RA Bill Cement Reconciliation
RA Bill Cement Reconciliation
1st RA Bill
PROJECT - _____________________________________________-
___________________-, BANGALORE
M/s. Nestled Haven Developers LLP Bill Index M/s. TJN Construction Private Limited
Tax Invoice
PROJECT - ______________________________________-, BANGALORE
Amount In Words:
uth. Sign
NAME OF CONTRACTOR : M/s________- Private Limited RUNNING BILL NO. : RA Bill No.
NAME OF PROJECT : _______- A High-Rise Residential Tower (2B+G+24 F) PERIOD OF MEASURMENT : Upto _________
NATURE OF WORK : Civil & Structure Work DATE OF SUBMISSION : __/__/2021
LOCATION : __________________, Bangalore CONTRACT VALUE : __________ (Incl. Taxes)
NAME OF OWNER : M/s ___________Developers LLP GST No. : ____________-Z7
NHDL GST No : _________ PAN No. : _________35C
Deductions
11 Adhoc Payment (on '9') - - -
12 TDS @ 2% (on '7') 547,047 547,047
13 Retention Money / Security Amount @ 5% (on '6') - 1,367,618 1,367,618
14.a Mobilisation Advance (Recovery Sheet Enclosed) 9,540,703 9,540,703
14.b T & P Advance (Recovery Sheet Enclosed) - -
15 Secured / Material Advance Recovery 900,998 900,998
16 Hold for PBG - Performance Bank Guarantee (If Not Submit)
17 Debit for Steel
18 Debit for Cement
19 Hold Others (As. PF Compliances not completed by Contractor) -
Amount In Words :
Prepared By Checked By
Conditions for GST - Goods & Service Tax Claim Contractor Cleint Location
1st Case Within State Billing (CGST 9% + SGST 9%) Haryana Haryana Haryana
2nd Case Within Inter State Billing (IGST 18%) Haryana Gujrat Haryana
3rd Case Within Inter State Billing (IGST 18%) Haryana Gujrat Gujrat /Maharastra
For 3rd Case Client need to register GST No. for (Gujrat / Maharastra) for material purchase tax input credit in ITR
NAME OF CONTRACTOR : M/s________- Private Limited RUNNING BILL NO. : RA Bill No.
NAME OF PROJECT : _______- A High-Rise Residential Tower (2B+G+24 F) PERIOD OF MEASURMENT : Upto _________
NATURE OF WORK : Civil & Structure Work DATE OF SUBMISSION : __/__/2021
LOCATION : __________________, Bangalore CONTRACT VALUE : __________ (Incl. Taxes)
NAME OF OWNER : M/s ___________Developers LLP GST No. : ____________-Z7
NHDL GST No : _________ PAN No. : _________35C
Deductions
11 Adhoc Payment (on '9') - - -
12 TDS @ 2% (on '7') 226,539 226,539
13 Retention Money / Security Amount @ 5% (on '6') - 1,132,696 1,132,696
14.a Mobilisation Advance (Recovery Sheet Enclosed) 9,540,703 9,540,703
14.b T & P Advance (Recovery Sheet Enclosed) - -
15 Secured / Material Advance Recovery 900,998 900,998
16 Others -
Amount In Words :
Prepared By Checked By
Conditions for GST - Goods & Service Tax Claim Contractor Cleint Location
1st Case Within Within State Billing (CGST 9% + SGST 9%) Haryana Haryana Haryana
2nd Case Within Inter State Billing (IGST 18%) Haryana Gujrat Haryana
3rd Case Within Inter State Billing (IGST 18%) Haryana Gujrat Gujrat /Maharastra
For 3rd Case Client need to register GST No. for (Gujrat / Maharastra) for material purchase tax input credit in ITR
1 Mobilisation Advance - - - - - - - -
2 1st RA Bill 27,352,360 4,923,425 273,524 32,549,308 - 547,047 2,735,236 3,282,283 29,267,025 29,267,025 29,267,025
2 2nd RA Bill
Total 27,352,360 - - - - - - -
M/s. Nestled Haven Developers LLP. Payment Status M/s. TJN Construction Private Limited
MOBILIZATION ADVANCE RECOVERY
NAME OF CONTRACTOR : M/s________- Private Limited RUNNING BILL NO. : RA Bill No.
NAME OF PROJECT : _______- A High-Rise Residential Tower (2B+G+24 F) PERIOD OF MEASURMENT : Upto _________
NATURE OF WORK : Civil & Structure Work DATE OF SUBMISSION : __/__/2021
LOCATION : __________________, Bangalore 0
NAME OF OWNER : M/s ___________Developers LLP GST No. : ____________-Z7
Description Amount
Civil & Structure Works
Description Amount
Civil & Structure Works
M/s. Nestled Haven Developers LLP. Mob. Advance Recovery M/s. TJN Construction Private Limited
STATUS OF BANK GAURANTEE'S & INSURANCE
NAME OF CONTRACTOR : M/s________- Private Limited RUNNING BILL NO. : RA Bill No.
NAME OF PROJECT : _______- A High-Rise Residential Tower (2B+G+24 F) PERIOD OF MEASURMENT : Upto _________
Sr. Description of Bank Guarantee / Date of Due Date for Apply Value
Issuing Authority Document No Expiry Date
No Insurance Commencement for Renewal ( Rs.)
1 Mobilization Advance Punjab National Bank, New Delhi 30.09.2016 30.08.2016 30,000,000
4 W.C.Policy
M/s. Nestled Haven Developers LLP BG Status M/s. TJN Construction Private Limited
SUMMARY OF CIVIL& STRUCTURE WORKS
PROJECT - ______________________________________-, BANGALORE
NAME OF CONTRACTOR : M/s________- Private Limited RUNNING BILL NO. : RA Bill No.
NAME OF PROJECT : _______- A High-Rise Residential Tower (2B+G+24 F) PERIOD OF MEASURMENT : Upto _________
SUMMARY OF ABSTRACTS
Cumulative
Amount Upto Amount in this
SUBHEAD DESCRIPTION OF AREAS Amount Till Date
Previous Bill (Rs.) Bill (Rs.)
(Rs.)
1 SITE DEVLOPMENT AND EARTH WORK - 258,438 258,438
5 FLOORING WORKS - - -
7 FINISHING WORKS - - -
8 MISCELLANEOUS - - -
9 DISMANTLING WORK - - -
M/s. Nestled Haven Developers LLP Summary - Abstract M/s TJN construction Private Limited
Bill Of Quantities Price Schedule
ABSTRACT
CIVIL AND STRUCTURAL WORKS FOR CONSTRUCTION OF "________________"
SECTOR-____, __________ GURGAON ( HARYANA )
(Tower 1B+GF+14)
1.1.1 All kinds of soils for all leads and lifts cum. 1345 115 0.00 819.64 819.64 94,259 94,259
For horizontal area (plinth area at ground floor level will be measured and paid for
a. sqm. 850 110 651.07 651.07 71,618 71,618
)
1.8 Dewatering 0
Dewatering of basement excavation with Pump ( the quoted rate shall including Per
providing detail design and getting it approved from the Architect / PMC,all piping, hour/per
equipments, running cost like disel, operators etc. all required for total operation.) 0 18
Horse
Power
1.9 Soling 0
Providing, laying, ramming and compacting dry rubble stone hardcore /soling in
required consolidated 100mm thickness in sub base to required levels and lines
with first quality rubble of 90-45mm in stone aggregate including stone screening
13.2mm size and finishing /blinding the surfaces with murrum including watering,
a. Sqm 13 240 624.23 624.23
consolidated in layers of 30 cm with vibratory compactor etc. complete as per
specifications, drawings and as directed by the Project Manager.
(Rates for all cement concrete items plain and reinforced described below shall
include work from lowest Basement to top of last roof including roof of machine
room, mumty, overhead tanks and parapets above. This section covers cast in
0
situ structural and architectural as well as precast structural and architectural
concrete.) Note :- Contractor shall use Marble Powder and Mechanical
grinder in repairing joints and honeycombs if required.
2.1 Plain cement concrete 0
Providing and laying plain cement concrete of specified grade as bed concrete
under foundation, bases for rafts, underground water tank, building machine
equipments, column footing, under floor landings, below road and pathways,cill,
2.1.1 coping, screeding at roof to required slope and other locations as called for laid, 0
consolidated and cured etc. complete including finishing the top surface to receive
the next course / layer as per specification and drawing excluding the cost of
centering and shuttering.
Providing & laying cast - in - place structural controlled design mix cement
concrete of M25 grade using pump with 20mm down gauge coarse aggregates
excluding cost of centering, shuttering and steel reinforcement but including cost
of making shear keys and provision of construction / control joints in various
locations, laid, consolidated and cured, item to include all structural items like
base raft, ramp, column, column capitals, wall, footings, equipment foundations, 0
fins, mullions, beams, lintels, pergola, chajja, facia, parapet, railing, slab,
trenches, drains and sumps etc. of any shape and sizes. The rates of concrete to
include the cost of Fly ash /admixtures / plasticisers/superplasticers/ bonding
agent to achieve specified strength and to facilitate pumpable concrete etc
complete for all height and level.
Foundation, raft slab, raft beams, plinth beam, lift pits, sump pits, pedestals /
2.3.1 bases of coloum, wall foundations grade slab etc. cum 1335 6750 214.27 214.27 1,446,323 1,446,323
Suspended floors, roofs, balconies, shelves/ counters, stair waist slabs, folded
plate stairs and landings, lintel and floor beams, girders (deep beams), RCC
2.3.2 cum 3127 6980 291.10 291.10 2,031,844 2,031,844
bands, cantilever projections, slab of tank, arches, other non-structural elements
etc.
Columns, pillars, piers, abutments, posts and struts,wall, offset and projection of
2.3.3 cum 913 7410 63.02 63.02 466,975 466,975
columns, etc.
2.3.4 Retaining Walls, water tank wall, shear wall, lift wall (any thickness) cum 694 7080
Parapets, planters, facias, fins, vertical projection of balconies, pergolas, copings,
2.3.5 cills etc. (for all heights as shown in the drawing) cum 47 7950 42.44 42.44 337,407 337,407
Extra for add or deduct for using Richer or leaner mix in place of M-25
2.4 0
Concrete.
2.4.1 M-30 instead of M-25 cum 157 180
2.4.2 M-35 instead of M-25 cum 180 235
2.4.3 M-40 instead of M-25 cum 300 265 63.02 63.02 16,700 16,700
2.4.4 M-45 instead of M-25 cum 20 310
2.4.5 M-50 instead of M-25 cum 0 550
Project:________________ 9 of 54
Bill Of Quantities Price Schedule
(Tower 1B+GF+14)
Allow for forming grooves, drip course, chamfers, cut-outs, openings etc. where
called for and for dressing with approved shuttering oil to prevent adhesion.
Unexposed concrete surfaces subsequently left untreated (in the condition
obtained on removal of form work) shall not constitute exposed concrete work and
shall be measured under this item only. Irregular shapes with sides which may not
be perpendicular to each other for shapes not conforming to rectangle or square 0
shall not be paid separately. including cost of shuttering and staging material
(quoted rate to include all staging upto any height).
Foundation, raft slabs, raft beams, plinth beam, pedestrals/ bases of columns
a. sqm 636 475 472.09 472.09 224,240 224,240
grade slab etc.
b. Retaining Walls, water tank wall, shear wall and lift wall (any thickness) sqm 5228 450 0.00
Suspended floors, roofs, landings, balconies, stairs and landings, slabs of water
c. tank, ramp slabs, lintels, beams, floor beams, girders, cantilever beams, deep sqm 24404 495 1944.78 1944.78 962,664 962,664
beams, ramp beams, arches etc..
Columns, pillars, piers, abutments, posts and struts, offset and projection of
d. sqm 8872 510 473.16 473.16 241,314 241,314
columns, etc.
e. Shelves in kitchen/ pantries and toilets etc sqm 0 400 0.00 - -
Parapets, Planters, vertical fins, balcony facias, projections, pergolas as per the
f. sqm 108 545 363.01 363.01 197,840 197,840
shape and profiles indicated in the drawings.
Extra over item no. a to f above for circular, semi circular vertical surfaces for all
sizes upto a mean radius not exceeding 1 meters. (shuttering for curved surfaces
g. with radius greater than 1 meter shall be treated as flat shuttering and paid under sqm 0 200
respective items).
Providing and Laying and fixing in position steel reinforcement ( Fe 500 ) in all
reinforced concrete work, including straightening, cutting, removal of loose rust by
wire brush and coating with cement slurry, bending, hoisting, laying in position to
the shape and profile required at all levels and heights as per drawing and design
and/ or as directed, The rate shall include cost of binding wire and fixing of 0
couplar and chairs, spacers which will not be measured separately for
payment. Quantity of steel as per drawing and with authorised overlaps only shall
be measured and paid for. ( Only Reinforcement steel and couplar will be
supplied free of cost by Client)
3 MASONARY WORK 0
(Quoted Rates are for all heights, all depths, all levels, including basement to roof
(mumty) & all leads and lifts, including racking curved or circular masonary work, 0
racking of brick work should be 10mm)
ALTERNATE ITEM: 0
Providing and laying flyash brick work using two hours fire rated flyash bricks in
super structure above plinth level in cement mortar 1:6 ( 1 cement : 6 coarse sand
3.2.1 a ) including, curing, joints finished flush/raked to 12 mm depth,scaffolding cum. 0
etc.complete as directed by PM.
Same as item no. 3.2 (a.) above but using machine made bricks in place of
3.3 cum. 0 3900
FPS bricks
ALTERNATE ITEM: 0
Providing & laying Flyash brick work using two hours fire rated flyash bricks in half
bricks walls in super structure above plinth level in cement mortar 1:4 ( 1
cement :4 coarse sand ) including joints finished flush/raked to 6 mm depth as
work proceeds including steel reinforcement (2 Nos of 6mm dia ) at every fourth
3.4.1 a course, cleaning and soaking the bricks at least for 6 hours before use, curing for sqm 0
7 days etc. complete at all heights / depth and for all leads.(MS Reinforcement to
be provided by the Contractor within the quoted rates). complete as directed by
PM.
4 WATER PROOFING 0
(Quoted Rates are for all heights, depths, levels, leads and lifts)
The operations describe below are only indicative & the item is to be executed as
per technical/ manufacturer's specification. 0
Testing shall be done by ponding water (150mm depth) for 72 hours.
Note: (The Water proofing work must be executed by an approved specialised
Agency. The Contractor shall give a 10 years guarentee as per instruction of the 0
Project Manager).
4.1 Tapecrete water proofing 0
Providing and laying composite built up waterproofing in the toilets/ kitchen/
pantry etc. comprising of three coats of Tapecrete or equivalent polymer, each
coat admixed with cement in the proportion 1:2 (one part tapcrete and two parts
cement) over a primer coat of neat cement sturry admixed with impermeable
chemical CH-9. After the second coat of tapecrete, all corners, edges, joints of
pipes with concrete / masonry should be sealed with epoxy putty. The 0
waterproofing treatment is to be laid underneath all sanitary pipes on the base
and taken up onto the verticals upto a level of minimum 300mm above the
finished toilet floor level including providing and fixing of PVC spout.
12mm thick protective plaster 1:4 (1 cement : 4 coarse sand) over treated surface
4.1.1 etc complete. (Quoted rate to include grouting of RCC surface for any cracks/ sqm. 1927 400 29.48 29.48 11,791 11,791
fissures)
Providing on top of slab surface cement slurry mixed with water proofing
compound thereafter providing cement mortar 1:4 (1 cement : 4 coarse sand)
20mm thick with polymer based water proofing compound and layer of new half
broken bricks (coba) giving gaps of 15-20mm between broken bricks, providing
necessary gradient for proper flow of water and providing cement slurry with water
proofing compound spread over brick bat coba in cement mortar 1:4 (1 cement : 4
coarse sand) with water proofing compound filled in gaps of broken bricks and 0
20mm plaster in cement mortar 1:4 (1 cement : 4 coarse sand) mixed with
polymer based water proofing compound, top finished smooth with neat cement
and providing rope chequers including extending the water proof plaster 300mm
on vertical surfaces with necessary chasing / treating of walls including providing
and making gola as per drawing etc. Average thickness of the brick bat coba to
be avg. 125mm.
The item also include providing and making khurrahs 450mm x 450mm with
average minimum thickness of 50mm cement concrete 1:2:4 (1 cement : 2 coarse
sand : 4 graded stone aggregate of 20 mm nominal size) finished with aluminium
sqm 755 1230 657.17 657.17 808,325 808,325
foil and 12mm cement plaster 1:3 (1 cement : 3 coarse sand) and a coat of neat
cement rounding the edges and making and finishing the outlet complete. (Plan
area will be measured and paid)
Project:________________ 10 of 54
Bill Of Quantities Price Schedule
(Tower 1B+GF+14)
4.3.1 Add or deduct for extra or less thickness of brick bat coba waterproofing cum 0 2854
Total : 5 : -
Applicator basic rate with material Rs. 150 /- per sqm. For external finish
7.3.1 sqm 11048 225
excluding the cost of scaffolding
Total : 7 : 0
8.0 MISCELLANEOUS 0
(Quoted Rates are for all heights, depths, levels, leads and lifts) 0
8.1 Structural Steel 0
Supplying, fabricating, assembling, hoisting / erecting and fixing in position at all
heights and with all leads, structural steel works of MS rolled sections (angle,
channel, beams, flats, tees, insert plates, bolts etc.) all as per structural drawings
0
and as per detailed specifications (for materials & workmanship) in the situations
described hereinafter including:
Project:________________ 11 of 54
Bill Of Quantities Price Schedule
(Tower 1B+GF+14)
Extra over item 8.3.1 of rolling shutter for providing MS flexible grill of 8mm dia
8.3.2 round bars. (The area of flexible grill provided shall be measured for payment) sqm. 0 500
8.5 MS Rungs 0
Providing and fixing in position the PVC coated MS steps of size 300 X 150 mm
for UG Sump and OH Tank including placing 150 mm inside concrete ( while
8.5.1 doing the form work ), aligning during concreting, grouting the junction if required. each 31 300
8.6.1 Dumb bell with central bulb (150mm wide, 6mm thick) rmt 0 254
8.6.2 as above but 230 mm wide & 9mm thick. rmt 0 363
8.6.3 as above but 300 mm wide & 9mm thick. rmt 0 497
8.7 Expansion joint AND CORE CUTTING 0
Providing and fixing armour board for expansion joints between column, beam,
8.7.1 slab and walls etc. as per manufacturers specification and recommendation. 0
Project:________________ 12 of 54
Bill Of Quantities Price Schedule
(Tower 1B+GF+14)
Service Tax 0
Net Total 0
Project:________________ 13 of 54
CEMENT RECONCILATION
PROJECT - ______________________________________-, BANGALORE
NAME OF CONTRACTOR : M/s________- Private Limited RUNNING BILL NO. : RA Bill No.
NAME OF PROJECT : _______- A High-Rise Residential Tower (2B+G+24 F) PERIOD OF MEASURMENT : Upto _________
NATURE OF WORK : Civil & Structure Work DATE OF SUBMISSION : __/__/2021
LOCATION : __________________, Bangalore CONTRACT VALUE : __________ (Incl. Taxes)
NAME OF OWNER : M/s ___________Developers LLP GST No. : ____________-Z7
As Theoretical As Actual
Total Received
Till date 10.10.20__ Issued for Misc. Non Billed Work Physical Balance
Theoretical Work in Theortical Total consumed as
S.No Type of Cement (Bag) in Store
Consumption Progress Mobilization work Misc Work Balance per store record
13.10.2019
1 2 3 4 5 6=1-(2+3+4+5) 7 As Actual
Cement Coeff as
Total Theoretical
BOQ item per DSR / Design Remarks
Description of Item Unit Previous Qty This Bill Qty Total Qty Qty of OPC Cement
No Mix
Bags/unit Bags
M/s M/s. Nestled Haven Developers LLP. Cement Reconciliation,Page-14 M/s TJN Construction Private Limited
Parapets, planters, facias, fins, vertical projection of balconies,
2.3.5
pergolas, copings, cills etc. (for all heights as shown in the drawing)
Cum 0.00 42.44 42.44 6.80 289
MASONARY WORK
Brick masonry of thickness 230 mm in cement mortar 1:6 (1 cement :6
3.2.1
coarse sand) mix.
Cum 0.00 188.93 188.93 1.25 236
3.4.1 Half brick masonry in cement mortar 1:4 (1 cement : 4 coarse sand) Sqm 0.00 104.83 104.83 0.2128 22
WATER PROOFING
4.1 Tapecrete water proofing Sqm 0.00 29.48 29.48 0.23 6.85
4.3 Terrace Brick bat coba waterproofing Sqm 0.00 657.17 657.17 0.77 509
PLASTERING WORKS
Internal Plaster
Ceiling Plaster
6mm thick plaster to RCC slab in cement mortar 1:3 (1 cement : 3 fine
6.2
and coarse sand in equal proportion)
Sqm 0.00 70.62 70.62 0.12 8.29
M/s M/s. Nestled Haven Developers LLP. Cement Reconciliation,Page-15 M/s TJN Construction Private Limited
Measurement Sheet DATE : 14.08.2021
PROJECT CODE: _______ FORMAT NO : F-02/___
__________________- FACTORY, BID DADRI VILLAGE, ___________-R -(HARYANA)
S. No. Description of Item UNIT Nos L B H Qty. Remarks
Item Code : 410
1 SITE DEVLOPMENT AND EARTH WORK
1.1 Excavation over areas from natural ground level
Earth work in excavation by mechanical means over areas from
existing natural ground level and stacking the excavated material
within the site or adjacent plots (within 500 m radius) including
dressing of bottom, sides strutting, timbering, shoring, trimming of
sides dewatering, all leads and lifts, incidentals, etc. complete with
ramming of bottom, surface preparation as per specifications to
receive the PCC. Excavation shall be payable only for vertical cut up
to the outer edge of foundation lean concrete as indicated in
drawings for all depths. Cost of extra excavation required for
working space, supporting side shuttering of foundations and
retaining walls and that required for making slopes for stability of
excavation shall be deemed to be included in the rate quoted. (Note:
The Line & levels in the drawings shall be strictly followed and the
rate shall be inclusive for all depths.)
PB1 (330 x 600) mm Grid A,C/1-2,5-6 Cum 4 3.350 0.430 0.515 2.967
PB5 (300 x 600)mm Grid B/1-2,5-6 Cum 2 2.700 0.400 0.515 1.112
PB2 (330 x 600)mm Grid A,C/2-3 Cum 2 3.100 0.430 0.515 1.373
PB6 (330 x 600)mm Grid B/2-3 Cum 1 2.100 0.430 0.515 0.465
PB6 (330 x 600)mm Grid A,C/3-4, 4-5 Cum 4 3.000 0.430 0.515 2.657
PB7 (330 x 1000)mm Grid B/3-4 Cum 1 2.100 0.430 0.915 0.826
PB8 (330 x 600)mm Grid B/4-5 Cum 1 2.100 0.430 0.515 0.465
PB11 (330 x 600)mm Grid A-C/1 Cum 2 6.930 0.430 0.515 3.069
PB16 (300 x 600) mm Grid A-C/2,5 Cum 2 6.800 0.400 0.515 2.802
PB16 (330 x 600) mm Grid A-C/3,4 Cum 2 6.600 0.430 0.515 2.923
PB17 (330 x 600)mm Grid A-C/6 Cum 1 8.000 0.430 0.515 1.772
d)
PI Building Unit-B
1.9 Soling
d)
PI Building Unit-B
(Rates for all cement concrete items plain and reinforced described
below shall include work from lowest Basement to top of last roof
including roof of machine room, mumty, overhead tanks and
parapets above. This section covers cast in situ structural and
architectural as well as precast structural and architectural
concrete.) Note :- Contractor shall use Marble Powder and
Mechanical grinder in repairing joints and honeycombs if required.
c)
PI Building Unit -B
PI Building - Unit B
Plinth Beams
PB1 (330 x 600) mm Grid A,C/1-2,5-6 Cum 3 6.700 0.430 0.075 0.648
PB1 (330 x 600) mm Grid C/5-6 Cum 1 6.500 0.430 0.075 0.210
PB5,PB9 (300 x 600)mm Grid B/1-2,5-6 Cum 2 6.700 0.400 0.075 0.402
PB2 (330 x 600)mm Grid A,C/2-3 Cum 2 6.700 0.430 0.075 0.432
PB6 (330 x 600)mm Grid B/2-3 Cum 1 6.700 0.430 0.075 0.216
PB6 (330 x 600)mm Grid A,C/3-4, 4-5 Cum 4 6.700 0.430 0.075 0.864
PB7 (330 x 1000)mm Grid B/3-4 Cum 1 6.700 0.430 0.075 0.216
PB8 (330 x 600)mm Grid B/4-5 Cum 1 6.700 0.430 0.075 0.216
PB11 (330 x 600)mm Grid A-C/1 Cum 1 15.000 0.430 0.075 0.484
PB16 (300 x 600) mm Grid A-C/2,5 Cum 2 15.000 0.400 0.075 0.900
PB16 (330 x 600) mm Grid A-C/3,4 Cum 2 15.000 0.430 0.075 0.968
PB17 (330 x 600)mm Grid A-C/6 Cum 1 14.800 0.430 0.075 0.477
PB3, PB4 (330 x 600) Staicase Beam Cum 2 2.400 0.430 0.075 0.155
PB10 (300 x 600) Staircase Beam Cum 1 6.280 0.330 0.075 0.155
Foundation, raft slab, raft beams, plinth beam, lift pits, sump pits,
2.3.1 pedestals / bases of coloum, wall foundations grade slab etc.
PI Building - Unit B
Plinth Beams
PB1 (330 x 600) mm Grid A,C/1-2,5-6 Cum 3 6.700 0.330 0.600 3.980
PB1 (330 x 600) mm Grid C/5-6 Cum 1 6.600 0.330 0.600 1.307
PB5,PB9 (300 x 600)mm Grid B/1-2,5-6 Cum 2 6.700 0.300 0.600 2.412
PB2 (330 x 600)mm Grid A,C/2-3 Cum 2 6.700 0.330 0.600 2.653
PB6 (330 x 600)mm Grid B/2-3 Cum 1 6.700 0.330 0.600 1.327
PB6 (330 x 600)mm Grid A,C/3-4, 4-5 Cum 4 6.700 0.330 0.600 5.306
PB7 (330 x 1000)mm Grid B/3-4 Cum 1 6.700 0.330 1.000 2.211
PB8 (330 x 600)mm Grid B/4-5 Cum 1 6.700 0.330 0.600 1.327
PB11 (330 x 600)mm Grid A-C/1 Cum 1 15.000 0.330 0.600 2.970
PB16 (300 x 600) mm Grid A-C/2,5 Cum 2 15.000 0.300 0.600 5.400
PB16 (330 x 600) mm Grid A-C/3,4 Cum 2 15.000 0.330 0.600 5.940
PB17 (330 x 600)mm Grid A-C/6 Cum 1 14.900 0.330 0.600 2.950
PB3, PB4 (330 x 600) Staicase Beam Cum 2 2.330 0.330 0.600 0.923
PB10 (300 x 600) Staircase Beam Cum 1 6.580 0.330 0.600 1.303
c)
PI Building (Unit- B)
a) PI Building (Unit- B)
Staircase Beam B-C/1' B12 230x600 Cum 1 6.280 0.230 0.600 0.867
Beam 1-2,2-3 & 5-6/A-C B14&14A 300x600 Cum 3 15.510 0.300 0.600 8.375
Beam 3 & 4/A-A' B17 300x600 Cum 2 9.550 0.300 0.600 3.438
Roof Beam A/1-2 RB1 300X750 Cum 1 6.700 0.330 0.750 1.658
Roof Beam C/1-2 RB1 300X600 Cum 1 6.700 0.330 0.600 1.327
Roof Beam A/2-5 RB2 300X750 Cum 1 20.100 0.330 0.750 4.975
Roof Beam C/2-5 RB2 300X600 Cum 1 20.100 0.330 0.600 3.980
Roof Beam A/5-6 RB1A 300X750 Cum 2 6.700 0.330 0.750 3.317
Roof Beam C/5-6 RB1A 300X600 Cum 2 6.700 0.330 0.600 2.653
Roof Beam B/1-2 RB5 300X670 Cum 1 6.400 0.300 0.675 1.296
Roof Beam B/2-3 RB6 300X670 Cum 1 6.400 0.300 0.675 1.296
Roof Beam B/3-4 RB7 300X670 Cum 1 6.400 0.300 0.675 1.296
Roof Beam B/4-5 RB8 300X670 Cum 1 6.400 0.300 0.675 1.296
Roof Beam B/5-6 RB9 300X670 Cum 1 6.400 0.300 0.675 1.296
Roof Beam 2,4,5/A-C RB 13& RB 13A 300X (750 slope 600) Cum 3 15.000 0.300 0.675 9.113
Roof Beam Grid 1 /A-C RB11 Cum 1 15.000 0.330 0.675 3.341
Roof Beam Grid 6 /A-B RB11 Cum 1 5.500 0.500 0.675 1.856
Roof Beam Grid 6/B-C RB11A Cum 1 7.500 0.330 0.675 1.671
Roof Beam Grid 3/A-B RB13A Cum 1 7.500 0.330 0.675 1.671
Roof Beam Grid 3/A-B RB13A Cum 1 7.500 0.330 0.675 1.671
Roof Beam 1-6/A-C RB12 & RB12A 300X600 Cum 5 15.510 0.300 0.670 15.588
Ground Floor
First Floor
Stair case Parapet Tie Beam 150mm Cum 1 9.800 0.230 0.150 0.338
Handwash Wall Anchor Beam Female (230x300) Cum 1 1.820 0.230 0.300 0.126
Handwash Wall Anchor Beam Male (230x300) Cum 1 2.145 0.230 0.300 0.148
Counter Slabs
Handwash Wall Anchor Beam Female (230x300) Cum 1 1.875 0.230 0.300 0.129
Handwash Wall Anchor Beam Male (230x300) Cum 1 1.825 0.230 0.300 0.126
Counter Slabs
c)
Office Building Unit B
Parapet Wall Ist Floor Grid A/3-4 Cum 1 6.660 0.330 0.920 2.022
Grid B/3-4 RCC Wall For Staircase Cum 1 6.700 0.230 2.800 4.315
PI Building - Unit B
Plinth Beams
PB6 (330 x 600)mm Grid A,C/3-4, 4-5 Sqm 4 6.700 0.075 4.020
PB3, PB4 (330 x 600) Staicase Beam Sqm 2 2.400 0.075 0.720
Isolated Footings
Plinth Beams
PB6 (330 x 600)mm Grid A,C/3-4, 4-5 Sqm 4 6.700 0.600 32.160
PB3, PB4 (330 x 600) Staicase Beam Sqm 2 2.330 0.600 5.592
a)
PI Building (Unit- B)
2,4,5/A-C RB 13& RB 13A 300X (750 slope 600) Sqm 3 15.000 1.350 60.750
Ist Floor
Ground Floor
First Floor
Stair case Parapet Tie Beam 150mm Sqm 1 9.800 0.300 2.940
PI Building (Unit- B)
12.4
c)
PI Office Building Unit B
Parapet Wall Ist Floor Grid A/3-4 Sqm 1 6.700 0.920 12.328
Grid B/3-4 Rcc Wall For Staircase-1 Sqm 1 6.700 2.800 37.520
Reinforcement steel
Measurement Sheet DATE : 14.08.2021
PROJECT CODE: _______ FORMAT NO : F-02/___
__________________- FACTORY, BID DADRI VILLAGE, ___________-R -(HARYANA)
S. No. Description of Item UNIT Nos L B H Qty. Remarks
Misc. Steel Quantity as per JMR & Pour Cards Details MT 0.599
MASONARY WORK
(Quoted Rates are for all heights, all depths, all levels, including
basement to roof (mumty) & all leads and lifts, including racking
curved or circular masonary work, racking of brick work should be
10mm)
b)
PI Office Building (Unit -B)
Ground Floor
Less Grid 4-5 (Beam Depth750mm) Cum -1 6.700 0.230 0.150 -0.231
Under Staircase Floor to 1st Landing Cum 1 3.300 0.230 0.795 0.603
First Floor
Ground Floor
First Floor
4 WATER PROOFING
(Quoted Rates are for all heights, depths, levels, leads and lifts)
The operations describe below are only indicative & the item is to be
executed as per technical/ manufacturer's specification.
Testing shall be done by ponding water (150mm depth) for 72 hours.
PLASTERING WORKS
(Quoted Rate shall be for all heights, depths, levels, leads and lifts
and to include providing and fixing chicken wire mesh in junction
RCC and brick / AAC Block walls etc for internal and external plaster
works).
Internal Plaster
Ground Floor
Add For Jambs and Soffits Sqm 1 1.800 2.100 0.270 1.620
First Floor
Parapit Wall top Side 270mm 2 Times Extra not Paid Sqm 1 105.080 0.270 28.372
Ground Floor Stair Case -2 Sqm 1 7.000 2.400 16.800 Incl. Landing Area
Entrance Hall Staircase -1 Sqm 1 6.700 1.370 9.179 Incl. Landing Area
External Plaster
6.3 20 mm cement plaster in two layer -External Plaster
Measurement Sheet DATE : 14.08.2021
PROJECT CODE: _______ FORMAT NO : F-02/___
__________________- FACTORY, BID DADRI VILLAGE, ___________-R -(HARYANA)
S. No. Description of Item UNIT Nos L B H Qty. Remarks
Providing and applying 18 mm thick plastering on external walls,
columns, beams , pergola beams and any projections, plaster bands
as per drawing etc. in two layers base layer 12 mm thick of cement
mortar 1:5 (1 Cement : 5 coarse sand) and top layer 6 mm thick 1:3
( 1 cement : 3 fine sand) including cost of mixing water proof
compound to be applied for both coats, finished to line and level,
including all leads, lifts, scaffolding and curing complete. The rate is
inclusive of forming of drip moulds as with all lead and lift and as
directed by Engineer in charge including providing and fixing in
position galvanised expanded metal mesh 20 gauge at junctions of
concrete and masonry and other locations as called for including
fixing with GI nails. Fixing approved column / , plaster band and
cornices as called for etc., complete at all levels
NAME OF CONTRACTOR : M/s________- Private Limited RUNNING BILL NO. : RA Bill No.
NAME OF PROJECT : _______- A High-Rise Residential Tower (2B+G+24 F) PERIOD OF MEASURMENT : Upto _________
NATURE OF WORK : Civil & Structure Work DATE OF SUBMISSION : __/__/2021
LOCATION : __________________, Bangalore 0
NAME OF OWNER : M/s ___________Developers LLP GST No. : ____________-Z7
MS Structural Steel
Granite Stone
Tile Flooring
Tile Cladding
Total Amount - 509,063 509,063
M/s. Nestled Haven Developers LLP Abstract - BRV M/s TJN Construction Private Limited
ABSTRACT - ESCALATION
Labour Escalation
POL Escalation
Cement Escalation
Bitumin Escalation
Total Amount -
TJN's Representative
T - ESCALATION
____________________-, BANGALORE
CLAIM SUMMARY
This Bill Cummulative Remarks
899,596 899,596
63,515 63,515
963,112 963,112
NHDL's Representative
BASIC RATE VARIATION CALCULATION
PROJECT - ______________________________________-, BANGALORE
NAME OF CONTRACTOR : M/s________- Private Limited RUNNING BILL NO. : RA Bill No.
NAME OF PROJECT : _______- A High-Rise Residential Tower (2B+G+24 F) PERIOD OF MEASURMENT : Upto _________
NATURE OF WORK : Civil & Structure Work DATE OF SUBMISSION : __/__/2021
LOCATION : __________________, Bangalore 0
NAME OF OWNER : M/s ___________Developers LLP GST No. : ____________-Z7
Total Material Recd upto This Bill 22350 250.00 5,587,500 270.99 6,056,720 469,220
M/s. Nestled Haven Developers LLP Basic Rate - Calculation M/s TJN Construction Private Limited
As Per Tender As Per Actual
S.No Bill / PI Date Name of Supplier Bill No Unit Qty Difference
Rate Amount Rate Amount
5/14/2021 JSW Xyz MT 28.500 47000 1,339,500 51650 1,472,025 132,525
5/14/2021 JSW Xyz MT 30.500 47000 1,433,500 53680 1,637,240 203,740
5/14/2021 TATA Steel Xyz MT 27.850 47000 1,308,950 49650 1,382,753 73,803
Total Material Recd upto This Bill 86.850 47000 4,081,950 51721.56 4,492,018 410,068
M/s. Nestled Haven Developers LLP Basic Rate - Calculation M/s TJN Construction Private Limited
M/s. Nestled Haven Developers LLP Basic Rate - Calculation M/s TJN Construction Private Limited
SECURED ADVANCE (Clause 38.2)
NAME OF CONTRACTOR : M/s________- Private Limited RUNNING BILL NO. : RA Bill No.
NAME OF PROJECT : _______- A High-Rise Residential Tower (2B+G+24 F) PERIOD OF MEASURMENT : Upto _________
NATURE OF WORK : Civil & Structure Work DATE OF SUBMISSION : __/__/2021
LOCATION : __________________, Bangalore 0
NAME OF OWNER : M/s ___________Developers LLP GST No. : ____________-Z7
NHDL GST No : _________ PAN No. : _________35C
Average Rate
Schedule of Non Perishable Secured Advance
S.No Bill Date Invoice No. Unit Delivered Payment Rate
Material's List Actual 75% of Actual
Qty 55% of BOQ Taken as per
BOQ Rate Procurement Procurement
Rate Agreement
Rate Rate
1 Reinforcement Steel 14.05.2021 Xyz01 MT 28.500 78500 43175 48650 36488 1,039,894
2 Reinforcement Steel 17.05.2022 Xyz02 MT 31.650 78500 43175 50530 37898 1,199,456
2 Reinforcement Steel 29.05.2022 Xyz03 MT 26.700 78500 43175 47650 35738 954,191
4 Tile Cladding / Dado Sqm 214.6 1630 896.5 530 397.5 85,304
Alpha Pecific Engineers Pvt Ltd Secured Advance Claim,Page-41 M/s Alpha Corp Devlopment Pvt Ltd
Secured Advance Recovery In This Bill
This Bill
Alpha Pecific Engineers Pvt Ltd Secured Advance Claim,Page-42 M/s Alpha Corp Devlopment Pvt Ltd
Diawise Steel :- 43
a Tower Area Raft Foundation G+31 Tower MT 0.000 1.117 2.125 0.458 2.980 48.573 4.861 186.231 246.35 246.346
b Iso lated Footings +Pedestals G+8 Tower MT 0.568 0.327 2.371 8.086 0.000 5.031 0.185 0.000 16.57 16.568
c Iso lated Footings +Pedestals Non tower MT 6.789 11.910 3.441 3.111 2.678 0.000 0.000 0.000 27.93 27.929
f Retaining Wall MT 15.966 34.297 35.759 13.658 0.000 0.000 0.000 0.000 99.68 99.680
1 G+31 Tower MT 125.954 168.867 27.859 63.109 39.525 83.145 38.641 50.700 597.80
2 G+8 Tower MT 28.802 2.341 5.682 18.956 12.368 19.192 10.135 1.643 99.12 719.069
3 Non Tower Area Columns MT 5.007 0.000 0.000 3.312 4.473 2.453 4.500 2.406 22.15
Basement -2 Beam & Slab Tower Area MT 2.011 0.181 0.377 2.888 1.741 0.498 - - 7.69
1 30.700
Basement -2 Beam & Slab Non Tower Area MT 2.97 5.57 1.41 4.54 5.64 2.88 - - 23.01
Basement -1 GF Beam & Slab Tower Area MT 0.57 11.31 1.08 0.48 5.44 5.30 1.99 1.18 27.35
2 107.581
Basement -1 GF Beam & Slab NonTower Area MT 1.31 31.81 6.42 0.78 6.31 13.82 11.37 8.41 80.23
3 Ground Floor Roof MT 0.87 8.65 1.14 2.34 3.64 3.60 1.45 - 21.68 21.677
4 1st floor Roof MT 0.87 8.65 1.14 2.34 3.64 3.60 1.45 - 21.68 21.677
5 2nd floor Roof MT 0.87 8.65 1.14 2.34 3.64 3.60 1.45 - 21.68 21.677
6 3rd floor Roof MT 0.87 8.65 1.14 2.34 3.64 3.60 1.45 - 21.68 21.677
7 4th floor Roof MT 0.87 8.65 1.14 2.34 3.64 3.60 1.45 - 21.68 21.677
8 5th floor Roof MT 0.87 8.65 1.14 2.34 3.64 3.60 1.45 - 21.68 21.677
9 6th floor Roof MT 0.87 8.65 1.14 2.34 3.64 3.60 1.45 - 21.68 21.677
10 7th floor Roof MT 0.87 8.65 1.14 2.34 3.64 3.60 1.45 - 21.68 21.677
11 8th Floor & G+8 Terrace & Pool deck Slab Area MT 0.87 8.65 1.14 2.34 3.64 3.60 1.45 - 21.68 21.677
13 9th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
14 10th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
15 11th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
16 12th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
17 13th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
18 14th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
19 15th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
20 Service Floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
21 16th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
22 17th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
23 18th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
24 19th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
25 20th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
26 21st floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
27 22nd floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
28 23rd floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
29 24th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
30 25th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
31 26th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
32 27th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
33 28th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
34 29th floor MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
35 Lower Pant House MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
36 Upper Pant House/Terrace Floor Slab MT 0.28 4.37 0.53 0.84 1.72 1.68 1.45 - 10.88 10.880
37 Machine Room & Mumty MT 0.08 1.31 0.16 0.25 0.52 0.50 0.43 - 3.26 3.264
40 U.G. Water Tank MT 0.000 1.333 5.459 14.793 0.000 0.000 0.000 0.000 21.59 21.586
Grand Total :- 240.271 473.150 115.151 187.625 177.264 264.130 119.899 250.570 1828.1
Diawise Steel :- 44
Sr.
Description Unit Remarks
No. 8 mm 10 mm 12 mm 16 mm 20 mm 25 mm 28 mm 32 mm
Total
Per Sqft Steel( Kg/Sqft) 8.146
B-Block Reinforcement
Bar Bending Schedule Date:- Date : 25.04.2021
S.No. Member Bar Mark Bar Dia Shape Cutting No. of Total Unit Wt. Total Wt.
& Spacing (in mm) Length Bars Length (Kg/m) (Kg)
(mm) (mtr) 8mm 10mm 12mm 16mm 20mm 25mm 28mm 32mm Remarks
Footings Reinforcement
F-1 Bot -200 c/c 12 300 2400 300 2.964 2x13 77.064 0.888 68.433 0.00 0.00 68.43 0.00 0.00 0.00 0.00 0.00
(2500x2500) Bot -200 c/c 12 300 2400 300 2.964 2x13 77.064 0.888 68.433 0.00 0.00 68.43 0.00 0.00 0.00 0.00 0.00
2 nos
Depth - 400
Binders 8 2400 2.400 2x4 19.200 0.395 7.584 7.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 As per JMR
F-2 Bot -125 c/c 12 300 3400 300 3.964 3x28 332.976 0.888 295.683 0.00 0.00 295.68 0.00 0.00 0.00 0.00 0.00
(3500x3500) Bot -125 c/c 12 300 3400 300 3.964 3x28 332.976 0.888 295.683 0.00 0.00 295.68 0.00 0.00 0.00 0.00 0.00
3 nos
Depth -400
Binders 8 3400 3.400 3x4 40.800 0.395 16.116 16.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00
F-3 Bot -120 c/c 12 400 3900 400 4.664 5x33 769.560 0.888 683.369 0.00 0.00 683.37 0.00 0.00 0.00 0.00 0.00
(4000x4000)
5 nos Bot -120 c/c 12 400 3900 400 4.664 5x33 769.560 0.888 683.369 0.00 0.00 683.37 0.00 0.00 0.00 0.00 0.00
Depth - 500
Binders 8 3900 3.900 5x4 78.000 0.395 30.810 30.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
F-4, F-5 Bot -100 c/c 12 400 4100 400 4.864 9x42 1838.592 0.888 1632.670 0.00 0.00 1632.67 0.00 0.00 0.00 0.00 0.00
(4200x4200)
9 nos Bot -100 c/c 12 400 4100 400 4.864 9x42 1838.592 0.888 1632.670 0.00 0.00 1632.67 0.00 0.00 0.00 0.00 0.00
Depth - 500
Binders 8 4100 4.100 9x4 147.600 0.395 58.302 58.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00
F-6 Bot -150 c/c 16 500 4900 500 5.864 3x34 797.504 1.578 1258.461 0.00 0.00 0.00 1258.46 0.00 0.00 0.00 0.00
(5000x5000)
4 nos Bot -150 c/c 16 500 4900 500 5.864 3x34 797.504 1.578 1258.461 0.00 0.00 0.00 1258.46 0.00 0.00 0.00 0.00
Depth -600
Binders 8 4900 4.900 4x4 78.400 0.395 30.968 30.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00
F-7 Bot -125 c/c 12 300 4170 300 4.734 1x28 132.552 0.888 117.706 0.00 0.00 117.71 0.00 0.00 0.00 0.00 0.00
(4270x3500)
1 nos Bot -125 c/c 12 300 3400 300 3.964 1x34 134.776 0.888 119.681 0.00 0.00 119.68 0.00 0.00 0.00 0.00 0.00
Depth -400
Binders 8 3400 3.400 1x2 6.800 0.395 2.686 2.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Binders 8 4170 4.170 1x2 8.340 0.395 3.294 3.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00
F-8 Bot -150 c/c 16 500 4500 500 5.452 1x26 141.752 1.578 223.685 0.00 0.00 0.00 223.68 0.00 0.00 0.00 0.00
(4600x3800)
1nos Bot -150 c/c 16 500 3700 500 4.652 1x31 144.212 1.578 227.567 0.00 0.00 0.00 227.57 0.00 0.00 0.00 0.00
Depth -600
Binders 8 4500 4.500 1x2 9.000 0.395 3.555 3.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Binders 8 3700 3.700 1x2 7.400 0.395 2.923 2.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00
F-9 Bot -200 c/c 12 300 1500 300 2.064 2x12 49.536 0.888 43.988 0.00 0.00 43.99 0.00 0.00 0.00 0.00 0.00
(1600x2200)
2 nos Bot -200 c/c 12 300 2100 300 2.664 2x9 47.952 0.888 42.581 0.00 0.00 42.58 0.00 0.00 0.00 0.00 0.00
Depth -400
Binders 8 1500 3.400 2x2 13.600 0.395 5.372 5.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Binders 8 2100 4.170 2x2 16.680 0.395 6.589 6.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Bot -150 c/c 10 150 650 150 0.92 1x8 7.360 0.617 4.541 0.00 4.54 0.00 0.00 0.00 0.00 0.00 0.00
Stair case
Footing
(750x1200) Bot -150 c/c 10 150 1100 150 1.37 1x5 6.850 0.617 4.226 0.00 4.23 0.00 0.00 0.00 0.00 0.00 0.00
1nos
Depth -250
920
Wall Vertical Bar-100 c/c 12 2.220 1x12 26.640 0.888 23.656 0.00 0.00 23.66 0.00 0.00 0.00 0.00 0.00
12 300
1.820 1x12 21.840 0.888 19.394 0.00 0.00 19.39 0.00 0.00 0.00 0.00 0.00
Binders Bar-100 c/c 8 2.600 1x8 20.800 0.395 8.216 8.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Retaining Wall 100
Grid 4-5/A-A' Porch Area 10 1.820 214 389.480 0.617 240.309 0.00 240.31 0.00 0.00 0.00 0.00 0.00 0.00
1450
Vetrical Bar-150c/c 300
Footing Bottom Bar -150 c/c 10 1.120 107 119.840 0.617 73.941 0.00 73.94 0.00 0.00 0.00 0.00 0.00 0.00
125 900 125
500
Chairs 10 1.230 14 17.220 0.617 10.625 0.00 10.62 0.00 0.00 0.00 0.00 0.00 0.00
95
0
30
125 125
Footing and Walll Binders 8 14415 4.776 64 305.664 0.395 120.737 120.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00
@ 150 c/c
125 125
Footing and Walll Binders 8 3400 7.326 30 219.78 0.395 86.813 86.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL QTY OF FOOTING - UNIT B MT 9.413 0.384 0.334 5.727 2.968 0.000 0.000 0.000 0.000
25 2.464 4x4 39.416 3.853 151.870 0.00 0.00 0.00 0.00 0.00 151.87 0.00 0.00
C1 (500 x500)
4 Nos 300
2200
Upto -300 mm 20 2.471 4x12 118.608 2.466 292.487 0.00 0.00 0.00 0.00 292.49 0.00 0.00 0.00
300
400
8 1.700 4x13 88.40 0.395 34.918 34.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00
400
145
20 2.464 8x14 275.912 2.466 680.399 0.00 0.00 0.00 0.00 680.40 0.00 0.00 0.00
C2 (500 x500) 300
8 Nos
Upto -300 mm
400
8 1.700 8x13 176.80 0.395 69.836 69.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
400
145
Upto -300 mm
400
8 1.700 3x13 66.30 0.395 26.189 26.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00
400
145
STRPS 150 c/c
8 1.190 3x26 92.82 0.395 36.664 36.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00
145
2200
25 2.464 2x12 59.124 3.853 227.805 0.00 0.00 0.00 0.00 0.00 227.80 0.00 0.00
C4 (500 x500)
2 Nos 300
2200
Upto -300 mm 20 2.471 2x4 19.768 2.466 48.748 0.00 0.00 0.00 0.00 48.75 0.00 0.00 0.00
300
400
8 1.700 2x13 44.20 0.395 17.459 17.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00
400
145
25 2.464 1x4 9.854 3.853 37.967 0.00 0.00 0.00 0.00 0.00 37.97 0.00 0.00
C6 (700 x700)
1 Nos 300
2200
Upto -300 mm 20 2.471 1x12 29.652 2.466 73.122 0.00 0.00 0.00 0.00 73.12 0.00 0.00 0.00
300
400
8 2.500 1x13 32.50 0.395 12.838 12.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00
210
400
25 2.464 2x10 49.270 3.853 189.837 0.00 0.00 0.00 0.00 0.00 189.84 0.00 0.00
C7 (450 x450)
2 Nos 300
2200
Upto -300 mm 20 2.471 2x6 29.652 2.466 73.122 0.00 0.00 0.00 0.00 73.12 0.00 0.00 0.00
300
350
8 1.500 2x13 39.00 0.395 15.405 15.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00
125
350
20 2.464 1x4 9.854 2.466 24.300 0.00 0.00 0.00 0.00 24.30 0.00 0.00 0.00
C8 (330 x450)
1 Nos 300
2200
Upto -300 mm 16 2.471 1x8 19.768 1.578 31.194 0.00 0.00 0.00 31.19 0.00 0.00 0.00 0.00
300
350
8 1.260 1x13 32.76 0.395 12.940 12.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00
230
85
8 0.970 1x13 12.61 0.395 4.981 4.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2200
20 2.464 2x12 59.124 2.466 145.800 0.00 0.00 0.00 0.00 145.80 0.00 0.00 0.00
C9 (230 x600) 300
2Nos
Upto -300 mm
130
19
5
8 1.360 2x13 35.36 0.395 13.967 13.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00
500
145
8 0.266 2x13 6.92 0.395 2.732 2.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL QTY OF COLUMNS UPTO PLINTH LEVEL MT 2.74 0.48 0.00 0.00 0.03 1.63 0.61 0.00 0.00
PLINTH BEAMS
PB1, PB2 Grid A,C/1-6 (330 x 600) mm 2 Nos
T & B Bars 16 300 36400 300 36.952 12 443.424 1.578 699.723 0.00 0.00 0.00 699.72 0.00 0.00 0.00 0.00
800
Overlap 16 0.800 24 19.200 1.578 30.298 0.00 0.00 0.00 30.30 0.00 0.00 0.00 0.00
Extra Top Left Support 20 300 2250 2.520 6 15.120 2.466 37.286 0.00 0.00 0.00 0.00 37.29 0.00 0.00 0.00
4800
Extra Top Right Support 20 4.800 24 115.200 2.466 284.083 0.00 0.00 0.00 0.00 284.08 0.00 0.00 0.00
Extra Top Right Support 20 2250 300 2.520 6 15.120 2.466 37.286 0.00 0.00 0.00 0.00 37.29 0.00 0.00 0.00
4540
Extra Bottom Mid Span PB1 20 4.540 8 36.320 2.466 89.565 0.00 0.00 0.00 0.00 89.57 0.00 0.00 0.00
4540
Extra Bottom Mid Span PB2 16 4.540 12 54.480 1.578 85.969 0.00 0.00 0.00 85.97 0.00 0.00 0.00 0.00
Stirrups 8 1.560 539 840.840 0.395 332.132 332.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
T & B Bars 20 300 17430 300 17.970 6 107.820 2.466 265.884 0.00 0.00 0.00 0.00 265.88 0.00 0.00 0.00
1000
Overlap 20 1.000 6 6.000 2.466 14.796 0.00 0.00 0.00 0.00 14.80 0.00 0.00 0.00
Top Alth. PB4 -PB5 Left 16 300 5240 5.516 2 11.032 1.578 17.408 0.00 0.00 0.00 17.41 0.00 0.00 0.00 0.00
4800
Extra Top Right of PB5 16 4.800 2 9.600 1.578 15.149 0.00 0.00 0.00 15.15 0.00 0.00 0.00 0.00
Extra Top Right of PB6 20 2250 300 2.520 2 5.040 2.466 12.429 0.00 0.00 0.00 0.00 12.43 0.00 0.00 0.00
Extra Bottom Mid Span PB5 12 4540 4.540 2 9.080 0.888 8.063 0.00 0.00 8.06 0.00 0.00 0.00 0.00 0.00
Extra boottom Right of PB6 12 2250 300 2.532 2 5.064 0.888 4.497 0.00 0.00 4.50 0.00 0.00 0.00 0.00 0.00
Stirrups 8 1.560 132 205.920 0.395 81.338 81.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00
T & B Bars 25 600 7430 600 8.570 6 51.420 3.853 198.121 0.00 0.00 0.00 0.00 0.00 198.12 0.00 0.00
Extra Top Left support 25 600 2250 2.813 3 8.438 3.853 32.510 0.00 0.00 0.00 0.00 0.00 32.51 0.00 0.00
Extra Bottom Mid span 20 4540 4.540 3 13.620 2.466 33.587 0.00 0.00 0.00 0.00 33.59 0.00 0.00 0.00
Extra Top Right Support 25 2250 600 2.813 3 8.438 3.853 32.510 0.00 0.00 0.00 0.00 0.00 32.51 0.00 0.00
Side Face Bars 16 6800 6.800 4 27.200 1.578 42.922 0.00 0.00 0.00 42.92 0.00 0.00 0.00 0.00
Stirrups 8 2.360 56 132.160 0.395 52.203 52.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
T & B Bars 20 300 14800 300 15.340 6 92.040 2.466 226.971 0.00 0.00 0.00 0.00 226.97 0.00 0.00 0.00
1000
Overlap 20 1.000 6 6.000 2.466 14.796 0.00 0.00 0.00 0.00 14.80 0.00 0.00 0.00
Extra Top Left Support PB8 16 300 2250 2.526 2 5.052 1.578 7.972 0.00 0.00 0.00 7.97 0.00 0.00 0.00 0.00
4800
Extra Top Right of PB8 12 4.800 2 9.600 1.580 15.168 0.00 0.00 15.17 0.00 0.00 0.00 0.00 0.00
Extra Top Right of PB9 16 2250 300 2.526 2 5.052 1.580 7.982 0.00 0.00 0.00 7.98 0.00 0.00 0.00 0.00
Extra Bottom Mid Span PB9 12 4540 4.540 2 9.080 0.888 8.063 0.00 0.00 8.06 0.00 0.00 0.00 0.00 0.00
Stirrups 8 1.560 108 168.480 0.395 66.550 66.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PB10 Grid B-C/1' Staircase Beam (300 x 600) mm 1 Nos
T & B Bars 16 300 7430 300 7.970 6 47.820 2.466 117.924 0.00 0.00 0.00 117.92 0.00 0.00 0.00 0.00
Extra Bottom Mid span 16 4180 4.180 2 8.360 2.466 20.616 0.00 0.00 0.00 20.62 0.00 0.00 0.00 0.00
Stirrups 8 1.560 53 82.680 0.395 32.659 32.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00
T op Bars 20 300 16400 300 16.940 3 50.820 2.466 125.322 0.00 0.00 0.00 0.00 125.32 0.00 0.00 0.00
1000
Overlap 20 1.000 3 3.000 2.466 7.398 0.00 0.00 0.00 0.00 7.40 0.00 0.00 0.00
Bottom Bars 16 300 16400 300 16.952 3 50.856 1.578 80.251 0.00 0.00 0.00 80.25 0.00 0.00 0.00 0.00
800
Overlap 16 0.800 3 2.400 1.578 3.787 0.00 0.00 0.00 3.79 0.00 0.00 0.00 0.00
Extra Top Left Support PB11 25 300 2450 2.713 2 5.425 3.853 20.903 0.00 0.00 0.00 0.00 0.00 20.90 0.00 0.00
Extra Top Left Support PB11 20 300 2450 2.720 1 2.720 2.466 6.708 0.00 0.00 0.00 0.00 6.71 0.00 0.00 0.00
5300
Extra Top Right of PB11 25 5.300 2 10.600 3.853 40.842 0.00 0.00 0.00 0.00 0.00 40.84 0.00 0.00
5300
Extra Top Right of PB11 20 5.300 1 5.300 2.466 13.070 0.00 0.00 0.00 0.00 13.07 0.00 0.00 0.00
Extra Top Right of PB11 25 2450 300 2.713 2 5.425 3.853 20.903 0.00 0.00 0.00 0.00 0.00 20.90 0.00 0.00
Extra Top Right of PB11 20 2450 300 2.720 1 2.720 2.466 6.708 0.00 0.00 0.00 0.00 6.71 0.00 0.00 0.00
Extra Bottom Mid Span PB9 12 5100 5.100 6 30.600 0.888 27.173 0.00 0.00 27.17 0.00 0.00 0.00 0.00 0.00
Stirrups 8 1.560 118 184.080 0.395 72.712 72.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00
T & B Bars 20 300 8150 300 8.702 6 52.212 2.466 128.755 0.00 0.00 0.00 0.00 128.75 0.00 0.00 0.00
Extra Top Right Support 20 2700 300 2.982 2 5.964 2.466 14.707 0.00 0.00 0.00 0.00 14.71 0.00 0.00 0.00
Stirrups 8 1.560 59 92.040 0.395 36.356 36.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00
T & B Bars 25 300 8150 300 8.675 4 34.700 3.853 133.699 0.00 0.00 0.00 0.00 0.00 133.70 0.00 0.00
T & B Bars 20 300 8150 300 8.690 2 17.380 2.466 42.859 0.00 0.00 0.00 0.00 42.86 0.00 0.00 0.00
Extra Top Left Support 16 300 2700 2.982 2 5.964 1.578 9.411 0.00 0.00 0.00 9.41 0.00 0.00 0.00 0.00
Extra Top Right Support 16 2700 300 2.982 2 5.964 1.578 9.411 0.00 0.00 0.00 9.41 0.00 0.00 0.00 0.00
Extra Bottom Mid Span 12 5100 5.100 2 10.200 0.888 9.058 0.00 0.00 9.06 0.00 0.00 0.00 0.00 0.00
Stirrups 8 1.560 59 92.040 0.395 36.356 36.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00
T & B Bars 25 300 16400 300 16.925 4 67.700 3.853 260.848 0.00 0.00 0.00 0.00 0.00 260.85 0.00 0.00
Overlap 25 1250 1.250 4 5.000 3.853 19.265 0.00 0.00 0.00 0.00 0.00 19.27 0.00 0.00
T & B Bars 20 300 16400 300 16.940 2 33.880 2.466 83.548 0.00 0.00 0.00 0.00 83.55 0.00 0.00 0.00
Overlap 20 1000 1.000 2 2.000 2.466 4.932 0.00 0.00 0.00 0.00 4.93 0.00 0.00 0.00
Extra Top Left Support 16 300 2700 2.976 2 5.952 1.578 9.392 0.00 0.00 0.00 9.39 0.00 0.00 0.00 0.00
Extra Top Right Support 16 5000 5.000 2 10.000 1.578 15.780 0.00 0.00 0.00 15.78 0.00 0.00 0.00 0.00
Extra Top Right Support 16 2700 300 2.976 2 5.952 1.578 9.392 0.00 0.00 0.00 9.39 0.00 0.00 0.00 0.00
Extra Bottom Mid Span 12 5100 5.100 4 20.400 0.888 18.115 0.00 0.00 18.12 0.00 0.00 0.00 0.00 0.00
Stirrups 8 1.560 118 184.080 0.395 72.712 72.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00
T & B Bars 25 300 16400 300 16.925 8 135.400 3.853 521.696 0.00 0.00 0.00 0.00 0.00 521.70 0.00 0.00
Overlap 25 1250 1.250 8 10.000 3.853 38.530 0.00 0.00 0.00 0.00 0.00 38.53 0.00 0.00
T & B Bars 20 300 16400 300 16.940 4 67.760 2.466 167.096 0.00 0.00 0.00 0.00 167.10 0.00 0.00 0.00
Overlap 20 1000 1.000 4 4.000 2.466 9.864 0.00 0.00 0.00 0.00 9.86 0.00 0.00 0.00
Extra Top Left Support 16 300 2700 2.976 4 11.904 1.578 18.785 0.00 0.00 0.00 18.78 0.00 0.00 0.00 0.00
Extra Top Right Support 16 5000 5.000 4 20.000 1.578 31.560 0.00 0.00 0.00 31.56 0.00 0.00 0.00 0.00
Extra Top Right Support 16 2700 300 2.976 4 11.904 1.578 18.785 0.00 0.00 0.00 18.78 0.00 0.00 0.00 0.00
Extra Bottom Mid Span 12 5100 5.100 8 40.800 0.888 36.230 0.00 0.00 36.23 0.00 0.00 0.00 0.00 0.00
Stirrups 8 1.500 236 354.000 0.395 139.830 139.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL QTY OFPLINTH BEAMS MT 5.25 0.92 0.00 0.13 1.25 1.63 1.32 0.00 0.00
Column Reinforcement - Plinth Level to 1st Floor
4375
25 4.375 4x4 70.000 3.853 269.710 0.00 0.00 0.00 0.00 0.00 269.71 0.00 0.00
C1 (500 x500)
4 Nos
Overlap 25 1.250 4x4 20.000 3.853 77.060 0.00 0.00 0.00 0.00 0.00 77.06 0.00 0.00
1250
4375
Upto -300 mm 20 4.375 4x12 210.000 2.466 517.860 0.00 0.00 0.00 0.00 517.86 0.00 0.00 0.00
25 1000 1.000 4x12 48.000 2.466 118.368 0.00 0.00 0.00 0.00 0.00 118.37 0.00 0.00
400
8 1.700 4x39 265.20 0.395 104.754 104.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
400
145
20 4.375 8x14 490.000 2.466 1208.340 0.00 0.00 0.00 0.00 1208.34 0.00 0.00 0.00
C2 (500 x500)
8 Nos
20 1000 1.000 8x14 112.000 2.466 276.192 0.00 0.00 0.00 0.00 276.19 0.00 0.00 0.00
Upto -300 mm
400
8 1.700 8x39 530.40 0.395 209.508 209.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00
400
145
20 4.375 3x16 210.000 2.466 517.860 0.00 0.00 0.00 0.00 517.86 0.00 0.00 0.00
C3 (500 x500)
3 Nos
20 1000 1.000 3x16 48.000 2.466 118.368 0.00 0.00 0.00 0.00 118.37 0.00 0.00 0.00
Upto -300 mm
400
8 1.700 3x39 198.90 0.395 78.566 78.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00
400
145
8 1.456 3x39 170.35 0.395 67.289 67.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4375
25 4.375 2x12 105.000 3.853 404.565 0.00 0.00 0.00 0.00 0.00 404.57 0.00 0.00
C4 (500 x500)
2 Nos
25 1250 1.250 2x12 30.000 3.853 115.590 0.00 0.00 0.00 0.00 0.00 115.59 0.00 0.00
4375
Upto -300 mm 20 4.375 2x4 35.000 2.466 86.310 0.00 0.00 0.00 0.00 86.31 0.00 0.00 0.00
20 1000 1.000 2x4 8.000 2.466 19.728 0.00 0.00 0.00 0.00 19.73 0.00 0.00 0.00
400
8 1.700 2x39 132.60 0.395 52.377 52.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00
400
145
25 4.375 1x4 17.500 3.853 67.428 0.00 0.00 0.00 0.00 0.00 67.43 0.00 0.00
C6 (700 x700)
1 Nos
25 1250 1.250 1x4 5.000 3.853 19.265 0.00 0.00 0.00 0.00 0.00 19.27 0.00 0.00
4375
Upto -300 mm 20 4.375 1x12 52.500 2.466 129.465 0.00 0.00 0.00 0.00 129.47 0.00 0.00 0.00
20 1000 1.000 1x12 12.000 2.466 29.592 0.00 0.00 0.00 0.00 29.59 0.00 0.00 0.00
400
8 2.500 1x39 97.50 0.395 38.513 38.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00
210
400
25 4.375 2x10 87.500 3.853 337.138 0.00 0.00 0.00 0.00 0.00 337.14 0.00 0.00
C7 (450 x450)
2 Nos
25 1250 1.250 2x10 25.000 3.853 96.325 0.00 0.00 0.00 0.00 0.00 96.33 0.00 0.00
4375
Upto -300 mm 20 4.375 2x6 52.500 2.466 129.465 0.00 0.00 0.00 0.00 129.47 0.00 0.00 0.00
20 1000 1.000 2x6 12.000 2.466 29.592 0.00 0.00 0.00 0.00 29.59 0.00 0.00 0.00
400
8 1.500 2x39 117.00 0.395 46.215 46.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00
125
350
20 1000 1.000 1x4 4.000 2.466 9.864 0.00 0.00 0.00 0.00 9.86 0.00 0.00 0.00
4375
Upto -300 mm 16 4.375 1x8 35.000 1.578 55.230 0.00 0.00 0.00 55.23 0.00 0.00 0.00 0.00
20 800 0.800 1x8 6.400 1.578 10.099 0.00 0.00 0.00 0.00 10.10 0.00 0.00 0.00
350
8 1.260 1x39 98.28 0.395 38.821 38.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00
230
85
8 0.970 1x39 37.83 0.395 14.943 14.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4375
20 4.375 2x12 105.000 2.466 258.930 0.00 0.00 0.00 0.00 258.93 0.00 0.00 0.00
C9 (230 x600)
2Nos
Upto -300 mm 20 1000 1.000 2x12 24.000 2.466 59.184 0.00 0.00 0.00 0.00 59.18 0.00 0.00 0.00
130
19
5
8 1.360 2x39 106.08 0.395 41.902 41.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00
500
8 0.266 2x39 20.75 0.395 8.195 8.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL QTY OF COLUMNS FROM PLINTH LEVEL TO FIRST FLOOR MT 6.50 1.49 0.00 0.00 0.06 3.44 1.51 0.00 0.00
Total Quantity of Reinforcemet In This Bill as Per Drawings MT 23.90 3.28 0.33 5.85 4.31 6.70 3.43 0.00 0.00
TOTAL QTY OF COLUMNS FROM PLINTH LEVEL TO FIRST FLOOR MT 0.60 0.00 0.00 0.52 0.08 0.00 0.00 0.00 0.00
Total Quantity of Reinforcemet Steel As Per JMR Records MT 0.60 0.00 0.00 0.52 0.08 0.00 0.00 0.00 0.00
LABOUR ESCALATION (Ref. Clause No.__)
NAME OF CONTRACTOR : M/s________- Private Limited RUNNING BILL NO. : RA Bill No.
NAME OF PROJECT : _______- A High-Rise Residential Tower (2B+G+24 F) PERIOD OF MEASURMENT : Upto _________
NATURE OF WORK : Civil & Structure Work DATE OF SUBMISSION : __/__/2021
LOCATION : __________________, Bangalore CONTRACT VALUE : __________ (Incl. Taxes)
NAME OF OWNER : M/s ___________Developers LLP GST No. : ____________-Z7
Ll
Period of R.A Bill Period of Escalation Llo
( Minimum daily wages in
( Minimum daily wages in
Rs of unskilled adult male
R.A. Bill Nos of Work done (W) Rs of unskilled adult male VL = 0.85 x W x
S No mazdoor as applicable for
No. Days for this RA bill mazdoor as applicable for Y/100 x (LI-LI0)/LI0
state of work on last date
state of work as on date of
Total Work Nos of of quarter under
From To From To Work Order )
done Days considration)
1 1st RA 7-Apr-21 31-May-21 11,326,959 55 7-Apr-21 30-Apr-21 24 4,942,673 342.60 268.50 347,837
2 1st RA 7-Apr-21 31-May-21 11,326,959 55 1-May-21 31-May-21 31 6,384,286 346.50 268.50 551,759
Total 899,596
Labour Escalation
POL Escalation (Ref. Clause No. _)
1 1st RA 7-Apr-21 31-May-21 11,326,959 55 7-Apr-21 30-Apr-21 24 4,942,673 114.50 86.10 27,716
2 1st RA 7-Apr-21 31-May-21 11,326,959 55 1-May-21 31-May-21 31 6,384,286 114.50 86.10 35,799
Total 63,515
POL Escalation