REQUEST FOR INSPECTION (RFI)
Date Issued Project RFI Number
16/08/2023 HMMI CYE PROJECT CYE-RFI-005
Soil CBR test and ground leveling before limestone layering
(Submitted to the Engineer at Least 24 Hours before the time of the inpection)
Civil ✓ M.E.P
Type of Work
Architecture Other
Date 19-Aug-23
To be Held Time 9:00:00
on / at / with Location Container Yard Project
HMMI PIC
Activities for Which - Checking As built soil elevation
The Inspection is - Specify Soil CBR test point
Requested - CBR Test
Other Information
Submitted by Received by
Inspection Result
Approved Rejected
Inspection Status
Approved with Note
Inspection
Comments
INSPECTION FOR
EXCAVATION RECORD
REPORT
Project : HMMI-Expansion Projects Report No. : …......................................
Site Name : Container Yard Projects Date : …......................................
Location : Engine Shop Subcon : PT. HANJIN KONSTRUKSI
Reff. Document : …...................................... Reff. Drawing :
Inspection Result
No Check Items Acceptance Criteria Design Code
Accept Reject
As per actual field
1 The work site is cleared
inspection
Excavation is performed to the lines, As per approved surveying
2
grades, and slopes drawing report
All excavation are cut true and straight
As per actual field
3 and loos stone and boulders shall be
inspection
removed in area
Excavation is made below the elevation
4 As per approved drawings
level indicates on the design drawing
Protection work of excavated slope area As per actual field
5
for safety inspection
As per approved surveying
6 Condition of compaction bottom survey
report
As per actual field
7 Quality Of Cleaning
inspection
Result Of Compaction test after As per approved soil test
8
Excavation, confirmed (if necessary) report
Note :
Prepared by PT. HKI Approved by HEIFM
QA / QC Site Manager Inspected By Checked By
INSPECTION FOR SURVEYING
RECORD
REPORT
Project : HMMI-Expansion Projects Report No. : …......................................
Site Name : Container Yard Projects Date : …......................................
Location : Engine Shop Subcon : PT. HANJIN KONSTRUKSI
Reff. Document : …...................................... Reff. Drawing :
Inspection Result
No Check Items Acceptance Criteria Design Code
Accept Reject
1 Description & Location As per approved drawings
2 Benchmark Used As per approved drawings
3 Surveying Data As per approved drawings
Note :
Prepared by PT. HKI Approved by HEIFM
QA / QC Site Manager Inspected By Checked By
CBR test will be conducted at one point on every 400 m2 Y14
Y13
In the yellow highlight is the area where the CBR test
will be carried out Y12
Testing point will be specify in random, but priority on the
Y11
soil area that looks down
Y10
CBR test working steps are attached in a separate section
of this method
Y09
C-10 C-7 C-4 C-1
SOIL CBR
TEST Y08
PLAN C-11 C-6 C-5 C-2
Y07
Y06
Y05
Y04
Y03
When penetrating during CBR test, 10 T Vibro will be used
Y02
for additional equipment
X06 X05 X04 X03 X02 X01