PRESIDENT’S OFFICE
REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT
SEPTEMBER 2021
______________________________________________________________________________
ERB Reg. No. 139,27/09/2011 MPR 20
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No. 20
Contract No.: AE/092/2019/2020/HQ/CR/05 September 2021
CONTROLLED DOCUMENT
Revision Record
Rev Date By Summary of Changes Chkd Aprvd
.
______________________________________________________________________________
TABLE OF CONTENTS
TABLES................................................................................................................................................................4
A. EXECUTIVE SUMMARY..........................................................................................................................6
A.1.PROGRAMME & PROGRESS..................................................................................................................7
A.1.1. PROGRAMME............................................................................................................................................7
A.1.2. WORKS PROGRESS SUMMARY....................................................................................................................7
A.1.3. MOBILISATION STATUS & PHYSICAL PROGRESS........................................................................................8
A.2.1. CONTRACT PRICE...................................................................................................................................12
A.2.2. CURRENT MONTH’S IPC........................................................................................................................12
A.2.3. CASHFLOW FORECAST............................................................................................................................12
A.3.MAIN ISSUES, RISKS & RECOMMENDATIONS..............................................................................13
A.4.CONSULTANTS MANAGEMENT.........................................................................................................13
B. MAIN REPORT..........................................................................................................................................16
B.1. PROGRAMME & PROGRESS................................................................................................................16
B.1.1. DESCRIPTION OF WORKS........................................................................................................................16
B.1.2. CONTRACTORS MOBILISATION/ESTABLISHMENT......................................................................................18
B.1.3. ENGINEERS CAMP & FACILITIES/ESTABLISHMENT...................................................................................18
B.1.4. MATERIAL SOURCES...............................................................................................................................18
B.1.5. PROGRESS OF MAJOR ACTIVITIES...........................................................................................................18
B.1.5.1. CLEARING & GRUBBING......................................................................................................................19
B.1.5.2. COMMON EXCAVATION........................................................................................................................20
B.1.5.3. G3 FILL...............................................................................................................................................21
B.1.5.4. G7 IMPROVED SUBGRADE....................................................................................................................23
B.1.5.5. G15 IMPROVED SUBGRADE..................................................................................................................25
B.1.5.6. PIPE CULVERTS...................................................................................................................................26
B.1.5.7. BOX CULVERTS....................................................................................................................................28
B.1.5.8. U-DRAINS............................................................................................................................................29
B.1.5.9. OPEN DRAINS......................................................................................................................................30
B.1.5.10. KERBSTONES......................................................................................................................................31
B.1.5.11. PAVING BLOCKS.................................................................................................................................32
B.1.5.12. C1 STABILISED SUBBASE....................................................................................................................33
B.1.5.13. CRR CRUSHED STONE BASE..............................................................................................................34
B.1.5.14. PRIME COAT......................................................................................................................................35
B.1.5.15. ASPHALT............................................................................................................................................36
B.1.6. MAJOR ACTIVITIES PLANNED FOR THE FORTHCOMING MONTH..............................................................37
B.1.7. SERVICES (UTILITIES).............................................................................................................................37
B.2. SOCIAL, ENVIRONMENTAL AND HEALTH & SAFETY................................................................38
B.2.1. ENVIRONMENTAL & SOCIAL MANAGEMENT ISSUES.................................................................................38
B.2.2. STD HIV/AIDS AND CORONA VIRUS ALLEVIATION MEASURES IMPLEMENTATION................................38
B.2.3. WORKER EMPLOYMENT..........................................................................................................................38
B.2.4. HEALTH AND SAFETY MANAGEMENT.......................................................................................................38
B.3. CONTRACT ADMINISTRATION..........................................................................................................39
B.3.1. DESIGN REVIEW STATUS.........................................................................................................................39
B.3.2. DELAYS, DISRUPTION & FRUSTRATIONS.................................................................................................39
B.3.3. SUBCONTRACTORS..................................................................................................................................39
_________________________________________________________________________
_________________________________________________________________________
CHARTS
_________________________________________________________________________
ABBREVIATIONS
DPr Director of Projects
JV Joint Venture
PE Project Engineer
PM Project Manager
RE Resident Engineer
SC Supervising Consultant
_________________________________________________________________________
A. EXECUTIVE SUMMARY
The report forms part of the Consultancy Services for Construction Supervision of Government City Roads to
Bitumen Standard (51.2km), Lot I and II in Dodoma. This is the supervision consultant’s monthly progress report
No. 20 which provides an update on the Contractors and Consultants activities undertaken during the reporting
period; 1st of September 2021 to 30th of September 2021.
The road project is located in the outskirts of Dodoma City about 17Km from the City Centre along Dodoma –
Morogoro road. The implementation of the project is intended to upgrade the Government City roads from
gravel/earth standard to bitumen standard.
Government City roads were opened in April 2019. Some sections of the roads (about 22Km) were built to gravel
standard while the rest are in earth condition. Maintenance operations carried out now on the roads are Routine &
Recurrent Maintenance, involving re-gravelling, grading, and de-silting of drainage structures.
Detailed Engineering Design and Preparation of Tender Documents for the upgrading of Government City roads
to bituminous standard was done in-house by TARURA Staff in collaboration with Individual Consultants. The
design was completed in May 2019.
The Government City Roads are designed to be built as Dual Carriage Way over a length of 22.4 Km and as
Single Carriage Way over a length of 28.8Km. The Pavement is designed using the Ministry of Works Pavement
and Materials Design Manual 1999 (PMDM) while Geometric design is designed using the Road Geometric
Design Manual by the Ministry of Works, 2011.
The design has resulted into the following pavement including improved subgrade layers: -
50 mm Asphalt Concrete
150mm CRR Base Course
200mm Subbase C1
_________________________________________________________________________
A.1.1. Programme
a. The Contractor submitted the Revised Construction Programme Rev 01 under GCC Clause 34.1 on the
23rd of June 2020.The Resident Engineer approved the Revised Construction Programme on the 26 th of
June 2020.
e. The Contractor submitted an Updated Construction Program Rev02 to reflect the Extension of Time and
a new completion date of 31st of December 2021. This was approved by the Consultant on the 23 rd of July
2021.
(Refer to Appendix 5.1 for abbreviated GCC clause 34.1 programme which shows the progress (%
completed of current activities including the critical activities).
a. Physical Progress
According to the Updated Construction Programme Rev 2. Time Lapsed is 87% (20 months out of 23 months
total)
Overall Works Progress (Including General Items) is 85% Achieved against 88% Planned. The Slippage is
3%. The Contractor is behind program.
Permanent Works Progress (Excluding General Items) is 83% Achieved against 88% Planned. The
Contractor is behind program and the slippage is 5%. The items of Permanent Works that are behind
schedule are:
Kerbstones
Walkways
_________________________________________________________________________
Financial Progress
Sixty Two Percent (62%) of the Contract Value has been spent to date, and the Expenditure on the on the works
Contract is detailed below:
1. Total Advance Amount was TZS 13,217,046,907.02 and this was fully paid on the 11th of March 2020.
2. Total Amount Certified is TZS 69,504,888,837.35
3. Total Amount paid to date including Advance is TZS 54,697,624,061.97
4. Total Amount Outstanding is TZS 14,807,264,775.38
Seventy-One (71%) of the Contract Value has been spent to date, and the summary of the Supervision Contract
Expenditure is shown below:
1. Total Amount Invoiced: TZS 931,035,023.11
2. Total Amount Paid to Consultant: TZS 706,586,958.27
3. Total Amount Outstanding to Consultant: TZS 224,448,064.84
_________________________________________________________________________
a Clearing, Grubbing & Removal of Topsoil 100% 100% 51.20 51.20 51.2 km
b Common excavation to spoil 100% 100% 182,321 182,321 182,321 m3
c Additional Common Excavation 72% 72% 131,594 131,594 131,594 m3
Total for Common Excavation 172% 172% 313,915 313,915 313,915 m3
d Rockfill 100% 100% 1,045 1,045 1,045 m3
e G3 Fill 100% 100% 346,311 346,311 346,311 m3
f Additional G3 Fill 96% 86% 331,255 331,255 299,271 m3
Total for G3 Fill 196% 186% 677,566 677,566 645,582 m3
g G7 Improved Subgrade 100% 98% 51.2 51.2 50.2 km
h G15 Improved Subgrade 100% 98% 51.2 51.2 50.2 km
i Stabilized Subbase Layer 95% 97% 51.2 48.6 49.7 km
j Crushed Aggregate Base Course 91% 92% 51.2 46.6 47.1 km
4 BITUMINOUS LAYERS & SEALS 80% 85%
a Prime Coat 82% 92% 51.2 42.0 47.1 km
b Bituminous Base Course and Asphalt Concrete Surfacing 79% 79% 51.2 40.4 40.4 km
5 OPEN & COVERED DRAINS 85% 76% -
a Covered Concrete Lined Drains 100% 100% 21,948.0 21,948 21,948 km
b Open Concrete Lined Drains 60% 35% 56.0 33.6 19.6 km
6 CONCRETE KERBING & WALKWAYS 59% 15%
a Kerbing 62% 20% 242 150 48.4 km
b Walkway 57% 10% 91,599 52,211 9,160 m2
7 ANCILLARY ROADWORKS 14% 2% -
a Supply, install, test and commission Street Lights 15% 6% 1,409.0 211.4 84.5 No.
b Landscaping & Grassing 15% 0% 1,000.0 150.0 - m2
c Road Signs 15% 0% 853.0 128.0 - No.
d Road Markings 0% 0% 181.0 - - km
_________________________________________________________________________
b. EARTH WORKS
Common Excavation
The overall percentage achieved on this item is 172% against the Design Review Estimate quantities. The
amount of common excavation increased due to unexpected unsuitable material and the high-water table
encountered in the southern section mainly on the Primary Roads. This condition has also been encountered
in the Northern Section.
G3 Fill
The cumulative quantity done to date is 645,582 cubic metres against a Design Review Quantity of 346,311
cubic metres. The percentage cumulative progress is 186%.
G7 Improved Subgrade
The cumulative quantity done to date is 50.2km out of a total of 51.2km. The percentage cumulative progress
is 98% versus a planned of 100%.
c. PAVEMENT LAYERS
d. BITUMINOUS LAYERS
Prime Coat
The cumulative quantity done to date is 47km out of a total of 51.2km.The percentage cumulative progress is
92% versus a planned of 82%. The Contractor is ahead of schedule on this activity.
Asphalt
The cumulative quantity done to date is 40km out of a total of 51.2km. The percentage cumulative progress
is 79% versus a planned of 79%. The Contractor is on track on this activity.
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
e. STRUCTURAL WORKS
Pipe Culverts
The Contractor has constructed 99 out of 106 Pipe Culverts to date. This activity is 93% complete. The
Contractor is behind on this activity.
Box Culverts
This activity is 100% complete.
Service Ducts
This activity is 100% complete.
Subsoil Drains
The Contractor has installed 27% (454m out of 1654m) of the proposed subsoil drains on Roads B18 & C1.
Kerbstones
The cumulative progress on this item is 48.4km (20%) out of a planned of 150Km (62%). The Contractor is
42% behind on this activity.
Paving Blocks
The cumulative progress on this item is 9,160sqm (10%) out of a planned of 52,211sqm (57%). The
Contractor is 47% behind on this activity.
Refer to Appendix 5.2 Visual Progress Chart.
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
VARIATIONS - -
PRICE ADJUSTMENT - -
CHANGES IN LEGISLATION - -
CLAIMS - -
Relocation of Existing Damage to roadworks if the water 40% of DUWASA relocation works is still
Services - DUWASA pipes under the roads are not outstanding. Assistance from the Prime
chambers and water relocated into the provided service Minister’s Office has been sought and
pipes. ducts. TANESCO have resumed works. DUWASA
is in the process of engaging a Subcontractor
to construct the chambers.
Delayed Progress on The Open Drains fall on the critical The Contractor has been advised to expedite
Construction of Drainage path of the Construction Program construction of open drains, kerbstone, and
Works: Open Drains, and if delayed will result in Delay to walkways by increasing resources in various
Kerbstones & Walkways the Intended Completion Date. The correspondences and site progress &
completed roadworks stands the planning meetings. The Contractor in Site
risk of being damaged by the rains Progress Meeting No.19 promised to bring in
if the open drains are not 3 more teams for open drains and increase
completed before the rainy season. the subcontractor’s team on paving blocks.
Installation of kerbstones and
paving blocks for walkways have
also fallen on the critical path and
they would affect the intended
completion date.
2. Technical/Planning Meetings
A Planning Meeting was held on the 22nd of September 2021.
3. Monthly Progress Meetings & Site Meetings
Nineteen Monthly Progress Meetings have been held to date and Monthly Progress Meeting No.19 was
held on the 30th of September 2021 at the Contractor’s Site Office at Mtumba at 0900Hrs.
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
4. Reports
The Consultant has submitted the following reports according to the Terms of Reference:
a. AFTZ038/R01 – Inception Report was submitted on 21 February 2020
c. AFTZ038/R03 – Monthly Progress Report No. 1 for the month of February 2020 was submitted on the 15 th of
March 2020
d. AFTZ038/R04 – Monthly Progress Report No.2 for the Month of March 2020 was submitted on the 15 th of April
2020
e. AFTZ038/R05 – Monthly Progress Report No. 3 for the Month of April 2020 was submitted on the 15 th of May 2020
g. AFTZ038/R07 – Monthly Progress Report No.4 for the Month of May 2020 was submitted on the 15 th of June 2020
h. AFTZ038/R08 – Monthly Progress Report No.5 for the Month of June 2020 was submitted on the 15 th of July 2020
i. AFTZ038/R09 – Monthly Progress Report No.6 for the Month of July 2020 was submitted on the 15 th of August
2020
j. AFTZ038/R10 – Monthly Progress Report No.7 for the Month of August 2020 was submitted on the 15 th of
September 2020
l. AFTZ038/R11 – Monthly Progress Report No.8 for the Month of September 2020 was submitted on the 15 th of
October 2020
m. AFTZ038/R12 – Monthly Progress Report No.9 for the Month of October 2020 was submitted on the 15 th of
November 2020
n. AFTZ038/R13 – Monthly Progress Report No.10 for the Month of November 2020 was submitted on the 15th of
December 2020
o. AFTZ038/R14 – Monthly Progress Report No.11 for the Month of December 2020 was submitted on the 15th of
January 2021
p. AFTZ038/R15 – Monthly Progress Report No.12 for the Month of January 2021 was submitted on the 15th of
February 2021
q. AFTZ038/R16 – Monthly Progress Report No.13 for the Month of February 2021 was submitted on the 15th of
March 2021
r. AFTZ038/R17 – Monthly Progress Report No.14 for the Month of March 2021 was submitted on the 15th of April
2021
s. AFTZ038/R18 – Monthly Progress Report No.15 for the Month of April 2021 was submitted on the 15th of May
2021
t. AFTZ038/R19 – Monthly Progress Report No.16 for the Month of May 2021 was submitted on the 15th of June
2021
v. AFTZ038/R21 – Monthly Progress Report No.17 for the Month of June 2021 was submitted on the 15th of July
2021
x. AFTZ038/R23 – Monthly Progress Report No.18 for the Month of July 2021 was submitted on the 15th of August
2021
y. AFTZ038/R24 – Monthly Progress Report No.19 for the Month of August 2021 was submitted on the 15th of
September 2021
5. Measurements
Measurements ongoing in preparation for IPC No.9.
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
6. Quality
During the period of this report NO new Borrow Pit has been investigated nor tested. Production of SP12.5
Asphalt Aggregates, Concrete Aggregates and CRR Aggregates are ongoing at Chinangali II Quarry and
Crusher Plant. Sub-Contractors are out-sourcing concrete aggregates.
C1/CM Cement Treated Layers constructed in the Northern Section. CRR Production and Construction for
Secondary Roads in the Northern Section were done. SP12.5 HMA Concrete Wearing Course production
along various Roads.
MC 70 Prime Coat and Production of Concrete/Precast elements and Concrete Open line drains did take
Place.
7. Administration
Correspondences to the Employer, to the Contractor, from the Employer and from the Contractor for this
reporting month are listed in Appendix 9.
8. Site Instructions
Nil
5 TABLE A.4.9: List of Site Instructions in September 2021
9. Drawings
Nil
10. Notices
Nil
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
B. MAIN REPORT
The Contractor continues to maintain the Engineer’s Office and Laboratory until these structures are
handed over to client at the end of the Contract. The Contractor continued with Pavement Layers in the
Northern Section. Construction of Open Drains/Catchwater Drains on Secondary & Primary Roads
continued in the southern section. The installation of kerbstones and paving blocks was done on the
southern section secondary and primary roads.
The project is being carried out in the vicinity of existing and functioning Government offices and there is
need to accommodate the public traffic and community at large to minimize any disruptions to normal traffic
flow and community activities.
FORECAST QTY
ELEMENT/ACTIVITY/ITEM UNIT BOQ OTY REVISED BOQ OTY
TO COMPLETION
Project Road Length km 51.20 49.80 49.80
Section Length
Lot 1 Primary Roads (Dual) km 22.40 22.40 22.40
Lot 2 Secondary Roads (Single) km 28.80 27.40 27.40
Carriageway Width
Dual m 14.00 14.00 14.00
Single m 7.00 7.00 7.00
Bike Lane Width
Dual m 2.71 2.40 2.40
Single m 2.71 2.40 2.40
Walkway Width
Dual m 1.50 1.20 1.20
Single m 1.50 1.20 1.20
Earthworks
Common Excavation m3 69,680.00 182,321.00 320,000.00
G3 Fill m3 280,730.00 346,311.00 670,000.00
G7 Improved Subgrade (150mm) m3 97,890.00 78,932.00 119,036.00
G15 Improved Subgrade (150mm) m3 109,510.00 119,036.00 119,036.00
Pavement
C1 Sub base (200mm) m3 102,520.00 97,382.00 97,382.00
CRR Base (150mm) m3 83,725.00 80,026.00 80,026.00
Asphalt Concrete Surfacing -
SP12.5 Superpave (30mm to 50mm) m3 25,480.00 24,570.00 24,570.00
Concrete Kerbing m 242,030.00 229,130.00 229,130.00
Side Walk
Prefabricated concrete paving blocks m2 109,049.00 91,599.00 91,599.00
Drainage
Concrete Lining-Open Drains m3 5,095.00 17,386.00 17,386.00
Concrete Lining-Covered Drains m3 24,247.00 10,957.00 8,765.28
Steel t 461.00 1,849.00 1,042.66
Precast concrete slab-ditch cover m2 72,800.00 37,013.00 37,013.00
Culverts
Circular m 6,395.00 3,025.00 2,700.00
Box - Concrete C30 m3 2,253.00 1,780.00 2,136.29
Steel t 185.00 240.00 189.84
Road Marking m 180,800.00 180,800.00 180,800.00
Road Signs no. 853.00 853.00 853.00
Solar Street Lights no. 739.00 1,408.00 1,408.00
Solar Traffic Lights no. 2.00 2.00 2.00
Landscaping m2 197,310.00 1,000.00 1,000.00
The status on mobilising extra equipment as agreed in the High-Level meeting of the 15 th of December
2020:
During the period of this report NO new Borrow Pit has been investigated nor tested. Production of SP12.5
Asphalt Aggregates, Concrete Aggregates and CRR Aggregates are ongoing at Chinangali II Quarry and
Crusher Plant. Sub-Contractors are out-sourcing concrete aggregates.
CM Cement Treated Layers constructed along Various Roads and at Intersections/ Road Junctions along
Road Section C US Embassy Production and Construction for Secondary Roads and cycle lanes were
done. SP12.5 HMA Concrete Wearing Course production along various Roads.
MC 70 Prime Coat and Production of Concrete/Precast elements and Concrete Open line drains did take
Place.
The progress on the major activities that are currently being executed are represented using summary
tables and charts below. The Progress on Permanent Works is 83% versus a planned of 88% and is
behind schedule by 5%. The main reasons why the progress behind is:
1. Low productivity on Concrete lined open drains, kerbstones, and paving blocks
2. Delayed Payments/Cashflow challenges
3. Delays in Renewal of VAT Exemption
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
NO OF PLANNED
MONTH-YR QTY QTY ACTUAL QTY
MONTHS (Programme Rev 1)
1 Feb-20 2.05 2.048 1.00 1 -1.048
2 Mar-20 5.63 7.68 3.00 4.00 -3.68
3 Apr-20 5.63 13.312 6.00 10.00 -3.31
4 May-20 6.14 19.456 0.00 10.00 -9.46
5 Jun-20 5.63 25.088 12.00 22.00 -3.09
6 Jul-20 6.14 31.232 4.00 26 -5.23
7 Aug-20 5.63 36.864 8.40 34.4 -2.464
8 Sep-20 6.14 43.008 0.00 34.4 -8.608
9 Oct-20 6.14 49.152 16.80 51.2 2.048
10 Nov-20 2.05 51.2 0.00 51.2 0
11 Dec-20 0.00 51.2 0.00 51.2 0
TOTAL 51.20 51.20
51.2
% PLANNED VS ACTUAL PROGRESS
% PLANNED % ACTUAL
NO OF CMULATIVE
MONTH-YR
MONTHS CUMULATIVE SLIPPAGE (%)
MONTHLY MONTHLY CUMULATIVE
(Programme Rev 1)
1 Feb-20 4% 4% 2% 2% -0.02
2 Mar-20 11% 15% 6% 8% -0.07
3 Apr-20 11% 26% 12% 20% -0.06
4 May-20 12% 38% 0% 20% -0.18
5 Jun-20 11% 49% 23% 43% -0.06
6 Jul-20 12% 61% 8% 51% -0.10
7 Aug-20 11% 72% 16% 67% -0.05
8 Sep-20 12% 84% 0% 67% -0.17
9 Oct-20 12% 96% 33% 100% 0.04
10 Nov-20 4% 100% 0% 100% 0.00
11 Dec-20 0% 100% 0% 100% 0.00
B.1.5.3. G3 Fill
The cumulative quantity done to date is 645,582 cubic metres. The percentage cumulative progress is 186%. The
quantity of G3 Fill has increased due to the increase in Common Excavation above.
PROGRESS - G7
PLANNED(KM) ACTUAL(KM) SLIPPAGE(KM)
MONTHLY CUMULATIVE MONTHLY CUMULATIVE CUMULATIVE
NO OF PLANNED
MONTH-YR QTY QTY ACTUAL QTY
MONTHS (Programme Rev 1)
1 Feb-20 0 0.0 0 0 0
2 Mar-20 0 0.0 0 0 0
3 Apr-20 0 0.0 1.6 1.6 2
4 May-20 4 3.6 2.0 3.6 0
5 Jun-20 5 8.7 2.1 5.7 -3
6 Jul-20 5 13.8 2.7 8.4 -5
7 Aug-20 5 18.4 5.6 14 -4
8 Sep-20 5 23.0 12.0 26 3
9 Oct-20 5 28.2 6.0 32 4
10 Nov-20 5 32.8 1.0 33 0
11 Dec-20 5 37.9 0.0 33 -5
12 Jan-21 5 42.5 1.0 34 -8
13 Feb-21 5 47.1 0.0 34 -13
14 Mar-21 4 51.2 0.0 34 -17
15 Apr-21 0 51.2 0.0 34 -17
16 May-21 0 51.2 1.0 35 -16
17 Jun-21 0 51.2 12.2 47 -4
18 Jul-21 0 51.2 3.1 50.3 -1
19 Aug-21 -1 50.7 0.0 50.3 0
20 Sep-21 0.5 51.2 0.0 50.3 -1
TOTAL 51.2 50.3
51.2
% PLANNED VS ACTUAL PROGRESS
% PLANNED % ACTUAL
NO OF CMULATIVE
MONTH-YR CUMULATIVE
MONTHS MONTHLY MONTHLY CUMULATIVE SLIPPAGE (%)
(Programme Rev 1)
1 Feb-20 0% 0% 0% 0% 0%
2 Mar-20 0% 0% 0% 0% 0%
3 Apr-20 0% 0% 3% 3% 3%
4 May-20 7% 7% 4% 7% 0%
5 Jun-20 10% 17% 4% 11% -6%
6 Jul-20 10% 27% 5% 16% -11%
7 Aug-20 9% 36% 11% 27% -9%
8 Sep-20 9% 45% 23% 51% 6%
9 Oct-20 10% 55% 12% 63% 8%
10 Nov-20 9% 64% 2% 64% 0%
11 Dec-20 10% 74% 0% 64% -10%
12 Jan-21 9% 83% 2% 66% -17%
13 Feb-21 9% 92% 0% 66% -26%
14 Mar-21 8% 100% 0% 66% -34%
15 Apr-21 0% 100% 0% 66% -34%
16 May-21 0% 100% 2% 68% -32%
17 Jun-21 0% 100% 24% 92% -8%
18 Jul-21 0% 100% 6% 98% -2%
19 Aug-21 -1% 99% 0% 98% -1%
20 Sep-21 1% 100% 0% 98% -2%
PROGRESS - G15
PLANNED(KM) ACTUAL(KM) SLIPPAGE(KM)
MONTHLY CUMULATIVE MONTHLY CUMULATIVE CUMULATIVE
PLANNED
NO OF
MONTH-YR QTY (Programme QTY ACTUAL QTY
MONTHS
Rev 1)
1 Feb-20 0.0 0.0 0 0 0
2 Mar-20 0.0 0.0 0 0 0
3 Apr-20 0.0 0.0 1.0 1.0 1
4 May-20 1.5 1.5 1.0 2.0 0
5 Jun-20 5.1 6.7 2.8 4.8 -2
6 Jul-20 5.1 11.8 2.8 7.6 -4
7 Aug-20 4.6 16.4 3.4 11 -5
8 Sep-20 4.6 21.0 15.0 26 5
9 Oct-20 5.1 26.1 6.0 32 6
10 Nov-20 4.6 30.7 1.0 33 2
11 Dec-20 4.6 35.3 0.0 33 -2
12 Jan-21 5.1 40.4 1.0 34 -6
13 Feb-21 4.6 45.1 0.0 34 -11
14 Mar-21 3.6 48.6 0.0 34 -15
15 Apr-21 2.6 51.2 0.0 34 -17
16 May-21 0.0 51.2 1.0 35 -16
17 Jun-21 0.0 51.2 12.2 47 -4
18 Jul-21 0.0 51.2 2.0 49.2 -2
19 Aug-21 -1.0 50.2 1.1 50.3 0
20 Sep-21 1.0 51.2 0.0 50.3 -1
TOTAL 51.2 50.3
51.2
% PLANNED VS ACTUAL PROGRESS
% PLANNED % ACTUAL
NO OF CUMULATIVE CMULATIVE
MONTH-YR
MONTHS MONTHLY (Programme MONTHLY CUMULATIVE SLIPPAGE (%)
Rev 0)
1 Feb-20 0% 0% 0% 0% 0%
2 Mar-20 0% 0% 0% 0% 0%
3 Apr-20 0% 0% 2% 2% 2%
4 May-20 3% 3% 2% 4% 1%
5 Jun-20 10% 13% 5% 9% -4%
6 Jul-20 10% 23% 5% 15% -8%
7 Aug-20 9% 32% 7% 21% -11%
8 Sep-20 9% 41% 29% 51% 10%
9 Oct-20 10% 51% 12% 63% 12%
10 Nov-20 9% 60% 2% 64% 4%
11 Dec-20 9% 69% 0% 64% -5%
12 Jan-21 10% 79% 2% 66% -13%
13 Feb-21 9% 88% 0% 66% -22%
14 Mar-21 7% 95% 0% 66% -29%
15 Apr-21 5% 100% 0% 66% -34%
16 May-21 0% 100% 2% 68% -32%
17 Jun-21 0% 100% 24% 92% -8%
18 Jul-21 0% 100% 4% 96% -4%
19 Aug-21 -2% 98% 2% 98% 0%
20 Sep-21 2% 100% 0% 98% -2%
The Contractor has constructed 99 pipe culverts out of a total of 106. This activity is 93% complete.
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
The Contractor has completed the construction of box culverts, with 10 Box culverts done . Table B1.5.7 and Chart B1.5.7
below show the details:-
B.1.5.8. U-Drains
The Contractor has constructed 22.4km of U-Drain out of a total of 22.4km. This activity is 100% complete. Table B1.5.8 and
Chart B1.5.8 below show the details.
This is now the most critical activity. The cumulative progress on this item is 36%(19.8km) versus a planned of
60%(33km). The Contractor is behind schedule, and he has been requested to increase resources. The
Contractor promised to increase the teams. Table B1.5.9 and Chart B1.5.9 below show the details
NO OF PLANNED
MONTH-YR QTY QTY ACTUAL QTY
MONTHS (Programme Rev 1)
B.1.5.10. Kerbstones
The contractor has constructed 48.7km(20%) out of 150km(62%) to date. The Contractor is behind schedule on
this activity and has been requested to increase resources. The Contractor promised to increase teams to catch
up with the construction program.
PROGRESS - KERBSTONE
PLANNED(KM) ACTUAL(KM) SLIPPAGE(KM)
MONTHLY CUMULATIVE MONTHLY CUMULATIVE CUMULATIVE
PLANNED
NO OF
MONTH-YR QTY (Programme QTY ACTUAL QTY
MONTHS
Rev 1)
1 Dec-20 0.0 0.0 0.0 0.0 0.0
2 Jan-21 31.5 31.5 0.0 0.0 -31.5
3 Feb-21 60.5 92.0 0.8 0.8 -91.1
4 Mar-21 33.9 125.8 1.2 2.0 -123.8
5 Apr-21 31.5 157.3 1.4 3.4 -153.9
6 May-21 31.5 188.8 5.6 9.0 -179.8
7 Jun-21 31.5 220.2 3.3 12.3 -208.0
8 Jul-21 21.8 242.0 5.2 17.4 -224.6
9 Aug-21 -128.3 113.7 10.6 28.1 -85.7
10 Sep-21 36.3 150.0 20.6 48.7 -101.3
PROGRESS - PAVING
PLANNED(SQM) ACTUAL(SQM) SLIPPAGE(SQM)
MONTHLY CUMULATIVE MONTHLY CUMULATIVE CUMULATIVE
PLANNED
NO OF
MONTH-YR QTY (Programme QTY ACTUAL QTY
MONTHS
Rev 1)
1 Dec-20 11907.9 11907.9 0.0 0.0 -11907.9
2 Jan-21 11907.9 23815.7 0.0 0.0 -23815.7
3 Feb-21 10991.9 34807.6 0.0 0.0 -34807.6
4 Mar-21 12823.9 47631.5 0.0 0.0 -47631.5
5 Apr-21 12823.9 60455.3 0.0 0.0 -60455.3
6 May-21 10991.9 71447.2 0.0 0.0 -71447.2
7 Jun-21 11907.9 83355.1 0.0 0.0 -83355.1
8 Jul-21 8243.9 91599.0 1064.0 1064.0 -90535.0
9 Aug-21 -53127.4 38471.6 4886.0 5950.0 -32521.6
10 Sep-21 13739.9 52211.4 3285.0 9235.0 -42976.4
PROGRESS - C1
PLANNED(KM) ACTUAL(KM) SLIPPAGE(KM)
MONTHLY CUMULATIVE MONTHLY CUMULATIVE CUMULATIVE
NO OF PLANNED
MONTH-YR QTY QTY ACTUAL QTY
MONTHS (Programme Rev 1)
1 Sep-20 4.6 4.6 0.0 0.0 -4.6
2 Oct-20 6.1 10.8 1.2 1.2 -9.6
3 Nov-20 5.6 16.4 12.0 13.2 -3.2
4 Dec-20 6.1 22.5 1.2 14.4 -8.1
5 Jan-21 5.6 28.2 0.0 14.4 -13.8
6 Feb-21 5.6 33.8 0.0 14.4 -19.4
7 Mar-21 6.1 39.9 3.1 17.5 -22.4
8 Apr-21 6.1 46.1 4.5 22.0 -24.1
9 May-21 5.1 51.2 4.0 26.0 -25.2
10 Jun-21 0.0 51.2 4.6 30.6 -20.6
11 Jul-21 0.0 51.2 11.2 41.8 -9.4
TOTAL 48.6 50
51.2
% PLANNED VS ACTUAL PROGRESS
% PLANNED % ACTUAL
NO OF CMULATIVE
MONTH-YR CUMULATIVE
MONTHS MONTHLY MONTHLY CUMULATIVE SLIPPAGE (%)
(Programme Rev 1)
1 Sep-20 9% 9% 0% 0% -9%
2 Oct-20 12% 21% 2% 2% -19%
3 Nov-20 11% 32% 23% 26% -6%
4 Dec-20 12% 44% 2% 28% -16%
5 Jan-21 11% 55% 0% 28% -27%
6 Feb-21 11% 66% 0% 28% -38%
7 Mar-21 12% 78% 6% 34% -44%
8 Apr-21 12% 90% 9% 43% -47%
9 May-21 10% 100% 8% 51% -49%
10 Jun-21 0% 100% 9% 60% -40%
11 Jul-21 0% 100% 22% 82% -18%
12 Aug-21 -5% 95% 16% 98% 3%
13 Sep-21 0% 95% 0% 98% 3%
PROGRESS - CRR
PLANNED(KM) ACTUAL(KM) SLIPPAGE(KM)
MONTHLY CUMULATIVE MONTHLY CUMULATIVE CUMULATIVE
NO OF PLANNED
MONTH-YR QTY QTY ACTUAL QTY
MONTHS (Programme Rev 1)
1 Nov-20 2.0 2.0 1.2 1.2 -1
2 Dec-20 7.7 9.7 6.4 7.6 -2
3 Jan-21 7.7 17.4 0.8 8.4 -9
4 Feb-21 6.7 24.1 4.0 12.4 -12
5 Mar-21 8.2 32.3 2.7 15.1 -17
6 Apr-21 7.7 39.9 6.4 21.5 -18
7 May-21 7.7 47.6 1.5 23.0 -25
8 Jun-21 3.6 51.2 7.6 30.6 -21
9 Jul-21 0.0 51.2 10.9 41.5 -10
10 Aug-21 -4.6 46.6 5.5 47.0 0
11 Sep-21 0.0 46.6 0.0 47.0 0
TOTAL 46.6 47.0
51.2
% PLANNED VS ACTUAL PROGRESS
% PLANNED % ACTUAL
NO OF CMULATIVE
MONTH-YR CUMULATIVE
MONTHS MONTHLY MONTHLY CUMULATIVE SLIPPAGE (%)
(Programme Rev 1)
1 Nov-20 4% 4% 2% 2% -2%
2 Dec-20 15% 19% 13% 15% -4%
3 Jan-21 15% 34% 2% 16% -18%
4 Feb-21 13% 47% 8% 24% -23%
5 Mar-21 16% 63% 5% 29% -34%
6 Apr-21 15% 78% 13% 42% -36%
7 May-21 15% 93% 3% 45% -48%
8 Jun-21 7% 100% 15% 60% -40%
9 Jul-21 0% 100% 21% 81% -19%
10 Aug-21 -9% 91% 11% 92% 1%
11 Sep-21 0% 91% 0% 92% 1%
PROGRESS - PRIME
PLANNED(KM) ACTUAL(KM) SLIPPAGE(KM)
MONTHLY CUMULATIVE MONTHLY CUMULATIVE CUMULATIVE
PLANNED
NO OF
MONTH-YR QTY (Programme QTY ACTUAL QTY
MONTHS
Rev 1)
1 Nov-20 0.5 0.5 1.2 1.2 0.7
2 Dec-20 7.7 8.2 4.0 5.2 -3.0
3 Jan-21 7.7 15.9 3.2 8.4 -7.5
4 Feb-21 7.2 23.0 3.0 11.4 -11.6
5 Mar-21 7.7 30.7 3.4 14.8 -15.9
6 Apr-21 7.7 38.4 5.2 20.0 -18.4
7 May-21 7.7 46.1 2.0 22.0 -24.1
8 Jun-21 5.1 51.2 8.6 30.6 -20.6
9 Jul-21 0.0 51.2 6.4 37.0 -14.2
10 Aug-21 -6.1 45.1 10.0 47.0 1.9
11 Sep-21 2.0 47.1 0.0 47.0 -0.1
TOTAL 47.1 47.0
51.2
% PLANNED VS ACTUAL PROGRESS
% PLANNED % ACTUAL
NO OF CUMULATIVE CMULATIVE
MONTH-YR
MONTHS MONTHLY (Programme MONTHLY CUMULATIVE SLIPPAGE (%)
Rev 0)
1 Nov-20 1% 1% 2% 2% 1%
2 Dec-20 15% 16% 8% 10% -6%
3 Jan-21 15% 31% 6% 16% -15%
4 Feb-21 14% 45% 6% 22% -23%
5 Mar-21 15% 60% 7% 29% -31%
6 Apr-21 15% 75% 10% 39% -36%
7 May-21 15% 90% 4% 43% -47%
8 Jun-21 10% 100% 17% 60% -40%
9 Jul-21 0% 100% 13% 72% -28%
10 Aug-21 -12% 88% 20% 92% 4%
11 Sep-21 4% 92% 0% 92% 0%
B.1.5.15. Asphalt
The cumulative quantity done to date is 41km out of a total of 51.2km. The percentage cumulative progress is
80% versus a planned of 80%. The Contractor is on schedule on this activity. Table B1.5.15 and Chart B1.5.15
below show the details: -
PROGRESS - ASPHALT
PLANNED(KM) ACTUAL(KM) SLIPPAGE(KM)
MONTHLY CUMULATIVE MONTHLY CUMULATIVE CUMULATIVE
PLANNED
NO OF
MONTH-YR QTY (Programme QTY ACTUAL QTY
MONTHS
Rev 1)
1 Dec-20 5.6 5.6 2.0 2.0 -3.6
2 Jan-21 7.7 13.3 6.0 8.0 -5.3
3 Feb-21 7.2 20.5 2.0 10.0 -10.5
4 Mar-21 8.2 28.7 3.5 13.5 -15.2
5 Apr-21 7.7 36.4 6.5 20.0 -16.4
6 May-21 7.7 44.0 2.0 22.0 -22.0
7 Jun-21 7.2 51.2 7.6 29.6 -21.6
8 Jul-21 0.0 51.2 4.4 34.0 -17.2
9 Aug-21 -10.2 41.0 7.0 41.0 0.0
10 Sep-21 0.0 41.0 0.0 41.0 0.0
Toolbox talks have been carried out to remind workers on Safety issues.
Condom distributed.
Condom Mode of Distribution Target Previous Total Condom Cumulative Total
distributed. Group Cumulative distributed
(In reporting)
Through the boxes All workers 4807 212 5019
placed on different
location at the camp
site
The main activities undertaken this month are detailed in Appendix 7.5
The Statistics on Incidents and Accidents on site was as follows: There were 2 medical treatment cases
and no accidents in the reporting month.
1)Fatality Case 0 0 0
2) Injuries - LTI 1 0 1
3)Medical Treatment Case 11 4 11
4)Occupational Disease 0 0 0
5)Machinery Incident/Accident 0 0 0
6)Property Damage 1 0 1
7) Near Miss 4 0 4
8) First Aid Case 14 2 16
9) Loss of Property 0 0 0
The Main activities undertaken in the reporting month are detailed in Appendix 7.5
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
B.3.3. Subcontractors
No. COMPANY NAME Disctiption
Based on the approved work methodology the acceptance criteria as specified under the contract are
followed. The contractor issues a Request for Inspection/Acceptance or Testing (RFI/RFA), compliance
confirmatory tests are conducted by the consultant and the Request for Approval is granted.
For all Non-compliance tests a Non-Conformance Report (NCR) is issued by the Contractor as specified
under the contract.
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
Laboratory sampling and tests have been conducted in the reporting Month as shown in table below: -
B.3.5. Variations
The summary of Variations is detailed in the Table below:
The Consultant submitted the Variations Report to the Employer on the 10th of September 2020.The
Tender Board approved the Variations on the 14th of January 2021. The Revised Bill of Quantities and the
Variation Orders were issued to the Contractor on the 17th of February 2021.
.
VALUE
REF DATE DESCRIPTION STATUS
TZS
VO. No.1 17-04-2020 Additional Building Cost of Engineer's Office and Laboratory TZS 85,909,731.83 Approved & Implemented
VO. No.2 27-07-2020 Subsoil Drainage Systems TZS 257,679,309.71 Approved & under Implementation
VO. No.3 Anti Termite Poison TZS 48,600,000.00 Approved & Implemented
VO. No.4 Service Ducts TZS 266,625,000.00 Approved & under Implementation
VO. No.5 Alternative Binder -TZS 440,958,882.49 Approved & under Implementation
VO. No.6 Active Filler TZS 477,772,105.95 Approved & under Implementation
VO. No.7 Street Lights TZS 3,217,500,000.00 Approved & under Implementation
September Planned September Achieved Cumulative Planned Cumulative Achieved Cumulative Variation October
Contract Planned
S/N Item Description Unit Quantities
Qtys Qtys % Qtys % Qtys % Qtys % Qtys
Overrall progress 88% 85% -3%
Permanent Progress 88% 83% -5%
table below:
1 Structural Work 100% 99% -1%
1.1 Construction of Pipe Culverts Line 106 - - - 106 100% 99 93% -7 -7% -
1.2 Construction of Box Culverts Line 10 - - - 10 100% 10 100% 0 0% -
1.3 Service Ducts M 6,620 - - - 10,817 163% 10,817 163% 0 0% -
2 Earthworks & Pavement layers 99% 99% 0%
2.1 Clearing & Grubbing & Removal of topsoil KM 51.2 - - - 51 100% 51 100% 0.0 0% -
B.3.6. Claims & Disputes
Contract No.: AE/092/2019/2020/HQ/CR/01
2.2 Common excavation m³ 182,321 - 800 - 313,915 172% 312,915 172% -1,000 -1% -
2.3 G3 filling m³ 346,311 10,000 10,016 100% 677,566 196% 645,582 186% -31,984 -9% 30,000
2.4 G7 filling KM 51.2 0.3 0.5 167% 51.2 100% 50 98% -0.9 -2% 1.0
2.5 G15 filling KM 51.2 1.0 1.1 112% 51.2 100% 50 98% -0.9 -2% 1.0
B.3.7. Contractors Monthly Report
2.6 C1/CM KM 51.2 7.0 7.7 110% 48.6 95% 50 97% 0.9 2% 1.5
2.7 CRR KM 51.2 5.0 5.5 111% 46.1 90% 47 92% 1.0 2% 1.5
3 BITUMINOUS LAYERS & SEALS 80% 85% 5%
3.1 Prime Coat KM 51.2 8.0 10.1 126% 42.0 82% 47 92% 5.1 10% 3.0
Construction of Government City Roads to Bitumen Standard(40km)
3.2 Asphalt Concrete Surfacing KM 51.2 5.0 11.8 236% 40.4 79% 41 79% 0.2 0% 3.0
4 OPEN & COVERED DRAINS 85% 76% -9%
4.1 Construction of U-drain M 22,240 - - - 24,093 108% 24,093 108% 0 0% -
4.2 Construction of open drain M 56,000 5,000 8,345 167% 33,600 60% 19,750 35% -13,850 -25% 10,000
5 CONCRETE KERBING & WALKWAYS 59% 15% -44%
5.1 Kerbstone M 242,030 20,000 20,671 103% 150,059 62% 48,734 20% -101,325 -42% 20,000
5.2 Paving blocks M2 91,599 10,000 3,285 33% 52,212 57% 9,235 10% -42,977 -47% 10,000
6 ANCILARY ROADWORKS 14% 2% -12%
6.1 Streetlights No. 1,408 100 90 90% 211 15% 90 6% -121 -9% 100
6.2 Landscaping & Grassing M2 1,000 0.0 0.0 0% 150 15% 0 0% 0.0 -15% 0.0
6.3 Road Signs No. 619 0.0 0.0 0% 93 15% 0 0% 0.0 -15% 0.0
6.4 Road Markings(White&Yellow) M 180,800 0.0 0.0 0% 0 0% 0 0% 0.0 0% 0.0
Monthly Progress Report MPR No 20
September 2021
The Contractor’s Monthly Progress Report and the Forecast Plan for September 2021 is detailed in the
Employer. The Employer granted the Contractor a 5-month Extension of Time to 31st of December 2021.
Contractor applied for 304 Days Extension of Time which would move the Intended Completion Date from
31 July 2021 to 31 May 2022. The Consultant analysed this Claim and submitted recommendations to the
The Contractor resubmitted an Application for Extension of Time on the 27 th of February 2021. The
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
B.4.1. Payments
The Contractor submitted an IPC No.8 amounting to TZS 5,610,171,507.96 in this reporting month.
IPC 1 TZS 4,090,697,430.43 15-Jul-20 12-Aug-20 22-Dec-20 TZS 3,693,332,375.00 TZS 397,365,055.43 Part Paid
Part Paid. Adv deducted at
IPC 2 TZS 6,113,834,086.11 14-Dec-20 11-Jan-21 23-Mar-21 TZS 5,466,326,226.33 TZS 647,507,859.78
MoF
IPC 3 TZS 6,217,181,633.95 31-Dec-20 28-Jan-21 2-Jun-21 TZS 5,929,684,756.85 TZS 287,496,877.10 Part Paid
IPC 4 TZS 8,841,526,245.85 25-Mar-21 22-Apr-21 18-Jun-21 TZS 8,673,440,980.34 TZS 168,085,265.51 Paid less interest
IPC 5 TZS 7,131,954,735.51 26-Apr-21 24-May-21 28-Jun-21 TZS 6,949,273,602.82 TZS 182,681,132.69 Part Paid
IPC 6 TZS 9,215,391,636.95 11-Jun-21 9-Jul-21 TZS 10,768,519,213.61 TZS 6,460,105,300.80 -TZS 1,553,127,576.66 Paid
B.4.3. Cashflow
The Contractors cumulative application for payments to date is TZS 69,504,888,837.35 including Advance
Payment. The Value of Work done and claimed to date is TZS 56.29billion versus a projection of TZS
60.76 billion.
Chart B.4.3 below shows the Contractor’s Cashflow and actual income.
CONTRACTORS CASHFLOW (% )
% PLANNED % ACTUAL
NO OF CUMULATIVE
MONTH-YR CUMULATIVE CUMULATIVE
MONTHS MONTHLY MONTHLY SLIPPAGE (%)
(Programme Rev 0) (IPC + Retention)
1 Feb-20 0% 0% 0% 0% 0%
2 Mar-20 0% 0% 0% 0% 0%
3 Apr-20 1% 1% 0% 0% -1%
4 May-20 1% 2% 0% 0% -2%
5 Jun-20 3% 5% 0% 0% -5%
6 Jul-20 4% 9% 5% 5% -4%
7 Aug-20 5% 14% 0% 5% -9%
8 Sep-20 6% 19% 0% 5% -15%
9 Oct-20 7% 27% 0% 5% -22%
10 Nov-20 9% 35% 7% 12% -24%
11 Dec-20 7% 42% 7% 19% -23%
12 Jan-21 4% 46% 0% 19% -27%
13 Feb-21 7% 52% 0% 19% -34%
14 Mar-21 9% 61% 10% 29% -33%
15 Apr-21 10% 71% 8% 37% -35%
16 May-21 10% 81% 0% 37% -45%
17 Jun-21 9% 91% 10% 47% -44%
18 Jul-21 9% 100% 10% 58% -42%
19 Aug-21 0% 58% 0% 58% 0%
20 Sep-21 1% 69% 6% 64% -5%
a. Effects of Corona Virus on the Project on the 2nd of April 2020 with letter REF: CHICODODOM—
01-2/4/2020.
b. Delays due to Advance Payment, Water Table and Rainfall on 2 nd of April 2020 with letter REF:
CHICODODOMA—02/2/4/2020.
c. Delays on Relocation of Existing Services belonging to DUWASA and TANESCO on 11 April 2020
with letter REF: CHICODODOMA—01-11/4/2020.
d. Increased quantities of Common Excavation and G3 Fill Layer Works on the 2 nd of June 2020 with
letter REF: CHICODODOMA—01-02/6/2020
e. Types and quantities of Service Ducts: 30 June 2020 with letter REF: CHICODODOMA—01-
30/06/2020
f. Delayed Payment of IPC No.1: 9 October 2020 with letter REF: CHICODODOMA—01-09/10/2020
g. Cement shortage with letter REF: CHICODODOMA--01-26/11/2020.
h. Relocation of The Hut on 17th January 2021 with letter REF: CHICODODOMA--01-17/01/2021
i. Relocation of Utilities of TANESCO on 17th January 2021 with letter REF:CHICODODOMA--02-
17/01/2021
j. Late Payment of IPC No. 2 and 3 on 23 rd January 2021 with letter REF CHICODODOMA--02-
23/01/2021
k. Early Notice Regarding passing of the President of the United Republic of Tanzania Ref.
CHICODODOMA--01-18/03/2021
l. Early Notice Regarding adverse effect of cement shortage Ref. CHICODODOMA--01-12/04/2021
m. Early Warning Notice regarding late payment of IPC No.6 Ref: CHICODODOMA--01-13/7/2021
n. Early Warning Notice Regarding the VAT Exception Procedure Delay the Order of Traffic Lights
Ref No. CHICODODOMA--01-18/09/2021
B.6. MISCELLANEOUS
B.6.2. Visitors
The District Commissioner Honourable Jabir Shekimweri visited site on 7 September 2021
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
C. APPENDICES
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
CONTRACT DATA
FINANCIAL DATA
DELIVERABLE DATA
3.2 Contractors
CONTRACT DATA
Construction of Government City Roads to Bitumen Standard(40km) Monthly Progress Report MPR No 20
Contract No.: AE/092/2019/2020/HQ/CR/01 September 2021
PROGRESS DATA
Reporting Date 15 October 2021
Time Elapsed (Months) 20
Percentage of Time Elapsed 87
APPENDIX TO BID
Performance Security (TZS/%/Expire Date) 12 June 2022
Third Party Insurance (TZS/Expire Date)
TZS13,220,046,907.02
Advance Payment (TZS/%)
Bank Security (Expire Date)
Commence Repayment when certification reaches (TZS/%) IPC No.2
Recovery Rate per IPC (TZS/%) 20
IPC
Minimum certification (TZS/%) 2
Time for Payment (Days) 56
Liquidated Damages
Amount per Day (TZS/%) 0.1
Limit (TZS/%) 10
Retention
Per IPC (%) 10
Limit (TZS/%) 5
PROJECT ORGANIZATION CHART
Financing Authority
(Government of Tanzania)
SITE AGENT
QUANTITY SURVEYOR
WORKS MANAGER
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________