Gantt chart for software development life cycle
Task start date End Date Duration(days)
Planning 12/16/2024 12/21/2024 4
Requirement Gathering 12/16/2024 12/18/2024 2
Analyze Client Needs 12/19/2024 12/21/2024 2
System Design 12/22/2024 12/30/2024 7
Create Architecture 12/22/2024 12/25/2024 3
Design Database 12/26/2024 12/30/2024 4
Implementation 12/31/2024 1/14/2025 13
Develop Code 12/31/2024 1/10/2025 10
Module Review 1/11/2025 1/14/2025 3
Testing 1/15/2025 1/27/2025 10
Unit Testing 1/15/2025 1/17/2025 2
Integrating Testing 1/18/2025 1/21/2025 3
System Testing 1/22/2025 1/27/2025 5
Deployment 1/28/2025 2/4/2025 6
Deployment System on Server 1/28/2025 1/31/2025 3
Configure Environment 2/1/2025 2/4/2025 3
Maintanance 2/5/2025 2/18/2025 11
Bug Fixes 2/5/2025 2/10/2025 5
Update 2/11/2025 2/14/2025 3
Feature Enhancement 2/15/2025 2/18/2025 3
Progress Days completed (duration *progress)
100% 5
100% 2
100% 2
100% 8
100% 3
100% 4
100% 13
100% 10
100% 3
100% 12
100% 2
100% 3
100% 5
100% 6
100% 3
100% 3
100% 11
100% 5
100% 3
100% 3