress concentrations that may cause cracking. In
this case, the best prevention is to provide additional reinforcement in areas where stress
concentrations are expected to occur.
(c) Inadequate provision for deflection
Deflection in excess of those anticipated may result in loading of members or sections beyond the
capacities for which they were designed. Typically, these loadings will be induced in walls or
partitions, resulting in cracking.
(d) Inadequate provision for drainage
Poor attention to the details of draining a structure may result in the ponding of water. This ponding
may result in leakage or saturation of concrete. Leakage may result in damage to the interior of the
structure. Saturation may result in severely damaged concrete if the structure is in an area that is
subjected to freezing and thawing.
(e) Insufficient travel in expansion joints:
Inadequately designed expansion joints may result in spalling of concrete adjacent to the joints. The
full range of possible temperature differentials that a concrete may be expected to experience should
be taken into account in the specification for expansion joints. There is no single expansion joint that
will work for all cases of temperature differential.
(f) Incompatibility of materials: The use of materials with different properties (modulus of
elasticity or coefficient of thermal expansion) adjacent to one another may result in cracking or
spalling as the structure is loaded or as it is subjected to daily or annual temperature variations.
(g) Neglect of creep effect:
Neglect of creep may have similar effects as noted earlier for inadequate provision for deflections.
Additionally, neglect of creep in prestressed concrete members may lead to excessive prestress loss
that in turn results in cracking as loads are applied.
(h) Rigid joints between precast units:
Designs utilizing precast elements must provide for movement between adjacent precast elements or
between the precast elements and the supporting frame. Failure to provide for this movement can
result in cracking or spalling.
Construction Errors
 Fail to follow specified procedures and good practice or outright carelessness may lead to a
number of conditions that may be grouped together as construction errors.
 Most of these errors do not lead directly to failure or deterioration of concrete. Instead, they
enhance the adverse impacts of other mechanisms.
(a) Adding water to concrete :
Water is usually added to concrete in one or both of the following circumstances:

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 5


Serviceability and Durability
SIET, Department of Civil Engineering

1. First, water is added to the concrete in a delivery truck to increase slump and decrease
emplacement effort. This practice will generally lead to concrete with lowered strength and
reduced durability. As the w/c of the concrete increases, the strength and durability will
decrease.
2. In the second case, water is commonly added during finishing of flatwork. This practice leads
to scaling, crazing, and dusting of the concrete in service
(b) Improper alignment of formwork
Improper alignment of the formwork will lead to discontinuities on the surface of the concrete.
While these discontinuities are unsightly in all circumstances, their occurrence may be more critical
in areas that are subjected to high-velocity flow of water, where cavitations erosion may be induced,
or in lock chambers where the “rubbing” surfaces must be straight.
(c) Improper consolidation:
Improper consolidation of concrete may result in a variety of defects, the most common being
bugholes, honeycombing, and cold joints.
“Bugholes” are formed when small pockets of air or water are trapped against the forms. A change in
the mixture to make it less “sticky” or the use of small vibrators worked near the form has been used
to help eliminate bugholes.
Honeycombing can be reduced by inserting the vibrator more frequently, inserting the vibrator as
close as possible to the form face without touching the form, and slower withdrawal of the vibrator.
(d) Improper curing:

Curing is probably the most abused aspect of the concrete construction process. Unless concrete is
given adequate time to cure at a proper humidity and temperature, it will not develop the
characteristics that are expected and that are necessary to provide durability. Symptoms of
improperly cured concrete can include various types of cracking and surface disintegration. In
extreme cases where poor curing leads to failure to achieve anticipated concrete strengths, structural
cracking may occur.

(e) Improper location of reinforcing steel:

This section refers to reinforcing steel that is improperly located or is not adequately secured in the
proper location. Either of these faults may lead to two general types of problems.

1. First, the steel may not function structurally as intended, resulting in structural cracking or failure.
A particularly prevalent example is the placement of welded wire mesh in floor slabs. In many case,
the mesh ends up on the bottom of the slab which will subsequently crack because the steel is not in
the proper location.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 6


Serviceability and Durability
SIET, Department of Civil Engineering

2. The second type of problem stemming from improperly located or tied reinforcing steel is one of
durability. The tendency seems to be for the steel to end up near the surface of the concrete. As the
concrete cover over the steel is reduced, it is much easier for corrosion to begin.

(f) Movement of formwork: Movement of formwork during the period while the concrete is going
from fluid to a rigid material may induce cracking and separation within the concrete. A crack open
to the surface will allow access of water to the interior of the concrete. An internal void may give rise
to freezing or corrosion problems if the void becomes saturated.

(g) Premature removal of shores or reshores: If shores or reshores are removed too soon, the
concrete affected may become overstressed and cracked. In extreme cases there may be major
failures.

(h) Settling of the concrete: During the period between placing and initial setting of the concrete,
the heavier components of the concrete will settle under the influence of gravity. This situation may
be aggravated by the use of highly fluid concretes. If any restraint tends to prevent this settling,
cracking or separations may result. These cracks or separations may also develop problems of
corrosion or freezing if saturated.

(j) Vibration of freshly placed concrete: Most construction sites are subjected to vibration from
various sources, such as blasting, pile driving, and form the operation of construction equipment.
Freshly placed concrete is vulnerable to weakening of its properties if subjected to forces which
disrupt the concrete matrix during setting.

(k) Improper finishing of flat work: The most common improper finishing procedures which are
detrimental to the durability of flat work are discussed below.

(1) Adding water to the surface. Evidence that water is being added to the surface is the presence of a
large paint brush, along with other finishing tools. The brush is dipped in water and water is “slung”
onto the surface being finished.

(2) Timing and finishing. Final finishing operations must be done after the concrete has taken its
initial set and bleeding has stopped. The waiting period depends on the amounts of water, cement,
and admixtures in the mixture but primarily on the temperatures of the concrete surface.

(3) Adding cement to the surface. This practice is often done to dry up bleed water to allow finishing
to proceed and will result in a thin cement-rich coating which will craze or flake off easily.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 7


Serviceability and Durability
SIET, Department of Civil Engineering

3.6 CORROSION

Corrosion is the conversion of iron in to its oxides and hydroxides in the presence of oxygen and
water.

Corrosion is defined as the process of deterioration (or destruction) and consequent loss of a solid
metallic material, through an unwanted (or unintentional) chemical or electro-chemical attack by
its environment, starting at its surface, is called Corrosion. Thus corrosion is a process of ‘reverse
of extraction of metals”.

The nature of reinforcement corrosion mechanism can be attributed to three predominant process

1. Chemical Process : In this the alkalinity of concrete can get reduced to a pH < 10 by the ingress
of carbon dioxide or the passivity of steel can be destroyed by the ingress of chloride

2. Electrochemical Process : In this the galvanic cells get established by forming locally or
generally cathodic and anodic sites resulting in a flow of current with moist concrete serving as
the electrolyte.

3. Physical Process: In this the corrosion product (rust) experiences a volume growth as high as six
to 7 times the corroding metal. This volume growth exerts physical expansive forces to the
concrete surrounding the steel.

3.6.1 Corrosion Mechanism


The corrosion process of reinforcement embedded in concrete has two distinct periods namely,

1. Initiation Period: This is the time taken to initiate corrosion which can be caused either by
ingress of carbon dioxide or chloride ions.

2. Propagation Period: the propagation period, during which begins at the moment of
depassivation and involves the propagation of corrosion at a significant rate, until a final state is
reached

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 8


Serviceability and Durability
SIET, Department of Civil Engineering

 Corrosion of steel concrete is an electro-chemical process. When there is a difference in electrical


potential, along the reinforcement in concrete, an electro-chemical cell is set up.

 In the steel, one part becomes anode (an electrode with a +ve charge) and other part becomes
cathode, (an electrode with a –ve charge) connected by electrolyte in the form of pore water, in
the hardened cement paste.

 The +vely charged ferrous ions Fe+ at the anode pass into solution, while the –vely charged free
electrons pass through the steel into cathode, where they are absorbed by the constitutents of the
electrolyte, and combine with water and oxygen to form hydroxyl ions (OH).

 These travel through the electrolyte and combine with the ferrous ions to form ferric hydroxide,
which is converted by further oxidation to rust.

 A moist concrete matrix forms an acceptable electrolyte and the steel reinforcement provides
anode and cathode. Electric current flows between the anode and cathode, and the reaction results
in an increase in metal volume as Fe(Iron) is oxidised in to Fe(OH)2 and Fe(OH)3 and
precipitates as FeOH(rust)

Fig 3.1: Simplified model representing corrosion mechanism

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 9


Serviceability and Durability
SIET, Department of Civil Engineering

 It can be noted that no corrosion takes place if the concrete is dry probably below relative
humidity of 60%, because enough water is not there to promote corrosion.

 it can also be noted that corrosion does not take place, if concrete is fully immersed in water,
because diffusion of oxygen does not take place into the concrete. probably the optimum relative
humidity for corrosion is 70-80%

 The products of corrosion occupy a volume as much as 6 times the original volume of steel,
depending upon the oxidation state. Figure below shows the increase in volume of steel,
depending upon the oxidation state.

 It may be pointed out that though the 2 reactions Fe and OH originate iron the anode and cathode
respectively, their combination occurs more commonly at the cathode, because the Smaller Fe2+
ions diffuse more rapidly than the larger OH ions. So, corrosion occurs at the anode, but rust is
deposited at or near the cathode.

3.6.2 CORROSION PROTECTION TECHNIQUES

1. Coatings to Reinforcement: The objective of coating to steel bar is to provide a sufficiently


durable barrier to aggressive materials such as chlorides. The epoxy coating is done. The bar is
heated to controlled temperature before passing through a spray booth. Hence, electro-statically
charged powder particles are deposited evenly on the surface of the bar. The coating thickness
typically varies from 130 micron to 300 micron.

a. Simple cement slurry coating is a cheap method for temporary protection, against rusting of
reinforcement in storage.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 10


Serviceability and Durability
SIET, Department of Civil Engineering

b. Central electro chemical Research institute (CECRI), Karaikudi, have suggested a method for
prevention of corrosion in steel reinforcement in concrete. The steps involved in this process are:
ü Derusting
The reinforcement are cleaned with a derusting solution. This is followed without delay by leaning
the rods, with wet waste cloth and cleaning powder. The rods are then rinsed in running water and air
dried.
ü Phosphating
Phosphate jelly is applied to the bars, with fine brush. The jelly is left for 45-60 minutes, and then
removed by wet cloth an inhibitor solution is then brushed over the phosphated surface.
c. Cement Coating
Slurry is made by mixing the inhibitor solution, with Portland cement and applied on the bar. A
sealing solution is brushed after the rods are air cured. The sealing solution has an insite curing effect.
The second coat of slurry is then applied and the bars are air dried.
d. Sealing
Two coats of sealing solution are applied to the bars, in order to seal the micro-pores of the cement
coated and to make it impermeable to corrosive sails.

Fig 3.2: Epoxy coated rods


2. Galvanized Reinforcement: Galvanized reinforcement consists of standard black bar, hot dipped
in molten zinc. This process forms a coating which is metallurgically bonded to the surface of the
metal. The surface of the zinc reacts with calcium hydroxide in the concrete to form a passive layer,
preventing corrosion. It is expensive.
3. Improve metallurgically by adding metals
The bars can be improved for its corrosion resistance by adding certain elements such as chromium
and copper during the formation or process itself

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 11


Serviceability and Durability
SIET, Department of Civil Engineering

Fig 3.3: Galvanized rods


4. Stainless steel Reinforcement
Stainless steel is the name given to a family of corrosion resistant steels containing a minimum of
12% chromium. On contact with air, chromium forms a thin oxide layer on the surface of steel. This
is passive and resists corrosion.
5. Non-ferrous reinforcement
Non- ferrous reinforcement is an alternative to the conventional reinforcement in traditional
structures currently being developed by manufacturers. The most commonly used man-made fibres
are glass, carbon and aramid. The fibres are used either in the form of ropes or combined with
suitable resins to form rods.

Fig 3.4: Glass fibre reinforcement Fig 3.5: Glass fibres

Fig 3.6: Aramid fibre reinforcement

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 12


Serviceability and Durability
SIET, Department of Civil Engineering

Fig 3.7: Carbon fibre reinforcement Fig 3.8: Carbon fibre wrappings

Fig 3.9: Placing of carbon fibre to the beams


6. Concrete Coatings
A concrete surface coating of silane-siloxane type was evaluated for its corrosion performance.
7. Improving the concrete
Low W/C
High cement content
Minimum cover
Careful curing
8. Corrosion Inhibitors
A corrosion inhibitor is a substance which, when added to an environment in a small concentration,
effectively reduces the corrosion rate of a metal exposed to that environment.
There are three types of corrosion inhibitors
Anodic inhibitors
Cathodic inhibitors
Mixed inhibitors
 Of the available corrosion inhibiting materials, the most wide used admixture is based on calcium
nitric. It is added to the concrete during mixing of concrete. The typical dosage is of the order of
10-30 litres per m3 of concrete, depending on the chloride levels in concrete.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 13


Serviceability and Durability
SIET, Department of Civil Engineering

 Passivity is the result of the formation of a highly protective, but very thin, (about 0.0004mm
thick) and quite invisible film on the surface of metal or an alloy, which makes it finer. However,
the passivating layer also contains some ferrous oxide, which can initiate corrosion, when the
chloride ions reach the steel. The nitrite ions present in the corrosion inhibiting admixture will
oxidize the ferrous oxide.
 Calcium nitrite corrosion inhibitor comes in a liquid form, containing about 30% calcium nitrite
solids by weight. The more corrosion inhibitor is added, the longer the onset of corrosion will be
delayed. Since most structures in a chloride environment reach a level of about 7 Kg of chloride
iron per m3 during their service life, use of less than 18 litres/m3 of calcium nitrite solution is not
recommended.
 Figure shows that without an inhibitor, the reinforcing steel starts to corrode, when the chloride
content at the rebar reaches a threshold level of 0.7Kg/m3. Although the corrosion process starts
when the thereshold level is reacted, it may take several years for staining, cracking & spalling to
become apparent, (clear) and several more years before deterioration occurs.

9. Cathodic Protection
 Cathode protection is one of the effective, well known, and extensively used methods for
prevention of corrosion in concrete structures in more advanced countries. Due to high cost and
long term monitoring required for this method, it is not very much used in India.
 The cathode protection comprises of application of impressed current, to an electrode laid on the
concrete, above steel reinforcement. This electrode serves as anode and the steel reinforcement,
which is connected to the negative terminal of a DC source acts as a cathode.
 In this process, the external anode is subjected to corrode and the cathode reinforcement is
protected against corrosion and hence the name ‘Cathode Protection”.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 14


Serviceability and Durability
SIET, Department of Civil Engineering

 In this process, the –ve chloride ions, which are responsible for the damage of the passivating
film, are drawn away from the vicinity of steel towards the anode, where they are oxidized to
form chlorine gas.
3.7 EFFECT OF COVER THICKNESS AND CRACKING

In reinforced concrete structures, sufficient cover of concrete has to be provided to avoid exposure of
reinforcement to aggressive environmental conditions and consequent rusting and deterioration of the
cross sectional area in the structural elements. The most common construction defect, particularly in
buildings, is lack of adequate thickness of cover.
It provides the nominal cover requirements to meet
 The durability requirements
 Specified period of fire resistance

Requirements of concrete cover


The protection of the steel in concrete against corrosion depends upon an adequate thickness of good
quality of concrete
 Refer Table 16 of IS: 456-2000 which gives clear information about nominal or clear cover to
be given based on exposure conditions.
 Clear cover is also given based on type of structures i.e., footings, columns, beams and slabs.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 3- Influence on 15


Serviceability and Durability
SIET, Department of Civil Engineering

MODULE-4
Maintenance and Retrofitting Techniques
4.1 Definition
Maintenance is defined as the work done to keep the civil Engineering structures and work in
conditions so as to enable them to carry out the functions for which they are constructed.
It is preventive in nature. Activities include inspection and works, necessary to fulfill the intended
function, or to sustain original standard of service.
The maintenance of structure is done to meet the following objectives
 Prevention of damages due to natural agencies and to keep them in good appearance and working
condition.
 Repair of the defects occurred in the structure and strengthen them, if necessary.
4.2 Types of Maintenance
The Maintenance work is broadly classifies as
a) Preventive Maintenance
b) Remedial Maintenance
c) Routine Maintenance
d) Special Maintenance
a) Preventive Maintenance
 The maintenance work done before the defects occurred or damage developed in the structure is
called preventive maintenance.
 It includes thorough inspection, planning the programs of maintenance and executing the work
 It depends upon the specifications, condition and use of structure.
b) Remedial Maintenance
It is the maintenance done after the defects or damage occurs in the structure. It involves the
following basic steps.
 Finding the deterioration
 Determining the causes
 Evaluating the strength of the existing structure
 Evaluating the need of the structure
 Selecting and implementing the repair procedure
c) Routine Maintenance
 It is the service maintenance attended to the structure periodically.
 The nature of work done and interval of time at which it is done depends upon specifications and
materials of structure, purpose, intensity and condition of use.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 1
Techniques
SIET, Department of Civil Engineering

 It includes white washing, patch repair to plaster, replacement of fittings and fixtures, binding of
road surface.
d) Special Maintenance
 It is the work done under special condition and requires sanction and performed to rectify heavy
damage.
 It may be done for strengthening and updating of the structure to meet the new condition of
usage or to increase its serviceability.
 It may include particular or complete renewal occurring at long interval, such as floors, roofs etc.
4.3 Necessity of Maintenance
The causes which necessitate the maintenance effects the service and durability of the structure as
follows:
a) Atmospheric agencies
b) Normal wear and tear
c) Failure of structure
a) Atmospheric agencies
Rain: It is the important source of water, which affects the structure in the following ways;
Physical:
• Dissolving and carrying away minerals as it is universal solvent.
• Expansion and contraction – The materials is subjected to repetitive expansion and contraction
while they become wet and dry and develops the stresses.
• Expansion of water – The variation of temperature causes the expansion and contraction absorbed
water and affects the micro-structures of the materials.
• Erosion – Transportation, attrition and abrasion of the materials is quite evident effect of the
water.
Chemical: The water available in nature contains acids and alkaline and other compound in dissolve
form acts over the material to give rise, which is known as chemical weathering.
• Wind: It is the agent, which transports the abrasive material and assists the physical weathering
Its action is aggravated during rains and, When it is moving with high speed, it may contains
acidic gases like CO2 fumes which may act over the material and penetrates quite deeply in
materials and structure.
• Temperature: The seasonal and annual variation of the temperature, difference in temperature in
two parts of the materials and the surface of material causes expansion and contraction, this
movement of the material bond and adhesion between them is lost when it is repeated. This
responsible for the development of cracks and the rocks may break away into small units.
b) Normal Wear and tear: During the use of structure it is subjected to abrasion and thereby it loses
appearance and serviceability.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 2
Techniques
SIET, Department of Civil Engineering

c) Failure of structure: Failure is defined as the behavior of structure not in agreement with
expected condition of stability or lacking freedom from necessary repair or non-compliance with
desired use of and occupancy of the completed structure.
The causes of failure may be broadly grouped as:
 Improper Design: Due to incorrect, insufficient data regarding use, loading and environmental
conditions, selection of material and poor detailing.
 Defective Construction: Poor materials, poor workmanship, lack of quality control and
supervision.
 Improper use of structure: Overloading, selecting the structure for the use for which they are not
designed such as deteriorating environment due to impurities from industrial fuel burning, sea
water minerals, chemicals, storage of chemicals etc.
 Lack of maintenance: Lack of upkeep, proper protection, precaution and preservation,
deteriorated the structure, which may result in the failure.
4.4 Facts of Maintenance
Maintenance operations have many facets such as
a) Emergency maintenance: Necessitated by unforeseen breakdown drainage or damage caused by
natural calamity like fire, floods, cyclone earthquake etc.
b) Condition Based maintenance: Work initiated after due inspection
c) Fixed time maintenance: Activities repeated at predetermined intervals of time.
d) Preventive maintenance: This is intended to preserve by preventing failure and detecting
incipient faults (Work is done before failure takes place)
e) Opportunity maintenance: Work did as and when possible within the limits of operation
demand.
f) Day-to-Day care and maintenance
g) Shut down maintenance: Thorough overhaul and maintenance after closing a facility.
h) Improvement plans: This is essentially maintenance operation wherein the weak links in the
original construction are either replaced by new parts or strengthened.
4.5 Importance of Maintenance
 Improves the life of structure
 Improved life period gives better return on investment
 Better appearance and aesthetically appealing
 Better serviceability of elements and components
 Leads to quicker detection of defects and hence remedial measures
 Prevents major deterioration and leading to collapse
 Ensures safety to occupants
 Ensures feeling of confidence on the user

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 3
Techniques
SIET, Department of Civil Engineering

 Maintenance is a continuous cycle involves every element of building science namely Structural,
Electrical wiring Plumbing-water-supply-sanitation, Finishes in floors and walls, Roof terrace,
Service platform/verandah, Lifts, Doors windows and other elements.
4.6 Various aspects of inspection
The following are the various maintenance aspects,
a) Daily Routine Maintenance
b) Weekly Routine Maintenance
c) Monthly Routine Maintenance
d) Yearly Routine Maintenance
a) Daily Routine Maintenance
 Basically an inspection oriented and may not contain action to be taken
 Help in identifying major changes, development of cracks, identifying new cracks etc
 Inspection of all essential items by visual observation
 Check on proper function of sewer, water lines, wash basins, sinks etc
 Check on drain pipes from roof during rainy season
b) Weekly Routing Maintenance
 Electrical accessories
 Cob webs cleaning
 Flushing sewer line
 Leakage of water line
c) Monthly Routing Maintenance
 Cleaning doors, windows‟ latches etc
 Checking septic tank/ sewer
 Observation for cracks in the elements
 Cleaning of overhead tanks
 Peeling of plaster, dampness, floor cracks
d) Yearly Routing Maintenance
 Attending to small repairs and white washing
 Painting of steel components exposed to weather
 Check of displacements and remedial measures

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 4
Techniques
SIET, Department of Civil Engineering

RETROFITTING TECHNIQUES
4.7 Need for retrofitting
1. Load increases due to higher live loads, increased wheel loads, installations of heavy machinery
or vibrations.
2. Damage to structural parts due to aging of construction materials or fire damage, corrosion of
the steel reinforcement, and / or impact of vehicles.
3. Improvements in suitability for use due to limitation of deflections, reduction of stress in steel
reinforcement and / or reduction of crack widths.
4. Modification of structural system due to the elimination of walls or columns and or openings cut
through slabs.
5. Errors in planning or construction due to insufficient design dimensions and / or insufficient
reinforcing steel.
4.8 Retrofitting of structural members
1. COLUMNS AND BEAMS BY JACKETING TECHNIQUE
 One of the simplest and most effective methods for strengthening a column is an existing
building is to partially loaded the column by jacketing between floors and then insert two or more
props to carry portion of the axial load.
 The props are usually rolled steel sections which may subsequently be encased in concrete to
improve fire protection and appearance.
JACKETING
 Jacketing is the process of fastening a durable material over concrete and filling the gap with a
grout that provides needed performance characteristics.
 Jacketing is the most popularly used method for strengthening of building columns.
 The most common types of jackets are steel jacket, reinforced concrete jacket, fibre
reinforced polymer composite jacket, jacket with high tension materials like carbon fibre,
glass fibre etc
 This restores structural values, protects the reinforcements from exposure to the harmful elements
and improves the appearance of the original concrete.
 The main purposes of jacketing are:
1. To increase concrete confinement by transverse fibre reinforcement, especially for circular
Cross-sectional columns,
2. To increase shear strength by transverse fibre reinforcement,
3. To increase flexural strength by longitudinal fibre reinforcement provided.
 Jacketing of columns consists of added concrete with longitudinal and transverse reinforcement
around the existing columns. This type of strengthening improves the axial and shear strength of

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 5
Techniques
SIET, Department of Civil Engineering

columns while the flexural strength of column and strength of the beam-column joints remain the
same.
 A major advantage of column jacketing is that it improves the lateral load capacity of the building
in a reasonably uniform and distributed way and hence avoiding the concentration of stiffness as
in the case of shear walls.
 The jacketing of columns is generally carried out by two methods: (i) reinforced concrete
jacketing and (ii) steel jacketing.
 Jacketing materials may also be secured to concrete by means of bolts, screws, nails or adhesive
by bond with the existing concrete or by gravity.
 The column jacket can also be used for increasing the punching shear strength of column slab
connections by using it as a column capital.
 When the jacket is provided around the periphery of the column, it is termed a collar.
 In most of the applications, the main function of the collar is to transfer vertical load to the
column.
 Circular reinforcement can be used for load transfer.
 The practice of transferring load through dowel bars embedded into or shear keys has a
disadvantage in that they required drilling of holes for dowels or cutting shear keys which are
costly and time consuming, and can damage the existing column.
 The expansion of collar as it slides along the roughened surfaces causes the tensioning of circular
reinforcement resulting in radial compression, which provides normal force needed for load
transfer.
 The shear transfer strength is provided by both frictional resistance to sliding and dowel action of
reinforcement crossing the crack.

Fig 4.1: Column Jacketing

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 6
Techniques
SIET, Department of Civil Engineering

2. EXTERNAL BONDING TECHNIQUE


 Suitable laminates are pasted externally in the flexural zone to improve upon the strength and
deformation characteristics of distressed structural members.
 The laminates may be fabricated from any one of the following material: Steel, Stainless steel,
FRP, Ferro cement and SIFCON and SIMCON.
 The laminates are bonded to the distressed structural elements using epoxy resin.
 Design criteria suggested by researchers worked in plate bending techniques:
 The plate or laminates width to thickness ratio should not be greater than 50.
 The central axis depth should not be greater then 0.4 times the effective depth of member.
 Strengthening with Externally Bonding of plates has the following limitations
 Difficulty in manipulating the plates in field conditions
 Deterioration of the bend steel concrete interface
 Lack of proper formation of joints
(a) Externally bonded mild steel plates
 The technique of gluing mild steel plates to the soffit of reinforced concrete beams and slabs
can be applied to improve the structural performance of the existing structures.
 It increases the strength and rigidity and also reduces the flexural crack width in the concrete.
 The technique can be used to enhance the load carrying capacity either due to increase in load
requirements or design or construction deficiencies.
 This technique has many advantages when applied to bridges.
 The plates can be easily handled and placed, this allowing the procedure to be carried out
relatively quickly with minimal disruption to traffic.
 However, this technique is not recommended for application to bridges with unformed
concrete or those affected by corrosion unless the source of problem is rectified.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 7
Techniques
SIET, Department of Civil Engineering

Fig 4.2: External bonding by mils steel plates


(b) Bonded Steel Elements
 Strengthening concrete members by using bonded steel plates was developed in the 1960s.
 With this method, steel elements are glued to the concrete surface by two-component epoxy
adhesive to create a composite system and improve shear or flexural strength.
 The steel elements can be steel plates, channels, angles, or built up members.
 In addition to epoxy adhesive, mechanical anchors typically are used to ensure that the steel
element will share external loads in case of adhesive failure.
 The exposed steel elements must be protected with a suitable system immediately following
installation and regardless of the specified corrosion protection system, its long term durability
properties and maintenance requirements must be considered fully.
(c) Strengthening with FRP composites
 Fiber reinforced polymer (FRP) systems are high-strength, light weight reinforcement in the
form of paper thin fabric sheets, thin laminates, or bars that are bonded to concrete members with
epoxy adhesive to increase their load carrying capacity.
 These systems have been used extensively in the aerospace, automotive and sport-equipment
industries, and now are becoming a technology for the structural upgrade of concrete structures.
 Important characteristics of FRP’s for structural repair and strengthening applications include
their non-corrosive properties, speed and ease of installation, lower cost and aesthetic appeal.
 with any other externally bonded system, the bond between the FRP system and the existing
concrete is critical and surface preparation is very important.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 8
Techniques
SIET, Department of Civil Engineering

Fig 4.3: Strengthening with FRP laminates


3. NEAR SURFACE MOUNTED REINFORCEMENT
 The technique of near-surface mounted reinforcement for strengthening concrete structures is
currently being developed as an alternative to externally bonded fibre composite materials.
 The process involves cutting a series of shallow grooves in the concrete surface in the required
direction. (The depth of the groove must obviously be less than the cover so that the existing
reinforcement is not damaged.)
 The grooves are partially filled with epoxy mortar into which pultruded carbon fibre composite
rods or strips are pressed.
 The remainder of the groove is then filled with epoxy mortar and the surface levelled.
 The approach can be used to increase the flexural (bending) of beams and slabs, or the shear
capacity of beams. It can also be used for strengthening concrete masonry walls.
 As the fibre composite material is embedded in the concrete, it is less susceptible to damage, for
example by fire or vandalism, than material bonded to the surface.
 It is obviously very appropriate for strengthening the top surfaces of slabs, where externally
bonded fibre composites would require a protective layer; damage may be caused to the
composite if it is necessary to remove the protective layer at a later date.
 A further potential advantage of the technique over the use of externally bonded fibre composite
is that no preparation of the concrete surface is required.
 Clearly one limitation on the technique is the need to have sufficient cover to the existing
reinforcement to allow the grooves to be cut without the risk of damaging the steel.

Step 1: Grooves are cut after marking the layout as per the Engineer of Records’ specifications.
Generally the final groove dimension is 1.5 times the bar diameter in depth and width. Dado cuts are
also effective if possible.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 9
Techniques
SIET, Department of Civil Engineering

Step 2: Chisel any remaining concrete between cut paths.

Step 3: Clean the groove and eliminate any residual dust with compressed air or vacuum.
Note: It is not necessary to roughen the interior of the groove with additional abrasion, or brushing.
Step 4: For a clean appearance, mask the concrete adjacent to the groove.
Note: A time saving tip is to mask over the groove and then trim the masking to each edge.

Step 5: Fill the groove approximately half way with adhesive.


Note: Consider bulk dispensing of adhesive when making your choice of adhesive for the project.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 10
Techniques
SIET, Department of Civil Engineering

Step 6: Press bar or tape into the groove partially filled with adhesive. The objective is to ensure
adhesive is well consolidated around the bar without air pockets.
Note: Some contractors have developed their own system based on epoxy crack injection methods
using a low viscosity epoxy crack injection resin.

Step 7: Completely fill the groove with adhesive ensuring the bar is fully covered.

Step 9: Remove masking.


Note: pull the masking off before adhesive is fully cured.

4. EXTERNAL POST-TENSIONING
 The external post-tensioning technique has been used effectively to increase the flexural and
shear capacity of both reinforced and prestressed concrete members

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 11
Techniques
SIET, Department of Civil Engineering

 With this type of upgrading, active external forces are applied to the structural member using
post-tensioned cables to resist new loads.
 Because of the minimal, additional weight of the repair system, this technique is effective and
economical, and has been employed with great success to correct excessive deflections and
cracking in beams and slabs, parking structures and cantilevered members.
 The post-tensioning forces are delivered by means of standard prestressing tendons or high
strength steel rods, usually located outside the original section.
 The tendons are connected to the structure at anchor points, typically located at the ends of the
member.
 End anchors can be made of steel fixtures bolted to the structural member, or reinforced concrete
blocks that are cast into place.
 The desired uplift force is provided by deviation blocks, fastened at the high or low points of the
structural element.
 Prior to external prestressing, all existing cracks are epoxy injected and spalls are patched to
ensure that prestressing forces are distributed uniformly across the section of the member.
 An external post-tensioning system used to strengthen prestressed double tees damaged by
vehicular impact.
 Four double tee stems on an overpass located were damaged when the driver of an over-height
truck failed to observe the posted height restriction.
 The four stems suffered excessive concrete cracking and spalling, and damaged occurred to some
of the internal prestressing steel.
 Proposed solutions included replacing the damaged double tees with ones and installing a steel
frame underneath for support.

Fig 4.4: External post tensioning

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 12
Techniques
SIET, Department of Civil Engineering

5. SECTION ENLARGEMENT
 This method of strengthening involves placing additional bonded reinforced concrete to an
existing structural member in the form of an overlay or a jacket.
 With section enlargement, columns, beams, slabs and walls can be enlarged to increase their load
carrying capacity or stiffness.
 A typical enlargement is approximately 2 to 3 inches for slabs and 3 to 5 inches for beams and
columns.
 Section enlargement used to increase the capacity of a main girder.The girder was re-evaluated
because of a change in the required loading and found to be deficient in flexure and shear.
 To correct the deficiency, additional flexural and shear steel were added.
 The entire beam then was formed and a 4inch jacket of concrete was cast to enlarge the section.

Fig 4.5: Section enlargement


4.8 Guidelines for seismic rehabilitation of existing building
1. Seismic vulnerability
2. Common seismic deficiencies
3. Strategies for rehabilitation schemes
4. Rehabilitation techniques
1. Seismic Vulnerability
 The vulnerability of a building subjected to an earthquake is dependent on seismic deficiency of
that building relative to a required performance objective.
 The seismic deficiency is defined as a condition that will prevent a building from meeting the
required performance objective.
 Thus, a building evaluated to provide full occupancy immediately after an event may have
significantly more deficiencies than the same building evaluated to prevent collapse.
 Depending on the vulnerability assessment, a building can be condemned and demolished,
rehabilitated to increase its capacity, or modified so that the seismic demand on the building can
be reduced.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 13
Techniques
SIET, Department of Civil Engineering

 Thus, structural rehabilitation of a building can be accomplished in variety of ways, each with
specific merits and limitations related to improving seismic deficiencies.
2. Common seismic deficiencies
 Global strength
 Global stiffness
 Configuration
 Load path
 Inadequate component detailing
 Diaphragm deficiencies
 Foundation deficiencies
 Other deficiencies
Global Strength
 Global strength typically refers to the lateral strength of the vertically lateral force resisting
system.
 For degrading structural systems characterized by a negative post yield slope on the pushover
curve, a minimum strength requirement may apply.
 In certain cases, the strength will also affect the total expected inelastic displacement and added
strength may reduce nonlinear demands into acceptable ranges.
 A deficiency in global strength is common in older buildings either due to a complete lack of
seismic design or a design to an early building code with inadequate strength requirements.
 If prescriptive equivalent lateral force methods or linear static procedures have been used for
evaluation, inadequate strength will directly relate to unacceptable demand to capacity ratios
within elements of the lateral force resisting system.
Global stiffness
 Global stiffness refers to the stiffness of the entire lateral force resisting system although the
lack of stiffness may not be critical at all levels.
 For example, in buildings with narrow walls, critical drift levels occur in the upper floors.
 Conversely, critical drifts most often occur in the lowest levels in frame buildings.
 Stiffness must be added in such a way that drifts are efficiently reduced in the critical levels.
 Although strength and stiffness are often controlled by the same existing elements or the same
retrofit techniques, the two deficiencies are typically considered separately.
 Failure to meet evaluation standards is often the result of a building placing excess drift
demands on existing poorly detailed components.

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 14
Techniques
SIET, Department of Civil Engineering

Load path
 A discontinuity in the load path, or inadequate strength in the load path, may be considered
overarching because this deficiency will prevent the positive attributes of the seismic system from
being effective.
 The load path is typically considered to extend from each mass in the building to the supporting
soil.
 For example, for a panel of cladding, this path would include its connection to the supporting
floor or floors, the diaphragm and collectors that deliver the load to the components of the
primary lateral force resisting system (walls, frames etc.), continuity of these components to the
foundation, and finally the transfer of loads between foundation and soil.
Inadequate component detailing
 Detailing, in this context, refers to design decisions that affect a component’s or system’s
behavior beyond the strength determined by nominal demand, often in the nonlinear range.
 An example of a detailing deficiency is poor confinement in concrete gravity columns.
 Often in older concrete buildings, the expected drifts from the design event will exceed the
deformation capacity of such columns, potentially leading to degradation and collapse.
 Although the primary gravity load design is adequate, the post elastic behavior is not, most often
due to inadequate configuration and spacing of ties.
 Identification of detailing deficiencies is significant in selection of mitigation strategies because
acceptable performance often may be achieved by local adjustment of detailing rather then by
adding new lateral force-resisting elements.
Diaphragm deficiencies
 The primary purpose of diaphragms in the overall seismic system is to act as a horizontal beam
spanning between lateral force resisting elements.
 Diaphragm deficiencies include such factors as inadequate shear or bending strength, stiffness or
reinforcing around openings or corners.
Foundation deficiencies
 Foundations deficiencies can occur within the foundation element itself, or due to inadequate
transfer mechanisms between foundation and soil.
 Element deficiencies include inadequate bending or shear strength foundations and grade beams,
inadequate axial capacity or detailing of piers, and weak and degrading connections between
piles, piers and caps.

 Technical considerations
 Non-technical considerations
 Cost

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 15
Techniques
SIET, Department of Civil Engineering

 Seismic performance
 Short-term disruption of occupant
 Effects on long term functionality of building
 Aesthetics
4. Rehabilitation techniques
 Wood light frames
 Multi story, multi unit residential wood frames
 Steel moment frames
 Steel braced frames
 Steel frames with infill masonry shear wall
 Concrete moment frames
 Concrete shear wall buildings (Bearing wall system)

Repair, Retrofitting & Rehabilitation of Structures (21CV736) Module 4- Maintenance and Retrofitting 16
Techniques
SIET, Department of Civil Engineering

MODULE-5
Materials for Repair and Retrofitting
5.1 FRP Composites
An FRP composite is defined as a polymer matrix which is reinforced with a fibre.
 The primary function of fibre reinforcement is to carry load along the length of the fiber and to
provide strength and stiffness in one direction.
 FRP represents a class of materials that falls into a category referred to as composite materials.
Composite materials consist of two or more materials that retain their respective chemical and
physical characteristics when combined together.
 FRP composites are different from traditional construction materials like steel or aluminium. FRP
composites are anisotropic (properties apparent in the direction of applied load) whereas steel or
aluminium is isotropic (uniform properties in all directions, independent of applied load).
5.1.1 Constituents of FRP
1. Fibres
 The composite’s properties are mainly influenced by the choice of fibres. In civil engineering
three types of fibres are dominate. They are carbon, glass, and aramid fibres and the composite is
often named by the reinforcing fibre, e.g.CFRP for Carbon Fibre Reinforced Polymer. They have
different properties.
 For strengthening purposes, carbon fibres are the most suitable.
 All fibres have generally higher stress capacity than the ordinary steel and are linear elastic until
failure.
 The most important properties that differ between the fibre types are stiffness and tensile strain.
 The three fibre types are schematically presented in figure in comparison with an ordinary steel
bar and a steel tendon.
Types of Fibres
Artificial Fibres
1. Glass Fibre or mineral fibre
2. Aramid Fibre
3. Carbon Fibre
Natural Fibres
1. Sisal Fibre
2. Jute Fibre

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 1
Retrofitting
SIET, Department of Civil Engineering

Fig 5.1: Types of fibres

2. Matrices
The matrix should transfer forces between the fibres and protect the fibres from the environment. In
civil engineering, thermosetting resins (thermosets) are almost exclusively used. Of the thermo sets
vinyl ester and epoxy are the most common matrices. Epoxy is mostly favoured above vinyl ester but
is also more costly. Epoxy has a pot life around 30 minutes at 20degree Celsius but can be changed
with different formulations. The curing goes faster with increased temperature. Material properties
for polyester and epoxy are shown in table 2. Epoxies have good strength, bond, creep properties and
chemical resistance.
Table 5.1: Properties of matrix materials

TYPES OF FIBRE REINFORCED POLYMERS


The different types of fibre reinforced polymer are: glass fibre, carbon, aramid, ultra high molecular
weight polyethylene, polypropylene, polyester and nylon. The change in properties of these fibres is
due to the raw materials and the temperature at which the fibre is formed.
1. Glass fibre reinforced polymer

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 2
Retrofitting
SIET, Department of Civil Engineering

Glass fibres are basically made by mixing silica sand, limestone, folic acid and other minor
ingredients. The mix is heated until it melts at about 1260°C. The molten glass is then allowed to
flow through fine holes in a platinum plate. The glass strands are cooled, gathered and wound. The
fibres are drawn to increase the directional strength. The fibres are then woven into various forms for
use in composites.

Fig. 5.2: Glass fiber reinforced polymer sheet

Based on an aluminium lime borosilicate composition glass produced fibres are considered the
predominant reinforcement for polymer matrix composites due to their high electrical insulating
properties, low susceptibility to moisture and high mechanical properties. Glass is generally a good
impact resistant fibre but weighs more than carbon or aramid. Glass fibres have excellent
characteristics equal to or better than steel in certain forms.
2. Carbon Fibre Reinforced Polymer
Carbon fibres have a high modulus of elasticity, 200-800 GPa. The ultimate elongation is 0.3-2.5 %
where the lower elongation corresponds to the higher stiffness and vice versa. Carbon fibres do not
absorb water and are resistant to many chemical solutions. They with stand fatigue excellently, do not
stress corrode and do not show any creep or relaxation, having less relaxation compared to low
relaxation high tensile prestressing steel strands.
Carbon fibre is electrically conductive and, therefore might give galvanic corrosion in direct contact
with steel.

Fig 5.3: Carbon Fibre Reinforced Polymer

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 3
Retrofitting
SIET, Department of Civil Engineering

3. Aramid Fibre Reinforced Polymer


Aramid is the short form for aromatic polyamide. A well known trademark of aramid fibres is Kevlar
but there exists other brands too, e.g Twaron, Technora and SVM.The modulli of the fibres are 70-
200 GPa with ultimate elongation of 1.5-5% depending on the quality. Aramid has a high fracture
energy and is therefore used for helmets and bullet-proof garments. Aramid fibres are sensitive to
elevated temperatures, moisture and ultraviolet radiation and therefore not widely used in civil
engineering applications. Further aramid fibres do have problems with relaxation and stress
corrosion.
ADVANTAGES OF FIBRE REINFORCED POLYMERS
The advantages of FRP are
 FRP can provide a maximum material stiffness to density ratio of 3.5 to 5 times that of aluminum
or steel.
 It has high fatigue endurance limits
 It can absorb impact energies
 The material properties can be strengthened where required
 The corrosion potential is reduced
 Joints and fasteners are eliminated or simplified.
Natural Fibres

Natural fibres such as sisal, bamboo, coir and jute can be used successfully in composite components
in order to realise reduction of weight and cost. These fibres are renewable, non-abrasive to Process
equipment, and can be incinerated at the end of their life cycle for energy recovery as they possess a
good deal of calorific value. They are also very safe during handling, processing and use. The
distinctive properties of natural fibre reinforced polymers are improved tensile and bending strength,
greater ductility and greater resistance to cracking and hence improved impact strength and
toughness. By changing the direction of the fibres in the resin, the material properties can be tailored
to the external loads.

1. Sisal
The plants look like giant pineapples, and during harvest the leaves are cut as close to the ground as
possible. The soft tissue is scraped from the fibres by hand or machine. The fibres are dried and
brushes remove the remaining dirt, resulting in a clean fibre. Sisal produces sturdy and strong fibres.
Sisal fibre is one of the prospective reinforcing materials that its use has been more experiential than
technical until now. The use of 0.2% volume fraction of 25mm sisal fibres leads to free plastic
shrinkage reduction. Sisal fibres conditioned in a sodium hydroxide solution retained respectively
72.7% and 60.9% of their initial strength after 420 days. As for the immersion of the fibres in a

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 4
Retrofitting
SIET, Department of Civil Engineering

calcium hydroxide solution, it was noticed that original strength was completely lost after 300 days. The
composition of Sisal fibre is basically of cellulose, lignin and hemicelluloses. The failure strength and
the modulus of elasticity, besides the lengthening of rupture, depend on the amount of cellulose and
the orientation of the micro-fibres. As a natural product these characteristics have a wide variation
from one plant to another. The Sisal fibres are found commercially in several formats: fabric, cords,
strips, wire, rolls, etc.

Fig 5.4: Sisal Fibres production process


Properties of this fibre are as follows:
Specific gravity [Kg/m3] 1370
Water absorption [%] 110
Tensile strength [M Pa] 347-378
Modulus of elasticity [G Pa] 15
Available countries: - East Africa, Bahamas, Antiqua, Kenya, Tanzania, India
Advantages
a) They are very well resistant against moist.

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 5
Retrofitting
SIET, Department of Civil Engineering

b) These fibres have a good tension resistance or tensile strength.


c) They are very well resistant against heat.
d) Sisal short fibres delay restrained plastic shrinkage controlling crack development at early ages.
e) Sisal fibres conditioned in a sodium hydroxide solution retained respectively 72.7% and 60.9% of
their initial strength.
Disadvantages
a) Decomposition in alkaline environments or in biological attack
Applications
a) It is mainly used for ropes, mats, carpets. and cement reinforcement
b) It is also used cement reinforcement.
c) In developing countries, sisal fibres are used as reinforcement in houses.
2. Jute Fibre
The fibres are extracted from the ribbon of the stem. When harvested the plants are cut near the
ground with a sickle shaped knife. The small fibres, 5 mm, are obtained by successively retting in
water, beating, stripping the fibre from the core and drying. A single jute fibre is a three dimensional
composite composed mainly of cellulose, hemicelluloses, and lignin with minor amounts of protein,
extractives and inorganics. These fibres were designed, after millions of years of evolution, to
perform, in nature, in a wet environment. To achieve better wet ability of jute with resin and to
improve strength properties, fibre pre-treatment is necessary. Simple pre-treatment is done with low-
condensed resins like melamine resin, phenolic resin and CNSL modified phenol formaldehyde resin.
Jute as other lignocellulosic fibres consists of –OH group which causes it susceptible to moisture and
directly impairs the properties of jute composite specially dimensional stability.

Fig 5.5: Jute Fibres production process

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 6
Retrofitting
SIET, Department of Civil Engineering

Properties of the fibre are as follows:


Specific gravity [kg/m3 ] 1460
Water absorption [%] 13
Tensile strength [MPa] 400-800
Stiffness [KN/mm2 ] 10-30
Available countries:- India, Egypt, Guyana, Jamaica, Ghana, Malawi, Sudan, Tanzania
Advantages
a) It can withstand rotting very easily.
b) Lignocellulosic fibres are favorably bonded with phenolic resin to have better water resistance.
c) The fibres can easily withstand heat.
d) It has high tensile strength.
Disadvantages
a) Due to its short fibre length, Jute is the weakest stem fibre than other fibres.
b) Jute fibre based composites involve reactions with acetic anhydride (acetylation).
c) The fibres are biodegradable.
Applications
a) It is used as packaging material (bags).
b) It is used as carpet backing, ropes, yarns.
c) It is used for wall decoration.
5.2 ADHESIVE-Epoxy Resin
 The various adhesives used are epoxy, polyester, acrylic, polyurethane etc.
 Epoxy resin possesses very high mechanical and adhesive strength properties most desirable for
civil engineering applications.
 Epoxy resin when cured with different hardness it offers a wide range of properties such as
• High adhesive strength.
• Low shrinkage during curing.
• Exceptional dimensional stability.
• Natural gap filling properties.
• Thermosetting
• Resistance to chemical and environment.
5.2.1 Epoxy for crack repair
 The most appropriate method of crack depends on whether crack is still actively moving or not.
 Active cracks may be due to inadequate provision of movement joint in the structure.
 The injection of low-viscosity epoxy is a possible repair method for cracks between 0.02mm to
6mm in width.

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 7
Retrofitting
SIET, Department of Civil Engineering

 There are wide range of low-viscosity epoxy systems and which depends upon temperature of
application, capability of bonding to moist concrete, shrinkage, thermal & elastic properties of the
hardened resin.
5.2.2 Epoxy mortars/Concrete
 Epoxy resin systems are superior in almost all properties to concrete. The adhesive strength of
the epoxy resin is 50 times more than that of cement concrete.
 The use of epoxy in mortar is recommended only in emergency repair, since they have low
modulus of elasticity and high creep than most portland cement products.
 Fillers such as flyash or silica fume are must when workability is to be improved and to minimise
the use of resin.
5.3 Concrete Chemicals
An admixture is defined as a material other than water, aggregate, hydraulic cements and others,
used as an ingredient of concrete or mortar and added to the batch immediately before or during
mixing.
Types of chemical admixtures
1. Water Reducers- Plasticizers and superplasticizers
2. Retarders.
3. Accelerators.
4. Air entraining agents
1. Water Reducer
 Water-reducing admixtures are used to reduce the quantity of mixing water required to produce
concrete of a certain slump, reduce water-cement ratio, reduce cement content, or increase slump.
 Typical water reducers reduce the water content by approximately 5% to 10%. Adding a water-
reducing admixture to concrete without reducing the water content can produce a mixture with a
higher slump.
 An increase in strength is generally obtained with water-reducing admixtures as the water-
cement ratio is reduced.
2. Retarders
 A retarder is an admixture that slows down the chemical process of hydration so that concrete
remains plastic and workable for a longer time than concrete without the retarder.
 Retarders are the chemicals that delay the setting of concrete by an hour or more.
 These are used in hot weather to counter the rapid setting caused by high temperature.
 An increase in strength is generally obtained with water-reducing admixtures as the water-
cement ratio is reduced.
 The most common known retarder is calcium sulphate. It is interground to retard the setting of
cement.
Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 8
Retrofitting
SIET, Department of Civil Engineering

 Sugar is also one of the retarder.


3. Accelerators
 Accelerating admixtures are added to concrete to increase the rate of early strength development
in concrete to
· Permit earlier removal of formwork;
· Reduce the required period of curing;
· Advance the time that a structure can be placed in service;
· Partially compensate for the retarding effect of low temperature during cold weather concreting;
· Emergency repair work
 The commonly used materials as an accelerator were calcium chloride. But, now a day it is used.
Instead, some of the soluble carbonates, silicates fluosilicates and some of the organic compounds
such as triethnolamine are used.
4. Air entraining agents
 Air entraining agents are liquid are added during batching to produce microscopic bubbles, called
entrained air
 These air bubbles improve the resistance to damage caused by freezing & thawing and deicing
salt application.
 It reduces bleeding and segregation and improves workability.
 It is not necessary for interior structural concrete.
 In high cement content concretes, entrained air will reduce strength by about 5% for each 1%
added but in low cement content concrete adding air has less effect and may even cause modest
increase in strength.
5.4 Special Elements for Strength Gain
 In repairs of certain structures, particularly roadways and bridges, it may be desired that early
strength gain should be as rapid as possible.
 Formerly high doses of calcium chloride were advocated but this procedure has been rejected on
the basis of corrosion, problems associated with calcium chloride use.
 The time of setting of Portland cement concrete and its strength gain may be shortened by the use
of calcium aluminate cement. Because of problems associated with the conversion, under hot
humid conditions, of the calcium aluminate hydrates from one form to another, and the resultant
strength losses, other types of cements have been preferred.
 Regulated set cement is a modified Portland cement which contains a substantial amount of
calcium fluoro-aluminate. The cement meal contains a substantial amount of fluorite as a
substitute for limestone. The burning process has a problem due to the release of small amounts
of fluoro compounds. When prepared and ground the initial and final set of this type of cement

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 9
Retrofitting
SIET, Department of Civil Engineering

occurs almost simultaneously and therefore the time between mixing and set is often referred to
as the handling time. As a rule, this varies between 2 to 45 minutes.
 Special cements based on chemical reactions which are completely different from those of
normal Portland or similar cements are now part of the technology. These include fast-setting
magnesium phosphate and aluminium –phosphate cements, which when used for concrete
patching for pavements allow traffic flow after only 45 minutes.
5.5 Special Mortar
1. Cement-clay mortar: Here clay is introduced as an effective finely ground additive in quantities
ensuring a cement-clay proportion of not over 1:1. The addition of clay improves the grain
composition, the water retaining ability and the workability of mortar and also increases the
density of mortar.
2. Lightweight and Heavy mortars
Light weight mortars: These are prepared form light porous sands from pumice and other fine
aggregates. They are also prepared by mixing wood powder, wood shavings or saw dust with
cement mortar or lime mortar. In such mortars, fibres of jute coir and hair, cut into pieces of
suitable size, or asbestos fibres can also be used. These mortars have bulk density less than
15KN/m3.
Heavy weight mortars: These are prepared from heavy quartz or other sands. They have bulk
density of 15 KN/m3 or more. They are used in load bearing capacity.
3. Decorative mortars: These mortars are obtained by using- Colour cements or pigments and Fine
aggregate of appropriate color, texture and surface.
4. Air-entrained Mortar: The working qualities of lean cement-sand mortar can be improved by
entraining air in it(air serves as a plasticizer producing minute air bubbles which helps in flow
characteristics and workability)/ The air bubbles increase the volume of the binder paste and help
to fill the voids in the sand. The air entraining also makes the mortar weight and a better heat and
sound insulator.
5. Gypsum Mortar: These mortars are prepared from gypsum binding materials such as building
gypsum and anhydrite binding materials.
6. Fire Resistant Mortar: It is prepared by adding aluminous cement to a finely crushed power of
firebricks (Usually proportion being one part of aluminous cement to two parts of powder of fire-
bricks).
7. Sound Absorbing mortar: These mortars may have binding materials such as cement, lime,
gypsum slag etc and aggregate(light weight porous materials(such as pumice, cinders etc. The
bulk density of such a mortar varies from 6 to 12KN/m3. Noise level can be reduced by using
sound absorbing plaster formed with the help of sound absorbing mortar.

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 10
Retrofitting
SIET, Department of Civil Engineering

5.6 TECHNIQUES FOR REPAIR


1. Rust Eliminators
 Cement paste normally provides a highly alkaline environment that projects embedded steel
against corrosion.
 Concrete with a low water/cement ratio, well compacted and well cured, has a low permeability
and hence minimizes the penetration of atmospheric moisture as well as other components such
as oxygen, chloride ion, carbon dioxide and water, which encourage corrosion of steel bar.
 In very aggressive environments, the bars may be coated with special materials developed for
this purpose.
 Coating on reinforcing steel, therefore, servers as a means of isolating the steel from the
surrounding environment.
 Common metallic coatings galvanizing zinc.
 High chloride concentration around the embedded steel corrodes the zinc coating, followed by
corrosion of steel.
 Hence, this treatment used for moderately aggressive environments.
 For high corrosive atmospheres caused by chloride ions from the de-icing salts applied to protect
against sodium chloride and calcium chloride, usually near seashores, epoxy coating is applied to
protect the steel reinforcing bars from corrosion.
 Such bars have acceptable bond and creep characteristics.
 The coat normally applied is 150 mm thick.
 The reinforcement is epoxied in the factory itself, where the steel rods are manufactured. Such
reinforcement is known as fusion-bonded epoxy coated steel.
 Steel manufactures also manufacture CTD bars with better corrosion resistance, termed as
Corrosion resistance steel (CRS).
 The performance of the CRS CTD bars is better in resisting corrosion compared to plain CTD
bars. However, the use of CRS CTD bars will only delay the process of corrosion.
2. Polymer based coating
 These are generally of two types
 Resins blended with organic solvents
 Solvent free coating
 Solvent based coatings are subdivided into single and two component coatings.
 The coatings on drying produce a smooth dense continuous film that provides a barrier to
moisture and mild chemical attack of the concrete.
 Because of the resistance to moisture penetration, staining, and ease of cleaning, they are
preferred for locations of high humidity and those in which a lot of soiling occurs.

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 11
Retrofitting
SIET, Department of Civil Engineering

 Most products are low solids content materials which require multiple coats to produce a
continuous film over concrete, since materials are thermoplastic, and have a significant degree of
extensibility they are capable of bridging minor cracks which may be develop in the concrete
surface if they are applied in sufficient thickness.
 The number of coats required depends on the surface texture, porosity and the targeted dry film
thickness.
 Although some of the newer products have some moisture tolerance, enabling them to be applied
over damp surfaces, in normal usage they should be applied over dry surfaces.
 Due their relative in permeability to water vapor, they could blister when applied to concrete
surfaces with high moisture content or where the opposite surface of the concrete is in constant
contact with moisture.
 Careful control of wet film thickness is therefore necessary during application.
 Two component polymer coatings consist of a solution of a compounded polymer with or without
solvent and a reactive chemical component called the curing agent hardener or catalyst.
 The materials are usually mixed just prior to use in accordance with the manufacturer’s
instructions.
 When using two components polymer based coatings the following items are of importance to
the application of the materials.
1. Most produces are supplied as a kit containing the two components in the required
proportions. Therefore, in order to realize the full potential of the product the correct mix ratio of
the two components must be used
2. To ensure a complete reaction of the two components they must be mixed thoroughly.
3. Some two component material require an induction period of 15 to 40 min after mixing.
Therefore, such products cannot be used immediately after mixing
4. Viscosity reduction by the use of thinners should be resorted to only after the manufacturers are
consulted.
5. The storage temperature of solvent based coatings is not critical. They should be stored are a
temperature 16 to 32◦c just prior to use.
3. FOAM CONCRETE
 Foam concrete is a type of lightweight concrete that is manufactured from cement, sand or fly
ash, water, and the foam. Foam concrete is in the form of foamed grout or foamed mortar.
 Foam concrete can also be defined as a cementitious material that consists of minimum 20
percent of foam that is mechanically entrained into the plastic mortar.
 The dry density of foamed concrete may vary from 300 to 1600 kg/m3. The compressive strength
of foam concrete determined at 28 days, ranges from 0.2 to 10N/mm2 or can go higher.

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 12
Retrofitting
SIET, Department of Civil Engineering

 Foam concrete is differentiated from air entrained concrete in terms of the volume of air that is
entrained. The air entrained concrete takes in the air of 3 to 8 percent. It also differs from the
retarded mortar and aerated concrete for the same reason of percentage of air entrained.
Production of foam concrete
 The production of foam concrete involves the dilution of surfactant in water, which is passed
through a foam generator that will produce foam of stable form. The foam produced in mixed
with the cementitious mortar or the grout, so that foamed quantity of required density is produced.
 Two main methods are used for production of foamed concrete
1. Inline Method
The base mix of cement and sand is added to a unit. In this unit, the mix is blended with foam
thoroughly. The process of mixing is carried out with proper control. This will help in mixing of
larger quantities. The inline method comprises two processes;
 Wet Method- Inline System
 Dry Method -Inline System
2. Pre- Foam Method
Here, the ready-mix truck brings the base material to the site. Through the other end of the truck, the
pre- formed foam is injected into the truck, while the mixer is rotating. So, small quantities of foam
concrete can be produced for small works, like for grouting or trench fill works.
Composition of foam concrete
 Foamed concrete composition varies with the density that is demand. Generally, the foamed
concrete that has densities lesser than 600kg/m3 will have cement, foam, water also some addition
of fly ash or limestone dust.
 To achieve higher densities for foamed concrete, sand can be employed. The base mix is 1:1 to
1:3 for heavier foamed concrete, which is filler to portland cement ratio (CEM I).
Materials for foam concrete
1. Cement- 300-400kg/m3 (with fly ash blend)
2. Pozzolana – Fly ash or GGBS (30 to 70%)
3. Sand - The maximum size of sand used can be 5mm. Use of finer sands up to 2mm with amount
passing through 600 micron sieve range from 60 to 95%.
4. Foam - The hydrolyzed proteins or the synthetic surfactants are the most common forms based on
which foams are made. The synthetic based foam agents are easier to handle and are cheap. They
can be stored for a longer period.

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 13
Retrofitting
SIET, Department of Civil Engineering

Table 5.2: Typical Properties of Foamed Concrete in its Hardened State

Dry Density Compressive Tensile Strength Water Absorption


Kg/m3 Strength N/mm2 N/mm2 Kg/m2

400 0.5 – 1 0.05-0.1 75

600 1-1.5 0.2-0.3 33

800 1.5 -2 0.3-0.4 15

1000 2.5 -3 0.4-0.6 7

1200 4.5-5.5 0.6-1.1 5

1400 6-8 0.8-1.2 5

1600 7.5-10 1-1.6 5

The thermal conductivity of foam concrete ranges from 0.1W/mk to 0.7W/mk.


The drying shrinkage ranges from 0.3 to 0.07% at 400 and 1600kg/m3 respectively.
4. MORTAR & DRY PACK
 Dry pack is a combination of Portland cement and sand passing a No. 16 sieve(1.18mm) mixed
with just enough water to hydrate the cement(low water cement ratio).
 Dry pack should be used for filling holes having a depth equal to, or great then, the least surface
dimension of the repair area, for cone bolt, she hole, core holes, and grout-insert holes; for holes
left by the removal of form ties; and for narrow slots cut for repair cracks.
 Dry pack should not be used for relatively shallow depressions where lateral restraint cannot be
obtained, for filling behind reinforcement, or for filling holes that extend completely, through a
concrete section.
 For the dry-pack, method of concrete repair, holes should be sharp and square at the surface
edges, but corners within the holes should be rounded, especially when water tightness is
required.
Preparation and Application
 Application of dry-pack mortar should be preceded by a careful inspection of the hole, which
should be thoroughly cleaned and free from mechanically held loose pieces of aggregate.

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 14
Retrofitting
SIET, Department of Civil Engineering

 One of three methods should be used to ensure good bond of the dry-pack repair.
 The first method is the application of a stiff mortar or grout bond coat immediately before
applying the dry-pack mortar. The mix for the bonding grout is 1:1 cement and fine sand mixed
with water to a fluid paste consistency.
 All surfaces of the hole are thoroughly brushed with the grout, and dry packing is done quickly
before the bonding grout can dry. Under no circumstances should be bonding coat be so wet or
applied so heavily that the dry-pack material becomes more has slightly rubbery.
 The second method of ensuring good bond starts with presoaking the hole overnight with wet
rags or burlap. The hole is left slightly wet with a small amount of free water on the inside
surfaces. The surfaces have been covered and the free water absorbed. Any dry cement in the hole
should be removed using a jet of air before packing begins. The hole should not be painted with
neat cement grout because it could make the dry-pack material too wet and because high
shrinkage would prevent development of the bond that is essential to a good repair.
 A third method of ensuring good bond is use of an epoxy bonding resin. Epoxies bond best to
dry concrete. It may be necessary to dry the hole immediately prior to dry packing using hot air, a
propane torch, or other appropriate method.
 The concrete temperature however should not be high enough to cause instant setting of the
epoxy or to burn the epoxy when it is applied. After being mixed, the epoxy is thoroughly
brushed to cover all surfaces, but any excess epoxy is removed. Dry-pack mortar is then applied
immediately, before the epoxy starts to harden.
4. VACUUM CONCRETE
 Vacuum concrete is the type of concrete in which the excess water is removed for improving
concrete strength. The water is removed by use of vacuum mats connected to a vacuum pump.
 All the water used in mixing concrete is not required for hydration. Therefore, removal of excess
water before hardening take place improves concrete strength.

Fig 5.6: Vacuum concrete process

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 15
Retrofitting
SIET, Department of Civil Engineering

Procedure
In the usual manner, a concrete mix with good workability is pace in the form-works. As fresh
concrete contains continues the system of water-filled channels, the application of a vacuum to the
surface concrete results in a large amount of a vacuum to the surface of the concrete. This results in a
large amount of water being extracted from a certain depth of the concrete. The vacuum is applied
through porous mats connected to a vacuum pump. The final water cement ratio before setting is thus
reduced and as this ration largely controls the strength, vacuum concrete has a higher strength and
also density a lower permeability and a greater durability.
Advantages
 The final strength of concrete is increased by about 25%.
 Sufficient decrease in The permeability of concrete is sufficiently decreased.
 Vacuum concrete stiffens very rapidly so that the form-works can be removed within 30 minutes
of casting even on columns of 20 ft. high.
 This is of considerable economic value, particularly in a precast factory as the forms can be
reused at frequent intervals.
 The bond strength of vacuum concrete is about 20% higher.
 The density of vacuum concrete is higher.
 The surface of vacuum concrete is entirely free from pitting and the uppermost 1/16 inch is
highly resistant to abrasion.
 These characteristics are of special importance in the construction of concrete structures which
are to be in contact with flowing water at a high velocity.
 It bonds well to old concrete and can, therefore, be used for resurfacing road slabs and other
repair works.
5. EPOXY INJECTION
 Epoxy injection is an economical method of repairing non-moving cracks in concrete walls, slabs,
columns and piers and is capable of restoring the concrete to its pre-cracked strength.
 Two basic types of resin and injection techniques are used to repair concrete: epoxy resins and
polyurethane resins.
 Injection of epoxies under pressure may be used to bond the cracks having greater than or
equal to 0.05mm opening. This method is not applicable if the crack is active, the cracks are
large in number, or when the water leakage can not be controlled.
 Epoxy injection is commonly used to restore the pre-cracking condition of the member without
increasing its strength.

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 16
Retrofitting
SIET, Department of Civil Engineering

Steps
The general steps involved are as follows.
1. Preparation of the surface: The contaminated cracks are cleaned by removing all oil, grease,
dirt and fine particles of concrete which prevent the epoxy penetration and bonding. The
contaminants should preferably be removed by flushing the surface with water or a solvent. The
solvent is then blown out using compressed air, or by air drying. The surface cracks should be
sealed to keep the epoxy from leaking out before it has cured or gelled. A surface can be sealed
by brushing an epoxy along, the surface of cracks and allowing it to harden. If extremely high
injection pressures are needed, the crack should be routed to a depth of about 12mm and width of
about 20mm in V-shape, filled with an epoxy, and stuck off flush with the surface.
2. Installation of entry ports: The entry port or nipple is an opening to allow the injection of
adhesive directly into the crack without leaking. The spacing of injection ports depends upon a
number of factors such as depth of crack, width or crack and its variation with depth, viscosity of
epoxy, injection pressure etc. and choice must be based on experience.
3. Mixing of epoxy: The mixing can be done either by batch or continuous methods. In batch
mixing, the adhesive components are premixed in specified proportions with a mechanical stirrer,
in amounts that can be used prior to the commencement of curing of the material. In the
continuous mixing system, the two liquid adhesive components pass through metering and
driving pumps prior to passing through an automatic mixing head. The continuous mixing system
allows the use of fast-setting adhesives that have short working life.
4. Injection of epoxy: In its simplest form, the injection equipment consists of a small reservoir or
funnel attached to a length of flexible tubing, so as to provide a gravity head. For small quantities
of repair material small hand-held guns are usually the most economical. They can maintain a
steady pressure which reduces chances of damage to the surface seal. For big jobs power-driven
pumps are often used for injection. It is preferable to inject fine cracks under low pressure in
order to allow the material to be drawn into the concrete by capillary action and it is a common
practice to increase the injection pressure during the course of work to overcome the increase in
resistance against flow as crack is filled with material.
5. Removal of surface seal: After the injected epoxy has occurred; the surface seal may be
removed by grinding or other means as appropriate. Fittings and holes at the entry ports should be
painted with an epoxy patching compound.

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 17
Retrofitting
SIET, Department of Civil Engineering

6. GUNITE or SHOTCRETE
 Gunite can be defined as mortar conveyed through a hose and pneumatically projected at a high
velocity onto a surface.
 Recently this method has been further developed by the introduction of small sized coarse
aggregate into the mix deposited to obtain considerably greater thickness in one operation and to
make the process economical by reducing the cement content.
 There is not much difference between guniting and shotcreting. Gunite was first used in the early
1900 and this process is mostly used for pneumatical application of mortar of less thickness,
whereas shotcrete is a recent development on the similar principle of guniting for achieving
greater thickness with small coarse aggregates.
 There are two different processes in use, namely the “Wet-mix” process and the “dry-mix”
process.
1 Dry-mix Process: The dry mix process consists of number of stages and calls for some
specialized plan. A typical small plant set-up is shown. This material is carried by compressed air
through the delivery hose to a special nozzle. The nozzle is fitted inside with a perforated
manifold through which water is sprayed under pressure and intimately mixed with the
sand/cement jet. The wet mortar is jetted from the nozzle at high velocity onto the surface to
gunited.
2 Wet-mix process: In the wet-mix process the concrete is mixed with water as for ordinary
concrete before conveying through the delivery pipe line to the nozzle, at which point it is jetted
by a compressed air, onto the work in the same way, as that of dry-mix process.
The wet-mix process has been generally discarded in favour of dry-mix process, owing to the
greater success of the latter.

Fig 5.7: Wet and dry mix process

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 18
Retrofitting
SIET, Department of Civil Engineering

7. SHORING & UNDERPINING


 Shoring is a general term used in construction to describe the process of supporting a structure in
order to prevent collapse so that construction can proceed.
 Shoring is used to support the beams and floors in a building while a column or wall is removed.
In this situation vertical supports are used as a temporary replacement for the building columns or
walls.
 Trenches – During excavation, shoring systems provide safety for workers in a trench and speed
excavation. In this case, shoring should not be confused with shielding.
 Shoring is designed to prevent collapse where shielding is only designed to protect workers when
collapses occur. concrete structures shoring, in this case also referred to as false work, provides
temporary support until the concrete becomes hard and achieves the desired strength to support
loads.
Shoring Techniques in Building Construction
Raking Shore
Raking Shores consist of one or more timbers sloping between the face of the structure to be
supported and the ground. The most effective support is given if the raker meets the wall at an angle
of 60 to 70 degrees. A wall-plate is typically used to increase the area of support.
Hydraulic Shoring
Hydraulic shoring is the use of hydraulic pistons that can be pumped outward until they press up
against the trench walls. They are typically combined with steel plate or plywood, either being 1-1/8″
thick plywood, or special heavy Finland Form (FINFORM) 7/8″ thick.
Beam and Plate
Beam and Plate steel I-beams are driven into the ground and steel plates are slid in amongst them. A
similar method that uses wood planks is called soldier boarding. Hydraulics tend to be faster and
easier; the other methods tend to be used for longer term applications or larger excavations.
Soil Nailing
Soil nailing is a technique in which soil slopes, excavations or retaining walls are reinforced by the
insertion of relatively slender elements – normally steel reinforcing bars. The bars are usually
installed into a pre-drilled hole and then grouted into place or drilled and grouted simultaneously.
They are usually installed untensioned at a slight downward inclination. A rigid or flexible facing
(often sprayed concrete) or isolated soil nail heads may be used at the surface.
Continuous Flight Augering
Continuous Flight Augering (CFA) is a method used to create concrete piles to support soil so that
excavation can take place nearby. A Continuous Flight Augering drill is used to excavate a hole and

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 19
Retrofitting
SIET, Department of Civil Engineering

concrete is injected through a hollow shaft under pressure as the auger is extracted. This creates a
continuous pile without ever leaving an open hole.
Underpinning
Underpinning is the process of strengthening and stabilizing the foundation of an existing building or
other structure.
Underpinning may be necessary for a variety of reasons:
 The original foundation is simply not strong or stable enough, e.g. due to decay of wooden piles
under the foundation.
 The usage of the structure has changed.
 The properties of the soil supporting the foundation may have changed (possibly through
subsidence) or were mischaracterized during planning.
 The construction of nearby structures necessitates the excavation of soil supporting existing
foundations.It is more economical, due to land price or otherwise, to work on the present
structure’s foundation than to build a new one.
 Underpinning is accomplished by extending the foundation in depth or in breadth so it either rests
on a stronger soil stratum or distributes its load across a greater area. Use of micropiles and jet
grouting are common methods in underpinning.
 An alternative to underpinning is the strengthening of the soil by the introduction of a grout. All
of these processes are generally expensive and elaborate.
Methods of Underpinning
Following are the different underpinning methods used for foundation strengthening:
1. Mass concrete underpinning method (pit method)
2. Underpinning by cantilever needle beam method
3. Pier and beam underpinning method
4. Mini piled underpinning
5. Pile method of underpinning
6. Pre-test method of underpinning

1. Mass Concrete Underpinning Method (Pit Method)


Mass concrete underpinning method is the traditional method of underpinning, as it has been
followed by centuries. The method involves extending the old foundation till it reaches a stable
stratum.
The soil below the existing foundation is excavated in a controlled manner through stages or pins.
When strata suitable are reached, the excavation is filled with concrete and kept for curing, before
next excavation starts.

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 20
Retrofitting
SIET Department of Civil Engineering

Fig 5.8: Mass concreting


2. Underpinning by Cantilever Needle Beam Method
Figure-2 represents the arrangement of cantilever pit method of underpinning, which is an extension
of pit method. If the foundation has to be extended only to one side and the plan possess a stronger
interior column, this method can be used for underpinning.
Advantages of Cantilever Needle Beam Method:
Faster than traditional method
One side access only
High load carrying capability
Disadvantages:
Digging found uneconomical when existing foundation is deep
Constraint in access restricts the use of needle beams

Fig 5.9: cantilever needle beam

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 21
Retrofitting
SIET Department of Civil Engineering

3. Pier and Beam Underpinning Method


It is also termed as base and beam method which was implemented after the Second World War. This
method progressed because the mass concrete method couldn’t work well for a huge depth of
foundation.
It is found feasible for most of the ground conditions. Here reinforced concrete beams are placed to
transfer the load to mass concrete bases or piers as shown in figure 2.
The size and depth of the beams are based on the ground conditions and applied loads. It is found
economical for depth shallower than 6m.

Fig 5.10: Pier method


4. Mini Piled Underpinning
This method can be implemented where the loads from the foundation have to transferred to strata
located at a distance greater than 5m. This method is adaptable for soil that has variable nature,
access is restrictive and causes environmental pollution problems.
Piles of diameter between 150 to 300mm in diameter is driven which may be either augured or driven
steel cased ones.
5. Pile Method of Underpinning
In this method, piles are driven on adjacent sides of the wall that supports the weak foundation. A
needle or pin penetrates through the wall that is in turn connected to the piles as shown in figure.
These needles behave like pile caps. Settlement in soil due to water clogging or clayey nature can be
treated by this method

Fig 5.11: Pile method

Repair, Retrofitting & Rehabilitation of Structures (21CV736), Module 5- Materials for Repair and 22