Project Procurement Management Procureme
Project Procurement Management Procureme
By
SAEED AHMED AL MAHRI
(ID NO. 20050014)
INSTITUTE OF ENGINEERING
THE BRITISH UNIVERSITY IN DUBAI
BUiD
FEBRUARY 2007
ACKNOWLEDGEMENT
1. Dr. Mohammed F. Dulaimi, Sr. Lecturer, Project Management, BUiD, for his
guidance and supervision to this Dissertation and support for the research.
2. Dr. Jamal Al Bahar, PMP, President, PROMIS-Group, for his valuable ideas, review
3. Dr. Sami Freig, Civil Engineering Professor, Kuwait University, for his suggestions
4. Mr. Mahiyar Morawala, Clerical Services Supervisor, for his review and great support
5. Mr. Syed Abdul Kader, Contracts Assistant, for his help on presentation of this
Dissertation.
6. Hyder Consultancy, Mr. Stuart and staff for their support and participation in the
7. All my colleagues and staff at Procurement & Contracts Division, for their continuous
This Dissertation provides insights into improving aspects of Project Management in UAE. A
research is conducted in order to assess the impact of Procurement Strategy on Business and
Project Strategies with respect to management of Oil & Gas projects.
UAE is rapidly developing and International as well as local companies are participation in
hundreds of varied on-going projects. To elicit and maintain interest of majors, Procurement
of projects should be towards achieving strategic objectives and improving relationships.
The Aim of the research is to detect the link between Project and Business Strategies.
Procurement Strategy is identified as the missing link and, as a Hypothesis to the Research,
to solve project problems in meeting objectives. Research objectives are to assess influence of
Procurement Strategy on Projects/Business Strategies, show how current Procurement
Strategies are impediments in achieving project and strategic objectives and identify elements
of Procurement Strategy that aim at achieving strategic objectives.
The Literature reviewed on current knowledge of related issues suggested the inter-relation of
Business to Project Strategies through Portfolio and Programs Strategies. The links to
Procurement Strategy for outsourced projects in the Supply chain was explored extensively.
Research Methodologies of Quantitative and Qualitative methods were adopted to test the
Hypothesis and assess Objectives of the research. Questionnaire for investigating the strategic
role of Project Procurement in Oil & Gas was developed. As a qualitative method, a Case
Study for surveying four major projects in Refining industry within Oil & Gas was also
developed. The case study involved surveying different parties of the projects to assess
problems in projects Procurement. These methods generated valuable ideas in supporting the
position of project Procurement in Oil & Gas industry projects towards achieving objectives.
Data of the surveys responses were then presented in the both forms (Quantitative and
Qualitative responses). The data was then analyzed with the findings from Literature to
propose the recommended actions.
Recommendations cover Linking Procurement to Business Strategy in Oil & Gas and
proposing Procurement Strategies to overcome problems in Oil & Gas Projects.
Conclusions have been finally derived and a subject of investigating Procurement Strategies
on Project Performance was suggested for further research.
1. INTRODUCTION ........................................................................................... 1
1.1 Purpose of the Dissertation ....................................................................... 1
1.2 Background Information .......................................................................... 1
1.3 Problem Statement .................................................................................... 2
1.4 Aim, Objectives and Hypothesis of the Research ..................................... 3
1.5 Description of Dissertation Contents ........................................................ 5
7. RECOMMENDATIONS ................................................................................ 84
7.1 Procurement Methods and Systems for Oil & Gas Projects .................... 85
7.2 Contracts Management and Strategy for Oil & Gas Projects .................. 86
7.3 Procurement Strategy in Oil & Gas to Realise Business Strategy ............ 88
Annexure 1 – Phases & Activities of Oil & Gas Major Projects .............................. 93
Annexure 2 – Procurement Strategy Questionnaire Form ......................................... 95
Annexure 3 – Case Study Project Survey Form ........................................................ 96
Annexure 4 – Interview with Projects Division Manager.......................................... 99
Annexure 5 – Interview with Projects Procurement Services Manager .................... 101
Annexure 6 – Procurement Strategy Checklist for Oil & Gas Project ...................... 104
Glossary of Terms .................................................................................................... 106
References ................................................................................................................. 107
Waddel, 2004).
Figure 3 The strategic relationships in product delivery, (Martinelli & Waddel, 2004).
Figure 4 The link through Program Management, (Martinelli & Waddel, 2004).
Figure 5 The Business Strategy through Portfolio and Program Management, (a) Top
Down structure and (b) Value creation of projects, (Michel & Manon, 2007).
Figure 6 Supply chain in the Services sector in the US (a,b& c), (Ellram e al., 2004).
Figure 9 The strategic clients activities of SCM and relationships, (Cheung, 2004).
Figure 12 The percentages of total population requested, total responses and sample
responses.
This chapter describes the intent of the Dissertation. It reveals background information and
provides a problem statement to enable a full understanding of the issues involved.
Thereafter, it explains the aims, objectives and the hypothesis of the Dissertation.
The purpose of this Dissertation is to gain knowledge and insights that would contribute to
further developing and improving various aspects of Project Management in the UAE. The
Dissertation is designed to obtain more information and conduct further research in order to
assess the impact of Procurement Strategy on Business and Project Strategies with respect to
management of Oil & Gas projects.
UAE is rapidly developing and hundreds of varied projects are on-going. These projects
involve all sectors, whether public or private (i.e. Construction, Telecommunications, Real
Estate, Transportation, Environment, Oil & Gas, etc.). In fact, these projects have been
launched to incrementally achieve the objectives they are intended for and are to a great
extent in conformity with the strategic direction of organisations or UAE Government
directives to develop the country. Local as well as International companies are participating
in the development of this country. Consultants and Contractors from all over the world are
being invited to share their expertise in these Projects.
The main reason for inviting International expertise is lack of resources and specialization in
the region to undertake a huge number of projects of varying complexity. Attracting these
specialists has of course contributed to raising the knowledge and resource base of local
companies in addition to improving proficiency in handling projects. Therefore, Project
Management in this region needs to focus more on developing/implementing Strategies
which promote good relationships with International Contractors/Consultants. This is in order
to retain the interest of these firms locally with a view to improving quality and achieving
project objectives. Formulating procurement and contracting strategies and suitably awarding
a project on the basis of techno/commercial considerations is a strategic Management
decision to obtain optimum, cost-effective, world-wide professional services and expertise.
It is accepted that Oil & Gas is one of the major UAE industries contributing to the
development of this country. Oil & Gas projects are mostly of high specialisations that
demand the expertise and professional services mentioned. Oil & Gas projects are generally
similar to most Construction projects where Conceptual Study, Feasibility Study, Design,
Procurement and Construction phases are involved for a big sized (Major) project; however,
these phases might be slightly differently placed or named (Annexure 1 details the various
phases of a Major Oil & Gas Project).
Similar to Construction projects, Oil & Gas Major Projects have specific objectives to meet
overall business and strategic objectives. Specific project objectives of meeting its schedule,
quality and cost effectiveness may be associated more with Corporate / Business objectives
such as; increasing Oil & Gas production to meet international market demand, enhancing Oil
& Gas processing and operations, ensuring reliability of process units/equipments and ensuring
safety and protection of the environment. Other broader Strategic objectives to be met may be
furthering the growth of the company and more publicly, development of UAE economy.
It is sometimes alleged that the Oil & Gas industry fails to achieve many aspects of its overall
strategic business objectives because of problems occurring in the projects it undertakes.
These problems can be categorised as either not completing projects within a set schedule, at
the quality level required or around the budget allocated. Another problem associated with
Oil & Gas projects could be finding capable Contractors/Consultants, improper tendering
competition (i.e. different levels of contractors/consultants’ proficiencies, capabilities and
sizes in one tender).
Furthermore, a very persistent problem that figures in almost all projects is the reluctance of
Contractors/Consultants to accept Contracting Strategies specific to the Oil & Gas industry
projects which can include, but not be limited to, the following:
In the opinion of Turner (1995), the “Concept of establishing the terms of a contract by
‘reciprocal concession and compromise’ is an effective generality. However, it is difficult to
achieve in reality because one party is more powerful than the other.” It was further explained
that this might be the case in circumstances that involve Contracts between “Big Oil”
commercial muscle and small specialized contractors. Formulation of Procurement Strategies
in Oil & Gas requires high-level strategic management involvement to maximise gains and
optimise project deliverables. Hence, Management of Projects in the Oil & Gas industry
needs to effectively utilise many advanced Project Procurement strategies and practices.
Rashid (2006) explains that the impact of Procurement and Contracting Strategies on the
scope, execution and completion of projects drastically affects relationship between Owner
and Contractor in terms of coordination, cooperation, communication, scope management
and cost/risk associated. Thus, Procurement Strategies and processes in Oil & Gas sector
need to be more attuned to completing the project to its and strategic objectives.
This section is intended to explain the aim, objectives and hypothesis of the research.
The general aim of the research is detecting the link between Project and Business Strategies
in Oil & Gas industry. It is intended to propose Procurement Strategy as the missing link that
solves perceived problems in Oil & Gas projects, as hypothesis to the research to be tested.
The Objectives of the research hence derived from the above Aim are:
4. To develop a model of linking Procurement Strategy to Business Strategy in Oil & Gas.
The assumptions made in order to arrive at the Hypothesis of the research are as follows:
Business Strategy decides on Projects to fulfil the strategic business needs through Portfolio
and Program Management. Project Management handles initiation and execution of a Project.
Project Strategy decides on Projects, whether out-sourced or in-house, which enables the
Project to achieve its objectives through Portfolio/Program Management. For an outsourced
Project, a Procurement Strategy is set to complete the Project in the manner desired.
Procurement Strategy specifies how the two parties should proceed to successfully complete
the Project, by achieving its objectives in consonance with the overall Business Strategies and
goals of the company. Hence, the Hypothesis to the research is:
The ability of any Oil & Gas Project to successfully meet its objectives in accordance
with the prescribed strategic objectives is dependent on linking that Project’s
Procurement Strategy to the Corporate / Business Strategy of the Company.
The Hypothesis model is illustrated in Figure 1 showing the link and the loop of the
Strategies. It is intended to test this hypothesis for acceptance through Literature Review and
specific Research Methodologies adopted for the purpose.
In-House
Program & Portfolio Management Project Management Projects
Business Strategy
Out-Sourced
Procurement Strategy
Projects
Procurement Management
As the discussion progresses and gets influenced by Literature and research, modified and
final models of Procurement Strategy will given.
This section is intended to review the Literature for issues related to Corporate Business and
Project Strategies to see the links and relationships. Industries from Building, Construction
and IT were consulted to provide the necessary information on the subject.
First, the concept of each Strategy is explored; then, the links to Business Strategy are seen.
Hence, Strategy is the direction and scope of an organisation over the long term which
achieves advantage for the organisation through its configuration of resources within a
changing environment to fulfil stakeholder expectations. It was explained that Strategy differs
with organisations' sizes. For a huge multinational organisation, Overall Strategy is the ability
to achieve a position to becoming the ‘industry standard’ recognized by suppliers and buyers.
Furthermore, Organisation Strategy is divided into two levels: Corporate level Strategy and
Business level Strategy.
Corporate Strategy is the consistency in development in terms of: clarity of the rationale of
the corporate parent in seeking to add value to business units; the logic of the corporate
portfolio; the nature and the extent of the diversity of the portfolio and the nature of corporate
control exercised by the corporate parent.
A Strategic choice in Business level Strategy needs to take into account the environment in
which the organisation operates like competitive advantage maybe eroded as technology
changes or as new competitors emerge.
Hence, Business level Strategy is about how to compete successfully in a particular market.
The long term direction of an Organisation is stated through expressing the Mission, Vision
and Objectives of the Business for an organisation.
It was further discussed in details that strategic management process is about moving the
organisation from its present position, to a future strategic position, in order to exploit new
products and markets. In general, Modern Business Strategy deals with the matching of
activities of an organisation to the environment in which it operates. Strategic Management
is that set of managerial decisions that determines the long-term performance of a company.
It includes strategy analysis, strategy implementation, evaluation and control.
Strategic analysis process investigates current and future positions. Strategic implementation
is the way of getting the organisation to move swiftly and surely. Study of strategic
management therefore emphasises monitoring and evaluating the environmental opportunities
and threats in light of corporate strengths and weaknesses. The strategic objective setting process
is designed to make the program more fruitful.
Further, it was discussed that strategic decisions may also have to manage and perhaps
change relationships and networks outside the organisation, for example with suppliers,
distributors, customers and services providers.
The concerns are what new opportunities can be identified or created, which products or services
should be developed and the extent to which these meet stakeholders’ requirements or the
objectives of the organisation. The aim is meeting these strategic objectives regardless as
objectives vary from one organisation to another.
Organisations therefore select various projects to properly achieve these strategic objectives.
The above parts formulate the projects objectives along with requirements in existing
environment which should also be inline with strategic objectives. Hence, Project’s Strategy
should be aligned to overall Business strategy. Investigating the relationship and drawing the
link of these strategies are shown from Literature in the next section.
2.3 The Link to Overall Business Strategy through Program / Portfolio Management
In addition, outside these core industries, program management is not well understood and
there is much confusion between the disciplines of program and project management.
Program and Project Management are related but distinct disciplines. It is important for
everyone within the organization to fully understand the distinctions between the two, as well
as the various roles and responsibilities of program and project managers.
The greatest difference between Program and Project Management is that Program
Management focuses on achieving business results to create a competitive advantage while
Project Management focuses on planning and executing the work required to deliver the end product.
In the Program Management model, the program manager manages across the multiple
functional projects, while the project manager manages within a single functional project.
Other distinctions between program and project management are shown in Table 1.
Table 1 Comparison between Program and Project management, (Martinelli and Waddell, 2004)
It has been discussed that Program Management effectively and successfully fills the skill
gap between Project Strategy and Business Strategy in many organizations and industries.
This is because the discipline brings the requisite skills, abilities and business acumen to
perform this critical strategic role.
Figure 2 (a) and (b), graphically illustrates the identified gap between strategic elements and
project execution which exists in many organizations today.
As illustrated in the figure, when the Program Management function is employed, the gap
between strategic elements and project execution is effectively eliminated. Missing parts have
been identified and provided the complete link to Strategy. Figure 3 (a) and (b) illustrates the
closed-loop relationship between Business Strategy, Program, and Project Management in
delivering a product.
(a)
(b)
Figure 3 The strategic relationships in developing product delivery, (Martinelli and Waddell, 2004)
On the other hand, originating and correctly prioritizing programs of projects are Portfolio
Management activities. Michael & Manon (2007) in their discussion of project based
organisations (PBOs), linked Project Management to Business Strategy through Portfolio
Management which manages the programs. It is discussed that PBOs need to adopt integrative
approaches that will enable consistent structures and delivery of strategy. A research was
conducted to investigate and understand the double loop effect of strategy, governance and
structure on project management and vice versa. Then, through the research, it is suggested that
it is generally recognized that PBOs are struggling to integrate knowledge and structures and
that projects are often viewed as “singular ventures”.
Studies done in strategy implementation have demonstrated that strategies are seldom
implemented as planned. Strategy analysis, formulation and implementation are not a linear
process, but the three activities are going on concurrently all the time and strategies are
therefore formed incrementally. If programs and projects are used to implement strategies in
relatively unstable environments, PBOs are expected to be designed to cope with emergence
and enactment. A recommendation was laid out allowing great autonomy to program managers,
who would have responsibility for the business level strategy and displaying value chain
principles of cooperation and collaboration between the stakeholders of a program.
Portfolio Management is an approach that aims to align projects efforts through programs
with the corporate strategy and optimise the efficient use of resources throughout the
organisation. Portfolio management is a management approach for PBOs; its objective is to
guarantee efficient use of resources in support of the corporate strategy by managing
Programs of multi projects. Figure 5 (a) and (b) illustrates the above discussion.
(b)
Figure 5 The Business Strategy through Portfolio and Program Management, (Michel and Manon , 2007)
Figure 5 (a) shows the top down structure they developed from Top Management to Projects
showing levels of Portfolio, Programs and Projects to the Strategy.
Figure 5 (b) shows the value creation and value delivery out of projects to the Business and
Corporate Strategies through vertical integration of Portfolio Management and the Horizontal
integration of Program Management.
It is explained that POO’s hold a portfolio of projects. The more projects a company
performs, the more complex it becomes. In order to cope with this increasing complexity,
new management competences are required.
POO’s are highly complex organizations because of their dynamic boundaries and contexts.
On one side the number and the sizes of the projects and programs are constantly changing,
permanent and temporary resources are employed, and cooperations are organized in virtual
teams. On the other side varying strategic alliances are established and relationships to the
different social environments of the different projects and programs are managed.
In order to manage the dynamics of POO’s besides intensive corporate identity activities,
such as strategic planning activities, reflections of the corporate culture, and continuous
organizational development, specific integrative functions, such as program management and
managing the project portfolio, have to be performed.
Usually some of the projects in a program are performed sequentially and some are
performed in parallel. Programs have program-specific strategies, organizational rules and
structures.
It was added that typical programs are the development of a product family (and not of a
single product), the implementation of a comprehensive IT-solution (such as SAP), the
In order to allow for autonomous projects on one side but to assure the benefits of
organizational learning, economies of scale, and networking synergies in a program on
another side, a specific program organization is required. Typical program roles are program
owner, program manager, and a program coordination team, typical program communication
structures are program owner meetings and meetings of the program coordination team.
The advantages of designing specific program organizations with several subprojects are:
- a less hierarchical organization
- a clear terminology: a program- manager and several project managers instead of one
project manager and „project managers“ of the sub-projects
- empowerment of the projects of the program by allowing for specific project cultures,
specific relationships to environments and specific project organizations
- differentiation between program ownership and different ownerships for the different
projects.
The basis for the management of the project portfolio is a database with aggregated project
data, such as the project type, relations of a project to other projects, information about the
project organization, information about relevant project environments, and project ratios.
These data can be used for relating projects to each other, for deciding about new projects to
be started, for setting project priorities, and for stopping projects.
For Project-oriented Companies it is not sufficient to have the competence to manage single
projects efficiently, but additional competences, such as the competences for the assignment
of projects and programs, for project and program coaching and auditing, for networking
between projects, and for program management and project portfolio management are
required. For all of these processes an explicit assessment and continuous further
development is necessary.
Program management used to be a side job for executives, but in today's environment of
change, it is clear that a new approach is needed. In the near future, organizations will rely on
individuals to focus all of their energy on implementing an overarching strategy that pulls
together multiple disciplines within the organization. This new responsibility of program
management is a likely path for both functional managers and project managers.
A program manager’s focus never wavers from the organization’s strategic objective. The
strategic objective is a long-term objective that is essential for the business to achieve in
order to maintain a competitive advantage, for instance, reducing cost, increasing customer
satisfaction by, or increasing revenue. Once the strategic objective is identified, the tactics, in
terms of identifiable projects, must be outlined in order to achieve this objective.
The program manager must sustain the organization’s focus by continuing to identify and
drive the implementation of projects that will ultimately support the strategic objective.
Successful program managers are able to move the organization toward achievement of the
strategic objective in a timely manner without interrupting the day-to-day operations of the
organization.
Table 2 The Project, Program and Portfolio Management in Strategic Involvement, (PMFORUM, 2001)
Freytag (2002) stated that when preparing Outsourcing Strategy, a company must take into
account both its own position in the network as well as how the company develops. It is also
necessary for the company to clarify its own strengths and weaknesses, and draw up an
overall mission and strategy for the company in general. However, it was explained that for
companies to live up to its mission and implement its strategy, it must interact actively with
its surroundings. In other words, the company’s mission and strategy must be adapted to the
surroundings, as must the way in which in/out-sourcing takes place. The question of who you
are and what you want can only be seen with the surroundings. This includes the parties as
they part of the surroundings.
The above process introduces a Supply Chain to be managed. Stuart (1997) explained that the
growing dependency on out-sourcing will increase the role and involvement of the Supply
Chain Management (SCM) in the corporate strategy. This is because of the relationship
development brought through the SCM such as strategic supply alliances. The growing
recognition of SCM is through achieving its long overdue position, along with marketing and
operations as key element in corporate strategy.
It was also seen in the review of Corporate and Business Strategy that strategic decisions may
also have to manage and perhaps change relationships and networks outside the organisation,
for example with suppliers, distributors, customers and services providers. This gives further
rise to exploring the SCM strategies.
SCM therefore might be a separate strategic process or a strategic practice which is to be seen
and explored in the next chapter.
This section intends to review the Literature on how Supply Chain Management (SCM)
contributes to Strategic objectives achievement, and introduces Project Procurement.
As mentioned previously, SCM is a discipline to be attained by Organisations in managing
projects for outsourcing these projects to achieve the business objectives. Hence, whenever
outsourcing is involved, SCM comes into picture for strategic position of organisation. Also,
SCM is the strategic management of relationships which will be seen.
SCM seeks to enhance competitive projects by closely integrating the internal functions
within a company and effectively linking them with the external operations of suppliers and
channel members. Elmutti (2002) describes SCM as a network or web that brings the
supplier, distributor and the customer into one cohesive process and shows how each interacts
with the others. Supply Chain Strategy is defined as taking into account coordinating all the
different pieces of the chain as quickly as possible without losing any of the quality or
customer satisfaction while keeping the costs down.
The importance of SCM has risen in outsourced services sector as in the other sectors such as
manufacturing. Ellram et al. (2004), in discussing supply chain of out sourced services,
defined SCM as the management of information, processes, goods and funds from the earliest
supplier to the ultimate customer, including disposal. It was explained that in recent years,
services have become an increasingly important force in the U.S. economy. Services have
taken on an escalating level of importance as manufacturing became hollowed out in the
1980s and 1990s due to outsourcing to Asia, Mexico, South America and Eastern Europe.
Yet, from academic and practical standpoints, the emphasis of supply, supply chain and
operations management is still strongly skewed toward the manufacturing sector. Figure 6
illustrate the discussion of SCM enrolment in the services sectors in the US.
Hence, a supply chain framework appropriate for a services supply chain was developed by
comparing and contrasting the applicability of three product-based manufacturing models:
Global Supply Chain Forum Framework, SCOR and Hewlett- Packard’s Supply Chain
Management Model as in Figues 7 a, b and c.
(a)
(c)
Figure 7 a, b & c Supply Chain in the Manufacturing, (Ellram et al., 2004)
It was explained that Services are significant, and the spend is large and growing. Attention
to the services supply chain by practitioners is necessary for improvement, cost control and
minimization of value leakage. Similarly, more attention to the services supply chain is
needed by academics as they educate future practitioners and conduct research.
STUDENT ID: 20050014 PAGE 20
Disseminating information on best practices and trends in managing the services supply
chain and services purchases could help businesses retain their competitive advantage in the
growing global economy. Improved management of services spending could represent the
next major area of cost reduction and value enhancement for organizations. Supply
management academics and practitioners can play a significant role in this improvement
strategy.
Hence, SCM should suggest models and ways for the supply management executives to
understand and implement. Lan (2003) suggested an Integrated Supply Chain Management
(ISCM) that directly involves linking suppliers and customers with internal supply processes of
an organisation. The model is illustrated in Figure 8.
It is suggested that ISCM solutions allow organisations to automate workflows concerning the
execution and analysis of planning, sourcing, making, delivering, returns handling and
maintenance.
It was further discussed that strategy is defined as being a discernible pattern over time in a
stream of corporate decisions. The purpose of business- and functional-level strategies is to
develop and sustain competitive advantage.
It was stated that previous research has found that supply management is a strategic function
that has an impact on overall firm performance. As supply management continues its shift
from a passive/tactical function to a strategic/integrative function, its goals, objectives and
strategies need to change as well. However, the strategies that supply management
departments adopt need to both support and complement an organization's overall goals,
objectives and strategies.
Strategic supply management has been empirically linked to firm performance through
measures of return on investment, profit as a percent of sales, market share and market
position. Additionally, supply management's involvement as a strategic function has been
associated with supplier evaluation and building relationships/partnerships with suppliers,
both of which have resulted in greater corporate financial performance. On the other hand, a
misaligned supply management strategy is a recipe for disaster. Therefore, selecting the
correct supply management strategy becomes crucial to overall competitiveness.
This is how SCM contribute to achieving strategic objectives. To keep the link, SCM also
specifies relationship management, organisation culture and organisation change as strategic
objectives. Cheung (2006) confirmed that there are numerous activities that asset owners can
do and undertake to achieve strategic alignment of their objectives to selected supply chain
management strategies. It was noted that successful implementation of relationship
management, client organisation can obviously influence the supply chain culture and
commitment to the goals and objectives of an organisation.
The dimensions have been explored and come to the conclusion that SCM requires strategic
activities from clients as illustrated in Figure 9 below.
Figure 9 The Strategic clients activities of SCM and relationships, (Cheung, 2006)
However, these goals in the supply chain must be explicitly stated in the both the client
policy and the conditions of contract and must be fully understood by all parties for a project.
This builds and improves the organisational relationships to cut costs, increase technological
innovation, increase profitability and productivity, reduce risks, and competitiveness to
successfully complete the project and achieve intended objectives. Then, as can be seen from
the Figure 6, Procurement Strategy is necessary for strategic sourcing.
The connection therefore between SCM and Procurement is that SCM brings the
arrangements in Procurement such as Partnering, Alliances and the integration. Khalfan
(2005) explains that one of the key elements in innovative procurement methods is the
management of the supply chain. Further, a number of organisations and individuals within
the construction industry are already moving towards supply chain integration through the
use of partnering, framework agreements and techniques to rationalise their supplier base.
Innovative procurement methods are often considered as a tool to integrate the construction
supply chain because it provides:
- openness,
- trust,
- cooperation,
- harmony of decisions,
- sharing of benefits,
- intangible and long term investments,
- collective working routine,
- and fair allocation of risk.
Many organisations have taken up the challenge to introduce new procurement initiatives
such as partnering into their organisations. Supply chain specifies how to make partnering
and other methods successful, how to appoint suppliers, how to manage the integrated supply
chain, how to build trust and who will lead the whole process. It further added that SCM
brings the integration in Procurement. This is through the role and power of clients, the
responsibility of contractors, subcontractors, suppliers and manufacturers in the whole chain.
Thus, we can see that SCM in the context of projects involves Procurement in managing
relationships and delivery methods. SCM Strategy is the successful implementation of
Many practitioners nowadays confuse the term Procurement with either Contracts or
Purchasing. Procurement is however a wider term that should include both in terms of
supplying goods and services to the wide areas of projects management. Dulaimi (2006)
provided two definitions of Procurement:
Procurement as a strategy to satisfy client’s development and/or operational needs
with respect to the provision of constructed facilities for a discrete life cycle, (CIB
W92).
Procurement as the organisational structure adopted by the client for the
implementation, and at times eventual operation, of a project, (Masterman, 2002)
The above definitions introduce a Procurement Strategy. Koolwiji and Vrijhoef (2005)
defined Procurement Strategy as the achievement of joint benefit through a collective process
of progressive development of value and costs; and thus added value to Clients and profits for
supplying parties that can be achieved through Procurement methods and arrangements such
as alliance contracting to achieve goals of the parties.
Procurement Strategy for projects is also a mean of identifying and selecting the best options
for applying contracting management and assessing risks strategies and transfer. APM (1998)
defined Procurement Strategy as a way in which suppliers of goods and services are used to
suit the objectives and nature of a project and the Client. It may be dictated by law,
government policy, financial bodies and specific organisation procedures and should further
include a Contract Strategy that forms an agreement on the objectives, priorities and risks of
the project plus attention to how these may change during the work to be done.
If the key objectives to be isolated, there is evidence that the selection of an appropriate
procurement strategy which matches the objectives of the key stakeholders is an important
contributor to project overall success. An appropriate Procurement Strategy should be
developed and set at an early stage of a project and adopted throughout the project.
Procurement Strategy is also specifies risks management. H.M Treasury (1997) stated that
setting a Procurement Strategy should select the best option in assessing alternative risk
transfer strategies after identifying risks in Design and Build, client design and management
contracting. A more in depth study of the Procurement Strategic objectives and processes are
undertaken in the next chapter.
In the previous chapter, it was seen how Procurement falls form SCM. Procurement
Management and Procurement Strategy were defined. As also seen earlier, the essence of
strategy is the way a company defines its business and links together the resources such as
relationships, organization’s competencies and suppliers and contractors which really matter
in today's economy. Procurement Strategy in the Supply Chain contributes to such a way.
Thus Procurement strategies are further to be explored in details.
To see the wide range of Procurement, Procurement Strategies around the world can be
investigated. Morledge et al. (2006) stated that there are procurement strategies that achieve:
Certainty of cost and time for a design developed by architect employed by client but
this traditional procurement process is sequential and consequently low
Relative speed and cost certainty – but the design will be a greater or lesser extent the
responsibility of a contractor (develop and construct or design and build respectively)
Speedy completion for a design developed by an architect employed by the client
(either management contracting or construction management) – but this case cost is
uncertain until close to completion).
Then, that most appropriate selection of a Procurement Strategy has two components:
Analysis – assessing and setting the priorities of the project objectives and client
attitude to risk
Choice – considering possible options, evaluating them and selecting the appropriate.
For international comparisons, Xiao and Proverbs (2002) advised that international
comparisons of contract allow contractors in different countries to distinguish their own
strengths and weaknesses and improve their competitiveness accordingly. On a recent survey
of contractors in Japan, the UK and the US have evaluated and compared contractor time
performance. It was disclosed that Japanese contractors achieve shorter construction times
and higher levels of time certainty than their UK and US counterparts. Anticipated delays are
far shorter in Japan and levels of client satisfaction are significantly higher than in the US and
UK. The superior performance of Japanese contractors may be attributed to their working
practices which were characterized by the use of a larger workforce on site, detailed planning,
close working relationships with their subcontractors, and an overriding focus on time
certainty.
Focusing on Procurement selection, in Hong Kong for example, Cheung et al (2001) stated
that one of the key concerns of Procurement selection is how to enhance objectivity. A
method was selected using Multi-Attribute Utility Technology (MAUT) and the Analytical
Hierarchy Process (AHP).
Thus, Procurement for projects should also aim at achieving value to organisations. In U.K.
for example, H.M (1997) stated that procurement in construction is to achieve the best value
for money and accountability for public funds must not be used as an excuse for missing
opportunity to deliver this. The key features of achieving the best value for money in
construction procurement are:
Procurement Strategies around the world can thus be said to be quite varied. Some strategies
might be familiar and others are totally new.
APM (1998) specified the contents of projects’ Procurement Strategy that achieves objectives
and affects Strategic decisions, which are:
1. Priorities of the project to employ other organisations to supply good and services and the
availability and suitability of Clients resources.
2. The suitability, capability and selection of suppliers and/or contractors.
3. The responsibility matrix including defining requirements, scope of work, standards,
design, quality, fitness for purpose, supervision, operating and maintenance, health and
safety, approvals, schedules, equipment installation, inspection, testing and commissioning.
4. Terms and Motivation Of Payments
5. Commercial and Procurement Procedures.
6. Contract Formation and Management
7. Risks allocation, Changes, Variations and Claims Management.
The resulting Procurement Strategy should respond to all the above elements. This can be
seen in details in the next sections.
As a Strategic objective, the right Delivery method and Procurement system should be selected
in every project. Literature proposed many developed Procurement methods for projects
compared to Traditional procurement methods which result in problems.
One method proposed in Literature is Alliances; Stuart (1997) explained that Alliancing is a
key element in corporate strategy in the discussion of Supply Chain Strategy’s organisational
influence. It is proposed that Alliance practising firms will display an increase in involvement
and management support in the corporate strategic-making process. Alliancing practising
Other procurement methods in projects are the Design and Build (DB) and Partnering
methods. Koskela (2003) looked at renewal of construction suggesting D/B and Partnering
for projects’ procurement methods. It is explained that separation of design and building has
presented problems in construction.
Thus, it is no wonder that great expectations have been attached to D/B procurement of
construction projects, where these two stages are organisationally integrated from the outset.
In this case, the client gives a single contract for the execution of both design and
construction to one company (usually a contractor). The performance of the D/B delivery
system in comparison with other major delivery systems has been studied and the results
indicate that, statistically, D/B outperforms the Traditional process in several respects;
however, the differences are not great.
On the basis of statistical analysis, the construction speed of D/B is 12% faster than the
speed of Traditional methods and the total delivery speed is 30–33% faster. In the UK, the
share of projects ending up above budget by more than 5% was 21% in D/B projects in
contrast to 32% in traditionally procured projects. In the USA, the corresponding figures
were 38 and 51%. The diffusion of D/B has been relatively rapid and several variants have
evolved in the speedy process of the procurement method of Partnering. It is mentioned that
Partnering is used mostly in USA and UK primarily to improve relationships and cooperation
in all project management levels. It achieved superior results in controlling costs and
technical performance and in satisfying customers compared with other projects.
A further explanation revealed that a US study shows that there appear to be no correlation
between the use of alliances and project resulting in long-term contractual relationships
between owners and contractors which are intended to promote efficiency in capital projects.
In addition it is not the alliances but the substance of work processes that produces the result
but the problem of Partnering is visible when the long term trust for improvement is not
achieved so there is evidence of improving long term relationship and trust.
As advancing the method, it was further explained that D/B method handed over to the D/B
contractor is employed through System Dynamics Modelling (SDM). There are many
categories for SDM. However, they can be classified under six main categories as: (1)
traditional design and build, (2) package deal (including turnkey contracts), (3) design and
manage, (4) design manage and construct, (5) novation design and build; and (6) develop and
construct. Turner (1995) classified the D/B approach into four main categories: (1) package
deal; (2) turnkey; (3) all-in service; and (4) develop & construct. Figure 10 illustrates the
categories.
A cause problem was identified as the lack of clarity in the amount of design left to be
performed by the construction contractor is in Traditional procurement methods. It is
observed that much control of Design by the contractor means that cost benefits of
buildability and integration of programs of design and construction in D/B methods. Also,
there may be significant delay or cost overrun due to unclear scope from the client in the
Traditional methods. Splitting The D/B phases causes loss of control of design by the
Further, in D/B construction projects, there are two main parties responsible for the execution
of the project, the client and the contractor or a group of contractors. In theory, the client
assigns all responsibility to the contractor. The client's role is to respond by identifying
requirements and by inspecting how well the product accords to the specification. However,
in practice, the contractor may be assigned to the contract with varying levels of information.
The contractor may start working on the project from the conceptual design or may start the
project with almost complete design from the client. Further they introduce the importance of
Information management in such procurement method. They say that Construction
knowledge and information sharing between client and contractor are essential for project
success.
Dulaimi et al (2003) further mentioned that the D/B method in suggesting enhancing
integration and innovation for Singapore’s construction industry. It was stressed out that one
of the major causes of low productivity is lack of integration across the value chain. A
recommendation of two key changes and initiatives to encourage greater integration in
Singapore’s construction industry was emphasized. The first is the promotion of the D/B
procurement method through providing an environment for the D/B arrangement. The second
is for the client to play a catalytic role by embracing D/B and tendering methods that
emphasize greater integration across the value chain. Their emphasis on innovation that
requires initiatives from professional companies to enhance productivity and therefore the
image of industry resulted in adaptation of new procurement methods. These procurement
methods improve the ability of the industry to provide more integrated and innovative
solutions to customer needs and expectations.
Design-Build methods do not allow a high level of involvement by the owner. Using
Alternative delivery methods and minimizing the number of contracting parties help
minimizing adversarial relationships. With regards to project characteristics, design-build
method is more effective than construction management at risk, construction management
and design-bid-build (in that order) in handling essential, complex and unfamiliar projects.
Selecting the appropriate project delivery method is a key decision that has to be made in the
early phases of the project. There are many delivery methods that can be used on any project.
The decision is usually based on certain factors of importance to the owner. Owners are
usually tempted to use the delivery method that they are familiar with. However, this might be
a great mistake since familiar methods are not necessarily effective in all situations. The
effectiveness of the delivery methods vary according to the factors. Owners must rank their
objectives and choose the method that maximizes the effectiveness in achieving the project
objectives.
Procurement systems also aim at achieving business and project objectives. Seely (1997)
discussed measurement of Project Procurement Management (PPM) in the Public Sector in
Canada. It is stated that PPM plays a determining role in achieving the projects’ objectives
and should form an integral part to the project management process. It was argued that such
systems are required to monitor and control the time of delivery on the project. Without such
systems stakeholders of a project will wait longer time on procurement. It is not acceptable to
project stakeholders to wait five to ten years from the start of major project procurement.
Finally stating the measures of PPM, it is explained that the approach addresses both the
requirements for corporate accountability and the normative of the PPM function. The
solution to the insight that project stakeholders do not have on their investment into project
procurement is to initiate the PPM measurement.
It was explained that a system that benefits both the client and contractor should adopted and
implemented. This is argued to been seen most in the PIPS system which its core duty is to
update and maintain the contractor’s performance information and in price based
environment.
These systems are of general purposes that serve general organisations strategic objectives.
There are procurement systems that are closely applied to projects objectives. Kumaraswamy
(2006) provides the full project procurement system and its subsystems that can be selected in
a project.
Figure 11 shows the breakdown of a Procurement System into its subsystem. Figure 10
shows a template for assembling a project specific procurement system from various set of
options. The figure also shows the sub-sub-system of a subsystem indicating a break down of
a subsystem. It is explained that each subsystem has series of options.
(b)
We can see from figure that the structure gives full system of a project procurement including
also contractual systems and selection methodologies for contractors and consultants. Hence
procurement systems are also specifies contractor / consultants selection criteria. It is
assumed that no change to current Contractor Selection / Evaluation practices will be
undertaken without a Procurement proper method. The importance of Contractor selection
and evaluation is to be seen.
The important point after all this is choosing the right contractor. Sifri (2003) pointed out that
when penetrating in today’s leaner economy, choosing the right contract vehicle
(Procurement) is as important as choosing the right Contractor. Investigating on how
Procurement Strategy affects Contractors Selection Criteria, Wong et al (2001) explained that
the lowest-price wins philosophy has been a consistent theme of contractor selection over the
years. An investigation showed that a Multi-Criteria Selection (MCS) tender price selection
to comprehensively elucidate the preference and use it in bidder evaluation process. It
provided further insight into the evaluation of contractors’ attributes.
Levels of importance assigned for each criterion were analysed like quantitative analysis of
differences in opinions and variance amongst respondents in a multivariate statistical method.
A contrast was made between the MCS approach and the lowest-price wins option amongst
surveyed construction clients. It was found out that cost has to be tempered with the
evaluation of lowest-price wins and the attempt of construction clients searching for a new
Mahdi et al (2002) described a Multiple-Criteria Decision Support System (MCDSS) for the
selection of the most appropriate contractor. Their system can accommodate the unique
characteristics of a project in addition to qualifications and capabilities of those contractors
assessed. It can also evaluate the list of contractors by matching their qualifications with
specific project conditions.
A short list of eligible contractors is thus selected. Furthermore, a comparison was done with
regards to capabilities of the short listed contractors and their plans for the project under
consideration, to select the most appropriate contractor. They said the system can be easily
modified to adopt specific conditions of the proposed project and also to facilitate the
decision maker in explaining the reasons for the elimination of excluded contractor.
Hence, Procurement further enhances the ways in Contractor evaluation and selection Criteria
in Projects moving away from traditional ways. This is seen for Contractors / Consultants
selection. With regard to Contractors / Consultants Evaluation, It is a critical part in achieving
objectives. Simpson et al. (2002) explained that without careful monitoring of suppliers
performance firms are unable to assess whether their suppliers are meeting their needs and
suppliers are unable to respond to unexpressed partner needs.
The issues associated with evaluation of suppliers become problematic since a supplier is
instrumental in providing value to a firm and serving as a source of competitive advantage.
Prahinski and Fan (2007) stated that one tool used to manage suppliers is the supplier
evaluation which communicates the buying organisations’ perceptions of the suppliers’
performance and capabilities. For the buying organisations, supplier evaluation can be used
for supplier selection, supply base reduction decisions, supplier development and
benchmarking. For the suppliers, the supplier evaluation can provide information about the
buying organisation’s perceptions regarding the strengths and weakness of the suppliers’
process and performance.
It was also explained that the buying organisation’s ultimate goal in instituting supplier
evaluations is to improve the supplier’s performance and capabilities to meet the
organisation’s current and future needs. It was further explained that strategic factors such as
the supplier’s flexibility and capabilities, have become more commonly used in the
With regard to relationships, Vonderembse and Tracey (1999) explains that in manufacturing
to build more effective relationships with suppliers, organisations are using Supplier
Selection criteria to strengthen the selection process and using supplier involvement to
improve decision making and continuous improvement efforts. Procurement in improving
relationships is to be seen.
The relationship between parties is an important part of Procurement Strategy that is more
detailed and shaped as managing contracts. In viewing the Literature for SCM, it was seen
how aspects of managing relationships maintains procurement strategies in projects. Wessels
(2007) stated that organisations have come to realize that they can’t stay in business if they
cannot manage their projects to ensure better products delivery to internal and external
customers effectively and efficiently. Therefore, Procurement improves relationships when
customers and clients are satisfied with services and products.
Parties therefore intend to achieve their own objectives through procurement. Cox and
Ireland (2002) intended to overcome problems and failure to understand the circumstances
that are facing industry players which prevent clients, contractors and suppliers from
achieving their own objectives. The current problems are further compounded by the advice
espoused by government-sponsored industry reports advocating generic approaches. Their
intention was to provide practitioners with a theoretical framework for understanding supply
chains of construction industry. The attributes of buyer and supplier power, the
appropriateness of certain relationships according to the firm’s power position within the
Finally in setting a Procurement Strategy, clients should carefully examine their attributes
and contributions to contractors and consultants. Lim et al (2000) made it clear that a Clients’
financial status towards characteristics management competency and construction experience
can have significant effects upon the attainment of project success. A survey proved that
consultants and contractors are aware that client related attributes have influence on the
project outcome. Their data were collected via a mailed questionnaire. Results showed that
all clients related attributes are important and played a major role in the success of every
project.
The predicted five attributes are: 1. client sets down project objectives clearly, 2. client is
credit worthy, 3. client does not contribute to project complexity, 4. client is not litigious, and
5. client trusts project team members. This model provides consultants and contractors with a
tool to evaluate their clients. It was recommended that clients focus on the more important
attributes to ensure project success.
There is an extent of Clients contribution to a project. Chritamara et al (2001) pointed out that
there are two main parties responsible for the execution of the project, the client and the
contractor or a group of contractors. The client assigns all responsibility to the contractor.
The client's role is to respond by identifying requirements and by inspecting how well the
product accords to the specification. The contractor can start project from the conceptual
design or may start the project with almost complete design from the client.
A contract is a binding agreement between a project promoter (Owner) and a Project executor
(Contractor) to accomplish execution of a project required. Chen-Wishart (2005) defines a
contract as a promise or an agreement which is enforced or recognized by the law. It is
explained that contracts according to contract law have three elements: Promise, Agreement,
and Recognition by the law. Further, the requirements for enforcing a contract are: Signatures
of parties authorized agents, Method of Dispute Resolution and Applicable Law. Every
contract has terms and conditions.
Terms and conditions of a contract are not included to squeeze the contractor's arm to do the
work as many owners may practice. They are included for clarity on how the work could be
delivered to meet the objectives of the contract for the project. Therefore, conditions of
contract are developed to address the needs and protect the interests of both parties, the
Owner and the Contractor. This is all addressed in Contracts Law and enforcement of a
contract.
Contracts are made usually by owners on projects and suppliers / contractors accept them
after reviewing its terms and conditions. Every party agrees on the contract would like the
other party to abide the contents. This is assured when the contract is enforced. Bank
guarantees can protect purchasers against works or services performed. However, what
guarantees suppliers and contractors rights of payments and other contractual issues is the
enforcement of the contract. What enforces the contract is the Law. By law, what enforces a
contract and agreement between two parties is when one gives an offer and the other accepts
it. Furthermore, contracts are what contract law applies to although no definition of it exists
in common law.
What is important to understand is that whatever a contract might have that doesn’t contradict
the governing law becomes enforceable to both parties under the law. Habboub (2007)
provided a framework of laws and regulations in relation to Contracts and Procurement with
particular application to UAE and similar jurisdictions.
It is explained that within any jurisdiction, the collection of laws and regulations in relation to
contracts (e.g. Contracts Law) forms part of a legal system. The judicial structure in UAE is
What is more important to understand is that contract law specifies the enforcement of a
contract. It said that elements of a contract to be enforced are:
- Offer
- Acceptance
- Subject (Legal matter)
- Scope of Contract
- Invitation to treat
- Considerations
- Mutual obligations
- Intention
- Competency (Capability and Capacity of parties)
- Specification of date and venue (in some jurisdictions)
It is explained that a well known fact is that Companies don’t involve their legal department
in creative business endeavours because they are overwhelmed with tasks such as projects
planning and day to day activities to complete projects. The following are the issues of this
situation:
1. Inability to keep up with contract events such as renewal and expiration dates
2. Inability to find documents and provisions
3. Little or no reuse of work products
4. Lack of leverage during a legal or diligence audit
5. Lack of tools for the efficient review of acquisition targets
Hence, as solutions to above situations is the use of contract management systems that come
from perspectives and different tasks as stated bellow:
1. Home grown systems – such as spreadsheets, MS access which are useful for
organising
2. Document Management Systems – that prioritise and organise documents for searches
3. Enterprise Contract Management Systems – that organise events, record
communications data and give alerts to expiry and renewals
It was recommended that the above are very helpful in growing services organisations that
handle multiple services provided internally and externally. Hence, as part of project’s
procurement, managing contracts is important for successful projects management. However
the focus here is how Contracts Management as part of project’s procurement contributes to
strategic involvement and strategic objectives achievement.
This is established when Contracts management includes a proper Contracting Strategy that
specifies the relationships and roles of parties to the project. APM (1996) stated that a
contract should be designed to be the basis for successful project management. To do so it
has to be right in principle (the right contract strategy) and right in detail (right terms and
conditions). Contract Strategy is therefore needs to be set before forming the contract and the
Agreement documents.
Since forming a contract is basically an agreement between two parties (Purchaser and
Supplier) on the objectives, the theory of Contract Strategy sets the basics of forming a
contract for responsibilities, priorities, risks of the project, and payments, plus how these may
change during services to be carried. Manchester notes [3] (2006) explains that Contract
Strategy specifies terms of a contract that defines:
- Who is responsible for defining objectives and priorities, financing, innovations,
design, quality, operating decisions, safety studies, approvals, scheduling,
procurement, software, construction, equipment, installation, testing, commissioning
and managing each of these
- Who is to bear the risks of investing in the project, defining it, specifying
performance, design risks, selecting sub-contractors and their defaults, site
productivity, delays, mistakes and insurance..
How well defined are the objectives of project. Through a clear Scope of Services,
deliverables are stated and claims and variations are minimized.
2. Risks Management:
How risks are controlled and managed. Allocating of risks and responsibility are essential.
Risks borne by the purchaser (Company) are those stopping the work by forces beyond
Contractor’s control. Project investment risks, Acts of God, and Force Majeure are usually
not recoverable. APM (1998) says that “Experienced customers and analysts of completed
projects agree that only rarely should bids be invited for a contract on the basis that a supplier
must bear all the risks. The argument against this type of contract is that suppliers would have
to cover themselves by including high contingency sums in their estimates.”
In industrialized countries, risks responsibility should be allocated to the party which is best
able to manage it to suit the objectives of a project. This gives the purchaser the best value of
money. One should bear in mind that risks shall be in a way that supplier is motivated to meet
projects objectives. Once risk is identified, appropriate measures can be made to deal with it,
by avoidance, reducing its likelihood, by transferring responsibility for it, or by insuring
against it. Insuring against risks should be economic decided and insured risk should be
quantifiable, pure risk that is potential for harm not gain, and loss must be unintentional. Both
parties should know that some risks are uninsurable. Contract Strategy specifies the risk
management of a project whether transferring to one party, jointly taking the risk or
allocating it to the party that can best manage it.
When procuring a project, joint risk allocation and management can be considered. Rahman
and Kumaraswamy (2002) have conducted research through three planned questionnaire
surveys in the first phase of a broader Hong Kong based study on ‘Joint Risk Management’
(JRM). Their survey compared perceptions on both present and preferred risk allocation,
including JRM, in construction contracts. The respondents were having working experience
in Hong Kong from various professionals and practitioners representing broad groups of
academics, consultants, contractors and clients. The results showed the divergences in
perceptions on both present and preferred risk allocation, both within and between different
contracting parties.
Rahman and Kumaraswamy (2005) stated that exhaustive risk allocation cannot be achieved
through contract conditions, because all risk items cannot be foreseen at planning stage. An
effective management of unforeseen risks/events at post contract stage needs the collective
efforts of all major contracting parties. Furthermore, a theoretical construct was examining a
series of recent Hong Kong based studies on joint risk management. The results lead to the
development of a framework for building a coalesced team that includes owners, consultants,
contractors, subcontractors and suppliers. Project partners need to be conditioned, starting
with their selection processes, by incorporating appropriate relational qualities as important
selection criteria. They need to work under suitable teambuilding protocols, with flexible
contract conditions and appropriate adjustment mechanisms that would all be tailored to suit
each specific project.
The best terms of payments are those suiting the project to motivate both parties to achieve
objectives of the project. The payment terms mostly know are Fixed Price (Lump Sum)
payment, Activity Milestone payment, Unit Rate payment, Cost-Reimbursement, Target cost,
and mixed terms of payments. Whatever term of payment is used, it should be the best suiting
the nature of project. This is however the confusion in using the terms Pricing and Payments.
Blansnky et al. (2006) explain the differences between Pricing and Payment and the different
methods in both. It is stated that Pricing methods are how you come to an overall price for the
work/services. Different types of contract have different pricing methods. Some contracts can
only have one type, others can have many types. Payment Methods are how, where and when
the prices are turned to receive payments.
Lump Sum: Price for the whole of the contract, Global exposure, Only adjustable in
limited circumstances as set out in the contract, Easier and less expensive to administer,
Must allow time and information to calculate realistic price, Time and cost of tendering
can be very great, Need to get a proper breakdown of the Lump Sum.
Unit Price / Re-measurable: Price of the project calculated in accordance with actual
work done, Price established by multiplying units of work done, by unit of prices set out
in BOQ or Schedule of Rates, Used in amount of work is not certain, Employer has the
risk of number of units changing, Employer has the risk of unit price changing, Recent
trend to allow limited changes to the unit prices, Higher administration costs than lump
sum contracting.
Cost Plus / Cost – Reimbursable: Employer pays for all costs incurred by the, contractor
plus an agree fee for profit, The Fee can be fixed, fluctuating or % of actual costs, Cost
plus generally used where it is impossible to, estimate price/quantities, Usual to include
an incentive mechanism with cost, plus e.g. target costing, Sometimes only reasonable
costs can be recovered, Employers need large administrative teams to police, cost plus,
Many records are generated by cost plus.
Target Costing: Setting a Target Cost, Any costs above Target Cost means Contractor
contributes to overrun (Pain Share) and his fee is reduced, Any costs above Target Cost
means Contractor, shares in savings (Gain Share) and his fee is increased, Need
experience to set the Target Cost, Promotes good common working practices, Heavy
administrative burden, Flexible method of pricing.
Guaranteed Maximum Price (GMP): setting the maximum, Contractor bears cost of
everything in excess of GMP, Limited chance to adjust GMP, it is in effect a cap on a
lump sum cap but contractors tend to set a higher GMP than if lump sum pricing
The above process is usually decided by the Owner; however, there is no harm to decide it
with the help of Contractor since at the end he will be the receiving party. Also, whatever the
term of payment adopted, the purchaser should consider risks of these payments before
inviting the bids. Payment risks given by APM (1998) are:
a. Bonds or Guarantees are required: upon receiving bids from suppliers.
b. Effects of inflation: for lump sum contracts, upon standard cost index data,
extra payment can be made to supplier to compensate for inflation of his
costs.
c. Currency rate fluctuation: for lump sum contracts, this can be allowed in
purchaser’s budget.
d. Payments due on termination: including an option of terminating a
contract, with terms setting any payment due.
e. Payment Security: the purchaser ability to pay should be considered and
upon main supplier’s payment, sub-contractors’ payment should be made
The contract should clearly specify within the terms and conditions the LD’s terms.
Webb (1996) defined LD’s as a clause that is inserted into a contract to provide a
financial remedy to the customer for a failure by the contractor regarding some aspect of
the work. The LD’s are specified as follows:
1. The late charge method should be clearly specified; i.e. by saying “a 1% up to 10%
of contract price will be deducted from contractor’s payments” in case of delays.
2. It is necessary to review LDs on projects’ case by case basis. It should allow the use
of Milestones. Since a Contractor might meet certain milestones, he should be
No mater how clear contract Strategy is specified, disputes in a project can arise for many
other reasons. Cheung and Suen (2002) stated that Disputes are inevitable in construction
projects and Dispute Resolution Procedures such as litigation, arbitration, mediation, dispute
adviser and negotiation are widely practised. A decision-making model was created using the
Analytical Hierarchy Process (AHP) and Multi-Attribute Utility Technique (MAUT). The
model comprises four parts: selection criteria, dispute resolution strategies, collection of
utility factors and selection criteria weightings. These were gathered from an empirical data
collected through an interview survey with selected experts in the field.
It is important to set a dispute resolution in the contract before it goes through litigation
judgments. When represented to court, dispute resolution rout maybe questioned to what
extent the parties came finally to litigation. Manchester Notes [12] provides the means and
methods of Dispute resolutions in projects. Through Dispute resolution, stages of resolving a
conflict is drawn that might take the conflict into settlement before representing it to the
courts.
Further, the contract should mention whether works or services under the contract shall be
pending or disturbed during resolving a dispute. It was proven that ADR holds the best
practice being an effective method in projects.
ADR avoids legal procedures that take long period to issue a decision on settling a dispute.
Pollington (1999) explained that many legal issues such as ADR and mediation are impacting
procurement which bring extensive savings to industry. Industry should look more in trained
mediators to take role in projects. Hill (2003) explained that ADR has benefited many sectors
and specially private sectors. ADR has mainly benefited sectors that are unrepresented or
represented by lawyers primarily interested in fees. Many private sectors do not know to what
extent whether their lawyers fees are realistic upon successful cases. It was further explained
that ADR is less expensive that litigation, time effective and processed at convenience of the
parties. Parties can form the ADR as they prefer.
It is also explained that laws and regulations encourage more comprehensive use of ADR.
ADR’s might be formed in involving a third party or only higher management from both
Procurement Strategy should also specify methods and systems to deal with Claims and
Delays along with Dispute Resolution that should be properly covered. Harris and Scott
(2001) described methods of dealing with delay claims. This is followed by a discussion of
results from a survey aimed at finding out exactly how professionals in the UK construction
industry approach these difficult issues. It appeared that those who deal with delay claims in
the UK are likely to use a critical path method network to do this and generally approve of a
methodology that attempts to understand how well the contractor would have fared but for
the existence of employer-responsible delays. However, there is less agreement about who
should be said to ‘own the float’, but as is explained in their paper, it is possible for this
matter to be dealt with by the insertion of a clause in the contract documents.
Turner (1995) explains that to better control delays and claims in the project, client contractor
interface should be managed. It is explained that client and contractor are the parties to the
contract, which will be signed on their behalf by directors. However the administration of the
contract and the management of the project will be delegated to typically a project manager
and/or engineer. Both companies will delegate powers, duties and responsibilities to these
individuals to act on their behalf. When changes occur to the contract including delays to the
agreed schedule, the matter should be reported to directors if beyond the individuals control
to decide.
To avoid all this, the client and contractor should put in place an administrative procedure to
manage the contract and performance. Such procedure should include review meetings and
document control procedure. The review meeting should be as follows:
- Strategic Review meeting between client and contractor directors
- Progress review meetings between client and contractor project
managers
- Technical review meeting (design or compliance) between engineers.
Morledge et al. (2006) explains that the client should specify mechanisms for the changes in
the contract. To avoid changes, the client project manager’s objective should be to assist
contractor to be successful. He/She should understand that if the contractor is highly
performing, the clients representatives work is minimized and the other way around. If
changes are made by client then more time and change in schedule should be adopted.
However, if the contractor is delaying with no changes, there are two options for the client
regarding low performance. One is to penalize the contractor financially; two is to assist the
contractor to become better performing. It is explained that option two leads to client’s
understanding of how to address and adopt changes.
No matter what ways and methods to be adopted, the argument is that in the presence of
proper Procurement Strategy, proper ways and methods are deployed. If one of the project
objective is to complete the project on schedule, Procurement methods on handling delays
and claims ensure the objective is met either by specifying in the contract document or better
management of the contract administration phase. Blanksby [1] (2006) stated that delays in a
project affect both the client and contractor; hence, it should be clearly stated in the contact to
be bound between them. Contract also specifies provisions to extend this completion if reason
of delay is due to additional work, bad weather, employer’s delays and other circumstances.
Through Literature Project Strategy is placed through Portfolio and Program to the heart of
achieving strategic Business objectives which also form parts of the Hypothesis of the
research. SCM was found to be placed at Strategic position and linked to Corporate /
Business Strategy for projects Outsourcing. Literature also found dealing with project
procurement as part of the SCM. This modifies the hypothesis model given in Figure 1 details
of which will be given in Chapter 6. Thus, SCM was found linking Procurement to Corporate
/ Business through strategic relationships arrangement such as Alliancing and Partnering.
Procurement was found when concentrating on strategic objectives promotes for strategic
arrangements such as Alliancing, Partnering, PFI, PPP, and to some extent D/B and PIPS.
When however focusing on projects objectives it was found promoting methods such as
mainly D/B and PIPS, construction management and other procurement systems and
subsystems viewed in Literature.
We have also seen the contents of Procurement Strategy for projects which are:
1. Procurements selection and Delivery Methods and Systems of Projects
2. Relationships of Projects Parties
3. Selection and Evaluation of Contractors
4. Risk Management of projects
5. Contracts Management and Strategy
6. Handling Claims, Delays and Dispute Resolution in Projects
This section of the Dissertation is intended to show the research methodologies adopted to
respond to the open research questions from Literature findings. The open research questions
Literature led to are:
2. What are the bases of setting different Procurement Strategies and Processes in an Oil &
Gas Project?
3. What are the problems encountered in an Oil & Gas project due to a non-linked
Procurement Strategy of the Project to Corporate / Business Strategy?
4. What are the actions and strategies needed to improve and solve the problems?
The research methodologies adopted will assess the complete research objectives and test
hypothesis of Procurement Strategy for Oil & Gas industry projects in the UAE through the
data collected.
TK Co. (2005) provides the detailed information about the company. TK Co. was established
in 1999 as a public joint stock company to take over the responsibility of refining operations.
Two refineries now constitute TK Co.’s core business. Refinery 1 is located within Abu
Dhabi Area with a capacity of 88 Kilo Barrels Per Day (KBPD). Refinery 2 is located 250
Km from Abu Dhabi city toward Saudi and Qatar boarder with a capacity of 140 KBPD. The
company’s areas of operation include the refining of crude oil and condensate, supply of
petroleum products and production of granulated Sulphur in compliance with domestic and
international specifications. Refinery 1 is mainly for domestic demand and Refinery 2 is for
export to other Emirates and International market. The main products supplied are:
Liquefied Petroleum Gas (LPG)
Unleaded Gasoline (ULG) Octane 91 (Plus), ULG 95 (Special), and 98 (Premium).
Reformate and Naphtha
Aviation Turbine Kerosene (Jet Oil) and Domestic Kerosene.
Gas Oil, Straight Run Residue (SSR) and Liquid Sulphur.
TK Co. is responsible for developing the refining industry. The company is also in charge of
implementing national strategies aimed at enhancing the role of downstream industries in the
local economy of UAE. The number of Employees is near 1,800 from 40 Nationalities. TK
Co. was targeting to increase the Number of UAE nationals over 50 % by 2007.
Aiming at becoming a leader in the oil refining business, TK Co. is now working on
expanding its activities in the downstream sector. It is also exerting all possible efforts to face
the challenges of the 21st century in a rapidly-changing market. Hence, a large number of
projects are developed to facilitate the growth. Billions of UAE Dirhams (Dhs.) are invested
in these projects.
TK Co.’ Vision
To be world class, reliable, cost effective, quality focused in oil refining and related business
by implementing best practices, highest HSE standards, Environment protection and retaining
motivated professionals.
Its professional activities are governed by set of principles which define its teams’
relationships with all parties involved. The main guidelines of these principles are quality
backed by professional excellence, the highest standards of honesty, integrity and fairness.
Also, to conduct its business with highest standards of honesty, integrity and fairness to offer
opportunities for success to all its suppliers and contractors in spirit of fair competition and
mutually rewarding collaboration. It will work on enhancing its performance to meet its
overall objectives of cost control and adopt state of art equipment and technology to optimise
operations.
Finally, objectives of the Company come from actively pursuing its role towards greater
achievements for the benefit of the country and its people. It will exert all possible efforts to
seize today’s opportunities and meet tomorrow’s challenges. These efforts will result in
adding substantial increases to UAE’s refining business.
Hence, the Corporate / Business objectives of TK Co. with regard to HSE, Operations,
Organisation and Value are:
Operations:
Ensure efficient/economical operations and achieve higher rating in international
benchmarking standards.
Continually improve operations & related processes/ technologies to compete in the
refinery industry, both regionally and globally, and become a leading refiner.
Implement strategies to enhance safety, reliability, availability, operability, and
productivity of Plants.
Maintain reliable supply of refined products to local and international markets.
Value:
Enhance corporate performance/ returns through continuous improvement in business
processes, competencies, technologies and best practices.
Envisage and implement expansion, diversification and value-addition projects on
time, within cost, quality and performance parameters.
Acquire materials & services by implementing appropriate strategies to ensure on
time delivery, cycle time reduction, product/ service quality and optimum cost.
Organization:
Provide high quality working environment/ support services to enhance employee
satisfaction.
Create / maintain Company’s progressive image in the industry and society.
Enhance staff competency level through effective professional training.
Achieve UAE workforce target as per plan and develop nationals to achieve high
professional standards.
To answer the open research questions from Literature, Data is to be collected by gathering
responses from two groups. First group are professionals working in the area of Project
Procurement directly to assess their opinion on linking Project Procurement to Corporate /
Business Strategy. The second group are management staff (Projects Division Manager and
Contracts Manager) and the Project Management Staff for particular projects under study and
survey (Project Manager, Project Coordinators and Engineers) to assess their feedback on
Procurement process and practices adopted for those particular projects. Data then will be
collected through the methodologies adopted. The methodologies adopted to collect the data
are explained in the next section.
To collect the data mentioned, two methods are adopted for this research, a quantitative and
qualitative method. The methods are: 1. A Survey on Strategic Procurement, as a quantitative
method, which includes particular questions on aligning Procurement to Overall Business
Strategy (Questionnaire). 2. Case Studies, as qualitative method, for studying different
projects in Oil & Gas (either Interviews or on paper Study Survey) to assess the impact of the
Procurement practices, process and strategies undertaken in the projects.
These two methods are found most appropriate since the topic is of a highly specialized area
of Management of Projects and methods adopted should ensure responses on support to the
hypothesis, aim and objectives of the research. The first method will assist in examining
linking Procurement Strategy to Overall Business Strategy in Oil & Gas industry from
respondents working in the area of Project Procurement. The second method will assist in
assessing Procurement processes and practices in Oil & Gas Projects. This is to examine
linkage of Procurement Strategy of a particular project to Corporate / Business Strategy in Oil
& Gas to investigate the problems in the missing link.
Figure 12 (a) shows the total population requested. Figure 12 (b) shows the percentages of
Client and Contractor respondents out of the total population and (c) shows the percentages
of the two groups from the responded sample.
Total Population N= 60
Contractor
42%
Client
58%
(a)
Total Population N=60
Client
32%
No
Response
51%
Contractor
17%
(b)
Respondents (Sample) S= 29
Contractor
34%
Client
66%
(c)
Figure 12 The percentages of Total Population requested, Total Responses and Sample Responses
Questions were phrased in terms of eliciting a ‘Yes’, ‘No’ or ‘Maybe’ answer to ensure that
questions are:
- Time effective for the respondents.
- Easy to be answered.
- Exact views can be accurately obtained.
First a Contracts Manager in TK Co. was interviewed for Projects Procurement selections,
practices and bases also using the some of questions on the survey form. Then, Projects
Division Manager was interviewed on the approaches in managing projects such as higher
management involvement, Strategic objectives, Project objectives and the relations to
Procurement of the projects. Finally, project managers and different project team members of
the projects were interviewed / surveyed in detail using the questions developed. Those
members stated the Procurement routes in the projects, the procurement processes, bases of
selections projects and the problems encountered in the projects as asked. As also asked, they
gave their suggestions to improve current processes and practices.
Annexure 3 shows an example of the on paper Project Study Survey dully filled by a Project
Manager of one of the projects. From the Survey, the objectives, either Strategic or Project
based, are assessed to draw the links while viewing the Corporate / Business objectives. The
details of the projects and the surveys are given in the in the next chapter.
After Data gathering, results were analyzed to arrive at the solutions and recommendations
aimed at improving the current Procurement processes in the Oil & Gas industry in UAE and
the links intended. The analysis of results is also in the next chapter.
This chapter is intended to present, analyse and discuss the data collected from the methods.
This section will present the results from first methodology, analyse them and provide a
discussion in line with Literature findings.
Tables 3 and 4 show the responses to the Questionnaire developed on linking Procurement
Strategy to Business Strategy (Table 3) and the results of the contents that effectively link
Procurement Strategy to Business Strategy (Table 4).
In Table 3, the ranks of strategic activities of Procurement are given in hierarchies as per the
number of respondents agreeing.
Number of Respondents
Strategic Procurement N = 29 out of 60 Total
Rank Activities for Oil & Gas (19 Client and 10 Contractor)
Projects Agreeing Agreeing
Agreeing
(Client) (Contractor)
1 Improves Business and 15 10 25
organisational relationships
4 Requires developments 7 10 17
Table 3 Responses to Linking Procurement Strategy to Business Strategy in Oil and Gas
Figure 13 shows the chart to further illustrate the hierarchies of responses from Client,
Contractor and both. Numbers 1 - 7 on the x-axis represent the activities in Table 3.
30 Should be towards
achieving Overall
2
Client Contractor Total Business
25 Objectives
Number of Respondents
Lacks advanced
3
20 Strategies
Agreering
Requires
4
15 developments
Should involve
10 5
Higher
Management
decisions
5
Should be part of
6 strategic plans,
0 vision and mission
1 2 3 4 5 6 7 Affects Project's
7
Performance
Strategic Procurement Activities in Oil & Gas
Figure 13 Numbers of Respondents Agreeing to Strategic Activities of Procurement Strategy in Oil & Gas
Figure 14 shows the chart to further illustrate the hierarchies of responses from Client,
Contractor and both. Numbers 1 - 7 on the x-axis represent the contents in Table 4.
Payment Terms
20
Risk
4
15 Management
10 Relationship
5
Management
5 Dispute
0 Resolution,
6
claims &
1 2 3 4 5 6 7 delays
Questions Project
7
(Contents of Procurement Strategy) Performance
Figure 14 Numbers of Respondents Agreeing to Contents of Procurement Strategy in Oil & Gas
The results of data presented previously will be analyzed and discussed in this section.
From Table 3 above, the quantitative data on strategic activities of Procurement in Oil & Gas
as per the number of respondents agreeing are analyzed in percentages as in Table 5 for the
discussion purpose.
Table 5 % of Responses to Linking Procurement Strategy to Business Strategy in Oil and Gas
Figure 15 shows the chart to illustrate the response percentages. Detailed discussion of the
analysis is in the following section.
Client 79% 68% 37% 37% 47% 42% 26% Should be part of
6 strategic plans,
Contractor 100 80% 100 100 70% 60% 40% vision and mission
Total 86% 72% 59% 59% 55% 48% 31%
Affects Project's
7
Strategic Activities Performance
Figure 15 % of Responses Chart to Linking Procurement Strategy to Business Strategy in Oil and Gas
STUDENT ID: 20050014 PAGE 64
6.1.1.2 Discussion (Linking Procurement to Business Strategy)
From the percentages above we can see that a high percentage of respondents (86%) are for
adopting Procurement Strategy to improve contractor/client relationships. It was seen from
Literature the link of SCM to Corporate / Business Strategy for Outsourced Projects, Freytag
(2002) and Stuart (1997). Then, it was explained that Supply Chain Strategy is basically how
clients and suppliers work together to achieve overall business objectives, Elmutti (2002),
Ellram et al. (2004), Lan (2003) and Ogdenet al. (2005) Then, it was seen from Literature the
importance relationship management to link Procurement to SCM, Cheung (2006) and
Khalfan (2005). Hence, Procurement Strategy is linked to Supply Chain and Business
Strategies in that aspect.
In summation, at least focusing on Strategic objectives can reveal the acceptance of linking
Procurement Strategy to Corporate / Business Strategy. It can be said that the surveys
confirm acceptance of the Hypothesis of the research or as was found in Literature that
placing Procurement Strategy to Overall Business Strategy is to be through SCM to close the
loop. This was also suggested by one respondent (see next section).
From Table 4 above, the quantitative data on strategic contents of Procurement in Oil and
Gas as per the number of respondents are analyzed in percentages as in Table 6.
Figure 16 shows the chart to illustrate the response percentages. Detailed discussion of the
analysis is in the next section.
To confirm the strategic objectives of Procurement Strategy, from the percentages above, we
can see the highest percentage (100% of respondents) accept that an Effective Procurement
Strategy should include Contract Strategy. It was seen from Literature that (Sifri (2003),
Turner (2004) and APM (1998) suggested Procurement Strategy should include Contract
Strategy that is basically the document which clients and suppliers agree on to achieve project
objectives.
Also, high percentages of respondents agree that Procurement Strategy should include
Procurement Systems and Methods, and Financial rights and Payments (97% and 93% of
respondents, respectively). We have seen from Literature – Chritamara et al (2001), Dulaimi,
Ling, Ofori and Silva (2003), Koskela (2003), Koolwiji and Vrijhoef (2005) and H. M.
Treasury (2007) – that different procurement methods and systems suggest Procurement
Strategy should include on procurement methods. We have seen examples of Procurement
Systems and Sub Systems from Kumaraswamy (2006).
We can also see other items of Effective Procurement Strategy being agreed to by
respondents – 66% of respondents accept inclusion of Risks Management as also seen in
Literature by Rahman and Kumaraswamy (2002 & 2005). A total of 83% of respondents
agreed to inclusion of Relationship Management. This was seen in the earlier section.
79% of respondent agree on inclusion of Dispute Resolution, Claims and Delays; which
Literature explained in detail, Hill (2003), Pollington (1999), APM (1998), Harrisand Scott
(2001), Cheung and Suen (2002) and Blanksby (2006).
This modifies the hypothesis model given in Figure 1. Figure 17 shows the modified model
of the links.
In-House
Program & Portfolio Management Project Management Projects
Business Strategy
This section will present the results from the second methodology, analyse them and provide
a discussion in line with last section (Methodology – 1) and Literature review.
The case studies in detail serve the contents of Procurement Strategy that achieve Corporate
Business Objectives seen. Alterations and improper utilization of such contents can cause
problems that are to be seen in the projects
First the details of the projects studied are given. Then, the project team, detail results from
survey and problems will be shown. Refer to Annexure 1 for the phases of a major project in
Oil & Gas to understand the discussion. In the details, the difference between Scope of
project and Project objectives is that the latter is the outcomes of the project executing the
scope. Budget is the estimated cost and Price is the lowest or the awarded price.
The first case studied for investigating problems to Procurement Strategy and its contents is
“Replacement of Halon System from Company’s Refineries Fire Extinguishing Systems
project”. Table 7 summarizes the details of the project. Company here refers to TK Co.
Project Title Replacement of Halon from Company’s Refineries Fire Extinguishing Systems
Complying with international HSE standards.
International HSE standards stated that Halon decomposes toxic chemicals that are
harmful to human beings and unsafe to environment when spread out to put up fire
Business Strategic although it is a noble gas because.
Objectives Hence, feasibility Study was not required.
Company issued a policy to replace Halon with a safer gas that is noble and friendly
to Human beings and Environment by Oct. 2007.
Project to be carried out in Competition of tender to Contractors and Consultants.
Total Budget is Dhs. 12 Mil. (2 Mill for FEED, 5 Mil. for EPC of Refinery 1 and 5
Mil. for EPC of Refinery 2)
Project Budget and FEED price was Dhs. 2 Mil.
Price
EPC price was Dhs. 11 Mil. (6 Mil. For Refinery 1 and 5 Mil. for Refinery 2)
Total price was 13 Mil. (1 Mill over budget)
Stage of the project FEED is completed. EPC phase is on going
Scope of FEED included studying alternative gas agent and systems for both
Refineries as follows:
- Carry detailed survey and data collection of existing buildings and operations
- Carry out Qualitative Risk Assessment (QRA) for installation of the proposed
Agent with the detection and alarm system
- Develop a design of the system for the proposed gas agent including codes and
international standards.
Project Scope - Submit full Engineering Design, reports and presentation to Company
Scope of EPC included FEED verification and implementation and replacement of
Halon with the new agent including all systems modification and /or replacement.
Contractor shall strictly comply and carry works in accordance with company
procedures and the following international codes and standards:
- NFPA: National Fire Alarm code, National Electric code and Life safety code
- BS: British standards for Fire Alarm System
EN54: European Fire Alarm Standard
Removing Halon gas from the Refineries fire fighting systems by October 2007.
Replacement with a new Agent.
The proposed Agent and Systems shall be as per international standards specified.
Project Objectives
Achieve the targeted estimated cost which budget was allocated for.
To complete the project within schedule. Maximum duration is 1 year from award.
Warranty period for all works, materials shall be 12 months from completion.
Table 7 Details of Halon Replacement Project
The case study of the project carried on surveying the Project manager, Project Coordinator
and Contracts Engineer using the case study from in Annexure 3. After the survey, the details
of project were given as follows:
Procurement selection was based on procedures of FEED and EPC. Feasibility Study of this
project was not required because the Strategic objective was to comply with International
HSE standards. Hence, the project was assumed feasible.
Three contracts were made: one for FEED and two EPC contracts for Refinery 1 and 2
separately. All Tenders were on competitive bidding. Contracts types were all Lump Sum
price basis even for the FEED. Payments were on progress monthly basis against breakdown
of the Total Lump Sum price.
The FEED was completed in Feb., 2006 and EPC’s was awarded on 10 March, 2007. EPC
will be completed in Feb., 2008.
FEED Engineer (Consultant), on lump sum basis, carried designing of the system that will
replace the existing system of Halon. Consultant suggested “Inergen” gas to replace Halon
and provided all necessary system modifications.
Then, both EPC’s (for Refinery 1 and 2) were tendered out on the outcomes of FEED All
EPC bidders were required to verify the FEED during Tendering. Discussion of and problems
in the project are given next.
Consultant carried the design although Company didn’t specify only one gas to be proposed.
When the gas was approved by Company and FEED phase was completed earlier, it was
complained by EPC bidders that Inergen was solely supplied by one agent in the UAE. This
agent was also participating in the Tender which prevented other bidders from supplying it.
Company strategic policy of tendering is to allow competitive bidding for EPC from different
companies especially for a Major project. Other bidders however didn't want to bid against
the bidder solely supplying Inergen because purchasing should have been through it.
Therefore other gases had to be accepted or Tendering will end up on a Single source basis.
Also, every gas is having its own designing system. There are gases found to have exactly
similar systems to Halon and require no system modification. Basically these gases would
require just discharging Halon and use the same system. So, it was hard to implement the
design provided by Consultant because it concerned Inergen only. This design had to be
changed concerning other gases or only Inergen is to be supplied. To achieve a Company
strategy on Tendering, Consultant was asked to consider other gases and perform designs
accordingly. Every gas got accepted by Company a design was to be formed for it.
The Consultant did not accept changes in design with the same price because their design was
approved by Company. For the change, and since FEED was Lum Sum, Consultant asked
extra charges to perform the design concerning other gases. The additional price was found to
be the same as of original price for Inergen. Company did not accept the additional price
from Consultant. Lum Sum price was problematic for change. If FEED was on unit rates
basis, the change could have been calculated.
Then, designing other gases systems were requested from the EPC bidders. It was conveyed
to EPC bidders during Tendering that any bidder propping a gas different than Inergen has to
perform the design and Engineering of it completely. However this can be waived from
bidders proposing Inergen as the design of it is available from Consultant.
Again bidders proposing gases (decomposing of toxic chemicals) like Halon were excluded
from the tender. Only gases that are of the same components to Inergen which are called Inert
gases (not decomposing toxic chemicals) were accepted.
Another bidder proposing Argonite gas was the lowest for Refinery 1 EPC contract. This
EPC contract exceeded the budget for it by 1 Mil. This is because designing was part of the
EPC. The bidder who was lowest for Refinery 2 EPC and not requiring design formation was
even higher in price than the one preformed the design. Many reasons can be associated to
this; one reason is maybe the bidder didn’t want to take both contracts for limitation of
resources or other reasons.
The second project studied for investigating problems to Procurement Strategy is “Inter-
Refinery Pipeline (IRP) project”. Table 8 summarizes the details of the project.
The case study of the project carried on surveying the Project using the case study from in
Annexure 3. Projects Division Manager and Contracts manager also referred to this project
during the interview; refer to Annexure 4 & 5. After the survey and interviews, the details of
project were given as follows.
Procurement selection was based on procedures of Feasibility Study, FEED, PMC and EPC
as separate tenders. Four contracts were made: one for Feasibility Study, one for FEED, one
for PMC and one for EPC. The Project Management Consultancy (PMC) contract was made
to manage all phases and contracts of the project.
All Tenders were on competitive bidding. Contracts types were all Lump Sum price basis
except for FEED and PMC which were on unit rates based on man-hour estimates. Payments
were on progress monthly basis against breakdown of the Total Lump Sum / Estimated price.
The Feasibility Study was completed in Sept., 2003. The FEED was completed in June, 2004
and EPC was awarded on 05 April, 2005). EPC will be completed in Feb., 2008.
FEED Engineer (Consultant) carried complete designing of the pipeline. Then, EPC was
tendered out on the outcomes of FEED. All EPC bidders were required to verify the FEED
during Tendering. No EPC bidders were excluded. Discussion of and problems in the project
are given next.
Consultant completed the FEED design and accordingly the successful contractor carried the
EPC works. After, EPC was awarded; company has introduced a new product in the market
(ULG 91). ULG 91 has to be incorporated in the new pipeline which would result in a
dramatic change in the FEED. ULG 91 had to replace ULG 98 as the demand increase of
ULG 91 will reduce the demand of ULG 98. FEED 2 was introduced to be carried to design
the inclusion of the new product. The basis of FFED 2 should be FEED 1. The EPC was into
the scenario of suspension or completion. Company decided to keep EPC running and upon
completion of FEED 2, a variation order to EPC can be issued or a new EPC (EPC 2) can be
started. Company was also in the scenario of either issuing a variation order for FEED.
However, that was not seen feasible as the basis of FEED was the Feasibility study which
didn’t include ULG 91.
The final decision was to have another Feasibility study to incorporate ULG 91 and
accordingly a new FEED to be carried and a new EPC. This results in keeping the current
FEED and EPC running. Hence the project will end up have eight contracts. Four contracts
are for the current Feasibility Study, FEED, EPC and PMC. Additional four contracts will be
for Feasibility Study of including ULG 91, FEED, EPC and PMC for it.
This may result in a problem because the second Feasibility Study may suggest changes to
original FEED and EPC which are being built since original EPC is near completion. The
new design might suggest of removal along with additional facilities. This will result in
partial lose of original EPC items. Contracts Manager was asked for this (Refer Annexure 5).
As can be seen from the interview, he responded that there were many alternatives and the
best one was found to separate the FEED and EPC for the new product. This is in line with
management instruction and to allow for further competitive bidding strategy.
The third project investigated for the problems to Procurement Strategy is “Operational
Improvement to Process Units at Refinery 1”. Table 9 summarizes the details of the project.
The case study of the project carried on surveying the Project manager, Project Coordinator
and Contracts Engineer using the case study from in Annexure 3. After the survey, the details
of project were given as follows.
Procurement selection was based on procedures of FEED, PMC and EPC as separate tenders.
Feasibility study was not carried as the project only asks for modifications of existing units.
So, project was assumed feasible.
Two contracts were made: one for FEED and one for EPC. All Tenders were on competitive
bidding. Contracts types were all Lump Sum price basis even for the FEED.
Payments were on progress monthly basis against breakdown of the Total Lump Sum price.
PMC was part of FEED. The FEED consultant was required to carry the Project Management
of the EPC works also. The FEED was completed in May, 2001 and EPC’s tendering is still
on. EPC will be awarded sometime in June, 2008.
EPC was tendered twice. As seen before, FEED was completed sometime in 2001. First EPC
was started in 2002 and was cancelled after a long tendering cycle (around 1 ½ years).
The problems in cancelling the EPC tendering were:
1. Many bidders were incapable of undertaking the EPC works as the project call
for supplying huge number materials and equipments.
2. Participation ended in short number of bidders (2 bidders)
3. Both bidders didn’t agree on providing overall warranty. Warranty was to be
provided separately on every item only. As the items were to be installed
separately and since there is not integrity, the whole works can’t be granted to
be completed to the satisfactory of company.
Hence, Company decided that this tender to be cancelled and re-tendering to take place. Re-
tendering took place in July 2007. Bidders list finalized having seven bidders. Three bidders
declined to bid. The final technical bids were received from four bidders. The fourth bidder
was excluded because of requesting a cost plus contracting basis and not Lump Sum type of
contract. Company’s strategy to keep fair, equal and consistent bidding has resulted in
excluding this bidder as the rest agreed on Lump Sum price basis. Now, three bidders’
technical bids are being evaluated.
Because of re-tendering, FEED’s PMC part was not valid anymore. FEED Consultant didn’t
want to carry PMC on the open period and didn’t also validate FEED being too old. For
doing so, Consultant asked almost more than double price. Thereafter, Company looked for a
PMC consultant to validate the old FEED and manage the EPC works when awarded.
Company felt that there was no time to go on competitive bidding on PMC as award of EPC
can be done anytime. The bidder who was excluded for requesting a cost plus contract was
requested and accepted to carry PMC. Now, the PMC services tender from this bidder as
single source is being finalized. This might turn in a whole problem as the bidder not
accepting the contract type now will manage it on the basis of conflict.
The fourth project investigated for the investigating problems to Procurement Strategy is
“Refinery 2 Expansion Project”. Table 10 summarizes the details of the project.
The case study of the project carried on surveying the Project manager, Project Coordinator
and Contracts Engineer using the case study from in Annexure 3. Annexure 3 shows the
responses from the Project Manager. After the survey, the details of project were given as
follows.
Procurement selection was based on procedures of Feasibility Study, FEED, PMC and EPC
as separate tenders. Feasibility study was completed in June, 2007. FEED tendering started in
July, 2007.
One contract is made for Feasibility Study. Feasibility Study was on competitive bidding and
so will be all Tenders of next phases. FEED tendering is on going. FEED was tendered out on
units rates based on man-hour rates. FEED award is projected to happen in March, 2008. EPC
and PMC Tendering will start upon completion of FEED. Contracts types will be Lump Sum
for EPC and units rates based on man-hours rates for PMC.
Payments were on progress monthly basis for Feasibility study, however adopted for
milestone activities based on percentages of total estimated price for the FEED. This is
adopted when one of the bidders rejected progress payments tender.
Feasibility Study consultant carried complete study of Refinery expansion setting the basis of
all designs. FEED started on the basis of Statement of Requirements from Feasibility study.
Discussion of and problems in the project are given next.
This project is considered the most critical and strategic project to company. Upon
completion of this project, strategic objectives such as meeting international and local
demands and increase profitability, production, and capacity of units will be achieved. The
project (EPC) is forecasted to be completed by 2010.
Feasibility Study has delayed the start of FEED because of changes in requirements from
Company. Feasibility Study has taken double time its original completion period. Award of
Feasibility Study was in May, 2005 with completion period of one year. However, as seen
before completion took place in June, 2007. Three variation orders were issued to the
Feasibility study until completed.
FEED started on competitive basis of consultants and technical bids evaluation have been
completed. Upon approval of the technical evaluation, prices will be invited from consultants.
As seen before, some bidders of FEED didn’t accept monthly progress payments tendering.
Then this was then changed to percentage milestones as preferred. This is logical since the
contract type is based on units rated of man-hours.
Next section is concluding findings of common problems that are seen in Procurement
practices in the projects studied. It will be seen how these problems affected most of the
projects to achieve objectives that are inline with the reviewed Strategic objectives of TK Co.
From the details and the responses of the case studies of projects given above, the
Procurement practices mostly identified in the projects were observed to be:
1. The split contracts of the project phases appeared in all projects
2. Contract Types of being Lump Sum appeared in many projects
3. Payment methods of progress payment appeared in almost all projects
4. Traditional methods of Tendering Procedures and lowest price wins
These practices were informed to be procedural; however they were seen permanent to
almost all projects without being adapted to different project objectives and strategic
objectives for the particular project. In the first Case Study, Lump Sum price for FEED was
seen to be problematic when changes were made. Having a Lump Sum contract type couldn't
Also, to link strategic objectives, the above further entail combination of FEED to EPC (D/B
method seen in Literature). The separation of FEED and EPC was seen problematic in
achieving strategic objectives of the project. Some strategic objectives of the project in case
study 1 were:
Complying with HSE standards
Allowing for competitive advantage
Because FEED was separated from EPC, it limited the competitive advantage in the EPC
when Inergen was proposed and seen solely supplied by one party. Hence, Strategic objective
of completive bidding was about to be altered. Also, HSE standards didn't specify one gas,
so choosing multiple gases didn't contradict the strategic objective of complying to
international HSE.
In Case Study 2, when the new product (ULG 91) was introduced. If D/B (FEED + EPC) was
considered to be implemented from the start, as also agreed by the Contracts Manager, there
wouldn’t be a need for FEED 2 and EPC 2. The changes in FEED 1 and EPC 1 that would
result in loss wouldn’t have to be a concern. The strategic objective of receiving the best
value of cost is altered.
Further, in Case Study 3, we have seen the problems of FEED being invalid for the long
period of EPC. The combination of the two would have carried the validity together. The
strategic objectives of increasing productivity, increasing capacity and optimizing processing
are not achieved when EPC was seen not able to be carried.
There are no many problems can be seen in Case Study 4; however following the same
manner would also result in the same problems. Feasibility Study for the project was seen
gone through almost three variations. Again FEED and EPC will carry problems if same
procedures of the other three projects are carried. This is the most critical and strategic
project to Company so lessons should be learnt from other projects. Also, although contract
type was on units rates based on man-hours, still progress payments was retained. As
complained by bidders this was then changed to percentages of milestones payments.
Fixing these above Procurement practices and process, in the projects studied and not linking
them to specific project needs, results in problems to achieve projects objectives that are
inline with strategic objectives seen. Table 11 below shows the resulting problems appeared
or likely to appear because of these practices as expressed in the survey.
The above problems additionally affect achieving the projects objectives, as seen in the case
studies, and ultimately achieving strategic objectives of the projects.
Suggestions from respondents for these problems along with the advanced strategies
addressed in Literature to improve the current Procurement processes for Oil & Gas projects
will be covered in details in the next Chapter, Recommendations (Chapter 7).
This section of the Dissertation is intended to propose recommendations and offer solutions
to the problems investigated in research methodologies (Cases Studies). This is also by
referring to the objectives and hypothesis of the research supported by Literature and the first
research methodology developed (Linking Procurement to Business Strategy).
However, hypothesis model was modified to include SCM in the process for attaining
strategic goals and involvement of Procurement (Refer Figure 17, Chapter 6).
Hence, in order to maintain the link to Business Strategy and achieve Strategic objectives, it
is recommended that Oil & Gas Project Procurement Strategy should adopt advanced
strategies mainly in the following areas:
Hence, the details of these identified Procurement Strategy areas with recommendations for
improvement will be given next.
For Major Projects, it is recommended that Oil & Gas industry considers the D/B method
clearly explained in Literature. We have seen the FEED and EPC phases of an Oil & Gas
Major project. Although EPC refers to Engineering, Procurement and Construction, this is a
different method from the D/B method used in the Building and Construction industry, as
suggested in Literature.
An Oil & Gas ‘Major Project’ still carries a FEED phase which represents the Design phase
in Building and Construction industry. Therefore, FEED and EPC phases can be combined
together to eliminate problems for Major Projects resulting from separating Design and
Implementation phases, as highlighted in Literature. There is a confusion, which needs to be
clarified, that many practitioners in Oil & Gas think that EPC is similar to D/B in construction;
however, as shown above, Design phase is separated from Implementation since FEED phase
is separated from EPC. Therefore, EPC is basically only the Construction phase; and the
Engineering part of it is just the actual implementation of the Engineering Design (FEED).
Hence it is recommended that Oil & Gas adopt the D/B method used in Building and
Construction industry in Procuring for a Major Project which suggests that Design and
Implementation of a project is handed to one Contractor. However, the current method can be
kept if desired for small projects where minor Design or no Design is required.
Procurement Strategy also entails Procurement Systems. We have seen in Literature the
advanced strategies proposed, such as what Cheung et al (2001) offered for procurement
selection by enhancing objectivity. The systems they selected (MAUT and the AHP) as
critical procurement selection criteria and procurement strategies commonly used in Hong
Kong can be suggested here.
Literature also suggested several criteria and systems for selecting contractors and suppliers.
It also offered contractor's evaluation criteria. Hence, it is suggested that Oil & Gas gives up
traditional methods in selecting contractors and evaluating the bids based on lowest price
scenario.
Their system first evaluates the list of contractors by matching their qualifications with
specific project conditions. A short list of eligible contractors is thus selected and MCDSS
then compares the current capabilities of short-listed contractors and their plans for the
project under consideration, to select the most appropriate contractor. It is claimed that the
system can be easily modified to adopt specific conditions of the project and also to facilitate
the decision maker in explaining the reasons for the elimination of excluded contractor.
7.2 Contracts Management and Strategy for Oil & Gas Project
Contracts Management and Strategy was seen in Literature as part of Procurement Strategy
(APM, 1998). Contracts Management and strategy cover the relationship and responsibilities
of parties in the contract document, Contract Type, Terms & Conditions, Pricing, Payment,
Liquidated Damages and Risk Management which should clearly placed in the contract. As it
was stated in Literature these contracts should be formed for smooth execution of the project
Reference is also made to the study carried by Oyegoke (2001) on the framework for
construction management contracts practices in the UK and the US by exploring the main
delivery methods. As construction management contracting types, processes and procedures
and interaction between construction manager and other stakeholders, Contracts Management
systems within each practice and between both practices; the distribution of responsibilities
and risks both in pre-construction and during the construction stages; and allocation of
responsibility in both practices were examined.
As they identified it, the superior performance of Japanese contractors is attributed to their
working practices which were characterized by the use of a larger workforce on site, detailed
planning, close working relationships with their subcontractors, and an overriding focus on
time certainty. it is not clear whether these issues deal directly with Procurement Strategies.
As also suggested from the surveys Procurement processes should consider different actions
to resolve problems in projects. Table 12 below shows all suggestions by respondents to
resolve the problems in the Procurement Process for the projects and managing contracts.
Understanding and linking Financial Systems (i.e. Pricing Basis, Payments Terms
2
and Bank Guarantees) to Scope of Project.
3 Motivating Contractors / Consultants through Incentives systems not just
penalties. Proper Risks allocation and control.
The added Value and Collaborative Contracts Management: Better understanding
4
of responsibilities of parties.
5 The right Tendering and Contractor / Consultant Selection practices
Table 12 Suggestions and Actions by in Procurement Processes for Oil & Gas projects Surveyed
7.4 Project Procurement Strategy in Oil & Gas to Realise Business Strategy.
It is seen in Table 12 the suggestions in Procurement processes for Oil & Gas projects
identified by the projects respondents. In summary, the contention is that Procurement
processes in Oil & Gas should realise the Business needs and Strategy. This is established
when Procurement Strategy links the objectives of a project to Business objectives.
In addition, the responses emanating from the survey of an Oil & Gas Project respondents as
summarized in Table 12 are recommended to not only solve the problems but also to develop
the effective Procurement Strategies (linked to Corporate / Business Strategy) for projects.
Oil & Gas should consider such suggestions from its practitioners.
We have seen the emphasis in which perceptions on Corporate / Business objectives where
altered in the problems of the projects studied. It was also seen the procurement problems in
managing FEED and budget of the project. The recommendation here is that a balance
between Strategic objectives, project objectives, costs should be obtained in order to achieve
the best value of the project to Company. A balanced management will optimise the value to
Company through proper Procurement Strategy. As for project Strategy, linking Project
needs and objectives to business requirements should be formed at end of every stage such as
One of the methods as also Literature suggests is the strategy review at every stage of project
development. In the first project studied, Company’s strategy doesn’t constrain specific gas to
be designed rather the most valuable gas to replace Halon to comply with HSE standards.
Therefore the gases which require no system change to Halon were worth to be selected for
the optimum gas identical to Halon. Therefore, it is recommended here to manage the
procurement involved during FEED phase and the involvement in the EPC phase. The use of
proper procurement strategies such as D/B can help achieving this desire. If FEED was
included in the EPC, the optimum design that’s handled by the same Contractor / Consultant
can follow the EPC. As the strategic objectives are aligned with project objectives, they
should be aligned to Procurement Strategy to receive the necessary viability of FEED to EPC.
Covering the above and specifically for a project, a Procurement Strategy selection checklist
is developed in Annexure 6. However, the developed Model of Procurement Strategy for
projects in Oil & Gas Industry to realize Corporate / Business Strategy is shown Figure18.
This is suggested to Oil & Gas projects; however, also applicable to projects concerning other
industries endeavour management by projects.
Outsourcing
Strategy Business Management
Strategic
Objectives
Achievement
Supply Chain Portfolio
Strategy Strategy
Strategic Relationships
- Alliancing Portfolio Management
- Partnering
Procurement Program
Project
Strategy Strategy
Objectives
- Procurement Methods and Systems Achievement
- Contractors Selection Criteria
Program Management
- Contract Strategy
- Managing Relationships Project Management
- Managing Claims, Delays and variation
- Dispute Resolution
Project
Strategy
Figure 18 Procurement Strategy Model Suggested for Oil and Gas Projects
As we have seen in the analysis and discussion section, Procurement Strategy should be
linked to overall Business Strategy. As we have also seen in Literature, Johnson and Scholes
(1999) stated that Business Strategy is likely to be concerned with long term direction of an
organisation, especially for a big multinational company; Strategy facilitates achieving a
prominent position of becoming the “industry standard” recognized by suppliers and buyers.
Also we have seen, relationship management is what links procurement to SCM and hence to
Overall Business Strategy; as seen in Cheung’s (2006) explanation of sustainable supply
chain which requires a proactive relationship management. Hence it is recommended that Oil
& Gas consider improving its relationships with Contractors and Suppliers which can be
applied through Procurement Methods. The second part of the Hypothesis to the Dissertation
suggests that an Effective Procurement Strategy includes Procurement Systems, Procurement
Methods, Contract Strategy, Contract Types, Contractor/Client Relationships, Financial
All the above are recommendations to current procurement processes and practices for
projects in Oil & Gas for implementation. Also the above, once implemented in Oil & Gas
and used in other industries should support the hundreds of on-going projects in UAE and the
retention of Consultants and Contractors expertise, share and potential interest from all over
the world in the development of this country.
With regard to Procurement and Project performance, a little research was carried in this
regard. We have seen Literature addressed the issue and related it to procurement. Xiao and
Proverbs (2002) tackled the issue examining contractors’ performance in different countries
to distinguish their own strengths and weaknesses to improve their competitiveness
accordingly. However, this was to serve the purpose of contractors’ selection criteria and not
the performance of the project. This is highlighted in the conclusions in the next chapter.
However, a Procurement Strategy that avoids Project-stage ambiguities and helps to drive
Projects to success in terms of performance was not achieved through research. This was not
the main aim of the research; however, the issue was highlighted in Literature with rather
poor results in research methodologies. Hence, this particular view is recommended for
further research. Future research can examine Procurement Strategy's effect on Project
Performance. Whether effective Procurement Strategies improve Project Performance can be
further assessed. This is an important area for further research as it can be seen to complete
the full picture of Project Procurement. This research aimed at Strategic effect of
Procurement in an organisation. Inline with it if a research in the suggested area is carried
will give the complete research on procurement from top (Strategic position) to down
(Project performance) of an organisation.
The general phases and activities of a Major Project in Oil & Gas industry are:
OTHER COMMENTS
Procurement in this research covers all commercial aspects of a project (i.e. Materials, Contracts
Management, Tendering, Bidding, Awarding and Contract Administration)
Feasibility Study scope: To study the feasibility of expanding the Refinery. The
study should include all possible ways to extend the current refinery capacity from
120 KBPD to 250 KBPD.
BRIEF SCOPE
FEED scope: The design based on feasibility study should include all required
process units additions and modifications of existing facilities, utilities and
processing units. The study shall come up with full engineering design to the
required works for expansion.
EPC: to implement FEED of expanding the refinery.
What is the stage of the project Increase capacity of the Refinery
Meet the international and local demand of
(Conceptual Design, FEED, EPC) and whether
refined oil products
(Under Tendering, or % Completed) Reduce loads on current units
Increase production, Revenue and
profitability through optimum processing
Not provided
What is the Budget, Costs and Prices of the Project?
What are the Corporate / Business Objectives for Feasibility Study completed. FEED phase of
undertaking the Project? the project is on going. EPC phase is still not
initiated.
What are the Project specific Objectives? Turnkey engineering, detailed design,
procurement, construction, installation, pre-
commissioning, commissioning, testing and
supply of spare parts required for the
expanded facilities.
Develop units, equipments and utilities
required for the expansion integrated with
existing system.
Any Project Objectives for other purposes than Project will Comply with Environmental
those of business (i.e. Legal, Environment, Political standards
… etc)?
What is the Procurement Method selected (i.e. EPC model is option pursued with
Partnering, Design (SOR or FEED), Build (EPC), competitive bidding.
Design and Build (FEED & EPC), Prime
Contracting, …etc) Please explain
What were the Payment Terms selected (i.e. Both Milestone and Progress payment for
Milestone payments, Progress payments, percentage services provided
payments, Reimbursement, …etc) Please explain
What is the basis of Payment Terms selected? (i.e. Contract Standard in accordance with
Contract Standard, Traditional, Policy, Nature of Company procedures
project, some specific reasons) – please explain
Does the contract specify any Risks allocated to There is limited liability clause for FEED
Company? Or all Risks are placed to Contractor / engineering and Technology provided
Consultant? Please explain
What are schemes specified in the Contract for Company Standard covered in Agreement
handling Claims, Delays, and Disputes? (i.e. Agreed
with contractor, standard contract, changed with the
nature of contract, Strategic …etc)
Did any Contractor / Consultant during tendering Negotiations to reach mutual Terms and
complain for not accepting any commercial matters Conditions were protracted
such as (Procurement method, Contract Type,
Terms and Conditions, Risks allocated, Payment
Terms, etc)? If any, how were they resolved?
Do you think any of the Procurement activities / Today’s Market is difficult due to high
processes specified above caused any problems to commodity prices and high demand for Oil
the project in achieving Project or Strategic & Gas services Projects
objectives? Please explain how.
Any general problems occurred in the project (i.e. None Yet. Just entering FEED
Delivery of Materials, Delays, Progress,
Performance, Claims, Disputes on the Contract,
Payments ….etc) Please state the problems and
bases.
Thank you so much for your time, your responses will greatly help in developing the research.
Name: Philip Harrison
Designation: Senior Project Manager
Qualifications: B. Tech., MICHEME, C. Eng.
Signature: 23.01.08
1. PROJECT TITLE :
2. OBJECTIVES :
Strategic Objectives for the Project:
Project Specific Objectives:
7. PAYMENT METHOD :
Progress
Milestones
Other, _ _ _ _ _ _ _ _ _
Reason for selection / Link to Objectives:
8. ADVANCE PAYMENT
Yes
No
10. WARRANTY
12 Months
More than 12 Months
Special Warranty
None
1. APM (1998), “Contracts Strategy for Successful Project Management”, A Guide for
Project Managers on Best Practice for the Procurement of Goods and Services, The
Association for Project Management (APM), The APM Group Ltd., U.K., ISBN 0
9531590 1 9.
2. Blanksby, M., Michelle N. and Kerur, S. [1] (2006), “Money and Time in Contracts”,
Masons Galadari, Lecture Presentation, Module 5, ENG01505, Commercial &
Procurement, The British University in Dubai, BUiD, Dubai, UAE.
3. Blanksby, M., Michelle N. and Kerur, S. [2] (2006), “Supply Chain and Risk Control”,
Masons Galadari, Lecture Presentation, Module 5, ENG01505, Commercial &
Procurement, The British University in Dubai, BUiD, Dubai, UAE.
5. Cheung, S., Lam, T., Leung, M. and Wan, Y. (2001), “An analytical hierarchy Process
Based Procurement Selection Method”, Construction Management and Economics,
Taylor & Francis Ltd., Volume 19, Issue: 4, pp. 427-437.
8. Chritamara, S., Ogunlana, S. and Bach, N. (2001), “Investigating the Effect of Initial
Scope Establishment on the Performance of a Project through System Dynamics
Modelling”, Engineering, Construction and Architectural management, Blackwell
Science Ltd., Volume: 8, Issue: 5-6, pp. 381-392.
9. Cox, A. and Ireland, P. (2002), “Managing Construction Supply Chains: the Common
Sense Approach”, Engineering, Construction and Architectural management, Blackwell
Science Ltd., Volume 9, Issue: 5-6, pp. 466-467.
10. Dulaimi, M., Ling, F., Ofori, G. and Silva, N. (2002), "Enhancing Integration and
Innovation in Construction”, Department of Building, School of Design and
11. Ellram, M., Tate, W. and Billington, C. (2004), “Understanding and Managing the
Services Supply Chain”, Journal of Supply Chain Management, The Institute for Supply
Management, Inc., pp. 17-32.
13. El – Sayegh, S., (2006) “Evaluating the Effectiveness of Project Delivery Methods’,
Civil Engineering Department, American University of Sharjah, Sharjah, United Arab
Emirates, original: pp. 457-465, Summary: The Joint International Conference,
Construction Culture, Innovation and Management (CCIM),The British University in
Dubai, UAE, pp. 79-80, ISBN: 0 947974 53 9.
15. Gareis, R. (2000), “Program Management and Project Portfolio Management: New
Competences of Project – Oriented Organizations”, University of Economics and
Business Administration, PROJEKT MANAGEMENT Group, Franz – Klein – Gasse,
Vienna, Austria, PMI Symposium, Houston, pp. 1-8.
16. Habboub, A. (2007), “Framework of Laws and Regulations in Relation to Contracts and
Procurement – With Particular Application to UAE and Similar Jurisdictions”, Lecture
Presentation, Module 5, ENG01505, Commercial & Procurement, The British
University in Dubai, BUiD, Dubai, UAE.
17. Harris, R. and Scott, S. (2001), “UK Practice in Dealing with Claims for Delay”,
Engineering, Construction and Architectural Management, Blackwell Science Ltd.,
Volume 8, Issue: 5-6, pp. 317-324
20. Khalfan, M., McDermott, P., Vrihoef, R. and Asad, S. (2005), “The Effect of
Procurement on the Integration of the Supply Chain within the Construction Industry”,
21. Koolwijik, J. and Vrijhoef, R. (2005), “Procurement Strategies for Dynamic Control of
Construction Projects and Supply Chain”, TNO Building and Construction Research,
Centre for Process Innovation in Building and Construction, Delft University of
Technology, The Netherlands, In AS Kazi (Ed.), Systemic innovation in the
management of construction projects and processes. Espoo, Finland, pp. 122-134.
22. Koskela, L. (2003), “Is structural change the primary solution to the problems of
construction?”, Building Research and Information, Spon Press, Routledge, Taylor and
Francis Group, Volume: 31, Issue: 2, pp. 85-96.
23. Kumar, J. A. (2007), “Client - Contractor Relations: How changing from “Master –
Slave” to a “Master – Master” relationship can lead to more successful project
delivery”, PM World Today, Vol. IV, Issue III, pp. 1-3.
27. Lim, E. and Ling, F. (2002), “Model for Predicting Clients’ Contribution to Project
Success”, Engineering, Construction and Architectural management, Blackwell Science
Ltd., Volume 9, Issue: 5-6, pp. 388-395.
28. Love, P., Irani, Z., Cheng E., and Li, H. (2002), “A model for supporting inter-
organisational Relation in the Supply Chain”, Engineering, Construction and
Architectural management, Blackwell Science Ltd., Volume 9, Issue: 1, pp. 2-15.
29. Mahdi, I., Riley, M., Fereig, S., and Alex, A. (2002), “A Multi-Criteria Approach to
Contractor Selection”, Engineering, Construction and Architectural management,
Blackwell Science Ltd., Volume 9, Issue: 1, pp. 29-37.
31. Manchester Notes [7] (2006), “The Types of Contracts”, University of Manchester
Lecture Notes, Module 5, ENG01505, Commercial & Procurement Module, The British
University in Dubai, BUiD, Dubai, UAE.
32. Manchester Notes [12] (2006), “Contracts Management, Breach of Contract and
Disputes & Claims”, University of Manchester Lecture Notes, Module 5, ENG01505,
Commercial & Procurement Module, The British University in Dubai, BUiD, Dubai,
UAE.
36. Mineva, E. (2005), “Contracts management Systems: Tackling The Legal”, Contract
Management Center. www.ncmahq.org, accessed on: Nov., 01, 2007.
38. Morledge, R., Smith, A. and Kashiwagi, D. (2006), “Building Procurement”, Blackwell
Publishing Ltd, Oxford, U.K., ISBN-10: 0-632-06466-8.
39. Ogden, J., Petersen, K., Carter, J., and Monczka, R. (2005), “Supply Management
Strategies for the Future: A Delphi Study”, The Journal of Supply Chain Management,
Institute for Supply Management Inc., Blackwell Science Ltd., Volume 41, Issue: 3, pp.
29-48.
43. Pollington, C. (1999), “Legal and Procurement Practices for Sustainable Development",
Building Research and Information, Routledge, Taylor and Francis Group, Volume:
27, Issue: 6, pp. 409-411(3).
44. Prahinski, C. and Fan, Y. (2007), “Supplier Evaluation: The Role of Communication
Quality”, The Journal of Supply Chain Management, Blackwell Science, Volume: 35,
Issue: 3, pp. 33-39.
48. Seely, M. and Duong, Q. (1997), “Measuring Project Procurement Performance in the
Public Sector”, Public Works and Government Services, Ottawa, Canada. Paper, pp1-18
50. Simpson, Penny M., Siguaw, Judy A. and White, Susan C. (2002), “Measuring the
performance of suppliers: an analysis of evaluation processes”, The Journal of Supply
Chain Management, Blackwell Science Ltd., Volume: 38, Issue: 1, pp. 29-41
53. TK CO. (2004), “PMC Services Tender Documents”, Tender Documents Procurement
and Contracts Division, TK CO., Abu Dhabi, UAE.
54. TK CO. (2005), “Company Profile”, Booklet, TK CO., Abu Dhabi, UAE.
55. TK CO. (2006), “Performance Management System”, Booklet, TK CO., Abu Dhabi,
UAE.
56. Turner, J. R. (1995), “The Commercial Project Manager: Managing Owners, Sponsors,
Partners, Supporters, Stakeholders, Contractors and Consultants”, McGraw-Hill
International (UK) Ltd., ISBN 0-07-707946-9.
57. Turner, J. R. (1999), “Improving the Process for Achieving Strategic Objectives”, The
Handbook of Project-Based Management, McGraw-Hill International (UK) Ltd., 2nd
Edition, ISBN 0-07-709161-2.
59. Vonderembse, M. and Tracey, M. (1999), “The Impact of Supplier Selection Criteria
and Supplier Involvement on Manufacturing Performance”, The Journal of Supply
Chain Management, Blackwell Science, Volume: 35, Issue: 3, pp. 33-39.
60. Webb, A. (1996), “Managing Innovative Projects”, 2nd Edition, International Thomson
Business Press, ITP, High Holborn, London, U.K., ISBN 1-86152-038-7.
61. Wessels, D. J. (2007), “The Strategic Role of Project Management”, PM World Today,
Vol. IV, Issue II.
62. Wong, C., Holt G., and Harris P. (2001), “Multi-criteria Selection or Lowest Price?
Investigation of UK Construction Clients’ Tender Evaluation Preferences”,
Engineering, Construction and Architectural management, Blackwell Science Ltd.,
Volume: 8 Issue: 4, pp. 257-271.
63. Xiao, H., and Proverbs, D. (2002) “Construction Time Performance: An Evaluation of
Contractors from Japan, the UK and the US”, Engineering, Construction and
Architectural management, Blackwell Science Ltd, Volume: 9, Issue: 2, pp. 81-89.